ESTIMATE FOR CONSTRUCTION OF RCC CABLE TRENCH OF 900X1100 MM SIZE, LUCKNOW
(Taking length 10.0 M)
Sr.N Details of Item Nos L B D/H Qty Rate Amount
1 Excavation in foundation in ordinary soil (Loam Clay or Sand) including lift upto 1.5m and lead upto 30m and including filling, watering and ramming of excavated earth into the trenches or into the space between the building and sides of the foundation work. (CSI No. 4.01)
Cable Trench Cum 1 x 1 10.000 1.900 1.000 19.000
19.000 ₹ 133.00 ₹ 2,527.00 2 Concrete with 4 cm gauge 1st class brick ballast (class 150mm) coarse sand (F.M. 1.8 to 2.5) and cement in proportion of 8:4:1 in foundation & under floors including supply of all materials, labour & T&P etc. complete. (CSI no. 5.04)
Cable Trench Cum 1 x 1 10.000 1.900 0.100 1.900
1.900 ₹ 4,695.00 ₹ 8,920.50 3 TMT/Tor steel in plain work such as reinforced concrete or reinforced brick work (when not included in an over all rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of steel its Size Nos Ct.Length 8Ø 10Ø wastage, bend, hooks and authorized overlapping shall be measured. (Steel shall be arranged by the contractor) (CSI No. 9.03)
Trench Base Raft-Ring 10Ø 1 67 1 3.680 245.333
Binder 10Ø 1 25 1 10.000 245.333 Laps 10Ø 1 25 1 0.500 12.267 Chairs 10Ø 2 25 1 0.750 36.800 Trench garden Side wall-Main 10Ø 1 67 1 1.650 110.000 Binder 8Ø 1 8 1 10.000 82.500 Haunch 10Ø 1 50 1 0.800 40.000 Laps 8Ø 1 8 1 0.400 3.300 Trench garden Side wall-Temp.Steel 10Ø 1 67 1 1.650 110.000 Binder 8Ø 1 11 1 10.000 110.000 Laps 8Ø 3 11 1 0.400 13.200 Tie Bar 8Ø 2 11 1 0.450 9.900 Separator 8Ø 2 10 1 0.600 12.000 Trench Road Side wall-Main 10Ø 1 67 1 1.650 110.000 Binder 8Ø 1 8 1 10.000 82.500 Haunch 10Ø 1 50 1 0.800 40.000 Laps 8Ø 1 8 1 0.400 3.300 Trench Road Side wall-Temp.Steel 10Ø 1 67 1 1.650 110.000 Binder 8Ø 1 11 1 10.000 110.000 Laps 8Ø 3 11 1 0.400 13.200 Tie Bar 8Ø 2 11 1 0.450 9.900 Separator 8Ø 2 10 1 0.600 12.000 Total Length 461.800 1059.733 Unit Wt. 0.395 0.617 Total Wt. 182.411 653.855 Total Wt.= 836.266 Kg 8.36 ₹ 6,545.20 ₹ 54,735.28 4 RCC work with cement approved coarse sand (F.M. 1.8 to 2.5) and 2 cm gauge graded approved hard stone ballast like grainite, quartzite etc from Dalla, Jhansi or other quarries and approved coarse sand in proportion 1:1.5:3 in raft foundation and footings , excluding supply of reinforcement & its bending but including its fixing and binding the same with binding wire, including cost of all other materials labour and T&P. (CSI No. 5.27)
Trench Base slab Cum 1 x 1 10.000 1.600 0.150 2.40
Haunch Cum 2 x 1 10.000 0.150 0.075 0.23 Total= 2.63 ₹ 7,618.00 20035.34 5 RCC work with cement approved coarse sand (F.M. 1.8 to 2.5) and 2 cm gauge graded approved hard stone ballast like grainite, quartzite etc from Dalla, Jhansi or other quarries and approved coarse sand in proportion 1:1.5:3 in RCC T beamslab and column , excluding supply of reinforcement & its bending but including its fixing and binding the same with binding wire, including cost of all other materials labour and T&P . (CSI No. 5.29)
Trench wall-Opps.Road Side Cum 1 x 1 10.000 0.200 1.100 2.20
Trench wall-Road side Cum 1 x 1 10.000 0.200 1.100 2.20 Total= 4.40 ₹ 10,055.00 44242.00
6 Mild Steel or Iron work in heavy sizes such as
trusses built up gates, door frames, record, racks roof work gates etc. wrought to required form including holes rivetting or welding where necessary and also fixing in Size Nos proper position and alignment including cost of all materials supplied by contractor. (CSI No. 9.01)
Ct Length Total LengtUnit Wt. Total Wt.
