You are on page 1of 27

Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.

77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : limpieza permanete FECHA DE


4/5/2017
PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 128.10 m2/dia


CUADRILLA : Capataz. = 0.00
Operario. = 0.00
Oficial. = 0.00
Peón. = 1.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
Cemento Bolsas 0.00 S/. 20.33 S/. -
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 0.93
Capataz HH 0.00 S/. 24.12 S/. -
Operario HH 0.00 S/. 20.10 S/. -
Oficial HH 0.00 S/. 16.51 S/. -
Ayudante HH 0.06 S/. 14.85 S/. 0.93
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 0.93
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 1.00 S/. 0.93 S/. 0.93
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 1.85
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : zocalo de porcelanato 60 x 50 cm h=1.60 m (incluyFECHA DE 4/5/2017


PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 18.00 m2/dia


CUADRILLA : Capataz. = 0.00
Operario. = 1.00
Oficial. = 0.00
Peón. = 1.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
pegamento Bolsas 0.00 S/. 15.00 S/. -
porcelanato m2 0.00 S/. 40.00 S/. -
fragua kg 0.00 S/. 6.00 S/. -
crucetas bolsas 0.00 S/. 5.00 S/. -
MANO DE OBRA S/. 15.53
Capataz HH 0.00 S/. 24.12 S/. -
Operario HH 0.44 S/. 20.10 S/. 8.94
Oficial HH 0.00 S/. 16.51 S/. -
Ayudante HH 0.44 S/. 14.85 S/. 6.60
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 30.78
Mezcladora hm 2.00 S/. 15.00 S/. 30.00
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.05 S/. 15.53 S/. 0.78
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 46.31
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : piso porcelanato 60 x 60 cm primer piso(incluye r FECHA DE 4/5/2017


PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 14.00 m2/dia


CUADRILLA : Capataz. = 0.10
Operario. = 1.00
Oficial. = 0.00
Peón. = 0.30
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. 95.00


pegameto Bolsas 4.00 S/. 15.00 S/. 60.00
porcelanato m2 1.00 S/. 35.00 S/. 35.00
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 15.41
Capataz HH 0.06 S/. 24.12 S/. 1.38
Operario HH 0.57 S/. 20.10 S/. 11.49
Oficial HH 0.00 S/. 16.51 S/. -
Ayudante HH 0.17 S/. 14.85 S/. 2.55
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 0.77
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.05 S/. 15.41 S/. 0.77
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 111.18
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : 4/5/2017
FECHA DE
PRESUPUESTO:
ESPECIFICACIÓN………………….. tabiqueria de drywall (planchas de fibro cemento al
UNIDAD m3

RENDIMIENTO : 20.00 m2/dia


CUADRILLA : Capataz. = 0.10
Operario. = 1.00
Oficial. = 0.00
Peón. = 2.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
Cemento Bolsas 0.00 S/. 20.33 S/. -
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 20.88
Capataz HH 0.04 S/. 24.12 S/. 0.96
Operario HH 0.40 S/. 20.10 S/. 8.04
Oficial HH 0.00 S/. 16.51 S/. -
Ayudante HH 0.80 S/. 14.85 S/. 11.88
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 1.04
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.05 S/. 20.88 S/. 1.04
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 21.93
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : acero fy=4200 kg/cm2 grado 60 FECHA DE


4/5/2017
PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 250.00 kg
CUADRILLA : Capataz. = 0.10
Operario. = 1.00
Oficial. = 0.00
Peón. = 0.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
Cemento Bolsas 0.00 S/. 20.33 S/. -
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 0.72
Capataz HH 0.00 S/. 24.12 S/. 0.08
Operario HH 0.03 S/. 20.10 S/. 0.64
Oficial HH 0.00 S/. 16.51 S/. -
Ayudante HH 0.00 S/. 14.85 S/. -
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 0.04
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.05 S/. 0.72 S/. 0.04
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 0.76
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : encofrado y desencofrado normal en mesa de laboFECHA DE 4/5/2017


PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 7.50 m2
CUADRILLA : Capataz. = 0.10
Operario. = 1.00
Oficial. = 0.50
Peón. = 1.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
Cemento Bolsas 0.00 S/. 20.33 S/. -
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 48.66
Capataz HH 0.11 S/. 24.12 S/. 2.57
Operario HH 1.07 S/. 20.10 S/. 21.44
Oficial HH 0.53 S/. 16.51 S/. 8.81
Ayudante HH 1.07 S/. 14.85 S/. 15.84
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 1.46
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.03 S/. 48.66 S/. 1.46
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 50.12
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : concreto f'c= 175 kg/cm2 en mesa de laboratorios FECHA DE 4/5/2017


PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 2.20 m3/dia


CUADRILLA : Capataz. = 0.10
Operario. = 2.00
Oficial. = 1.00
Peón. = 3.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. 13.98


Cemento Bolsas 0.54 S/. 20.33 S/. 10.98
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.20 S/. 15.00 S/. 3.00
MANO DE OBRA S/. 376.99
Capataz HH 0.36 S/. 24.12 S/. 8.77
Operario HH 7.27 S/. 20.10 S/. 146.21
Oficial HH 3.64 S/. 16.51 S/. 60.05
Ayudante HH 10.91 S/. 14.85 S/. 161.96
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 138.85
Mezcladora hm 8.00 S/. 15.00 S/. 120.00
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.05 S/. 376.99 S/. 18.85
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 529.82
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : contra piso f'c=175 kg/cm2 e=0.20m FECHA DE


4/5/2017
PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 25.62 m2/dia


CUADRILLA : Capataz. = 0.10
Operario. = 1.00
Oficial. = 1.00
Peón. = 1.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
Cemento Bolsas 0.00 S/. 20.33 S/. -
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 16.82
Capataz HH 0.03 S/. 24.12 S/. 0.75
Operario HH 0.31 S/. 20.10 S/. 6.28
Oficial HH 0.31 S/. 16.51 S/. 5.16
Ayudante HH 0.31 S/. 14.85 S/. 4.64
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 0.84
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.05 S/. 16.82 S/. 0.84
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 17.66
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : excavacion de sanja tramo ef FECHA DE


4/5/2017
PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 3.00 m2/dia


CUADRILLA : Capataz. = 0.00
Operario. = 0.00
Oficial. = 0.00
Peón. = 1.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
Cemento Bolsas 0.00 S/. 20.33 S/. -
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 39.59
Capataz HH 0.00 S/. 24.12 S/. -
Operario HH 0.00 S/. 20.10 S/. -
Oficial HH 0.00 S/. 16.51 S/. -
Ayudante HH 2.67 S/. 14.85 S/. 39.59
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 1.98
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.05 S/. 39.59 S/. 1.98
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 41.57
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : excavacion de saexcava FECHA DE


4/5/2017
PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 3.00 m3/dia


CUADRILLA : Capataz. = 0.00
Operario. = 0.00
Oficial. = 0.00
Peón. = 1.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
Cemento Bolsas 0.00 S/. 20.33 S/. -
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 39.59
Capataz HH 0.00 S/. 24.12 S/. -
Operario HH 0.00 S/. 20.10 S/. -
Oficial HH 0.00 S/. 16.51 S/. -
Ayudante HH 2.67 S/. 14.85 S/. 39.59
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 1.98
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.05 S/. 39.59 S/. 1.98
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 41.57
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : excavancion de sanja tramo bc FECHA DE


4/5/2017
PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 3.00 m3/dia


CUADRILLA : Capataz. = 0.00
Operario. = 0.00
Oficial. = 0.00
Peón. = 1.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
Cemento Bolsas 0.00 S/. 20.33 S/. -
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 39.59
Capataz HH 0.00 S/. 24.12 S/. -
Operario HH 0.00 S/. 20.10 S/. -
Oficial HH 0.00 S/. 16.51 S/. -
Ayudante HH 2.67 S/. 14.85 S/. 39.59
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 1.98
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.05 S/. 39.59 S/. 1.98
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 41.57
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : excavacion de satramo ab FECHA DE


4/5/2017
PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 3.00 m3/dia


CUADRILLA : Capataz. = 0.00
Operario. = 0.00
Oficial. = 0.00
Peón. = 1.00
Operador. = .

