You are on page 1of 10

Available online at www.sciencedirect.

com

International Journal of Project Management 31 (2013) 424 – 433


www.elsevier.com/locate/ijproman

Public private partnership projects in Singapore: Factors, critical risks and


preferred risk allocation from the perspective of contractors
Bon-Gang Hwang a , Xianbo Zhao a,⁎, Mindy Jiang Shu Gay b

a
Department of Building, National University of Singapore, 117566, Singapore
b
Shimizu Corporation (Incorporated in Japan), 079120, Singapore

Received 22 March 2012; received in revised form 1 August 2012; accepted 7 August 2012

Abstract

Public private partnership (PPP) procurement was introduced into Singapore in 2003, and 10 PPP projects were successfully completed and
have been in operation. This study aims to examine the critical success factors as well as the relative importance of positive and negative factors
influencing the attractiveness of PPP projects in Singapore, and to identify the critical risk factors and preferred risk allocations for PPP projects in
Singapore. The questionnaire survey results indicated that negative factors were more affirmative than the positive factors, and that 23 risk factors
had significant criticalities. Eight risks would be preferably allocated to the public sector while 19 risks could be assigned to the private sector.
11 risks were preferred to be shared by both parties and the allocation of four risks depended on project circumstances. The findings of this study
provide valuable information for organizations that intend to participate in PPP projects in Singapore.
© 2012 Elsevier Ltd. APM and IPMA. All rights reserved.

Keywords: Public private partnership; Critical success factors; Attractiveness; Risk criticality; Risk allocation

1. Introduction Board (PUB) for a desalination plant (Gunawansa, 2010). The


Ministry of Finance (MOF) published the PPP Handbook in
Public private partnership (PPP) has been widespread in 2004, which provides the public and private sectors with the
infrastructure development in Asia and considered as an effective guidelines for successful structuring and management of PPP
way to achieve better value for money in delivering infrastructure projects in Singapore. Subsequently, the government outsourced
projects (Ke et al., 2010; Li et al., 2005b). Some countries have projects worth S$1.3 billion (S$1 ≈ US$0.79) to the private
adopted PPP due to fiscal deficit, budgetary pressure, demand– sector for the next 3 to 5 years (Li, 2006). 10 PPP projects were
supply gap, and inefficient public services to infrastructure, while successfully completed and are in operation now, while three
other countries choose PPP for operational efficiency, innovative projects were terminated or on hold (Gunawansa, 2010; Weaver,
technological and management skills, and more active involve- 2010).
ment of private players in public services (Chowdhury et al., The nature of PPP projects makes risk an important factor in
2011). the project procurement. Most PPP projects are involved with
The concept of PPP was introduced to Singapore in 2003 risks that are difficult to control and analyze. Hence, risk
when the first PPP contract was awarded by the Public Utilities management is critical for both public and private parties in
PPP projects to attain their objectives. In addition, it is necessary
to balance the risks and rewards of public and private sectors in
PPP projects (Grimsey and Lewis, 2002). Appropriate risk
allocation was recognized as critical to successful PPP projects
⁎ Corresponding author. Tel.: +65 9345 2665; fax: + 65 6775 5502. (Chan et al., 2010; Zhang, 2005) and should be done at the
E-mail address: zhaoxb1984@gmail.com (X. Zhao). early stage of the projects. A commonly accepted principle is to
0263-7863/$36.00 © 2012 Elsevier Ltd. APM and IPMA. All rights reserved.
http://dx.doi.org/10.1016/j.ijproman.2012.08.003
B.-G. Hwang et al. / International Journal of Project Management 31 (2013) 424–433 425

allocate risks to the party best able to manage it at least cost examined the significance of five main CSFs for PPP projects
(EC, 2003). based on a worldwide questionnaire survey: favorable investment
The objectives of this study are (1) to examine the critical environment; economic viability; reliable concessionaire consor-
success factors (CSFs) as well as the relative importance of tium with strong technical strength; sound financial package; and
positive and negative factors that influence the attractiveness appropriate risk allocation via reliable contractual arrangements.
of PPP projects in Singapore; and (2) to identify the critical risk Li et al. (2005a) identified five groups of CSFs for PPP projects in
factors and preferred risk allocations in PPP projects in Singapore. the UK: effective procurement; project implementability; gov-
The findings of this study help both public and private sectors to ernment guarantee; favorable economic conditions; and available
better understand the important factors for PPP projects as well as financial market. Chan et al. (2010) explored five underlying
risk factors and their allocation, providing valuable information CSFs for PPP infrastructure projects in China: macroeconomic
for organizations that intend to participate in PPP projects in environment; shared responsibility between public and private
Singapore. sectors; transparent and efficient procurement process; stable
Following the introduction to this study, the second section political and social environment; and judicious government
provides the background information relating to PPP projects. control. These previous studies enabled this study to select
In the third section, research methodology and a profile of the 8 CSFs for PPP projects based on the context of Singapore. The
respondents are presented. Then, data concerning the CSFs for importance of these 8 CSFs is identified in this study, which
PPP projects, positive and negative factors for PPP projects, demonstrates the factors most critical to a successful PPP project
risk criticalities and risk allocation preferences are analyzed, in Singapore.
and the results are discussed in the fourth section. Finally, the
fifth section draws conclusions of this study and recommends 2.3. Positive and negative factors for PPP projects
further research.
There are positive and negative features that influence the
2. Background attractiveness of PPP in the delivery of public facilities and
services. Li et al. (2005c) summarized a list of positive and
2.1. Current status of PPP in Singapore negative factors for PPP projects via a comprehensive literature
review, and identified the relative importance of these factors
According to the MOF (2004), implementing PPPs in based on the perceptions of PPP project participants in the UK. Li
Singapore enables the public sector to get better value for money et al. (2005c) found that the four most important groups of positive
in delivering public services, provides the private sector with more factors were associated with better project technology and
business opportunities to innovate and offer efficient solutions for economy, greater benefit to the public, public sector avoidance
public services, and combines the expertise of the government and of regulatory and financial constraints, and public saving in
the private sector to meet the needs of the public effectively and transaction costs, while the three most important groups of
efficiently. Hence, all government infrastructure projects that are negative factors were related to the inexperience of the public
worth over S$50 million need to be considered for suitability as and private sectors, the over-commercialization of projects,
PPP projects. A number of sectors in Singapore have been and high participation cost and time for participants. Similarly,
identified by the MOF as suitable for PPPs. These include sports Cheung et al. (2010) explored the perceived importance of
facilities, incineration plants, water and sewerage treatment works, positive and negative factors for PPP projects using questionnaire
large IT infrastructure deals, education and healthcare facilities, surveys conducted in Hong Kong and Australia, respectively, and
expressways and government buildings. In addition, the govern- found that the attractive factors were more affirmative than the
ment ensures that the private sector can meet the public needs negative ones. Based on the previous studies, seven positive
effectively; there is clear accountability when services are delivered factors and seven negative factors were selected in accordance
by the private sector and the public knows who to approach for with the context of Singapore. The relative importance of the
service queries and feedback; public security, health and safety positive and negative factors is shown in this study, revealing
are not compromised in PPP projects; and confidentiality of the attractiveness of PPP projects to the public and private
information is observed. sectors in Singapore.