Opps.Road sideTrench wall Angle-Rack with cleat 50x50x5 3 18 1 0.450 24.300 4.500 109.35 Road sideTrench wall Angle-Rack with cleat 50x50x5 3 18 1 0.450 24.300 4.500 109.35 Total= 218.70 2.19 ₹ 7,434.10 16258.38 7 Fixing of cable trench racks in proper position and alignment including cost of all labour, material and T&Petc. required for proper completion of the work (Labour rate only). (CSI No. 9.33)
Racks No. 2 x 54 108.000
108.000 ₹ 8.00 ₹ 864.00 8 TMT/Tor steel in plain work such as reinforced concrete or reinforced brick work (when not included in an over all rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of steel its Size Nos. Ct Length 10Ø 12Ø 20Ø wastage, bend, hooks and authorized overlapping shall be measured. (Steel shall be arranged by the contractor) (CSI No. 9.03)
Cross 12Ø 1 10 20 0.450 90.000 Trench CoverFirst Net-Main 20Ø 1 4 20 1.550 124.000 Cross 12Ø 1 10 20 0.450 90.000 Hucks 10Ø 1 4 20 0.400 32.000 Total Length 32.000 180.000 248.000 Unit Wt. 0.617 0.889 2.469 Total Wt. 19.744 160.020 612.312 Total Wt.= 772.332 Kg 7.72 ₹ 7,412.00 57245.25 8 Precast cement concrete in trench cover and similar small work with cement approved coarse sand (F.M. 1.8 to 2.5) and 2 cm gauge graded approved hard stone ballast in the proportion 1:1.5:3, excluding reinforcement but including fixig the same in position including cost of all other material, labor and T&P . (CSI No. 5.22)
Trench Cover Cum 1 x 20 1.400 0.500 0.150 2.10
Total= 2.10 ₹ 8,274.00 17375.40 10 Champering the edge of concrete in auxiliary structure, of size 25 mm wide in triangular section including all materials, labour & T&P etc complete. (CSI No.11.18)
Trench Edge RM 1 x 2 10.000 20.000
20.000 ₹ 7.00 ₹ 140.00 11 Placing of trench cover of all size in proper position including transportation from different places within the S/S area including all labour, T&P etc. required for proper completion of the work as per direction of Engineer - in - charge. (CSI No.20.11)
Trench Cover No. 1 x 20 20.000
20.000 ₹ 7.00 ₹ 140.00 12 Painting or varnishing new iron work in small areas or new wood work with one coat of ready mixed priming paint and one coat of approved superior quality ready mix paint "Luxol" or equivalent brand or varnish including supply of all materials, labour and T&P etc. required for proper completion of the work. Paint to be used should conform to the I.S. 103-1950. (CSI No. 13.01+13.02)
Racks Sqm 2 x 18 0.300 0.200 2.120
2.120 ₹ 97.00 ₹ 205.64 Total= ₹ 2,22,688.78 Add 3 % contingency Charges= ₹ 6,680.66 Sub total= ₹ 2,29,369.45 Add 5.60 % Service Charges= ₹ 12,844.69 Sub total= ₹ 2,42,214.14 Add 1.00 % Labour Cess Charges= ₹ 2,422.14 Grand Total= ₹ 2,44,636.28 PER RUNNING METER COST= ₹ 24,463.60