You are on page 1of 152

Global Organization

BOOK No 11
Innovative
Solutions
Version 0
Product &
Substation System
Business Business

Power Systems
for Industry

BA THS / BU Transmission Systems and Substations

LEC Support Programme


Suggestions for improvement of this book
as well as questions shall be addressed to:

BU TS / Global LEC Support Programme


C/o ABB Switchgear AB
SE-721 58 Västerås
Sweden

Telephone + 46 21 32 80 00
Telefax + 46 21 32 80 13
Telex 40490 abbsub s

Copyright  BU Transmission Systems and Substations

2 BA THS / BU Transmission Systems and Substations LEC Support Programme


Power Systems
for Industry
Welcome to the handbook "Power Sys-
tems for Industry". It is an extract from the
ABB Industrial Manual, published by the
Automation Segment in Sweden. This
extract includes the Industrial Power Sys-
tems part.
The reprint has been made by courtesy
of the A - segment in Sweden in order to
increase the mutual understanding be-
tween the two segments.
We hope you will find the booklet useful
in your work.
The authors welcome any idea you may
have to improve the quality of this booklet
as well as the other ones.

Best of luck!

BA THS / BU Transmission Systems and Substations LEC Support Programme


BA THS / BU Transmission Systems and Substations LEC Support Programme
INDUSTRIAL POWER SYSTEM
Industrial Power system (IPS) Design - an Overall Approach

INDUSTRIAL POWER SYSTEMS


Contents
page
1 Industrial Power System (IPS) Design - an Overall Approach 1
2 Low Voltage Distribution 12
3 Medium Voltage Distribution 57
4 Transformers 68
5 High Voltage Switchgear 77
6 Fault Control 90
7 Industrial Power System Control 104
8 Industrial Cogeneration of Power and Heat 114
9 Standby and Uninterrubted Power Supply (UPS) 126
10 Prefabricated and Mobile Substations 139
11 Bibliography 147

INDUSTRIAL POWER SYSTEM (IPS)


DESIGN - AN OVERALL APPROACH

Contents
page
1 General 1
2 Safety 3

General
The electrical power system of an industrial supply being ”only” a support function - be-
plant represents only 5-10 % of the total capital comes a “necessary evil”. However, it is the
investment. This is perhaps the main reason responsibility of the IPS designer to communi-
why it is sometimes difficult for the IPS electri- cate the fact that the manufacturing function or
cal design engineer to convince project man- process will not be more reliable than the elec-
agement that an economical and reliable power trical system supplying power to it.
system requires a great deal of careful analysis The conceptual design phase is often the
and planning, perhaps more than for some of most crucial in the chain of events leading to a
the more expensive parts of the project. The new, expanded, or modernised electrical power
manufacturing process is always of primary system, as well as of a co-generation project.
concern to project management, and electrical Conceptual design studies produce the criteria

5.1 1 97-03-05, 13.14


INDUSTRIAL POWER SYSTEM
Industrial Power system (IPS) Design - an Overall Approach

for the best single line architecture, the best IPS conceptual design studies. There are - with
voltage levels, the most efficient system earth- few exceptions - no college courses or engi-
ing and optimal fault protection consistent with neering handbooks to help guide interested
long-range safety, reliability, flexibility, engineers in such assignments.
maintainability and lowest lifetime costs. Fig. 1 suggests a procedure for IPS design
The achievement of a sound IPS design helps execution. In the absence of applicable litera-
assure a “first-time quality” system, while avoid- ture, course curriculum or training courses, this
ing the agony of failure that costly corrections procedure is offered as a basic framework for
of unforeseen flaws might otherwise require. conducting and evaluating or assisting in audits
There are no international industry stand- of IPS design.
ards, guidelines, or customer specifications for

Plant Layout Safety


Initial conditions Power company supply Simplicity
Production Capacity Maintainabily
Flexibility
Reliability
Economy
LOAD AND SUPPLY
PLANNING

SELECTING SELECTING SHORT CIRCUIT


VOLTAGES SYSTEM NETWORK AND DYNAMIC ANALYSIS

CALCULATE VOLTAGE
VARIATIONS

SELECT SYSTEM
EARTHING

SELECT SURGE
PROTECTION

RELAY PROTECTION
AND SELECTIVITY

POWER FACTOR Fig 1 Conceptual Design


CORRECTION of an Industrial Power
Specification and procurement System

5.1 2 97-03-05, 13.14


INDUSTRIAL POWER SYSTEM
Industrial Power system (IPS) Design - an Overall Approach

This guideline demonstrates how the various 2) Risk analysis, ergonomics and subjective
parts of the design process are intimately inter- feeling of risk.
connected. This procedure does not deal with So far, risk analysis has had its application
the selection of hardware itself, but rather with mostly in larger systems of more complex na-
those qualities a system should have, and those ture (e.g. nuclear power stations or large power
planning activities that lead to the successful systems).
specification of hardware and subsequent pro- Risk analysis has much in common with
curement. reliability analysis and is based on statistical
It should be noted that the approach de- data concerning various types of equipment
scribed and the categories chosen in the follow- failure and accidents. Such data is still not
ing represent just one of many possible ways of easily available, especially because health risks
representing a complex undertaking. in electrical plant are low compared to other
IPS design mastery cannot be gained simply industrial hazards, and since there has been
from a lifetime of working in an engineering little urgency expressed regarding the need to
office where project engineering production is collect such data on an international basis.
the primary criterion of performance. Only It may, therefore, still take some time before
long-term, hands-on experience under proper risk analysis of industrial electrical systems
guidance, in addition to selected graduate and equipment will be commonplace, and be-
courses can bring about the development of a fore ergonomics (man-machine theory) will be
seasoned conceptual system designer. generally applied to improve electrical opera-
tor safety. One area that is often overlooked in
personnel safety is that there may be little
Safety correlation between the statistical probability
From the designer’s point of view safety con- of a certain type of injury and the subjective or
sists of two main areas: psychological risk experienced by the opera-
1) Safety codes and regulations, (such as tors (for example the fear of health hazards
ISO 9000 Quality Standards) from electromagnetic non-ionising fields). This
In most countries power systems are required may admittedly lead manufacturers to improve
by law to follow applicable safety codes or aspects of their equipment, but they would be
wiring regulations. This guarantees some de- measures that only marginally improve ”real
gree of safety through the quality of the equip- world” safety.
ment and workmanship thus stipulated. Also,
the International Electrotechnical Commission Simplicity
and national bodies provide recommendations A simple single-line diagram and a plot of the
that further ensure that the power system will physical and mechanical layout of equipment
conform with a certain class of safety. (It should will assist operational safety because the risk of
be remembered that Quality Assurance can be making mistakes during commissioning, op-
no better than the specifications used in the eration and maintenance is reduced when things
project.) are easy to find and overview both in docu-
However, the final test of safety to person- ments and in the form of hardware. It is there-
nel, plant and environment will come after the fore important to make electrical systems and
system is commissioned and when electricians plant as simple as possible.
and operating staff take over the daily running This requirement is somewhat in contrast to
of the system. Simple, readable operating in- needs for reserve capacity and redundant feed-
structions are needed, together with a thorough ers, which tend to make networks more com-
knowledge of how all the equipment will be- plex. A balance has to be reached which re-
have, both under normal and abnormal condi- quires the IPS designer to have a full under-
tions. There is no place for guesswork and inde- standing of what actually goes on in an electri-
cision in emergency situations where the health cal operation and maintenance department.
and lives of personnel can be endangered. This
is when the designer’s ability to envisage the Expandability - Flexibility
operational phases will truly show up. For future growth of the power system to be

5.1 3 97-03-05, 13.14


INDUSTRIAL POWER SYSTEM
Industrial Power system (IPS) Design - an Overall Approach

included in planning, it is necessary to know still much to be done. Some large international
something about possible future expansion and industrial users have collected their own statis-
increased production capacity. Where such plans tical failure data, but this is generally not avail-
do not exist, it will be helpful to clarify how able to outsiders.
much expandability the system has and where
the bottlenecks to growth may lie, and to inform Total economy
the project team about it. It is well known that good economics for an IPS
is not only a question of the lowest purchase
Maintainability price of equipment. Total life-cycle cost of a
In order to make a power system and its equip- power system depends on equipment purchase
ment easy to maintain, it is important that the price and quality, construction and installation
maintenance programme be kept in mind al- costs, operating costs including losses, outage
ready at the planning stage. costs, repair costs, useful lifetime of the equip-
If continuous round-the clock operation of ment and administrative costs. A particular
all or parts of the process is required, the net- manufacturer’s likelihood of surviving into the
work must have reserve feeders or separate future and being able to supply spare parts is
supply to these components. Otherwise, provi- also an important consideration in the procure-
sions for maintenance of live equipment must ment evaluation. This holistic economic view
be made. In order to answer these questions, it has been termed “terotechnology”, but is not
will be helpful to clarify when and for how long always applied where IPS planning and design
the process equipment itself will require main- takes place.
tenance downtime.
The importance of a rigorous maintenance Planning activities
programme and a meticulous spare parts policy Even if engineering judgement is also required
in order to maintain high continuity of opera- in what follows, precise calculation and analy-
tion is well known. Various reliability surveys sis are more of a priority than in the previous
conducted for industrial plants provide plenty ”qualities” discussed.
of evidence for this. Inadequate or improper Fig. 1 describes how the conceptual design
electrical maintenance is a significant factor in work may proceed. At an early stage all four
all in-plant outages. And yet the owner will be of the first activities are normally carried out
prepared to have work going on round the clock simultaneously. This is a highly iterative proc-
to remedy the failure once it occurs. The para- ess for a new project, where equipment layout,
dox is obvious and well known, and demon- production capacity and the power company
strates the need to draw attention to preventive supply points represent initial conditions.
maintenance as a major factor in power supply Fig. 1 is by no means a strict guideline, but
reliability. rather a reminder of how the activities are
dependent on each other. Therefore, the feed-
Reliability - Availability back loops and the number of adjustments that
The technique of reliability analysis is well have to be made to the IPS design will vary
known and widely used for large power sys- from one project to another. The work will also
tems and might be considered a well estab- depend on how much and how often the initial
lished analytical tool. conditions are changed (which in some projects
However, until recently, reliability analysis constitute continual ”harassment” of the elec-
has not been applied widely to IPS planning for trical discipline).
the simple reason that statistical failure data for
medium and low voltage components have not The diagram in Fig. 1 illustrates the necessity
been readily available. for a central IPS engineering body to be in
With the advent of the IEEE “Report on charge of the overall view and make sure that
Reliability for Industrial Plants,” such statistics nothing is forgotten. The diagram represents an
have become available on American equip- ideal situation where all considerations and
ment used under American conditions, but for analyses have been attended to before the elec-
international applications elsewhere there is trical equipment is finally specified and pur-

5.1 4 97-03-05, 13.15


INDUSTRIAL POWER SYSTEM
Industrial Power system (IPS) Design - an Overall Approach

chased. In reality, the specifications and equip-


ment data sheets, and the purchase of hardware,
• All relay and overcurrent protection should
function for both maximum and minimum
have sometimes been completed while some available short-circuit current. During the
system analysis is still going on. This may not relay co-ordination study it usually becomes
always work out well, and there is a great risk apparent that available short-circuit current
that costly changes may come, or that some from small in-plant generators is very lim-
important requirements will have to be ne- ited. This should be kept in mind when se-
glected as a consequence. lecting both generator and relay protection,
which preferably should operate in a selec-
Load and supply planning tive manner even in emergency conditions.
Some of the fundamental questions which de-
termine network architecture and layout con- Choice of system network - single-line diagram
cerning the planned production capacity are: One of the main criteria, as mentioned under
• How many kW / kVA are required? “Simplicity”, is: Do not make the network
• Where are the major load points located on more complex than necessary!


the plot plan?
What types of load (motors, furnaces, etc.)? • The simpler the single-line diagram is, the
easier it is for the operator to avoid mistakes
• How much power is required at stage 1, 2, 3,
etc., of the process?
during switching operations. The more com-
plex the system is, the larger will be the
requirement for interlocking and automatic
The answers to these questions cannot be abso-
control with corresponding investment cost.
lute at an early stage, but assumptions for Also, from a service point of view, a simple
different alternatives must be made to prepare
radial system will provide less risk of ”back”
for the power company negotiations.
voltage and therefore is safer to maintain.
Whether to consider in-plant or co-generation ”Simple” usually also means lower initial
will depend on: cost.
• What tariff will the power company use? • A well planned maintenance programme
and a scrupulous spare parts policy will have
• What outage frequency and power quality
can the power company provide at the point so much influence on reliability that it may
of supply? outweigh a very simple network diagram
with restricted redundancy. See also
• What will be the cost of process shutdown?
“Maintainability”.
• Must part of the process keep running during
power company outage? • The simpler the network, the easier it will be
to visualise and carry out quick and accurate
• Will primary energy be available at low cost
(e.g. process steam or gas)? system estimates for load flow, short circuit
and voltage dips on motor starting by hand
• What plans does the power company have
for future expansion, with additional lines rather than by computer. The priority of
into the area that could improve availability? certain loads will, of necessity, require
standby supply. The more alternative ways
Discussions with the power company will of supplying each load or load centre, the
also concern the following: more complex the network will become.
• Present and future supply voltage and short-
circuit levels. These will determine what Some questions which should be asked about
voltage disturbances and harmonics there the system network are these:
will be due to the starting of motors, arc
furnaces, variable speed drives, etc., both
• What might future expansion look like and
how will it affect the network?
within the plant itself and from feedback into
the supply power system. This will also
• What kind of system network would the
plant operation engineers prefer?
determine if and how much of the plant will
have to be shut down to allow for motor
• How much overload can be expected at each
load centre? (Transformer fan cooling is a
restart/re-acceleration after return of supply cheap short-time reserve, but there are high
voltage following short outages. losses).

5.1 5 97-03-05, 13.15


INDUSTRIAL POWER SYSTEM
Industrial Power system (IPS) Design - an Overall Approach

With these questions in mind, the selection of main transformer and main distribution
the network may proceed along the following switchgear.
lines:
In order to simplify the discussion it is neces- Receiving or incoming switchgear
sary to use a block diagram representation for a In the 66-145 kV range this switchgear is usu-
collection of hardware which can naturally be ally in the form of an outdoor switchyard. If
lumped together, such as shown in Fig. 2. Each space is limited or pollution is a problem, GIS
small section of single-line diagram is repre- SF6 metal-enclosed gear is used. Normally one
sented by a box as shown. Figs. 3 and 4 then or two incoming lines from the power company
illustrate the two types of systems discussed, will supply the industry. The example in Fig. 2
the radial and the loop system. with a single busbar for this function is only one
of many possible arrangements, but more than
one busbar is seldom chosen since the overall
reliability does not improve much with more
complex arrangements. (This is normally dif-
ferent for larger power company substations)

Main transformer
The size may vary according to load levels, but
maximum sizes of 40-50 MVA seem usual for
this type of substation. The size will primarily
be determined by the available short-circuit
level on the low voltage side, as well as the
limitations and cost of the distribution
switchgear and associated protection. Trans-
former capacity is usually duplicated to give
back-up reserve in case of failure. Through
extra fan cooling one transformer may be able
to handle all or part of the substation load
during a period of limited supply or mainte-
nance work.

Main distribution switchgear


The voltage of this kind of switchgear may be
6-36 kV. The hardware is usually of indoor type
in a separate building or in an operating room
which is part of the plant building. Large indus-
tries have one or two switchgear assemblies per
substation, and they may or may not be in the
same physical location. Double bus switchgear
of the duplex type may also be used for this
Fig. 2 Functional blocks and description of important function, where one of the buses
IPS components carry all high priority loads.

Secondary or sub-distribution switchgear


The terms used are as follows: These switchgear assemblies are usually simi-
lar to the main distribution switchgear and carry
Main or primary substation the same voltage. Single bus is mostly used,
Depending on the size of the loads, there may with the addition of sectionalising in order to
be one or several main substations. As in Fig. 2, segregate high priority loads. The secondary
this usually consists of three separate functions distribution switchgear may wholly or partially
in the single-line diagram: Incoming switchgear, be a high voltage motor control centre.

5.1 6 97-03-05, 13.15


INDUSTRIAL POWER SYSTEM
Industrial Power system (IPS) Design - an Overall Approach

Radially fed secondary substation


This type of substation consists of 0.5-2.5 MVA,
dry or oil-insulated transformers with low volt-
age switchgear. Using dry transformers, the
substation may be located inside the manufac-
turing process building on the shop floor. Due
to fire regulations, oil-filled transformers are
placed in concrete “boxes”, normally outdoors.
As the substation is radially fed, it may not have
any high voltage equipment at all. In some
cases two transformers provide back-up for
each other with sectionalised low voltage
switchgear where high priority loads are con-
nected to one of the sections. Automatic change-
over may provide continuous operation with a
short break if one of the incoming feeders or
one transformer experiences a failure.

Loop-fed secondary substations


Differing from radial substations, these have
high-voltage switchgear consisting of load break
switches with current-limiting fuses or circuit
breakers for transformer protection. The sub-
station may have 1-4 transformers, usually with
segregated low voltage switchgear for each
transformer. The high voltage switchgear is Fig. 3 Radial distribution
sometimes called a “ring main unit” in coun-
tries with British electrical influence.

Fig. 4 Loop distribution

5.1 7 97-03-05, 13.15


INDUSTRIAL POWER SYSTEM
Industrial Power system (IPS) Design - an Overall Approach

Fig. 3 illustrates the radial system. The diagram Reduced or vital operation may be maintained
does not show the electrical paths, only the with standby generation or from a separate
functional blocks and their position. The sys- power company supply. When part of the power
tem is the simplest type possible and allows for company supply fails, a preset load-shedding
great flexibility and expandability. The radially procedure may automatically leave only high
fed secondary substations may be located close priority loads connected. For emergency op-
to the load centres, thereby saving losses and eration only such equipment as is necessary for
keeping the expensive low voltage network to personnel safety and preventing catastrophic
a minimum. failure of the process equipment is maintained.
The primary substation may be the same for
the loop system in Fig. 4 as for the radial
system. The loop system concerns only the
feeding of the secondary substations from the
secondary distribution switchgear. The rings or
loops are normally open in the middle so that in
case of failure only one half of the loop will
experience outage until the faulted section is
isolated and supply can continue.
The radial and loop systems are often mixed
to utilise the combined advantages of both.
The network layout will be influenced strongly
by requirements to maintain limited power sup-
ply in case of power company supply failure.
The operation of the plant may be divided into
three categories.
1. Normal operation
2. Reduced or vital operation
3. Emergency operation Fig. 6 System with three levels of local genera-
tion

Single-line diagrams for “typical” industries


are represented by the examples in Figs. 5 and
6. Fig. 5 shows a typical simple system without
any stringent requirement for redundancy or
reduced operation. In case of power company
failure on both incoming lines, the whole plant
is down. This may be acceptable if the process
does not require gradual shutdown. The system
in Fig. 5 is purely radial, except from the
reserve feeders between adjacent secondary
distribution switchgear assemblies. A some-
what more advanced system in Fig. 6 has two
stages of local generation, first a larger co-
generator for reduced operation, and secondly
two small emergency generators.

Choice of voltage(s)
The size of the industrial process, i.e., the
power requirement, will determine whether one
or several voltage levels are necessary. A small
Fig. 5 System without internal generation industry may well manage with only low volt-

5.1 8 97-03-05, 13.16


INDUSTRIAL POWER SYSTEM
Industrial Power system (IPS) Design - an Overall Approach

age, while a larger one could require 3 - 4


voltage levels. The choice of network and
• Distribution voltage 6-36 kV
The distribution voltage will depend on the
voltages are so closely linked that for all prac- total power demand by the plant, as well as
tical purposes they can be regarded as a single on the short-circuit level required to handle
integrated procedure. disturbances and harmonics.
Depending on the country and the standards
Short-circuit study - stability analysis
it is influenced by, there are a great variety of
voltages available which, when selected, may The calculation of available short-circuit cur-
rents in the network is the basis for selection of
determine and limit the number of manufactur-
switchgear, cables, relays and protection co-
ers that can submit competitive offers for the
equipment. Selection of voltages is, therefore, ordination study. Further, the short-circuit level
at each point in the network will determine
the most vital consideration for the designer in
voltage variations during starting of motors,
preselecting the supplier(s) of hardware.
Therefore, in selecting voltage levels, it welding machines, furnaces, or other intermit-
tent loads. The stronger the system is, the less
should be recognised that limitations to inter-
disturbances there will be. What the optimum
national trade may be imposed on a project.
The following main voltage areas may be short-circuit level will be is thus an economic-
technical judgement limited by available appa-
identified:
ratus and acceptable voltage variations.
• Low voltage 400-1000 V
There may be one or two voltage levels
Some reminders:

below 1000 V. Usually, lighting and general • Quick and simple hand calculations may be
carried out using only power company sys-
purpose loads such as heating and air condi-
tioning will have a separate voltage, usually tem, large generator and transformer reac-
tance, ignoring all other impedances. This
a 400/230 V system where both single-phase
will give a good first estimate of the short-
and three-phase loads are connected. If there
is a large number of motors above 50 kW, circuit level, and motor and small generator
contribution may be added as the system
they may require a somewhat higher voltage
layout takes shape. A number of good PC-
level of 500, 600 or 690 V. Almost without
exception, low voltage systems are radially operated computer programs are available
to-day for modelling the system, and for
fed from the secondary substations discussed
gradually adding new information as design
before. It is important to recognise that no
manufacturing distinction is made in IEC progesses.
between low voltage switchgear and motor
controlgear as is done in ANSI standards.
• Transformer reactance (size of the trans-
former) and current-limiting reactors, to-
gether with sectionalising, are the main tools
• Special motor voltage 3-11 kV
The decision as to which voltage is right for
in manipulating the short-circuit level.
large motors and generators depends both on
the cost of the motor itself, cable and bus
• Be aware that IEC 909 does not represent the
full international story regarding short-cir-
duct, as well as the cost of the starting cuit calculations. Unfortunately, IEC 363
method and switchgear involved. For cer- also stipulates rules for calculation in marine
tain smaller motors the starter may cost more systems. The IEC technical committees have
than the motor itself. not been able to agree on one common set of
For very large motors, it is worth while rules for both land and sea. Also be aware
looking at the motor-transformer unit prin- that ANSI standards are different from those
ciple, i.e., a separate transformer for each of IEC since the method of rating circuit
motor that will give a smooth start with breakers is different.
minimum disturbance along with lower cost The smallest available short-circuit level may
for the motor-starter-transformer combina- be critical for protective relaying and selectiv-
tion. If the plant distribution voltage is dif- ity to function during periods of reduced opera-
ferent from the motor voltage, this may well tion, e.g., during emergency or standby opera-
be a preferred solution. tion with only local generation source connected.

5.1 9 97-03-05, 13.16


INDUSTRIAL POWER SYSTEM
Industrial Power system (IPS) Design - an Overall Approach

When a short circuit occurs in the power sys- economy of each alternative will decide which
tem, voltage drops will occur throughout the one to select. At the same time, the available
system. Similarly, during short power com- starting torque of the motor should be checked
pany outages (auto-reclosing) the power sys- against the load torque to allow the motor to
tem can experience a period of severe distur- accelerate to full speed before becoming over-
bance. heated. The relay protection requirements of
When the short circuit is removed and volt- the motor are thus considered at this time to
age is restored, synchronous machines may allow for a co-ordinated and integrated drive
have fallen out of step, or induction motors may package.
have lost speed to such an extent that there is not Loads with fast-varying power demand, such
enough strength to re-accelerate all of them as welding equipment and arc furnaces are
simultaneously. A transient stability study will often placed separately in the network (on sepa-
give the answers to what happens during such rate transformers) to allow for minimum distur-
disturbances. This is achieved through the use bances. Static converters create more complex
of a computer program, and the outcome shows problems as they require both varying reactive
what measures will have to be adopted in terms current at the power frequency and, in addition,
of protective relaying, load shedding, restart create harmonic frequencies. Combinations of
sequence, etc. A type of automatic load shed- filters and switched capacitors are used to im-
ding that is often forgotten is inherent in the prove the voltage quality.
large number of voltage-held contactors present
in nearly every industrial plant. Contactors Choice of system earthing
drop out at approximately 65% of rated voltage The main purposes of connecting the system´s
if no steps are taken to delay the drop-out. neutral point directly to earth or through some
impedance is to:
Calculations of Voltage Variations - Load a) produce a current or voltage during an earth
Flow Study fault with a magnitude sufficient for selective
Where a power system is relatively complex, tripping or alarm signal
with a number of alternate feeding paths for b) limit the earth fault current to keep personnel
each load centre, a load flow study by computer hazard and material damage to a minimum
will be necessary. Sometimes this study is a c) limit overvoltages that may occur during
prerequisite for the short-circuit study. It pro- earth faults on a completely unearthed system
vides data for the sizing of cables and bus, and The selection of system earthing is, therefore,
determines the resulting voltage drop due to closely linked to the choice of protective relay-
steady-state loads with high power factor. When ing and voltage surge protection. Without go-
a simple radial system is used, load-flow calcu- ing into the merits of the various methods of
lations may easily be carried out by hand, system earthing, the following points should be
although a PC may be helpful in cutting down kept in mind:
the work. Apart from the above steady-state
conditions, there are some loads which at times • Ifable,transformer neutral points are not avail-
there will be an extra cost for special
will require high reactive currents. The most
common type is the starting of motors. With the earthing transformers to establish artificial
neutral points.
aid of the reactance diagram arrived at during
the short-circuit study, very fast and simple
offhand estimates of the voltage drops due to
• Generators often have special earthing re-
quirements which may deviate from the rest
starting may be carried out assuming a com- of the system. Low voltage systems up to
pletely reactive circuit at the instant of start. For 400 V are mostly solidly earthed, while 690
more comprehensive answers giving the sys- V systems more frequently are unearthed,
tem performance during the entire run-up pe- or, high-resistance-earthed to allow for de-
riod, a dynamic study is required. layed disconnection of the faulty circuit un-
If the network requires reinforcement, or if til such time in the plant process as is con-
reduction of starting current is achieved by venient to repair it. Internationally, high
some reduced voltage starting method, the impedance or Petersen coil (resonant) earth-

10

5.1 10 97-03-05, 13.16


INDUSTRIAL POWER SYSTEM
Industrial Power system (IPS) Design - an Overall Approach

ing is common in medium and high voltage relays, earth fault relays, etc., is an elaborate
(3-100 kV) systems, although each country procedure closely related to the choice of sys-
has developed some degree of individual tem network, system earthing and short-circuit
practice. and stability analysis. This is covered in rather
more detail in the section ”Fault control”.
• The power company will be responsible for
system earthing on the supply voltage side.
Instrument transformers and their ratios and
burdens must also be considered, as well as the
setting ranges of the relays. It will be necessary
Voltage surge protection
to carry out a protective co-ordination study for
The most common harmful overvoltages in an
all series-connected overcurrent devices. With
industrial power system stem from: the inverse characteristics of fuses, overcurrent
• Lightning surges on power company lines or
overhead lines within the plant itself.
and overload relays, direct acting trips, etc., it
will only be possible to demonstrate on time-
current log-log paper the degree of selectivity
• Switching overvoltages. obtained. On the same graph, such data as
• Intermittent or arcing earth faults in un-
earthed systems.
maximum and minimum short-circuit level,
starting currents of motors (including starting
time) and l2t curves for cable and transformer
Those components specifically vulnerable to withstand ability may be plotted for a total view
overvoltages are the low BIL and high-invest- of the protective function. Co-ordination with
ment parts; primarily motors. For the first two the power company´s protective relaying will
types of overvoltages the use of surge capaci- be directed by agreement as to how the two
tors at the terminals of each large motor should power systems should interact with each other
be considered to protect the turn-turn insulation during heavy disturbances.
against surges with steep front, and lightning
arresters to protect the total winding insulation Power factor correction
against the amplitude of the surge voltage. What power factor is considered acceptable
Which of these methods or what combination will depend on two cost assessments:
of them should be used will depend on the size First, to what extent does the power company
of the motor, its voltage rating and the degree to tariff penalise the use of reactive power?
which the network is exposed to lightning and Secondly, how much can be saved in cable
switching voltages. Dry type transformers also sizes, transformer capacity and loss reduction
have a low BIL and may need lightning arrest- through the installation of capacitor banks?
ers. Arcing or sputtering earth faults in un- The optimum location of the capacitors in the
earthed systems may build up harmful system network will have to be calculated too.
overvoltages in the system´s equivalent capaci- The closer to the load the capacitor is located,
tance. This may be avoided by earthing the the more effective the compensation will be,
system through a relatively high resistance. but there is also a higher cost per compensated
kvar. Do not forget to include the price for
Protective relaying and co-ordination switching equipment, if applicable.
study In choosing between large synchronous and
The sophistication and complexity of relay and induction motors, it should be remembered that
fault protection equipment necessary for each synchronous motors may be over-compensated
part of the power system will depend on the to improve a poor plant power factor. Induction
investment in the object protected, and the motors have no such facility. Fast varying var
degree of availability and personnel safety of- requirements may require more sophisticated
fered by the protection. The aim is to discon- compensation, such as thyristor-switched ca-
nect selectively the faulty part of the system as pacitors or synchronous condensers. The prob-
fast as possible to minimise damage. The choice lem here is the voltage disturbances caused by
of overcurrent relays, fuses, direct-acting trip the varying load, rather than the price of kvar
devices, overload relays, differential relays, used. This is covered in rather more detail in
overvoltage and undervoltage relays, frequency Chapter 6 ”Reactive power compensation”.

