PRESUPUESTO GENERAL

PROYECTO: CONSTRUCCION VIVIENDA UNIFAMILIAR FAMILIA ………………………………………..


Ubicacion: Yapacani B. ………………………………….
Moneda: Bolivianos
Fecha: 14/07/2015
PRECIO COSTO COSTO
ÍTEM DESCRIPCIÓN UND. CANTIDAD UNITARIO PARCIAL TOTAL
1 LIMPPIEZA DE TERRENO GLB 1.00 226.80 226.80
2 REPLANTEO M2 133.35 9.68 1,290.83
3 EXCAVACION PARA CIMIENTOS Y ZAPATAS M3 16.72 45.15 754.91
4 RELLENO Y COMPACTADO C/PROV. DE MATERIAL H 20-30CM M2 49.00 8.07 395.43
5 IMPERMEABILIZACION SOBRECIMIENTOS NYLON 200 M ML 86.00 19.69 1,693.34
6 MURO DE LAD. ADOBITO MORT. 1:4 E= 0.12 M M2 174.89 76.08 13,305.63
7 CORDON DE ACERA INCL. EXCAVACION ML 42.00 37.86 1,590.12
8 CARPETA DE HORMIGON POBRE E= 5 CM M2 5.76 36.24 208.74
9 HORMIGON ARMADO PARA ZAPATAS DOSIF. 1:2:3 M3 2.88 1,291.38 3,719.17
10 HORMIGON ARMADO PARA COLUMNAS DOSIF. 1:2:3 M3 0.12 3,943.59 473.23
11 CIMIENTO DE HºCº 60% PIEDRA DOSIF. 1:2:3 M3 15.96 496.96 7,931.48
12 HORMIGON ARMADO ENCADENADO INFERIOR DOSIF. 1:2:3 M3 3.59 2,830.17 10,160.31
13 HORMIGON ARMADO P/ENCADENADO SUPERIOR DOSIF. 1:2:3 M3 4.40 2,830.17 12,452.75
14 CUBIERTA DE CALAMINA CON EST. METALICA CELOSIA M2 226.20 270.23 61,126.03
15 CUBIERTA DE CALAMINA GALV. S/VIGA VISTA 2"X5" M2 19.34 190.49 3,684.08
16 REVOQUE FINO INTERIOR MORT. CEMENTO DOCIF. 1:4 M2 230.40 41.74 9,616.90
17 REVOQUE FINO EXTERIOR MORT. CEMENTO DOCIF. 1:4 C/SIKA1 M2 112.12 48.39 5,425.49
18 CONTRAPISO DE LADRILLO ADOBITO CALAFATEADO M2 164.00 68.51 11,235.64
19 CARPETA DE NIVELACION PARA DE 2-3 CM M2 164.00 40.07 6,571.48
20 PISO DE CERAMICA NACIONAL PI-4 M2 164.00 92.67 15,197.88
21 REVESTIMIENTO CERAMICO P/BAÑO 41X41 CM M2 14.28 94.56 1,350.32
22 REVESTIMIENTO CERAMICO P/COCINA 41X41 CM M2 31.61 94.56 2,989.04
23 ZOCALO DE CERAMICA ESMALTADA H= 10 CM ML 141.43 18.29 2,586.75
24 DOTACION Y COLOCADO DE VENTANAS ALUM. LINEA-25 ESP 8MM INCO M2 32.00 661.53 21,168.96
25 DOTACION Y COLOCADO DE MESON DE GRANITO CHIQUITANO ML 5.60 946.59 5,300.90
26 CIELO FALSO PLACA DE YESO ESP. 9 CM. M2 167.73 120.96 20,288.62
27 ESTUCADO BAJO VIGA VISTA M2 19.34 62.60 1,210.68
28 PINTURA LATEX CIELO FAZO M2 167.73 16.49 2,765.87
29 PINTURA LATEX SOBRE ESTUCADO VIGA VISTA M2 19.34 16.49 318.92
30 VIGAS DE MADERA DE 2X5 PROV. Y COLOCADO L=1.3 ML 12.00 92.27 1,107.24
31 PINTURA LATEX DE MURO INTERIOR M2 130.40 15.23 1,985.99
32 PINTURA LATEX DE MURO EXTERIOR M2 112.12 14.75 1,653.77
33 DOTACION Y COLOCADO DE MARCOS P/PUETAS 2"X6" TAJIBO ML 19.50 78.65 1,533.68
34 DOTACION Y COLOCADO DE PUERTA TABLERO TAJIBO M2 19.50 399.95 7,799.03
35 PINTURA AL OLEO MATE PARA MARCOS DE PUERTA ML 19.50 11.34 221.13
36 PINTURA AL OLEO MATE PARA MADERAMEN HOJAS DE PUERTA M2 27.67 27.10 749.86
37 DOTACION Y COLOCADO DE CHAPAS PAPAIZ PZA 5.00 418.25 2,091.25