2.2. CSFs for PPP projects 2.4. Risk identification in PPP projects

CSFs have been widely used as a method to make explicit the Risk identification is a critical phase in a project risk
key areas that are necessary for management success (Boynton and management process. It is desirable to identify the risks as
Zmud, 1984). A number of previous studies have been conducted early as possible (Wang et al., 2004), and a simple but valid
to identify the CSFs for PPP projects. Qiao et al. (2001) identified method is the development of a risk checklist (Fang et al., 2004).
eight CSFs for build-operate-transfer (BOT) projects in China: As an integrative part of risk identification, risk categorization
appropriate project identification; stable political and economic structures the diverse risks that affect a project (Zou et al., 2007).
situation; attractive financial package; acceptable toll/tariff levels; Xu et al. (2010) and Ke et al. (2010) identified 37 risk factors
reasonable risk allocation; selection of suitable subcontractors; associated with China's PPP projects, and Ke et al. (2010)
management control; and technology transfer. Zhang (2005) categorized them into country, project and market risks. Based
426 B.-G. Hwang et al. / International Journal of Project Management 31 (2013) 424–433

on the comprehensive literature review and content analysis, Table 1


this study identified risks for PPP projects. Content analysis Risk identification in PPP projects.
can assist in classifying textual material, and reduce it to more Risk factors References Total
relevant and manageable bits of data (Weber, 1990). This method A B C D E F G H I J
is often adopted to determine the major facets of a set of data, by Lack of support from government * * * * * 5
simply counting how many times an activity occurs, or a topic is Unstable government * * 2
depicted (Fellows and Liu, 2003). In this study, risks identified in Strong political interference * * * * * * 6
each literature were first marked down, and then similar risks Corruption and bribery * * * * 4
Nationalization/expropriation * * * * * * 6
were assembled. Thus, a total of 42 risks were finally identified
Poor financial market * * 2
from the analyzed literature, as Table 1 shows. Inflation * * * * * * 6
In addition, Li et al. (2005b) proposed a three-level meta- Interest rate * * * * * * * 7
classification approach by considering the relationship between Lack of legal/regulatory framework * * * 3
risk factors and projects. Macro level risks have their origins Inconsistent legal/regulatory * * * * * * * 7
framework
beyond the system boundaries of projects; meso level risks occur
Change in tax regulation * * * * * 6 *
within the system boundaries of the project; and micro level risk Level of public opposition to project * * * * 5 *
factors are associated with the stakeholder relationships in the Environment * * 3 *
procurement process. This classification approach is adopted in Force majeure * * * * * 6 *
this study because it can provide a comprehensive overview of Weather * * 3 *
Geological conditions * * 3 *
risk factors in PPP projects.
Construction time delay * * * 5 * *
Site safety and security * * 2
Poor quality workmanship * 1
2.5. Risk allocation in PPP projects Construction cost overrun * * 2
Excessive contract variation * 1
Material availability * * * * * * 6
Risk allocation in PPP projects can be the primary measure of
Availability of finance * * * * * 5
assigning risks to project participants, i.e. public and private High finance cost * * 2
sectors. When both parties bear a certain risk together, there is a Financial attraction of project to * 1
shared risk allocation mechanism (Li et al., 2005b). Identifying investors
risk allocation preferences of the stakeholders prior to project Delay in approval and permits * * * * 4
Design deficiency * * * * 4
procurement and contract negotiation is important for confirming
Scope variation * * * 3
value-for-money for the public sector and revenue flows for the Unproven engineering techniques * * * * 4
private sector (Roumboutsos and Anagnostopoulos, 2008). Hence, Level of demand for project * * * * * * * * 8
a number of studies have been conducted to obtain risk-sharing Site availability * * * * 4
schemes in PPP projects in various regions. For example, Thomas Operation cost overrun * * * * * 5
Low operation productivity * 1
et al. (2003) investigated risk allocation in BOT road projects in
Maintenance cost higher than * 1
India, and found that the principle that the most capable party for expected
managing the risk should assume it was often not followed due to Maintenance more frequent than * 1
the difference in the perception of risk management capabilities expected
among project participants; Li et al. (2005b) explored the preferred Residual asset risk * * * 3
Inadequate experience in PPP * * 2
risk allocation in PPP projects in the UK via a questionnaire
Organizational and communication * * * * 4
survey, and found that some risk factors should be handled on a risk
case-by-case basis; Abednego and Ogunlana (2006) provided Inadequate distribution of * * * * 4
good project governance for proper risk allocation in PPP toll responsibilities
way projects in Indonesia using a case study of a toll way project; Inadequate distribution of authority * * 2
Lack of commitment of between * * 2
Ng and Loosemore (2007) identified the rationale behind
parties
decisions about risk allocations between public and private Differences in working method * 1
sectors by presenting a case study of a railway PPP project in
* Inclusion of the specific risk factor in the reference.
Sydney; Roumboutsos and Anagnostopoulos (2008) identified References: A = Kumaraswamy and Zhang (2001); B = Grimsey and Lewis
the risk allocation preferences of the stakeholders of the Greek (2002); C = Li et al. (2005b); D = Shen et al. (2006); E = Ng and Loosemore
PPP projects based on a questionnaire survey and compared the (2007); F = Estache et al. (2007); G = Medda (2007); H = Zou et al. (2008); I =
results with those in the UK. More recent studies focused on the Thomas et al. (2003); J = Xu et al. (2010).
risk allocations in PPP projects in China. Xu et al. (2010)
developed a fuzzy risk allocation model, while Ke et al. (2010) 3. Methodology and data presentation
explored the preferred risk allocation via a two-round Delphi
survey. However, little effort has been committed to research on A comprehensive literature review was conducted to establish a
risk allocation preferences in PPP projects in Singapore. This foundation for this study and to support the development of a
paper attempts to fill this knowledge gap based on the opinions of survey questionnaire. A pilot study was conducted with a couple of
the private contractors. project managers with PPP experience in PPP projects to validate
B.-G. Hwang et al. / International Journal of Project Management 31 (2013) 424–433 427