11

5.1 11 97-03-05, 13.16


INDUSTRIAL POWER SYSTEM
Low voltage distribution

LOW VOLTAGE DISTRIBUTION


LOW-VOLTAGE SWITCHGEAR AND
CONTROLGEAR ASSEMBLIES
LV ASSEMBLIES

Contents
page
1 General 12
2 Requirements 17
3 Sizing faktor 25
4 Plant design 27
5 Apparatus and combination of apparatus 32
6 Selection of short-circuit protective device (SCPD) 43
7 Selection of overload protection 48
8 Microprocessor-baserad control technique for low-voltage distribution systems 50
9 Sizing of devices and cables 51
10 Project planning 51
11 Information to be provided on an LV ASSAMBLY 53

General
Introduction The transformer is mostly placed near the low-
In an industrial low-voltage distribution sys- voltage switchgear and controlgear assem-
tem the loads consist of motors and electrical bly located in a locked operating room to which
devices in some producing processes, see sin- only skilled persons have access. The abbrevia-
gle-line diagram Fig. 2, p. ? below and the tion LV ASSEMBLY/IES is hereafter used for
section Sizing factors, p. ?. a ”Low-voltage switchgear and controlgear
Larger industries have their own receiving assemblies”.
substations, from where medium-voltage (6-36 The LV ASSEMBLY can be divided up into
kV) power is distributed. main distribution and sub-distribution.
Each sector has an incoming medium-volt- The main distribution LV ASSEMBLY is
age switchgear and controlgear assembly with then placed in a locked operating room and the
a circuit-breaker, see Medium-voltage distri- sub-distribution LV ASSEMBLY can be lo-
bution in Chapter 5.4 on p. ?, which feeds a cated close to process objects. In many countries
transformer of up to 3.15 MVA, see Distribu- it is common that not only the main distribution
tion transformers, p. ?. LV ASSEMBLIES but also the sub-distribution
The most common secondary voltages (low LV ASSEMBLIES are placed in operating
voltages) are 400, 500 or 690 V. rooms. See the section Plant design, p. ?.
See the section Voltage levels, p. ?. The main incoming unit in an LV ASSEM-

12

5.2 12 97-03-05, 13.17


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Fig 20, Typical LV-ASSEMBLY

BLY is normally a circuit breaker cubicle. The stated by the manufacturer the time is 1 s.)
circuit breaker should be sized to trip at the
maximum short-circuit currents, and to The rated current (load current) of an LV
continously carry the total current load. The ASSEMBLY is normally between 800 A and
circuit breaker is supplied with a short-circuit 6000 A.
protective device (SCPD) and overload protec- The rated voltage of an LV ASSEMBLY does
tion, which break the circuit in the event of a not exceed 1000 V AC.
short circuit or an abnormally high load cur-
rent. Circuit breakers are described under the Main distribution - Load Center, LC
section Circuit breakers, p. ?. The breaker that is directly connected to the
To achieve a very short breaking time if an secondary side of the transformer, feeds the
arc arises, it is recommended that the LV AS- main busbar in the LV ASSEMBLY.
SEMBLY be supplied with arc monitors. The Outgoing units are connected to this busbar:
co-ordinat system is described in the section • for sub-distribution
with the same name on p. ?. • for resistive loads
The rated short-time withstand current of • for motors and motor drives
an LV ASSEMBLY is normally in the range
between 20 kA and 100 kA. (Unless otherwise
• for other types of loads
See the section Sizing factors, p. ?.

13

5.2 13 97-03-05, 13.18


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Sub-distribution: • Soft starters for heavy motor start


• LV ASSEMBLIES with outgoing units for
motor drives, Motor Control Center, MCC.
• Earthing switches for short circuit and earth-
ing of the busbars related to maintenance on
• LV ASSEMBLIES with outgoing units for
distribution.
disconnected part of the plant.
In the section Apparatus and combination of
• Multibox-type LV ASSEMBLIES with out-
going units for lighting panels, fan motors,
apparatus, p. ?, more information can be found
on the above devices.
ventilation equipment, heating equipment,
pump motors, etc. Power factor control
The loads in a process industry mainly consist
Examples of outgoing units: of motors, which work with magnetic fields
• Switch (mechanical) + fuses needing current. This current is reactive and is
• Circuit breakers (normally as incoming unit,
see above).
not transformed into energy, or useful work.To
compensate this, it is appropriate to connect an
• Moulded case circuit breakers, MCCBs automatically power factor control device to
• Disconnectors the LV ASSEMBLY. The equipment consists
• Fuse-switches, Switch-fuses of capacitors which are switched on and off by
• Distribution boards with D-type fuses or
with miniature circuit breakers, MCBs.
contactors, guided by an electronic reactive
power control unit that measures the power
• Motor starters (the most common outgoing
units in an MCC).
factor, cos j. Fig. 3 below shows the principle
applied.
• Current
motors
converters for speed adjusted DC Power factor control is described in more
detail in Chapter 6, Reactive power compensa-
• Frequency
AC motors.
converters for rev/min adjusted tion (power factor control) on pp.?-?.

Fig 21. Single-line diagram

14

5.2 14 97-03-05, 13.18


INDUSTRIAL POWER SYSTEM
Low voltage distribution

The main busbars (primary system) are assem-


bled horizontally, and are connected in each
cubicle to vertically assembled busbars (sec-
ondary system).
Functional units (in most cases outgoing
units) are connected to the vertical busbars.
The primary busbar system has a rated current
in the range 800 A to 6000 A and the rated
current of the secondary busbar system is be-
tween 300 and 2000 A.
Besides the horizontal and vertical busbars -
the phase conductors (L1,L2,L3) - there is also
a neutral conductor (N), a protective conductor
(PE) or a combined neutral and protective con-
ductor (PEN).
The neutral conductor (N) is insulated, while
the protective conductor (PE) or the combined
Fig. 3 Principle of power factor control neutral and protective conductor (PEN) is
mounted with good contact to the cubicle. See
the section Types of distribution system, p. ?.

Design and construction Degree of protection, IP CODE (IEC 529)


The LV ASSEMBLY is designed in the form The enclosure protects against:
of cubicles (floor-standing) containing mo-
dularised incoming and outgoing units. See
• Unintentional contact with hazardous live
parts
Fig. 1 above. • Ingress of water or moisture
There is a separate compartment for wiring
(cables), for busbars and for functional units
• Ingress of solid foreign objects and dust

(incoming and outgoing). See more about sepa- The classifying of the degrees of protection is
ration in the section Protection against electric described in International Standard Publication
shock, p. ?. IEC 529. The degree of protection provided by
The cubicles are mostly manufactured from an enclosure is indicated by the IP Code (IP is
steel sheet (1.5-2.5 mm gauge), treated or an abbreviation for International Protection).
painted. In the code IP 21C, for instance, the first
The most common dimensions (including numeral indicates the degree of protection
cable compartment) are: against solid foreign objects, the second nu-
Width 600-1200 mm meral the degree of protection against water
Depth 300-800 mm and the additional letter the degree of protec-
Height 1800-2300 mm. tion against access to hazardous parts. Fig. 4
below gives a brief description of the IP Code
Cable compartment elements.
The cable compartment is generally separated The sections Enclosure and degree of pro-
from the apparatus compartment (functional tection, p. ?, and Environmental aspects, p. ?,
units) and from the busbar compartment and give more information on requirements for
has its own door. protection.

Busbars Incoming and outgoing units


The busbars are made of copper or copper- The incoming and outgoing units in an LV
coated aluminium and separated from func- ASSEMBLY are built as complete functional
tional units and from the cable compartment by units. They contain all the necessary apparatus,
barriers or partitions. See the section Protec- components and connections. All this is assem-
tion against electric shock, p. ?. bled in a modularised mechanical unit.

15

5.2 15 97-03-05, 13.19


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Fig. 4. Degree of protection (IP Code)

To provide a high degree of protection against Removable and withdrawable parts


unintentional contact with hazardous live parts Removable and withdrawable parts can be
in adjacent functional units, and protection safely removed or installed in the LV ASSEM-
against the passage of solid foreign bodies from BLY without the busbar system needing to be
one unit to an adjacent unit, each unit is built as disconnected. This allows removal or installa-
a separate, screened compartment with its own tion of an unit while other units in the LV
door. See the section Protection against elec- ASSEMBLY are live.
tric shock, p. ?. To make this possible, the removable and
The units can be designed as: withdrawable parts are connected by plugging
• Fixed parts in to the secondary busbar system. The differ-
• Removable parts ence between removable and withdrawable parts
• Withdrawable parts is that the withdrawable parts have plug-in
contacts on the cable connection side (outgoing
Fixed parts side) as well, and have fixed ”Connected”,
The fixed parts are fastened by bolts to the ”Test” and ”Disconnected” positions. In the
secondary busbar system (the vertical busbars). ”Test” position the main circuit is discon-
This means that the unit cannot be removed, nected while the auxiliary circuit is live. In the
drawn out or installed in the LV ASSEMBLY ”Disconnected” position both the main circuit
without the busbar system being disconnected. and the auxiliary circuit are disconnected.

16

5.2 16 97-03-05, 13.19


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Multibox-type LV ASSEMBLIES Requirements


Multibox-type LV ASSEMBLIES are built with Introduction
separate boxes for incoming and outgoing units. Many electrical accidents take place when
The boxes are designed for wall mounting. working with live LV ASSEMBLIES. Most of
The boxes are modularised and designed for these accidents occur in plants with an operat-
standard apparatus up to a rated current of 800 ing voltage below 1000 V. A large proportion
A. The degree of protection is usually IP 43 or are arc accidents (short-circuit phase to phase
IP 65. See the section Degree of protection, p. or phase to earth), with operators suffering
?. The boxes are generally made of treated or serious burn wounds, and/or major material
painted sheet steel. destruction causing expensive shutdown. The
The busbars are made of copper or alu- main reasons for arc accidents are:
minium and are available for rated current up to
800 A. The busbars can be placed in a separate • uninsulated tools
row of boxes or built in to the same box as the • changing of fuses
devices. • voltage testing
The apparatus is internally connected with • falling metal objects
cables or with copper bars. Plug-in connection • uninsulated wire ends
of the apparatus is also available, a safe and • overheating
quick system that eliminates subsequent ad- The accidents thus often happen when an elec-
justment of bolts and simplifies assembly. trician is working with a live LV ASSEMBLY.
Boxes can also have covers of plastics. The The requirements of an LV ASSEMBLY is that
material should be polycarbonate, which has it should be properly designed and well main-
good impact resistance, resistance to ageing tained, so that risks of overheating, short cir-
and is recyclable. The most usual degree of cuits and arcing inside an LV ASSEMBLY are
protection for this type of box is IP 54 or IP 65. eliminated as far as possible.
The requirements are documented in several
Apparatus commonly found in boxes: international standards. See Bibliography:
• Switch + fuses Applicable IEC standards, p. ?. See also the
• Switches
Blade fuses section Standardisation in Chapter 14.1 , p. ?.
• Moulded case circuit breakers, MCCBs
• Distribution boards with D-type fuses or The main standard for low-voltage switchgear
• with miniature circuit breakers, MCBs and control gear assemblies, LV ASSEM-
BLIES, is the International Standard Publica-
tion IEC 439-1, ”Requirements for Type-
Tested and Partially Type-Tested Assem-
blies”

Service conditions
LV ASSEMBLIES are normally designed spe-
cifically for indoor installation, except for
multibox-type LV ASSEMBLIES, which can
also be installed outdoors.

Normal service conditions


The ambient air temperature does not exceed
+40oC and its average over a period of 24 h does
not exceed + 35oC.
The lower limit of the ambient air tempera-
ture is -5oC for indoor installations.
For outdoor installations the lower limit of
the ambient air temperature is -25oC in a tem-
Fig. 5 Multi-box type LV ASSEMBLY perate climate and -50oC in an arctic climate.

17

5.2 17 97-03-05, 13.20


INDUSTRIAL POWER SYSTEM
Low voltage distribution

The air is clean and its relative humidity does form and polarity which the circuit of an LV
not exceed 50% at a maximum temperature ASSEMBLY is capable of withstanding with-
of +40oC for indoor installations. For outdoor out failure under specified conditions of test
installations, the relative humidity may tempo- and to which the values of clearances are re-
rarily be as high as 100% at a maximum tem- ferred.
perature of +25oC. Before sizing of minimum clearances and
The standard degree of pollution for indus- creepage distances the following must be de-
trial applications is degree 3, which means: termined:
Conductive pollution occurs, or dry, non-con- a) Material group (7.1.2.3.5 in IEC 439-1)
ductive pollution occurs which becomes con- b) Polution degree (6.1.2.3 in IEC 439-1)
ductive due to condensation. (the standard polution degree is degree 3)
The altitude of the site of installation does c) Rated impulse withstand voltage (table G.1
not exceed 2000 m. or G.2 in IEC 439-1)
(More information is given in the section Clear- d) Rated insulation voltage (4.1.2 in IEC
ances, creepage distances and insulating dis- 439-1)
tances, p. ?.) e) Altitude (6.1.3 and table 13 in IEC 439-1)
f) Test voltages (table 13 in IEC 439-1)
Special service conditions g) Homogeneous (uniform) or non-homogene-
The user is to inform the manufacturer if excep- ous (non-uniform) field (2.9.15 and 16 in
tional service conditions exist. IEC 439-1)
See more about special service conditions in h) Rated operational voltage (4.1.1 in IEC
the section Environmental aspects, p, ?. 439-1)
j) Overvoltage category (table G.1 or G.2 in
Conditions during transport, storage and IEC 439-1
erection. k) AC r.m.s. star or delta (table G.1 or.2 in IEC
Unless otherwise specified, the following tem- 439-1, distribution system with or without a
perature range applies during transport and neutral point)
storage: between -25oC and +55oC and, for
short periods not exceeding 24 h, up to +70oC. After this determination, minimum clearances
Equipment subjected to these extreme tem- and creepage distances can be sized according
peratures without being operated, provided that to tables 14, 15 and 16 in IEC 439-1.
it does not suffer irreversible damage, is then to
operate normally in the specified conditions. Example: a) = II; b) = 3; c) = 8 kV; d) = max.
690 V; e) = sea level; f) = 9.8 kVAC peak and
DC f) = 7 kV AC r.m.s.; g) = non-homogene-
Design and construction ous; h) = max. 690 V; j) = III; k) = AC r.m.s. star
Mechanical design or delta, all live parts insulated from earth (no
General neutral point).
The LV ASSEMBLIES are to be constructed Result: Minimum clearance = 8 mm and
only of materials capable of withstanding the Minimum creepage distance = 9 mm
mechanical, electrical and thermal stresses, as
well as the effects of humidity, which are likely Apparatuses forming part of the LV ASSEM-
to be encountered in normal service. BLY are to have distances complying with the
requirements of their relevant specifications
Clearances, creepage distances and (IEC standard), and this is to be maintained
insulating distances during normal sevice conditions.
Determination of clearances distances, creep- When arranging apparatuses within the LV
ing distances and insulating distances in LV ASSEMBLY, the specified creepage distances
ASSEMBLIES is normally based on the Im- and clearances or impulse withstand voltages
pulse voltage rating. are to be complied with, taking into account the
The rated impulse withstand voltage is the relevant service conditions.
peak value of an impulse voltage of prescribed For bare live conductors and terminations

18

5.2 18 97-03-05, 13.20


INDUSTRIAL POWER SYSTEM
Low voltage distribution

(e.g. busbars, connections between apparatus, If connecting facilities for incoming and outgo-
cable lugs), the creepage distances and the ing neutral (N), protective (PE) and
clearances or impulse withstand voltages are, combined neutral and protective (PEN) con-
at the least, to comply with those specified for ductors are provided, they are to be arranged in
the apparatus with which they are directly asso- the vicinity of the associated phase conductor
ciated. terminals.
The insulation of withdrawable parts is, at
the least, to comply with the requirements for Enclosure and degree of protection (IEC
disconnectors (IEC 947-3). 529)
The classification system for the degree of
Terminals for external conductors protection, the IP system, is described in the
The terminals are to be such that the exter- section Degree of protection, p. ?.
nal conductors may be connected by a means The degree of protection of an enclosed LV
(screws, connectors, etc.) which ensures that ASSEMBLY is to be at least IP 2X after instal-
the necessary contact pressure corresponding lation.
to the current rating and the short-circuit strength In locations with high humidity and tem-
of the apparatus and the circuit is maintained. peratures varying within wide limits, and in
The available wiring space is to permit proper locations with heavy pollution of the air by
connection of the external conductors of the dust, smoke, corrosive or radioactive particles,
indicated material and, in the case of multicore suitable arrangements (ventilation and/or inter-
cables, spreading of the cores. nal heating, drain holes, etc,) must be made to
The conductors must not be subjected to prevent harmful corrosion and condensation
stresses which reduce their normal life. within the ASSEMBLY. See more about spe-
Terminals for neutral conductors are to al- cial service conditions in the section Environ-
low connection of copper conductors having a mental aspects, p. ?.
current-carrying capacity:
– equal to half the current-carrying capacity Temperature rise
of the phase conductor, with a minimum of The temperature rise in an LV ASSEMBLY
10 mm2 if the size of the phase conductor must not be allowed to damage apparatus, com-
exceeds 10 mm2. ponents, devices, wires, connections, termi-
– equal to the full current-carrying capacity nals, etc.
of the phase conductor if the size of the latter In service, normal live parts are not permit-
is less than or equal to 10 mm2. ted to have a temperature that causes overheat-
Note: For certain applications in which the ing with the risk of internal arcing accidents.
current in the neutral conductor may reach high External surfaces are not permitted to be so
values, for example large fluorescent installa- hot that skin contact is made impossible.
tions, a neutral conductor having the same The table below shows the highest tempera-
current-carrying capacity as the phase conduc- ture rise allowed for different parts of the LV
tors may be necessary. ASSEMBLY.

Temperature rise limits (IEC 439-1)


Part of LV ASSEMBLIES Temperature rise (oK over the
ambient temp.)
Built-in components In accordance with the relevant
requirements for individual com-
ponents, if any, or , in accordance
with the manufacturer´s instruc-
tions, taking into consideration
the temperature inside the LV
ASSEMBLY

19

5.2 19 97-03-05, 13.20


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Terminals for external insulated conductors 70oK


Busbars and conductors, plug-in contacts Limited by:
of removable or withdrawable parts 1). mechanical strength of their
connected to busbars conducting material;
2.) possible effect on adjacent
equipment;
3.) permissible temperature limit
of the insulating materials in con-
tact with the conductor;
4.) the effect of the temperature of
the conductor on the apparatus
connected to it
5.) for plug-in contacts, the nature
and surface treatment of the con-
tact material
Manual operating means:
– of metal 15oK
– of insulating material 25oK
Accessible external enclosures and
covers:
– metal surfaces 30oK
– insulating surfaces 40oK
Discrete arrangements of plug and socket-type
connection Determined by the limit for those
components of the related equip-
ment of which they form part

Protection against electric shock


The LV ASSEMBLY is to be so designed and disconnected before the door can be opened
manufactured that the risk of unintentional con- (for example by interlocking the door with a
tact -direct contact- with live parts - is elimi- disconnector).
nated as far as possible and any exposed con-
ductive part is not, through a fault, to become a The LV ASSEMBLY is to have internal
dangerous live part -indirect contact. separation by barriers or partitions.
By dividing LV ASSEMBLIES by means of
Protecting against Direct contact created by partitions or barriers (metallic or non-metallic)
enclosures and barriers. into separate compartments or barriered sub-
All external surfaces are to conform to a degree sections the following conditions can be at-
of protection against direct contact of at least IP tained:
2X or IP XXB. – protection against contact with live parts
All barriers and enclosures are to be firmly belonging to adjacent functional units.
secured in place. They are to have sufficient The degree of protection is to be at least IP
stability and durability to resist the strains and 2X or IPXXB.
stresses likely to occur in normal service with- – limitation of the probability of initiating arc
out reducing clearances. faults
Removal, opening or withdrawal must ne-
cessitate the use of key or tool.
Note: The effects of an arc can be reduced by use of
All live parts which can unintentionally be means limiting the magnitude and duration of the short-
touched after the door has been opened must be circuit current. See the section Arc guard system, p. ?

20

5.2 20 97-03-05, 13.21


INDUSTRIAL POWER SYSTEM
Low voltage distribution

– protection against the passage of solid for- 2. The protective circuit may not include
eign bodies from one unit of an LV ASSEM- switches.
BLY to an adjacent unit. The degree of 3. Terminals for incoming protective con-
protection is to be at least IP 2X. ductors are to be bare and normally be
designed for copper conductors.
The following are typical forms of separation 4. A separate terminal of adequate size is
(IEC 439-1): to be provided for the outgoing protec-
Form 1 No separation tive conductor(s) of each circuit.
Form 2 Separation of busbars from the func- 5. If the protective conductor is an insu-
tional units. lated single-core cable it is to be green-
Form 3a Separation of busbars from the func- yellow (twin-coloured). See the section
tional units and separation of all Identification, p. ?.
functional units, but not of their
terminals, from one another. The The cross-section of protective conductors (PE)
terminals for external conductors in an LV ASSEMBLY is to be determined in
need not be separated from the one of the following ways:
busbars. a) The cross-sectional area of the protective
Form 3b Separation of busbars from the conductor is to be not less than the appropriate
functional units and separation of value shown below:
all functional units from one another.
Separation of the terminals for ex- Cross-sectional area of the protective con-
ternal conductors from the functional ductor (IEC 439-1)
units, but not from each other. Cross-sectional area of Minimum cross-
Form 4 Separation of busbars from the func- phase conductors sectional area of
tional units and separation of all the corresponding
functional units from one another, S protective conduc-
including the terminals for external tor Sp
conductors which are an integral part
of the functional unit. mm2 mm2
S</= 16 S
Protection against Indirect contact by using 16<S</= 35 16
protective circuits 35<S</= 400 S/2
A protective circuit in an LV ASSEMBLY 400<S</= 800 200
consists of either a separate protective conduc- S> 800 S/4
tor or conductive structural parts or both. It
provides the following: b) The cross-sectional area of the protective
– protection against the consequences of faults conductor is to be calculated with the aid of the
within the LV ASSEMBLY formula: Sp= √I2t / k
– protection against the consequences of faults
in external circuits supplied through the LV where:
ASSEMBLY. -Sp is the cross-sectional area, in
Constructional precautions are to be taken to square millimetres
ensure electrical continuity between the ex- -I is the value (r.m.s.) of AC fault
posed conductive parts of the LV ASSEMBLY current for a fault of negligible im-
and between these parts and the protective pedance which can flow through
circuits of the installation. Types of system the protective device, in amperes
earthing are described in the section Types of -t is the operating time of the discon-
distribution system, p. ?. necting device
The main requirements are: -k is the factor dependent on the ma-
1. It should not be possible to break the terial of the protective conductor, the
protective circuit. For example, when a insulation and other parts, and the
part in the LV ASSEMBLY is removed. initial and final temperature

21

5.2 21 97-03-05, 13.21


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Requirements related to accessibility in rent including DC component) for determining


service by authorised personnel the electrodynamic stresses is to be obtained by
The LV ASSEMBLY must be designed in such multiplying the r.m.s. value of the short-circuit
a way that its accessibility when the LV AS- current by the factor n.
SEMBLY is in service and under voltage is as Standard values for the factor n and the
high as possible, with very low likelihood of corresponding power factor are given in the
accidents. table below.
Accessibility is of three types:
1. Accessibility for inspection and similar Peak withstand current factor n (IEC 439-1)
operations, e.g. replacement of fuse-links R.M.S. value of
2. Accessibility for maintenance, e.g. chang- short-circuit current P.F. n
ing of contacts in a contactor
I >/= 5 kA 0.7 1.5
3. Accessibility for extension under voltage,
e.g. extension of the LV ASSEMBLY with 5 kA < I </= 10 kA 0.5 1.7
10 kA < I </= 20 kA 0.3 2
additional functional units
20 kA < I </= 50 kA 0.25 2.1
Short-circuit protection and short-circuit 50 kA < I 0.2 2.2
withstand strength
LV ASSEMBLIES are to be so constructed as Arcing inside an LV ASSEMBLY, Internal
to be capable of withstanding the thermal and arcing tests
dynamic stresses resulting from short-circuit It is desirable that the highest possible degree
currents up to rated values. of protection for personnel should be provided
LV ASSEMBLIES are to be protected against in case of a fault leading to arcing inside an
short-circuit currents by means of, for example, LV ASSEMBLY, although the prime objective
circuit-breakers, fuses or combinations of both, should be to avoid such arcs by suitable design
which may either be incorporated in the LV or to limit their duration.
ASSEMBLY or arranged outside it. The tripping time should be less than 0.1 s
(100 ms).
Short-circuit rating An incoming circuit breaker which has a
The manufacturer is to state the short-circuit fast-working short-circuit protective device as
strength in one or more of the following ways: well as arc guards with detectors in each cubicle
a) The rated short-time withstand current to- is recommended. See the section Arc guard
gether with the associated time, if different system, p. ?.
from 1 s and the rated peak withstand current. It is recommended that internal arcing tests
Note: For times up to a maximum of 3 s the re- be carried out in accordance with a relevant test
lationship between the short-time withstand current method.The purpose of internal arcing tests is
and the associated time is given by the for-mula: to verify that the enclosure of the LV ASSEM-
I2t=constant, provided that the peak value does not BLY provides the necessary protection for per-
exceed the rated peak withstand current. sons in front of or in the vicinity of the LV
b) The rated conditional short-circuit current ASSEMBLY in the event of internal arcing.
The testing is intended to verify that the
c) The rated fused short-circuit current
enclosure withstands the pressure and the tem-
For items b) and c) the manufacturer is to indi- perature arising from internal arcing with short-
cate the characteristics (current rating, break- circuit current and thus provides the necessary
ing capacity, cut-off current, I2t, etc.) of the protection against injury by radiation from the
short-circuit protective devices necessary for arc, glowing particles, ejected hot gases or
the protection of the LV ASSEMBLY. flying parts.
The requirements differ, depending on
Relationship between peak and r.m.s. values whether accessibility to the vicinity of the LV
of short-circuit current ASSEMBLY is restricted or not.
The value of peak short-circuit current (peak The recommended test method can also be used
value of the first loop of the short-circuit cur- to verify the performance of partitions.

22

5.2 22 97-03-05, 13.21


INDUSTRIAL POWER SYSTEM
Low voltage distribution

It should further be observed that the intended nents, for example co-ordination of motor start-
protection against internal arcing faults is only ers with short-circuit protective devices, are to
obtained if the doors of the LV ASSEMBLY comply with the relevant IEC standards.
are properly closed and if the LV ASSEMBLY
has been installed according to the Installation
manufacturer´s instructions. Switching devices and components are to be
The recommended arcing tests are not in- installed in accordance with the instructions of
tended to give any guidance on service avail- their manufacturer (position of use, clearances
ability after an arcing fault. Because of the to be observed for electric arcs or for the re-
extensive material damage caused by free arcs moval of the arc chute, etc.)
of short-circuit currents during normal tripping The apparatus, functional units mounted on
times, it is not possible to put an LV ASSEM- the same support (mounting plate, mounting
BLY back into service immediately after an frame) and the terminals for external conduc-
arcing fault. tors are to be so arranged as to be accessible for
mounting, wiring, maintenance and replace-
Co-ordination ment. In particular, it is recommended that the
It is very important that the short-circuit pro- terminals be situated at least 0.2 m above the
tective devices in a plant (distribution system) base of floor-mounted LV ASSEMBLIES and,
be co-ordinated. See the section Choice of moreover, be so placed that the cables can be
short-circuit protective device, SCPD, p. ?. easily connected to them.
Where there are considerable demands of con- In general, for floor-mounted LV ASSEM-
tinuous service, the short-circuit protective de- BLIES, indicating instruments which need to
vices and their settings are co-ordinated so that be read by the operator should not be located
a short circuit is disconnected by a breaker or a higher than 2 m above the base of the LV
fuse without disturbing any other circuits, i.e., ASSEMBLY.
selectivity. See more about selectivity in the Operating devices such as handles,
section Selectivity plan, p. ?. pushbuttons, etc., should be located at such a
height that they can easily be operated; this
Unprotected conductor means in general that their centreline should
Within a section in an LV ASSEMBLY, the not be higher than 2 m above the base of the LV
conductors (including distribution busbars) ASSEMBLY.
between the main busbars and the supply side Actuators for emergency switching devices
of functional units, as well as components in- should be accessible within a zone between 0.8
cluded in these units, may be rated on the basis m and 1.6 m above servicing level.
of the reduced short-circuit stresses occurring The switching devices and components are
on the load side of the respective short-circuit to be installed and wired in the LV ASSEM-
protective device within each unit, provided BLY in such a manner that its proper function-
that these conductors are arranged so that under ing is not impaired by interaction.
normal operating conditions, an internal short More specified requirements are stated in the
circuit between phases and/or between phases standard mentioned.
and earth is only a remote possibility. Such
conductors are preferably of solid, rigid manu- Fixed, removable and withdrawable parts
facture. Insulated flexible conductors may be The three types of functional units are de-
used provided that they are securely fastened. scribed above in the section Incoming and
outgoing units, p. ?.
Switching devices and components instal-
led in LV ASSEMBLIES Markings
Selection of switching devices and Inside the LV ASSEMBLY, it must be possible
components to identify individual circuits and their protec-
Switching devices and components incorpo- tive devices (switching devices and compo-
rated in LV ASSEMBLIES, as well as co- nents).
ordination of switching devices and compo- Items of equipment in the LV ASSEMBLY

23

5.2 23 97-03-05, 13.22


INDUSTRIAL POWER SYSTEM
Low voltage distribution

are to be designated, and the designations must rials to the temperatures reached, are all to be
be identical with those in the wiring diagrams taken into consideration.
which may be supplied together with the LV Connections between current-carrying parts
ASSEMBLY, and are to be in accordance with are to be established by means that ensure a
the International standard publication IEC 750. sufficient and durable contact pressure.