38 DOTACION Y COLOCADO DE CHAPAS PAPAIZ BAÑOS PZA 1.00 328.25 328.25
39 DINTEL DE LADRILLO ARMADO 3X1/2" ML 11.68 75.50 881.84
40 JUEGO BAÑO CALIPSO PROV. E INSTALACION JGO 1.00 2,783.76 2,783.76
41 JUEGO DE ACCESORIOS DE BAÑO PROV. E INSTALACION JGO 1.00 140.55 140.55
42 LLAVE DE PASO 3/4" PZA 3.00 122.26 366.78
43 PUNTO SANITARIO PVC 4" PTO 1.00 104.80 104.80
44 PUNTO SANITARIO PVC 2" PTO 4.00 92.40 369.60
45 CAJA SIFONADA PVCØ4" C/REJILLA ALUMINIO PTO 2.00 106.32 212.64
46 TENDIDO TUBERIA PVCØ2" S-R ML 12.00 16.88 202.56
47 TENDIDO TUBERIA PVCØ4" S-R ML 23.00 20.65 474.95
48 TENDIDO DE TUBERIA PVC Ø4" C-6 PLUVIAL ML 12.00 19.80 237.60
49 TENDIDO DE CAÑERIA DE PVC 3/4'' (HIDRO) ML 31.00 45.18 1,400.58
50 LAVARROPA DE CEMENTO PZA 0.00 842.40 0.00
51 LAVAPLATOS 2 BACHAS DE ACERO INOX PZA 0.00 536.56 0.00
52 CAMARA DE INSPECCION 60 X 60 CM PZA 0.00 421.60 0.00
53 PROV. Y COL. DE GRIFERIA PARA LAVAPLATOS AGUA CAL. PZA 0.00 267.00 0.00
54 GRIFERIA PARA LAVARROPA PZA 0.00 107.00 0.00
55 CAJA DE DISTRIBUCION 2 CIRCUITOS C/TERMICOS PZA 1.00 371.90 371.90
56 INSTALACION ELECTRICA PARA ILUMINACION PTO 10.00 206.60 2,066.00
57 TOMACORRIENTE DOBLE 15A PTO 18.00 231.40 4,165.20
58 TOMACORRIENTE ATERRADA PTO 1.00 238.05 238.05
59 PUNTO DE TELEFONO PTO 3.00 325.75 977.25
60 PUNTO DE VENTILACION EN BAñOS PTO 1.00 125.70 125.70
COSTO TOTAL DEL PROYECTO 257,630.26
PRESUPUESTO GENERAL
PROYECTO: CONSTRUCCION VIVIENDA UNIFAMILIAR FAMILIA ………………………………………..
Ubicacion: Yapacani B. ………………………………….
Moneda: Bolivianos
Fecha: 14/07/2015
PRECIO COSTO COSTO
ÍTEM DESCRIPCIÓN UND. CANTIDAD UNITARIO PARCIAL TOTAL
1 LIMPPIEZA DE TERRENO GLB 1.00 226.80 226.80
2 REPLANTEO M2 133.35 9.68 1,290.83
3 EXCAVACION PARA CIMIENTOS Y ZAPATAS M3 16.72 45.15 754.91
4 RELLENO Y COMPACTADO C/PROV. DE MATERIAL H 20-30CM M2 49.00 8.07 395.43
5 IMPERMEABILIZACION SOBRECIMIENTOS NYLON 200 M ML 86.00 19.69 1,693.34
6 MURO DE LAD. ADOBITO MORT. 1:4 E= 0.12 M M2 174.89 76.08 13,305.63
7 CORDON DE ACERA INCL. EXCAVACION ML 42.00 37.86 1,590.12
8 CARPETA DE HORMIGON POBRE E= 5 CM M2 5.76 36.24 208.74
9 HORMIGON ARMADO PARA ZAPATAS DOSIF. 1:2:3 M3 2.88 1,291.38 3,719.17
10 HORMIGON ARMADO PARA COLUMNAS DOSIF. 1:2:3 M3 0.12 3,943.59 473.23
11 CIMIENTO DE HºCº 60% PIEDRA DOSIF. 1:2:3 M3 15.96 496.96 7,931.48
12 HORMIGON ARMADO ENCADENADO INFERIOR DOSIF. 1:2:3 M3 3.59 2,830.17 10,160.31
13 HORMIGON ARMADO P/ENCADENADO SUPERIOR DOSIF. 1:2:3 M3 4.40 2,830.17 12,452.75
14 CUBIERTA DE TEJA CERAMICA INCL. ESTR. MET. CELOSIA+OMEGAS M2 226.20 321.09 72,630.56
15 CUBIERTA TEJA CERAMICA S/ VIGA VISTA DE 2"X6" M2 19.34 236.69 4,577.58
16 REVOQUE FINO INTERIOR MORT. CEMENTO DOCIF. 1:4 M2 230.40 41.74 9,616.90
17 REVOQUE FINO EXTERIOR MORT. CEMENTO DOCIF. 1:4 C/SIKA1 M2 112.12 48.39 5,425.49