the questionnaire. The questionnaire consisted of three main Table 2


sections. The first section included questions meant to profile the Profile of respondents.
respondents and their companies. In the second section, the Respondent profiles Categorization N %
respondents were asked to rate the CSFs as well as positive and Registry grades of contractors A1 37 77.1%
negative factors for PPP projects in Singapore using a five-point A2 8 16.7%
Likert scale (1 = least important and 5 = most important). The B1 1 2.1%
B2 2 4.2%
third section investigated the risk criticality and risk allocation
Years of experience 0–5 5 10.4%
preferences within PPP projects in Singapore. A risk matrix was 6–10 17 35.4%
provided in order to make it easier for the respondents to rate 11–15 15 31.3%
the criticality of the risk factors which were identified from a 16–20 7 14.6%
comprehensive literature review. Since the evaluation of risk Above 20 4 8.3%
Job title Directors 4 8.3%
criticality is complex and vague qualitative linguistic terms are
Senior manager 3 6.3%
unavoidable (Wang et al., 2004), a five-degree rating system (1 = Project manager 25 52.1%
lowest; 2 = low; 3 = moderate; 4 = high; 5 = extreme) for the Quantity surveyor 12 25.0%
evaluation of risk criticality was adopted. Respondents were also Others 4 8.3%
asked to select a party to which each risk should be allocated.
The sampling frame used for this study was a list of the
contractors registered with the Building and Construction Author-
ity (BCA), which is an agency under the Ministry of National using a five-point Likert scale (1 = least important and 5 = most
Development in Singapore. As a probability sampling technique, important). The mean score ranking technique was used to rank
stratified sampling was adopted. The sample was stratified the CSFs for PPP projects. The perceived importance from the
according to contractors' grade, and consisted of 120 contractors respondents acted as scores used to calculate the mean score
with grades of A1, A2, B1 and B2 because they had higher tender for each factor. Then, the factors were ranked based on the
limits and resources to tender for PPP projects that involved mean score.
high capital costs. According to the BCA grading system, A1 The analysis revealed that practitioners recognized “well-
contractors enjoy no tendering limit. A2, B1, and B2 contractors organized public agency” as the most important CSF (mean =
can bid for projects worth up to S$85 million, S$40 million, and S 4.08) for PPP projects. This may imply that the public sector
$13 million, respectively. The target respondents included middle performing PPP projects should represent public interest (Li et
and top management, who assumed the responsibility of risk al., 2005a) and have adequate expertise and capacity to procure
management of projects. The data collection effort produced 48 PPP projects. “Appropriate risk allocation and sharing” was
completed questionnaires from 48 different contractors. The ranked second (mean = 4.02). Risks should be allocated to the
response rate was 40%, which was high compared with the party who are best able to manage it (EC, 2003). Hence, the
norm of 20–30% with most questionnaire surveys in the public sector should bear the risks out of the control of private
construction industry (Akintoye, 2000). participants and would transfer risks associated with asset
The mean score ranking technique was used to rank the procurement and service delivery to the private participants,
CSFs for PPP projects, positive and negative factors for PPP who are more experienced in managing them (Chan et al., 2010;
projects as well as risk factors. The perceived importance or the Zhang, 2005). In addition, appropriate risk allocation enables
risk criticalities from the respondents acted as scores used to contractors to be clear about their risk profile and reduces
calculate the mean score for each factor. As for the analysis of disputes during the project implementation stage. The third most
risk allocation preferences, the percentage of the respondents important CSF was “strong private consortium” (mean = 3.44),
who believed that a risk should be allocated to a party was which implied that the private consortium should be competent
analyzed. enough and financially capable of taking up the projects to ensure
A summarized profile of the contractors and respondents is successful PPP projects (Chan et al., 2010; Li et al., 2005a).
presented in Table 2. 77.1% of the respondents were from A1
contractors. 54.2% of them had more than 10 year experience in
the construction industry, and 66.7% held positions at middle and
top levels. Since all government infrastructure projects that are
Table 3
worth over S$50 million are actively considered for suitability of CSFs for PPP projects in Singapore.
adopting PPP procurement (MOF, 2004), large contractors (A1
CSFs Rank Mean Std.
and A2) would be more appropriate for PPP projects.
Well-organized public agency 1 4.08 1.33
Appropriate risk allocation and sharing 2 4.02 1.44
4. Data analysis and discussions
Strong private consortium 3 3.44 1.95
Transparency in procurement process 4 3.31 1.61
4.1. Importance of CSFs for PPP projects in Singapore Clear defined responsibilities and roles 5 3.19 1.55
Clarification of contract documents 6 3.06 1.57
As shown in Table 3, eight CSFs were presented in the Favorable legal framework 7 2.98 1.96
Shared authority between public and private sector 8 2.35 1.68
questionnaire. The respondents were asked to rate these CSFs
428 B.-G. Hwang et al. / International Journal of Project Management 31 (2013) 424–433