Identification Electronic equipment supply circuits


Where appropriate, the identification of the and electronic equipment incorporated
conductors of main and auxiliary circuits is to in LV ASSEMBLIES
be in accordance with international standard General
publications IEC 445 and IEC 446. The protec- When electronic equipment is incorporated in
tive conductor (PE) is to be readily distinguish- LV ASSEMBLIES it is important to take into
able by shape, location, marking or colour. If consideration the interference factor, or elec-
identification by colour is used, it must be green tromagnetic compatibility (EMC).
and yellow (twin-coloured). When the protec- There are several sources of interference that
tive conductor is an insulated single-core cable, must be taken into account to ensure interfer-
this colour identification is to be used, prefer- ence-free operation. They come under the fol-
ably throughout its whole length. lowing headings:
Any neutral (N) conductor in the main circuit
should be readily distinguishable by shape, •ThisConducted interference
group has a very wide frequency range and
location, marking or colour. If identification by
can be subdivided into the following groups:
colour is used, it is recommended that a light
blue colour be selected. a) Low-frequency interference
Any combined neutral and protective con- b) Medium-frequency interference
ductor (PEN) is, like the PE conductor and the c) High-frequency interference
N conductor, to be readily distinguishable by
shape, location, marking or colour. When the In addition to conducted interference, electron-
PEN conductor is an insulated single-core ca- ics can be affected by:
ble it is recommended that a green and yellow
• Electrostatic discharges (ESD)
(twin-coloured) scheme be selected, preferably
• Radio interference
throughout the whole length, with a light blue
• Low-frequency magnetic fields
marking at the connection points (the end
• Input voltage variations
points).
• Overvoltages
The terminals for external protective con-
• Waveform
ductors (PE) are to be marked with the earth
sign as per international standard publication
• Temporary
frequency
variations in voltage and

IEC 445 This symbol is not required where the The requirements are stated in the standard
external protective conductor is intended to be mentioned.
connected to an internal protective conductor It is recommended that Chapter 13.9
which is clearly identified with the colours Electronic and magnetic disturbances be read.
green and yellow.
Test specifications (8 in IEC 439-1)
Electrical connections inside an LV ASS- General
EMBLY: bars and insulated conductors The tests to verify the characteristics of an LV
General ASSEMBLY include :
The connections of current-carrying parts are
• Type tests
not to suffer deterioration as a result of normal
temperature rise, ageing of the insulating mate-
• Routine tests

rials or vibrations occurring in normal opera- Type tests (8.2 in IEC 439-1)
tion. In particular, the effects of thermal expan- Type tests are intended to verify compliance
sion and of electrolytic action in the case of with the requirements laid down for a given
dissimilar metals, and the reaction of the mate- type of LV ASSEMBLY.

24

5.2 24 97-03-05, 13.22


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Type tests will be carried out on a sample of Note: The performance of the routine tests at the
such an LV ASSEMBLY or on such parts of manufacturer´s works does not relieve the firm install-
ing the LV ASSEMBLY of the obligation of checking
LV ASSEMBLIES manufactured to the same
it after transport and installation.
or similar design.
Summary
Type tests include: It is very important that there be a dialogue
a) verification of temperature-rise limits between the manufacturer and the user so that
b) verification of dielectric properties the LV ASSEMBLY meets the customer´s (the
c) verification of short-circuit withstand user´s) expectations.
strength
d) verification of the effectiveness of the
protective circuit
e) verification of clearances and creepage Sizing factors
distances Different types of loads
f) verification of mechanical operation It is very important to clearly specify the type of
g) verification of the degree of protection load when planning. Motor data alone is not
(IP Code) sufficient information to determine what motor
starter is needed. For correct sizing, more infor-
These tests may be carried out in any order and/ mation about the type of machine that the motor
or on different samples of the same type. will drive is necessary. The following points
If modifications are made to the components are to be considered.
of the LV ASSEMBLY, new type tests have to
be carried out only insofar as such modifica- Motor load
tions are likely to adversely affect the results of The driven machine generates requirements for
these tests. starting method, starting time, starting current,
The type tests are described in detail in the utilisation category (AC category), required
above standard. lifetime, etc. The starting current, for example,
can cause problems when a circuit breaker is
Routine tests (8.3 in IEC 439-1) chosen as short-circuit protective device. Even
Routine tests are intended to detect faults in with theoretically correct sizing, problems can
materials and workmanship. They are carried occur, for example, when the motor is over-
out on every new (delivered) LV ASSEMBLY sized, since the connection current is propor-
after its assembly or on each transport unit. A tional to the size of the motor.
further routine test at the place of installation is See Chapter 4.4 Motor starting systems.
not required.
LV ASSEMBLIES which are assembled Distribution transformers
from standardised components outside the For optimum setting of the protection the start-
works of the manufacturer of these compo- ing current must also be considered here. In
nents, by the exclusive use of parts and acces- unfavourable conditions it can be over 30 x In,
sories specified by the manufacturer for this which requires a time-lag on the short-circuit
purpose, are to be routine-tested by the firm protective device. Another important point is
which has assembled the LV ASSEMBLY. the load of the transformer. The transformer
can temporarily cope with an overload. The
Routine tests include: protective breaker does not need to be over-
a) inspection of the LV ASSEMBLY including sized to manage this, but the protection must
wiring and, if necessary, an electricalope- cover the transformer´s whole field of applica-
ration test tion.
b) dielectric test See Chapter 5.4 Transformers, Distribution
c) checking of protective measures and of transformers, p. ?.
the electrical continuity of the protective
circuit Furnaces
These tests may be carried out in any order. Large current peaks can occur, depending on

25

5.2 25 97-03-05, 13.22


INDUSTRIAL POWER SYSTEM
Low voltage distribution

the type of furnace. An arc furnace generates (gas-tight joints). Contacts in breakers, contac-
complicated overtones. tors, switches, etc., plug-in contacts for main
circuits and auxiliary circuits and plug-in con-
Power electronics for rev/min-adjusted tacts for electronics are examples of contact
drives (Current converter, frequency surfaces that are not protected against corrosive
converter, soft starter) gases.
Generating of overtones is common in all appli- In hostile environments special measures
cations with power electronics that can disturb must be adopted to prevent corrosion and the
sensitive equipment. This imposes special re- subsequent rise in resistance. The consequences
quirements on the earth fault equipment in a for main current paths (busbars, busbar connec-
non-direct-earthed circuit. More problems can tions, breaking contacts, fuses, plug-in contacts,
occur when a thyristor and a frequency con- etc.) can be high temperature rise, flashover and
verter are in the same system. arcing, with damage to material, long periods
This type of equipment is more frequently of downtime (loss of production) and worst
seen in modern LV ASSEMBLIES and the of all, serious injuries to operators, etc.
temperature rise becomes an important sizing Where electronics is concerned, the attack
factor. on contact surfaces could lead to temporary or
See Chapter 4 Electric drive systems, p. ?. permanent interruption in control circuits; in-
terruptions that lead to operational disturbances
Lighting and loss of production.
Fluorescent tube fittings also generate over-
tones that can be disturbing in a system. These Which gases are the ”villains”?
also consume reactive power and might need In industrial environments the most common
power factor correction. See the section Termi- aggressive gases are sulphur hydrogen (H2S),
nals for external conductors (sizing of the neu- chlorine (Cl2), nitrogen (NO2) and sulphur di-
tral (N) conductor) under Mechanical design oxides (SO2). All of these gases are separately
on p. ?. corrosive, but combined, they lead to even
faster degradation.
Capacitor banks
Power factor correction and the need for filters • SO occurs in the petrochemical, pulp and
2
paper, and metal-producing industries.
in distribution systems are described in Chapter SO 2 attacks all metals except precious
6 Reactive power compensation, p. ?. metals such as gold, silver and platinum.
Capacitor inputs and outputs require special
connection devices. In general, they must be • NO2 occurs when burning oil, petrol and
coal (fossil fuels).
over-sized by 30 % and the possibility of re- NO2 is aggressive towards copper and brass
ignition during the breaking sequence must be and, together with SO2, increases the degra-
minimised. Re-ignition generates overvoltages dation of many materials. (Together with
which can damage the capacitors and other reactive chlorine even gold can be affected.)
devices.
• H2S occurs in the pulp and paper and chemi-
cal industries.
H2S attacks all copper based metals. In dry
Environmental aspects environments even silver can suffer dam-
As mentioned above, LV ASSEMBLIES are age.
usually designed for indoor location in normal
service conditions. See the section Service con-
• Cl2 occurs in bleaching plants, in pulp and
paper industries and in the production of
ditions, p. ?. PVC.
In some industrial environments, however, Reactive chlorine, Cl2, affects most metals,
there is a high level of corrosive gas, which can even in low concentrations. In combination
have an adverse effect on the functions of the with other pollutants its effects are aggra-
components and devices. The most sensitive vated.
parts are the contact surfaces, where it is impos-
sible to maintain a very high contact pressure
• Cl, chlorides, mostly arise from seawater.
They attack most metals.

26

5.2 26 97-03-05, 13.22


INDUSTRIAL POWER SYSTEM
Low voltage distribution

• Grime, smoke and dust attract other kinds


of pollution and moisture, increasing the
that apply are to be complied with, or else
special agreements are to be reached between
rate of corrosion. user and manufacturer. The user should in-
• Moisture (together with pollution) acceler-
ates corrosion.
form the manufacturer if such exceptional
service conditions exist.
(Note. To avoid static electricity discharges Such special service conditions are, for
that interfere with electronics, the relative hu- example:
midity should not be less than 30 %.) 1. Values for temperature, relative humidity
If the proportion of pollution in the air is and/or altitude that differ from normal ser-
too high, 1-100 m/m3, steps must be taken vice conditions.
to decrease the risk of corrosion in and on the 2. Applications where variations in tempera-
LV ASSEMBLY. Location of the LV ASSEM- ture and/or air pressure take place at such
BLY in the same operating rooms as air treat- speed that exceptional condensation is lia-
ment equipment (ventilation systems) is com- ble to collect inside the LV ASSEMBLY.
mon in the heavy process industries (pulp, 3. Heavy pollution of the air by dust, smoke,
paper, petrochemical and steel industries). corrosive or radioactive particles, fumes
In such harsh environments surface coating or salt.
of copper and/or aluminium bars with tin, or in 4. Exposure to strong electric or magnetic
some cases silver, is recommended. fields.
The trend towards dividing the LV ASSEM- 5. Exposure to extreme temperatures, for ex-
BLY into main distribution (Load Centre, LC) ample radiation from sun or furnaces.
and sub-distribution (Motor Control Centres, 6. Attack from fungi, vermin, rodents, etc.
MCC), has the consequence that the MCCs are 7. Installation in locations where fire or explo-
located as close as possible to the process sion hazards exist.
equipment and are exposed to aggressive gases, 8. Exposure to severe vibrations and impacts.
which can be removed in the operating room 9. Installation in such a manner that the cur-
through filtering in the air treatment equipment rent-carrying capacity or breaking capac-
(see above). See the sections Introduction, p. ?, ity is affected, for example equipment built
and Plant design, p. ?.The surfaces of the enclo- into machines or recessed into walls.
sures for these MCCs should be treated to resist 10. Appropriate measures to counteract elec-
corrosion. trical or radiated interference need to be
Built-in devices and components must be taken into account.
chosen with the best contact material possible.
For more information on corrosion it is recom-
mended that”Corrosion of electronics” a hand- Plant design
book based on experiences from a Nordic Re- Introduction
search Project (Bulletin No 102, Swedish Cor- The planning of an industrial system involves a
rosion Institute, August 1991) be read. See also great deal of money, both in direct investments
Chapter 3.5Industrial Environments, p. ?. and future running costs. However, a system-
Apart from air pollution, the location and atic approach and an overall view of the prob-
surroundings of the LV ASSEMBLY can in- lems are often lacking.
volve problems, e.g. vibrations and humidity Designing an industrial low-voltage distri-
and large differences in temperature between bution network requires experience, extensive
night and day (leading to condensation). It is, knowledge, intuition and analytical ability.
as mentioned earlier, vital that the manufac- How should one start to design and size an
turer obtain information from the user regard- industrial system, what considerations need to
ing all factors that affect the design of the be examined and what are the most important
LV ASSEMBLY. issues to be addressed? These problems are not
new and most of the design technique has been
Special service conditions available for decades.
Where any of the following special service However, over the last few years new tech-
conditions exist, the particular requirements nology has been developed that offers fresh

27

5.2 27 97-03-05, 13.23


INDUSTRIAL POWER SYSTEM
Low voltage distribution

opportunities in plant design. Further, mainte- MCCs) out closer to the process equipment
nance costs can now often be reduced. has always existed. However, this arrange-
The power system represents some 10-15 % ment has not been viewed with favour in the
of the capital costs for a major industrial project. past due to the adverse effects of the surround-
There are several ways to plan an LV ASSEM- ings (see the section Environmental aspects,
BLY design, but two main principles apply: p. ?) on the bars, fuses, circuit breakers, mov-
able contacts (e.g. plug-in contacts) and elec-
1) Place the transformer next to the LV AS- tronics. In recent years, though, equipment has
SEMBLY and collect all units and devices in
been developed to protect the electrical parts
a single LV ASSEMBLY located in a locked
when they are located close to the process.
operating room. This distribution system (with the distribu-
2) Split the LV ASSEMBLY equipment up tion LV ASSEMBLY or the MCC located close
into main distribution Load Centre (LC) and to the process equipment) results in lower short-
sub-distribution Motor Control Centres circuit currents in the LV ASSEMBLY con-
(MCCs). cerned. This design results in lower investment
costs for the LV ASSEMBLY and lower costs
See the section General, Introduction, p, ? and for installation (e.g. cable costs) and for venti-
the single-line diagram in Fig. 2, p, ?. lation equipment.
The load centre (LC) is direct fed from the
transformer and is normally designed for high Voltage levels
currents. It distributes the current to sub-distri- The size of the process, i.e., the power required,
bution MCCs (which can be placed near the determines to a certain extent if one or several
process). voltage levels are needed. Selection of voltage
Sub-distribution units (distribution switch- level cannot be made until after the circuit
gear and MCCs) are most often fed via cable system has been settled on. For major indus-
from units in the load centre. The cable area and tries with a considerable number of large mo-
length (impedance) determine how much of the tors it may be more advantageous economi-
short-circuit current is limited at the sub-distri- cally to select two main voltage levels, 400 V
bution point. This limitation makes it possible and 690 V. If a main voltage of 690 V is used,
to design sub-distribution for the reduced short- a voltage of 10 kV can normally be used as
circuit current. It also provides the possibility motor voltage for high voltage drives. For an
to use circuit breakers with a lower tripping AC system with a nominal voltage of 120 to
value in the outgoing feeder units. See the 1000 V and with the appropriate equipment, the
section Short-circuit levels, p, ?. values shown in the table below apply.
A common arrangement is to place the trans-
former near the LV ASSEMBLY and collect all Three-phase 4-wire or 3-wire system (IEC 38)
units and devices in this LV ASSEMBLY. This Three-phase, four-wire Single-phase,
design gives a good overview of the distribu- or three-wire systems three-wire
tion system, which is located in a locked oper- systems
ating room.
Nominal voltage Nominal
See above in the section Introduction, p. ?. (V) voltage (V)
The operating room is cleaned and ventilated
to protect the electrical equipment against cor- – 120/240
rosion. See the section Environmental aspects, 230/4001) –
p. ?. 277/4802) –
This kind of design normally implies long 400/6901) –
cables and high short-circuit currents in the 1000 –
LV ASSEMBLY. High short-circuit currents
make it necessary to select more advanced Under normal system conditions it is recom-
apparatus. mended that the voltage at the supply terminals
The possibility of moving the LV ASSEM- should not differ from the nominal voltage by
BLIES (distribution LV ASSEMBLIES or more than +/- 10 %

28

5.2 28 97-03-05, 13.23


INDUSTRIAL POWER SYSTEM
Low voltage distribution

1)
The nominal voltage of existing 220/380 V and The lower value states the voltages between
240/415 V systems is to evolve towards the recom- phase and the neutral conductor (N conductor)
mended value of 230/400 V. The transition period and the higher value states the voltage between
should be as short as possible and should not phases.
exceed 20 years aftter the issue of the IEC stand-
Three-phase systems with a voltage of 400/
ard publication (= year 2003).
During this period, as a first step, the electricity
690 V are intended only for heavy industrial
supply authorities of countries having 220/380 V applications or similar. Some industries have
systems should bring the voltage within the range an internal distribution system using a main
230/400 V +6 %, -10 % and those of countries voltage of 500 V.
having 240/415 V systems should bring the voltage
within the range 230/400 V +10 %, - 6 %. At the end Short-circuit levels - Rated current and
of this transition period the tolerance of 230/400 V Short-circuit current
+/- 10 % should have been achieved; after this a The transformer data and wiring give the nec-
reduction of this range will be considered. All the essary information on the principal data needed
above considerations also apply to the present for the LV ASSEMBLY. The most important
380/660 V value with respect to the recommended data are:
value 400/690 V.
2)
Not to be utilised together with 230/400 V or 400/
690 V. • Main voltage and frequency
As can be seen, the table includes single- • Rated current
phase circuits connected to three-phase, four- • Short-circuit level
wire systems. • Connection

Example of calculation of rated current and short-circuit current


Transformer data: 2 MVA, 10,000/400 V (10/0.4 kV), uk= 6.25 %
Rated current, In= 2,000,000/400 x 3= 2890 A
Short-circuit current, Ik= 2,000,000 x 100/400 x 3 x 6.25= 46 kA

Ik depending on transformer and cable, U= 400 V

Pn uk Ik Ik limited by the cable impedance


Cable Cable Cable
25 mm2 95 mm2 240 mm2
Cu Cu Al
Length m Length m Length m
kVA % kA 25 100 25 100 25 100
1000 5.00 29 8 3 14 5 19 10
1250 5.00 36 8 3 15 5 20 10
1600 6.25 37 8 3 16 5 22 11
2000 6.25 46 9 3 16 5 23 11
2500 6.25 58 9 3 18 6 27 11

Ik= Short-circuit current


Pn= Rated power
uk= Short-circuit voltage in %

Diversity factor ship of the maximum sum, at any one time, of


The rated diversity factor of an LV ASSEM- the assumed currents of all the main circuits
BLY or part of an LV ASSEMBLY having involved, to the sum of the rated currents of all
several main circuits (e.g. a section or a sub- the main circuits of the LV ASSEMBLY or the
section) is the ratio obtained from the relation- selected part of the LV ASSEMBLY.

29

5.2 29 97-03-05, 13.23


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Standard rated (recommended) diversity Directly earthed system, TN system, (TN-C


factors (IEC 439-1): and TN-S)
Number of main circuits Diversity factor Figs. 6 and 7 (figur 24 and 25, p. 332)
2 and 3 0.9
4 and 5 0.8
6 to 9 inclusive 0.7
10 (and above) 0.6

Types of distribution system; TN, IT,


and TT systems (IEC 364-3)
The following characteristics of the distribu-
tion system are to be assessed:

• types of live conductor


• types of system earthing Not-directly-earthed systems, IT systems
These have all live parts isolated from earth or
Types of live conductor systems: one point connected to earth through a high
AC systems DC systems impedance, the exposed conductive parts of the
Single-phase 2-wire 2-wire electrical installation being earthed independ-
Single phase 3-wire 3-wire ently or collectively or connected to the system
Two-phase 3-wire earthing. Not-directly-earthed systems are only
Two-phase 5-wire utilised in industrial establishments and are to
Three-phase 3-wire (3 phase conductors have an earth fault protection.device that indi-
+ PEN conductor) cates earth faults. An earth fault protective
Three-phase 4-wire (3 phase conductors device of this kind can be arranged through zero
+ PE conductor + N conductor) point equipment.

Types of system earthing


Directly earthed systems, TN systems
These have one point directly earthed, the ex-
posed conductive parts of the installation being
connected to that point by protective conduc-
tors (PE).
Three types of TN system are considered
according to the arrangement of neutral and
protective conductors, as follows:
Fig. 8 Not-directly-earthed system, IT sys-
TN-S system: in which, throughout the tem
system, a separate protec-
tive conductor (PE) is used; TT system s have one point directly earthed,
the exposed conductive parts of the installation
TN-C-S system: in which neutral and protec- being connected to earth electrodes electrically
tive functions are combined independent of the earth electrodes of the
in a single conductor (PEN) power system.
in a part of the system; Note: TT systems are to be used very restrictively.

TN-C system: in which neutral and protec- Demands on availability


tive functions are combined Maintenance work should be kept in mind
in a single conductor (PEN) during the projecting/planning period. If con-
throughout the system. tinuous operation is required, the system must
be designed so that bypass links and standby
supply possibilities are ensured so that neces-

30

5.2 30 97-03-05, 13.24


INDUSTRIAL POWER SYSTEM
Low voltage distribution

sary inspections of those components that re- 2. By incoming disconnector


quire the circuit being broken can be carried With a normal disconnector as incoming de-
out. See also the section Requirements related vice, making or breaking cannot/should not be
to accessibility in service by authorised per- carried out using the disconnector. See the
sonnel, p. 13 ?. section Disconnectors, p. ? 29. A disconnector
on its own normally has no breaking/making
Selectivity (p. 332 in the Swedish edition) capacity and should therefore be operated only
Selectivity refers to disconnecting only part of when not under voltage.
the equipment that is affected by the fault. With a switch-disconnector, voltage can be
Selectivity is brought about by co-ordinating switched on and off, but making and breaking
different current and time curves, and/or with of a high-current load is not recommended.
time functions. A switch-disconnector can be supplied with
More detailed information on selectivity auxiliary contacts and an interlocking magnet,
is provided in the section Selectivity plan, p, ?. which prevents incorrect manoeuvring.
(p. 315). The disconnector allows switching off so
as to carry out work on the LV ASSEMBLY,
Connection to the LV ASSEMBLY (see the section Disconnection for work pur-
Connection of incoming supply conductors from poses, p. ? 27) but no protection functions
the transformer to the LV ASSEMBLY can be can be accomplished through automatic dis-
effected in one of the following ways: connection.
1. By incoming circuit breaker A disconnector is often used as an inexpen-
2. By incoming disconnector sive solution, or when there already is an effec-
3. By switch and fuses tive protective device in the supply system.
4. By direct connection from the transformer Sometimes disconnectos are used by selectiv-
to the main busbars in the LV ASSEMBLY ity reasons, i.e., when a chain of selectivity
cannot be built up without an incoming circuit
1. By incoming circuit breaker breaker tripping. This is a bad argument since
An incoming circuit breaker is the best and selectivity can often be achieved by means of
most dependable (in many countries a demand) time characteristics. The breaking and protec-
solution for connection to LV ASSEMBLIES. tion functions must be located in the supply
Having a circuit breaker allows quick dis- system.
connection in the event of faults. See the sec-
tion Circuit breakers, p.?. If work is needed 3. By switch and fuses
on the LV ASSEMBLY it is then easy to dis- Breaking and protection against overloads and
connect and selectivity can be accomplished short circuits can be achieved by using switches
through time functions in the breaker´s protec- and fuses in the incoming unit.
tive device. The units can hardly be rated for more than
Circuit breakers normally have overload 800 A (largest fuse) and only occur in small LV
protection, delayed and instant shortcircuit ASSEMBLIES and multibox-type LV ASSEM-
protection, earth-fault protection and under- BLIES.
voltage protection. If only switches are used, the protection
The circuit breaker can be remotely control- function is lost, but breaking is naturally still
led by a motor-operated apparatus. Measuring, possible.
automatic making/breaking of contacts and
reconnection are possible. 4. By direct connection from the transformer
If the LV ASSEMBLY is supplied with arc to the main busbars in the LV ASSEMBLY
guards connected to the circuit breaker on The breaking and protection functions have to
the low-voltage side of the transformer, a be located in the supply line
fast tripping time is obtained even when arc (on the primary side of the transformer, a me-
faults occur giving limited fault currents in dium-voltage circuit breaker with protective
the LV ASSEMBLY. See the section Arc devices is necessary).
guards, p. ? 39.

31

5.2 31 97-03-05, 13.24


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Disconnection for work purposes The first two are not to be recommended.
Disconnection of a plant part for work purposes The safest, most up-to-date and most used
should be executed such that power supply is method is to fit earthing switches in the incom-
prevented from all directions. Fully adequate ing circuit breaker cubicle in an LV ASSEM-
safety devices should be used. BLY (often both before and after the circuit
Where the power supply is from several breaker).
directions, or where there are no electrical The earthing switch can be operated from the
switches, special care needs to be taken to front of the cubicle with door closed.
prevent errors. The primary side of the earthing switch is
connected to the phases and the secondary side
To ensure that the necessary level of security is is short-circuited and connected to the protec-
achieved, disconnection is required using one tive earth bar (PE).
of the following methods: The earthing switch is to be interlocked with
1. Disconnection of a voltage not exceeding the circuit breaker via auxiliary contacts and
1000 V AC : can further be interlocked with a blocking mag-
1.1 Use of disconnector or switch-discon- net to prevent incorrect operation.
nector with visible breaking points See the single-line diagram below.
1.2 Use of switch-disconnector without vis-
ible breaking points, provided with reli-
able position indications.
1.3 Use of ”safety switch”
1.4 By removing fuse-links
1.5 Use of other electrical switches than un-
der items 1.1 and 1.2 in combination with
earthing for work purposes behind closed
cubicle front or similar.
It is presupposed that:
– interlocking between electrical switch
and earthing device is so arranged that it is not
possible to perform earthing before the electri-
cal switch has broken the circuit
in all phases.
– earthing can be carried out without risk
of injury to operators, etc., even if it is per-
formed on live parts. Earthing device with earthing switches
See the following section Earthing for Fig. 9 ?
work purposes.
1.6 Use of withdrawable units in disconnected
position (see the section Incoming and
outgoing units, p. ? 6) Apparatus and combination
1.7 Other ways than those under items 1.1 to of apparatus
1.6; methods that can be easily checked
visually. Disconnectors (IEC 947-3)
A disconnector is a mechanical switching de-
Earthing for work purposes vice which, in the open position, complies with
Earthing of an LV ASSEMBLY when working the requirements specified for the isolating
in it, or close to it, is a precautionary measure to function (isolating distance).
make sure that no accident will occur. A disconnector is capable of opening and
There are three methods: closing a circuit when either negligible current
1. Earthing device with earthing cable is broken or made, or when no significant
2. Earthing device with earthing lance change in the voltage across the terminals of
3. Earthing device with earthing switch each of the poles of the disconnector occurs.

32

5.2 32 97-03-05, 13.24


INDUSTRIAL POWER SYSTEM
Low voltage distribution

It is also capable of carrying currents under contact separation of main contacts will be
normal circuit conditions and carrying for a prevented. It should be possible in all cases to
specified time currents under abnormal condi- perform operations with satisfactory safety.
tions such those of short-circuit. If the switch is to be used as a switch-
A disconnector normally has no breaking/ disconnector when working on a part of a
making capacity and should only be operated plant the switch must be chosen to conform
when under no voltage. with Utilisation Category AC 21 (see Utilisa-
tion categories above and the section Discon-
Switches (IEC 947-3) nection for work purposes, p. ? 27).
A mechanical switch is a switching device Switches can normally be supplied with aux-
capable of making, carrying and breaking cur- iliary contacts for indicating of on/off position.
rents under normal circuit conditions, which
may include specified operating overload con- Fuses (IEC 269)
ditions, and also carrying for a specified time A fuse is a device that, by the fusing of one or
currents under specified abnormal circuit con- more of its specifically designed and propor-
ditions such as those of short-circuit. tioned components, opens the circuit in which
Note: A switch may be capable of making but not it is inserted by breaking the current when this
breaking short-circuit currents. exceeds a given value for a sufficient time. The
fuse comprises all the parts that form the com-
Utilisation categories plete device.
(The utilisation categories define the intended The fuse represents a weakness in the wire
applications.) system, and contains a meltable wire called a
AC 21 Switching of resistive loads including fuse-element. The fuse-element is designed and
moderate overloads sized to melt when the current exceeds a certain
AC 22 Switching of mixed resistive and in- value, and consequently the circuit is broken.
ductive loads, including moderate over- In most fuses the wire is enclosed in a fuse-
loads link made of porcelain and filled with quartz
AC 23 Switching of motor loads or highly sand. The quartz sand makes it easier to switch
inductive loads off the arc inside the fuse-link at the moment
of tripping. The most common material in the
The requirements of switch tripping and break- fuse-element is silver for low currents and
ing capacity are related to which of the three a thin silver-plated copper strip for higher
utilisation categories the switch comes under. currents. The temperature rise in the fuse-
A switch should always be protected by an element is proportional to the square of the
overcurrent/overload protective device (fuse). rated current. The higher the current, the quicker
In the data for the switch, the maximum rated the temperature rise. When the fuse-element
current for the pre-connected fuse, related to melts and the metallic connection breaks, an
the prospective short-circuit current in the ac- arc ignites over the breaking gap. The heat of
tual circuit, should be mentioned. the arc melts and turns the fuse-element into
The fuse is normally connected after the gas. When the impedance becomes too high
switch because it is considered that the design through the arc, the energy is no longer enough
is such that a short circuit will not occur in the to maintain the arc and this is extinguished.
fuse-combination unit (switch+fuses). Any fault The breaking sequence when the fuse blows
is expected to take place after the combination. can be divided into two phases, the melting
The requirement of short-circuit safety is time and the arcing time. The total breaking
related to the prospective short-circuit current time for the fuse is thus the sum of these two
of the actual circuit and the maximum stated times.
fuse size for the switch. Fuses can be divided up according to two
If a fault occurs, this combination will pro- different principles, those of mechanical de-
vide protection so that switching can be per- sign: D-type fuses (diazed fuses) and blade-
formed without, for example, contact welding fuses, and those with a disconnection function:
occurring, or if the fault occurs during running, gG and aM fuses.