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
Cemento Bolsas 0.00 S/. 20.33 S/. -
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 39.59
Capataz HH 0.00 S/. 24.12 S/. -
Operario HH 0.00 S/. 20.10 S/. -
Oficial HH 0.00 S/. 16.51 S/. -
Ayudante HH 2.67 S/. 14.85 S/. 39.59
Operador HH 2.67 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 1.98
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.05 S/. 39.59 S/. 1.98
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 41.57
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : picado de socalo existente FECHA DE


4/5/2017
PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 134.80 m2/dia


CUADRILLA : Capataz. = 0.01
Operario. = 1.00
Oficial. = 2.00
Peón. = 2.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
Cemento Bolsas 0.00 S/. 20.33 S/. -
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 4.93
Capataz HH 0.00 S/. 24.12 S/. 0.01
Operario HH 0.06 S/. 20.10 S/. 1.19
Oficial HH 0.12 S/. 16.51 S/. 1.96
Ayudante HH 0.12 S/. 14.85 S/. 1.76
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 0.25
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.05 S/. 4.93 S/. 0.25
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 5.18
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : demolicion de pisos existentes FECHA DE


4/5/2017
PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 128.10 m2/dia


CUADRILLA : Capataz. = 0.10
Operario. = 0.00
Oficial. = 2.00
Peón. = 4.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
Cemento Bolsas 0.00 S/. 20.33 S/. -
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 5.92
Capataz HH 0.01 S/. 24.12 S/. 0.15
Operario HH 0.00 S/. 20.10 S/. -
Oficial HH 0.12 S/. 16.51 S/. 2.06
Ayudante HH 0.25 S/. 14.85 S/. 3.71
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 0.30
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.05 S/. 5.92 S/. 0.30
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 6.22
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : demolicion de muros existentes FECHA DE


4/5/2017
PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 6.00 m2/dia


CUADRILLA : Capataz. = 0.01
Operario. = 0.00
Oficial. = 0.20
Peón. = 0.01
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
Cemento Bolsas 0.00 S/. 20.33 S/. -
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 4.92
Capataz HH 0.01 S/. 24.12 S/. 0.32
Operario HH 0.00 S/. 20.10 S/. -
Oficial HH 0.27 S/. 16.51 S/. 4.40
Ayudante HH 0.01 S/. 14.85 S/. 0.20
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 0.25
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.05 S/. 4.92 S/. 0.25
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 5.17
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : demolicion de mesadas existentes FECHA DE


4/5/2017
PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 1.00 m3/dia


CUADRILLA : Capataz. = 0.10
Operario. = 0.00
Oficial. = 0.00
Peón. = 0.05
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
Cemento Bolsas 0.00 S/. 20.33 S/. -
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 25.24
Capataz HH 0.80 S/. 24.12 S/. 19.30
Operario HH 0.00 S/. 20.10 S/. -
Oficial HH 0.00 S/. 16.51 S/. -
Ayudante HH 0.40 S/. 14.85 S/. 5.94
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 0.50
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.02 S/. 25.24 S/. 0.50
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 25.74
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : desmontaje de aparatos sanitarios FECHA DE


