You are on page 1of 8

"TECHNICAL REPORT"

Name of Work: CONSTRUCTION OF LOW COST COW SHED ( 2 UNITS )

Estimated Cost: ` 56,749/- Rupees ( Fifty Six Thousand Seven Hundred and Forty Nine )

Design: The Engineering cell of the Department was directed to prepare the
architectural plans and detail estimates for the construction of a low cost Cow
Shed (2 units) considering the modern day requirements. In view of the
same,the plan shows a single storey structure size of (2.7 X 3.0) sqm with a
total built up area of 8.10 sqm(87.16 sq ft). The architectural plan
accomodates 2 nos of the animal with free working space for the caretaker of
the same.

Scope of Work: The structure has been built using MS Tubular Pipes of 50mm dia
acting as the columns for the shed (4nos in each column) with the 24 BWG
GCI Sheet roofing embedded in the MS Tubular Truss sections. The estimate
provides for laying of stone soling of 150mm thick and two layers of cement
concrete in 1:3:6mix ratio of 100mm and 75mm thick respectively for the total
floor area. The scope of work involves provision for a urine pit of size
(1.2mx1.2m) built in 1:2:4 mix plum concrete and a fodder trough of
dimensions (2.7mX0.45mX0.6m) is provided with same. U Shaped drain
(23cmX23cm) connects the animal wastes to the urine pit.

Rates: SOR 2012

Mode of execution: Departmental.

Time: One Month

Assistant Engineer, Divisional Engineer,


AH,L,F&VS Department AH,L,F&VS Department
Government of Sikkim. Government of Sikkim.
ESTIMATE FOR THE CONSTRUCTION OF LOW COST COW SHED ( 2 UNITS )
Sl Particulars Quantity Rate Amount
1 Manpower engaged for Jungle clearance, Site Preparation,levelling and throwing
of spoils etc all complete.
2 x 3 = 6.00 mdays 6.00 mdays 200 /day ` 1200
labours days
2 Earth work in excavation in mixed soil in foundation trenches i/c dressing of all
sides, watering and ramming i/c disposal of excavated earth upto 30 m lead and
lift upto 1.5 m, disposed earth to be leveled and neatly dressed as per the
direction of Engineer - in - charge all complete.
Columns:
4 x 0.60 x 0.60 x 1.20 = 1.73 cum
Plinth Area:
1 x 2.70 x 3.00 x 0.45 = 3.65 cum
Urine Pit:
1 x 0.90 x 0.90 x 0.90 = 0.73 cum
= 6.10 cum 6.10 cum 164.74 /cum ` 1005

3 Providing and laying hand packed stone soling in building works with clean hard
selected stones all complete.
Columns:
4 x 0.60 x 0.60 x 0.15 = 0.22 cum
Plinth Area:
1 x 2.70 x 3.00 x 0.20 = 1.62 cum
Urine Pit:
1 x 0.90 x 0.90 x 0.15 = 0.12 cum
= 1.96 cum 1.96 cum 560.280 /cum ` 1097

4 Providing & Laying in position cement concrete of 1:3:6 mix, including


compacting curing etc. all complete.
Columns:
4 x 0.60 x 0.60 x 0.10 = 0.14 cum
Plinth Area:
1 x 2.70 x 3.00 x 0.10 = 0.81 cum
1 x 2.70 x 3.00 x 0.075 = 0.61 cum
Urine Pit:
1 x 0.90 x 0.90 x 0.10 = 0.08 cum
= 1.64 cum 1.64 cum 3821.970 /cum ` 6278
5 Providing U shaped drain of 23cm (ht) x 23 cm (width) of internal dimension
with 1:2:4 Plum concrete (40mm & down) side wall thickness of 23 cm on both
side with 1:3:6 (20 mm & down) base concrete of thickness of 15 cm with
standard specification over 15 cm stone soling including 1:3 cement plaster with
neat cement polishing & rounding of junction, as per the direction of the
Engineer in Charge.
All four sides:
1 x 10.20 = 11.40 mtr
Connecting drain to Cow dung / urine Pit:
1 x 2.00 = 2.00 mtr
= 13.40 mtr 13.40 mtr 694.290 /mtr ` 9303

6 Providing, fitting, fixing of 24 BWG GCI sheet roofing with lapping of 150mm
(two corrugation) with G.I. hooks, bolts and nut 8mm dia with bitumen, GI
limpet washers filled with white bad including coat of approved steel primer and
two coats of approved paint, on overlapping of sheet excluding carriage all
complete.
1 x 3.30 x 3.90 = 12.87 sqm 12.87 sqm 853.44 /sqm ` 10984

7 Supplying, fabricating, fitting and fixing steel tubular trusses including cutting,
hoisting, fixing in position and applying a priming coat of approved steel primer,
welded and bolted including special shape washer etc as per the standard
specification and design and direction of Engineer - in- Charge all complete.