33

5.2 33 97-03-05, 13.25


INDUSTRIAL POWER SYSTEM
Low voltage distribution

gG fuses have a disconnection characteristic


which ranges from 1.6 times the rated current as
stamped on the fuse up to current-limiting char-
acteristics at very high fault currents.

aM fuses have no thermal protective function.


Their breaking characteristic does not start un-
til at 6.3 times the rated current as stamped on
the fuse. At higher currents, on the other hand,
the aM fuses have a steeper breaking character-
istic, which makes it easier to size the apparatus
behind them.
The rated current for blade-fuses is from
6 A up to 800 A with rated voltage = 690 V. Current limiting diagram, Fig. 11 ?
The rated current for D-type fuses is from
2 A up to 100 A with rated voltage = 500 V. I2t diagram
A longer type of fuse-link exists for 690 V The I2t value is a measure of how much energy
rated voltage. the fuse lets through for different fault currents.
This diagram is thus of great significance when
Melting-time diagram sizing, for example, apparatus, cables and se-
For melting times above 100 ms the arcing lectivity calculations involved in the circuit.
time has a very little significance, since this
time is relatively short. For a melting time
below 100 ms the arcing time assumes greater
significance.

Melting-time diagram Fig. 10 ? I2t diagram, Fig. 12 ?

Contactors (mechanical) (IEC 947-4-1)


Current-limiting diagram A contactor is a mechanical switching device
In the case of very high currents through the having only one position of rest, operated other-
fuse, any fault current present will be limited. wise than by hand, capable of making, carrying
This means that the circuit will be broken and breaking currents under normal circuit con-
before the fault current reaches its highest value. ditions including operating overload conditions.

34

5.2 34 97-03-05, 13.25


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Note: Contactors combined with suitable relays and Other advantages of some contactor relays are
which are intended to provide short-circuit protection fast mounting on profile bars and high-speed
must also satisfy the relevent conditions specified for
circuit-breakers (IEC 947-2). plug-in connection.

Brief description and requirements There are two types of contactors:


The contactor must be able to withstand a short • Contactors for main circuits
circuit if it is combined with a suitable short-
circuit protective device. The contactor does not
• Contactor relays for auxiliary circuits.
This type of contactor is not described in
need to be able to break short-circuit currents. this book.
The contactor is normally operated by an The normal rated current range for contactors
electro-magnet but some pneumatic controlling is from 9 A up to a maximum of 800 A (for
devices also exist. A contactor cannot be oper- motors, the power range 4 kW to 450 kW).
ated manually.
Contactor features include a high operating Recommended utilisation categories
frequency, a long life, and the possibility of (The utilisation categories define the intended
remote control and of automatic operation via a application.)
pilot switch or a sensor. The rated current for a contactor depends on
how the contactor is to be used.

Standard utilisation categories for contactors and motor starters


Type of current Utilisation Typical
categories applications

AC AC-1 Non-inductive or slightly inductive loads, resistance furnaces


AC-2 Slip-ring motors: starting, switching off
AC-3 Squirrel-cage motors: starting, switching off motors
during running
AC-4 Squirrel-cage motors: starting, rheostatic braking,
inching, reversing

DC DC-1 Non-inductive or slightly inductive loads,


resistance furnaces
DC-3 Shunt motors: starting, rheostatic braking, inching, reversing
Dynamic braking of DC motors
DC-5 Series motors: starting, rheostatic braking, inching, reversing
Dynamic braking of DC motors

General
For a contactor to work well, there are require- the operating frequency can be so high that it
ments of correct auxiliary circuit design and that results in flashovers due to ionised gas or abnor-
the tolerance level of the operating voltage is not mal contact wear. In most cases where a break-
exceeded. The contactor is the most hard-work- down occurs, such faults are the cause. It is very
ing power switch in an auxiliary circuit, with its rare that the fault is in the switchgear itself.
whole chain of conditions and demands. An The contactor must always be combined with
incorrectly designed auxiliary circuit can result a short-circuit protective device, normally fuses,
in a total breakdown. and for motor drives, overload protection as
A contactor can normally be operated much well. MCCBs may also be used as short-circuit
faster than the time de-ionising of the extin- and overload protective devices. See below the
guishing segments takes. When faults occur in section Selection of short-circuit protective de-
the auxiliary circuit (rebounds, unreliable con- vice (SCPD), p. ? 41.
tact-making or any other type of disturbance)

35

5.2 35 97-03-05, 13.26


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Service and maintenance with a cold relay, and here too there is a reduc-
Normal service includes checking the wear on tion to about a third for a hot relay.
the main contacts, and replacement when the
wear level is such that the spring force for a Electronic overload relays
switched-on contactor has reached the limit The use of electronic overload relays is becom-
value which is fixed for each contactor type. ing increasingly common. They are expensive,
The expected contact life is related to the but normally have a wide range of applications
type of drive/lifetime curve and this should be with several functions that are not available
borne in mind when sizing the equipment. with mechanical overload relays. An electronic
The contactor is usually fitted with a number relay requires a current transformer.
of auxiliary contacts. Among their functions the following can be
mentioned:
Overload relays (IEC 255-8)
An overload relay is an overcurrent relay or • Overload protection
release intended for protection against over- • Re-start protection
Phase failure protection
load. An overcurrent relay or release is a relay or • of starts per hour) (counting the number
release which causes a mechanical switching
device to open with or without time-lag when • Symmetry protection
the current in the relay or release exceeds a
predetermined value. The relays are microprocessor-based (see also
the section Microprocessor-based control
An overload relay is mostly used in combi-
technique for low-voltage systems, p. ? 49)
nation with a contactor in starters. See the
sections Motor starters, p, ? 36 and Selection of and sample values, ”draw curves” and compare
actual values with reference values. When these
overload protective device, p. ? 47.
diverge, the relay will give a signal, or trip.
Thermal overload relays (bi-metallic relays) The big difference between the electronic over-
load relay and the thermal overload relay is
A thermal overload relay is an inverse time-lag
the possibility the former has of varying the
overload relay or release depending for its
operation (including its time delay) on the ther- tripping time and setting the alarm before trip-
ping.
mal action of the current flowing in the relay or
release.
The most common overload relays are ther- Circuit breakers
A circuit breaker is a mechanical switching de-
mal overload relays, which are simple, robust
vice, capable of making and breaking currents
and cheap. They are either direct-fed or fed via
a current transformer. The relays should be under normal circuit conditions and also mak-
ing, carrying for a specified time and breaking
adjusted to the motor´s rated current (for star-
currents under specified abnormal circuit con-
delta starters = rated current /÷3), and are nor-
mally temperature-compensated from - 20oC ditions such as those of short-circuit.
Circuit breakers normally have both short-
to + 65oC. This means that the relays can work
circuit protective devices and overload protec-
in the most usual ambient temperatures without
any special calibration. tive devices. Undervoltage protective devices
are usual.
Modern overload relays are often fitted with
(See the section Fault control, undervoltage
protection against phase failure. Should there be
a phase failure, the relay then trips the contactor protection, p. ?)
The following types of circuit breaker are
before the motor´s two ”healthy” phases be-
standard:
come overheated.
Overload relays normally have two tripping
characteristics. Normal relays have a possible
• Air circuit breakers, ACBs (IEC 947-2)
An ACB is a circuit breaker in which the
starting time of 8-10 s when the relay is cold. For contacts open and close in air at atmospheric
a hot relay the possible starting time is reduced pressure
to about a third. Relays for heavy-duty starting
have a possible starting time of approx. 15-20 s
• Moulded case circuit breakers, MCCBs
(IEC 947-2)

36

5.2 36 97-03-05, 13.26


INDUSTRIAL POWER SYSTEM
Low voltage distribution

An MCCB is a circuit breaker having a support- MCB


ing housing of moulded insulating material MCBs are available for rated currents up to
forming an integral part of the circuit breaker 125 A, but 63 A is usually the highest value.
There are various designs, depending on
• Miniature circuit breakers, MCBs (IEC 898)
An MCB is a circuit breaker intended for
breaking capacity and characteristics. See Fig.
14, p. ? 35 (below).
protection against overcurrents in wiring MCBs are mainly used in auxiliary circuits
installations in buildings and in similar ap- and in distribution boards (instead of fuses).
plications; they are designed for use by in-
expert people and do not need being main- Differences between ACBs and MCCBs
tained Being subject to the same design standard it is
not surprising that the differences between
ACB ACBs and MCCBs are becoming finer. Where
ACBs are available for rated currents from 630 they exist it can be said that the main difference
A to 6300 A, but the range most frequently used lies in the possibility to add accessories and
is 1250 A - 3200 A. Until recently all ACBs opportunities for service and maintenance. In
were of non-current-limiting type with break- this respect MCCBs have limitations compared
ing capacity up to 85 kA. Now there are also to ACBs.
current-limiting ACBs with tripping times </= Further, there are better possibilities of de-
10 ms for current up to 2500 A. With tripping laying the short-circuit protection in an ACB,
times of 10 ms for such high currents, however, as an ACB can withstand a higher short-circuit
the trip overvoltage that is generated has to be current for a longer time than an MCCB. This
watched out for. There is now concentration on is shown by the rated short-time withstand
the development of built-in protective devices. current, the 1-second value, (see the section
Today more sophisticated, microprocessor- Short-circuit protection, p. ? 41), which is
based devices for protection with communicat- much higher for ACBs than for MCCBs.
ing ability to a monitoring system are available
at much lower costs than those of a separate Current-limiting circuit breakers
relay protection. One often refers to current-limiting and non-
The main field of application for ACBs is current-limiting circuit breakers, see Fig. 13 ?,
as incoming circuit breakers in an LV ASSEM- p. ? 35 (below). All MCCBs and MCBs are
BLY and as motor starters for large motors. more or less current-limiting, since the current
forces that arise upon a short circuit press the
MCCB contacts apart. This usually results in an arc,
MCCBs are available for rated currents from and thus an impedance which limits the current
1 A to 3200 A, but the range most frequently allowed through.
used is 10-630 A, and for incoming breakers up A current-limiting circuit breaker is a breaker
to 1600 A. Current-limiting and non-current- which is able to extinguish an arc before the
limiting breakers are available from most sup- current passes through neutral for the first time
pliers. The non-current-limiting breaker is of- after a short circuit has occurred. This gives
ten available in more designs with different extremely short break times.
levels of breaking capacity. Development is Non-current-limiting circuit breakers have
moving towards a better current-limiting ca- to wait for the current to pass through neutral
pacity. In the MCCB field too there are protec- before they extinguish the arc generated. This
tive devices based on electronics that are be- means that the break time is around 20 millisec-
coming more and more sophisticated. onds.
The overload protective devices in MCCBs It should be observed that current-limiting
are mainly used for protection of cables and breakers need a theoretical short-circuit current
conductors, but there are breakers in the lower of 20-30 kA to work correctly.
current area where the overload protective de-
vice is designed for motor protection and with Breaking capacity
the extra functions that this application needs. Breaking capacities for circuit breakers are

37

5.2 37 97-03-05, 13.26


INDUSTRIAL POWER SYSTEM
Low voltage distribution

described in the section Selection of short- Motor starters (IEC 947-4-1)


circuit protective device, p. ? 41. See also Chapter 4.4 Motor starting systems
(p. 140-164).
Utilisation categories A motor starter is a combination of all the
Category A: Circuit breakers not specifically switching means necessary to start and stop a
intended for selectivity motor in combination with suitable overload
Category B: Circuit breakers specifically in- protection, a manual externally-operated switch-
tended for selectivity ing device and a short-circuit protective device,
mounted and wired in a dedicated enclosure.
The switching and short-circuit protective
Strömbegränsande Ej strömbegränsande devices may be a fuse combination, a switch
I I
kA kA
with fuses or a circuit breaker with or without
50 50
an isolating function.
Note: 1. A dedicated enclosure is an enclosure
20 20 specifically designed and sized for its application,
in which all tests are conducted.
2. The manually-operated switching device
and the short-circuit protective device may be a
5 ms single device and may incorporate the overload
13 ms protection as well.

General: The most common outgoing units in


a Motor Control Center, MCC, are motor start-
ers. The main parts in a motor starter are:
I1 I2 Termisk utlösning Contactor for on/off switching of the motor
T
}

(s) K
current (see the section Contactors, p. ? 31)
B
K Short-circuit protective device, SCPD,
C K switch+fuses or circuit breaker, often an
D
MCCB (see the sections Switches, p. ? 29,
Circuit breakers, p. ? 34 and Selection of
103 SCPD, p. ? 41)
Thermal overload relay, in some cases an
electronic overload relay
(see the section Overload relays, p. ? 33)
102 The rated current for motor starters is limited to
a maximum of 700 A (400 kW output for
motors).

101
K

L U

B C D
100
1 3 5 10 ×In
}

Momentan utlösning
I3 I4

Figs. 13 and 14, Current-limiting diagram


and non-current-limiting diagram, Thermal
and instantaneous tripping of different
MCB types. Fig. 15 Motor starter
38

5.2 38 97-03-05, 13.27


INDUSTRIAL POWER SYSTEM
Low voltage distribution

1 9 5

I> I> I>

4 2 4 2 4 2

3 3

6
8

4 2 4 2

3 3

Fig. 16 Typical variants of motor starters,


circuit diagrams.

Utilisation categories Type 2 co-ordination requires that, under short-


Recommended utilisation categories for motor circuit conditions, the contactor or starter should
starters are the same as for contactors, see p. ? cause no danger to persons or installation and
32. must be suitable for further use. The risk of
contact welding is recognized, in which case
Co-ordination with short-circuit protective the manufacturer is to indicate the measures to
devices be taken with regard to the maintenance of the
Types of co-ordination: equipment.
(Conditions after a short-circuit test carried
out with bolted short-circuited outgoing termi- Important:After an actual short circuit the
nals.) location of the fault must always be pin-pointed
Type 1 co-ordination requires that, under short- and the motor starter examined and repaired
circuit conditions, the contactor or starter should before re-starting.
cause no danger to persons or installation and
may not be suitable for further service without See also the section Inspection of condition, p.
repair and replacement of parts. ? 45.

39

5.2 39 97-03-05, 13.27


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Main types of motor starters: Note: In star connection, the current in the line
1. Direct-on-line starter and the torque of the motor are about one-third of
This is a starter which connects the line the corresponding values for delta connection.
Therefore, star-delta starters are used when the
voltage across the motor terminals in one inrush current due to starting is to be limited, or
step. when the driven machine requires a limited torque
Direct-on-line starters are designed to start for starting.
and accelerate a motor to normal speed, to
provide means for the protection of the 4. Pole changing starter
motor and its associated circuits against This is a starter for motors with multiple
operating overloads, and to switch off the speeds. These motors could have two
supply from the motor. windings, with a different number of poles
This also applies to reversing starters. for different speeds, or a switchable winding
so that that the number of poles is divided
2. Reversing starter into halves upon switch-over, a so-called
This is a starter designed to cause the motor Dahlander connection. Pole-changing start-
to reverse the direction of rotation by revers- ers for Dahlander-connected motors have
ing the motor´s primary connections while an extra contactor for the switch-over from
the motor is running. See also above under high speed to low speed or vice-versa.
direct-on-line starters, second paragraph.
3. Star-delta starter 5. Two-step auto-transformer starters
This is a starter for a three-phase induction This is a starter designed to start and accel-
motor such that in the starting position the erate an AC induction motor from rest with
stator windings are connected in star and in reduced torque to normal speed, to provide
the final running position they are connected means for the protection of the motor and its
in delta. Star-delta starters are designed to associated circuits against operating over-
start a three-phase motor in star connection, loads, and to switch off the supply from the
to ensure continuous operation in delta con- motor.
nection, to provide means for the protection Auto-transformer starters are normally not
of the motor and its associated circuits against intended for inching duty or reversing mo-
operating overloads, and to switch off the tors rapidly and therefore Utilisation Cat-
supply from the motor. egory 4 does not apply.
Star-delta starters are not normally designed
for reversing motors rapidly and therefore
Utilisation Category 4 does not apply.
I L 0.8 tap I T 0.5 tap I L 0.65 tap
IR
6
Current /rated operational current I e

6
Current /rated operational current I e

ID 5 IT 0.8 tap

5 IT
4 0.65 tap

4
3

3
2 IL 0.5 tap
IY Synchronous speed
2
1
Synchronous speed
1
0.8 1 Speed/rated speed

0.8 1 Speed/rated speed


Torque/rated torque

Torque/rated torque

CM D CM R
1 1
Synchronous speed 0.65 tap Synchronous speed
CM Y CM T

CR CR

0.8 1 Speed/rated speed 0.8 1 Speed/rated speed

Fig. 17 Typical curves of currents and tor- Fig. 18 Typical curves of currents and tor-
ques during a star-delta start. ques during an auto-transformer start.

40

5.2 40 97-03-05, 13.27


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Note: In the starting position, the current in Voltage


the line and the torque of the motor related DoL Star/Delta Softstart
to motor starting with rated voltage are reduced 100%
approximately as the square of the ratio: starting
voltage/rated voltage. Therefore, auto-transformer
starters are used when the inrush current due to
the starting operation is to be limited, or when 60%
the driven machine requires a limited torque 58%
for starting. Adjust-
able
starting
Accessories ramp
Motor starters can be supplied with various 10%
accessories such as:
• indicating lamps Fig. 20. Motor voltage when starting with dif-
• on and off pushbuttons ferent starting methods.
• auxiliary relay for remote control
Current limiters
• switch for choice of remote control and
local control Current limiters are used as complementary
short-circuit protective devices for smaller
• ammeter
motors (max. approx. 22 kW, max. rated cur-
• remote reset by thermal overload relay
rent approx. 50 A).
Soft starters A current limiter, based on polymeric mate-
A soft starter is a starter which is supplied with rial, acts as a conductor at rated currents but
six anti-parallel-connected thyristors. The becomes high resistive if a short circuit occurs.
thyristors´ ignition angle is controlled by a Consequently, the fault current is limited. A
microprocessor that increases the voltage to the current limiter is connected in series with a
motor during starting. There is a scale on the breaker (mostly an MCB) and will limit the
soft starter where the starting time can be ad- fault current to a value under the breaking
justed so as to achieve a soft start. The soft capacity of the breaker. The breaking capacity
starter makes it possible to control the voltage of the circuit breaker is thus enhanced.
to match the actual need, so that power losses Using conventional technology, it is not on-
are minimised and smoother, more sparing ly the short-circuit protective devices, SCPDs,
operation is obtained, with longer life as a that have to be upgraded, but also any auxiliary
result. equipment, such as contactors, due to higher
Soft starters are becoming increasingly usual let-through energies (I2t). The busbar system
in process industries and for motor sizes of 160 and cables often need to be upgraded too. Using
kW and above. a current limiter, the fault levels are reduced to
a much lower level, e.g. 6 kA instead of 50 kA,
and subsequently the let-through energies in-
volved will be linked to the limited fault level.
Torque There are current limiters for use in MCC
DoL
(Motor Control Centre) applications with mo-
tor starters up to 690 V, 63 A, and others for
distribution applications with standard MCBs
Star/Delta
(miniature circuit breakers). In order to ensure
Softstart good interaction between breakers and the cur-
rent limiter, only breakers specified in official
co-ordination tables should be used.

Arc guard system


General
Speed
Very short disconnection times are the best way
Fig. 19. Starting torque with different starting of limiting the risk of injury to personnel and
methods. damage to equipment due to arcing faults.

41

5.2 41 97-03-05, 13.27


INDUSTRIAL POWER SYSTEM
Low voltage distribution

A combination of an arc guard system and high-


speed circuit breakers provides the best means Q2
of ensuring a minimum of damage and injury.
Cleaning and repair times become shorter, op-
erating reliability and equipment availability F11 Q3
increases, and downtime is dramatically de-
creased. Potential breakdowns are very largely D
avoided, production losses are drastically cut
and there are clear savings in costs.

Fig. 22 Arc monitor with detectors, circuit


2
diagram
kA S ➂

Operational features
The arc monitor delivers the trip signal in
Steel
➁ Fire approximately 1 to 2 milliseconds. The actual
Cable
Fire disconnection time depends on the type of
➀ circuit breaker used, but the entire process is
0 35 ms 100 ms 200 ms 400 ms 500 ms over in less than 50 milliseconds if an LV
ASSEMBLY has been provided with an arc
guard system.
Fig. 21 Arc duration and resulting damage
Current sensing unit
The detectors can also be sensitive to other
Description forms of intense light, such as camera flashes,
The watchful eye (the detector) of the arc guard
lightning, direct sunlight, switching arcs in
system detects any large increase in light inten- circuit breakers and other large apparatuses. By
sity. The detector transfers light from the arc combining the arc monitor with a current sens-
through a state-of-the-art solid-state electron-
ing unit set at just over the normal operating
ics package (an arc monitor). Within an interval level, a current-dependent condition is intro-
of one to two milliseconds, the system sends a duced which prevents triggering from irrel-
trip signal to the disconnecting circuit breaker
evant light sources. This prevents spurious trip-
(upstream) located in the LV ASSEMBLY, ping of the LV ASSEMBLY, causing nuisance
bypassing delays caused by selective features power outages.
of relaying schemes. This protects both equip-
ment and personnel.

The system includes: T3


• Arc monitor with detectors (normally one
detector in each cubicle in an LV ASSEM-
F12

BLY)
• Current sensing unit Q2
• Breaker fault unit
F11 Q3
All communication between the detectors, arc
monitor, current sensing unit and the breaker
fault unit is through fibre optics. Fibre optics D
eliminate the risk of interference from extreme
high electromagnetic fields, especially during
an arcing fault. Fig. 23 Arc monitor with detectors and current
sensing unit, circuit diagram.

42

5.2 42 97-03-05, 13.27


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Breaker fault unit arranged to give maximum coverage to the


The breaker fault unit provides a safeguard compartment in which they are located. Addi-
against failures in downstream circuit breakers tional detectors are to be added as required to
(on the low-voltage side of the transformer obtain complete coverage. Tripping should be
where the circuit breaker is mounted in the LV arranged so that all internal feeders connected
ASSEMBLY). In installations with access to to a faulty section of main busbar are discon-
the main upstream circuit breakers (on the nected. To cover the situation when feeder
medium-voltage side of the transformer) the circuits act as incoming or outgoing circuits,
addition of a breaker fault unit can be utilised. the current measuring input for each section of
This ensures protection if the downstream main busbar is to be operated from current
branch circuit breaker does not function. If the transformers.
downstream breaker fails to disconnect the
supply within the set time, the breaker fault unit
will override and trip the main upstream breaker Selection of short-circuit
(on the medium-voltage side).
protective device (SCPD)
Introduction
Q1 Short-circuit protection is a question of select-
ing between fuses and circuit breakers. Both
F13 types of protection are still highly applicable in
T3 plants and described below is what application
F12 they work best in.
Sizing of circuit breakers or fuses requires
somewhat different input data in order to make
Q2 a fair comparison. Circuit breakers are more
dependent on voltage and short-circuit power
than fuses are. This means, in turn, that there are
F11 Q3 a great many circuit breaker variants. See Chap-
ter 4.4, Motor starting systems, p. ?...........
D An analysis of short-circuit currents that
occur in main distribution and sub-distribution
systems has always been important as an instru-
ment to check selectivity and trip conditions,
Fig. 24 Arc monitor with detectors, current for example. With circuit breakers in the plant,
sensing unit and circuit breaker, circuit dia- the analysis will also have a considerable effect
gram. on the cost level.
Unfortunately, this analysis mostly concerns
the highest short-circuit current occurring, even
LV ASSEMBLY protection though the lowest short-circuit current is at
An LV ASSEMBLY protection system is based least as important to know for various fault
on the ABB arc guard system, or equivalent, cases, so that tripping of the circuit occurs
operating in conjunction with an arc monitor. within a few seconds.
At least one detector is to be included for each A simple definition of the best-working short-
compartment of the LV ASSEMBLY. circuit protective device is that it should not trip
In the LV AssemblY, optical detectors are to at overcurrents (starting currents) occurring in
be located in each vertical busbar section, in- service, but that it should for the lowest short-
cluding detectors in the main horizontal busbar circuit current in the plant.
compartments, in each circuit breaker compart- The relationship between operating current
ment and in the compartments where the con- and switching currents occurring in the appli-
nections for outgoing cables are to be moni- cation determines the selection of tripping level:
tored. Detectors are also to be located to moni-
tor the main busbar, breakers, and connections For Utilisation Category AC21 (resistive
to outgoing cables. All detectors are to be load) the relationship is Imax to In = 1

43

5.2 43 97-03-05, 13.28


INDUSTRIAL POWER SYSTEM
Low voltage distribution

For Utilisation Category AC22 (distribu- ment in the event of a short circuit, even if the
tion) the relationship is Imax to In = 2.5 -3 fuse is sized to trip the circuit within a few
seconds.
For Utilisation Category AC23 (three- In order to always have the best short-circuit
phase induction motor) the relationship protective device, selection must be based on
is Imax to In = 7 the need of short-circuit current, i.e., the switch-
ing current occurring in the circuit, and the
tripping level should be chosen accordingly.
Transformator 10/0,4 kV A rule of thumb for this, representing a ”safe
800 kVA
I = 23 kA level”, can be given for Utilisation Category:
k

AC21: Tripping level 2 x In


AC22
AC22: Tripping level 5 x In
AC23: Tripping level 10 x In
Stum kortslutning i centralen
ger 5,7 kA.
Säkring 250 A
The calculated values should be checked in
Ett fas–jordfel ger 3,3 kA.
Med hänsyn taget till dämpning relation to these levels and any relationship
av felljusbåge 30 % är lägsta between the requirement level and the results
kortslutningsströmmen 2,3 kA. 4 × 240 mm2 Al-kabel
200 meter from the calculation should be assessed. When
studying this and starting to evaluate different
Undercentral
250 A short-circuit protection alternatives, differences
between fuses and circuit breakers are soon
observed. With these differences established
and set in their right context in the plant, good
progress has been made in pursuit of the best
Driftström
inkl. startström 2,3 kA
Fas–jord
3,3 kA
possible solution; a solution that takes into
Fas–fas
5,7 kA
account costs due to unplanned production
downtime in relation to the investment in elec-
trical equipment.

Special terminology
Figs. 25 and 26 Example of short-circuit cat- Before making any direct comparisons between
egory AC 22. different short-circuit protective devices, a
number of terms need be clarified.

According to the fuse´s tripping curve, the Cascade connection


tripping time is 0.5 seconds at a fault current of Cascade connection is the term used when a
2.3 kA. The plant´s rated current is 250 A and breaker with a high tripping capacity backs
starting currents in service for Utilisation Cat- up a breaker with a lower tripping capacity.
egory AC22 are stated at 2.5-3 times the rated This is a very useful economic alternative
current. if limited selectivity can be accepted, since
The area (1) between the lowest calculated both breakers in the chain trip for currents
value and the operating current value is also to exceeding the breaking capacity of the lower
be considered as a fault area. It is impossible to breaker. The most common application is when
predict what current will result from a fault. In an MCCB backs up a number of MCBs in a
the case of a fault with higher absorption of distribution board. (MCCBs and MCBs are
a fault arc, for example a 1000 A fault current, described under the section Circuit breakers,
the same fuse would have a tripping time of p. ? 34.)
about 20 seconds, with the obvious risk of fire Note that accurate sizing necessitates joint
breaking out in cabling and equipment. testing of apparatus. It is very difficult to achieve
In other words, there is nothing to ensure that the required function by combining different
there will be no damage to cables and equip- devices merely on the basis of catalogue data.

