1. Plant Maintenance Overview
Ensuring a high availability of objects in the long term is an important role of Plant Maintenance. SAP
ERP will provide a complete Plant Maintenance solution for ARASCO, with SAP ERP PM Module.
Planned maintenance is used to avoid system breakdowns or the breakdown of other objects, which
- in addition to the repair costs - often result in much higher costs subsequently owing to production
breakdown.
1.1.1 Purpose
We have explained how to create, change and display Notification. There are two methods of
creating a maintenance order: from maintenance notification or to create an order directly without
a notification.
1.1.2 Prerequisites
Notification & Order Type must be defined. Work Centers must be created.
1.1.3 Trigger
Perform this procedure when there is need to create maintenance Notification / order.
4
1.1.4 Procedure
Access the transaction using
5
In the initial screen of create Notification; user has to define the relevant Notification Type (Click
button or select from popup menu available on pressing F4). The notification No. field will be
left blank.
6
The System Status field shows the current status of notification like OSNO (Outstanding
Notification), NOPR (Notification in process), NOCO (Notification Completed), etc. Details of the
status can be seen by pressing the small blue button on the right side of the status field.
Enter the brief description of the fault in the description field. If the equipment number is not
known, the user can search the equipment by single clicking the equipment field and pressing F4 for
searching. The following screen appears.
7
Select any criteria from the following screen to limit the search and press Execute or F8
8
Select the Equipment from the following screen and Enter
By selecting the required equipment from the above shown list, the equipment No. comes in its
field. By pressing enter the warranty information about the equipment will appear in a popup
window
9
10
Once press enter at the warranty information screen, Following screen will show the previous
history of the object/equipment about orders & notifications, Enter for next screen
11
After Equipment, There are some more fields (As per requirement) i.e. Notification Description,Work
Center and planner group which needs to be filled for better reporting and for execution of Work
Flow.
12
Field name Description User action and values
This tab is mainly used for providing the Warranty & Partner Information. The warranty start and
end date will be calculated by the system based on the master data.
13
This tab is mainly used for providing the Malfunction / Breakdown durations. The start date and time
comes as default and user can change it and enter end date and time. If this is a case of breakdown,
user should tick breakdown check box and the breakdown duration is automatically calculated by
the system.
14
In this tab user can see the master data attached with the specific equipment/ Functional location
and can change it if required like cost center or asset code etc.
15
In this tab user can see the all the relevent dates regarding the notification. Also user can see the
persons invloved in the notification e.g. Reported By, Tech Inspection By
1.1.5 Result
16
1.2 Change Maintenance Notification
Access the transaction using
17
By entering the notification Number in the ‘Change Notification Screen’, user goes into the
Notification for any required changes. If Notification Number is not known, user can press F4 or click
the icon
18
Select the Notification status with other search criteria like Notification type “R1” to limit the search
in the following screen
19
Enter when following screen appears
20
Select to put notification in process
21
After the above activity the Notification Status will be changed from OSNO to NOPR (out standing
notification to Notification in process)
22
1.3 Create Maintenance Order
This case is used for where the user does not create a notification before an Order.
23
In the initial screen user has to enter relevant order Type, Planning Plant and Equipment No. may be
entered in the initial screen directly or through search (by pressing F4). This information may also be
entered later in the Header Tab.
Order Type Order Type Different Order types are available in the system.
User to select relevant according to department
Planning Plant Planning Plant E.g. 1202, 1201, 1101, 1102, 1103, 1104, 1105
Order Order The number of the order you want to use as a
copy model for the current order.
24
Order can also be created from previously created notification
25
This can be done from Change Notification transaction; click on the icon on the right side of Order
field.
By clicking on “Create Order” icon, a window appears which mentions the Order Type, however
user can change the order type according to situation. Other data is taken from the Notification
which user created.
26
If user comes in Order Creation directly (by Transaction code IW31), he has to enter the Order
description, Planner Group, Maintenance Work Center, Equipment (if not entered in Initial Screen).
In case of order creation from Notification, this data is taken automatically by the system from the
Notification. The Order No. assigned is a temporary number. A final No. is assigned by the system
when Order is saved.
27
Field name Description User action and values
28
Write down the operation, which have to be performed
Write down the number of persons who will perform the job.
29
To add an external operation, user has to first input the relevant Control Key (eg. PM03). Then user
has to input the brief text of that operation (Up to 40 characters; for more text, long text option can
be used), and press “Enter”.
30
Press Enter at the previous screen and enter Material group in the following screenand press
“Enter”.
31
Select the external service operation and click on Button.
32
After this, Enter the services required in the service tab. Put the required entries like short text,
quantity, Unit and gross price and then press Enter
Click on the button at top. The components tab shows the components and their
details with required quantity for that particular maintenance task.
33
Enter the material number and quantity
Enter the Operation number for which material is required from the operation list button.
34
In case of goods return, select the same material or another with –ive quantity e.g. 1- and enter the
batch in which it is returned to store e.g. “DAMAGED”. As shown in following screen
35
Costs tab is used to determine the overall costs of the Maintenance Work Order. Press calculator
Button to determine the costs.
36
In the Object tab user can enter if he is working on more than one notification or equipment in one
order
This tab is for also viewing only. All data entered comes from previous windows. User will not enter
any information in this screen.
37
The location tab is for viewing purpose only. It shows all data previously entered. The cost centre
shown is the cost centre of the equipment entered at the time of equipment creation. User only
need to enter cost center in this tab if it is not already maintained.
38
1.4 Release of Order
Click on the green flag icon in the extreme left to release the maintenance order. After releasing the
order the material can be issued and operation can be confirmed. The system status is before releasing CRTD
(Created) as mentioned below;
After releasing the Order, The status REL (Released) appears in the status bar.
39
Click on Save Button to save Maintenance Order and Notification. The order and notification
number can be viewed at the left bottom of the screen.
40
1.5 Change Maintenance Order
Access the transaction using following path then select the order number with the same searching
process as define in notification
41
Search the order number and to search out press F4 or click
42
In the following screen, give the search criteria to limit the search like date
43
Press Enter
Note: Purchase requisition will be generated automatically oce the order is saved and it can be
viewed as shown in below screen in operation tab click button.
44
Maintenance order will be opened in Change mode make necessary changes and save the order
45
1.6 Display Maintenance Order
Access the transaction using following path
46
Search the order number and to search out press F4 or click
47
In the following screen, give the search criteria to limit the search like date
48
Press Enter
49
Order will be opened in display mode
50
1.7 Operation Confirmation
Access the transaction using following path
51
Select the order number by searching process as described above and press Enter
Double click the operation number which is to be confirmed or select operation and click
52
Put the confirmation data like Personnel number (who has done the operation and this person
should be attached with work center) Actual work, remaining work, Actual duration and other
information and click Final confirmation (Operation is completed) No remaining work, and clear
open reservation (material has been consumed if any against this operation) and click save.
53
Operation 10 has been confirmed and message can be seen at the left bottom of the screen
Through Order change transaction IW32 and entering Order number: In the Status of Order, PCNF
(Partially confirmed) is shown which means Order has some other operations which are yet to be
confirmed
54
Go again to Transaction code IW41 to confirm the remaining operations.After confirmation of all
operations go to transaction code IW32 (change order) the system status has been changed as CNF
(Confirmed all operations) as shown in the following screen
Click to complete the order. The following screen will be appeared in which check the date and
time of completeion of order and under the Notification put the start and end time of the
malfunction under malfunction data