You are on page 1of 117

PLANNING AND CONTROLLING OF EARTHWORK BLD

OPERATION MULTI-STOREY PROJECT 410

NAME OF STUDENT AND


NO UITM NO SIGNATURE
HAND-PHONE NO

MD ABDULHADI
1 2009249132
MOHAMMED SOPAFI
0122090493

ILYAS MUSTAPHA
2 2009647962
MOHAMMAD
0176671030

3 RIDUAN MOHD TAHIR 2009667776


0135013035

NURHAFIZAH FATIN
4 2009697746
A RAHMAN
0194190164

5 SITI ATIEKAH JUSOH 2009815488


0179226492

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

Contents
1 LIST OF FIGURE................................................................................................................4
2 PROJECT..........................................................................................................................6
2.1 PROJECT DESCRIPTION............................................................................................7
2.2 SITE ORGANISATION CHART..................................................................................10
2.3 INTRODUCTION.....................................................................................................11
3 PLANNING OF EARTHWORK OPERATION MULTI-STOREY PROJECT...............................12
3.1 INTRODUCTION.....................................................................................................12
3.2 DESIGN STAGE.......................................................................................................13
3.2.1 SCOPE............................................................................................................13
3.2.2 GENERAL........................................................................................................13
3.2.3 TECHNICAL RESPONSIBILITIES........................................................................14
3.2.4 SITE INVESTIGATIONS....................................................................................15
3.2.5 PLANNING AND DESIGN................................................................................17
3.2.6 FINAL DOCUMENTATION...............................................................................24
3.2.7 PROTECTION OF THE WORKS........................................................................25
3.2.8 CLEARING AND GRUBBING............................................................................29
3.2.9 Disposal of Material.......................................................................................30
3.3 PLANNING STAGE..................................................................................................31
3.3.1 COST ESTIMATED...........................................................................................31
3.3.2 METHOD STATEMENT AND PROJECT PLANNING...........................................39
3.3.3 CONSTRUCTION METHOD AND USE OF PLANT.............................................49
4 CONTROLLING FOR OPERATION OF EARTHWORK.........................................................58
4.1 INTRODUCTION.....................................................................................................58
4.1.1 SURFACE LEVELLING STATION (MONUMENT)...............................................59
4.1.2 SETTELEMENT PLATE (ROD EXTENSOMETER)................................................60
4.1.3 MAGNETIC EXTENSOMETER..........................................................................61
4.1.4 USBR SETTLEMENT GAUGE............................................................................61
4.1.5 PIEZOMETER..................................................................................................62
4.2 SLOPE PROTECTION...............................................................................................63
4.2.1 STABILIZATION OF CUT SLOPES.....................................................................64

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

4.3 Methods of Groundwater Control.........................................................................65


4.3.1 Sumps and Ditches........................................................................................65
4.3.2 Deep-Well Systems........................................................................................67
4.3.3 Wellpoint Systems.........................................................................................71
4.3.4 Vertical Sand Drains.......................................................................................79
4.3.5 Electro-Osmosis.............................................................................................80
4.3.6 Cutoffs...........................................................................................................82
4.4 CONSTRUCTION PROCEDURES..............................................................................90
4.4.1 SPECIFICATIONS.............................................................................................90
4.4.2 FILL CONSTRUCTION......................................................................................91
4.4.3 INSPECTION AND QUALITY CONTROL............................................................93
4.5 CASE STUDY...........................................................................................................95
4.5.1 SLOPE STABILIZATION/ SLOPE PROTECTION..................................................95
4.5.2 DEWATERING SYSTEM.................................................................................100
4.5.3 TRAFFIC CONTROL.......................................................................................104
4.5.4 SAFETY CONTROL.........................................................................................107
4.5.5 SETTLEMENT CONTROL...............................................................................110
4.5.6 DOCUMENTATION CONTROL......................................................................111
5 CONCLUSION.............................................................................................................116
6 Bibliography................................................................................................................117

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

1 LIST OF FIGURE

FIGURE 1 SUBANG SOHO PROJECT............................................................................................................6


FIGURE 2 SITE PLAN OF SOHO PROJECT..........................................................................................9
FIGURE 3 SITE LAYOUT - SOHO PROJECT.....................................................................................9
FIGURE 4 THE SOIL THAT WILL EXCAVATE. (35, 000M 3)....................................................................38
FIGURE 5 CRITICAL PATH METHOD....................................................................................................48
FIGURE 6 DEWATERING OPEN EXCAVATION BY SUMP AND DITCH........................................................................66
FIGURE 7 SUBMERSIBLE PUMP FOR DEWATERING AN EXCAVATION......................................................................66
FIGURE 8 DEEP WELL SYSTEM FOR DEWATERING AN EXCAVATION IN SAND...........................................................67
FIGURE 9 DEEP WELLS WITH AUXILIARY VACUUM SYSTEM FOR DEWATERING A SHAFT IN STRATIFIED MATERIALS..........68
FIGURE 10 PLAN OF A TYPICAL WELLPOINT SYSTEM..........................................................................................71
FIGURE 11 A TYPICAL WELLPOINT SYSTEM AT SITE............................................................................................71
FIGURE 12 USE OF WELLPOINTS WHERE SUBMERGENCE IS SMALL.......................................................................72
FIGURE 13 DRAINAGE OF AN OPEN DEEP CUT BY MEANS OF A MULTISTAGE WELLPOINT SYSTEM...............................73
FIGURE 14 VACUUM WELLPOINT SYSTEM........................................................................................................74
FIGURE 15 A WELLPOINT PUMP USED IN SUNWAY PYRAMID II PROJECT...............................................................75
FIGURE 16 SELF-JETTING WELLPOINT.............................................................................................................76
FIGURE 17 JET-EDUCTOR WELLPOINT SYSTEM FOR DEWATERING A SHAFT.............................................................79
FIGURE 18 SAND DRAINS FOR DEWATERING A SLOPE........................................................................................80
FIGURE 19 INSTALLATION OF MANDRELS USING DRAIN STITCHER.........................................................................80
FIGURE 20 ELECTRO-OSMOSIS WELLPOINT SYSTEM FOR STABILIZING AN EXCAVATION SLOPE....................................81
FIGURE 21 INSTALLATION OF ELECTRO-OSMOSIS IN A DEWATERING SITE...............................................................82
FIGURE 22 GROUT CURTAIN OR CUTOFF TRENCH AROUND AN EXCAVATION..........................................................83
FIGURE 23 DETAIL OF SLURRY TRENCH...........................................................................................................85
FIGURE 24 STEEL SHEETING TO TOP OF ROCK. A BOULDER ABOVE THE ROCK CAN AGGRAVATE THE SITUATION............86
FIGURE 25 STEEL SHEETING IN SUNWAY PYRAMID II PROJECT TO CONTROL SEEPAGE AND STABILIZING THE SLOPE.......87
FIGURE 26 EXCAVATION SUPPORTED BY A GRAVITY FREEZEWALL.........................................................................88
FIGURE 27 TYPICAL SCENARIO OF FREEZE PIPE SPACING AND INDICATION WHICH CAN BE CONNECTED TO A PORTABLE
REFRIGERATION PLANT, OR LIQUID NITROGEN TANKER..............................................................................88
FIGURE 28 CIRCULAR EXCAVATION SUPPORTED BY A FREEZEWALL. (A) PLAN. (B) SECTION......................................89
FIGURE 29 A DEEP EXCAVATION SUPPORTED BY FREEZE WALL............................................................................89
FIGURE 30 CSP AT THE SOHO PROJECT........................................................................................................96
FIGURE 31 RE-BAR OF CSP..........................................................................................................................97
FIGURE 32 CSP SIDE USE MORTAR................................................................................................................97
FIGURE 33 LAYOUT OF CSP.........................................................................................................................98
FIGURE 34 CANVAS METHOD.......................................................................................................................99
FIGURE 35 CANVAS TO THE SLOPE.................................................................................................................99
FIGURE 36 RETAINING WALL......................................................................................................................100
FIGURE 37 WATER PUMP..........................................................................................................................101
FIGURE 38 WATER FLOW..........................................................................................................................101
FIGURE 39 PONDING AT SITE......................................................................................................................102
FIGURE 40 TEMPORARY DRAINAGE..............................................................................................................102
FIGURE 41 TEMPORARY DRAINAGE..............................................................................................................103

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

FIGURE 42 ACCESS ROUTE..........................................................................................................................104


FIGURE 43 BARIER GATE............................................................................................................................105
FIGURE 44 WASH PIT................................................................................................................................106
FIGURE 45 HOUSEKEEPING.........................................................................................................................106
FIGURE 46 HOARDING...............................................................................................................................107
FIGURE 47 WASH PIT................................................................................................................................108
FIGURE 48 GATE BARIER...........................................................................................................................108
FIGURE 49 PROJECT SIGNAGE.....................................................................................................................109
FIGURE 50 POINT OF STTLEMENT CONTROL...................................................................................................110
FIGURE 51 SETTLEMENT MARKER RECORDS..................................................................................................111

2 PROJECT

AP 226 / 1C | JULY – NOVEMBER 2009

Figure 1 SUBANG SOHO PROJECT


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

2.1 PROJECT DESCRIPTION

PROJECT SUBANG SOHO


CADANGAN PEMBANGUNAN FASA B YANG
MENGANDUNGI 1 BLOK SOHO 23 TINGKAT (488 UNIT)
TERMASUK 5 TINGKAT TEMPAT LETAK KERETA DI
ATAS LOT 20926 (P.T. 11921) H.S (D) 48924, MUKIM
DAMANSARA, DAERAH PETALING, SELANGOR
DARUL EHSAN UNTUK TETUAN SENDI BANGGA
DEVELOPMENT SDN. BHD.

CLIENT SENDI BANGGA DEVELOPMENT SDN. BHD


(whole subsidiary by Titijaya Group)
Lot 3-10, 3rd Floor,
First Tower, Jalan Meru,
41050 Klang, Selangor.
Tel : 03-3341 1111 Fax : 03-3341 2992

ARCHITECT ARKITEK KDI SDN. BHD


1st Floor,
No 87 & 89, Jalan Ipoh
51200 Kuala Lumpur.
Tel : 03-4045 3193 Fax : 03-4045 3187

STRUCTURAL CSI CONSULTANT


ENGINEER No. 25-7, Jalan USJ 9/5Q,
Subang Business Centre,
47620 UEP Subang Jaya, Selangor
Tel : 03-8023 6312 Fax : 03-8023 6316

CIVIL ENGINEER PETAREKA PERUNDING (M) SDN. BHD


No.5, jalan 11/62 A,
Bandar Seri Menjalara,
52200 Kuala Lumpur, Malaysia
Tel : 03-6272 6878 Fax : 03-6272 8878

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

M&E FADHULLAH & ASSOCIATES CONSULTING


No. 4A&4B, Jalan BPU 9,
14th Mile, Jalan Puchong,
Bandar Puchong Utama, 47100 Selangor.
Tel : 03-5891 1535/1536 Fax : 03-5891 1538

LANDSCAPE ECO HABITAT


ARCHITECT 3-3, Jalan Damar SD 15/1,
Bandar Sri Damansara,
52200 Kuala Lumpur.
Tel : 03-6277 0083 Fax : 03-6277 1646

QUANTITY DL QS CONSULT
SURVEYOR No. 11-2 (2nd Floor), Jalan USJ 10/1E
Taipan Business Centre,
47620 UEP Subang Jaya, Selangor.
Tel : 03-5638 8267 Fax : 03-5638 0268

CONTRACTOR G-PILE SISTEM SDN. BHD


Lot 1.01 Level 1, KPMG Tower,
No. 8 First Avenue, Bandar Utama,
47800 Petaling Jaya, Selangor.
Tel : 03-7710 6477/8477 Fax : 03-7710 5477

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

Figure 2 Site Plan of SOHO Project

Figure 3 SITE LAYOUT - SOHO Project

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

2.2 SITE ORGANISATION CHART

G-PILE SISTEM SDN BHD

DIRECTOR
LING HUA EE

SR. CONTRACTS MANAGER SENIOR MANAGER TECHNICAL MANAGER


SHIRLEY SIM DING CHENG HUAT IR. WARREN CHOO

PROJECT QS PLANNING MANAGER


SHARON TAN YAU KIM WEI

ASST. PROJECT MANAGER


LOH MUN HONG

Base in HQ

Base on Site

SURVEYOR SUPERVISOR SAFETY OFFICER


LEE FONG YONG RIDZUWAN/ZULKIFLI AZAHARI

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

2.3 INTRODUCTION

The subtopics that we get for our case study about Planning and
Controlling of Earthwork Operation Multi-Storey Building; for the assigment’s
subject in Construction Technology’s (BLD 410).

Practicality that can be seen and understand, the planning and


controlling by the contractor when get the project. Planning operation is
include about cost estimated, method/sequence of work, project planning and
also the machineries used during the earthwork operations. For the
controlling, included about slope, dewatering system, trafic control, safety
control, settlement control, and documantation control.

Based on this topic, we are together chosen one of the private


companies to do this research. The company is Sendi Bangga
Development Sdn. Bhd this company is a wholly owned subsidiary of Titi
Jaya Holding Sdn. Bhd.

These construction works were done and responsibility by Sendi


Bangga Development Sdn. Bhd as a developer of “SUBANG SOHO;
Cadangan Pembangunan Fasa B Yang Mengandungi 1 Blok Soho 23
Tingkat (488 Unit) Termasuk 5 Tingkat Tempat Letak Kereta Di Atas Lot
20926 (P.T. 11921) H.S (D) 48924, Mukim Damansara, Daerah Petaling,
Selangor Darul Ehsan Untuk Tetuan Sendi Bangga Development Sdn.
Bhd.”; 2.7 million project (earthwork operation).

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

3 PLANNING OF EARTHWORK OPERATION MULTI-STOREY


PROJECT

3.1 INTRODUCTION

Earthwork operations involve the excavation, transportation and placement or


disposal of materials. They typically involve repetitive work cycles, expensive
fleets and large volumes of work. Consequently, even small improvements in
planning result in substantial cost and time savings. It is for these reasons
that earthwork operations improvement has been the focus of so many
studies. The work is performed outdoors under conditions that are highly
variable and that affect the performance of the different pieces of equipment.
Factors that affect performance include weather (i.e., trucks cannot travel as
fast on wet, muddy haul roads), haul road maintenance (i.e., a well-
maintained road reduces rolling resistance), operator experience, ground
conditions, load and dump area layouts, and the material being excavated.

Earthwork operations are actively managed with many decisions made


dynamically on site in reaction to the evolving status. A truck, for example,
may be routed to an alternate load area if the loading unit at the main area is
under maintenance or if several other trucks are queuing for it. Sometimes
the strategies that guide these dynamic decisions are quite complex but
necessary. They can also significantly impact the performance of the
operation. The probabilistic nature of the work and the dynamics of earthwork
operations make them difficult to plan. They are typically planned using
simplified back-of-the envelope calculations, but mainly relying on the
experience and insights of the planner. Discrete-event simulation is the only
earthwork analysis method that can explicitly incorporate the detailed but
significant aspects (e.g., equipment characteristics, haul road conditions,
load and dump area configuration, and dynamic context-based decisions) of
an operation.