44

5.2 44 97-03-05, 13.28


INDUSTRIAL POWER SYSTEM
Low voltage distribution

The difference in the new standard is that it is


now required that the two values (ICU and ICS)
be presented on the breaker´s rating plate. This
was not the case previously, which resulted in
problems since not all suppliers clearly stated
a which value it was that was stamped on the
plate.
It is worth noting that the standard does not
b differentiate between ACB and MCCB, which
means that an ACB too is only able to withstand
a few short circuits at its maximum breaking
c F capacity. The difference is that the ACB´s de-
Fig. 27 Cascade con- sign makes it quite easy to replace arc contacts
nection and quenching chambers, which extends the
M M M
lifetime of the ACB. In practice, however, it
is extremely unlikely that the same breaker
Breaking capacity will be repeatedly exposed to fully developed
Breaking capacity describes the breaker´s ca- short circuits.
pacity to trip short-circuit currents. It is impor- A fuse has, in principle, unlimited breaking
tant to know how the breaking capacity is capacity.
defined in order to impose the right require-
ments on the apparatus. An IEC standard clearly Thermal trip conditions
specifies how the test must be conducted when There is another description of a breaker´s
the breaking capacity is to be verified. There is performance where it is important to know
some difference here between the old standard, the background.
IEC 157-1, and the new one, IEC 947-2 (see the According to IEC 947-2 the breaker´s ther-
section Circuit breakers, p. ? 34), but the test mal overload protective device should be cali-
procedures are virtually identical. In both cases brated at +30o C unless otherwise stated. How-
two different values for breaking capacity are ever, the calibrating temperature is more usu-
verified by two different test series. After the ally +40oC or +45oC. The standard for circuit
first of the test series, a limited function is breakers, IEC 947-2, has wider tolerances than
accepted for the breaker and this value is termed the standard for motor starters, IEC 947-4-1.
the P1 value, as stated in IEC 157-1, and the ICU The MCCB is quite simply primarily de-
value, as in IEC 947-2. After the second test signed for the protection of cables and normally
series the breaker is still to retain its full func- does not have the kind of overload protection
tion and this value is termed P2 in IEC 157-1 required to safeguard motors.
and ICS in IEC 947-2. These values are of course An example of how the calibration tempera-
at a lower level than the values P1 and ICU. ture can play an important part is an MCB

Test of short-circuit breaking capacity, test sequence


Standard Test sequence Requirements after test
IEC 947-2:
ICU O-CO Limited function
ICS O-CO-CO Full function
IEC 157-1:
Cat. P1 O-CO Limited function
Cat. P2 O-CO-CO Full function

O = one break
CO = one make, automatically followed by one break

45

5.2 45 97-03-05, 13.28


INDUSTRIAL POWER SYSTEM
Low voltage distribution

installed in a car engine heating distribution current-limiting circuit breakers. See the sec-
board located outdoors. This breaker may be tion Circuit breakers, current-limiting circuit
calibrated at +20oC, whereas the ambient tem- breakers, p. ? 35.
perature might be -20oC. This naturally means The goal is to have the same low level of let-
that the breaker will not perform as intended. through energy (I2t) for circuit breakers as for
fuses at high short-circuit currents.
× Ie
1,40
IEC 947-2 Ip
1,30 (kA)

1,20 IEC 947-4


100
1,05
1,00
Effektbrytare
–10 –5 0 10 20 30 40 °C 160 A gG
Omgivningstemperatur 160 A aM
100 A aM
Fig. 28 Thermal trip conditions Ambient tem- 10
perature

Co-ordination type
Types of co-ordination for motor starters are
described in the section Motor starters, p. ? 36.
104 105
Let-through energy (I2t) and let-through I (A)
current peak
Let-through energy and current peak are two
important magnitudes that give us reason to
examine the differences between fuses and I2t-värde, A2s
107
circuit breakers. 8
6 I2t 660 V
4 I2t 500 V
Fuses I2t 380 V
The breaking procedure for fuses depends en- 2
tirely on the size of the short-circuit current. 106
The higher the current, the shorter the breaking 8
6
time is.This means that the let-through energy 4
(I2t) is relatively independent of the short-
circuit current at high levels of fault current 2

(see the graphs below). Note that the short- 105


8
circuit current must be at a relatively high level 6
for the fuse to be able to limit the current peak 4
(see the section Fuses,current-limiting diagram,
2
p. ? 31).
104
8
Circuit breakers 6
The circuit breaker´s short-circuit protective 4

device, on the other hand, trips at approxi- 2


mately the same time, whatever the size of the
103
short-circuit current. This means that the let- 63 125 250 400 630 Märkström, A
through energy (I2t) will increase with higher
short-circuit currents. This is counteracted by Figs. 29 and 30 I2t curves and current limiting

46

5.2 46 97-03-05, 13.28


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Let-through energy (I2t) and current peak are Comparison of fuses and circuit breakers
important data for fuses and circuit breakers, as short-circuit protection
since they are of importance to the sizing The comparison is based upon three basic con-
of other components in the circuit, not for- ditions:
getting cable sizing (see the section Cable siz-
1. The short-circuit protective device is not to
ing, p. ?...........).
trip if the rotor is locked in the motor. Overload
Condition monitoring currents up to that level are to be taken care of
by the thermal overload protective device.
The problem is to find out what the breaker has
been exposed to and what condition it is in. 2. The motor starter is not to trip during normal
Such checking is very much a question of starting of the motor.
subjective judgement and requires some expe-
rience. A visual inspection of this kind should 3. The contactor in a motor starter is to have a
be included in a periodic inspection control higher making and breaking capacity, than the
plan, as well as after a breaker has tripped for a tripping value of the short-circuit protective
short circuit. device, so that the contactor is able to break the
In the regular inspection the breaker should fault current when the therrmal overload pro-
also be operated a few times. Furthermore, the tective device gives an overload signal.
trip test button that is to be found on most
MCCBs today should be tested. Fuses
A more objective assessment of condition It has been described above how fuses should
can be made, after a trip, by measuring the be sized so as to fulfil the first two require-
contact resistance over the main contacts, as ments. It is the third requirement that causes
well as the insulation resistance to earth. Tables problems, since the fuse performance in the
of acceptable values are available. It is also overlapping area is rather difficult to control.
important to remember that the breaker that can With short-circuit currents that are too low, the
carry its rated current can also cope with trip- breaking times for the fuse are too long. Often
ping for a short circuit. It is the characteristics the contactor has to withstand and interrupt
of the thermal overload protective device that fault currents which the fuse should really have
may be adversely affected. dealt with.
The current-time curves given for fuses do
Dependable disconnection not provide much help as they only describe the
Not all experts approve of using the same melting time for the fuses. The total breaking
device for breaking short-circuit current and time is often far too long to protect the contactor
employing it as a disconnector when carrying effectively. Often the fuse will not blow fast
out work on equipment (see the section Discon- enough, or in the worst case not blow at all if,
nection for work purposes, p. ? 27). Technical for example, there is an attempt to switch on a
solutions that ensure dependable disconnection contactor when there is an insulation fault in
have been developed, for example taking out a motor.
and turning round the thermal overload relay in This is more than the contactor can handle
a breaker and using it as an disconnector. and causes damage to the contacts and often
In heavy industry, withdrawable units (see results in contact welding. The contactor is
the section Incoming and outgoing units, p. ? 6) often given the blame for defective operation
are used in LV ASSEMBLIES. The units are but in reality it is the short-circuit protective
located in a disconnected position - a reliable device that did not work correctly.
solution.
For those who do not wish to choose with- Circuit breakers
drawable units there are today several With a circuit breaker as the short-circuit pro-
switchgear alternatives. Plug-in MCCB types tective device, the first requirement above is, in
can, for example, be used as disconnectors theory, easy to fulfil. The breaker has a very
when isolated or withdrawn. steep characteristic in the short-circuit range,
and it is therefore easy to adjust to match the

47

5.2 47 97-03-05, 13.29


INDUSTRIAL POWER SYSTEM
Low voltage distribution

motor´s starting current. On the other hand, for the difficulties is that the breaker lets through
only a very short current over the tripping value more energy the higher the short-circuit cur-
is needed for the breaker to react. Once it has rents become. Apparatuses and devices after
started to move there is no return, and the the breaker have to be selected so that they can
breaker will trip. The very short current peak, cope with the amount of energy involved.
which inevitably occurs when starting a motor, The next general rule is that sizing is easy
is quite sufficient to trip the breaker. This with fuses when there are fully developed,
means that this peak determines sizing of the direct short circuits.
setting of the short-circuit protective device. The problem of the fuse´s long breaking time
Since it is much easier here to predict a in the case of limited short-circuit currents is
breaker´s operation than that of a fuse, it is also most critical for larger motors (> 70 kW. How-
easier to choose a contactor with sufficient ever, it may be solved to some extent with aM
performance to fulfil the three requirements fuses. See the section Fuses, p. ? 30 and Chap-
mentioned earlier. ter 4.4 Motor starting systems., p. ?
The graph below shows the problems and
As a general rule it can be said that it is much also the possibilities in selecting a short-circuit
easier to size with circuit breakers as the protective device in a motor starter.
short-circuit protection at these limited When it comes to pure distribution, the ad-
short-circuit currents. vantageous properties of the circuit breaker can
Difficulties with circuit breakers arise in com- be fully utilised. The weaknesses of circuit
binations with equipment in a motor starter. breakers at high short-circuit currents are far
These combinations have to be protected against less marked in pure distribution than in the
a bolted short circuit (no arc) directly on the protection of motor starters, since no co-ordi-
outgoing side of the combination. The reason nation is required with other components.
In the United Kingdom and Italy, for exam-
T
ple, fuses are very seldom used in pure distribu-
(s)
tion. On the other hand, there are still fuses in
102 around 50 % of all motor starters. The reason is
not lack of technology; it is often due to over-
sizing of other components in trying to achieve
Termiskt sizing equivalent to that of fuses at higher
relä short-circuit currents.This has in its turn re-
101
sulted in higher initial costs.
Nowadays, there are more, improved cur-
MCCB
100 A aM rent-limiting breakers available, allowing con-
tactors to be better utilised. If the voltage is
100 limited to 500 V and the short-circuit current to
50 kA, the differences today are small com-
pared with fuses as short-circuit protection.
160 A gG Recent price development, too, has made the
Motor
MCCB more attractive for motor starter appli-
10-1 cations.

Selection of overload protection


10-2 See also Chapter 4.4 Motor starting systems
Introduction
102 103 104 It is primarily in the selection of short-circuit
I (A) protection that a comparison between fuse and
Fig. 31 Current-time curves. Comparison- circuit breaker assumes most importance. Irre-
Fuses/MCCBs spective of the choice of short-circuit protec-

48

5.2 48 97-03-05, 13.29


INDUSTRIAL POWER SYSTEM
Low voltage distribution

tion, perfectly adequate overload protection is Conventional thermal overload relays


obtained for the cable. The question is whether The simplest and still the most common over-
the protection is enough to protect the object load protective device is the thermal overload
in question. To protect a motor from overload, relay. See the section Overload relays, p. ? 33.
the fuse´s thermal characteristic is obviously This is a good solution at a good price
not enough. Further, the suitability of the inte- which gives enough protection for most mo-
gral thermal protective device present in most tors.
MCCBs as overload protection for a motor
should also be questioned. Electronic overload relays
Development is moving towards more strin- Vital continuous drives often require functions
gent demands regarding plant availability. In that are not available with thermal overload
connection with this, demands for adequate relays. A current-transformer-fed electronic
protective devices of different kinds are in- overload relay is then a good alternative. See
creasing. Therefore, selecting an overload pro- the sections Overload relays, p. ? 33 and Micro-
tection with worse capacity than traditional processor-based control technique for low-volt-
thermal overload relays (see the section Over- age distribution systems, p. ? 49.
load relays, p. ? 33) cannot be correct. Conse-
quently, both fuse and MCCB should be sup- Electronic overload relays with communica-
plemented with the best possible overload pro- tion possibilities
tection feature for the motor. The object, i.e., To ensure maximum availability of a plant,
the motor and the machine the motor is to drive, preventive maintenance is important.
determines the nature of the required protective It is then required that various protection
functions. functions provide an alarm for impending and
incipient faults. These could include measuring
Different types of overload protective de- of temperature at different points, operating
vices hours and the number of makes and breaks.
Standard protective device in MCCBs All this can be measured and stored in a moni-
The thermal relay built into all MCCBs is toring system. See the sections Overload re-
designed to protect cables. It does this job better lays, p. ? 33 and Microprocessor-based control
than a fuse, which means that in most cases the technique for low-voltage distribution systems,
cable can be better utilised if a circuit breaker p. ? 49.
has been selected. However, as mentioned pre-
viously, the let-through energy (I2t) upon short Temperature measurement
circuit for cables < 25 mm2 must be checked. It is not the overload itself that is damaging to
Manually controlled direct-on-line starters the motor; it is the elevated temperature that the
and various types of combination starters (see overload causes. So long as all that is required
the section Motor starters, p. ? 36) that have is to measure the current to avoid damage to
been developed in recent years contain thermal the motor, there is optimum protection as the
overload protective devices that fulfil the current characteristics of the protection are just
IEC standard for contactors and motor starters above the current characteristics of the motor
(IEC 947-4-1). during inrush, start and continuous operation.
One or more of the following functions are, However, in the case of abnormal temperature
however, often missing: conditions in the LV ASSEMBLY or at the site
of the motor, current measuring gives only a
• Signal contacts that differentiate between
overload and short circuit.
poor indication of how severely the motor is
loaded.
• Temperature compensation. To obtain complete protection, temperature
measurement of the motor´s windings is neces-
• Phase fault protection. sary. An increasing number of motor starters
• Possibility of automatic resetting (and
thereby remotely controlled resetting via
can accept signals from, for example, a ther-
mistor (built into the windings of the motor)
electrical interlocking). for tripping or warning.

49

5.2 49 97-03-05, 13.29


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Microprocessor-based control All this helps lead to more efficient production


through optimum use of the electrical plant.
technique for low-voltage
distribution systems System principles
General There are three types of electronic microproc-
It is not only the supply to the motors but also essor-based systems for Motor Control Cen-
the protection and control functions that are tres, MCCs, on the market.
attended to by an LV ASSEMBLY. 1. Systems with motor protection functions
Normally, these protection and control func- (electronic overload relay)
tions are realised by combining apparatus with 2. Communication systems that have bus
the right functions and data, where the choice of communication between MCC and master
apparatus depends on both motor data and the process control system
application. The apparatus should usually be 3. Systems that include both motor protec-
connected in a certain manner to obtain the tion and bus communication with master
required operation for the motor drive. process control system, for example ABB´s
With the help of microprocessor technology INSUM.
such electrical installations can today be built
up in a much easier way. Describtion of type 3 above (ABB´s INSUM
All monitoring and control, for example system)
of motor drives, is concentrated to a common All conventional components are replaced by a
master operation centre. Information that needs microprocessor-based device. This consists of
to be known about a motor in the plant can be measuring and control units that have all func-
read on a display, for example current level, tions for protection, controlling, monitoring,
fault messages, operating hours, maintenance measuring and operating of, for example, a
period and a great deal more. This information motor drive. Each unit collects, processes and
can also be found on control and indication stores measured values and transmits control
panels on the LV ASSEMBLY. signals to the motor starter.
The large number of monitoring functions, A current transformer ensures galvanic sepa-
and the possibility of getting warnings at pro- ration between main circuits and auxiliary cir-
grammed-in measuring levels, results in more cuits and provides a suitable measuring level.
efficient process monitoring. In an operating and indicating unit the bus
The warning signals make it possible to take connection is able to handle up to 32 measuring
steps in time and breakdowns can thus be and control devices, communicating with a
avoided. master process control system.
At the same time as control and monitoring
functions are being improved and extended, the The functions that are monitored in a motor
actual design of the electrical plant is being drive are:
simplified. Point-to-point conductors are being
replaced with bus connections, which reduces • Overload
the number of cables needed. • Phase failure
• Locked rotor in the motor
Some of the advantages of this technique are: • Underload
• Improved • Earth fault
monitoring and controlling
• More reliable • Undervoltagerise
Temperature
Improved motor protection
• Extended protection
system processing •
There are also units for controlling and moni-
• Simpler plant design functions toring circuit breakers.
• Quicker and more efficient plant Together with the master process control
• construction system, for example the ABB Master system,
controlling and monitoring of the electrical
• More effective maintenance
plant can be integrated in the production proc-
• Easier and faster troubleshooting
ess. The operator and the plant electrician are

50

5.2 50 97-03-05, 13.29


INDUSTRIAL POWER SYSTEM
Low voltage distribution

thus equipped with an effective tool to control short circuit (short circuit without arc) must
and run the process. be determined. See the section Motor starters,
All necessary functions for process control, p. ? 36.
drive equipment, motor control, machine con- In the suppliers´ tables a certain type of
trol, instrumentation, drive optimisation, qual- motor is used as the point of departure. A 4-pole
ity control, etc., can be included. motor of a well-known make is usually chosen.
An important feature where motor makes differ
ABB is the power factor, cos j, during start-up. The
Master current peak generated during the start is en-
tirely dependent on the P.F. or cos j. Modern,
BAG
INSUM high-efficiency motors have a lower P.F. and
this results in a higher switching current surge
when starting. This current surge determines
Start- Max 32 stycken Luftbrytare sizing in setting the short-circuit protective
kopplare Megamax
device in the circuit breaker.
MSG
INSUM Corresponding problems can arise when
changing to circuit breakers in an existing plant
M Lokal where the motors are often over-sized. Unfor-
manöverlåda
tunately, the short-circuit protective device can-
T.ex.
Nödstopp
not be set with too broad a margin, since this
directly affects the maximum cable length,
Fig. 32 The INSUM system which is also dependent on the short-circuit
protective device setting.
The manufacturer can provide information
Sizing of devices and cables on which power factor has been calculate with
For direct outgoing units (motor starters, for for different motor outputs. This information
example) this is largely a question of selectivity must be checked against all actual motors in the
and cable sizing. This requires, as input data, plant. In the sizing tables there are recom-
the calculated short-circuit current at the differ- mended settings for the short-circuit protective
ent locations where the short-circuit protective device. With help of these figues the cables can
device is to be installed, and the short-circuit then be sized. See Chapter 10 Cables, as men-
current for various fault cases at the item to be tioned above.
protected, With circuit breakers, the require- Note that when calculating the nominal set-
ments made regarding the condition of the ting of the circuit breaker, a possible voltage
breaker after a bolted short circuit (short circuit variation of +/- 10 % needs to be taken into
without arc) in the LV ASSEMBLY must also account, as well as a tolerance of +/- 20 % in
be determined. Further, co-ordination tables the short-circuit protective device.
from the supplier of the circuit breaker are With regard to the maximum settings, based
needed in developing selectivity plans. upon defined tripping with a certain cable, a
See more about selectivity under the section 30 % voltage drop in any arc that occurs can
Selectivity, p. 26 ?.......... be reckoned on, and a tolerance of +/- 20 %
Cable sizing is described in detail in Chapter in the breaker´s set value.
10 Cables, Cable sizing, p. ?..........
For sizing of motor starters, the supplier
should be able to supply complete co-ordina- Project planning
tion and sizing tables. One should avoid com- Planning steps
bining a motor starter on one´s own. Correct Aspects affecting the design and the selection
sizing requires careful joint testing of the com- of components for the LV ASSEMBLY have
ponents (i.e., the complete starter, see the sec- been described earlier.
tion Motor starters, p. ? 36). This section constitutes a summary and a
For combination starters, the requirements check list for planning steps in logical se-
made of the device´s function after a bolted quence.

51

5.2 51 97-03-05, 13.30


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Step 1: Determination of plant design Step 5: Determination of incoming supply


See the section Plant design, p. ? 22. from the transformer
See the section Connection to the LV ASSEM-
Alternative 1 Place the transformer next
BLY, p. ? 26.
to the LV ASSEMBLY and
gather all incoming and out- • Via circuit breaker
going units in a common • Via disconnector
switchgear assembly located • Direct connection
Via switch + fuses or MCCB

Alternative 2
in an operating room.
Divide the LV ASSEMBLY

into a main distribution Load Step 6: Determination of short-circuit pro-
Centre (LC) located in an tective device for the outgoing units
locked operating room, and See the section Selection of short-circuit pro-
sub-distribution Motor Con- tective device (SCPD), p. ? 41.
trol Centres (MCCs), placed
Alternative 1 Switch + fuses
close to the process equip-
Alternative 2 MCCB
ment.
The requirements of selectiv-
Step 2: Determination of rated data for the ity must be closely considered.
switchgear - rated current, rated voltage,
rated short-time current Step 7: Determination of the design of outgo-
See the section Plant design, p. ? 22. ing units
See the section Switching devices and compo-
Data for the feeding trans- nents installed in LV ASSEMBLIES, p. ? 15.
former and the sum of the load
currents, taking into conside- Alternative 1 Fixed groups
ration the diversity factor (see Alternative 2 Removable
the section Diversity factor, groups
p. ? 24), form the basis for Alternative 3 Withdrawable
the rated data of the LV AS- groups
SEMBLY. Future extensions
and any requirements regard- Step 8: Determination of utilisation category
ing maximum temperature rise See the sections Contactors, p. ? 31, Motor
should also be considered. starters, p. ? 36 and Selection of short-circuit
protection device (SCPD), p. ? 41.
Step 3: Determination of system earthing
See the section Types of distribution system, Step 9: Determination of power factor con-
p. ? 25. trol, where necessary
See the section Power factor control, p. ? 4.
• Directly earthed
• Not directly earthed
Step 10: Control of power losses
• Three-phase 3-wire
Resistances in conductors,
• Three-phase 4-wire
connections, apparatus (coils,
for example) and resistors
Step 4: Determination of degree of protec-
give rise to power losses and
tion, IP Code and environmental adaptation
See the section Service conditions, p. ? 8. temperature rise.

• IPIP 21, normal design Jag A number of guidelines


• againstextra
41, protection
direct contact with live parts
• If the diversity factor is in accordance with
the standard values, see under the section
• IPAnother
54, waterproof design Diversity factor, p. ? 24 (see also Step 2
• adaptationIP Code and environmental above), there is usually no need for special
consideration.

52

5.2 52 97-03-05, 13.30


INDUSTRIAL POWER SYSTEM
Low voltage distribution

• Ifstandard
the diversity factor is higher than the
values, the LV ASSEMBLY
ence and submits a preliminary tender to the
user - the client. The latter makes his own
should be fitted with a fewer number of adjustments and thereafter a final tender can be
”separated” groups (the space in the cubic- arrived at.
le thus not fully utilised). The rated Clients and consultants having PCs can be
currents for groups and for the equipped given access to the program.
cubicle could also be increased in relation to
the operational currents.
• For enclosure class IP 21the power losses Information to be provided
of the horizontal busbars need not be on an LV ASSEMBLY
considered.
Documentation (5 in IEC 439-1)
• For enhanced enclosure class IP 41 the rated
current must be reduced by 10-30 %. The documentation constitutes an important
feature of an LV ASSEMBLY delivery.
• For enclosure class IP 54 the rated current
is reduced by 30 % for horizontal busbars. It can be divided up into the following groups:
• When sizing the ventilation system for the
operating room, a power loss of 1 kW
1. Catalogues, pamphlets,
brochures and other printed
for a normally equipped cubicle can be used sales matter
as a guideline. 2. Test reports
3. Instructions on installation
Planning tools (p. ? 350) and maintenance
Large manufacturers of LV ASSEMBLIES all 4. Customer documentation
have some type of computerised system for for the delivery in question
project planning and producing tenders and
documentation. 1. Catalogues, pamphlets, brochures and
The following are usual features: other printed sales matter
• Preparing a questionnaire A catalogue supplies tech-
• Preliminary tender, designing documenta-
tion for buildings
nical information on data,
dimensions, functions, stan-
• Making changes dards, etc. Pamphlets, bro-
• Final tender chures and other sales matter
• Ordering are intended to stimulate in-
• Documentation terest. They may contain a
• Providing input data for the creation of manu-
facturing documents.
certain amount of technical
data but the information in the
catalogue is what counts
The complete switchgear and controlgear stand- when planning.
ard is stored in the system, including all stand-
ardised units, enclosures, accessories, etc. 2. Test reports
Input particulars include primary data for A type test report is required.
motors, loads and feeding transformer. The The tests can be performed
system creates a ”proposal” for a complete LV in the manufacturer´s own
ASSEMBLY, including price and the follow- laboratory, with or without
ing documents: witnesses, or in another inde-
pendent test facility. See the
• Single-line diagram section Test specifications,
• Front and floor layout, drilling plans p. ? 17.
• Circuit diagrams
• List of name-plates 3. Instructions and manuals
• List of apparatus There are a number of prod-
The proposal is scrutinised by the planner, who uct-related instructions that
then makes adjustments based on his experi- concern mounting, assembly,

53

5.2 53 97-03-05, 13.31


INDUSTRIAL POWER SYSTEM
Low voltage distribution

service and maintenance, etc.


Instructions often form part of • General assembly drawing (with dimensions
for the LV ASSEMBLY, cubicles, units, etc.)
complete customer documen-
tation, together with cata- • Front layout
logues and order—related • List of apparatus
documentation, e.g. circuit Possible additional inclusions:
diagrams, lists of apparatus,
etc. • Wiring tables (cubicle level)
• List of name-plates
4. Customer documentation • Erection plans
Customer documentation normally contains: • and maintenance
Instructions and manuals for installation

• Circuit diagrams
• Single-line
diagrams)
diagrams (and/or overview

54

5.2 54 97-03-05, 13.31


INDUSTRIAL POWER SYSTEM
Low voltage distribution

Bibliography
Applicable IEC standards
As mentioned in the introductory section, p. ? 2, the International Standard Publication IEC 439-
1, Low-voltage switchgear and controlgear assemblies, Part 1: Requirements for Type-
Tested (TTA) and Partially Type-Tested (PTTA) Assemblies is the main standard for LV
ASSEMBLIES. The object of the standard is to establish requirements. The standard has eight main
divisions:
1. General, 1.1: Scope and object, 1.2: Normative references (=applicable IEC standards, see
list below)
2. Definitions
3. Classification of ASSEMBLIES
4. Electrical characteristics of ASSEMBLIES (rated voltage, rated current,etc.)
5. Information to be provided on the ASSEMBLY
6. Service conditions
7. Design and construction
8. Test specifications

List of applicable IEC standards


Name Number
Coding of indicating devices and actuators
by colours and supplementary means IEC 73: 1991

Degree of protection provided by enclosures (IP Code) IEC 529: 1989


Electrical installations of buildings IEC 364
Assessment of general characteristics. IEC 3643:1977
Protection for safety; Protection against electric shock. IEC 364-4-41
Choice of protective measures against electric shock
in relation to external influences. IEC 364-4-481
Selection and erection of electrical equipment;
Earthing arrangements and protective conductors. IEC 364-5-54
Graphical symbols for use on equipment.
Index, survey and compilation of the single sheets. IEC 417: 1973
High-voltage test techniques IEC 60
IEC standard voltages IEC 38: 1983

Identification of equipment terminals and of terminations of certain


designated conductors, including general rules for an alphanumeric system. IEC 445: 1988
Identification of conductors by colours or numerals. IEC 446: 1989
Insulation co-ordination, Part 1: Terms, definitions, principles and rules. IEC 71-1: 1976
Insulation co-ordination for equipment within low-voltage systems,
Part 1: Basic principles and requirements. IEC 664-1: 1992

55

5.2 55 97-03-05, 13.31


INDUSTRIAL POWER SYSTEM
Low voltage distribution

International Electrotechnical Vocabulary (IEV) IEC 50


Switchgear, controlgear and fuses IEC 50 (441): 1984
Insulators IEC 50 (471): 1984
Generation, transmission and distribution of electricity, Operation IEC 50 (604): 1984
Item designation in electrotechnology. IEC 750: 1983
Low-voltage fuses IEC 269
Low-voltage controlgear; Semiconductor contactors
(solid state contactors) IEC 158-2: 1982
Low-voltage switchgear and controlgear IEC 947
General rules IEC 947-1: 1988
Circuit breakers IEC 947-2: 1989
Switches, disconnectors, switch-disconnectors and
fuse-combination units. IEC 947-3: 1990
Contactors and motor starters;
Electromechanical contactors and motor starters. IEC 947-4-1: 1990
Method for determining the comparative and
the proof-tracking indices of solid insulating materials
under moist conditions. IEC 112: 1979

Method of temperature-rise assessment by extrapolation for


partially type-tested assemblies (PTTA) of low-voltage
switchgear and controlgear. EC 890: 1987
Miniature Circuit Breakers, MCBs;
Circuit breakers for overcurrent protection for household
and similar installations. IEC 898
(Amendment No. 1-3): 1990
Semiconductor convertors;
Semiconductor self-commutated convertors IEC 146-2: 1974
Standard directions of movement for actuators which control
the operation of electrical apparatus. IEC 447: 1974

Surge arresters;
Non-linear resistor-type gapped surge arresters
for AC systems. IEC 99-1: 1991

Thermal electrical relays, Overload relays IEC 255-8: 1990

Literature:
”Corrosion of electronics”, A Handbook based on
Experiences from a Nordic Research Project
Authors: Jan Henriksen, Risto Hienonen, Torbjörn Imrell,
Christofer Leygraf, Lena Sjögren Bulletin No. 102
Swedish Corrosion
Institute, August 1991

56

5.2 56 97-03-05, 13.31


INDUSTRIAL POWER SYSTEM
Medium Voltage Distribution

MEDIUM VOLTAGE DISTRIBUTION

Contents
page
1 Design 57
2 Switchgear 58
3 Equipment items 61
4 Charactristics of various circuit breakers 63
5 Measuring transformers and relay protection 65
6 Condition monitoring 66

Design
Medium-voltage switchgear for industry is switchgear in such cases.
nearly always of in-house design. Under IEC Moisture is also a serious problem in switchgear.
298, temperatures in switchgear rooms may Condensation on insulation surfaces, particu-
range from -5 to +35°C (+40°C peak value) larly in combination with dust, nearly always
and the air in them may have a maximum 24- leads to flashover and consequent damage.
hour average moisture content of 95% and Cubicles in operation usually develop suffi-
must be free from pollutants such as dust, cient heat to prevent condensation, but there is
smoke, corrosive or explosive gases, etc. great risk of condensation in cubicles not oper-
ating (standby cubicles) if air humidity is high
Environmental aspects and the temperature falls. In cases where there
Environmental problems are liable to arise in is risk of condensation, each cubicle should be
many industries, e.g. the dust often released provided with a heating element, the switching
into the atmosphere by the cement industry, on and off of which needs to be controlled by a
smelters, etc. Switchgear rooms have to be hydrometer if condensation is to be prevented.
ventilated in such a way as to prevent dust A simpler but completely reliable alternative
making its way in and affecting the operation of control system for the heating element is to
switchgear. It is, of course, important that the arrange for it to be disconnected when the
filters that have in many cases to be used in connection equipment is in operation, so that
ventilation ducts be cleaned at regular inter- when the latter switches off, the heat element
vals. comes on automatically.
Other types of environmental problems arise
where there are air pollutants that have chemi- Location
cal effects on switchgear. Sulphur, for exam- Switchgear in industry may be housed in sepa-
ple, is capable of reacting with copper and rate buildings but is often located in special
silver to form sulphides. A coating of sulphur operating rooms within industrial buildings.
on contact surfaces may lead to increased As there are so many different kinds of indus-
resistances, higher temperatures and eventu- try, the range of possible environments is far
ally to overheating and damage. Industries li- too great to be able to give any general indica-
able to create explosive atmospheres have to tions about the design of industrial switchgear.
avoid using certain kinds of equipment capable Where it is in special operating rooms, how-
of generating even tiny sparks (auxiliary con- ever, there are a number of points that have to
tacts, motors, microswitches, etc.). Very severe be catered for, such as pressure relief and per-
requirements therefore have to be imposed for sonnel evacuation.

