CRONOGRAMA VALORIZADO DE GASTOS DE LA ACTIVIDAD


Actividad MANTENIMIENTO DE CAMINOS PEATONALES DE ANEXO SACUAYA, DISTRITO DE CUCHUMBAYA -PROVINCIA
MARISCAL NIETO - MOQUEGUA

Lugar MOQUEGUA - MARISCAL NIETO - CUCHUMBAYA

Item Descripción Und. Metrado Precio S/. Parcial S/. Mes 01 Mes 02 Total
60dias
01 OBRAS PROVISIONALES 1,995.52 1,995.52 1,995.52
01.01 CARTEL DE IDENTIFICACION DE LA OBRA 3.60x2.40 und 1.00 481.52 481.52 481.52 0.00 481.52
01.02 ALMACEN OFICINA Y CASETA DE GUARDIANIA m2 20.00 75.70 1,514.00 1,514.00 0.00 1,514.00
02 SEGURIDAD Y SALUD 13,445.91 13,445.91
02.01 PLAN DE SEGURIDAD 12,775.91 9,920.71 2,855.20 12,775.91
02.01.01 ELABORACION, E IMPLEMENTACION DE PLAN DE SEGU glb 1.00 500.00 500.00 500.00 500.00
02.01.02 SALUD EN EL TRABAJO 12,275.91 9,420.71 2,855.20 12,275.91
02.01.02.01 EXAMEN DE EVALUACION PREUCUPACIONAL und 60.00 30.00 1,800.00 900.00 900.00 1,800.00
02.01.02.02 IMPLEMENTACION DE SEGURIDAD glb 1.00 6,530.00 6,530.00 6,530.00 0.00 6,530.00
02.01.02.03 SEÑALISACION TEMPORAL und 1.00 35.51 35.51 35.51 0.00 35.51
02.01.02.04 CAPACITACION DE SEGURIDAD Y SALUD und 52.00 75.20 3,910.40 1,955.20 1955.20 3,910.40
02.02 SUMINISTROS DE RECURSOS PARA EMERGENCIAS 670.00 670.00 670.00
02.02.01 SUMINISTRO DE RECURSOS DE EMERGENCIAS glb 1.00 670.00 670.00 670.00 0.00 670.00
03 OBRAS PRELIMINARES 82,114.56 41,057.28 41,057.28 82,114.56
03.01 LIMPIEZA MANUAL DE CAMINO PEATONAL km 16.60 1,570.61 26,072.13 13,036.07 13036.065 26,072.13
03.02 DESBROCE DE MALEZA Y ACOPIO km 16.60 1,996.14 33,135.92 16,567.96 16567.96 33,135.92
03.03 ELIMINACION DE MALEZA km 16.60 1,379.91 22,906.51 11,453.26 11453.255 22,906.51
04 MOVIMIENTO DE TIERRAS 39,356.39 19,678.20 19,678.20 39,356.39
04.01 NIVELACION Y AREGLO DE CAMINOS PEATONALES m2 24,706.50 1.21 29,894.87 14,947.44 14947.435 29,894.87
04.02 ELIMINACION DE MATERIAL EXCEDENTE PRODUCTO DE m3 76.50 123.68 9,461.52 4,730.76 4730.76 9,461.52
05 REHABILITACION DE CAMINOS PEATONALES 29,035.00 5,807.00 23,228.00 29,035.00
05.01 SELECCION Y ACOPIO DE PIEDRAS EN FORMA MANUAL m3 120.00 59.05 7,086.00 1,417.20 5668.8 7,086.00
05.02 CARGUIO Y TRANSPORTE DE PIEDRA MANUAL m3 120.00 66.34 7,960.80 1,592.16 6368.64 7,960.80
05.03 EMPEDRADO DE CAMINO m2 404.40 34.59 13,988.20 2,797.64 11190.56 13,988.20
06 MURO SECO 6,581.49 1,316.30 5,265.19 6,581.49
06.01 EXCAVACION ZAJA MANUAL P/MURO m3 20.00 43.61 872.20 174.44 697.76 872.20
06.02 MURO SECO DE PIEDRA m3 60.00 61.57 3,694.20 738.84 2955.36 3,694.20
06.03 RELLENO APIZONADO CON MATERIAL PROPIO m3 43.41 46.42 2,015.09 403.02 1612.072 2,015.09
07 MEJORAMIENTO DE CANAL DE PASO 3,105.09 153.62 2,951.47 3,105.09
07.01 MAMPOSTERIA DE PIEDRA GRANDE Y CONCRETO EN CANund 3.00 256.03 768.09 153.62 614.472 768.09
07.02 TAPAS DE CONCRETO PREFABRICADAS DE 1.20X0.80M h und 6.00 190.00 1,140.00 1,140.00 1,140.00
07.03 TRASLADO RURAL und 6.00 199.50 1,197.00 1,197.00 1,197.00
Costo Directo 175,633.96 80,598.62 95,035.34 ### 175,633.96
GASTOS GENERALES 12% 21,076.08 21,076.08
GASTOS DE SUPERVISION 4% 7,025.36 7,025.36
GASTOS DE ADMINISTRACION 4% 7,025.36 7,025.36
GASTOS DE LIQUIDACION 2% 3,512.68 3,512.68
ELABORACION DE FICHA TECNICA 3,500.00 3,500.00

TOTAL PRESUPUESTO 217,773.43 ###