18 CONTRAPISO DE LADRILLO ADOBITO CALAFATEADO M2 164.00 68.51 11,235.64
19 CARPETA DE NIVELACION PARA DE 2-3 CM M2 164.00 40.07 6,571.48
20 PISO DE CERAMICA NACIONAL PI-4 M2 164.00 92.67 15,197.88
21 REVESTIMIENTO CERAMICO P/BAÑO 41X41 CM M2 14.28 94.56 1,350.32
22 REVESTIMIENTO CERAMICO P/COCINA 41X41 CM M2 31.61 94.56 2,989.04
23 ZOCALO DE CERAMICA ESMALTADA H= 10 CM ML 141.43 18.29 2,586.75
24 DOTACION Y COLOCADO DE VENTANAS ALUM. LINEA-25 ESP 8MM INCOLM2 32.00 661.53 21,168.96
25 DOTACION Y COLOCADO DE MESON DE GRANITO CHIQUITANO ML 5.60 946.59 5,300.90
26 CIELO FALSO PLACA DE YESO ESP. 9 CM. M2 167.73 120.96 20,288.62
27 ESTUCADO BAJO VIGA VISTA M2 19.34 62.60 1,210.68
28 PINTURA LATEX CIELO FAZO M2 167.73 16.49 2,765.87
29 PINTURA LATEX SOBRE ESTUCADO VIGA VISTA M2 19.34 16.49 318.92
30 VIGAS DE MADERA DE 2X5 PROV. Y COLOCADO L=1.3 ML 12.00 92.27 1,107.24
31 PINTURA LATEX DE MURO INTERIOR M2 130.40 15.23 1,985.99
32 PINTURA LATEX DE MURO EXTERIOR M2 112.12 14.75 1,653.77
33 DOTACION Y COLOCADO DE MARCOS P/PUETAS 2"X6" TAJIBO ML 19.50 78.65 1,533.68
34 DOTACION Y COLOCADO DE PUERTA TABLERO TAJIBO M2 19.50 399.95 7,799.03
35 PINTURA AL OLEO MATE PARA MARCOS DE PUERTA ML 19.50 11.34 221.13
36 PINTURA AL OLEO MATE PARA MADERAMEN HOJAS DE PUERTA M2 27.67 27.10 749.86
37 DOTACION Y COLOCADO DE CHAPAS PAPAIZ PZA 5.00 418.25 2,091.25
38 DOTACION Y COLOCADO DE CHAPAS PAPAIZ BAÑOS PZA 1.00 328.25 328.25
39 DINTEL DE LADRILLO ARMADO 3X1/2" ML 11.68 75.50 881.84
40 JUEGO BAÑO CALIPSO PROV. E INSTALACION JGO 1.00 2,783.76 2,783.76
41 JUEGO DE ACCESORIOS DE BAÑO PROV. E INSTALACION JGO 1.00 140.55 140.55
42 LLAVE DE PASO 3/4" PZA 3.00 122.26 366.78
43 PUNTO SANITARIO PVC 4" PTO 1.00 104.80 104.80
44 PUNTO SANITARIO PVC 2" PTO 4.00 92.40 369.60
45 CAJA SIFONADA PVCØ4" C/REJILLA ALUMINIO PTO 2.00 106.32 212.64
46 TENDIDO TUBERIA PVCØ2" S-R ML 12.00 16.88 202.56
47 TENDIDO TUBERIA PVCØ4" S-R ML 23.00 20.65 474.95
48 TENDIDO DE TUBERIA PVC Ø4" C-6 PLUVIAL ML 12.00 19.80 237.60
49 TENDIDO DE CAÑERIA DE PVC 3/4'' (HIDRO) ML 31.00 45.18 1,400.58
50 LAVARROPA DE CEMENTO PZA 0.00 842.40 0.00
51 LAVAPLATOS 2 BACHAS DE ACERO INOX PZA 0.00 536.56 0.00
52 CAMARA DE INSPECCION 60 X 60 CM PZA 0.00 421.60 0.00
53 PROV. Y COL. DE GRIFERIA PARA LAVAPLATOS AGUA CAL. PZA 0.00 267.00 0.00
54 GRIFERIA PARA LAVARROPA PZA 0.00 107.00 0.00
55 CAJA DE DISTRIBUCION 2 CIRCUITOS C/TERMICOS PZA 1.00 371.90 371.90
56 INSTALACION ELECTRICA PARA ILUMINACION PTO 10.00 206.60 2,066.00
57 TOMACORRIENTE DOBLE 15A PTO 18.00 231.40 4,165.20
58 TOMACORRIENTE ATERRADA PTO 1.00 238.05 238.05
59 PUNTO DE TELEFONO PTO 3.00 325.75 977.25
60 PUNTO DE VENTILACION EN BAñOS PTO 1.00 125.70 125.70
COSTO TOTAL DEL PROYECTO 270,028.29
PLANILLA DE PRESUPUESTO GENERAL DE CONSTRUCCION EN SECO