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

3.2 DESIGN STAGE

3.2.1 SCOPE

This part is sets out the recommendations for the carrying out of earthworks
or preparation or foundations of multi-storey project at SUBANG SOHO, or
both, including:

a) The excavation and filling of land to form new contours;


b) The assessment and protection of slope stability;
c) The suitability of both natural and filled ground for the founding of
roads, buildings,
d) Services and other works;
e) The control of erosion and siltation’s during and after earthworks.

Because of the wide range of soil types, physical conditions and


environmental factors which apply in different areas it is not often possible to
lay down precise requirements which will be subject in particular instances to
the judgement of the Engineer, owner's representative or soils engineer.
[ CITATION Gar07 \l 1033 ]

3.2.2 GENERAL

Choice of final landform is dependent on many factors which may be specific


to the subdivision or development. These include:

a) Relation with surrounding landscape;


b) Size;
c) Roading pattern;
d) Preservation of natural features;
e) Stability;

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

f) Damage by flood or other natural occurrences such as erosion by sea,


river, or surface storm water run-off.

Provision is made in this standard for certification of suitability of land for


subdivision and development to meet the requirements of this Standard. This
requirement is independent of the requirements under the Building Act 1991.
Reference is made to the desirability of using local material which may
provide a satisfactory foundation in particular circumstances.

3.2.3 TECHNICAL RESPONSIBILITIES

Where any land development or subdivision involves the carrying out of bulk
earthworks, the assessment of slope stability, or the detailed evaluation of
the suitability of natural ground for the foundations of buildings, roads,
services or other works, then a soil engineer should be appointed by the
developer to carry out the following instructions:

a) Prior to detailed planning of any development to undertake a site


inspection and such investigations of subsurface conditions as may be
required.
b) Before work commences to review the drawings and specifications
defining the earthworks proposed, and submit a written report to the
Engineer on foundation and stability aspects and any proposed
departures from this Code and associated standards.
c) Before work commences and during construction to determine the
extent of further specialist soils engineering services required
(including investigation and geological work).
d) Before and during construction to determine the methods and
frequency of construction control tests to be carried out, determine the
reliability of the testing, and to evaluate the significance to test results

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

and field inspection reports in assessing the quality of the finished


work.
e) During construction to provide regular inspection (while a daily visit
might be regarded as reasonable on earthwork construction on minor
projects, inspection on a nearly full time basis is often necessary).
f) On completion to submit a written report to the Engineer attesting to
the compliance of the earthworks with the specifications, and as to the
suitability of the subdivision for building construction.

The owner's representative may act as the soils engineer if he possesses


suitable qualifications and experience.

The construction control testing should be carried out by a competent person,


or, preferably, under the control of the soils engineer, and with Testing
Laboratory Registration Council (Telarc) registration in all relevant tests.
[ CITATION Gar07 \l 1033 ]

3.2.4 SITE INVESTIGATIONS

3.2.4.1 PRELIMINARY SITE EVALUATION

Prior to any detailed planning or design, the owner's representative or soils


engineer, as applicable, should undertake a preliminary evaluation of the
general nature and character of the site in sufficient detail to determine the
likely requirements for earthworks or the need for further investigations into
the suitability of foundation conditions, or both, and the stability of the natural
ground. The preliminary evaluations should be carried out in the context of
the total surrounds of the site, and should not be influenced by details of land
tenure, territorial or other boundary considerations. In simple cases a visual
appraisal may be sufficient, but in other cases depending on the nature of the
project, its locality, the scale of development proposed and individual site
characteristics, particular attention may need to be given to the following

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

matters which should normally be considered prior to preparing a proposal


for subdivision or development.

a) Drainage. It is important to identify the existing natural drainage


pattern of any area and to locate the natural springs or seepage.

b) Where any natural drainage paths are interfered with or altered by


earthworks then appropriate measures should be taken to ensure that
sufficient adequate alternative drainage facilities are provided.

c) Slope Stability. Some natural slopes exist in a state of only marginal


stability and relatively minor works such as trenching, excavation for
road or building platforms, removal of scrub and vegetation, or the
erection of buildings, can lead to failure. Signs of instability include
cracked or hummocky surfaces, crescent shaped depressions,
crooked fences, trees or power poles leaning uphill or downhill,
uneven surfaces, swamps or wet ground in elevated positions, plants
such as rushes growing on a slope and water seeping from the
ground.

d) Foundation Stability. A study of the general topography of the site and


its surroundings may indicate areas which have previously been built
up as a result of natural ground movement or by the deliberate placing
of fill material. Unless such fill has been placed and compacted under
proper control, long term differential settlement could occur causing
damage to superimposed structures, roads, services or other
subdivision works.

Note: The District contains a number of areas where 'tomos' have developed.
These may affect the suitability of a site for development and consequently
these will require identification and addressing as part of any development
proposal.
AP 226 / 1C | JULY – NOVEMBER 2009
PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

3.2.4.2 SPECIALIST SERVICES

Where a soils engineer has been appointed as recommended in section


Technical Responsibilities then prior to or at the time of submission of an
application or subdivision or development he should submit to Council a
written report setting out the particulars of any investigations carried out
including details of contours, natural features and modifications proposed
thereto; and shall furnish to Council a statement of professional opinion as to
the suitability of the land for subdivision with details of any special conditions
that should be imposed.

3.2.5 PLANNING AND DESIGN

3.2.5.1 LANDFORM

The final choice of landform should represent the most desirable compromise
between the factors referred to above and the preservation of natural
features and the natural quality of the landscape including the retention of
natural watercourses.

The choice of suitable landform is dependent on many factors which may be


specific to a particular site. In general, unnecessary earthworks should be
avoided but considerations which may justify the carrying out of earthworks
include:

a) The minimisation of the possibility of damage to property occurring


through ground movement in the form of slips, subsidence, creep,
erosion of settlement.
b) The minimisation of the possibility of damage to property occurring
through flooding, or surface water run-off.
c) The development of a more desirable roading pattern with improved
accessibility to and within the site and the creation of a better sense of
orientation and identity of the area as a whole.

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

d) The efficiency of overall land utilisation including the quality of


individual sites and amenity areas around buildings, the economics of
providing engineering services, and the standard of roading and on-
site vehicular access.
e) The need to create suitably graded areas for playing fields and other
community facilities.
f) The enhancement of the general environmental character of the area
by softening the landscape or by artificially creating or emphasizing
landforms of visual significance particularly on flat sites or on areas
devoid of landscape features, or preservation of some specifically
significant feature.

3.2.5.2 SOIL INVESTIGATIONS

Where appropriate the general nature and shape of the ground should be
studied and particular note taken of:
a) The geological nature and distribution of soils and rock;
b) Existing and proposed drainage conditions and the likely effects on
ground water;
c) Previous history of ground movements in similar soils in the area; and
d) Performance of comparable cuts and fills (if any) in adjacent areas.

Soil data should be obtained for areas which:


a) Are intended to form in situ bases for fills;
b) Are intended to yield material for construction of fills; and
c) Are intended to be exposed as permanent batters.

Sufficient borings, probing or open cuts should be made:


a) Classify the soil strata by field and visual methods;
b) Evaluate the likely extent and variation in depths of the principal soil
types, and

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

c) Relating subsequent soil test properties to relevant strata over the site.

The test data appropriate in different areas shall be determined by the soils
engineer.

3.2.5.3 STABILITY CRITERIA

Settlement. The most important factor in ensuring satisfactory performance of


stable fills is the limiting of post-construction differential settlements. The
design and construction of fills should be such that these settlements are
kept within acceptable limits.

The weight of residential buildings of one-storey and two-storey construction


not requiring specific design, is unlikely to produce significant settlement of fill
constructed in accordance with this Code. Local filling placed close to a
house during or after construction, for example, for a patio, will produce much
larger stress increases which may induce differential settlement of the house.

Bearing Capacity. The strength of the ground resisting general shear failure
(and resulting gross deformation) under the footings of a house is a local
phenomenon distinct from settlement. Fill constructed to minimize settlement
in accordance with this Code will have adequate shear strength.

It should be noted, however, that despite careful construction there may be


localised soft areas in the upper layers of fill within the zone of influence of
small foundations. Should the routine foundations inspection by the building
or the local authority during construction suggest, or should the Engineer
suspect, that localised soft areas are present, then
tests should be made to determine the required treatment of the fill material,
or of the foundations. These tests should extend to a depth as agreed with
the Group Manager Asset Management and may include shear strength

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

tests, field load tests or dynamic penetrometer tests or other recognised soil
strength tests.

Note: The developer should refer to the Natural Hazards Register contained
in Volume 4 of the District Plan.

The adequacy of subgrade compaction and proposed pavement depth for


road works shall be confirmed by tests on the finished subgrade. This
requirement is compulsory for new roads to be vested in Council.

Shrinkage and Expansion. Because some clay soils are likely to undergo
shrinkage and swelling when subjected to seasonal changes in water
content, special examination of welling and shrinkage characteristics should
be made in the case of highly plastic soils.

Where applicable, the need for a foundation depth or design to minimise


these effects, particularly for continuous brittle walls, should be noted in the
completion report and statement of the soils engineer.

Slope Stability. In most cases, it is unnecessary or impracticable to measure


quantitatively the factor of safety of a slope against shear failure. Maximum
slopes of cuts and fills may be determined by the soils engineer from
experience and from observation of slopes in the vicinity which have a long-
standing history of stability, are of similar height to the proposed slope and
are of apparently similar geological formation.

Where necessary or a precedent is not available, a special soils engineer


investigation should be carried out by the soils engineer to determine
acceptable limits to cut and fill slopes. In assessing slope stability account
should be taken of possible future changes in ground water level or other
conditions. Where a fill may be required to act under extreme conditions as a

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

detention dam, investigation should include the ability of the fill to act as a
detention dam and upstream effect of the fill.

3.2.5.4 QUALITY OF FILLING MATERIAL


The majority of soils, other than organic material, are potentially suitable for
fillings under controlled conditions. However, the Group Manager Asset
Management retains the right to disallow the use of unsuitable fill material.

3.2.5.5 COMPACTION STANDARDS FOR FILL MATERIAL


The standard of compaction should be measured in terms of one of the
following:
a) Relative Compaction. That is, the ratio of the field dry density of fill to
the maximum (laboratory) dry density expressed as a percentage.
Unless otherwise required by the soils engineer, fill should be
compacted to at least 95% relative compaction, in terms of the
standard method of compaction.
b) Air Voids and Shear Strength. Used for cohesive soils, where specific
test methods and criteria should be determined by the soils engineer,
who may, for example, require air voids to be less than 10% and shear
strength to be not less than 50 kPa on completion of construction.
c) Relative Density. That is, the field dry density expressed in terms of
maximum minimum densities established by laboratory test (used for
cohesionless soils). The specific minimum value should be determined
by the soils engineer who may, for example, require a minimum
relative density of 80%.
d) Field Relative Compaction (Field Proctor Test). This is the ratio of the
density of the compacted fill material at its in situ moisture content,
relative to the density of the same material at the same moisture
content after standard compaction (Proctor compaction). (This method
gives a quick determination of the actual field compactive effort being
applied, relative to Proctor compaction, without need for drying in the

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

testing procedure, and this may be adequate control provided the


material is close to optimum moisture content.)

3.2.5.6 EROSION CONTROL


Subdivision or development should be carried out in such a manner as to
restrict soil erosion to acceptable levels. This can be achieved by adopting
sound design and construction procedures.

Diversions of natural water and the discharge of water containing silt arising
from subdivision or development works are subject to either a land use, water
or discharge permit in terms of the Resource Management Act 1991. Where
the Regional Council has issued a general authorisation, that is - for the
diversion or discharge of water or water containing sediment associated with
subdivision or development, the subdividing owner's representative shall
comply with the conditions of such authorisation including notification to the
Regional Council if required. Where water is to be diverted from one
catchment to another, the effect on that catchment should be investigated,
and where necessary approvals shall be obtained from the respective
authorities or owners, or both.

Without prejudice to the conditions of any Resource Consent the following


practices should be adopted in the planning and design of land subdivision or
development projects involving earthworks:

a) Large projects should be programmed for construction in selfcontained


stages which can be largely completed within one earthworks season.
Where possible, the upper part of a catchment should be developed
first.
b) Where possible, the permanent storm-water system should be
designed so it can be constructed at an early stage in the project and

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

be used to collect run-off from the site during construction in


conjunction with silt control measures.
c) The specifications should require the use of construction procedures
which minimise concentration of run-off and excessive velocities,
which could otherwise result in erosion.
d) Silt retention ponds should be constructed and maintained in all
earthworks projects where they are feasible and necessary.
e) Graded "V" drains (also called contour drains) should be used to divert
run-off water from non-construction areas past site-works or to divert
run-off from exposed areas into silt retention ponds and reduce
overland flow distances on bar surfaces. Such drains should have a
maximum slope of 1 in 30 and a maximum design velocity of flow
2m/s.
f) Cut and fill areas should be re-topsoiled and sown as soon as possible
after earthworks and drainage works.
g) The batter faces of cuts and fills should be protected as soon as
possible after construction by grassing, hydroseeding, tree planting, or
other suitable surfacing.

3.2.5.7 PROVISION FOR PERMANENT SERVICES

Where settlement is expected to occur, all service pipes installed within or


under earth filling shall be designed and constructed to ensure adequate
capacity, strength and water-tightness to withstand the loads due to
settlement and to prevent leakage into the fill.

Where surface water could cause erosion of batters or internal instability


through soakage in the soil, open interceptor drains should be constructed in
permanent materials, and benches in batter faces should be sloped back and
graded longitudinally to reduce spillage of storm-water over the batter. Water
from storm water systems should be prevented from flowing into a fill or into

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

natural ground near the toe or sides of a fill and no storm-water soak pits
should be constructed in a fill whereby the stability of the fill might be
impaired.

All drains required permanently to protect the stability of fillings or to prevent


flooding and erosion should be clearly identified as such on "as built"
drawings.

3.2.6 FINAL DOCUMENTATION

3.2.6.1 "AS-BUILT" DRAWINGS

On completion of the earthworks an "as-built" plan should be prepared


showing the extent and depth of fill in the form of lines joining all points of
equal depth of fill at vertical intervals of for example, 500mm or 1m as
appropriate. The "as-built" plans should also record the position, type and
size of all subsoil drains, and their outlets. The plans should also show areas
of filling of low density and any fill areas which the soils engineer considers
do not comply with this Standard.

3.2.6.2 SOILS ENGINEER'S REPORT

On completion of construction, the soils engineer should furnish for the


engineer a report describing the extent of the inspection and the results of
testing together with a statement of professional opinion as to the compliance
of the filled ground to the specification, the suitability of filled ground for
specified types of building construction, and where applicable, the suitability
of original ground for specified types of building construction.