57

5.3 57 97-03-05, 13.31


INDUSTRIAL POWER SYSTEM
Medium Voltage Distribution

Operating rooms, construction requirements for calculating these pressure stresses are avail-
Pressure relief able from ABB.
Switchgear should be arc-tested to IEC 298 Low ceilings may sometimes make it impos-
standard. Arcing results in large amounts of sible for gases due to arcing to be discharged
gas that have to be discharged to prevent seri- upwards sufficiently quickly, in which case it
ous pressure damage to the switchgear. This may even be necessary to reduce the short-
gas has to be removed from the operating area circuit current in order to cope with potential
and led out into the open air to prevent anyone pressure increases caused by arcing.
being harmed by its toxic components.
The pressure created by an arcing fault may Escape routes
amount to several tonnes per square metre and In principle, no-one should ever be more than
can be calculated approximately by means of 5 m from an exit. This means that if the
the empirical formula switchgear room is longer than 5 m there has to
be an exit at each end. However, if the switchgear
2xNxUxIxt meets the arcing requirements and the tripping
P= V time does not exceed 0.15 s (e.g. by means of
arcing monitors), it is possible to have an exit at
where P = positive pressure in atmg only one end of switchgear rooms up to 10 m
N = number of arcs long. The width of the operating area should be
U =arc voltage in kV such that there is always a clear escape route at
I = arc current in kA least 0.5 m wide even when cubicle doors are
t = time in seconds before cubicle pressure open.
relief vents open Immediately outside the doors of switchgear
V = volume in m3 rooms there must be a level area of at least 2 x
1.5 m in the same plane as the switchgear floor.
The following criteria are used for evaluating If the exit is directly onto open ground, there
an arcing test: may be a certain difference in height, but pref-
erably not more than 250 mm. These require-
• Do doors, enclosure parts, etc., that are closed
and locked in the intended manner remain
ments relate, of course, to the need for it to be
possible to evacuate the room and look after
closed after the test? injured persons immediately after an accident.
• Do parts of the metalclad switchgear capa-
ble of harming persons become loose?
Switchgear housed in industrial buildings
may sometimes cause problems. The switchgear
• Have holes been caused in freely accessible
external parts of the enclosure by burn-
room may be well below ground level or high
up in a building. In new buildings, this matter
through? should always be resolved at the design stage,
• Do cotton indicators positioned vertically
30 cm in front of the switchgear ignite (dis-
but where switchgear has to be installed in
existing buildings, evacuation requirements
regarding those ignited by burning paint or often cause problems.
flakes)? The running of pipes, cables, etc., through
• Do cotton indicators positioned horizontally
over the operating area ignite (same paren-
switchgear rooms should be avoided.

thesis)?
• Do the earth current paths remain opera- Switchgear
tional after the test? General, standards
All medium-voltage switchgear is governed by
In industry it is not unusual for switchgear to be international standard IEC 298 and the voltage
situated far from any outside wall, which means levels mostly used for industrial applications
that the pressure relief ducts may be very long, are 7.2 and 12 kV, which means test voltages of
requiring verification that pressure stresses in 60 and 75 kV peak voltage and 20 and 28 kV
the switchgear do not exceed the values ob- AC voltage, respectively.
tained in type tests. Special computer programs Short-circuit currents and operating currents

58

5.3 58 97-03-05, 13.32


INDUSTRIAL POWER SYSTEM
Medium Voltage Distribution

are very high, partly because of the rather low Such arrangements provide the continuous pos-
voltages used, but mainly because most indus- sibility of supply via another path if a fault
tries have large power requirements. Operating occurs anywhere. Double busbars may be placed
currents of up to about 4000 A are not unusual, side by side in the same cubicle, or in what is
which corresponds to the data of ABB’s Safesix known as a duplex arrangement, i.e., two rows
switchgear. of cubicles (see Fig. 48), or in a single row of
cubicles with sectioning switches and different
Composition incoming supplies (see Fig. 49).
One of the most characteristic features of in-
dustrial switchgear is the requirement for high
operational availability, particularly in the case
of process industries.
Industrial switchgear is therefore often de-
signed so that there are alternative incoming
supplies. This involves various kinds of double
busbar arrangements (see Fig. 46).

Fig. 48 Safesix in duplex form

Systems with double busbars in the same cubi-


cle or variants of such systems are now in
decline. Having two busbar systems in the
same cubicle increases not only the risk of both
systems being affected by faults but also the
risks to personnel who have to work on one
system while the other is energised.
Duplex systems have therefore become more
Fig. 46 Double busbars usual, despite their somewhat higher cost. The
safest is the duplex front-to-front, which in-
volves two rows of cubicles installed facing
one another (see Fig. 48). This means that the
Strömbegränsande Ej strömbegränsande two busbar systems are several metres apart
and a fault on one side will not affect the other.
I I Anyone working on one busbar is also a safe
kA kA distance from the other. Front-to-front arrange-
ments are also relatively economical on space,
50 50 since they require only one operating area.
Duplex back-to-back arrangements involve two
operating areas and a consequently larger
switchgear room. The fact that back-to-back
20 20 arrangements make it impossible to see the A
and B sides at the same time also increases
somewhat the risk of incorrect action.
In some situations it may be more economi-
cal to place all the cubicles in one row with
sectioning switches between them, in which
case each busbar has its own incoming supply
5 ms and it is possible, for example, to use two
Fig. 47 13 ms incoming supplies to cater for a number of

59

5.3 59 97-03-05, 13.32


INDUSTRIAL POWER SYSTEM
Medium Voltage Distribution

different supply possibilities (see Fig. 49). Cer- cial measures such as painting of busbars may
tain industries also prefer to have each busbar also result in increased radiation, allowing
system in a different room to further reduce the higher currents without exceeding standard tem-
risk of loss of supply. perature values. If rectangular busbars are used,
every possible endeavour should be made to
Cooling position them edgewise, as this provides opti-
High currents are usual in industrial applica- mum cooling.
tions, which means that particular attention
usually needs to be paid to cooling. IEC 298 Cubicle types
permits temperature rises to a maximum of There is, in principle, an infinite variety of
50°C for bolted connections between bare cop- switchgear for industrial applications. A small
per busbars in air. The temperature permitted in engineering establishment may have switchgear
the case of silver-coated contact surfaces is consisting of a few individual cubicles of very
75°C. The permitted temperature rise for plug- simple design with one incoming supply breaker
in contacts is 65°C for silvered copper contacts and a few outgoing load isolating cubicles (Fig.
and 35°C for unsilvered contacts. 50). At the other end of the scale, switchgear for
The current that a given busbar system can oil platforms, nuclear power stations, paper
carry depends partly on the materials and sur- mills or rolling mills sometimes involves very
face treatment of joints and contacts and partly complicated equipment incorporating isolating
on what cooling can be provided. Forced cool- cubicles, load isolating cubicles, metering cu-
ing by fans means that higher currents can be bicles, breaker cubicles, contactor cubicles,
used, but this does, of course, depend on the fan etc. IEC 298 divides metal-enclosed indoor
system always functioning. It is therefore usual switchgear into three main categories:
in most cases to try to manage with natural
ventilation. Properly thought-out design can • Metalclad switchgear
achieve automatic air circulation and conse- • Compartmented switchgear
quently good cooling even without fans. Spe- • Cubicle switchgear

Fig. 49
Double incoming
supply with
sectioning breakers.

60

5.3 60 97-03-05, 13.32


INDUSTRIAL POWER SYSTEM
Medium Voltage Distribution

Metalclad switchgear has its components in can be provided with capacitive voltage indica-
separate cells with intermediate walls made of tors built into the insulators of the earthing
metal (see Fig. 51). switch, in which case the cubicle front incorpo-
rates a warning device to show whether the
phases are live or not.

Equipment items
General, various operating situations
All kinds of operating situations occur in indus-
try. Power supply may be from subordinate
transformers within the industrial area in cases
where the switching on or off of power is only
required extremely rarely. Another possibility
is the connection and disconnection of a bank of
capacitors for controlling reactive power
offtake, with switching taking place several
times a day. Different equipment is also used
depending on whether operation is to be con-
tinuous with stringent requirements for
uninterruptible power supply or whether inter-
ruptions can be tolerated without unduly ex-
Fig. 51 Safesix type metalclad switchgear. pensive consequences.
The appropriateness of each piece of equip-
ment depends on the type of load. Achieving an
Compartmented switchgear also has all its optimum solution requires a clear picture of the
components in separate cells but now the inter- types of currents and voltages that will occur,
mediate walls are made of non-metallic materi- how often switching will take place, what inter-
als. ruptions of operation are acceptable, etc. Only
on the basis of this kind of information is it
Cubicle switchgear is any switchgear which is possible to decide on the most suitable equip-
not classifiable as metalclad or compartmented, ment.
e.g. it may have the breaker and the cables in the
same space. Personnel safety is, of course, at a Disconnectors
considerably lower level, since cubicle A disconnector may be a separate piece of
switchgear has no automatic protection against equipment or simply a mechanism for connect-
energised cables harming anyone drawing out ing/disconnerting, for example, a cirquit
the breakers. breaker. A disconnector has neither breaking
nor making capacity and may only be operated
Earthing for work when there is no current in the conducting path,
Some kind of integrated earthing for work is a so it always has to be interlocked so as to be
common feature of all three types of cubicle. only operable in the de-energised state. It also
The safest kind is an earthing switch with has to withstand not only its rated current con-
making capacity for the full short-circuit cur- tinuously without dangerous temperature rise
rent for the earthing of cables and, in most but also a short-circuit current characterised by
cases, the busbar as well. The earthing switch the impulse current (peak value at the begin-
should always be interlocked so that it cannot ning) and short-time current (r.m.s. value dur-
be operated against voltage. Mechanical inter- ing short circuits, usually 1 second).
locking is the first choice but is not always A disconnector involves more stringent re-
possible for earthing switches in incoming sup- quirements for insulation across open separa-
ply cubicles. If energisation checks are desired tion points than the separation point of a breaker
before earthing, ABB’s Safesix type switchgear does. In principle, flashovers should be to earth

61

5.3 61 97-03-05, 13.32


INDUSTRIAL POWER SYSTEM
Medium Voltage Distribution

rather than across the separation distance. A The mechanical life of the motorised spring
separation distance should preferably also be operating devices incorporated in all circuit
visible, unlike a breaking distance. If the con- breakers is limited to 10,000-20,000 switching
tact position indication is satisfactory, how- operations. This means, for example, that the
ever, there is no need for the separation distance service life of a drive that has to be switched
to be visible. three times per hour on a two-shift basis will be
only 1 to 2 years, which is not a particularly
Switch disconnectors economical solution.
Switch disconnectors are used for disconnec- The connecting equipment for this kind of
tion and connection of operating currents. They drive should not be a circuit breaker but a high-
can be switched against a specified short-cir- voltage contactor, which is mainly available in
cuit current and can also carry the short-circuit vacuum or SF6 versions. Vacuum contactors
current for a certain time in the closed position. usually have longer service life (several million
They can break the load current, i.e., their rated switching operations) but have the disadvan-
current, usually 400 or 630 A, but cannot break tage that in certain positions they are liable to
short-circuit currents. The short-circuit protec- generate overvoltages that may, for example,
tion used in some cases consists of built- damage motors that lack suitable protection.
in fuses that break short-circuit currents. To Contactors are available for 3.6, 7.2 and 12
avoid that just one phase is broken by a single- kV, operating currents are usually 400 or 630 A
phase fault, these fuses are provided with a and breaking currents between 5 and 10 kA. As
striker pin that trips the opening mechanism their breaking capacity is limited, they are often
of the switch disconnector. Switch disconnec- provided with built-in fuses as protection against
tors are usually operated by means of a spring short-circuit currents. It is also possible to use
operating device tensioned manually or by relay protection to block the contactor and a
motor. circuit breaker to take care of short-circuit
Fuses are often used as short-circuit protec- currents.
tion in conjunction with load disconnectors and Contactors thus have the great advantage of
contactors. Each fuse consists of two contacts very long mechanical life, partly because the
associated with one or more fusible conductors movable contact is operated by means of a
made of silver or copper. These fusible conduc- solenoid and not by a spring operating device.
tors are surrounded by an extinguishing me- The result is an operating device with few
dium consisting of quartz sand of suitable grain moving parts that copes with a very large number
size. The fusible conductors and the extin- of switching operations (over a million).
guishing medium are enclosed in an insulating
cartridge body. To ensure controlled melting of Circuit breakers
the fusible conductor, it is usually provided Circuit breakers are the most common type of
with weak points in the form of punched holes. switch in industry. They can make and break
Each fuse may be provided with a warning the full short-circuit current and are provided
device. The cartridges are fitted to load with a motorised spring operating device.
disconnectors or contactors. When a high fault They may have an operating sequence known
current passes through the fuse, the fusible as rapid auto reclosing which is particularly
conductor becomes hot and melts. important in industries in which periods of
A fuse creates a fault current limit that may, interruption are very expensive. This means
for example, be useful in the dimensioning of that a temporary fault will make the breaker
cables. switch off but then immediately switch back
on. If the fault has by then disappeared, the
Contactors process will continue as usual, but if the fault
Operating situations sometimes occur in indus- persists, the breaker switches off again.
try in which operating currents at medium- IEC 56 defines various test cycles for break-
voltage level have to be connected and discon- ers, but the one most commonly used is 0-0,35-
nected several times an hour, e.g. for the switch- CO-3 min-CO.
ing of motors, capacitor banks, furnaces etc. A point to be particularly noted for industrial

62

5.3 62 97-03-05, 13.33


INDUSTRIAL POWER SYSTEM
Medium Voltage Distribution

applications is that switching operations may The opening pulse makes the cylinder move
be very frequent, as in the case of breakers for downwards, the upper normal current contacts
capacitor banks, certain motor applications, arc open and the current is commutated to the
furnaces, etc. Breaker selection therefore in- arcing contacts. At the same time, the gas in
volves looking not only at optimum service life the cylinder is compressed. As the opening
but also at servicing and maintenance costs. operation continues, the arc is drawn out be-
The various types of breaker available each tween the arcing contacts.
have their advantages and disadvantages. When The compression of the gas in the puffer is
assessing possible breakers, it is therefore im- increased by the heat of the are itself. At current
portant to consider all parameters. The breakers zero the compressed, cool, gas mixes with the
most commonly used are of the vacuum and SF6 hot gas in the former are region, preventing
types. A great many minimum-oil breakers, reignition and completing the interruption.
magnetic air breakers and compressed air break- SF6 breakers without mechanical compres-
ers are also still operating but are no longer used sion, known as self-blasters, are also available.
in new installations except in very special cases, (ABB HA)
e.g. for generators.

Vacuum breakers Characteristics of various


There are several differences between vacuum circuit breakers
and other types of breaker. One is that vacuum Industry involves many different operating situ-
breakers contain from the outset no gas that ations for which different kinds of breaker are
could be conducting. The parting of the metal more or less suitable, depending on the types
contacts during breaking causes an arc that of current and voltage that occur.
burns in metal vapour from the contacts. The
hot base points of the arc give off sufficient Breaking short-circuit currents
vapour for the arc to persist even when the The breaking of short-circuit currents subjects
contacts are rather far apart. When the current breakers to great stresses, both mechanical (elec-
passes through zero, vapour ceases momentar- trical forces, pressure development in poles)
ily to be given off and existing vapour con- and thermal. As breakers are put through com-
denses on available surfaces. If vapour devel- prehensive type tests involving a variety of
opment is not resumed, the breaking operation short-circuit currents, these stresses are nor-
is complete. mally no great problem. Where an installation
incorporates a number of parallel turbogenera-
SF6 breakers using the puffer principlec tors with switchgear installed very close to
(ABB’s type HPA breaker, see Fig. 52) them, as on oil platforms, it is possible for there
When the breaker is in the closed position, to be a very high DC component at the begin-
current flows via the normal current contacts. ning of a fault. As all breakers need a zero

Fig. 52 SF6 breaker using the puffer principle, ABB type HPA.

63

5.3 63 97-03-05, 13.33


INDUSTRIAL POWER SYSTEM
Medium Voltage Distribution

crossing to enable them to break, the associated overvoltages may be generated where there are
arcing times may be long and result in exces- small leakage capacitances (e.g. very short ca-
sive stresses. ble between breaker and load), but such
overvoltages are fairly low-frequency (a few
Connecting capacitive currents Hz) and can be taken care of by surge diverters,
Capacitive currents (no-load line, cable or ca- if installed.
pacitor bank) have to be broken without Considerably more serious is another phe-
restriking and this is usually coped with by all nomenon, known as voltage escalation, which
modern breakers. Connecting individual ca- only occurs with vacuum breakers. The “prob-
pacitor banks is likewise no problem, although lem” is that they are too good at breaking high-
the connecting current peaks during the con- frequency currents, so if they restrike (which
nection of parallel banks may sometimes cause happens when the contacts do not part suffi-
problems. Minimum-oil breakers are more sen- ciently the first time the current passes through
sitive in this respect than SF6 and vacuum zero), the high-frequency current is broken
breakers, so damping reactors are often used in after restriking at the first zero crossing. The
conjunction with them. Certain breakers, e.g. voltage rises between the contacts, a further
type HPA, are available with synchronised restrike occurs, and so on.
closing, which largely eliminates the connect- Hundreds of restrikes of constantly increas-
ing current and the distortions it might cause ing amplitude over a few milliseconds have
to the mains supply. sometimes been observed. Depending on the
characteristics of the circuit connected, this
Breaking small inductive currents may result in very high overvoltages, but above
Industries often use high-voltage motors of all in very large and steep voltage jumps dis-
various sizes. This frequently creates a need to tributed unevenly over the load. If the latter is,
break small inductive currents, which may in- for example, a motor, 90% of the sharp voltage
volve special problems. rise takes place across the first winding turn and
All breakers have a tendency to “chop” the destroys its insulation. In such cases, vacuum
current off before the natural zero crossing. If breakers have to be fitted with special forms of
this happens during the disconnection of an protection, like RC-links.
inductive load, the energy that is in the inductor
at the time is released and then oscillates be- Electrical endurance
tween the parallel capacitance and the induct- Some industrial applications involve a high
ance of the load. This may result in high breaking frequency, i.e., many switching opera-
overvoltages. The high chopping level (20- tions per day, which calls for breakers that pro-
30 A) of compressed air breakers has caused vide the installation concerned with optimum
many problems. The chopping level of mini- economy. Generally speaking, vacuum break-
mum-oil and SF6 breakers depends on the par- ers may be said to have the longest electrical life,
allel capacitance. This means that a higher with up to about 100 full short-circuit interrup-
capacitance results in higher chopping levels tions. SF6 breakers have the second longest life
but also more “spare” for the energy released, in this respect and minimum-oil breakers come
which means that the overvoltage level be- third. The number of rated current breaks (load
comes largely independent of the capacitance breaks) performed by breakers is considerably
and depends only on the inductance. Mini- higher, often up to about their mechanical life,
mum-oil and SF6 breakers are approximately 10,000-20,000 connections in the case of
similar in this respect, with chopping levels vacuum and SF6 breakers. Operating situations
of 2-3 A. These “chopping overvoltages” are where breaking has to take place several times
fairly low-frequency, so they represent no great an hour are not suitable for circuit breakers but
danger to motors, etc. require the use of contactors.
The chopping level of vacuum breakers,
which is 2-5 A with the most commonly used Maintenance
contact materials, is rather independent of the The various types of breakers differ radically in
parallel capacitance. This means that high their maintenance requirements, as illustrated

64

5.3 64 97-03-05, 13.33


INDUSTRIAL POWER SYSTEM
Medium Voltage Distribution

by the following description of major over- moulded case insulation. They are usually in-
hauls after a large number of operations: stalled in such a way as to act also as supporting
• Minimum-oil breakers: Overhauls involv-
ing the replacement of oil, contacts and
insulators for busbars and contacts.
These current transformers are designed ac-
possibly some breaking chamber parts have cording to IEC 185 and may be provided with
to take place more frequently than in the case various types of core. Measuring cores have
of other types of breaker, but they are very great accuracy at normal operating current but
easy to carry out, can be undertaken by the low saturation limits. Relay cores have to reg-
user’s personnel in a normal room and should ister fault currents and therefore have a high
take not more than 4-5 hours after simple saturation limit but relatively low accuracy. A
training. An overhaul interval of 6-10 years current transformer may contain several cores,
may normally be adopted. usually two or three.
• Vaccum breakers and SF, breakers need a
minimum of maintenance. The electrical en-
The following considerations apply when
selecting current transformers:
durance is very high. In case of mal function
the poles have to be exchanged. The me- 1. At least the same insulation level is required
diavisions are normally to be inspected eve- as for the rest of the switchgear.
ry 5000 operations. SF6 gas may be refilled
2. The relevant rated current has to be adopted.
in use of a pressare alarm.
For certain types of current transformer there
is the possibility of changing the rated cur-
From the operational availability point of view,
rent by primary changeover, e.g. when the
continuous monitoring of the breaking medium
is very important. No breaker can break par- load increases.
ticularly high currents if the breaking medium 3. The short-circuit current, i.e., the maximum
is replaced by air, although it should be noted current the transformer can cope with for 1
that an SF6 breaker of the buffer type can break second, also has to be tested at peak current,
the rated current and small short-circuit cur- which causes mechanical stresses. The peak
rents even when the positive pressure has com- current is normally 2.5 times the short-cir-
pletely disappeared, provided that the poles cuit current. Caution is required if primary
mainly contain SF6 gas. changeover of the current transformer is
The maintenance costs of SF6 and vacuum possible, as series connection results in lower
breakers are generally regarded as lower, which short-circuit strength than parallel connec-
compensates for their usually higher purchase tion of the primary windings.
price as compared with minimum-oil breakers.
4. The rated burden is stated in VA (volt-
amperes) and represents the load which the
Measuring transformers and secondary side of the transformer can cope
relay protection with. It may be for driving an ammeter or a
An important aspect of medium-voltage relay but it is also necessary to allow for line
losses, particularly if the relays are situated
switchgear is the various kinds of measuring
in a separate control room.
transformers used for obtaining necessary in-
formation about currents and voltages, not only 5. The overcurrent factor (ALF, accuracy limit
for charging purposes but also for detecting factor) denotes the overcurrent as a multiple
abnormal states. of the primary rated current up to which
Measuring transformers convert currents and accuracy is maintained.
voltages from very high values (kA, kV) to
values that can be used for driving relay protec- Voltage transformers (IEC 186)
tion, meters, etc. (V and A). Voltage transformers for medium-voltage
switchgear are always of the magnetic type and
Current transformers (IEC 185) insulated with cast resin. Single-phase versions
The current transformers used in medium-volt- are normally used, although two-phase are also
age switchgear are mainly of the type with available. As in the case of current transform-

65

5.3 65 97-03-05, 13.33


INDUSTRIAL POWER SYSTEM
Medium Voltage Distribution

ers, there are different accuracy classes de- Condition monitoring


pending on whether the transformer is to be One of the essentials for good operational avail-
used for measurement or for relay protection. ability is to always have good knowledge of the
Here again the choice of transformer is based state of the installation. The possibility of con-
on insulation level, rated burden, accuracy, etc. tinuously monitoring temperature changes on
See also the chapter on measuring trans- contacts and busbars provides a way to avoid
formers in ABB’s Electric Power Manual, ever being exposed to incidents due to over-
pages 219-230. heating. Being able also to check continuously
that the content of the breaking poles is correct
Relay protection means that there is no need to risk incidents due
There has been discussion over the years as to to leakage.
whether relay protection should be situated in Condition monitoring is thus an important
the switchgear or in a separate relay cubicle. Its factor in industrial applications, many of which
location used to be partly based on how safe to involve very high standstill costs. It may be
personnel the switchgear was considered, but used not only to reduce the risk of unscheduled
most switchgear is now regarded as so safe that downtime, but also to achieve better planning
relay protection can normally be installed in of maintenance work and hence lower mainte-
switchgear cubicles. The fact that relay protec- nance costs.
tion for busbar faults has been speeded up has ABB offers the Safe Guard condition moni-
also reduced the risk of harm arising from toring system for the switchgear and the circuit
faults. breakers.
Efficiency test Breaking media of circuit breaker
It is always necessary to perform an efficiency For vacuum breakers there is at present no
test by using the measuring transformer to method for continuous monitoring of negative
check that the earth fault protection actually pressure during normal operation, although SF6
works at the intended primary value. This is breakers are easy to monitor by means of pres-
particularly important in cases involving what sure monitors that give an alarm if the pressure
is known as summated current connection in the poles falls below a certain level.
whereby three single-phase transformers are
connected to one neutral and the relay protec- Operating devices
tion is provided with power supply. The Safe Guard system has an optical mea-
Earth fault protection usually takes the form suring arrangement for the circuit breaker to
of cable current transformers. Optimum pro- measure the contact velocity during each clos-
tection is achieved by placing them round the ing and opening operation and the closing and
outgoing cable. Their cores are normally made opening times. Any unduly high or low value
of silicon alloy sheet metal, although in some trigger alarms. The mechanical system is thus
cases this may be replaced by mumetal, which monitored and any imminent fault may also
has very little phase angle error. Cable current be detected, since data from up to 32 events
transformers are normally openable, i.e., the can be stored.
core can be opened to make it easy to fit round
a cable, although this procedure cannot be ap- Contact wear
plied to transformers that have mumetal cores, The breaker monitor also records the wear from
which lose their characteristics when they are each breaking operation. A large number of
divided. experiments have recorded electrical life as a
function of the breaking current. The breaker
Switchgear relay boxes have to include space monitor then measures the level of the breaking
for terminal blocks, meters, switches, warning current and generates the value that corresponds
lamps, relays etc. In cases where there is con- to the inverse of the number of possible breaks.
siderable integrated relay protection, this some- This value shows the amount of wear on arcing
times has to be moved to a control room be- contacts and other wearing parts of the break-
cause of insufficient space. ing poles. An alarm may then be set to operate

66

5.3 66 97-03-05, 13.34


INDUSTRIAL POWER SYSTEM
Medium Voltage Distribution

at a certain level, e.g. at 80% of their electri- in between. As thermovision measurement nec-
cal life. This makes it possible to achieve opti- essarily involves visual contact with high volt-
mum utilisation of the electrical life of the age, personnel safety is not best served by this
breaker and to plan maintenance work in good method.
time, resulting in more efficient use of the Temperature indicators are affixed at ex-
installation. posed points and can be read from the cubicle
front. Their colour shows the temperature, which
Temperature monitoring can therefore be checked on each visit to the
Switchgear overheating is a universally known switchgear room.
possibility, perhaps particularly in industries None of these methods provides continuous
that release corrosive gases into the atmos- temperature monitoring, nor do they trigger
phere. Here again it is of course extremely alarms to signal incipient overheating.
important to be able to detect abnormal tem- ABB has therefore developed a new moni-
perature rises in good time so as to be able to toring system whereby the temperature on high-
deal with faults before they become incidents. voltage equipment can be continuously moni-
The two methods so far developed for indicat- tored and recorded (see Fig. 53).
ing temperatures on high-voltage equipment This makes it possible not only to prevent
are thermovision measurement and tempera- unscheduled stoppages due to overheating but
ture indicators that change colour. also to use the installation more efficiently by
Thermovision measures the temperature of controlling power offtake due to temporary
a busbar at the exact time of measurement. The overloads.
next measurement may perhaps be a year later
and nothing may be known about what happens

Fig. 53 Temperature monitoring system.