4.2. Importance of positive and negative factors for PPP projects There are also some factors that discourage contractors from
in Singapore participating in PPP projects. “Lengthy delays in negotiation”
was seen as the most important negative factor for PPP projects
As shown in Table 4, seven positive factors and seven in Singapore (mean = 4.92). This result confirmed that the
negative factors were presented in the questionnaire and rated consideration of “lengthy delays in negotiation” can be a typical
using a five-point Likert scale (1 = least important and 5 = most feature of PPP projects regardless of their geographical location.
important). The mean score ranking technique was also used to Previous studies also found this factor to be a highly ranked
rank the positive and negative factors for PPP projects. negative factor for PPP projects in the UK (Li et al., 2005c),
“Better value for money” was identified as the greatest positive Australia and Hong Kong (Cheung et al., 2010). Long PPP
factor (mean = 4.54). Value for money, which was defined as the procurement can be attributed to the large size and high complexity
optimum combination of whole life-cycle costs, risks, completion of PPP projects and the procedural requirements (Li et al., 2005c),
time and quality in order to meet public requirements (Grimsey and would discourage contractors from tendering for PPP projects
and Lewis, 2002), is an important consideration for the public in Singapore. “High participation costs” was ranked second
sector (Cheung et al., 2010). According to the MOF (2004), PPP (mean = 4.77). The complexity of PPP project requirements
projects enable public services to be delivered in a more value for increases participation costs for the private sectors. The costs
money way by making optimal use of the expertise of both the of tendering for Private Finance Initiative (PFI) projects were
public and private sectors, resources and innovation to meet public found much higher than that for traditional procurement
needs effectively and efficiently. The emphasis of the respondents systems (Birnie, 1999). Hence, “high participation costs” also
on value for money revealed that the contractors in Singapore significantly reduced the attractiveness of PPP projects for
recognized the purpose of adopting PPP procurement, and would contractors in Singapore. The third most important negative
like to benefit from participating in PPP projects. factor was “confusion on government objectives and criteria
“Improved risk profile” was ranked second (mean = 4.42), evaluations”. Conflicting objectives tend to result in confusion on
indicating that the risk profile of contractors could be improved the assessment criteria for both contractors and public partici-
by PPP procurement. This is probably because contractors pants, which makes participants operate inefficiently (Li et al.,
were clear about the risks that were allocated to them and can 2005c). Contractors in Singapore also regarded this negative
be better prepared for dealing with these risks. “Facilitated factor as a significant barrier to being engaged in PPP projects.
creative, innovative and cost-effective approaches” was per- Furthermore, “lack of experience or appropriate skills” had the
ceived as the third most important (mean = 4.29). This is also same mean score (mean = 4.56) as “confusion on government
supported by Akintoye et al. (2003) and Cheung et al. (2010) who objectives and criteria evaluations”. PPP projects are typically
argued that creativity and innovation had been viewed as an large-scale and complex. “Lack of experience or appropriate
important advantage that can be brought to public services by the skills” increases the likelihood of suffering losses and thus makes
private sector and can contribute to less costs and higher-level PPP projects less attractive to the private sector.
competitiveness of the private sector. Any cost-effective approach Comparison of the mean score between positive and negative
adopted by the private sector would lead to cost saving and factors can assess the suitability of adopting PPP projects (Cheung
increasing profit. Hence, contractors in Singapore would partici- et al., 2010). The mean score of all the negative factors (mean =
pate in PPP projects for competitive advantages and greater profits. 4.23) was higher than that of all the positive factors (mean= 3.91),
which may imply that the negative factors were more affirmative
than the positive factors and that PPP projects were not well
Table 4 accepted in the Singapore construction industry. Hence, efforts
Positive and negative factors for PPP projects in Singapore. should be made by the Singapore government to strengthen the
Factors Rank Mean Std. positive factors and weaken the negative factors.
The negative factors are also related to risk factors in PPP
Positive factors 3.91
Better value for money 1 4.54 1.32 projects. The following sections further discuss the criticality and
Improved risk profile 2 4.42 0.87 preferred allocation of risk factors in PPP projects in Singapore.
Facilitated creative, innovative and cost-effective 3 4.29 1.32
solutions
Improved quality and services 4 4.00 1.74
4.3. Criticalities of risk factors
Tap on private's expertise 5 3.50 1.53
Shared of total project cost 6 3.40 1.53
Optimal resource allocation 7 3.25 1.73 42 risk factors that had been identified through the literature
Negative factors 4.23 review performed for this study were presented in the question-
Lengthy delays in negotiation 1 4.92 0.28 naire. These risk factors were also categorized into three
High participation costs 2 4.77 0.59
meta-levels with reference to Li et al. (2005b): macro, meso
Confusion on government objectives and criteria 3 4.56 0.68
evaluation and micro levels. The respondents were asked to evaluate the
Lack of experience or appropriate skills 3 4.56 1.10 criticalities of the 42 risk factors using a five-point Likert scale
High project costs 5 4.13 1.14 (1 = lowest; 2 = low; 3 = moderate; 4 = high; 5 = extreme). The
High risk replying on private sector 6 3.71 1.30 criticalities were ranked based on their mean scores, as shown
Excessive restriction on participation 7 2.96 1.86
in Table 5.
B.-G. Hwang et al. / International Journal of Project Management 31 (2013) 424–433 429