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

3.2.7 PROTECTION OF THE WORKS

The Contractor's responsibility for care of the Works shall include the
protection of earthworks. The Contractor requires an Environment Protection
Agreement or an Authorisation with the Environment Management Authority
for all construction or building activities on a site more than 0.3 hectare and
must be obtained prior to commencement of work. No extensions of time will
be granted or allowed relative to any delay with obtaining of the necessary
Agreement and other approvals unless it is shown to the satisfaction of the
Superintendent that all necessary steps have been taken on time by the
Contractor.

Where the Contract documents include a suggested Sediment and Erosion


Control Concept Plan, the Contractor is still responsible for the adequacy of
those arrangements. The Contractor may choose to adopt those concept
arrangements as the basis for applying for approval, or alternatively the
Contractor may propose his own measures as the basis for approval. Prior to
commencement of work the Contractor must provide two copies of the
Sediment and Erosion control measures plan to Environment ACT – Water
Unit for approval. Two copies of the endorsed as approved drawing(s) shall
be provided to the Superintendent.
In addition to those erosion and sediment control measures suggested in the
Contract documents and the Sediment and Erosion Control Measures Plan
the Contractor shall generally plan and manage the works to minimise
erosion on the site. It is expected that control measures may include the
following

1) Control over surface run-off by:


a. construction of interception drains to divert run-off from undisturbed
areas around the works area
b. installation of temporary drains

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

c. early stabilisation of floodways


d. use of straw bales, silt fences, swales, contour ploughing or rip dozer
cleat impressions, spreader banks.

2) Limit movement of vehicles and equipment to:


a. a single approved stabilised construction entrance
b. prepared parking areas by the construction of temporary fencing.

3) Minimise the area exposed by:


a. staging of clearing operations
b. progressive stabilisation of the works as completed
c. provision of temporary grassing
d. contour ploughing to disturbed areas.

4) Construction of sediment control measures such as:


a. sediment retention ponds,
b. sediment basins
c. sediment traps (various types)
d. silt fences
e. buffer zones

Refer to "Erosion and Sediment Control During Land Development –


Environment ACT" for details. Where the approved control measures include
sediment retention ponds, and notwithstanding the requirements arising
elsewhere in the Contract documents or from Environment ACT and, then:

a) The ponds shall be kept empty of water for the longest practical
duration. During periods of high in-flow of water and sediment, causing
overtopping over the pond spillway, the Contractor shall regularly test
the quality of the waters being released and treat the water with
chemicals as and when necessary in order to achieve a water quality
for the released water complying with the above legislation and licence

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

and to maintain sufficient residual gypsum or an acceptable chemical


in solution to sustain treatment of subsequent inflow. When there is an
inflow which is insufficient to cause overtopping over the pond
spillway, then the water is to be treated as necessary and emptied
within three days of the inflow occurring.

b) The Contractor shall remove and dispose of accumulations of


materials from the ponds as often as is necessary to maintain their
interception capacity to at least ninety percent (90%) of the design
volume of the pond.

c) The Contractor shall develop and implement procedures and a


programme and provide all necessary equipment, materials and
labour to carry out water testing; calibration test; dosing with
chemicals; and the controlled release of waters so as to comply with
the requirements of the legislation and licence. The testing procedure
shall be developed using a turbidity meter which shall be calibrated
with a series of test results on water samples with a range of Non-
Filterable Residue levels. The Contractor shall arrange laboratory
tests for Non-Filterable Residue and obtain advice on dosage rates
ensuring that the pH is within acceptable limits, and then if possible
develop a simple field correlation technique for assessing the
suitability of the water for release. Dosing can be carried out using an
acceptable chemical such as gypsum, using a simple slurry mixing
and spreading technique designed to achieve acceptable water
quality. Gypsum is preferred because it does not change the pH and
unless there are problems in effectiveness it shall be the chemical
used. Unless specified elsewhere within the Contract, or directed
otherwise by the Superintendent, then the sediment and erosion
quality control measures will be provided, operated and managed,
maintained or replaced as necessary for the period of the contract,

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

including the consolidation period and/or the Defects Liability Period


as required to fulfil the requirements of the Pollution Control Act.

3.2.7.1 PROTECTION OF EARTHWORKS

Protect earthworks and in particular road formations from the effects of


erosion and deposition. Grade earthworks and particularly subgrades to drain
at all stages without ponding. Where run-off must cross the formation, ensure
that the stream is a broad sheet flow which crosses roughly at right angles to
the alignment and minimises the likelihood of subgrade softening. When rain
is likely or when work is not proposed to continue in a working area on the
following day, precautions shall be taken to minimise ingress of any excess
water into earthworks material. Ripped material remaining in cuttings and
material placed on embankments shall be sealed off by adequate compaction
to provide a smooth tight surface. Should insitu or stockpiled material
become over wet as a result of the Contractor not providing adequate
protection of earthworks, the Contractor shall be responsible for replacing
and/or drying out the material and for any consequent delays to the
operations.

3.2.7.2 PROTECTION OF COMPLETED EARTHWORKS

In areas where earthworks, including open drains, have been completed and
no further treatment is specified other than topsoiling and grassing or
hydroseeding, then the topsoiling and seeding shall be carried out as
specified at the earliest practicable date. Areas of exposed completed
earthworks shall, if directed, be stabilised using temporary grassing, within 28
days of formation.

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

3.2.8 CLEARING AND GRUBBING

3.2.8.1 GENERAL

Unless otherwise specified, remove all vegetation, logs, stumps, boulders,


roots, scrub, debris and dumped material and items within the limits of
clearing. Demolish and dispose of any minor man-made structures (such as
fences and livestock yards), all rubbish and other materials that are
unsuitable for use in the Works. Grass and topsoil shall not be removed as
part of this initial clearing. In advance of clearing and grubbing operations,
effective erosion and sedimentation control measures shall be implemented
in accordance with this Specification.

All trees and stumps, on or within the limits of clearing, unable to be felled
and removed by the clearing methods used by the Contractor shall be
removed by grubbing. Grub out stumps and roots over 75mm diameter to a
minimum depth of 0.5m below the natural surface or 1.5m below the finished
surface level, whichever is the lower. Backfill grub holes with suitable spoil
from excavations compacted in layers to the density of the surrounding
undisturbed soil.

The Contractor shall take all measures to prevent damage to existing


underground and overhead utility services. Every precaution shall be taken to
prevent timber from falling on private property and the Contractor shall
dispose of any timber so fallen or produce the written consent of the owner to
its remaining there. The cost of disposal of such fallen timber shall be borne
by the Contractor. Prior to entering private property, the Contractor shall
obtain consent from the Superintendent and the property owner. Damage of
any kind, including damage to trees and fencing occurring during clearing
operations shall be made good by the Contractor. The cost of repair of such
damage shall be borne by the Contractor.

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

Limits of clearing are defined as lines one metre outside the intersections of
excavation or embankment slopes with the natural surface or the outside
limits of slope rounding together with any other limits detailed. For services
trenches outside the general limits of clearing, limit of clearing is defined as
trench width plus one (1) metre either side of the trench. The Contractor shall
ensure that only the absolute minimum necessary for construction is cleared.

3.2.9 Disposal of Material

Unless otherwise specified, all materials cleared and grubbed in accordance


with this Specification shall become the property of the Contractor and shall
be removed from the site and legally disposed of. Unless otherwise specified
elsewhere, disposal of timber and other combustible materials by burning
shall not be permitted. Where permitted, the Contractor shall comply with all
Statutory requirements applicable to burning off, and any such burning off
shall be carried out in such a manner that no damage is done to any trees
outside the limits of clearing. Smoke resulting from such burning off shall not
cause a traffic hazard or a nuisance to adjacent landholders.

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

3.3 PLANNING STAGE

3.3.1 COST ESTIMATED

Construction cost estimating is demanding work, no matter what type of


construction is involved. But, estimating earthwork is the hardest of all. That
is because, excavation has more variables and unknowns; don’t know what’s
down there until start digging. Also have to rely on information from many
sources – some of which may not be accurate.
That’s why every earthwork estimator needs special skills:
a) The ability to read plans and specifications
b) An understanding of surveying and engineering practice
c) A facility with mathematical calculations
d) The ability to anticipate environmental and legal issues
e) An abundance of good common sense

In the past, many smaller dirt jobs were bid as a lump sum rather than by the
cubic yard. Dirt contractors based their bid on guesses – what equipment
was needed and how long should it takes? They didn’t bother estimating soil
quantities. Making estimates this way overcome one problem; most
excavation contractors didn’t know how to estimated soil and rock quantities.

Fuel and labour costs are too high now. And the competition is too intense.
There’s too much risk in “seat-of-the-pants” guesses. A few mistakes, a
couple of surprises and to be looking for some other type of work. Only the
best survive for long in this business. Most of the survivors know how to
make accurate bids by the cubic yard. Fortunately, making good quantity
estimates isn’t too hard if mastered a few simple skills.
[ CITATION Der07 \l 1033 ]

3.3.1.1 THE SITE VISIT


A site visit is an important part of every earthwork estimate. If skip this
important step, the estimate is just a guess.

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

1) Review the plans first


Before go to the site, take time to review the plans completely. Make
an itemized list of any special problems or unusual requirements; pick
up from plans and specifications. Take that list and check each item
while in the field.

The amount of information provided on the plans will determine how


much work have to do to prepare for the site visit. If have a complete
set of plans and specifications, it’s easy to list the questions that need
answers.

When go into the field on a site visit take along two lists. The first is a
list of specific questions based on the current plans and specifications.
The second is standard checklist for site visit. Every estimator needs a
checklist to work from. Maybe overlooked something once; put it on
the list.

2) Make the visit productive


The visit to the site can make a significant difference in the amount of
the bid – and size of contractor’s profit. Analyze the job site anticipate
problems that might interrupt work scheduling, situations that require
specialized equipment, or shortcuts to speed the work along. It takes
knowledge and experience to make the site visit productive. Most of
the know-how comes from experience on past projects. Also can use
common sense to come up with a more cost-effective way to d the job.
Use the site visit to plan the construction scheduling and to anticipate
equipment and labour requirements. The actual conditions of the site
will dictate the type of equipment needed and the way the work is
done.

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

3) Accessibility
First, consider the physical location of the site. How remote is it? What
roads or streets lead to the site? Are the any one-way streets leading
to the site? All this will have a direct bearing on the work. If have to
bring dirt in or take it out, consider the distance to the borrow or dump
site. In fact, recommend driving the route several times, using different
roads to find the shortest and best route. If the surrounding streets
carry heavy traffic, it will slow down the movement of equipment to
and from the work site. Will traffic problems require the use of one or
more flagmen? Look for any other safety-related problems that might
require additional manpower. Is the site near any homes or business?
Is there a noise ordinance and its enforced? Take complete notes
during the site visit on any variable that will affect the profit and works.

4) Degree of job difficulty


Are there any steep slopes that would require unusual equipment? Is
the area open, or are these obstructions like buildings, trees,
sidewalks, or utility lines in the way? Any of these will slow down the
production. If specialized equipment is needed, will it e available in the
area or will have to bring it in from a distance. This is a good time to
decide what size and type of earthmoving equipment to use. Consider
whether there’s enough room for the equipment to turn and move
economically. When making the decision, consider the ground
conditions, traction, and the distances and directions have to move.
Remember, the track machines have a slower working speed.

5) Surface condition
Drainage problems, steep slopes, dense vegetation, and sharp or
large rocks scattered on the surface will all hamper production.
Drainage is one of the biggest problems. Provide the drainage
channels to reroute water during construction. But can’t divert water
onto streets or roads.
AP 226 / 1C | JULY – NOVEMBER 2009
PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

6) Subsurface conditions
Even have the soil tests on the site, the actual conditions of the soil
below the surface are really anybody’s guess. Water running on the
surface indicates underground water seeps. If the work limits are
below the local water table, have to pump water from trenches and the
excavation portions of the job.

7) Utilities
Try to determine if utility lines are shown in the correct location on the
plans. Utility lines sometimes aren’t where the plans show them. A
variation of just a few feet can make a big difference in time when
working in a confined area. If there exist storm or sewer lines, check
the manholes for conditions, material and depth to flow line. Also
check for size, direction and number of inlets and outlets in the
manhole. Check for overhead wires that would be in the way of
working equipment. Will the temporary electric or phone connection
are needed.

8) Project size
Consider whether building materials and equipment can be stored on
the job site without interfering with the work.

9) Local needs
Locate local suppliers of fuel, repairs, parts and any other operations
needs. Find out the policy on credit or payments. Get an agreement in
writing if possible. Plan to use local workers, expected wages for the
labour.

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

10)Traffic control
If the project will need traffic control, check with the local authorities to
see what they require. Most of them spell out traffic control
requirements very clearly. There are exact standards for barricades,
delineators, flashing light and other safety precaution.

11)Security
The job site is isolated or in an area with high crime rate, may want to
hire a security company. Vandalism to equipment or material, theft,
and destruction of completed work can be a major financial loss. Most
of it won’t be covered by the insurance. That makes it a cost of doing
business. Also consider public safety. Job will probably drawn
sidewalk superintendents. Everyone loves watching heavy equipment
at work. So, need to protective fencing around the area, to keep
people out of danger.

12)Existing and imported soil


Look at the soil itself, both the existing soil any soil that must be
trucked in. Checked the compaction requirements. The more
compaction needed, the more time required for rollers.

3.3.1.2 THE BULK AND SHRINK FACTORS


Using the bulk and shrink factors to make the estimated more accurate.
That’s because a given quantity of soil has no constant volume. Add moisture
and the soil bulks, expanding in volume. Soil volume also increases when it’s
loosened or disturbed by excavation. Conversely, the soil volume shrinks or
contracts when apply pressure to compact the fill. Actual bulk and shrink
factors consider the combined effect of:
a) Moisture content
b) Density (compact versus loose)
c) Soil type

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

The volume of soil in the original ground will change when the soil is
excavated and loosened, or when it is filled and compacted. The volume of
soil should be adjusted so as to compute the volume to be excavated, hauled
and embankment on a common basis.

1) Bulking Factors

Volume of loosened soil after excavation


Bulking factors (L) =
Volume in the ground before excavation

Soils and rocks usually swell when they are excavated; thus 1m 3 of
material in the ground will occupy more than 1m 3 in the transporting
vehicle. This must be allowed for in assessing the amount of transport
required and their number of trips and therefore the cost of
transporting materials.

2) Shrinkage Factors

Volume after compaction


Shrinkage factors (L) =
Volume in the ground before excavation

Excavated soils except some firm granular materials usually shrink


when they are compacted. Necessary to plan how much volume of
soils is to be hauled to which parts of embankments; to estimate how
much volume of soil in the ground shall be cut and borrowed to form
an embankment.

