SOLAR PV – DIESEL HYBRID

Win-win business models and PPA arrangement


1.
What is a solar PV – Diesel
Hybrid system
How does it work?
Basic Components
Hybrid System in a Grid Network
G GRID FOLLOWER

L
L
L
G
GRID FORMING - G GRID FOLLOWER
MASTER

H GRID FOLLOWER

H Hybrid Power Plant


L
L G Generator – any type
L
L Load – Substation/Feeder
Topologies of Hybrid Systems
Five major categories (*):
1. Single fixed master – converter
2. Single fixed master – synchronous generator
3. Single changing master
4. Multi-master synchronous generator dominated
5. Multi-master converter dominated

(Based on : IEA Photovoltaic Power Systems Programme (PVPS) Task 11)


* http://www.iea-pvps.org/index.php?id=227&eID=dam_frontend_push&docID=1127
Topologies of Hybrid Systems
Single fixed master – inverter

• One grid forming converter-based


generator

• Typically a battery innverter

• Mostly for small systems that


combine solar PV and/or wind with
battery storage

• Diesel genset as backup only

• Small grid (kw size) up to ~ 1MW


Topologies of Hybrid Systems
Single fixed master – generator

• One grid forming synchronous generator

• Typically a rotating generator (diesel/gas


genset or biogas generator)

• Other generators are grid following

• Generators can be distributed or in a


single location

• Any size, but larger than ~25MW may be


more efficient with other technologies
other than diesel genset
Topologies of Hybrid Systems
Single changing master

• Two or more generators are


assigned as grid formers

• Only one is the master at any time

• Only one grid forming generator

• Both energy storage and a


synchronous generator are present

• Synchronous generator can be


turned off, but when on it is the grid
forming
Topologies of Hybrid Systems
Single changing master - variant

• DC couple variant

• Automatic transfer switch controls


whether the inverter or the
synchronous generator is the grid
forming

• Flexible operating modes


Topologies of Hybrid Systems
Multi-master synchronous
generator dominant

• Two or more synchronous


generators are assigned as grid
formers and operate in parallel

• Energy storage is used at higher


intermittent penetration in grid
following mode (e.g. for grid
frequency support)

• Minigrid size or larger


Topologies of Hybrid Systems
Multi-master inverter dominated

• Two or more inverters are assigned


as grid formers and operate in
parallel

• System is inertia-less or has very


low inertia.

• Most advanced topology, not yet in


common use

• Any mix of generation technologies


can be applied
Types of Solar PV – Diesel Hybrid
Systems

Typical system

Solar PV Storage

Diesel Genset Controller


The Goal – Minimizing LCOE
2.
SIZING THE SYSTEM
What size is the hybrid system
Which Size?
Is it the installed/available Is it the installed solar PV
diesel generator size? system size?

What if there is battery Which solar PV system size:


inverter installed? - Installed grid inverter AC
capacity?
- Installed total solar PV
panel capacity?
- Installed battery inverter
AC capacity?
Which Size?
Is it the installed/available Is it the total generation
dispatchable power? capacity?

Combination of battery Include all possible


inverter and solar PV? generation such as grid
inverter, battery inverter,
What if there is only limited synchronous generator?
battery capacity (stabilizing
only : ~15 to 60 minutes)?

Does the PPA contract cover


dispatchability and how to
calculate the project
revenues?
How was it designed?
Load profile matching Penetration ratio

Was load profile carefully Or was it designed based on


considered? the penetration ratio to the
existing diesel generation?
Was the system designed to
reduce fuel costs by sizing
the generators to the load?

Does it consider project


revenues from the solar sales
and maximizes solar power
utilization?
Penetration Ratio of VRE Generation
Energy Penetration (%) Capacity Penetration (%)

Ratio of annual VRE Installed capacity of VRE as a


generation energy to annual percentage of total installed
total energy demand on the generation.
grid (excludes any net
exports) gives a relative measure of
the VRE power plant to the
rest of the system

DOES NOT capture the


capacity factor or
operational penetration
levels.
Penetration Ratio of VRE Generation
Maximum instantaneous Söder Metric
penetration (%)
The ratio of maximum solar
Ratio of maximum observed output (installed inverter
VRE power plant energy to capacity) to minimum
demand (including exports) demand plus maximum
over a defined period export.
(typically one year) at any
instant in time (typically on In an isolated grid, there is
an hour/ half hourly no possibility of export
intervals).