• = measuring points

67

5.3 67 97-03-05, 13.34


INDUSTRIAL POWER SYSTEM
Transformers

TRANSFORMERS

Contents
page
1 Standard specification 68
2 Three-phase connections and nation of phase displacement 69
3 Short-cicuit impedance and voltage drop 71
4 Parallel connecition of transformers 73
5 Agering considerations and emergency service 74
6 Inrush current 75
7 Capitalisation of losses 75
8 Installation considerations 76

Standard specifications
Some general terms and concepts a desiccant breather or with a membrane for
A power transformer is a transformer in- prevention of contact with the atmosphere.
tended for transmission of power - at least 5 Another system, in American practice, has a
kVA three-phase or 1 kVA single-phase. Such cushion or ”blanket” of nitrogen gas above the
transformers are specified and tested according oil in a hermetically sealed or controlled-pres-
to Power Transformer Standards. There are sure tank.
other standards for smaller transformers, for There is also a type of distribution transfor-
certain special transformers for protection and mer of European design with corrugated tanks
safety, and for instrument transformers (meas- (cooling fins), completely filled with oil and
uring transformers). hermetically sealed. The corrugations take up the
volume expansion elastically (although one
A distribution transformer is the last link in must be alert to possible overloading capability).
the chain of step-down transformers. It steps Liquid-immersed transformers with non-
down from local distribution high voltage (6, flammable liquid (earlier: chlorinated biphe-
10, 20 kV) to consumer low voltage (not above nyls - many trade-names exist) were marketed
1 kV). According to European tradition, distri- aggressively in the past, but have been banned
bution transformers are three-phase units. In nowadays for environmental reasons. Alterna-
the American tradition, single-phase distribu- tive liquids have been proposed, but have had
tion transformers are common. little market penetration as yet.
The usual range of rated power is from 30-
100 kVA to 1 000-2 000 kVA. Standards have Dry-type transformers are generally avail-
set a limit at 3150 kVA. able in the distribution transformer range of
Distribution transformers are either oil-insu- voltage and power rating. Two different prac-
lated or of dry type. tices are followed: bare windings with air ducts
for insulation, and encapsulated (resin-cast)
Oil-immersed and dry-type transformers. windings. The types differ mainly in terms of
Large power transformers are oil-immersed immunity against moisture and pollution.
and provided with some kind of oil preserva-
tion system. The more common system em- Items to be specified. Power transformer stand-
ploys a ”conservator” (expansion vessel) with ards contain lists of items - in addition to the

68

5.4 68 97-03-05, 13.35


INDUSTRIAL POWER SYSTEM
Transformers

rated electrical quantities - that have to be low voltage winding is to carry the taps. In the
specified for a customised transformer - such as European tradition, the taps and the on-load
cooling system and oil preservation system tap-changer are usually fitted on the high volt-
(self-cooling, or forced cooling with fans and/ age side. In America it has traditionally been
or oil pumps), insulation levels, tappings and the other way round.
tap-changer, desired value or range of short- It may be that the untapped winding faces the
circuit impedance, etc. system having the widest variation of service
At medium system voltages the insulation voltage, and the tapped winding runs with nearly
levels are fixed in relation to the system voltages, constant voltage. This means that the volts-per-
but at higher voltages there are alternative op- turn will vary when tappings are changed (vari-
tions. able flux regulation).
Recommended lists of auxiliary equipment The latest IEC Standard, Publ. 76-1 (1993-
for protection and supervision are given in 03) and national standards in conformity there-
national standards for certain categories of trans- with prescribe that the notation of tapping range
formers, and in manufacturers’ catalogues. is to be related to the variation of turns in the
tapped winding, but it is also recommended
The term regulating transformer has a differ- that a full table should be provided on the name-
ent meaning in different countries. It is some- plate, indicating for every numbered tapping
times used for any transformer provided with a the maximum service voltages on both the
tap-changer for adjustment of its ratio - in tapped and the untapped winding. This table
contrast to a fixed ratio transformer. Otherwise also deals with optional truncation of ultra high
the word is used specially for a separate booster voltages or extremely high currents towards the
unit (inserted for voltage correction in a weak ends of the tapping range. This is elaborated in
system - having a variable ratio close to unity), Chapters 5 ??? and 7 ???, and Annex B of IEC
or for a transformer which is to deliver second- Publ. 76-1.
ary voltage over a wide range from nearly zero
up to a maximum value (e.g. testing equip- Tap-changers. As the term indicates, an on-
ment). Special process transformers for fur- load tap-changer is capable of changing the
naces or electrolysis, delivering very high sec- ratio of the transformer without interruption of
ondary current, may consist of a set of two units service. The off-load tap-changer is a simpler
- one wide-range, high voltage regulating trans- device that must not be operated unless the
former and another fixed-ratio, step-down trans- transformer is disconnected.
former fed from the regulating unit. The extent to which medium-size step-down
transformers for utilities are provided with on-
The tapping range of a transformer is usual- load tap-changing varies from country to coun-
ly expressed as a rated voltage, plus-minus try. The conventional width of the tapping
a number of equal tapping steps (e.g. 120 kV range in per cent also varies.
± 9 x 1.5%). According to older practices, the Distribution transformers are as a rule pro-
numbers may either indicate the specified range vided with a small range of off-load taps (plus-
of variation of service voltage on the winding in minus 5 per cent in three or five positions). A
question (regardless whether the winding is suitable tapping is not selected until the trans-
tapped or not) or, instead, the range of variation former is installed, and will usually not be
of turns available on the winding. In interna- changed later.
tional standardisation a comprehensive treat-
ment of transformers with considerable tapping
range has not existed until quite recently. It is
important to establish what the name-plate in- Three-phase connections and
formation on older transformers really means! notation of phase displacement.
In actual service, the voltages will vary more or (The following refers to IEC Standards. Ameri-
less on both sides of the transformer, but only can practice differs somewhat.)
one of the windings is tapped. There is not a free Short notation of three-phase winding con-
choice whether the high voltage winding or the nection and phase displacement employs a code

69

5.4 69 97-03-05, 13.35


INDUSTRIAL POWER SYSTEM
Transformers

of letters and numerals, e.g. YNyn0, Dy11, power minus power loss and reactive power
YNautod5. The system is as follows: consumption in the transformer. These conven-
tions are independent of direction of power
• The windings are noted beginning with the
high voltage winding, and with following
flow through the transformer.
U.S. Standards interpret rated power as
windings in the order of falling rated voltages. delivered secondary power. Primary input
The high voltage winding connection is noted power and voltage will be rated power and
with capital letters; the others with lower- voltage plus the consumption and voltage drop.
case letters. Step-down transformation is presupposed, and
• The connections are Y(or y) for star, D (d)
for delta, Z (z) for zigzag, and I I I (i i i ) for
the power factor is to be at least 0.8 (inductive).
In most practical cases the difference be-
open windings (all ends brought out sepa- tween the two systems of standards is apparent
rately) only at the specification stage, and will be of
• A neutral terminal taken out from a y or z
winding is indicated by the letter ”n”: YN, zn
little importance. Once the ratings are fixed,
tests and other related data (losses, short-circuit
• Phase displacement between ”correspond-
ing terminals” of the windings is expressed
impedance) come out the same.

by the ”clock method”. The high voltage Rated voltage is a quite critical parameter
winding phasor is understood to be at 12 nowadays, since transformers with modern core
o’clock (not indicated). The other winding steel are operated with flux density close to
or windings are given clock hour numbers saturation. Overfluxing a transformer results in
showing the direction of their respective abnormal magnetising current, and may cause
phasors in the phasor diagram. The clock overheating of steel parts in the vicinity of the
hour number is written after the connection core. For a transformer with tappings, the ”tap-
letter. All usual connections lead to full ping voltages” for specific tapping numbers
hours. The system is best understood by (indicated on the name-plate table) have the
studying the examples in Fig. [ ? ]. same significance as the rated voltage has for
• Auto-connection between two y windings is
indicated - for example as YNauto or YNa0
the ”principal” (central) tapping.

• A separate equaliser delta winding (not avail-


able for loading) is indicated as ”+d” , e.g.
Difficulties with overfluxing may occur if a
transformer is connected to a load with a very
YNy0 +d low power factor (capacitor bank or compen-
sating reactor). The numerical voltage drop
Note that there are different systems of termi- across the transformer is then at its maximum
nal markings in use in different countries: (positive or negative). Such cases should be
ABC - RST - UVW - H1H2H3. National stand- indicated and analysed before the transformer
ards specify this. is ordered. The important fact is whether the
direction of reactive power flow is from an
Specified ratings and loadability in service outer winding towards the winding closest to
Rated quantities are reference values for guar- the core, or the opposite. (A priori it is often not
antees and tests. The no-load loss is referred to known whether the low voltage or the high
rated voltage. The short-circuit impedance and voltage winding is closest to the core - this is not
the load loss are referred to rated current. Dur- apparent from the name-plate, for example.)
ing the temperature rise test, the total loss to be
injected also corresponds to the rated quanti- Rated current is not critical in the same sense.
ties. Temporary loading of the transformer above
IEC Standards interpret rated power as rated current leads to higher winding tempera-
incoming power (rated voltage, rated current). ture rise above surrounding oil, and (more
On a loaded transformer, if the primary voltage slowly) increasing oil temperature in the whole
is equal to rated voltage, the secondary voltage tank. The ordinary winding loss and eddy cur-
will be equal to secondary rated voltage minus rent loss rise strictly by the square of the current.
voltage drop. Delivered power is incoming The stray flux between the windings rises in

70

5.4 70 97-03-05, 13.35


INDUSTRIAL POWER SYSTEM
Transformers

proportion to the current, and its stray loss small separate ”earthing transformer” with a
heating effects on adjacent steel parts rise by YN or ZN winding.
about the square. In a well designed transformer Distribution transformers feeding four-wire
there is considerable margin between rated cur- or five-wire low voltage networks with single-
rent loading and an overload which would cre- phase loading between phase and neutral (”zero
ate immediate risk of serious damage to the sequence”) are specified with mixed connec-
transformer. Cyclic or temporary loading up to tion: Dyn, or Yzn. These connections provide
high values with corresponding temperature neutralisation of the secondary neutral current,
swings, however, results in mechanical dilation so that this is not carried over to the primary
of the windings and corresponding permanent system. The primary system is usually reso-
set of the insulation structures, which may re- nant-earthed in some European countries.
duce the rigidity of the design in case of heavy
through-fault current. See also the section on Type of cooling is indicated by a four-letter
ageing and emergency loading below. code (IEC). The common alternatives for oil-
General information on loading characteristics immersed and air-cooled transformers are:
of representative power transformers is pre-
sented in the form of ”Loading Guides” by ONAN: self-cooled by air - without oil pump
or fan
standardisation bodies (IEC and ANSI). These
ONAF: natural oil circulation - forced air cool-
documents, however, cannot give guarantees
for any specific transformer; only general guid- ing by fans
OFAF: oil circulation through coolers forced
ance.
by pumps - air flow by fans
Three-phase connections are selected based ODAF: oil flow by pumps, directed right in-
to the windings - air flow by fans
on several considerations.
(mainly for large transformers, above
The simplest combination is Yy. It is used in
large system transformers - often with auto- 100 MVA)
connection. In separate-winding transformers
Alternative cooling systems may be specified
either the high or the low voltage winding, or
both, may have their neutral terminals taken out for the transformer. Information is thereby given
about, for example, the permissible load on an
for system earthing according to different princi-
ONAF transformer if the fans are stopped (the
ples (see Chapter ??? on this subject). The
connections are then YNy, Yyn, or YNyn. transformer becomes ONAN). According to
IEC, the rated power figure is unique, and
If either of the connected systems carries
relates to the highest cooling capacity.
zero-sequence current (current to the neutral -
either single-phase load between phase and According to U.S. Standards, there are mul-
tiple power ratings assigned for the different
neutral or earth-fault current) which cannot be
cooling steps.
transformed across the transformer to the oppo-
site system, then it may be required to provide
an equaliser delta winding, in which compen-
sating zero-sequence current will be induced Short-circuit impedance and
(circulating around the delta winding). This voltage drop
”reduces the zero sequence impedance”. (See Short-circuit impedance (or short-circuit volt-
the section on system earthing under Chapter age) is the series impedance that the transformer
??? , Relay protection, p. [?] presents when current flows through it. The name
derives from the measurement of this quantity in
”Mixed connections” are, for example, the com- one of the routine tests on the transformer, the
binations YNd, Dyn, or Zyn. Again, the selec- short-circuit test. A reduced voltage is applied to
tion of these combinations is related to system the terminals of one of the windings with the
earthing and earth fault considerations. As there opposite winding short-circuited. The test volt-
is no neutral terminal on a D winding, it may be age is raised, until rated current flows - this is the
necessary to provide an artificial system neu- ”short-circuit voltage”. It is expressed as a
tral point at the transformer by connecting a percentage of the rated voltage of the energised

71

5.4 71 97-03-05, 13.35


INDUSTRIAL POWER SYSTEM
Transformers

winding. The percentage figure is the same, re- limitation for cable systems, accuracy of reac-
gardless of whether it is measured from the high tive power compensation, etc.
voltage or the low voltage winding.
The ”short-circuit impedance” is the same Three-phase conventions for symmetrical quan-
percentage of the ”reference impedance” of tities:
the transformer, i.e., the impedance that the Current I is line current
loaded transformer represents when it passes Voltage U is line-to-line voltage
rated current at rated primary voltage. (The Three-phase apparent power S = ô3 ⫻ U ⫻ I
percentage figure also indicates the apparent U
Impedance per phase Z = 3:I
power in MVA that the transformer itself ab- ô
sorbs under the same conditions, as a fraction of (”As in Y-connection”)
the rated apparent power).
Other expression for Z = U 2
S
The short-circuit impedance is represented in where S is the three-phase power
the equivalent diagram of the transformer as a (Z in ohms, U in volts, S in Volt-amperes, or
resistance, representing the load loss, in series Z in ohms, U in kV, S in MVA)
with an inductive reactance, representing the
reactive power required by the leakage flux Rated quantities for the transformer are denoted
betweeen the current-carrying windings (cf. with index ”r”
equations below). Sr, Ur, Ir, and Zr
All percentage figures are referred to the rated
The reactive part of the short-circuit impedance quantities.
dominates, and the larger the transformer, the They are noted with common letters, not capi-
more this is the case. tals.
A 1 000 kVA distribution transformer has a
loss figure of the order of 1 % of the rated power, Short-circuit voltage: uk = 100 ⫻ Uk
while the short-circuit reactance is typically 6 (dimensionless) Ur
%. At higher power ratings the percentage loss
becomes lower, but the percentage reactance Short-circuit impedance ZT = RT + j XT
increases. A ”natural” reactance of a trans- (impedance per phase)
former emerges from economic optimisation of
the design with regard to capitalisation of no- Percentage short-circuit impedance
load loss and load loss. A transformer with low ZT
average loading has a low load loss capitalisa- zT = rT + j ⫻ T = 100 ⫻
Zr
tion rate; this results in a transformer with light (This number is also dimensionless and is iden-
magnetic core, low no-load loss, high load loss tical with uk)
and high percentage short-circuit reactance.
The voltage drop across the transformer is the
In some countries there is a praxis that the user product of the load current, multiplied by the
specifies fixed values of series reactance. This transformer short-circuit impedance. However,
may be in order to facilitate parallel operation this ”vectorial voltage drop” is not in phase with
between arbitrary transformers of the same the current, leading it by nearly 90 degrees,
range; cf. the section below on parallel opera- since the short-circuit impedance is mainly in-
tion of transformers. Typical reactance values ductive. The conventional, ”arithmetic” voltage
for normal utility step-down transformers are drop which is observed on the voltmeter is the
astonishingly different in different countries; a ”arithmetic” difference between the voltage at
10 - 20 MVA transformer may have values rang- no load and the actual voltage with the load
ing from below 10 % up to 20 - 25 %. These applied. Depending on the phase angle of the
traditional practices depend on different phi- load, this quantity may assume any value be-
losophies regarding the layout of medium volt- tween zero and the full vectorial voltage drop,
age systems: average distance between stations, and may even be negative (the secondary volt-
installation of spare capacity, short-circuit power age of a transformer will rise, not fall, when

72

5.4 72 97-03-05, 13.36


INDUSTRIAL POWER SYSTEM
Transformers

capacitive load is added). The voltage drop is section below on ageing and emergency serv-
largest for low power factor, inductive load. ice). Under the light load season one of the units
This explains why there is such a heavy voltage may be taken off (the no-load loss in the station
dip when a large motor is started - the starting is then reduced to half). Under normal condi-
current is large, and the power factor is low. tions with both units available it is possible to
sectionalise the secondary busbar (reduced short-
Assume stiff source voltage on the primary side circuit fault current).
of the transformer. ”Dual-secondary” transformers have two sec-
The secondary voltage at not load is then U20 ondary windings with the same rated power, and
with low coupling between them (”double-con-
Apply an apparent power load centric” winding system or ”vertically split
S windings”). They work, as it were, like two
S=P+jQ=
cos j + j sin j parallel transformers on a common core.
This load represents an impedance per phase
Tap-changer mismatch by one step not a
ZL = U2 ⫻ (cos j + j sin j) problem
S When two parallel transformers are equipped
The secondary voltage changes by the drop with tap-changers, there are different systems to
DU from U20 to U2 coordinate their movement. During the short
U2 = ZL interval while the two tap-changers rest in dis-
(this equation is complex) similar (staggered) positions, there will be a
U20 ZL+ZT
small superimposed current that circulates be-
After algebraic operations an approximate ex-
tween the transformers. The e.m.f. which drives
pression of the voltage drop is optained, ex- this current is one-step voltage, and it meets the
pressed in percent of rated voltage:
series-connected short-circuit impedances of
Du = S ⫻ (xT sin j + rT cos j), the two transformers. The circulating current
Sr will be of the order of 1/10 or 1/20 of rated
or I ⫻ (xT sin j + rT cos j) current. It is essentially reactive, and combines
Ir vectorially with the load current. Obviously, the
Example: Load is 50 % of rated current or rated whole phenomenon is in fact negligible. The
apparent power. Power factor is 0.8, inductive estimate is also applicable in cases of parallel-
Transformer load loss rT = 08 % of rated power. ing non-identical transformers which have
Transformer rectance xT= 12 %. (If cos j = 0.8, slightly different rated or tapping voltages (see
sin j = 0.6). the following section).

Du = 0.50 (12 ⫻ 0.6+0.8 ⫻ 0.8) = 3.9% - say, 4% Paralleling of transformers with non-identi-
cal data
Parallel connection of transformers having non-
identical data is possible under the following
Parallel connection of conditions:
transformers
Two units with the same data - spare capacity
consideration
• They must have the same clock-hour phase
relationship. (There are stratagems with re-
A normal utility installation practice is having versed phase sequence, etc., which make a
two identical units side by side. If the rated few additional combinations possible; con-
power of each unit is, say, 70 % of the full load sult experts or the IEC standard)
in the station, then there is 40 % overcapacity
under normal service. However, if one of the
• They must have identical or closely similar
rated voltages. Units with tap-changers need
units should fail, continued emergency service not have precisely the same tapping voltages,
may be provided by overloading the remain- but there must be a sufficiently wide overlap
ing unit, in the worst case up to the proportion of the tapping ranges. A small difference in
100/70. This may still be acceptable (cf. the tapping voltages between the units would be

73

5.4 73 97-03-05, 13.36


INDUSTRIAL POWER SYSTEM
Transformers

limited to not more than one tapping step if of either turns ratio, or differing short-circuit
the co-ordination of the tap-changer controls impedances. This implies that requirements re-
is optimised. The remaining mismatch of garding matching transformer data should not
current sharing should not be given exagger- be exaggerated. A more rational approach in the
ated attention (cf. preceding paragraph about enquiry would be to request from the designer a
staggered tap-changer positions). calculation of the resulting load sharing. The
• They must have approximately the same
short-circuit impedance in per cent. If the
load must be described with both apparent power
and power factor, or by separate figures for
short-circuit impedances in per cent are the active and reactive load power. A reasonable,
same, the transformers will share the load allowable tolerance (e.g. 10 %) for the load
current in proportion to their rated currents mismatch should be specified.
(or rated power values). It is easy to under-
stand that if one of the units has a lower
reactance it will absorb a relatively larger Ageing considerations and
proportion of the load current (so that the emergency service.
voltage drops become equal for both trans- Rated current or rated power is not a precise
formers). The result will be that the sum of limit of loadability for the transformer. How-
the rated power values for the two transform- ever, loading beyond name-plate rating natu-
ers cannot be utilised fully. Standards some- rally means more rapid wear and tear on the unit.
times give the recommendation that the reac- It is very difficult to express this in quantitative
tance values should not differ by more than terms. An effort to provide a scientific back-
plus/minus one-tenth of the average value. ground is based on spontaneous chemical dete-
For two units having the same rated power rioration of the insulation system as a function
this would result in a reduction of their com- of the service temperature.
mon loadability of the order of 10 per cent. The rate of reaction of the chemical oxydation
One should not connect transformers with widely processes grows exponentially with the tem-
perature. An addition of a certain number of
differing power ratings together. The risk is that
degrees of temperature corresponds to a multi-
the small transformer will be the one that sets the
limit of common loadability since it is likely to plication of the rate of deterioration by a certain
factor. Conventionally, an increment of 8 Kel-
have a lower short-circuit impedance in per
vin is supposed to correspond to a doubling of
cent. Standardised distribution transformers
often have short-circuit impedance values fixed the rate of deterioration. Or, about 25 K higher
temperature raises the deterioration rate by a
in large steps: 4, 5, 6%, increasing with the rated
factor of 10.
power.
Emergency service implies that the unit takes
Specification of a new transformer intended over load which would normally flow through a
for parallel operation with an existing unit. different route. The pattern of variation over the
Suppose that it is not possible to obtain a true day will remain unchanged, but the level will be
repeat of the old transformer. The manufacturer higher - in the worst case perhaps close to
may have modified his design standards or double the load. Carrying the above example
completely changed his range of products. Or further, a month of moderate emergency serv-
else, the enquiry may be directed to a different ice, leading to a representative temperature 25
factory. It is then often difficult to obtain close Kelvin higher than before, would then affect
agreement with the previous data, particularly and shorten the life of the transformer about as
the variation pattern of the impedance along the much as a full year of undisturbed service would.
tapping range of a regulated transformer. This is If such scenarios are identified and recognised
dependent on the physical arrangement of the during strategic planning, and the transformer
windings with respect to each other, and is also ratings selected to cope with them, then the
subject to several design considerations. In the installed overcapacity becomes a kind of calcu-
previous paragraphs of this section it has been lated insurance premium.
explained how to estimate the magnitude of a There is no basis, though, for calculations of
circulating current that results from mismatch consumed or remaining lifetime of a trans-

74

5.4 74 97-03-05, 13.36


INDUSTRIAL POWER SYSTEM
Transformers

former in absolute terms: years, or percentages. as of a full short circuit through the trans-
Besides, there are many other factors, e.g. in the former: far above rated current peak. This worst-
form of occasional overvoltages or overcurrents, case current amplitude is possible only if the
or neglected maintenance and inner contamina- transformer is energised on the inner winding,
tion, that may contribute to the breakdown of a which is usually the low voltage winding. En-
transformer. ergising from the low voltage side should there-
fore be avoided. (However, it should be noted
Some conventional guidelines concerning emer- that the oscillatory, transferred switching
gency service have been agreed upon (IEC overvoltage on the non-connected high voltage
Loading Guide): side is not without risk either.)
During ”long-time emergency loading” - last- A particular phenomenon has been observed
ing for weeks or even months - it is recom- when a second transformer is energised in par-
mended that the hottest part of the windings allel with another, both at no load. The transient
should never exceed 140°C in a medium-size asymmetric saturation may then oscillate back
transformer, or 150°C in a distribution trans- and forth between the two for a considerable
former, while the current should never exceed time, which may confuse the relay protection.
150 % or 180 %, respectively, of the rated fig- The inrush current is sensed by the differen-
ure. The top oil temperature should never ex- tial protection relay, as well as by the neutral
ceed 115°C in any transformer. current protection and overcurrent protection.
The characteristic content of even-order har-
”Short-time emergency loading” is loading monics has, however, made it possible to design
which is so high that some remedial action has a blocking feature against inrush current trip-
to take place; within half an hour or so. This may ping. Another, more simple method is to install
be by manual intervention or through tripping a time-lag device, so that the inrush transient
by thermostats for oil temperature or winding gets time to decay before any tripping signal is
temperature, well before the temperature in the released.
transformer has reached its critical value. The
top oil rise limit is again limited to 115°C
(tripping at 120°C). The maximum allowable Capitalisation of losses
current is tentatively limited to 180 % for a
Utilities apply capitalisation of loss figures for
medium transformer (overcurrent tripping pos-
the evaluation of transformer bids. They submit
sibly set at 200 %). Note that it is also usual to separate capitalisation rates per kW of no-load
have a blocking function in the tap-changer
losses and of load losses. These capitalisation
which prevents operation when the current ex-
rates are based on the applied interest rate for
ceeds 200 %. investment, and - for the variable load loss - on
the expected utilisation of the transformer, ex-
pressed as utilisation time of the maximum load
Inrush current in hours per year.
When a transformer is energised, a high inrush In industries there are some transformers
current sometimes occurs at random. This is which see load variations over the day and over
caused by transient saturation of the core steel. the year that are similar to utility loading char-
Its magnitude depends on the remanence condi- acteristics, with a typical utlisation time of 4000
tion of the transformer core since the previous hours. For such transformers, the capitalisation
disconnection, and on the point of wave of the of load loss should be given a rate 1/3 to 1/5 of
AC voltage at which the phases are closed. the rate applied for no-load loss. The absolute
The inrush current does not have symmetri- figures depend on the interest rate for invest-
cal half-cycles, but has a pronounced DC com- ment money.
ponent, and contains harmonics of even num- Process transformers (e.g. for electrolysis)
bers of order. The whole phenomenon decays in may have utilisation times ranging up towards
the course of a few seconds. It is accompanied 7000 hours. The correct rate for load loss capitali-
by a distinctive sound - a heavy thud. The maxi- sation would then rise to about 2/3 of the no-
mum possible current peak is of the same order load loss rate.

75

5.4 75 97-03-05, 13.36


INDUSTRIAL POWER SYSTEM
Transformers

Installation considerations
Most transformers are air-cooled. When they
are installed in closed cells for fire protection,
there must be adequate provision of cooling air.
For satisfactory cooling, the temperature rise of
the air cannot be taken higher than about 10
Kelvin. This corresponds to a consumption of
about 5 cubic metres of air per minute for each
kW of dissipated losses. All ducts must be sized
for this capacity.
ONAF transformers with radiators and fans
are usually arranged so that the fans blow
horizontally into the radiator banks. The warm
air flows upwards spontaneously. It is impor-
tant to arrange the cell so that this warm air will
disappear out, and not be recirculated down
again in the cell by the fans. Either there have
to be sufficiently wide ducts for incoming and
outgoing air, or separate fans for supplying
sufficient cooling air to the cell.
In case of fire in the cell, the large flows of
cooling air, sometimes forced, would be an
aggravating factor. Therefore, automatic flaps
or shutters have to be installed to stop the supply
of air when fire in the cell is detected.
In metallurgic plants large transformers are
installed close to the furnaces, where the ambi-
ent air is full of dust and fumes. The transform-
ers are then often specified as having water
cooling. A different solution has been practised
with advantage, namely that of designing for
OFAF cooling and running oil pipes to compact
oil-to-air coolers located outside the building.

Distribution transformers in a factory typically


feed widespread motor drive installations. If
oil-insulated transformers are used, they have to
be placed in cells outside the building, out of
regard for the risk of fire and oil spillage. In
order to limit the cost of heavy low voltage
cables and also the losses in these, a popular
solution is to distribute the load centres over the
floor area. This then leads to the choice of dry-
type units which can be installed in simple
metal-clad cubicles with self-cooling by ambi-
ent air through venting slots.

76

5.4 76 97-03-05, 13.36


INDUSTRIAL POWER SYSTEM
High voltage switchgear

HIGH VOLTAGE SWITCHGEAR

Contents
page
1 Air insulated (AIS) and Gas Insulated Switchgear 77
2 Switchgear components 78
3 AIR Insulated Switchgear (AIS) 80
4 GAS Insulated Switchgear (GIS) 84

Air Insulated (AIS) and Gas


Insulated Switchgear (GIS)
General
Until the 1970s, air insulated switchgear (AIS) out easily. When equipment capacities need to
was the type most in use. AIS requires large be uprated, or the network arrangement has
distances between earth and phase conductors been altered, new equipment may be more
and therefore a good deal of space. Hence, for easily added or changes made.
the higher voltages, this type of installation was With regard to investment costs for the
only feasible outdoors. In some cases it was switchgear alone, AIS is considerably less ex-
possible to install indoor air insulated equip- pensive than GIS. However, when costs for
ment at voltages up to 145 kV, but above 36 kV, maintenance and land area are added, the dif-
outdoor installations had traditionally been the ference becomes less.
rule.
Germany and Japan first introduced SF6 (sul-
phur hexafluoride) as an insulating medium in
switchgear enclosures in order to reduce phase-
to-earth distances. By giving the gas an
overpressure of approx. 500 kPa, this further
improved insulating properties and led to a
reduction in space requirements.
There are now approximately ten world
manufacturers of GIS switchgear, most of them
in Europe and Japan. The advantages of GIS as
compared to AIS are as follows:

• Less space requirements - especially in con-


gested city areas
• Less sensitivity to pollution, as well as salt,
sand or even large amounts of snow
• Higher personnel safety - enclosed high volt-
age and insignificant EM fields

Conventional AIS is constructed outdoors with Fig. 1. Comparison of dielectric strengths.


free-standing switchgear components joined
together by lines or tubular buswork. The ad-
vantage of such an arrangement as compared to
GIS is mostly that modifications may be carried

77

5.5 77 97-03-05, 13.37


INDUSTRIAL POWER SYSTEM
High voltage switchgear

Switchgear components
High voltage equipment has to match or exceed
the available short-circuit level at the location
in the network where it is installed. It is also
commonly agreed that the equipment must with-
stand this short-circuit current for the time taken
for the back-up protection to clear the fault.