Both factors are assisting to measure the output productivity before run the
construction. It does also can calculate the number of excavator, Lorries and
labour needed to carry out soil from the site or embankment the soil to the

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

site. There are also help to preparing the budget and time duration for
earthwork operations.

Bulking and shrinkage factor of various soil


Type of soil Bulking factor Shrinkage factor
(L) (C)
Rocks
a) Hard rocks 1.65 – 2.00 1.30 – 1.50
b) Loose rocks 1.30 – 1.70 1.00 – 1.30
c) Boulders/cobbles 1.10 – 1.20 0.95 – 1.05

Gravelly Soils
a) Gravels 1.10 – 1.20 0.85 – 1.05
b) Gravelly soils 1.10 – 1.30 0.85 – 1.00
c) Solidified gravelly soil 1.25 – 1.45 1.10 – 1.30

Sands
a) Sandy 1.10 – 1.20 0.85 – 0.95
b) Sandy & cobble 1.15 – 1.20 0.90 – 1.00

Common soil
a) Sandy soils 1.20 – 1.30 0.85 – 0.95
b) Sandy soils with cobbles 1.40 – 1.45 0.90 – 1.00

Cohesive soil
a) Cohesive soils 1.20 – 1.45 0.85 – 0.95
b) Cohesive soil with 1.30 – 1.45 0.90 – 1.00
gravels 1.40 – 1.45 0.90 – 1.00
c) Cohesive soil with
cobbles

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

3.3.1.3 CALCULATION

Figure 4 The soil that will excavate. (35, 000m3)

This site will be excavate soil from reduce level 21.00 to 15.00 and the soil
had to dispose to the dumping area. The total volume of soil to be disposed
is about 35,000 m3.

Below show the calculation how many excavator and lorries required for this
project done in 9 weeks.

If duration to complete = 9 weeks


= 54 days

Bulking Volume
35, 000m3 x 1.15 (bulking factor) = 40, 250 m3

Excavator required
40, 250 m3
= 0.57 = 1 unit excavator
1, 300 m3 (output excavator/day) x 54 days

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

Lorries required

a) Nos of trip
40, 250 m3
= 4, 025 trip
10 m3 (capacity lorry per trip – unlicensed lorry)

b) Time taken per trip


60 minute x 1km (distance) x
= 4 minutes
30 km/hour (lorry speed) 2

c) Time to load and upload


Assume = 7 minutes + 4 minutes (time taken per trip)
= 11 minutes

d) Total time taken


4, 025 trip x 11 minutes = 44, 275 minutes

e) No of lorries required
44, 275 minutes
= 1.7 = 2 units Lorries
54 days x 60 minutes x 8 hour (per day)

So, for this project, they are requiring to have 1 unit of excavator and 2 units
of unlicensed lorry to complete the project in 9 weeks. This calculation is help
to measure the requirement more accuracy and the contractor will know their
profit also can budget the cost and planning of earthwork operations.

3.3.2 METHOD STATEMENT AND PROJECT PLANNING


This Construction Method Statement (CMS) provides a summary and
explanation of the construction methods and sequencing of contractors on
site in earthwork operation of this project. This CMS is not intended to

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

provide a detailed specification for the proposed works. Rather it outlines the
sequence and extent of construction activities that may not be obvious from
the design drawings alone and that need to be considered in terms of their
impact on the surrounding environment. Detailed specifications for each type
of work will be prepared prior to the start of construction and these will
incorporate any restrictions on working practices demanded by the outcome
of the various environmental and planning studies that will accompany the
planning application, together with any Planning Conditions that may
subsequently be applied.

3.3.2.1 EARTHWORK

1) Scope of Works

The main purpose of this method statement is to outline the activities and
method, which will be used in general to carry out the earthworks in
accordance with the Contract Specification, and details shown in the
drawings.

2) Resources

a) Hydraulic Excavator PC300 for excavation and shifting material.


b) Hydraulic Excavator EX200 for excavation and shifting material.
c) Unlicensed 10-Wheeled Dump Truck for transport material.
d) Back pusher Tractor Ford 5000 for levelling.
e) Vibratory Compacting Roller CA25 for compaction of earth.
f) Concrete mixer.
g) Manpower etc.

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

3) Sequence of Works
a) Survey Setting Out

Confirm pre-computation plan and other given references for establishment


of points or lines for our setting out of the Works (e.g. control stations, level
pegging etc). These lines or points will be referenced to enable their
re-establishments as construction proceeds. Original Ground Level (OGL)
survey will be checked on site and verified against the construction drawing
progressively after the site clearing for any discrepancies.

b) Site Clearing

Site clearance shall be carried out within the limit of contract by removal of
fallen trees, shrubs etc. to approved tips. Stripping of topsoil will be carried
out up to about 150mm layer of soil that can support vegetation.

c) Earth excavation

For earth cut fill within the site, earth will be excavated in bulk from
designated high areas within the site to the required depths and levels in
accordance with the drawings. Prior to filling with earth excavated area need
to be survey to confirm excavation level verified by C.O.W/client
representative. For excess excavated earth, these shall be transported,
spread and levelled along side of the site boundary. Compaction of the earth
shall be carried out in layers with a vibratory compacting roller of 20-tonnes
capacity or more in operation. The thickness for fill shall be 300mm each
layer according to specification. However, the swell factories are various from
0.6 to 0.8 depend on the properties of the earth. Hence, at the loose state,
the loose measure thickness various. A trial compaction test will be carried
out to demonstrate the compaction method and numbers of passes to be
used. The method statement of the trial compaction will be submitted
separately. Field density tests as per compaction requirements shall be

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

carded out on requests and at an agreed interval depths at earth fill areas
and to be witnessed by authorized Representative. Close turfing to slopes
shall be carried out upon completion of sizeable area. As built level survey
shall be carried out upon work completion and submit to Engineer.

d) Rock excavation & blasting

Excavation in solid rock in open excavation shall mean in rock found in


ledges or masses in its original position, which would normally have to
loosened either by drilling and blasting or be pneumatics tools. All solid
boulders or detached piece of rock exceeding 9 cubic feet in size, but not
otherwise, shall be regarded as solid rock. The solid rock shall be joint
measured with Clerk-of-Work prior to commencement of blasting operation.
The crawler drilling machine shall used to drill the 3" diameter blast-holes
with interval of 1.8m to 3.Om depend on the site condition. Blast-holes shall
be placed in lines parallel to the rock face because a rectangular patter gives
better breakage and vibration control. Depth of drill holes is determined by
height of face desired and distance it is necessary to drill below grade so that
bottom can be controlled. Air compressor shall be used to -remove water
capture inside the blast-hole prior to insert explosive to the blast-hole. ANFO
consists of ammonium nitrate (AN) and fuel oil (FO) at the ratio of 6% (FO)
and 94% AN. Ammonium nitrate shall be used as explosive for blasting rock
into pieces small enough to be handled efficiently by hydraulic excavator.

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

The recommended method of making primer with a small diameter cartridge


as below:

i. Punch a hole through the plastic film with wooden pricket near the
middle of the cartridge.
ii. Fully insert the plain detonator into the cartridge.
iii. Wrap electrical insulation tape, around the cartridges from the
detonator to the end of the cartridge along safety fuse, securing the
detonator. When priming the blast hole, ensure that the detonator
points to the bottom of the blast hole so that the safety fuse is not bent
sharply.
iv. It is necessary to vary the length of safety fuses when firing multiple
blast hole so that the blast holes fire in the desired sequence. All
safety fuses shall be connected into series and joint to exploder to
commence the blasting works.
v. Safety signboard and red flag shall be placed in the necessary places
prior to commencement of blasting works.
vi. Blasted rock shall be removed and deposited to the area within the
site directed by S.O.

e) Field Density Test

A trial compaction test will be carried out to demonstrate the compaction


method and numbers of passes to be used. The method statement of the trial
compaction will be submitted separately. Field density tests (Sand cone
replacement method) as per compaction requirements shall be carried out on
requests and at agreed interval depths at earth fill areas and to be witnessed
by authorized Representative.

AP 226 / 1C | JULY – NOVEMBER 2009


PLANNING AND CONTROLLING OF EARTHWORK BLD
OPERATION MULTI-STOREY PROJECT 410

The requirement of the degree of compaction are:

i. For the topmost 12 in below formation level less than 95% of the
maximum dry density obtained from BS Heavy Compaction Tests.
ii. For the remainder below formation level less than 90% of the
maximum dry density obtained from BS Heavy Compaction Tests.

AP 226 / 1C | JULY – NOVEMBER 2009


3.3.2.2 EXAMPLE OF METHOD STATEMENT FORM

NO OPERATION SEQUENT OF DIAGRAM MACHINERIE REMARKS


S/PLANT

1. Site Clearance and Stripping Top 1 Excavator,


Soil
1 Bulldozer,
- For a site condition that full of
bushes and vegetation, as well as 1 Back pusher.
several huge trees that existed in that
area. Site clearance is carried out to
all areas occupied by the works area.
All the trees, scrub, stumps and
bushes within the site boundary are
removed completely, including
grubbing out of all roots.

AP 226 / 1C | JULY – NOVEMBER 2009


NO OPERATION SEQUENT OF DIAGRAM MACHINERIE REMARKS
S/PLANT

NO OPERATION SEQUENT OF DIAGRAM MACHINERIE REMARKS


2. Excavation (Cutting Soils) and 1S/PLANT
Excavator,
Removing Unsuitable Materials
2 Dump Truck,
3. Placing,
A surveyor shallSpreading
mark at certain point and 1 Excavator,
Compaction Of Fill Materials
at the site. Marking point using wood To
The
sticksSpecified
are for Dry theDensitypurpose of 1 Back pusher,
awareness of the machine operator
The
whennext stepsoils,
cutting is filling thewritten
which soils ishow
the
selected position with
deep the excavation suppose hasto be an
information of platform level
done at certain area at the site. and then
spread by the back pusher.
The excavation had done by used an
After that, compact the soil using the
excavator.
vibrating roller. This step must do with
properly
While 2 dumpto get a is
truck soilwaiting
with for
neatly
the
packed together and to make
excavator to fill the soil on the truck sure
that the building
and remove it to thethat is going
disposal to be
area.
build is stable and will not collapse.

AP 226 / 1C | JULY – NOVEMBER 2009


AP 226 / 1C | JULY – NOVEMBER 2009
3.3.2.3 PROJECT PLANNING

This is an example for preparing the Critical Path Method. The project
planning must included the time duration, cost, resource, management and
sequence of work for this SOHO project.

Figure 5 Critical Path Method

AP 226 / 1C | JULY – NOVEMBER 2009


3.3.3 CONSTRUCTION METHOD AND USE OF PLANT

3.3.3.1 PLANNING OF WORK

Prior to the commencement of excavation all the relevant data should be


collected and drawings prepared showing the location of the excavation,
tipping and filling. On these drawings both the excavation and filling should
be divided into section and the quantity of material to be excavated and filled
stated in these sections. This information is required to ensure economic
hauls throughout the work, in which connexion a ‘mass-haul’ diagram is
often. [ CITATION Bri03 \l 1033 ]

Where the material is to be excavated consists of different types, and if the


various types have to be used separately in the fill or run to spoil tip, the
quantities of each class of material in each area should be shown on the
drawing. From the nature of the material to be excavated and the method of
its disposal, the type of excavation, the length of haul, and the amount of
compaction necessary, it is possible to select the most suitable type of plant
for:

a) Excavating (when quantities are large it may be economical to use


diffrent types of equipment for the various materials to be excavated).
b) Transporting the excavated material (the length of haul, the nature of
the route selected, the conditions of tiping or speading, and the type of
excavator adopt, should be considered).
c) Placing the material (the methods and plant used for transporting and
compacting the material should be considered).
d) Compacting the material (the nature of the material and the relative
compaction specified are essential considerations).

AP 226 / 1C | JULY – NOVEMBER 2009


3.3.3.2 SETTING OUT

When setting out earthworks it is first necessary to set out the centre line or
other reference lines, and then the lines indicating the top of the cutting or the
toe of embankment. These lines should be ascertained from cross sections
of the existing ground the finished work. Reference pegs should also be
driven into the ground at a fixed distance outside the peg marking the top of
the cutting or the toe of embankment. All levels should be referred to an
established bench mark not subject to subsidence or interference. Batten
profiles are useful to indicate the slopes to which embankments are to be
constructed. In setting out both cuttings and embankments, allowance should
be made for hand trimming and soiling.
Method of Excavation

The types of excavating plant to be used will depend on the materials to be


excavated.

For soft or loose materials, e.g. topsoil, gravel, sand, and most clays, all
types of excavating plant referred to in Clause 7.05 are most suitable and the
choose for a particular job will depend on the conditions of working and
possibly, on the plant available.

When excavation has to be carried out below water level, draglines or grabs
are generally used. In deep or wide water, floating dredgers may be
desirable.

For hardest materials, e.g. stiff clays, shale’s, marls, soft chalk, heavier and
more powerful models than those used for soft or loose materials are
generally required. It may also be necessary to employ rooters or scarifies to
break up the surface of the material before the excavating plant can be used.

AP 226 / 1C | JULY – NOVEMBER 2009


For hard rocks, e.g. all rocks which require drilling and blasting before they
can be excavated, face shovels are most suitable excavators for loading after
blasting. Draglines or grab can be used but not so useful as face shovels.

3.3.3.3 OBSTRUCTIONS

In general, obstructions such as trees, roots, and boulders should be


removed if they are detrimental to or likely to hinder the works.

a) Trees
Trees can be removed using mechanical equipment such as tree
pullers, bulldozers, special rooting attachments fitted to crawler
tractors, and power-operated logging winches mounted at the rear of
track laying tractor.

Alternatively, the trees may cut off at a height of not more than 3 ft
above the ground and the stumps grubbed out by means of winch
gear or high-velocity explosives, or a combination of both.

b) Boulders
Generally boulders which may interfere with the work should be
removed, after breaking down if necessary. In the case of
embankments they may instead be broken down to a size not
exceeding the thickness of the compacted layer of fill. Boulders are
usually broken down by means of explosives although plugs and
feathers or hydraulic cartridges may be used, particularly when the
use of explosives is inadmissible.
There are three methods of dealing with boulders by explosives:
i) Bore a hole about halfway through the boulder into which the
explosive charge is placed and thoroughly tamped.

AP 226 / 1C | JULY – NOVEMBER 2009


ii) Plaster Shot methods. The surface of the boulder should be
roughened by means of a chisel or other implement, removing
any moss or clay coating and thus ensuring a clean surface.
iii) Place a sufficient charge underneath and in contact with the
boulder in a hole made in the ground by means of crowbar.

c) Safety Precautions
Blasting methods should be carried out only by persons thoroughly
conversant with the working methods and precaution and regulations
to be observed in using explosives, and with local police requirements.
To avoid the danger of injury from flying debris all personnel in a
blasting area should retreat several hundred feet and take adequate
cover.