The results of one-sample t-test (test value = 3; confidence introduced into Singapore has functioned largely as an entity to
level = 95%) indicated that 23 risk factors had significantly high promote PPP awareness, help draft relevant policy and provide
criticalities while nine risk factors had significantly low critical- guidance on PPP matters. However, a centralized agency within
ities in PPP projects in Singapore. The top five risk factors are the MOF or outside of the MOF to champion the cause of PPP is
discussed below. still required because it could act as the “one stop shop” between
As indicated in Table 5, “lack of support from government” public and private sector entities to facilitate PPPs (Gunawansa,
was assigned with the highest criticality (mean = 4.46), indicating 2010). Hence, just a PPP Handbook published by the MOF was
that the government support for PPP projects in Singapore was not viewed as an adequate support from the government, and that
perceived inadequate. This was probably due to the fact that the more efforts had to be made to ensure the government support for
Singapore government had sufficient funds to improve its social the PPP mechanism.
and other infrastructures (KPMG, 2007). The introduction of PPP “Availability of finance” was ranked second (mean = 4.25).
into Singapore is mainly focused on the need to achieve value for The private sector is not paid until the start of project operation.
money in the delivery of public services (MOF, 2004). Moreover, Unavailability of financial instrument, which leads to difficulty
the PPP Advisory Council that was established when PPP was in financing, would engender project termination and loss of
the funds invested. This factor was also ranked high in PPP
Table 5 projects based in Mainland China (Xu et al., 2010).
Criticalities of risk factors in PPP projects in Singapore. The third most critical risk factor was “construction time
Risk factors Level Rank Mean Std. p-Value delay” (mean = 4.21). Delay in construction can result in delay
Lack of support from government Macro 1 4.46 1.05 0.000 ⁎ in project completion, and thus postpone the start of operation.
Availability of finance Meso 2 4.25 1.08 0.018 ⁎ Hence, revenue gain is also postponed.
Construction time delay Meso 3 4.21 1.07 0.000 ⁎ “Inadequate experience in PPP” was ranked the fourth
Inadequate experience in PPP Micro 4 4.17 0.99 0.000 ⁎
(mean = 4.17), which implied that contractors in Singapore still
Unstable government Macro 5 4.15 1.30 0.000 ⁎
Lack of legal/regulatory framework Macro 6 4.13 1.02 0.000 ⁎ lacked experience in PPP arrangement even though 10 projects
Site safety and security Meso 7 4.08 1.32 0.000 ⁎ have been successfully completed since 2003. PPP projects are
Construction cost overrun Meso 8 4.08 1.50 0.000 ⁎ typically large-scale and complex, which makes the contractors
Organizational and communication risk Micro 9 4.06 1.26 0.000 ⁎ without adequate experience more likely to suffer losses.
Strong political interference Macro 10 4.04 1.32 0.000 ⁎
“Unstable government” was seen as the fifth most critical risk
Inflation Macro 11 3.98 1.28 0.000 ⁎
Interest rate Macro 12 3.85 1.24 0.000 ⁎ factor (mean = 4.15) in adopting PPP projects in Singapore. It is
Corruption and bribery Macro 13 3.79 1.41 0.000 ⁎ well-known that Singapore has enjoyed a long span of political
Inadequate distribution of Micro 14 3.77 1.40 0.000 ⁎ stability. However, given a long concession period involved in
responsibilities PPP projects, any change in government policies or the regime
Delay in approval and permits Meso 15 3.65 1.26 0.001 ⁎
can directly impose additional risks and increase cost.
Inconsistent legal/regulatory framework Macro 16 3.60 1.27 0.002 ⁎
Inadequate distribution of authority Micro 17 3.56 1.27 0.004 ⁎ By contrast, “residual asset risk”, “force majeure”, “weather”,
Lack of commitment of between parties Micro 18 3.54 1.27 0.005 ⁎ “maintenance more frequent than expected”, and “geological
Poor financial market Macro 19 3.42 1.18 0.000 ⁎ conditions” were the five least critical risk factors according to the
Differences in working method Micro 20 3.40 1.19 0.027 ⁎ respondents. The low rank of “residual assets risk” (mean = 2.48)
Excessive contract variation Meso 21 3.38 1.02 0.015 ⁎
is consistent with the study of Xu et al. (2010) in which the
Financial attraction of project to Meso 22 3.38 1.20 0.035 ⁎
investors “residual asset risk” was ranked bottom for PPP projects
Level of demand for project Meso 23 3.33 0.97 0.022 ⁎ performed in Mainland China. Moreover, it is not strange that
Operation cost overrun Meso 24 3.29 1.09 0.070 “force majeure” (mean = 2.46) and “weather” (mean = 2.42) were
Material availability Meso 25 3.28 1.18 0.119 perceived less critical because Singapore has experienced few
Low operation productivity Meso 26 3.23 1.13 0.168
natural disasters or severe weather conditions and is characterized
Nationalization/expropriation Macro 27 3.19 1.23 0.297
Design deficiency Meso 28 3.17 1.02 0.262 by politically steady, corruption free and investment friendly
Poor quality workmanship Meso 29 3.15 1.15 0.383 environments (Gunawansa, 2010; Peebles and Wilson, 2002).
Scope variation Meso 30 3.13 1.21 0.479 In addition, the low rank of “maintenance more frequent than
Change in tax regulation Macro 31 3.10 1.24 0.564 expected” (mean = 2.43) implied that maintenance frequency
High finance cost Meso 32 3.02 1.02 0.888
was under control in PPP projects. Furthermore, “geological
Unproven engineering techniques Meso 33 2.69 1.26 0.092
Level of public opposition to project Macro 34 2.54 1.17 0.009 ⁎ conditions”, which is a common risk factor in construction
Environment Meso 36 2.50 1.18 0.005 ⁎ projects, was ranked bottom by the respondents (mean = 2.23).
Site availability Macro 35 2.50 1.19 0.005 ⁎ This was probably because the geological conditions were
Maintenance cost higher than expected Meso 37 2.48 1.05 0.001 ⁎ favorable for the PPP projects that have been completed and in
Residual asset risk Meso 38 2.48 1.20 0.004 ⁎
operation in Singapore.
Force majeure Macro 39 2.46 1.32 0.007 ⁎
Weather Macro 40 2.42 1.22 0.002 ⁎
Maintenance more frequent than Meso 41 2.40 1.01 0.000 ⁎ 4.4. Risk allocation preferences
expected
Geological conditions Macro 42 2.23 1.20 0.000 ⁎ The respondents were asked to show their risk allocation
⁎ Significant at 95% level (two-tailed), test value = 3, degree of freedom = 47. preferences for the 42 risk factors. As indicated in Table 6, the
430 B.-G. Hwang et al. / International Journal of Project Management 31 (2013) 424–433

preferred risk allocation options are presented as percentages of government”, “strong political interference”, “nationalization/
total counts of participant responses. Four risk allocation categories expropriation”, “lack of support from government”, “change in
are identified: (1) risks to be allocated to the public sector; (2) risks tax regulation”, “inconsistent legal regulatory framework “, as
to be allocated to the private sector; (3) risks to be shared between well as “lack of legal/regulatory framework”. “Site availability”
the public and private sectors; and (4) risks to be negotiated was the only risk at the meso level.
based on project circumstances. The analysis is based on the The seven risks at the macro level are related to political and
majority opinion (N 50%). For example, if more than 50% of government policies. It is not surprising that the political risks
the respondents chose to allocate a risk factor to the public are preferred to be allocated to the public sector. Singapore has
sector, the risk allocation preference for this risk factor is enjoyed political stability for a long time, and has a well-knit
categorized as “allocated to the public sector”. This principle is legal framework that provides a sound architecture for efficient
also applied to the second and third categories. If none of the and corruption free public procurement (Gunawansa, 2010).
percentages are over 50%, the risk allocation should be dependent Hence, the public sector is able to better manage these risk
on the specific project circumstances. factors at low costs and ensure that PPP projects are in a
favorable environment for private sectors.
4.4.1. Risks to be allocated to the public sector The public sector should also retain the risk of site acquisition
As shown in Table 6, eight risks should be retained by the as it has higher authority to control the process of land acquisition.
public sector. Seven of them fell within the macro level: “unstable The Singapore Land Authority (SLA) has enacted the “Land