DATOS DEL CLIENTE Nombre: Arq.Elizabeth Maizman Molina


Nombre: ROLY ALBA PEREZ Poblacion: Yapacani- Santa Cruz
Poblacion: Yapacani Direccion: Av Epifanio Rios No. 0215 esq.Florida
Direccion: Reg. Nacional: 6239
Lote: Telf. Fijo: 0933-6614 Telef. Cel. 78450605

Modalidad: OBRA VENDIDA Fecha de Presupuesto: 25 de febrero 2018


Area Construida: Validez : 20 dias habiles
No. De Presupuesto: 12/2018

PLANTA BAJA, ALTA Unidad Cantidad Precio TOTAL


CIELO FALSO PLACA DE PVC BRASILERO M2 184.06 165.00 30369.9
CIELO FALSO PLACA DE YESO ESP. 9 mm placa blanca M2 51.58 115.00 5931.7
CIELO FALSO PLACA DE YESO ESP. 9 mm placa Verde (Cocina) M2 27.07 160.00 4331.2
CENEFA BORDE CURVO ML 51.02 110.00 5612.2
CENEFA BORDE RECTO (Placa Verde) ML 19.95 140.00 2793
49038.0

COSTO TOTAL DE LA OBRA BS 49038.00


Son cuarenta nueve mil treinta ocho con 90/100 Bs. $US 7106.96
PLANTA ALTA
CIELO FALSO PVC ARGENTINO M2 100.75 225.00 22668.75
CIELO FALSO PLACA DE YESO ESP. 9 mm placa verde (Contra humedad) M2 3.26 180.00 586.8

23255.55

Contratista Contratante

PROPUESTA 2
PLANTA ALTA
CIELO FALSO PVC BRASILERO M2 100.75 185.00 18638.75
CIELO FALSO PLACA DE YESO ESP. 9 mm placa verde (Contra humedad) M2 3.26 180.00 586.8

19225.55

Contratista Contratante
587 Saldo

69.00
23.00

46.00

25
14
6
45
7061.96