3.3.3.4 EXCAVATING PLANT

Some notes on the types and use of excavating plant are given below:
a) General purpose excavator
This machine is a versatile and universal construction tool capable of
carrying out many different type of front end or jib equipment it can be
used as a dragline, backater or drag-shovel, grab, crane, shovel,
skimmer, or pile driver.

b) Face (or crowd) shovel


Face shovels will dig soft or reasonably hard materials, including soft
chalk, shale and marl, and hard rock when reduced by blasting. They
are a quickly-acting type of machine and work from the bottom of
excavation, digging upwards from the level on which they stand. They
can produce a reasonably clean bottom in many materials. Generally,
the face shovel requires vehicles for transporting the material away
from the excavation.

AP 226 / 1C | JULY – NOVEMBER 2009


c) Dragline
The dragline is suitable for a wide range of materials but it will not dig
such hard material or leave such a clean surface as the face shovel. It
operates from the surface of the material to be excavated, digging
below itself. Where access of vehicles to the bottom of the excavation
is difficult, the dragline working from the top is to the face shovel
working on the bottom; the time cycle of operation is slightly longer
than of the face shovel and its output is rather less. For digging
narrow cuts and depositing alongside it have great advantages over
the face shovel as it has a much greater reach. It is, therefore, used
extensively for cleaning out river beds, forming flood banks alongside
rivers and stripping overburden from mineral deposits. In trench work,
this machine is generally used, with buckets varying in capacity from
¼ to 2 cu.yd, for wide trenches with roughly battered sides. It is
particularly useful for excavating water-logged materials.

d) Backwater or drag-shovel (trench hoe)


This type of excavator is generally used for excavating trenches of
comparatively narrow width and in materials whichare too hard for a
dragline. It is commonly of ¼ to ¾ cu.yd bucket capacity, working on
the surface, will dig in a single cut vertical trenches up to about 15 ft
deep and from 2 to 5 ft wide.

e) Grab
A grab may be used with a dragline excavator or crane on sites such
as foundation pits and trenches where the dragline bucket cannot be
employed. It is also largely used for under water work.

f) Track-laying tractor and scaper


This equipment is capable of both excavating and transporting the
material, and can in certain materials and where suitably routed give a

AP 226 / 1C | JULY – NOVEMBER 2009


considerable degree of compaction in the fill without the use of any
other compacting equipment. It is suitable for use in the softer
materials, but can be used for harder materials if the material to be
excavated is first scarified or broken up with a rooter, or with the help
of booster. It may become uneconomic to use this type of tractor and
scraper for lengths of haul over about 600 yd.

g) Grader or blade grader


Graders or blade graders are used principally for the finished grade for
roadways, aerodrome runways, or similar types of work, and for
spreading a sub-base of ashes or similar material over the area being
treated. They may also be used for bank trimming where the slope of
the embankment is not to steep, and for cutting V-Shaped ditches up
to 3 ft deep in open country. Heavy types of graders are capable of
moving large quantities of earth over short distances and may be used
for constructing the whole earthworks for a roadway from virgin ground
to completed soil information. Heavy types of graders can be fitted
with scarifiers, bulldozer blades, snow ploughs, and side or rear end
elevator loader attachments of the endless belt type.

h) Bulldozer and angle dozer


These machines are primarily designed for spreading and levelling
operations, but are also used for backfilling and excavating shallow
cuttings. They will work satisfactorily in soft or loose materials
provided the tracks will gap. The usual length of push does not
normally exceed 100 – 200 ft.

3.3.3.5 TRANSPORT PLANT


a) Tractor-drawn equipment
Scrapers or wagons drawn by track-laying tractors are satisfactory for
the transportation of excavated materials over short distances and

AP 226 / 1C | JULY – NOVEMBER 2009


rough ground, or where tipping is difficult. Normally the distance
should not exceed about 600 yd. If a suitable road is available,
wheeled tractors are preferable and, in any case, where long hauls are
involved they should be used; the larger types then become more
economical. The advantages of the wheeled tractor over the track-
laying type are in the speed of operation, the greater capacities and
the freedom from expensive track renewals. The capacities of
scrapers and wagons range from 4 to 40 cu.yd or more. Hauls of 2 to
3 miles are common for wheeled tractors.

b) Lorries and other rubber-tyred vehicle


Many types of lorries and other from 5 to 20 tons. They include steel-
bodied tipping trucks, and end- or side- tipping or bottom-opening
dump wagons. Special rubber-tyred vehicles not suitable for operating
over public roads are made up to40 cu.yd capacity. Dumpers, with
capacities of up to 5 cu.yd, are suitable for hauls of up to about 1 mile.

c) Belt conveyors
Belt conveyors are finding increasing use for the transport of
excavated material both on short and long hauls. Operating with
suitable loading and spreading equipment to ensure uniform flow,
there are very suitable for moving large volumes of excavation. They
are most frequently used for handling materials of fairly even
consistency, such as sand and gravel, over short distance, but really
large quantities may justify the expense of installing them for moving
almost any excavated material over long distances.

3.3.3.6 COMPACTION PLANT


a) Vibrating rollers and plates
These machines are particularly effective on granular soils. The
vibrating roller is a smooth wheeled machine fitted with an engine

AP 226 / 1C | JULY – NOVEMBER 2009


driven vibrating unit. It is made in various sizes ranging from about 3
cwt (hand propelled) to 3½ tons (tractor drawn). Power-propelled
machines, both of the single roller and tandem-type, are available in
the intermediate sizes, the smaller models being hand-guided.
Vibrating rollers have a tendency to dig themselves in when used on
too thick a layer.

b) Construction equipment
Plant used for construction purposes will provide useful compaction if
it is suitably routed to cover the whole area, and if the soil is spread in
sufficiently thin layers. Such compaction may in certain cases be
useful in minimizing or even obviating the use of special compacting
plant. Where material is transported by scraper equipment, the fill may
be distributed in shallow lifts by the scrapers themselves. Where
lorries or dumpers are used, bulldozers and angle dozers should be
used to spread the fill material.

3.3.3.7 EFFECT OF WEATHER ON CONSTRUCTION OPERATION

Very little can be done to protect earthworks from weather as the nature of
the works and their extent generally preclude the use of any covering.

a) Effect of wet weather on plant operation.


Rainfall may so affect the exposed surface of cohesive soils as to
result in interruptions both in the use of excavating plant in the
transport of materials. Airfield works, with their extensive use of
pneumatic-tyred plant over shallow cuts fills, are particularly affected
by intermittent wet periods. Where construction roads are required in
connection with earthworks they should be adequate for the
anticipated traffic, and if possible, laid out and constructed during dry
weather.

AP 226 / 1C | JULY – NOVEMBER 2009


b) Effect of weather on compaction of earthworks.
The moisture content of any soil governs the degree to which it may
be compacted.

If the soil is very wet it may be impossible to achieve a satisfactory


degree of compaction. If the soil is very dry, a large amount of rolling
or tamping may be required to compact is satisfactory. Thus, in wet
weather, work may have to be stopped entirely owing to excessive
moisture near the surface of the soil, while in dry weather it may be
necessary to add water to the soil before compacting it in a fill or
embankment. Both of these difficulties may be diminished if the soil
required for filling is protected as much as possible from direct
exposure to the weather, e.g. by leaving the topsoil or over-burden in
place until the time has come to excavate the subsoil. It is advisable to
compact the soil in its final position in the fill or embankment
immediately after it is placed.

AP 226 / 1C | JULY – NOVEMBER 2009


4 CONTROLLING FOR OPERATION OF EARTHWORK

4.1 INTRODUCTION
Earthworks monitoring checks the performance of the fill during or post-filling,
depending upon the design of the equipment. Normally, the engineering
quantities measured are fill settlement or groundwater level, since both may
have significant effects on performance. Thus if the specification required a
certain maximum settlement after embankment construction, post-filling
settlement monitoring would indicate whether or not settlement was within
the stated limits. Hence monitoring is a control on the engineering
performance of the fill platform.

Monitoring should be regarded as essential for sensitive structures and


where groundwater rise within the fill is a possibility. The techniques available
include:

Surface leveling stations (monuments) to measure settlement of the fill


surface (post-filling).
Settlement plates (rod extensometers) to measure the settlement of
the fill thickness (during and post-filling)
Magnetic extensometers to measure the settlement at incremental
depths of the fill (during and post-filling)
USBR settlement gauges (during and post-filling)
Piezometers to measure to measure the water level in the fill (post-
filling)

Instrument reading should be made for as long as possible after construction,


if necessary during commissioning the structure. In practice, except for large
sites, it is difficult for continuous monitoring to extend beyond a year or so
but, for sensitive structures, it is vitally important that measurements should
be obtained during at least one wet season. If collapse settlement in

AP 226 / 1C | JULY – NOVEMBER 2009


occurring, due to inundation, some indication may be obtained during this
period.

4.1.1 SURFACE LEVELLING STATION (MONUMENT)


Such stations should be positioned as soon as an area of fill has been
brought up to finished level. This will mean that the maximum time will be
available for settlement readings, noting that, for obvious reasons, none can
be made using this form of equipment during fill placement itself. Because of
the heavy plant frequenting construction sites, a surfacing leveling station
should be robust, comprising a concrete block about 1 m³ in size, sunk about
300 mm into the fill surface; a metal stud should be cast into the top, from
which optical leveling may be conducted. Readings will give the total
settlement of the fill and that of the underlying soils, if they were not removed
prior to filling.

AP 226 / 1C | JULY – NOVEMBER 2009


4.1.2 SETTELEMENT PLATE (ROD EXTENSOMETER)
Unless the natural ground is stiff and will not deform significantly under fill
(and structure) load, surface leveling stations measure settlement of the
underlying soils as well as the settlement of the fill. This is problem where the
natural ground is soil and rock, and where the settlement of the soil beneath
the fill could represent a significant proportion of the total settlement at the fill
surface. In cases such as these, settlement plates (rod extensometers) may
be employed. They monitor fill settlement continuously during and after
placement and not from completion of filling only.

Settlement plates comprise a base plate, usually of the order of one metre
diameter, on to which a suitable length of casing is welded. The base plate is
placed on to natural ground surface with the casing upstanding and fill
carefully placed and compacted around it, during filling works. If it is
necessary to extend the casing vertically upwards in order to cope with
greater fill thickness, additional casing lengths may be welded or screwed on.
From time to time, a rod of known length is introduced into the casing from
the surface to the base plate and a reading of the settlement of the
underlying natural ground is taken by leveling the top of the rod. The surface
of the fill, say 2 m from the casing, is leveled at the same time at say four
position (N, S, E and W) and the result averaged. The difference between the
settlement of the underlying natural ground and the fill surface is the
settlement of the fill. Settlements may be measured a different time during
and after filling and a graph plotted showing settlement against time.

Friction between the fill and the casing means that the fill can hang-up on the
casing, so that the settlement at the surface close to the casing may be less
than the true value. To avoid this undesirable feature, reading of the fill
surface should not be taken too close to the casing. Care should also be
taken to site the settlement plate on reasonably flat natural ground beneath
the fill.

AP 226 / 1C | JULY – NOVEMBER 2009


4.1.3 MAGNETIC EXTENSOMETER
This equipment is often employed where, for example, the compressibility of
one fill type is being compared with the compressibility of another, or where it
is necessary to separate the settlement of the fill from that of the underlying
soil upon which the fill is placed. Magnets are located is the fill about a
central plastic tube grouted into a borehole sunk to hard ground beneath the
fill. A probe lowered down the tube locates the magnets and measures their
position with respect to the base of the borehole (presumed fixed). Results of
the settlements recorded by a magnetic extensometer installed at the site
referred to in Section 8.7.2 are illustrated in Figure 8.8, where the settlement
are recorded as percentage change in fill thickness.

A device which can be built up from the base of the fill, along the lines of the
settlement plate and USBR gauge (describe in the next section) is also
available. It therefore has the distinct advantage over the surface leveling
station in monitoring fill settlement continuously during and after placement
and not from completion of filling only.

4.1.4 USBR SETTLEMENT GAUGE


The USBR settlement gauge (United States Bureau of Reclamation Manual,
1974) comprises a series of cross –arm being separated by standard length
spacers. The basal pipe sections is grouted into hard ground beneath the fill
(perfumed fixed) and further sections added at a rate consistent with the rate
of fill being deposited. Settlements of the various cross-arms are measured
by a torpedo unit lowered down the central pipe sections. Unlike the
settlement plate which provides the total fills settlement, the USBR gauge
indicates the settlement of the fill at each cross-arm location. In this respect,
the device compares with the magnetic extensometer.

Results obtained from a USBR gauge installed in 59 m of the open-cast fill


arm (expressed as percentage change in fill thickness) are plotted against fill
thickness t a log scale and an approximately linear relationship results. There

AP 226 / 1C | JULY – NOVEMBER 2009


is some scatter about the trend lie but this should be expected given the
variable nature of the open-cast fill concerned.

4.1.5 PIEZOMETER
A piezometer (preferably a porous ceramic pot, equipped with granular
surround) provides a direct indication of the water level at the location
installed. Dipped at the same intervals at which settlement readings are
recorded it provides direct evidence of any link between settlement and water
rising in the fill (Figure 8.7 is an example).

Because of the importance of establishing such a link, piezometers should be


positioned as close as possible to the settlement measuring device: not only
does this procedure provide maximum information at the position at which
settlement readings are being taken but, by ring-fencing the top of the
piezometer and the settlement device, allows better protection from
construction plant.

Where pore pressures measurements are desired in clay fill, hydraulic


ceramic piezometers are normally employed. They required a much more
sophisticated level of monitoring, with each piezometer controlled via twin
nylon tubes to a manometer in an adjoining gauge hut. Unlike the
Casagrande piezometer which measures positive pore pressures only; such
equipment can measure both positive and negative pore pressures. Further
information may be had from Hanna (1985) or Dunnicliff (1988).

AP 226 / 1C | JULY – NOVEMBER 2009


4.2 SLOPE PROTECTION.
Often excavations for earthwork construction intercept the existing
groundwater table, thus interrupting the natural flow of groundwater. This
does not affect the building until the groundwater flow emerges on the cut
slope. If the flow is small, there may be no adverse effects. However, when
the flow is significant and the conditions at the site are favorable, flowing
water can cause seepage forces that will in turn cause the slope to slough or
fail.

To stabilize slopes under these conditions, a heavy material is placed


on the face of the slope. This material is heavy enough to hold down the
existing soil even though seepage forces are acting in an outward direction.
At the same time, it is open enough to carry all the water emerging from the
existing soil. A coarse-graded stone, slag or gravel blanket on top of a
recommended geotextile has proven to be effective in these cases. The
drainage blanket should be designed before construction, but weather
condition during construction will substantially influence the actual need for
such treatment.