Table 6
Preferred risk allocation in PPP projects in Singapore.
Allocation Risk factors Level Public Private Shared
Public sector Unstable government Macro 73% 10% 17%
Nationalization/expropriation Macro 90% 9% 10%
Strong political interference Macro 73% 21% 6%
Lack of support from government Macro 67% 6% 27%
Change in tax regulation Macro 52% 34% 14%
Inconsistent legal regulatory framework Macro 75% 13% 13%
Lack of legal/regulatory framework Macro 52% 34% 14%
Site availability Meso 70% 10% 20%
Private sector Geological conditions Macro 0% 88% 12%
Weather Macro 0% 90% 10%
Environment Macro 9% 50% 41%
Poor financial market Macro 0% 83% 17%
Level of demand in project Meso 9% 50% 41%
Availability of finance Meso 14% 63% 23%
Financial attraction of project to investors Meso 5% 77% 18%
High finance cost Meso 2% 68% 30%
Design deficiency Meso 4% 86% 10%
Construction cost overrun Meso 0% 94% 6%
Construction time delay Meso 0% 100% 0%
Material availability Meso 0% 81% 19%
Poor quality workmanship Meso 0% 100% 0%
Site safety and security Meso 0% 100% 0%
Operation cost overrun Meso 0% 80% 20%
Low operation productivity Meso 0% 92% 8%
Maintenance cost higher than expected Meso 0% 100% 0%
Maintenance more frequent than expected Meso 0% 100% 0%
Organizational and communication risk Micro 0% 100% 0%
Shared Inflation Macro 34% 17% 51%
Interest rate Macro 34% 13% 53%
Force majeure Macro 0% 6% 94%
Corruption and bribery Macro 15% 12% 73%
Residual asset risk Meso 13% 34% 53%
Scope variation Meso 14% 34% 52%
Inadequate experience in PPP Micro 23% 14% 63%
Inadequate distribution of responsibilities Micro 4% 29% 67%
Inadequate distribution of authority Micro 13% 13% 75%
Differences in working method Micro 27% 23% 51%
Lack of commitment between parties Micro 13% 13% 75%
Negotiated based on specific circumstances Level of public opposition to project Macro 46% 42% 13%
Delay in approvals and permits Meso 30% 34% 37%
Unproven engineering techniques Meso 33% 33% 33%
Excessive contract variation Meso 30% 34% 37%
B.-G. Hwang et al. / International Journal of Project Management 31 (2013) 424–433 431

Acquisition Act” to provide the legal framework for private sectors Finally, “organizational and communication risk” was the
in order to ensure that acquisitions are properly justified through only micro-level risk that was assigned to the private sector.
close scrutiny. The rationale of this lies in the fact that this risk is related to the
daily operational requirements of the project and operational
4.4.2. Risks to be allocated to the private sector responsibility is taken by the private sector (Li et al., 2005b).
The survey results indicated that 19 risk factors (representing
45% of all the risk factors identified) were preferred to be 4.4.3. Risks to be shared
allocated to the private sector. The percentage can be used to 11 risks were preferably shared between the public and private
evaluate the extent to which the objective of risk transfer from the sectors. Four of them were macro-level risk factors. Macroeco-
public sector to the private sector is achieved. Li et al. (2005b) nomic risks such as “inflation” and “interest rate” should be
found that 70% of all the catalogued risks were allocated to the shared because both parties would not deal with it well alone (Ke
private sector in the UK, but Ke et al. (2010) found the percentage et al., 2010) and the government has the ability to influence the
to be only 27% in PPP projects in China. Hence, the analysis macroeconomic conditions. The results coincided with the findings
result at this study showed that the extent of transferring risks to of Grimsey and Lewis (2002) and Ke et al. (2010), but contrasted
the private sector was higher than that in China, but much lower with the results of Li et al. (2005b). In addition, “corruption and
than that in the UK. This may be because PPP procurement has bribery” was preferred to be shared between both parties, which
become relatively mature in the UK since the first PPP project implied that the private sector should also play a part in ensuring a
was launched in 1992. corruption free and transparent procurement process, even if the
Four macro-level risks, including “geological conditions”, Singapore government has been recognized to be free of corruption
“weather”, “environment”, and “poor financial market”, were (Gunawansa, 2010). Moreover, “force majeure” is an unforeseen
preferred to be transferred to the private sector. “Geological risk and was found to be shared in several previous studies (Arndt,
conditions”, “weather”, and “environment” are natural risks that 1998; Ke et al., 2010; Li et al., 2005b; Ng and Loosemore, 2007;
are crucial in construction stage and should be taken by the Roumboutsos and Anagnostopoulos, 2008) because it cannot be
private sector, which echoed the findings of Li et al. (2005b). handled well by any party alone.
The financial market should be investigated by the private The two meso-level risks to be shared were “residual asset
sector because it is closely associated with project financing. risk” and “scope variation”. “Residual asset risk” should be
Hence, the private sector should bear this risk. shared because the ability to operate the project transferred to the
14 meso-level risks within the project boundaries were public sector at the end of the concession period is concerned
preferably allocated to the private sector. Financial risks, including with not only the operation responsibility of the private sector but
“availability of finance”, “financial attraction of project to also the work of the public sector. In addition, “scope variation”
investors”, and “high finance cost” should be considered during may be resulted from the creativity and innovative solutions
the detailed feasibility study by the private consortium, who should proposed by the private sector and the requirements from the
provide public services efficiently. Hence, the private sector was public sector. Hence, it should be shared by both parties.
more experienced in dealing with project financing issues than The other remaining five micro-level risks to be shared
the public sector and should bear the financial risks. Similarly, were: “inadequate experience in PPP”, “inadequate distribu-
financial risks were also preferred to be assigned to the private tion of responsibilities”, “inadequate distribution of authority”,
sector in PPP projects in the UK (Li et al., 2005b), China (Ke et “lack of commitment between parties” and “differences in
al., 2010) and Greece (Roumboutsos and Anagnostopoulos, working method”. These risks were labeled as relationship
2008). risks by Li et al. (2005b) and can be caused by both parties in a
In addition, the private sector should be more familiar with PPP project. Hence, one party should rely on the other to
design and construction risks, including “design deficiency”, manage these risks.
“construction cost overrun”, “construction time delay”, “ma-
terial availability”, “poor quality workmanship” and “site 4.4.4. Risks to be negotiated
safety and security”. Hence, it is not surprising that they were Four risks, including “level of public opposition to project”,
preferably assigned to the private sector, which confirmed the “delay in approvals and permits”, “unproven engineering tech-
findings of several previous studies (Ke et al., 2010; Lam et al., niques” and “excessive contract variations”, were found to be
2007; Li et al., 2005b; Ng and Loosemore, 2007; Roumboutsos difficult to be clearly classified into the above three risk allocation
and Anagnostopoulos, 2008). preferences. Roumboutsos and Anagnostopoulos (2008) suggested
Unlike conventional project, the private sector is responsi- that these risks should be negotiated based on specific project
ble for PPP project operation and depends on the operation to circumstances.
obtain its revenue. Hence, operation risks, including “level of
demand in project”, “operation cost overrun”, “low operation 4.5. Limitations
productivity”, “maintenance cost higher than expected”, and
“maintenance more frequent than expected” should be borne This study involves some limitations. Low response rate
by the private sector, which was consistent with the findings of from the contractors with grades of B1 and B2 made the sample
Arndt (1998), Li et al. (2005b), Ke et al. (2010), as well as represent contractors of relatively large size, even if large
Roumboutsos and Anagnostopoulos (2008). contractors with grades of A1 and A2 would be more appropriate
432 B.-G. Hwang et al. / International Journal of Project Management 31 (2013) 424–433