4/5/2017
PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 2.00 unid


CUADRILLA : Capataz. = 0.10
Operario. = 0.03
Oficial. = 0.00
Peón. = 0.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
Cemento Bolsas 0.00 S/. 20.33 S/. -
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 12.06
Capataz HH 0.40 S/. 24.12 S/. 9.65
Operario HH 0.12 S/. 20.10 S/. 2.41
Oficial HH 0.00 S/. 16.51 S/. -
Ayudante HH 0.00 S/. 14.85 S/. -
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 0.60
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.05 S/. 12.06 S/. 0.60
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 12.67
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : concreto f'c= 175 kg/cm2 en mesa de laboratorios FECHA DE 4/5/2017


PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 2.20 m3/dia


CUADRILLA : Capataz. = 0.10
Operario. = 1.00
Oficial. = 1.00
Peón. = 2.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
Cemento Bolsas 0.00 S/. 20.33 S/. -
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 249.90
Capataz HH 0.36 S/. 24.12 S/. 8.77
Operario HH 3.64 S/. 20.10 S/. 73.10
Oficial HH 3.64 S/. 16.51 S/. 60.05
Ayudante HH 7.27 S/. 14.85 S/. 107.97
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 1,369.60
Mezcladora hm 8.00 S/. 15.00 S/. 120.00
Vibradora hm 0.01 S/. 10.00 S/. 0.10
Herramientas Manuales (3% mo) % 5.00 S/. 249.90 S/. 1,249.50
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 1,619.50
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : desmontaje de ventnas existentes FECHA DE


4/5/2017
PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 16.00 m3 / día


CUADRILLA : Capataz. = 0.10
Operario. = 2.00
Oficial. = 1.00
Peón. = 0.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
cemento Bolsas 0.00 S/. 20.33 S/. -
2.00 m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 29.57
Capataz HH 0.05 S/. 24.12 S/. 1.21
Operario HH 1.00 S/. 20.10 S/. 20.10
Oficial HH 0.50 S/. 16.51 S/. 8.26
Ayudante HH 0.00 S/. 14.85 S/. -
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 1.18
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.04 S/. 29.57 S/. 1.18
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 30.75
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : desmontaje de puertas existentes FECHA DE


4/5/2017
PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 10.00 m3 / día


CUADRILLA : Capataz. = 0.10
Operario. = 2.00
Oficial. = 2.00
Peón. = 0.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
cemento Bolsas 0.00 S/. 20.33 S/. -
. m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 60.52
Capataz HH 0.08 S/. 24.12 S/. 1.93
Operario HH 1.60 S/. 20.10 S/. 32.17
Oficial HH 1.60 S/. 16.51 S/. 26.42
Ayudante HH 0.00 S/. 14.85 S/. -
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 1.82
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.03 S/. 60.52 S/. 1.82
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 62.33
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : trazo nivel y replanteo FECHA DE


4/5/2017
PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 128.10 m2/dia


CUADRILLA : Capataz. = 0.20
Operario. = 2.00
Oficial. = 1.00
Peón. = 1.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. 0.79


cemento Bolsas 0.04 S/. 20.33 S/. 0.79
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 4.77
Capataz HH 0.01 S/. 24.12 S/. 0.30
Operario HH 0.12 S/. 20.10 S/. 2.51
Oficial HH 0.06 S/. 16.51 S/. 1.03
Ayudante HH 0.06 S/. 14.85 S/. 0.93
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 0.14
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.03 S/. 4.77 S/. 0.14
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 5.71
REMODELACION Y ADECUACION DE LAS INSTALACIONES ELECTROMECANICAS DEL AREA DE BIOLOGIA MOLECULAR DEL LAB
REGIONAL DE SALUD - REGION

Ítem Descripción Und.