AP 226 / 1C | JULY – NOVEMBER 2009


4.2.1 STABILIZATION OF CUT SLOPES

4.2.1.1 INTRODUCTION
Cut slopes may require stabilization for the following reasons:

Failure of the slope as originally designed


Strictly limited land-take, requiring steeper slopes than the ground
would safety provide unaided. This is common in an urban or sub-
urban environment.
Ground conditions at the time of construction are found to be less
favourable than those foreseen at time of the site investigation. As a
consequence, either slacker slope have to be adopted (resulting in
increased land –take) or the originally planned side slopes are
maintained but a form of stabilization has to be adopted
Road widening is necessary

For these conditions, stabilization may be achieved by retaining wall, soil


nails, anchors or reticulated mini-piles. Other methods of the stabilization
include drainage and embedded gravity, gabion or crib walls. An excellent
account of the various methods available for slope stabilization.

AP 226 / 1C | JULY – NOVEMBER 2009


4.3 METHODS OF GROUNDWATER CONTROL

4.3.1 Sumps and Ditches


Installation of ditches, French drains, and sumps within an excavation
is one of dewatering procedure. The water entering the excavation can be
pumped out. This method of dewatering generally lower groundwater head
more than a few feet but seepage into the excavation may impair the stability
of excavation slopes or have a detrimental effect on the integrity of the
foundation soils. Therefore, filter blankets or drains may be included in a
sump and ditch system to overcome minor raveling and facilitate collection of
seepage. The disadvantages of a sump dewatering system are slowness in
drainage of the slopes, potentially wet conditions during excavation and
backfilling which may impede construction and adversely affect the sub-
grade soil, the space required in the bottom of the excavation for drains,
ditches, sumps, and pumps and the frequent lack of workmen who are skilled
in the proper construction or operation of sumps.

A common method of excavating below the groundwater table in


confined areas is called as cofferdam. Wood or steel sheet piling are drove
below subgrade elevation and bracing are installed to excavate the earth.
Any seepage that enters the cofferdammed area will be pumped out.
Dewatering a sheeted excavation with sumps and ditches is subject to the
same limitations and disadvantages as for open excavations. However, the
danger of hydraulic heave in the bottom of an excavation in sand may be
reduced where the sheeting can be driven into an underlying impermeable
stratum, thereby reducing the seepage into the bottom of the excavation.
Excavations below the water table using sheeting and sump pumping can
sometimes be successful. However, the sheeting and bracing must be
designed for hydrostatic pressures and reduced toe support caused by
upward seepage forces. The bottom of the excavation can be covered with
an inverted sand and gravel filter blanket to facilitate construction and
pumping out seepage water.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 6 Dewatering open excavation by sump and ditch.

The necessary characteristics of a sump are as follow:


1) The final sump must be deep enough so that when it is pumped out,
the entire excavation will be drained. Digging the sump down that
extra several feet is difficult and sometimes risky. Therefore,
temporary sump at shallower level should be constructed to improve
conditions so that the final sump can be safely constructed to the
proper depth.
2) Water flowing to the sump will carry fines, which are abrasive and
damaging to pumping equipment. The approaches to the sump should
be arranged to remove much of the fines by sedimentation or filtration.
3) The size of the sump should be substantially larger than that
necessary to physically accommodate the pumps. Ample size allows
for a reduction in water velocity so that fines settle out, and the space
provides storage for the sediment between cleanings.
4) The sump should be arranged for convenient servicing of the pumps
and so that accumulated sediment can be readily removed.

Figure 7 Submersible pump for dewatering an excavation.

AP 226 / 1C | JULY – NOVEMBER 2009


4.3.2 Deep-Well Systems
Deep wells can be used to dewater pervious sand, rock formations or to
relieve artesian pressure beneath an excavation. They are suited for
dewatering large excavations which require high rates of pumping. Deep
wells also can be used for dewatering deep excavations such as dams,
tunnels, locks, powerhouses, and shafts. Turbine or submersible pumps are
used to dewater by pumping from deep wells for deep excavations. The
advantages of deep wells are that they can be installed around the periphery
of an excavation and thus leave the construction area unencumbered by
dewatering equipment.. Besides, the excavation can be predrained for its full
depth.

Figure 8 Deep well system for dewatering an excavation in sand.

Deep wells for dewatering have a screen with a diameter of 6 to 24 inches


with lengths up to 300 feet. They are generally installed with a filter around
the screen to prevent the infiltration of foundation materials into the well and
to improve the yield of the well. In order to dewater small, deep excavations
for tunnels, shafts, or caissons sunk, deep wells may be used by adding a
vacuum system to the well screen and filter. The addition of a vacuum will

AP 226 / 1C | JULY – NOVEMBER 2009


create a vacuum within the surrounding soil. This will prevent or minimize
seepage from perched water into the excavation. Installations of this type,
require adequate vacuum capacity to ensure efficient operations of the
system.

Figure 9 Deep wells with auxiliary vacuum system for dewatering a shaft in stratified materials.

One of the method to install deep wells is by the reverse-rotary drilling


method. A casing is being drive and jetted into the ground and a bailer or jet
or a bucket auger is used to clean it. In the reverse-rotary method, the hole

AP 226 / 1C | JULY – NOVEMBER 2009


for the well is made by rotary drilling. Soil from the drilling is removed from
the hole by the flow of water circulating from the ground surface down the
hole and back up the (hollow) drill stem from the bit.
Construction dewatering in fine soils can be difficult, because well
yields are often low and it is usually necessary to apply a vacuum to assist
drainage. Ejector systems are therefore ideally suited to groundwater control
in fine soils and have been used increasingly in the UK in recent years (W.
Powrie et al., 1994). A centrifugal or jet-eductor pump pumps the flow from
the drill stem into a sump pit to circulate the drill water. The soil particles
settle out in the sump pit and the muddy water flows back into the drill hole
through a ditch cut from the sump to the hole. The sides of the drill hole are
stabilized by seepage forces acting against a thin film of fine grained soil that
forms on the wall of the hole. Some silt soil may need to be added to the
drilling water to attain the desired degree of muddiness if the hole is drilled in
clean sands. The sump pit should be large enough to allow the sand to settle
out but small enough so that the silt is kept in suspension.
In order to install a straight and plumb screen and riser, the holes for
deep wells should be vertical and deeper than the well screen and riser. The
additional depth of the hole should be provided to put wasting filter material in
the tremie pipe if used. The filter is tremied in after the screen is in place. The
tremie pipe should be 4 to 5 inches in diameter, be perforated with slots 1/16
to 3/32 inch wide and about 6 inches long, and have flush screw joints. The
slots will allow the filter material to become saturated, thereby breaking the
surface tension and “bulking” of the filter in the tremie. The tremie pipe
should be filled with filter material after it has been lowered to the bottom of
the hole. It then slowly raised, keeping it full of filter material at all times, until
the filter material is 5 to 10 feet above the top of the screen.

After the filter is placed, the well should be developed to obtain the
maximum yield and efficiency of the well. The purpose of the development is
to remove any film of silt from the walls of the drilled hole and to develop the
filter immediately adjacent to the screen to permit an easy flow of water into

AP 226 / 1C | JULY – NOVEMBER 2009


the well. Development of a well should be accomplished as soon after the
hole has been drilled so that the efficiency assumed in well design will
maintain the same. A well may be developed by surge pumping or surging it
with a loosely fitting surge block diameter 1 to 2 inches smaller than the
inside diameter of the well screen and should be slightly flexible. The surge
block is raised and lowered through the well screen at a speed of about 2
feet per second.
The amount of material deposited in the bottom of the well should be
determined after each cycle (about 15 trips per cycle) and surging should
continue until the accumulation of material pulled through the well screen in
any one cycle becomes less than about 0.2 foot deep. If the accumulation of
material in the bottom of the screen becomes more than 1 to 2 feet at any
time during surging, it should be bailed clean and recleaned after surging is
completed.
The well should be pumped at approximately the design discharge
from 30 minutes to several hours to clear it of muddy water and sand after it
has been developed. Measurements of well discharge and drawdown may be
used to determine the efficiency and degree of development of the well. The
performance of the well filter may be evaluated by measuring the
accumulation of sand in the bottom of the well and in the discharge.
An airtight seal around the well riser pipe from the ground surface
down for a distance of 10 to 50 feet is required in which a vacuum is to be
maintained. The seal may be made with compacted clay, nonshrinking grout
or concrete, bentonitic mud, or a short length of surface casing capped at the
top. The seal is impossible to attain a sufficient vacuum in the system if
improper or careless placement. This will cause the dewatering system failing
to operate as designed. Besides, the top of the well must also be sealed
airtight. After the wells are developed and satisfactorily tested by pumping,
the pumps, power units, and discharge piping may be installed.

AP 226 / 1C | JULY – NOVEMBER 2009


4.3.3 Wellpoint Systems
Another commonly used dewatering method are wellpoint systems as they
are applicable to a wide range of excavations and groundwater conditions.
Wellpoint systems are installed by first laying the header at the location and
elevation called for by the plans. After the header pipe is laid, the stopcock
portion of the swing connection should be connected to the header on the
spacing called for by the design, and all fittings and plugs in the header made
airtight using a pipe joint compound to prevent leakage. Installation of the
wellpoints generally follows layout of the header pipe.

Figure 10 Plan of a typical wellpoint system.

Figure 11 A typical wellpoint system at site

AP 226 / 1C | JULY – NOVEMBER 2009


A wellpoint pump uses a combined vacuum and a centrifugal pump
connected to the header to produce a vacuum in the system and to pump out
the water that drains to the wellpoints. When additional air handling capacity
is required, one or more supplementary vacuum pumps may be added to the
main pumps. Generally, wellpoints connected to a header at a common
elevation capable of lowering the groundwater table about 15 feet. To lower
the groundwater more than 15 feet, A wellpoint system is usually the most
practical method for dewatering at accessible site, the excavation and water-
bearing strata to be drained are not too deep. It may be more practical to use
eductor-type wellpoints or deep wells with turbine or submersible pumps and
wellpoints as a supplementary method of dewatering for large or deep
excavations where the depth of excavation is more than 30 or 40 feet or
where artesian pressure in a deep aquifer must be reduced. Wellpoints are
more suitable than deep wells where the submergence available for the well
screens is small and close spacing is required to intercept seepage.
[ CITATION UTM06 \l 1033 ]

Figure 12 Use of wellpoints where submergence is small

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 13 Drainage of an open deep cut by means of a multistage wellpoint system.

Vacuum wellpoint systems are installed in the same manner as


ordinary wellpoint systems. It uses a jet casing and filter, except the upper 5
feet of the riser is sealed airtight to maintain the vacuum in the filter. A
vacuum wellpoint system is used to stabilized silts and sandy silts (D 10 <

0.05 milimetre) with a low coefficient of permeability (k = 0.1 x 10 -4 to 10 x

10-4 centimetres per second) where it cannot be drained successfully by


gravity methods. It is a conventional well system. The partial vacuum is
maintained in the sand filter around the wellpoint and riser pipe. This vacuum
will increase the hydraulic gradient producing flow to the wellpoints and will
improve drainage and stabilization of the surrounding soil. It may be
necessary to provide additional vacuum pumps if there is much air loss to
ensure maintaining the maximum vacuum in the filter column. The required
capacity of the water pump is small.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 14 Vacuum wellpoint system

Wellpoint pumps, are used to provide the vacuum and to remove water
flowing to the system. The suction intake of the pump should be set level with
the header pipe to obtain the maximum possible vacuum. Wellpoint pumps
should be protected from the weather by a shelter and from surface water or
sloughing slopes by ditches and dikes. The discharge pipe should be
watertight and supported independently of the pump.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 15 A wellpoint pump used in Sunway Pyramid II project.

AP 226 / 1C | JULY – NOVEMBER 2009


Self-jetting wellpoints are installed by jetting into the ground. Water is
forced out the tip of the wellpoint under high pressure. It can be installed in
medium and fine sand. The water pressures is about 50 pounds per square
inch. To carry out the heavier particles in the coarse sand and gravel, more
water and higher water pressures (about 125 pounds per square inch) are
required. A hydrant or a jetting pump of appropriate size for the pressures
and quantities of jetting water required can be used. The jetting hose which is
attached to the wellpoint riser is picked up either by a crane or hand and held
in a vertical position as the jet water is turned on. The diameter is usually 2 to
3 inches.

Figure 16 Self-jetting wellpoint.

The wellpoint is allowed to sink and raised slowly in the ground. This is
to ensure that all fine sand and dirt are washed out of the hole. Jet water
should be returned to the surface otherwise the point may “freeze” before it

AP 226 / 1C | JULY – NOVEMBER 2009


reaches grade. Therefore, care should be taken. If the return of jet water
disappears, the point should be quickly raised until circulation is restored and
then slowly relowered. It may be necessary to supplement the jet water with
a separate air supply at about 125 pounds per square inch to lift the gravel to
the surface in gravelly soils. Filter sand is required around the wellpoint to
increase its efficiency and prevent infiltration of foundation soils. In order to
form the hole for the wellpoint and filter, the wellpoints should be installed
using a hole puncher and a jet casing. The two halves of a swing connection,
if used, should be lined up for easy connection when the jet water is turned
off and the jetting hose disconnected.

Generally, a wellpoint should be installed in a hole formed by jetting


down a 10- to 12- inch heavy steel casing at where it is to be installed with a
filter. The casing may be fitted with a removable cap at the top. Air and water
may be introduced through and a return of air and water along the outside of
the casing when the casing is jetted into the ground. Jetting pressures of 125
pounds per square inch are commonly used. The casing may have to be
raised and dropped with a crane to chop through and penetrate to the
required depth when resistant strata are encountered. Most of the return
water from a ‘hole puncher” rises inside the casing causing less disturbance
of the adjacent foundation soils. The jet is allowed to run until the casing is
flushed clean with clear water after the casing is installed to a depth of 1 to 3
feet greater than the length of the assembled wellpoint.

Another type of dewatering system is the jet-eductor wellpoint system.


Jet-eductor wellpoints are usually installed using a hole puncher and
surrounding the wellpoint and riser pipe with filter sand. It is installed in the
same manner as conventional wellpoints with a filter as required by the
foundation soils. It consists of an eductor installed in a small diameter well or
a wellpoint screen attached to a jet-eductor installed at the end of double
riser pipes. A pressure pipe is used to supply the jet-eductor and another
pipe for the discharge from the eductor pump. Eductor wellpoints may also
be pumped with a pressure pipe within a larger return pipe. The advantage of

AP 226 / 1C | JULY – NOVEMBER 2009


this type of system compare to conventional wellpoint system is able to lower
the water table as much as 100 feet from the top of the excavation. Jet-
eductor wellpoint systems are most advantageously used to dewater deep
excavations where the volume of water to be pumped is relatively small
because of the low permeability of the aquifer.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 17 Jet-eductor wellpoint system for dewatering a shaft.