for PPP projects. In addition, risk criticalities were evaluated based the public sector to the private sector was relatively low
on the experience and subjective judgments of the respondents. compared with that in the UK. These risks were mainly natural
Another limitation is that while 42 risk factors studied in this paper risks, financial risks, design and construction risks, as well as
were identified by caring out a comprehensive literature review operation risks. Moreover, 11 risks, which were difficult to be
(see Table 1), some biases might exist in the selection of the 42 handled well by only one party alone, fell within the shared risk
factors. Also, the eight CSFs, seven positive and seven negative category. Five of the 11 risks were associated with the relation-
factors that were selected from a preliminary set through the pilot ships between the parties of PPP projects. There were still four
study would not be exhaustive. Nonetheless, through this study, risks that can neither be allocated to a party nor shared by both
specific factors for PPP projects in Singapore have been identified. parties. Their allocation should be negotiated based on specific
Moreover, there are common and geographically specific factors project circumstances.
affecting PPP projects. This study confirms some common factors It should be noted that there are common and geographically
affecting PPP projects performed in other countries. However, the specific factors and risks affecting PPP projects no matter where
findings from this study may not be readily generalized due to these projects are performed. The implication of this study lies in
some specific aspects of the Singapore construction industry that identifying the CSFs, positive and negative factors, as well as the
may be different from the industries of other countries. Lastly, this risk criticalities and allocation preferences, which are geograph-
study only focused on the opinions of the contractors, and did not ically specific to the PPP projects in Singapore. Nonetheless, the
involve third parties such as financial banks, legal firms and implication of this study is not limited to Singapore because the
insurance companies who may have different views on the risk findings of this study provide valuable information for the
allocation in PPP projects. This may make the findings of this international organizations that intend to participate in PPP
study unable to be generalized to other stakeholders. projects to be performed in Singapore. Thus, this study also
contributes to the knowledge body on PPP procurement in the
5. Conclusions and recommendations broader global community.
Further research can be focused on case studies of successful
This study examined the CSFs as well as positive and negative PPP projects that were completed in Singapore. This is because
factors of PPP projects in Singapore and identified the critical such case studies can help both public and private sectors learn
risks and preferred risk allocation based on the inputs from lessons, strengthen the importance of positive factors and thus
construction companies in Singapore. increase the attractiveness of PPP procurement. Similar studies
The respondents perceived “well-organized public agency”, can also be conducted to discover the current status of PPP
“appropriate risk allocation and sharing” and “strong private procurement in other countries of ASEAN (Association of
consortium” as the top three CSFs for PPP projects. The relative Southeast Asian Nations).
importance of positive and negative factors that influence the
attractiveness of PPP projects was also identified. “Better value
for money”, “improved risk profile”, and “facilitated creative, References
innovative and cost-effective solutions” were the top three
Abednego, M.P., Ogunlana, S.O., 2006. Good project governance for proper
positive factors. “Lengthy delays in negotiation”, “high partici- risk allocation in public–private partnerships in Indonesia. International
pation costs”, “confusion on government objectives and criteria Journal of Project Management 24 (7), 622–634.
evaluation” and “lack of experience or appropriate skills” were Akintoye, A., 2000. Analysis of factors influencing project cost estimating
recognized as the top four negative factors for PPP projects in practice. Construction Management and Economics 18 (1), 77–89.
Akintoye, A., Beck, M., Hardcastle, C., 2003. Public–Private Partnerships:
Singapore. The survey results also indicated that the negative
Managing Risks and Opportunities. Blackwell Science, Oxford.
factors were more affirmative than the positive factors and that Arndt, R.H., 1998. Risk allocation in the Melbourne city link project. Journal of
PPP projects were not well accepted by contractors in Singapore. Structured Finance 4 (3), 11–24.
Hence, the Singapore government needs to take more measures to Birnie, J., 1999. Private finance initiative (PFI)—UK construction industry
promote PPP projects. response. Journal of Construction Procurement 5 (1), 5–14.
42 risk factors, which were identified from literature review, Boynton, A., Zmud, R., 1984. An assessment of critical success factors. Sloan
Management Review 25 (4), 17–27.
were ranked based on their criticalities, and 23 of them were Chan, A.P.C., Lam, P.T.I., Chan, D.W.M., Cheung, E., Ke, Y., 2010. Critical
found to have significantly high criticalities (mean scores) that success factors for PPPs in infrastructure developments: Chinese perspec-
ranged from 4.46 to 3.33. “Lack of support from government”, tive. Journal of Construction Engineering and Management 136 (5),
“availability of finance”, “construction time delay”, “inade- 484–494.
Cheung, E., Chan, A.P.C., Kajewski, S., 2010. Suitability of procuring large
quate experience in PPP”, and “unstable government” were the
public works by PPP in Hong Kong. Engineering Construction and
top five critical risk factors in PPP projects in Singapore. Architectural Management 17 (3), 292–308.
Risk allocation preferences were explored based on the Chowdhury, A.N., Chen, P.H., Tiong, R.L.K., 2011. Analysing the structure of
opinions of the contractors. Seven out of the 42 risks were public–private partnership projects using network theory. Construction
preferably allocated to the public sector. Six of the seven risks Management and Economics 29 (3), 247–260.
were concerned with political and government policies while EC, 2003. Guidelines for Successful Public–Private PartnershipRetrieved June
17, 2010, from European Commission.: http://www.pppcentrum.cz/res/
the remaining one was the availability of the project site. In data/000025.pdf.
addition, 19 risks were preferred to be assigned to the private Estache, A., Juan, E., Trujillo, L., 2007. Public–Private Partnerships in
sector, which implied that the extent of transferring risks from Transport. The World Bank.
B.-G. Hwang et al. / International Journal of Project Management 31 (2013) 424–433 433