01.00.00 Trabajos provisionales
01.01.00 Agua para servicio glb
01.02.00 Movilización y desmovilización de equipo glb
02.00.00 Trabajos preliminares
02.01.00 Limpieza de terreno m2
02.02.00 Trazo, nivel y replanteo m2
02.03.00 Desmontaje de puertas existentes und
02.04.00 Desmontaje de ventanas existentes und
02.05.00 Desmontaje de aparatos sanitarios und
02.06.00 Desmontaje de luminarias existentes und
02.07.00 Demolición de mesadas existentes glb
02.08.00 Demolición de muros existentes m2
02.09.00 Demolición de pisos existentes m2
02.10.00 Picado de zacalo existente de mayolica h=1.60m m2
03.00.00 Movimiento de tierras
03.01.00 Excavación de zanja tramo ab m3
03.02.00 Excavación de zanja tramo bc m3
03.03.00 Excavación de zanja tramo cd m3
03.04.00 Excavación de zanja tramo de m3
03.05.00 Excavación de zanja tramo ef m3
04.00.00 Trabajos de concreto simple
04.01.00 Contra piso f'c=175 kg/cm2 e=0.20m m2
05.00.00 Trabajos de concreto armado
05.01.00 Concreto f'c=175 kg/cm2 en mesa de laboratorios m3
05.02.00 Encofrado y desencofrado normal de mesa de laboratorios m2
05.03.00 Acero fy=4200 kg/cm2 grado 60 kg
06.00.00 Muros y tabiques
06.01.00 Muro de soga ladrillo maquinado, mortero 1:4 m2

06.02.00 Tabiquería de drywall (planchas de fibro cemento al exterior y fibro yeso al interior) m2
07.00.00 Salidas para centros de luz
07.01.00 Salidas para centros de luz pto
08.00.00 Salidas para tomacorrientes
08.01.00 Tomacorrientes con toma a tierra Isoh 4mm+2.5mm pto
09.00.00 Salida de comunicaciones
09.01.00 Salida para telefono interno pto
10.00.00 Salidas de fuerzas especiales
10.01.00 Salida de fuerza c/toma a tierra Isoh 3-1x4mm+1x2.5mm2(t)- 25mm pvc-p pto
10.02.00 Salida de fuerza c/toma a tierra Isoh 2-1x4mm+1x2.5mm2(t)- 20mm pvc-p pto
11.00.00 Cajas de pase
11.01.00 Caja f°g 100x100x55mm und
11.02.00 Caja f°g 150x150x55mm und
12.00.00 Alimentadores y circuitos electricos
12.01.00 Alimentador 3-1x16mm2Isoh + 1x10mm2Isoh(t)-35mm pvc-p m
12.02.00 Alimentador 3-1x50mm2nyy + 1x25mm2Isoh(t)-50mm pvc-p m
13.00.00 Tableros electricos
13.01.00 Tablero a t-g und
13.02.00 Tablero a t-e und
14.00.00 Artefactos de iluminación
14.01.00 Artefacto tipo b1 und
14.02.00 Artefacto tipo b2 und
14.03.00 Artefacto tipo f und
14.04.00 Artefacto tipo braquete und
14.05.00 Artefacto para luz de emergencia con equipo y lampara de 2x40 w und
15.00.00 Prueba electrica
15.01.00 Prueba electrica und
16.00.00 Sistema de alarma contra incendio
16.01.00 Accesorio portatil del tipo adosado en techo con bateria interna und
17.00.00 Acabados
17.01.00 Pisos y pavimentos
Piso porcelanato 60x60 cm primer piso (incluye revestimiento de mesada interior y
17.01.01 exterior) m2
17.02.00 Zocalos
Zocalo de porcelanato 60x50 cm h=1.60 m (incluye revestimiento de mesada interior y
17.02.01 exterior) m2
18.00.00 Varios, limpieza
18.01.00 Limpieza permanente glb
BIOLOGIA MOLECULAR DEL LABORATORIO DE PIURA UE- 400 - DIRECCION
EGION

