Part thereof means in case applied load is 4.5 KW for domestic, the Application
processing fee required will be Rs 50 x 5 = 250.
(a) Extension of Load: - Incase of consumers who are sanctioned additional connected
load, the ACD be got deposited for the additional connected load.
(b) Part thereof means in case applied load is 4.5 KW for domestic, the ACD required
will be Rs 750 x 5 = 3750.
(iii) Metering charges
(c) In the following categories, the fixed service connection charges and additional