MS Pipe 50mm dia:


Columns: 4 x 4 x 3.90 = 62.40 Rm
Supports to the 1 x 5 x 3.30 = 16.50 Rm
Roofing: 1 x 5 x 3.90 = 19.50 Rm
= 98.40 Rm
98 x 3.80 kgs/Rm = 373.92 kg 373.92 kg 65.580 kg ` 24522
8 Providing and laying in position Plum concrete in 1:4:8 mix with stone aggregate
of size 20mm down all complete.
Fodder Trough:
2 x 2.70 x 0.90 x 0.15 = 0.73 cum
1 x 2.70 x 0.45 x 0.20 = 0.24 cum
2 x 0.45 x 0.90 x 0.15 = 0.12 cum
Urine Pit:
4 x 0.90 x 0.90 x 0.20 = 0.65 cum
= 1.74 cum 1.74 cum 2705.71 /cum ` 4712
9 Carriage of stock materials.
Cement: 10 Kms
v.i.no.( 4 ) = 1.64 x 4.400 = 7.23 bags
v.i.no.( 5 ) = 13.40 x 0.254 = 3.40 bags
v.i.no.( 8 ) = 1.74 x 1.700 = 2.96 bags
= 13.59 bags
say = 6.80 qtls
MS Pipe:
v.i.no.( 7 ) = 3.74 qtls
= 10.53 qtls
= 1.05 MT 1.05 MT 55.700 /MT ` 59
(carriage of materials per MT/Km.) = 5.57
Loading and unloading of cement or steel by manual means and stacking. 1.05 MT 153.580 /MT ` 162
10 Carriage of non stock materials.
Sand: 10 Kms
v.i.no.( 4 ) = 1.64 x 0.470 = 0.77 cum
v.i.no.( 5 ) = 13.40 x 0.063 = 0.84 cum
v.i.no.( 8 ) = 1.74 x 0.224 = 0.39 cum
= 2.01 cum
= 3690 kgs
= 3.69 MT 3.69 MT 55.7 /MT ` 206
(carriage of materials per MT/Km.) = 5.57
Loading and unloading of stone boulders / stone aggregates / sand / kankar /
moorum.
2.01 cum 87.000 /cum ` 174
Stone: 10 Kms
v.i.no.( 3 ) = 1.96 x 0.950 = 1.86 cum
v.i.no.( 5 ) = 13.40 x 0.115 = 1.54 cum
v.i.no.( 8 ) = 1.74 x 0.500 = 0.87 cum
= 4.27 cum
= 9397 kgs
= 9.40 MT 9.40 MT 55.7 /cum ` 523
(carriage of materials per MT/Km.) = 5.57
Loading and unloading of stone boulders / stone aggregates / sand / kankar /
moorum. 4.27 cum 87.000 /cum ` 372

Stone Chips: 10 Kms


v.i.no.( 4 ) = 1.64 x 0.940 = 1.54 cum
v.i.no.( 5 ) = 13.40 x 0.106 = 1.42 cum
v.i.no.( 8 ) = 1.74 x 0.445 = 0.77 cum
= 3.74 cum
= 7684.3 kgs
= 7.68 MT 7.68 MT 55.7 /cum ` 428
(carriage of materials per MT/Km.) = 5.57
Loading and unloading of stone boulders / stone aggregates / sand / kankar /
moorum.
3.74 cum 87.000 /cum ` 325
Structure Cost= ` 61350
Deduction of 7.5% Contractors' Profit ` 4601
Total= ` 56749