Metrado PU Parcial Total


S/. 3,000.00
1.00 S/. 1,000.00 S/. 1,000.00
1.00 S/. 2,000.00 S/. 2,000.00
S/. 3,845.38
128.10 S/. 3.80 S/. 486.78
128.10 S/. 4.91 S/. 628.97
10.00 S/. 62.33 S/. 623.30
16.00 S/. 30.75 S/. 492.00
2.00 S/. 12.67 S/. 25.34
11.00 S/. 3.38 S/. 37.18
1.00 S/. 25.74 S/. 25.74
6.00 S/. 5.17 S/. 31.02
128.10 S/. 6.22 S/. 796.78
134.80 S/. 5.18 S/. 698.26
S/. 715.00
0.32 S/. 41.57 S/. 13.30
9.00 S/. 41.57 S/. 374.13
0.68 S/. 41.57 S/. 28.27
1.08 S/. 41.57 S/. 44.90
6.12 S/. 41.57 S/. 254.41
S/. 452.45
25.62 S/. 17.66 S/. 452.45
S/. 2,772.17
2.20 S/. 1,068.55 S/. 2,350.81
7.50 S/. 50.12 S/. 375.90
59.81 S/. 0.76 S/. 45.46
S/. 403.82
18.19 S/. 22.20 S/. 403.82

31.29 S/. - S/. -


S/. -
26.00 S/. - S/. -
S/. -
60.00 S/. - S/. -
S/. -
6.00 S/. - S/. -
S/. -
6.00 S/. - S/. -
4.00 S/. - S/. -
S/. -
1.00 S/. - S/. -
2.00 S/. - S/. -
S/. -
8.00 S/. - S/. -
82.00 S/. - S/. -
S/. -
1.00 S/. - S/. -
1.00 S/. - S/. -
S/. -
10.00 S/. - S/. -
10.00 S/. - S/. -
5.00 S/. - S/. -
1.00 S/. - S/. -
8.00 S/. - S/. -
S/. -
1.00 S/. - S/. -
S/. -
8.00 S/. - S/. -

S/. 14,242.16

128.10 S/. 111.18 S/. 14,242.16


S/. 10,890.72

235.17 S/. 46.31 S/. 10,890.72


S/. 1,000.00
1.00 S/. 1,000.00 S/. 1,000.00
Costo Directo S/. 34,321.69
Jonada (horas/d 8.00 Operario S/. 160.83 Peón S/. 118.77
Capataz S/. 193.00 Oficial S/. 132.11 Operador S/. -

PARTIDA : MOVIMIENTO DE TIERRA FECHA DE


4/5/2017
PRESUPUESTO:
ESPECIFICACIÓN…………………..

UNIDAD m3

RENDIMIENTO : 128.10 m2/dia


CUADRILLA : Capataz. = 0.10
Operario. = 0.00
Oficial. = 0.00
Peón. = 3.00
Operador. = 0.00

PRECIO UNIT. PRECIO


DESCRIPCIÓN UNIDAD. CANTIDAD. TOTAL.
(S/.) PARCIAL (S/.)

MATERIALES S/. -
Cemento Bolsas 0.00 S/. 20.33 S/. -
Hormigon m3 0.00 S/. 50.00 S/. -
Piedra m3 0.00 S/. 50.00 S/. -
Agua m3 0.00 S/. 15.00 S/. -
MANO DE OBRA S/. 2.93
Capataz HH 0.01 S/. 24.12 S/. 0.15
Operario HH 0.00 S/. 20.10 S/. -
Oficial HH 0.00 S/. 16.51 S/. -
Ayudante HH 0.19 S/. 14.85 S/. 2.78
Operador HH 0.00 S/. - S/. -
EQUIPO Y HERRAMIENTAS S/. 0.15
Mezcladora hm 0.00 S/. 15.00 S/. -
Vibradora hm 0.00 S/. 10.00 S/. -
Herramientas Manuales (3% mo) % 0.05 S/. 2.93 S/. 0.15
0.00 S/. - S/. -
SUBCONTRATOS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
SUBPARTIDAS S/. -
0.00 S/. - S/. -
0.00 S/. - S/. -
Costo Unitario S/. 3.08