4.3.4 Vertical Sand Drains


Vertical drains accelerate the consolidation process by reducing the
drainage path and by reorienting the direction of flow into a more permeable
(horizontal) direction. The earliest version of vertical drains was sand drains
which consisted of a borehole filled with sand (Basu, D. et al., 2000). The
water table in the upper stratum can be lowered by means of sand drains
when a stratified semipervious stratum with a low vertical permeability
overlies a pervious stratum and the groundwater table has to be lowered in
both strata. Sand drains will intercept seepage in the upper stratum and
conduct it into the lower when properly designed and installed Sand drains
consist of a column of pervious sand placed in a cased hole. The cased hole
is either driven or drilled through the soil, with the casing subsequently
removed. Installation of a slotted 1% or 2 inch pipe inside the sand drain can
significantly increase the capacity of sand drains. This is to conduct the water
down to the more pervious stratum. The installation of mandrels into the soil
using a drain stitcher.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 18 Sand drains for dewatering a slope.

Figure 19 Installation of mandrels using drain stitcher.

4.3.5 Electro-Osmosis
When soils such as silts, clayey silts, and clayey silty sands cannot be
dewatered by pumping from wellpoints or wells, it can be drained by wells or
wellpoints combined with a flow of direct electric current through the soil
toward the wells. Creation of a hydraulic gradient by pumping from the wells
or wellpoints with the passage of direct electrical current through the soil
causes the water contained in the soil voids to migrate from the positive
electrode (anode) to the negative electrode (cathode). The water that
migrates to the cathode can be removed by either vacuum or eductor

AP 226 / 1C | JULY – NOVEMBER 2009


pumping by making the cathode a wellpoint. The installation of electro-
osmosis on a dewatering site.

Figure 20 Electro-osmosis wellpoint system for stabilizing an excavation slope.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 21 Installation of electro-osmosis in a dewatering site.

4.3.6 Cutoffs
In order to stop or minimize seepage into an excavation, cutoff
curtains can be used. Cutoff can be installed down to an impervious
formation. There are many methods to construct cutoff curtains. Such cutoffs
can be constructed by driving steel sheet piling, grouting existing soil with
cement or chemical grout, excavating by means of a slurry trench and
backfilling with a plastic mix of bentonite and soil, installing a concrete wall,
possibly consisting of overlapping shafts, or freezing. However, groundwater
within the area enclosed by a cutoff curtain, or leakage through or under such
a curtain will have to be pumped out with a well or wellpoint system.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 22 Grout curtain or cutoff trench around an excavation.

A cutoff around an excavation in coarse sand and gravel or porous


rock can be created by injecting cement or chemical grout into the voids of
the soil. The voids in the rock or soil must be large enough to accept the
grout for grouting to be effective. Besides, the holes must be close enough
together so that a continuous grout curtain is obtained. Pervious soil or rock
formations are grouted from the top of the formation downward through pipes
installed in the soil or rock. The hole for the grout pipe is first cored or drilled
down to the first depth to be grouted, the grout pipe and packer set, and the
first zone grouted. The hole is redrilled after the grout is set for the second
stage of grouting. This process is repeated until the entire depth of the
formation has been grouted. The type of grout that can be used varies. It
depends on the size of voids in the sand and gravel or rock to be grouted.
The commonly used grouts are portland cement and water, cement,
bentonite, an admixture to reduce surface tension, and water, silica gels, or a
commercial product. Grouting of fine or medium sand is not very effective for
blocking seepage.

Mixing tanks and pump equipment for pressure injection of cement or


chemical grouts vary depending upon the materials being handled.
Ingredients for a grout mix are loaded into a mixing tank equipped with an
agitator. Then, grout are pumped to a storage tank which also equipped with
an agitator. Pumps for grouting with cement are generally duplex, positive

AP 226 / 1C | JULY – NOVEMBER 2009


displacement, reciprocating pumps similar to slush pumps used in oil fields.
Cement grouts are highly abrasive. So the cylinder liners and valves should
be of case-hardened steel. Chemical grouts can be pumped with any type of
pump that produces a satisfactory pressure because of their low viscosity
and nonabrasive nature. There are two types of distribution system for
grouting which are the single-line system and the recirculating system. The
line must occasionally be flushed to ensure that the grout being pumped into
the formation is homogeneous and has the correct viscosity. The grout in a
single-line system is flushed through a blowoff valve onto the ground surface
and wasted. A recirculating system has a return line to the grout storage tank
so that the grout is constantly being circulated through the supply line, with a
tap off to the injection pipe where desired.

Slurry wall is one of cutoff method to prevent or minimize seepage into


an excavation. It can be formed by digging a narrow trench around the area
to be excavated and backfilling it with an impervious soil. Slurry cutoff
trenches can be dug with a trenching machine, backhoe, dragline, or a clam
bucket, typically 2 to 5 feet wide. Such a trench can be constructed in almost
any soil. It can be constructed either above or below the water table.
Generally, the trench is backfilled with a well-graded clayey sand gravel
mixed with bentonite slurry. Thick bentonitic slurry as shown in figure 2.23 is
used to stabilize the walls of the trench until the trench can be backfilled. It is
best mixed at a central plant and delivered to the trench in trucks or pumped
from slurry ponds. [ CITATION UTM06 \l 1033 ]

Cleaning of the slurry is commenced in order to remove gravelly or


sandy soil particles that have collected in the slurry, especially near the
bottom of the trench. Fair cleanup can be obtained using a clamshell bucket.
More thorough cleaning can be obtained by airlifting the slurry to the surface
for circulation through desanding units. Cleaning of the slurry makes it less
viscous and ensures that the slurry will be displaced by the soilbentonite
backfill. After cleaning the “in-trench” slurry, the trench is generally backfilled
with a well-graded mix of sand-clay-gravel and bentonite slurry with a slump

AP 226 / 1C | JULY – NOVEMBER 2009


of about 4 to 6 inches. The backfill material and slurry may be mixed either
along and adjacent to the trench or in a central mixing plant and delivered to
the trench in trucks.

Figure 23 Detail of slurry trench.

The other cutoff method is by constructing concrete walls. Concrete


cutoff walls can be constructed by overlapping cylinders and also as
continuous walls excavated and concreted in sections. These walls can be
reinforced and are sometimes incorporated as a permanent part of a
structure.

Steel sheet piling is a very effective method to reduce seepage. The


effectiveness of steel sheet piling depends on the perviousness of the soil,
the tightness of the interlocks and the length of the seepage path. Some
seepage through the interlocks should be expected. Precautions should be
taken in handling and driving sheet piling to ensure that the interlocks are
tight for the full depth of the piling and that all of the sheets are driven into the
underlying impermeable stratum at all locations along the sheet pile cutoff.

AP 226 / 1C | JULY – NOVEMBER 2009


Driving steel sheet piling around the structure, excavate the soil underwater,
and then tremie in a concrete seal is desirable when constructing small
structures in open water. The concrete tremie seal must withstand uplift
pressures. In restricted areas, it may be necessary to use a combination of
sheeting and bracing with wells or wellpoints. Wells or wellpoints can be
installed inside or outside of the sheeting. Sheet piling is not very effective in
blocking seepage where boulders or other hard obstructions may be
encountered because of driving out of interlock. The sheet piling used in
Sunway Pyramid II project in blocking seepage and stabilizing the slope.

Figure 24 Steel sheeting to top of rock. A boulder above the rock can aggravate the situation.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 25 Steel sheeting in Sunway Pyramid II project to control seepage and stabilizing the slope.

Seepage into an excavation or shaft can be prevented by freezing the


surrounding soil. However, freezing is expensive and requires expert design,
installation, and operation. If the soil around the excavation is not completely
frozen, seepage can cause rapid enlargement of a fault (unfrozen zone) with
consequent serious trouble, which is difficult to remedy. Freezing the soil
around a shaft or tunnel requires the installation of pipes into the soil and
circulating chilled brine through them. These pipes generally consist of a 2-
inch inflow pipe placed in a 6-inch closed-end “freezing” pipe installed in the
ground by any convenient drilling means. Two headers are required for a
freezing installation. One is to carry chilled brine from the refrigeration plant
and the other to carry the return flow of refrigerant. The refrigeration plant
should be of adequate capacity and should include standby or auxiliary
equipment to maintain a continuous operation. An excavation supported by
freeze wall, a typical scenario of freeze pipe spacing, plan and section view
of circular excavation by a freeze wall and a deep excavation supported by
freeze wall.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 26 Excavation supported by a gravity freezewall.

Figure 27 Typical scenario of freeze pipe spacing and indication which can be connected to a portable
refrigeration plant, or liquid nitrogen tanker.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 28 Circular excavation supported by a freezewall. (a) Plan. (b) Section.

Figure 29 A deep excavation supported by freeze wall.

AP 226 / 1C | JULY – NOVEMBER 2009


4.4 CONSTRUCTION PROCEDURES

4.4.1 SPECIFICATIONS
Before any earthworks are commenced, areas of cut and fill should be clearly
defined. Where necessary, sufficient fencing or barriers should be provided
around trees or other features to be protected. All site activities including
clearing, storage, cutting and filling should be kept away from the root zone
of trees (best defined as the extent of the canopy). Adequate provision
should also be made for the control of erosion, surface water run-off and
siltation. [ CITATION Gar07 \l 1033 ]

The normal necessary specifications are to be prepared to control the


earthwork construction as follows:
i. All rubbish, vegetation and debris should be removed from earthworks
areas prior to the commencement of topsoil stripping. Areas on which
fill is to be placed, or from which cut is to be removed, and haul roads
should be stripped of all topsoil and such unsuitable soft or organic
material as determined by the soils engineer. Special care should be
taken to ensure that organic materials and areas of old uncompacted
filling are not overlooked through being overlaid by other soils.
ii. Stripping should be carried out as a specific operation with areas
being stripped in large enough increments to ensure that there is an
adequate margin of stripped ground beyond any current cutting or
filling operation. Particular care should be taken to ensure that
overspill is not left in an uncompacted state anywhere on the site,
when constructing temporary haul roads.
iii. All stripped material should be deposited in temporary stockpiles or
permanent dumps, in locations where there is no possibility of the
material being unintentionally covered by, or incorporated into,
structural fills.

AP 226 / 1C | JULY – NOVEMBER 2009


iv. Where a fill abuts against sloping ground, benches should be cut into
the ground to prevent the development of a continuous surface of low
shear strength.
v. Previous drains or similar subsoil seepage control systems should be
installed (as necessary) to lead seepage away from all springs and
potential areas of ground water under or adjacent to fills in order to
a) Prevent saturation of the fill before construction of the fill is
complete;
b) Prevent internal ground water pressures which would
detrimentally reduce shear strengths.
vi. Subsoil drains should discharge via flexible jointed pipes to an outlet
approved by the Engineer, preferably a stable watercourse or a piped
storm-water system. The position of all subsoil drains should be
recorded on the "as-built' plan.
vii. The stripped ground surface should be prepared and then inspected
by the soils engineer before any fill is placed thereon.

4.4.2 FILL CONSTRUCTION


The quality of fill material and required control testing should be determined
and specified before the placing of fill commences. Fill should be placed in a
systematic and uniform manner with near horizontal layers of uniform
thickness (less than 225mm) of material being deposited and compacted
progressively across the fill area.

Before any loose layer of fill is compacted, the water content should be
suitable for the compaction required and as uniform as possible. Any
compacted layer which has deteriorated after an interruption in the
earthmoving operation, should be rectified before further material is placed
over it.

AP 226 / 1C | JULY – NOVEMBER 2009


Fill batter faces should be compacted as a separate operation, or
alternatively, overfilled and cut back.

Where testing shows the compaction achieved in the field to be below the
specified minimum, all material represented by the test should be further
compacted or removed as necessary.
Temporary Drainage and Erosion Control

During the construction period, measures should be taken to prevent


excessive water-logging of surface materials yet to be excavated or
compacted or both, and to prevent fill material from being eroded and
redeposited at lower levels. Such measures should include:
i. The surfaces of fills and cuts should be graded to prevent ponding.
ii. Temporary drains should be constructed at the toe of steep slopes to
intercept surface run-off and to lead drainage away to a suitable
watercourse or pipe storm-water system.
iii. Surface water should be prevented from discharging over batter faces
by drains formed to intercept surface run-off and discharge via stable
channels or pipes, preferably into stable watercourses or piped storm-
water systems.
iv. The upper surface of fills should be compacted with rubber tyres or
smooth wheeled plant when rain is impending, or when the site is to
be left unattended.
v. The completed battered surfaces of fills should be compacted with
sheepsfoot or similar non-smooth compaction plant to reduce runoff
velocities.
vi. Silt traps and retention ponds should be constructed where they are
feasible and necessary. These should be cleaned out, as required to
ensure that adequate silt storage is maintained.
vii. Temporary barriers or fences choked with brush, sacking or the
like,should be used to reduce flow velocities and to trap silt.

AP 226 / 1C | JULY – NOVEMBER 2009


viii. Section of natural ground should be left unstripped to act as grass (or
other vegetation) filters for run-off from adjacent areas.
ix. All earthwork areas should be retopsoiled and grassed or
hydroseeded as soon as possible after completion of the earthworks
and drainage works.

4.4.3 INSPECTION AND QUALITY CONTROL


The soils engineer should provide an adequate level of inspection and
testing, in order to enable him to evaluate properly the general quality of the
finished work, and to enable him to furnish a report as to the compliance of
the work with the specifications. This is not to be construed as a guarantee or
warranty but rather a record of his professional opinion based on reasonable
care.

Visual inspection should be made by the soils engineer or a competent


inspector acting on his behalf at the following times:
i. After any part of the existing ground has been finally stripped and
prepared and before the placing of any fill on that ground.
ii. After any drain has been installed and before the drain is covered by
fill.
iii. At such other times as the soils engineer considers necessary to
enable him to assess the general standard of earthworks and to
reasonably satisfy himself that;
a) Fill is not placed over soft or organic material;
b) All areas of existing ground showing seepage or potential
seepage emission have relief drains provided;
c) Compaction operations are systematic, the water content of fill
material appears on visual inspection to be suitable and the
degree of compaction appears to be consistently satisfactory.

AP 226 / 1C | JULY – NOVEMBER 2009


During the construction of earth fills some or the entire following quantitative
control test should be made on the fill material:
i. Tests to determine whether the water content is suitable;
ii. In situ density tests to determine whether the degree of compaction is
up to the specified minimum;
iii. Where appropriate tests to determine the maximum dry density for the
soil tested in each in situ field density test;
iv. Such other tests as may be specified by the soils engineer for control
testing of fills or particular soil types, providing that the soil property
tested shall be related to in situ density or water content of the fill by a
laboratory investigation. Such tests include shear strength tests, cone
penetrometer tests, and other Proctor needle tests.

Once the filling work is progressing as a steady operation with uniform


construction methods, and provided that:-
i. Adequate construction effort is being maintained;
ii. Adequate visual inspection is being maintained;
iii. The specification requirements are being met.