Rupees ( Fifty Six Thousand Seven Hundred and Forty Nine ) Only

Junior Engineer Assistant Engineer


AH,L,F& VS Department AH,L,F& VS Department
Govt. of Sikkim Govt. of Sikkim
DETAIL FINANCIAL COMPONENT WISE BREAK-UP (LABOUR / SUPPLY
COMPONENTS) FOR THE WORK "CONSTRUCTION OF LOW COST COW SHED ( 2
Sl Particulars Amount
A) Labour Components:
1 Manpower engaged for Jungle clearance, Site Preparation,levelling and
throwing of spoils etc all complete. ` 1200
2 Earth work in excavation in mixed soil in foundation trenches i/c dressing
of all sides, watering and ramming i/c disposal of excavated earth upto 30 m
lead and lift upto 1.5 m, disposed earth to be leveled and neatly dressed as
per the direction of Engineer - in - charge all complete. ` 1005
3 Providing and laying hand packed stone soling in building works with clean
hard selected stones all complete. ` 662
4 Providing & Laying in position cement concrete of 1:3:6 mix, including
compacting curing etc. all complete. ` 2072
5 Providing U shaped drain of 23cm (ht) x 23 cm (width) of internal
dimension with 1:2:4 Plum concrete (40mm & down) side wall thickness of
23 cm on both side with 1:3:6 (20 mm & down) base concrete of thickness
of 15 cm with standard specification over 15 cm stone soling including 1:3
cement plaster with neat cement polishing & rounding of junction, as per the
direction of the Engineer in Charge. ` 3070
6 Providing, fitting, fixing of 24 BWG GCI sheet roofing with lapping of
150mm (two corrugation) with G.I. hooks, bolts and nut 8mm dia with
bitumen, GI limpet washers filled with white bad including coat of approved
steel primer and two coats of approved paint, on overlapping of sheet
excluding carriage all complete. ` 3625
7 Supplying, fabricating, fitting and fixing steel tubular trusses including
cutting, hoisting, fixing in position and applying a priming coat of approved
steel primer, welded and bolted including special shape washer etc as per
the standard specification and design and direction of Engineer - in- Charge
all complete.
MS Pipe 50mm dia: ` 7357
8 Providing and laying in position Plum concrete in 1:4:8 mix with stone
aggregate of size 20mm down all complete. ` 1555
9 Carriage of stock materials.
Loading and unloading of cement or steel by manual means and stacking. ` 162
10 Carriage of non stock materials.
Loading and unloading of sand. ` 174
Loading and unloading of stone. ` 372
Loading and unloading of stone chips. ` 325
al Labour Component (A)= ` 21579

B) Supply Components:
Particulars Quantity Unit Rate Unit ` Amount
to be beneficiary
1 Sand 70.93 cft 21 cft ` 1490 contribution

to be beneficiary
2 Stone 150.67 cft 18 cft ` 2712 contribution
3 Stone chips 131.97 cft 30 cft ` 3959
4 G.C.I Sheets (3 'x 8') 6 nos 745.5 nos ` 4473
5 M.S pipes. 373.92kgs 43.5 kgs ` 16266
6 Cement. 14 bgs 350 bgs ` 4900
7 Mixed Nails. 2 kgs 85 kgs ` 170
8 Carriage of materials. 1 trip 1200 trip ` 1200
tal SupplyComponent (B)= ` 35170
Total Amount (A + B )= ` 56749
Rupees ( Fifty Six Thousand Seven Hundred and Forty Nine ) Only
Junior Engineer Assistant Engineer
AH,L,F& VS Department AH,L,F& VS Department
Govt. of Sikkim Govt. of Sikkim
MGNREGA Harmonization of the SPWD SOR 2012 Estimate

Total cost as per SOR 2012 56,749


Total supply component 35,170
Total supply component - 7.5% contractor profit 32,532
Total wage component 21,579
Total wage component - 7.5% contractor profit 19,961
Unskilled wage component (70%) 13,972
Skilled wage component (30%) 5,988
Unskilled Persondays 70
Stone instead of stone chips (resulting in additional
persondays of 131.97 x 12 / 135 12
Total persondays 82
Local material of stone and local wood to be beneficiary contribution
Revised supply component as per MGNREGA 28,330
Revised unskilled wage component as per MGNREGA 12,647
Revised Skilled wage component under MGNREGA 5,988
Revised cost as per MGNREGA 46,965
1% contingency 470
Total cost 47,435
Wage material ratio 36% 64%
12,647 34,788
Wages Material
x' x'

Fodder Trough

THIS DRAWING IS A PROPERTY OF


AH,LF & VS DEPARTMENT
GOVERNMENT OF SIKKIM
THE DRAWING OR ANY PART OF THE DRAWING
IS NOT TO BE REPRODUCED WITHOUT THE
PERMISSION OF THE DEPARTMENT

x
NOTES
Plan 1. THIS DRAWING IS TO BE READ AND NOT MEASURED

2. ALL THE DIMENSIONS ARE IN METERS UNLESS SPECIFIED

3. THE DRAWING SHALL BE READ IN CONJUNCTURE WITH ALL


Urine SERVICES,STRUCTURAL AND OTHER RELEVANT DRAWINGS

Tank
PROJECT
G.c.i Sheet CONSTRUCTION OF A LOW COST COW SHED
0.45 Roofing (2 UNITS)

0.45

2.40
Fodder Trough
0.08

0.45m wide
0.1
0.2

and 0.60m ht.


DRN. BY
Cement Concrete G.L
(1:3:6 mix) JUNIOR ENGINEER
Stone Soling AH,LF & VS DEPARTMENT
3.0 Urine CHECKED BY
Tank
ASSISTANT ENGINEER
AH,LF & VS DEPARTMENT

Cross Section at X-X' APPROVED BY

DIV. ENGINEER
AH,LF & VS DEPARTMENT