Annex 01

Defect photographs of Construction of Primary Learning Resource Center Cathedral Boys School
Colombo 13.

Figure No 1

No stools or concrete blocks used to separate Top and Bottom R/F layers

700mms instead of 1020mm

Figure No 2 – Insufficient lap length

i
Annex 01
Defect photographs of Construction of Primary Learning Resource Center Cathedral Boys School
Colombo 13.

Figure No 3 – Insufficient Clear cover to the main R/F

Figure No 4

Clear cover to main R/F more than the specified level

ii
Annex 01
Defect photographs of Construction of Primary Learning Resource Center Cathedral Boys School
Colombo 13.

Figure No 5

Curtail of main R/F without anchoring to the column

Figure No 6 - Insufficient Crank length

iii
Annex 01
Defect photographs of Construction of Primary Learning Resource Center Cathedral Boys School
Colombo 13.

600mm

Figure No 7

Distance between plywood support timber joist is about 600mm

Figure No 8

Insufficient beam and column side locking system

iv
Annex 01
Defect photographs of Construction of Primary Learning Resource Center Cathedral Boys School
Colombo 13.

Figure No 9

Acro Jacks supported directly to beam bottom without GI pipe or timber joist

Figure No 10

Beam depth is 25mm higher than the specified depth