Then minimum frequency of control testing shall generally be one in site


density test (or equivalent) for each 2000m3 or 1.0m lift of fill. Testing shall
be more frequent than specified above, under any of the following
circumstances:
i. During the first 4000m3 of filling carried out on the project.
ii. On the final layer of not less than 1.0m depth.
iii. When soil type or conditions are variable.
iv. When the soils engineer or his inspector is in any doubt about the
adequacy of construction methods or soil properties.
v. When a decision to reject work based on the judgement of the soils
engineer or his inspector is disputed, and;
vi. When relatively small quantities of fill are concentrated in localized
areas or placed discontinuously over a long period of time.
AP 226 / 1C | JULY – NOVEMBER 2009
The locations of tests should be decided by the soils engineer or his
inspector, who should select them so as to test material likely to be furthest
from the specified quality. In addition, a proportion of tests should be taken at
random locations to check the average standard being obtained.

All field and laboratory test data should be recorded in a systematic manner
that will allow the results to be identified and allow the calculations to be
checked at a later date, if necessary. All control test results should have
recorded the time, date, location and elevation. Test results relating to
sections of fill that have been subsequently removed or reworked and
recompacted should be noted accordingly.

4.5 CASE STUDY

4.5.1 SLOPE STABILIZATION/ SLOPE PROTECTION

For these conditions, stabilization may be achieved by retaining wall, soil


nails, anchors or reticulated mini-piles. Other methods of the stabilization
include drainage and embedded gravity, gabion or crib walls. An excellent
account of the various methods available for slope stabilization. Types of
method to be use for slope protection is:-

4.5.1.1 CONTIGUOUS SPUN PILE


A certain exposed slope to be contiguous spun pile immediately to control
soil erosion during excavation works. The CSP for slope protection to be use
after 6 meters excavation from original level, the original level is 21 meter.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 30 CSP at the SOHO Project.

The method of excavation work step by step, where the contractor made a
few of the slope. This method use because it more effective for site area to
control soil erosion. And then after 6 meter excavated and disposed of the
soil, the contractors use the contiguous spun pile for slope protection. The
contiguous spun pile buried into the soil, the figure show how the contiguous
spun pile to be buried at the third level.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 31 Re-bar of CSP.

And then the reinforcement bar and concrete work started after all contiguous
spun pile buried into the soil. The gaps between the CSP will closed using
the mortar because to ensure the erosion does not happen and disturb the
working area soon. So, the contractor ensures the retaining wall strong and
safety following the standard in the contract.

Using the grout


cement

Figure 32 CSP side use Mortar.

AP 226 / 1C | JULY – NOVEMBER 2009


The figure shows the using use to fill the gaps between the contiguous spun
piles. It’s important to control erosion and for slope protection.

Figure 33 Layout of CSP.

4.5.1.2 CANVAS METHOD


The contractor also use the canvas method for slope protection, its mean that
the rain water does not give effected for the soil properties and the strength
of the soil. Its can prevent from the erosion, and also as an additional method
for slope protection. The canvas lay at each slope; the reason is to ensure
the rain water only flow on the canvas. The figure below show how the
canvas lay by the slope.

Figure 34 Canvas Method

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 35 Canvas to the Slope

4.5.1.3 RETAINING WALL


Third method for slope protection is retaining wall. The area of retaining wall
constructed is beside the railway KTM, to separate between disposal area
and railway KTM. This method as a slope protection to ensure the erosion
does not happen. The construction for retaining wall is important and
following the standard specification from CIDB. The retaining wall is use the
precast and in-situ method of construction where the materials make at the
factory and then bring to the site and fixed. After that, the construction
continues by the in-situ method until fixed level. These figures show the
construction of retaining wall using the precast and in-situ method.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 36 Retaining Wall.

4.5.2 DEWATERING SYSTEM

4.5.2.1 USE THE SUMP PUMPING SYSTEM


The rain water will damage the soil properties, so the strength of the
soil will decrease and settlement will be happen. To protect the
strength of the soil, the water must be flow out from the site area. In
this case, the pumping system is use to flow out the water from the
construction site. Where the water in the site will remove by the water
pump and flowing into the temporary drainage. The temporary
drainage located outside of site area where it located beside the
railway KTM.

The method how the water removed by using the pumping system:-

AP 226 / 1C | JULY – NOVEMBER 2009


a) The water at the foundation will remove by the water pump.

Figure 37 Water Pump.

b) The water flowing through the pipe to temporary sump.

Figure 38 Water Flow.

c) And then, from the temporary hole the water will flow through the
circle culvert with diameter 2 feet.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 39 Ponding at site.

d) The water flow to the temporary drainage before flow to the large
drainage.

Figure 40 Temporary drainage.

Using the pumping system is effective dewatering system in the


construction site because it easy to set up the system. During
earthwork, this system helps to remove the water in the site. The
water pump had maintained to make sure the project not delay
because of the water. Its also depend on the size of project and
condition of the site. The other method of dewatering system is

AP 226 / 1C | JULY – NOVEMBER 2009


well point system, sump pump system, deep-well system, vertical
sand drain and electro-osmosis.

4.5.2.2 TEMPORARY DRAINAGE.


The temporary drainage located near the railway (KTM) where at the
out off construction site. The perimeter of the drainage is half
construction site; it’s around 500 m until main drainage. During the
construction period, measures had take to prevent excessive water
logging of surface materials yet to be excavated or compacted or both,
and to prevent fill material from being eroded and redeposited at lower
levels. Temporary drains should be constructed at the toe of steep
slopes to intercept surface run-off and to lead drainage away to a
stable watercourse. For monitoring, ensure that the Developer/
Contractor maintain the temporary drain regularly (each one week). It
important to make sure drainage will flowing the water smooth such as
dispose any material and rubbish inside. All earthwork areas should
be retopsoiled and grassed or hydroseeded as soon aspossible after
completion of the earthworks and drainage works.

Figure 41 Temporary drainage.

AP 226 / 1C | JULY – NOVEMBER 2009


4.5.3 TRAFFIC CONTROL
Traffic control is important to make sure the site access smooth and must
logistic. The machineries can move to other position using the access road.
For examples, the tipper lorry can bring the soil from excavation area to the
disposal area without obstructions. This site area provided two ways for
access road is access and exit road. In site area has two ways (to excavation
area and to the disposal area). So, any machinery can move clearly to bring
the soil or other material and also make earthwork smoothly.

Figure 42 Access route.

AP 226 / 1C | JULY – NOVEMBER 2009


The figures show the access road for the lorry or vehicles access the site
area and exit road. It effective traffic control to make sure no obstruction
during move the soil and other material.

Figure 43 Barier gate.

The access road and exit road is logistic, that means easy to going and goes
out after finish work and also easy to see by the people and parties involve
also.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 44 Wash Pit

Figure 45 Housekeeping.

So, the contractor must make sure the access road in good condition always.
That means, the access road must clean always and remove any material
have on the road such as soil and other materials. The figure shows two
worker cleaning the wash pit area and access road.

AP 226 / 1C | JULY – NOVEMBER 2009


4.5.4 SAFETY CONTROL
The safety control is very important to make sure no accident will be happen
and also trespassers. The contractor had provided a few of the safety control
in this site area such as hoarding, wash pit or wash through, barrier and
signboard.

4.5.4.1 HOARDING
Hoarding fixed at surrounding area of construction site, the high for
hoarding is 3 meters. It important and must provide at any construction
site following the CIDB standard because its can protect from the
trespassers, illegal and as the site boundary. For this site, hoarding
also likes a separator between construction site area and railway
KTM.

Figure 46 Hoarding.

4.5.4.2 WASH PIT / WASH THROUGH


Wash pit located at the exit road behind the public road. Areas of
wash pit makes from steel, concrete and have the hole for trap the
water. There are using the manual operation where the workers used
the water pipe to clean the machineries or vehicles. The main function
for wash pit is to ensure that vehicles leaving the site are clean and
does not dirty the public road.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 47 Wash pit.

4.5.4.3 GATE BARRIER


The barrier will be open at the working hours and will be close after
working hour. Usually it’s open from 8.00 am until 5.00 pm., using the
manual system.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 48 Gate Barier.

4.5.4.4 PROJECT SIGNBOARD


The signboard is reference or announcement for peoples about the
project. All construction sites must have the signboard; it usually
located at front site area or at some location where people can see.
The information at the project signboard is title of the project, duration
of the project and also the parties involve in the project.

AP 226 / 1C | JULY – NOVEMBER 2009


Figure 49 Project signage.

4.5.4.5 SAFETY EQUIPMENT


Contractor has to make sure their workers should wearing the safety
equipments such as safety boot safety helmet and etc... The
equipment is very important especially for workers and parties involve
also when enter the construction site. Contractor should provide
precautions of unexpected events. Contractor should provide the good
working space for their workers to work in a good condition. The good
working area can increase the workers productivity and indirectly
provide the good quality of work.

4.5.5 SETTLEMENT CONTROL


Many type of how to control the settlement at the site, such as leveling
method or surface leveling station. Such stations should be positioned as
soon as an area of fill has been brought up to finished level. This will mean
that the maximum time will be available for settlement readings, noting that,
for obvious reasons, none can be made using this form of equipment during

AP 226 / 1C | JULY – NOVEMBER 2009


fill placement itself. Because of the heavy plant frequenting construction
sites, a surfacing leveling station should be robust.

Figure 50 Point of sttlement control.

Figure 51 Settlement Marker Records.

AP 226 / 1C | JULY – NOVEMBER 2009


The settlement Marker Record are needed during the measured the level that
had been decided to control. If the level are falling down, the settlement are
occur and must create a solution to settle the problems.

4.5.6 DOCUMENTATION CONTROL

4.5.6.1 STATEMENT OF QUALITY POLICY AND AUTHORITY

It is SENDI BANGGA DEVELOPMENT SDN. BHD. (SBD) objective to


supply client with materials and services to the highest possible quality level
consistent with the requirements of our Client job specification. SBD
recognize the importance of maintaining a high quality system in order to
assure the safety to the general public.

The Quality Assurance Plan defines philosophy, policies and applicability of


our Quality Assurance Program and describes SBD’s organization,
procurement and construction. The quality control specifications and
procedures which are referred to in this Quality Assurance Plan provide
instructions for the implementation of the Quality Assurance Program.
Compliance to this Quality Assurance Plan and referenced specifications and
procedures is mandatory and shall consistently applied within SBD.

4.5.6.2 QUALITY CONTROL PROCEDURE

PURPOSE

All documents and data are reviewed, approved and controlled to ensure that.
The correct revision of appropriate documents are available at the point of work.
Obsolete documents are promptly removed from all points of issue or use.

AP 226 / 1C | JULY – NOVEMBER 2009


APPLICATION

The following types of documents shall be controlled :

1. Project Quality Procedures / Method Statement


2. Quality Assurance Quality Control
3. Specifications / Standards / Method Statement
4. Operation documents including drawings, design calculation etc.

4.5.6.3 PROCEDURE

Control of Document Issue

1. All controlled documents shall, be reviewed and approved for


adequacy by authorized person prior to issue. They shall have their
issue number, date and signature or initials of authorized person entered
on them.
2. All documents shall be controlled by the department that issues the
document and shall be protected against damage and misuse.
3. It shall be the responsibility of the manager of the department that
issue the documents carry the necessary authorizing signatures and
dates of issue and distributed to the points of use throughout the
company.

Control of Document Use

1. It shall be the responsibility of the supervisor or manager of each work


area to ensure that the correct documents and correct revisions of such
documents are the ones in use in that area at all times.

AP 226 / 1C | JULY – NOVEMBER 2009


2. At no time shall the supervisor or manager permit wrongful marking,
use or other action would be defeat the intent of document control.
3. At all times the documents shall be readily available to Client needing
access to their contents.

Control of Document Change

1. Each change in a controlled document shall be initiated / signed and


dated by the authorized person making change.
2. The document carrying changes shall be subject permanent revision
and reissue at the earliest practicable time.
3. Documents shall be directly identified with their revision level using
consecutive numbering.
4. Where practicable, the nature of the change shall be identified in
document by placing description of the change in Revision History Sheet.
Only Cover page and Revision History Sheet shall be transmitted to
the concerned personnel using transmittal form.
5. Changes to the documents shall be reviewed and approved by the
same department that performed the original review and approval unless
specifically designated otherwise.
6. The review and reissue of the documents shall be reviewed by and
shall receive approval of the department manager. .
7. It shall be the responsibility of the managers and supervisors who are
responsible for performing work affected by the reissued or revised
documents to remove and destroy all obsolete documents from all
points of use upon receiving the revised or reissued documents.
8. Any obsolete documents retained for legal and/or knowledge
preservation purposes shall be stamped "Void - For Information Only"
and kept separate from current documents to preclude unintended use.
9. It shall be the responsibility of the department that issue, reissue or
revise the documents:

AP 226 / 1C | JULY – NOVEMBER 2009


a) to distribute documents to their destinations
b) to maintain distribution / master list

10. To notify immediately the Quality Assurance Department and forward


copy of the document to the Quality Assurance Department.
11. Documents issued to personnel and outside company who need a
copy for information only shall be stamped "Uncontrolled".

RETENTION OF DOCUMENTATION

1. It shall be the responsibility of the supervisor or manager at each work


area to maintain and retain all documentation in accordance with legal
and contractual requirements in retrievable and secure manner.
2. The company departments shall establish and maintain active files for
documents. The company departments shall retain all documents in
active files for a minimum of two years and for as long as they deem
necessary.
3. Unless, otherwise specified, all documents shall be removed from the
active files at the end of two years, indexed and stored in bonded area for
a minimum five years and as long as necessary. While in storage all
documents shall be protected from damage, loss and deterioration.

AP 226 / 1C | JULY – NOVEMBER 2009


5 CONCLUSION

For the conclusion, earthworks sites are amongst the most dangerous
because of the variety of work being conducted and because of the speed at
which some earth moving plant can operate. However, nothing can be built
without some excavation and some transfer soil (or rock) from a one part of a
side to another. That’s why; a proper planning and controlling of earthwork
must have to any contractors.

Danger includes:

a) Failing objects from overhead plant and during demolition of existing


structures
b) Collapse of excavations during site clearance
c) Damage to public utilities such as electricity and gas
d) Blasting operations
e) Heavy plant left at the edges of embankments or at part-completed
retaining wall
f) Heavy earth moving plant on haul roads and elsewhe
g) Reversing plant all over the site

Staffs on site are particularly at risk from earth moving and compaction plant.
They should be protected by warning lights and barriers. Haul surface should
be well maintained because this improves breaking distance; watering during
dry weather helps to reduce the nuisance. Plant should be restricted to
travelling parallel t the dip of the slope, wherever possible.

AP 226 / 1C | JULY – NOVEMBER 2009


6 BIBLIOGRAPHY
Burch, D. (2007). Estimating Excavation. Carlsbad: Craftsman Book Company.

Institution, B. S. (2003). Earthworks. Park Street, London: British Standard House.

John, G. (2007). Earthworks. Waikato District Council.

UTM. (2006). GROUNDWATER CONTROL IN THE CONSTRUCTION OF BUILDING. BA. Civil


Engineering.

AP 226 / 1C | JULY – NOVEMBER 2009

You might also like