Captures observed values,


rather than theoretical
Why is it important?
Legal classification Reference and comparisons

Foreign investment How do we compare the


allowance various hybrid systems when
often the size mentioned is
Permit requirements based on different
measurements
Project financing
Investment, LCOE and cost
Taxes and other benefits savings references are not
comparable
Recommendation
Installed synchronous generator size / inverter output (net AC output)

Shows the ratio of available synchronous generator compared to the inverter


output of the power plant
3.
BUSINESS MODELS
Win-Win Solution
Risks
Whose responsibility?
Types of Risk

Diesel Fuel Costs Variability of Grid Availability


Solar Input
Diesel fuel cost is Grid availability
unpredictable in the Solar and Wind are (network or generator
open market and can be Variable Renewable issues) can be a
difficult to project Energy (VRE) sources. problem for project
The design of the developers and out of
In today’s Indonesian system determines how their control
situation, the to mitigate this risk
government through PLN should cover this
PLN should cover this The project should risk since they’re fully
risk cover this risk in the responsible for the grid
PPA requiring a certain operation in Indonesia
ramp up/down rate
requirement with
penalties IF there are
other generators on the
grid
Types of Risk

Power Curtailment Future Growth


Due to grid stability, solar PV Sizing for future growth in an
systems can be curtailed isolated grid is important for grid
significantly performance

Even with hybrid systems, Who bears the cost of oversizing the
curtailment can still happen if the system for future growth?
generators are not sized properly
What happens when additional
Excess solar PV power has power plants are added that are not
nowhere to go in smaller isolated compatible with the previous
grids penetration ratio of VRE power
plants (such as solar) ?
Example of Curtailment
Example of curtailment including future proofing risk
PPA Arrangements
Finding the right match between PLN’s needs in
isolated grids and the available technologies
ESCO Model
Shared savings Most of the risks are on
Project developer MUST be the project owner
allowed to design the system If allowed, the project is
to the load profile responsible for all generation
in the grid
Initial design prioritizes cost
savings from total If the system does not
generation expenditure perform as expected, the
project owner loses money
Total control of all from the projected income
generation preferred
Grid stability is protected
since dispatchable
synchronous generation is
always available (no savings)
Combined Revenue Model
Follows current processes Most of the risks are on the project
Solar PV energy sales follow owner
MEMR regulations (currently System designed for prioritizing solar PV
MEMR regulation 50/2017) energy sale

Synchronous generation is Synchronous generation only available for


rented from the project smoothing and stabilizing the solar input
and spinning reserve
Fuel costs are passed
through to PLN Grid stability protected because the
project controls its own spinning reserve
as defined in the PPA contract

Optional : synchronous generation


available for various level of dispatchability
Dispatchable Hybrid System
Follows current processes Most of the risks are on the project
Solar PV energy sales follow owner
MEMR regulations (currently System designed for dispatchability of the
MEMR regulation 50/2017) power plant according to PLN grid’s needs

Synchronous generation is Synchronous generation available at any


rented from the project time for dispatching and load following

Fuel costs are passed Grid stability protected because the


through to PLN project controls its own spinning reserve
as defined in the PPA contract

PPA contract controls ramp up/down rate


with penalties IF there are other
generators on the grid
5.
FINAL THOUGHTS
Putting it all together
The Business of Hybrids
Win-win solution

Sizing to the demand Grid analysis Revenue and risk sharing


Load profile need to be What is the hosting Identifying PLN’s limitations
known and sizing as well as capacity of the grid for and the grid’s conditions is
design of the hybrid power Variable Renewable Energy a key step in developing
plant needs to be matched. generation? What are the the right business model.
PPA agreement need to issues limiting this The final agreement needs
reflect this capacity? How can hybrid to reflect that the project
systems solve this limit? solves relevant grid issues

Alignment of interests
Project developer need enough revenues to
cover their costs whereas PLN is limited in its
capacity to pay PPAs even from renewable
energy. If the business model and the design
of the agreement can reflect this alignment, it
creates a mutually beneficial framework.

Example : PPAs need to include ramp up/down


rate and its costs to PLN can be discounted
when transferred to the developer
Thanks!