Fang, D., Li, M., Fong, P., Shen, L., 2004. Risks in Chinese construction MOF, 2004. Public Private Partnership Handbook. Ministry of Finance,
market—Contractors' perspective. Journal of Construction Engineering and Singapore.
Management 130 (6), 853–861. Ng, A., Loosemore, M., 2007. Risk allocation in the private provision of public
Fellows, R., Liu, A., 2003. Research Methods for Construction, 2nd ed. infrastructure. International Journal of Project Management 25 (1), 66–76.
Blackwell Publishing, Oxford, UK. Peebles, G., Wilson, P., 2002. Economic Growth and Development in
Grimsey, D., Lewis, M.K., 2002. Evaluating the risks of public private Singapore: Past and Future. Edward Elgar, Cheltenham, UK.
partnerships for infrastructure projects. International Journal of Project Qiao, L., Wang, S.Q., Tiong, R.L.K., Chan, T.S., 2001. Framework for critical
Management 20 (2), 107–118. success factors of BOT projects in China. Journal of Structured Finance 7 (1),
Gunawansa, A., 2010. Is there a need for public private partnership projects in 53–61.
Singapore? Paper presented at the Proceedings of the Construction, Roumboutsos, A., Anagnostopoulos, K.P., 2008. Public–private partnership
Building and Real Estate Research Conference of the Royal Institution of projects in Greece: risk ranking and preferred risk allocation. Construction
Chartered Surveyors, Paris, France. Management and Economics 26 (7), 751–763.
Ke, Y., Wang, S.Q., Chan, A.P.C., Lam, P.T.I., 2010. Preferred risk allocation Shen, L.Y., Platten, A., Deng, X., 2006. Role of public private partnerships to
in China's public–private partnership (PPP) projects. International Journal manage risks in public sector projects in Hong Kong. International Journal
of Project Management 28 (5), 482–492. of Project Management 24 (7), 587–594.
KPMG, 2007. Building for Prosperity: Exploring the Prospects for Thomas, A.V., Kalidindi, S.N., Ananthanarayanan, K., 2003. Risk perception
Public Private Partnerships in Asia PacificRetrieved 20 August, 2010, analysis of BOT road project participants in India. Construction Manage-
from KPMG International: http://www.kpmg.com/CN/en/IssuesAndInsights/ ment and Economics 21 (4), 393–407.
ArticlesPublications/Documents/ppp_aspac_O_0703.pdf. Wang, S.Q., Dulaimi, M.F., Aguria, M.Y., 2004. Risk management framework
Kumaraswamy, M.M., Zhang, X., 2001. Governmental role in BOT-led for construction projects in developing countries. Construction Management
infrastructure development. International Journal of Project Management and Economics 22 (3), 237–252.
19 (4), 195–205. Weaver, H., 2010. PPPs in Singapore: The international PerspectiveRetrieved
Lam, K.C., Wang, D., Lee, P.T.K., Tsang, Y., 2007. Modelling risk allocation 12 July, 2010, from Ashurst: http://www.adb.org/Documents/India-PPP/
decision in construction contracts. International Journal of Project Singapore-Harvey-Weaver.pdf.
Management 25 (5), 485–493. Weber, R.P., 1990. Basic Content Analysis, 2nd ed. Sage, Newbury Park, CA.
Li, J., 2006. Overcoming Obstacles to PPP in SingaporeRetrieved 2 July, 2011, Xu, Y., Yeung, J.F.Y., Chan, A.P.C., Chan, D.W.M., Wang, S.Q., Ke, Y.,
from Asia Pacific FutureGov. : http://www.futuregov.asia/articles/2006/dec/ 2010. Developing a risk assessment model for PPP projects in China—a
12/overcoming-obstacles-ppp-singapore/. fuzzy synthetic evaluation approach. Automation in Construction 19 (7),
Li, B., Akintoye, A., Corresponding, P.J.E., Hardcastle, C., 2005a. Critical 929–943.
success factors for PPP/PFI projects in the UK construction industry. Zhang, X.Q., 2005. Critical success factors for public–private partnerships in
Construction Management and Economics 23 (5), 459–471. infrastructure development. Journal of Construction Engineering and
Li, B., Akintoye, A., Edwards, P., Hardcastle, C., 2005b. The allocation of risk Management 131 (1), 3–14.
in PPP/PFI construction projects in the UK. International Journal of Project Zou, P.X.W., Zhang, G., Wang, J., 2007. Understanding the key risks in
Management 23 (1), 25–35. construction projects in China. International Journal of Project Management
Li, B., Akintoye, A., Edwards, P.J., Hardcastle, C., 2005c. Perceptions of 25 (6), 601–614.
positive and negative factors influencing the attractiveness of PPP/PFI Zou, P.X.W., Wang, S., Fang, D., 2008. A life-cycle risk management
procurement for construction projects in the UK: findings from a framework for PPP infrastructure projects. Journal of Financial Manage-
questionnaire survey. Engineering Construction and Architectural Manage- ment of Property and Construction 13 (2), 123–142.
ment 12 (2), 125–148.
Medda, F., 2007. A game theory approach for the allocation of risks in transport
public private partnerships. International Journal of Project Management
25 (3), 213–218.

You might also like