Circuit breaker
This is the most important switchgear compo-
nent. It must be able to break and make normal
load currents, but above all be able to interrupt
short-circuit currents due to faults in the sys-
tem. Modern circuit breakers have interrupting
times as short as 20 milliseconds. Such an
operation is performed automatically in re-
sponse to signals from fault sensing relays.
The main components of a circuit breaker are

Fig B Centerbreak disconnect switch

the interrupting chamber and the mechanical


operating mechanism.
Energy is stored in charged springs in the
operating mechanism, and when called upon,
this energy is released such that the breaker
contacts are forced apart. The arc now estab-
lishing itself between the parting contacts is
then extinguished by high pressure oil or SF6
gas blown towards the arc. The stored ener-gy
must be sufficient in order for the circuit breaker
to manage one complete open-close-open se-
quence.
There is a tendency for SF6 gas to become a
common interrupting medium for circuit break-
ers used in outdoor AIS as well.

Disconnector
Disconnectors are used in order to switch dur-
Fig A Live tank circuit breaker for outdoor ing no load conditions. In order to make a
switchgear circuit breaker ”dead” (without voltage) and

78

5.5 78 97-03-05, 13.37


INDUSTRIAL POWER SYSTEM
High voltage switchgear

thereby available for service or maintenance, a


disconnector may be used on either side.
Disconnectors may also be used in order to
change the switching arrangement. A discon-
nector has a very low breaking capacity and
may only be operated under no load (no cur-
rent) conditions. The disconnector’s main pur-
pose is to provide an open circuit on both sides
of an item of equipment prior to working on it.
Opening or closing a disconnector takes sev-
eral seconds to complete.

Earth switch
An earth switch is a special kind of disconnector,
used to connect parts of the switchgear to earth,
also prior to working on otherwise live equip-
ment such as lines or cables. Earthing can also
be done in AIS by means of manual earthing
hooks or portable earthing and short-circuiting
devices. However, in GIS there is no access to
phase conductors in this manner. Therefore,
permanent earthing switches must be installed.
Some of these are designed to connect to earth
under full voltage, which requires them to with-
stand, both electrically and mechanically, clos-
ing of a full short circuit.

Surge arrester
Surge arresters protect switchgear against high
overvoltages caused by for example lightning Fig C Zink-oxide surge arrester with polymeric
or switching overvoltages. They work on the insulator
principle of leveling the incoming voltage wave
and diverting the energy as a current. When the
voltage returns to normal, the current is re- Current and voltage transformer (instru-
duced to zero. A good surge arrester has a low ment transformer)
ignition voltage and a high extinction voltage, Instrument transformers are required in order
thus providing a non-linear function between to provide signals for metering and protective
current and voltage. Earlier makes of surge relaying. Depending on the purpose of the sig-
arresters generally had silicon carbide resistors nal, the accuracy may vary greatly. Current
and a spark gap (valve type) to obtain a high transformers operate under almost short-circuit
non-linear function between voltage and cur- conditions, while voltage transformers operate
rent. Modern zinc-oxide arresters have no spark at no load.
gap and provide many advantages such as low Current transformers normally have a magnetic
voltage during dissipation, elimination of coupling between primary and secondary side.
reignition transients as well as a high capacity Magnetic flux follows cores of different mag-
for diverting energy. netic material, depending on whether its use is
Correct insulation co-ordination is achieved for metering or protection purposes.
through properly selecting and locating surge Protection current transformers must withstand
arresters in the network. The most strategic both the peak short-circuit currents as well as
locations for surge arresters are at the terminals the time taken for the longest set back-up relays
of transformers, reactors and incoming over- to operate. It is very important to match the
head lines. relay burden to the current transformers in

79

5.5 79 97-03-05, 13.38


INDUSTRIAL POWER SYSTEM
High voltage switchgear

order that saturation of the cores at high cur- that it is important to specify data for the total
rents does not trick the relays into thinking they relay and metering burden. Voltage transform-
are seeing a different current from the actual ers are usually connected phase to earth.
one.
Voltage transformers can be divided into in-
ductive and capacitive types. The inductive
type is normally used up to approximately 145
kV, while the capacitive type is used above this
voltage. If power line carrier frequencies are
required for communication or for protective
relaying, capacitive types may be used for this
purpose at lower voltages too.
The metering range for the secondary voltage
transformer winding is 80-120% of the nomi-
nal voltage. The relay winding has a range from
5-150 or 190%. The different secondary
windings of voltage transformers have a cou-
pling dependency on each other (which is dif-
ferent from current transformers), and this means

Fig D 2 Top core type current transformers

Line traps
Line traps are installed in power systems where
high frequencies are used for communication
via the high voltage system itself. The line traps
are in reality a barrier that effectivily prevents
high frequency from entering the substation. In
this way a frequency can be reused in other
parts of the network.

AIR INSULATED
SWITCHGEAR (AIS)
Busbar arrangements
Some common arrangements for industrial ap-
Fig D 1 Hair pin type current transformers plications are:

80

5.5 80 97-03-05, 13.39


INDUSTRIAL POWER SYSTEM
High voltage switchgear

Single busbar
Arrangements of this type are the most com-
mon. The majority of Scandinavian power com-
panies use this arrangement up to 145 kV, and
it is growing in popularity in other countries too
for ordinary, uncomplicated industrial purposes.

Single bus with transfer bus


The transfer busbar is used only as an auxiliary
busbar when maintenance is being carried out
on a line circuit breaker. The breaker can be
disconnected on both sides while the line re-
mains in service. One limitation of this arrange-
ment is that the whole station is shut down
when a fault occurs on the main busbar.

Double busbar
This system has two identical buses, i.e., one
can be a standby for the other. This arrange-
ment guarantees uninterrupted service in the
event of a busbar fault. The circuit breakers,

Fig D 3 Magnetic voltage transformer

No busbar
This arrangement represents the simplest de-
sign for small transformer substations. When a
fault occurs, the whole station is shut down but,
on the other hand, initial costs are the lowest.

Fig. 2. Some common switchyard arrangements. Fig D 4 Capacitive voltage transformer

81

5.5 81 97-03-05, 13.39


INDUSTRIAL POWER SYSTEM
High voltage switchgear

however, are not available for maintenance and also involves different design problems.
without the associated bay being disconnected.
Apart from that, operating flexibility is good. For low current ratings requiring only light-
weight conductors, a strain bus may result in a
Design considerations for civil works more economical design, i.e., with lower costs
A large part of the design work for an outdoor for foundations, structures, insulators, conduc-
switchyard is civil and structural engineering. tors, etc., as longer spans can be used than with
Levelling of ground, sizing of foundations, tubular conductors.
layout of cable ducts, etc., require civil works On the other hand, increased loads, considera-
drawings for foundation plan and cable ducts. tion of the dynamic stresses imposed upon buses,
For manufacturing and ordering of equipment, together with a preference for the low-profile
for erection and commissioning of the plant, concept, have combined to bring about a move
further drawings are required for steelwork and towards a supported tubular bus rather than the
other hardware, as well as layout (plan and use of heavy stranded bundle conductors.
section) drawings, material lists, purchase or- The bus design usually includes aluminium
ders, cable schedules, etc. Today this documen- conductors with bolted connectors. The fully
tation is mostly produced by computers. welded design, however, is also used. There are
some problems involved in welding on site as
When establishing the design parameters for this must be done in a protective gas flow. Fur-
steel structures and foundations, it is logical to thermore, special reinforcements have to be
evaluate the maximum force which any piece introduced into the design to compensate for the
of equipment is expected to withstand in its material strength reduction resulting from weld-
lifetime. ing temperatures. On the other hand, these joints
Mechanical forces acting on electrical equip- will be of the highest quality from the electrical
ment and support structures are as follows: point of view.
• dead weights from conductor loads and ice
covering,
Tubular sections are usually chosen for rea-
sons of economy, strength and symmetry and the
• wind load, mechanical problems of tubular bus with spans
• short-circuit loading, up to around 20 metres are not difficult to solve
• mechanical operation and .
• forces due to earthquake. Long tubular spans are subject to aeolian
vibrations, although there are various solutions
The worst case for the electrical equipment and
to this problem. One is to lay aluminium cable
support structures arises from a combination of
inside the tubes to damp these vibrations.
these factors. Increasing fault levels in power The bundle conductor arrangement of strung
systems require an accurate understanding of
type busbars constitutes a special calculation
the mechanical forces resulting from short-
and evaluation problem due to the ”snatch”
circuit currents. forces caused by short-circuit currents (parallel
conductors forcibly pulled together by mag-
Bus design
netic attraction cause high axial forces in the
Designing the bus includes consideration of a conductors).
number of factors, the following being the most
On installations with very high voltage, co-
important:
rona rings and large radius bends are used to
• max. load current achieve a low value of electric stress on the
• max. withstand impulse voltage
conductor surface.
• mechanical strength to withstand dynamic
forces
The busbar insulators must be carefully se-
lected to meet electrical requirements, i.e., in-
• atmospheric contamination
sulation level, pollution corona, coefficients
There are two basic kinds of bus arrangement; for temperature and altitude. Mechanical re-
the flexible stranded conductor or strain busbar, quirements are: withstanding short circuits,
and the supported tubular busbar. Each gives seismic and wind forces, normal and composite
the outdoor switchyard a different appearance loads.

82

5.5 82 97-03-05, 13.40


INDUSTRIAL POWER SYSTEM
High voltage switchgear

1. Power transformer Distances between feeders (centre to centre C-C)


2. Circuit breaker and total length for various voltages.
3. Disconnector
4. Current transformer Voltage (kV)C-C (m) L (m)
5. Voltage transformer 52 6,5 21,0
6. Surge arrester 72,5 7,5 21,8
7. Earth switch 145/123 11,0 25,3
8. Post type insulator

Fig. 3. (earlier Fig. 58) Outdoor switchyard for single bus arrangement.
83

5.5 83 97-03-05, 13.40


INDUSTRIAL POWER SYSTEM
High voltage switchgear

Safety clearances Countermeasures against pollution are:


Selection of electrical clearances is fundamen- • increasing creepage distance
tal in AIS design. To ensure reliability and the • applying silicon
washing the insulators
safety of operating personnel, it is essential that
adequate clearance is provided for live parts.
• (encapsulating thegrease to the insulators
pollution)
There are two main aspects here:
Earth grid and safety earthing
1) insulation clearances The purpose of the earth grid is to provide a
2) personnel safety clearances reliable low resistance path for dissipating large
currents to earth from faults on the system or
A high degree of insulation level standardisa- from lightning surges. The lower the resistance
tion has been established, although IEC recom- the better, and the voltage build-up will then be
mendations include alternatives to match es- smaller.
tablished practice in different countries. Com- The earth grid is usually composed of bare
mon practice for voltages up to 300 kV is to use copper conductors laid in the ground at a depth
standard minimum clearances in air, the same of about half a metre. To make the voltage
for phase-to-phase and phase-to-earth. distribution as uniform as possible, the grid
Personnel safety clearances are established should consist of uniform rectangular meshes.
by adding to non-flashover insulation clear- Furthermore, earth rods penetrating a few me-
ances the dimensions of a typified body. tres into the ground are usually connected to the
Space and electrical clearances must also be earth grid, giving dual action between the com-
provided for equipment moving in or out of ponents. The purpose is to limit the step and
position. touch voltages to safe levels during fault condi-
tions. Both resistance to earth and step and
Air pollution touch voltages are dependent on earth resistiv-
In recent years air contamination in switchyards ity. Measurements are recommended to check
has become a growing problem. The contami- the actual soil resistance and potential gradi-
nation is mainly of two kinds, coastal and ents.
industrial. Temporary maintenance earthing in switch-
A dry, clean insulator has the highest voltage yards during work is an important safety proce-
withstand value for outdoor insulation. A clean dure. Higher demands on reliability have led to
insulator in fog conditions has a slightly lower a growing use of permanently installed earth
withstand value, and the dirty-wet combination switches. However, the most frequently used
has the lowest. This dirty-wet condition can, in method is still portable maintenance earthing.
extreme circumstances, be disastrous to the The conductor size for this equipment has in-
power system. creased considerably with increasing earth-fault
The pollution problem is a very complex currents, which has made earthing work strenu-
one, influenced by wind, gravity, electrical ous and time-consuming. Some aids have been
forces acting on particles suspended in the air, introduced, such as suitable lifting tackle and
adhesion, as well as the insulator shape and its shortening of the conductors by placing the
position in service. In addition, rain can coun- earth stud at the top of the equipment stand.
teract or partly rinse the pollution, or at least
wash away the soluble ingredients.
Industrial pollution flashover is a long-time
phenomenon of a thermal nature, evolving GAS INSULATED
slowly as the salts first dissolve, and since dry SWITCHGEAR (GIS)
band formations develop only gradually. Gas insulated switchgear take advantage of the
Flashovers from coastal salt pollution evolve excellent properties of SF6 gas, both as an
more rapidly since the salts are already dis- electric insulation medium, and as arc extin-
solved and the whole surface suddenly starts guishing medium in the circuit-breakers. As a
conducting. result, the designs are compact, with small
requirements on floor or ground area.

84

5.5 84 97-03-05, 13.40


INDUSTRIAL POWER SYSTEM
High voltage switchgear

Pure SF6 gas, as used in GIS equipment, is A 72 kV GIS cubicle concept


nontoxic. Electric arcs in the gas will initiale Using a low differential pressure of only 20 kPa
some chemical reactions in the gas and with makes possible an enclosure design of cubicle
solid matrials, forming a number of decompo- shape, similar to traditional metal-enclosed
sition products. This will occur in circuit-break- medium voltage switchgear. The box shape
ers, and in the extremely unlikely event of also makes it possible to use disconnector and
insulation failures in a GIS compartment. Well earthing switch designs common in medium
established procedures exist to safely handle voltage switchgear. SF6 gas, even at this low
these decomposition products during mainte- pressure, provides the dielectric strength re-
nance and repair work. quired for 72.5 kV with a cubicle size only
SF6 leaking into the atmosphere does not slightly larger than the standard 24 kV air
influence the ozone layer of the earth, and gives insulated cubicle.
minimal greenhouse effect in the concentra- Figs. 4 and 5 show the exterior view and
tions which maf occur. Emission og SF6 to the cross-section through a typical double busbar
atmosphere should, however, be restricted as feeder. The cubicle is sub-divided into the
much as possible. At the end of the lifetime, and following four separate compartments, which
during repair of the GIS, care should be taken to can vary depending on the arrangement:
prevent gas from being released.
Arrangements should be made with either • Circuit-breaker compartment
the manufacturer or specialized contractors to • Feeder equipment compartment
reuse the gas, or to dispose of it in a conrolled • Busbar I compartment
manner. • Busbar II compartment

Fig. 4. Cubicle type 72.5 kV SF6 switchgear for indoor installation.

85

5.5 85 97-03-05, 13.41


INDUSTRIAL POWER SYSTEM
High voltage switchgear

Fig. 5. Cross-section of a 72.5 kV double bus feeder.


1. Voltage transformer 8 Terminal bushing for C.T. and V.T. secondaries
2. V.T. disconnecting device 9 Pressure relief device
3. Cable end unit with deflector funnel
4. Disconnector with earthing switch 10 Gas barrier insulator
5a Busbar system I 11 Circuit-breaker
5b Busbar system II 12 Operating mechanisms
6 Busbar insulator for disconnectors
7 Current transformer 13 C.B. operating mechanism

Two circuit breaker quenching systems are


used:
• the feeder disconnector with its integrated
fast-acting maintenance earth switches
1. The interrupter functions on the compres- • instrument transformers.
sion piston principle, i.e., puffer-type breaker
Each of the separate busbar compartments con-
2. The energy required for interruption of the tains a busbar and associated disconnector. In
short-circuit current is mainly taken from addition to the maintenance earth switch on the
the arc itself, i.e., self-blast breaker circuit breaker side, the disconnector also ac-
commodates a fast-acting earth switch for the
The feeder compartment contains the follow- busbar. The busbars are furthermore fitted with
ing equipment: gas barriers between feeder sections, making
each feeder autonomous.
• cable end unit (or alternatively a terminal
bushing),

86

5.5 86 97-03-05, 13.41


INDUSTRIAL POWER SYSTEM
High voltage switchgear

The individual compartments are gas-tight and The SF6 in the various compartments is main-
segregated from each other. The conductors tained at an absolute pressure of 120 kPa. Be-
pass through gas-tight cast resin barriers. The cause of the cubicle shape, the compartments
walls of the separate compartments are of gas- are not evacuated prior to filling gas, but filled
tight welded sheet steel. as if it was a liquid, exploiting the fact that SF6
Ribs of U-profile steel are welded to the has a specific density of approx. five times that
enclosure walls to give additional mechanical of air.
strength. Each compartment is fitted with a The gas is introduced through a pipe leading
pressure relief valve to relieve excessive to the bottom of the compartment and the air
overpressure in the unlikely event of an internal escapes through a pipe at the top. This method
arc fault. of filling will permit a small amount of air to
The switchgear equipment - disconnectors, mix with the SF6 gas due to a certain amount of
circuit breaker, instrument transformers - is in- turbulence. On the other hand, an SF6/air mix-
stalled through openings in each individual ture with up to 20 % concentration of air exhib-
compartment, closed by special sheet steel cov- its a higher dielectric strength than pure SF6.
ers. These access openings make possible equip- Each individual gas compartment, including
ment inspection and repair or replacement with- those of the circuit breaker interrupters, is moni-
out removal of the enclosure. The access open- tored separately by a density relay. Referred to
ing to the circuit breaker compartment is de- 20oC, an alarm is initiated when the insulating
signed such that the puffer-type circuit breaker, gas pressure drops to 110 kPa.
pivoted at the base plate, can be swung out In the circuit breaker an alarm is initiated
through an arc of 30 degrees, facilitating inspec- when the pressure drops from 700 to 620 kPa,
tion and replacement of interrupter contacts and a second alarm also blocks the circuit
without removing the circuit breaker itself. breaker from operating when the pressure drops
The operating mechanisms of disconnectors to 600 kPa. This is the lowest pressure at which
and earth switches are located in a compart- the name-plate rating of the circuit breaker is
ment at the front of each feeder. The SF6 gas still maintained.
filling points, together with the gas density
relays and supervisory equipment, are also lo- A 145 kV GIS concept
cated in the same compartment. This type of design uses corrosion-proof alu-
Furthermore, control, interlocking, supervi- minium as equipment casing. All three phases
sory and other secondary equipment is accom- are enclosed within the same enclosure, as
modated in the same atmospheric control com- compared to one phase design often used for
partment, fitted with doors with mimic dia- higher voltages. Due to low specific weight,
gram, control switches, semaphores and instru- floor loading is at a minimum, and expensive
ments. foundations are avoided. A double busbar feeder
The complete feeder together with its control bay weighs approx. 3700 kg.
equipment forms a rugged and free-standing The individual equipment modules are con-
shipping unit for mounting on an aligned con- nected such that expansion or modification is
crete foundation. The weight of a fully equipped facilitated at a later date. At the same time, gas
double-busbar feeder is approx. 3000 kg. barrier insulators ensure minimum disturbance
to neighbouring equipment modules.
SF6 gas system True-to-scale plastic models of switchgear
Each feeder is divided into independent gas- modules and equipment simplify application
segregated enclosures. A typical double-busbar engineering. Three-dimensional comparisons
arrangement has four separate gas compart- facilitate the engineering evaluation of alterna-
ments: tive layouts.
When applying a layout of this type of GIS,
• Busbar compartment 1
the same standard electrical arrangements as
• Busbar compartment 2 for conventional AIS installations can be ap-
• Feeder terminating
Circuit breaker compartment
plied. Single and double busbar arrangements -
• compartment
alternatively with transfer bus - as well as bus

87

5.5 87 97-03-05, 13.42


INDUSTRIAL POWER SYSTEM
High voltage switchgear

sections, and bus couplers are realised using Busbar with combined disconnector and earth
standard equipment modules. switch
Similarly, other solutions not so common in The busbar is built from modular bus sections,
Europe, such as duplex, one-and-a-half circuit each 1200 mm long corresponding to the feeder
breaker or ring-bus arrangements can be ac- spacing.
complished. The phase conductors are fixed to the gas
Standardised flange dimensions provide for barrier insulator of each feeder section. Each
flexibility in combining switchgear modules. insulator is combined with a telescopic trans-
Application engineering and planning of an verse assembly cover, which simplifies switch-
installation are thus simplified. gear extension or rearrangement. The spring
loaded flange coupling serves to compensate
forces generated by the internal gas pressure
and axial movement caused by temperature
change.
Split, multifinger tulip contacts connect the
phase conductors at the assembly cover. They
absorb axial movement caused by temperature
change. Mechanical stress on the insulators
from temperature difference between individual
phases and enclosure is thus avoided.
A combination of busbar disconnector and
maintenance earth switch for maintenance, etc.,
is an integral part of each busbar module. The
common operating mechanism for the com-
Fig. 6. Exterior view of a 145 kV SF6 switch- bined disconnector and earth switch is mounted
gear bay. at the front. Depending on the direction of
movement the contacts act either as a discon-
nector or an earth switch.

SF6 gas system


The SF6 gas has a dual function as arc extinction
and insulating medium. Therefore the circuit
current extinguishing chambers are differenti-
ated from the insulating gas compartments of
busbars, disconnectors, load break switches,
etc. The gas compartments are segregated by
gas barrier insulators, and the gas pressure is
monitored by temperature compensated pres-
sure relays.
Fig. 7. Cross-section of double busbar 145 kV During commissioning, each compartment
feeder. receives a final filling of gas, allowing for an
extremely small leakage over a lengthy period
of time.
1 Busbar with combined disconnector/ All gas compartments have their own auto-
earthing switch matic vacuum coupling, so that all maintenance
2 Circuit-breaker jobs, such as gas sampling, conditioning or
3 Current transformer filling up can be carried out during normal
4 Potential transformer operation.
5 Cable end unit with combined
disconnector/earthing switch
6 Fast acting earthing switch
7 Control cubicle

88

5.5 88 97-03-05, 13.43


INDUSTRIAL POWER SYSTEM
High voltage switchgear

145 kV application example


This type of modular switchgear concept lends
itself ideally to the usual switchgear configura-
tions.
A feeder spacing of 1.2 m is typical, and the
required building depth is normally 7 m, the
building height being less than 6 m. Although
installation of a crane is recommended for this
size of switchgear, erection and maintenance
on the factory-assembled feeders and equip-
ment can be performed effectively even with-
out a permanent crane.
Small industrial substations are often of the
single busbar arrangement. A bus section
disconnector or circuit breaker gives opera-
tional flexibility. In this way it is possible to
extend or modify the switchgear with part of the
substation still in service.
A load break switch is recommended for bus
sectionalising, with the distinct advantage of
switching under load. The single busbar layout
closely resembles that of the double busbar
since only the top or bottom busbar is omitted.
If the appropriate connecting flanges have al-
ready been fixed to the circuit breakers in the
initial extension stage, then subsequent up-
grading to a double busbar version is easy to
implement.

89

5.5 89 97-03-05, 13.43


INDUSTRIAL POWER SYSTEM
Fault Control

FAULT CONTROL

Contents
page
1 Protectiv relayng and Co-ordination 90
2 Motor protection 91
3 Transformer protection overview 94
4 Generator protection 96
5 Selectivity in industrial power systems 99

Protectiv relayng and


Co-ordination
Introduction
Although ”Fault Control” may sound like a new tions. The high costs of power distribution equip-
expression to some, the protective relaying and ment and the time required to repair or replace
co-ordination in a power system is indeed a ”con- damaged equipment such as motors, transform-
trol” system with an inherent intelligence which ers, cable, high voltage circuit breakers, etc.,
senses faults and abnormal conditions, makes make relay protection design a very important
decisions and carries out remedial action to iso- consideration.
late as small a part of the system as possible The losses associated with an electrical power
(selectivity). Today this type of ”control” interruption due to equipment or system failures
is more and more being entrusted to micro- vary widely with different types of industries.
processors. For example, a service interruption in a machin-
Industrial plants vary greatly in the complex- ing operation means loss of production, loss of
ity of their power distribution systems. A small tooling, and loss from damaged products. Like-
plant may have a simple radial design with low wise, an interruption in a chemical plant can
voltage fuse protection only, whereas a major cause loss of product and create major clean-up
industrial process complex may incorporate an and restart problems. To avoid a disorderly shut-
intricate network of high, medium and low volt- down which can be both hazardous and costly,
age substations, uninterruptible power sources, it may be necessary to tolerate a short-time over-
and co-generation required to operate in parallel load condition and the associated reduction in
with and/or isolated from local power company life expectancy of the affected electrical appara-
networks. At an early design stage, the electrical tus. Other industries such as oil refineries, paper
engineering project team will meet with local mills, automotive plants, offshore oil and gas
power company staff to review and resolve the plants, textile mills, steel mills, and food process-
common protection requirements. ing plants are similarly affected, and losses can
The need for increased production from and represent substantial expenses.
availability of xindustrial plants has created de- For some types of processes, even a momen-
mands for greater industrial power system reli- tary voltage dip can shut down the entire plant.
ability. Meshed networks and parallel operation Thus the nature of the industrial operation will
with power companies have produced extremely determine the degree of protection which can
high short-circuit capacities during fault condi- be justified.

90

5.6 90 97-03-05, 13.43


INDUSTRIAL POWER SYSTEM
Fault Control

MOTOR PROTECTION cable, and associated switchgear or controlgear.


This excessive load may be a gradual increase
General aspects
from overloading, voltage drop, faulty bear-
The mandatory electrical safety regulations in
ings, or other reasons. In any case, it is a slowly
any country usually offer minimum motor pro-
built up type of overcurrent, whereas the short
tection. Therefore, a number of additional con-
circuit is a sudden burst of current. Protection
siderations have to be evaluated. The equip-
of both types must be considered.
ment being driven by the motor must be taken
into account as well as whether running the
motor to destruction is preferable to “instant” SMALL THREE-PHASE ASYNCHRO-
shutdown. Further, the anticipated areas of fail- NOUS MOTORS (MAX. 200 kW)
ure, such as bearing failure, winding failure, Three-phase induction motors stand for the bulk
ventilation failure, phase reversal, winding turn of application work in an industrial plant. Up to
failure, vibration, field failure, etc., must be 200 kW, all motors are normally low voltage.
considered. Last, but not least, comes the cost Usually protection complying with local wiring
of the protection itself. The totality of all this is regulations is adequate, unless special high-
to provide “optimum” protection, which means inertia loads exist. The setting of the motor
that total costs of shutdown, loss of production, circuit overcurrent device is primarily to protect
repair, reinstallation and recommissioning is the cable and starter from short-circuit stresses
weighed against the costs for varying degrees and temperatures.
of protection. The motor running overload protection is
These decisions will all be different, de- usually provided by three thermal heaters lo-
pending on who decides what. The chemical cated in the motor starter. These are fixed-rated
engineer may decide that the process could units, and the correct one should be installed
become unstable and that the motor should be with the starter to meet the allowed overcurrent.
run to destruction. An accountant might think This is listed in most mandatory electrical safety
that extra money is good insurance if it shortens regulations, but 115% is a generally acceptable
downtime. A few extra seconds running time value. Allowances should be made for motors
may provide valuable purging time for gas with switched capacitors.
process systems where contamination of gas In dual-speed motors the windings provide
without the purging could involve costs, repre- two different power outputs. Therefore, two
senting money which could have purchased different sizes of thermal overloads are re-
many replacement motors. What all this means quired, each set of windings being considered
is that there are no easy answers. However, separately.
some specific advice is presented in the follow-
ing sections. LARGE THREE-PHASE MOTORS
Synchronous motors resemble generators, (ABOVE 300 kW)
and therefore some generator protection Three-phase motors above 300 kW are nor-
schemes may also be used for synchronous mally medium voltage, that is 3 to 11 kV. This
motors. makes everything, including the motor, more
expensive than the equivalent at low voltage.
TWO TYPES OF OVERCURRENT Each medium voltage motor is considered as an
PROTECTION individual unit with its own specific application
Whether at low or medium voltage, a motor problems and cost.
circuit is supplied either via a circuit breaker or First, it has to be established whether the
a fused contactor. This is the “last” overcurrent motor is essential or non-essential to the proc-
device in a series of overcurrent devices. There ess. If it is essential, then the basic short-circuit
are two types of protection required for a motor protection will be installed and all other over-
circuit. First of all, the motor and feeder cables load devices will actuate alarms rather than
are protected against a short circuit by the initiate shutdown. This will allow the operator
circuit breaker or fuses. Secondly, protection is time to reduce overload conditions or start a
required to prevent an increase in load causing shutdown procedure before closing down the
excessive current and heating in the motor, motor.

91

5.6 91 97-03-05, 13.43


INDUSTRIAL POWER SYSTEM
Fault Control

f the motor is non-essential, the overload and setting to prevent operation due to the starting
other protective devices will be set to shut the current.
motor down as fast as possible.
Large motors vary in size, cost and charac- Stator overheating
teristics. The following is therefore a typical For large motors stator overheating is much
menu of protection schemes. more serious than for smaller motors. Apart
from insulation damage, stator overheating can
Short circuit protection cause frame distortion and, in some cases, bear-
This protection applies to the feeder cable, the ing damage. In small motors a bimetallic heater
stator winding and the motor starter itself (cir- or electronic replica type relay monitors
cuit breaker or fused contactor). One protective overcurrent and thus estimates temperature as a
device for each phase is required. Where a consequence of this current. In large motors
circuit breaker is used, mandatory electrical RTDs (resistance-temperature detectors) are
safety regulations usually permit sensing the installed together with the winding in the slot to
fault by integral or external sensing elements detect actual hot-spot temperatures. Manda-
which disconnect all phase conductors simulta- tory electrical safety regulations allow this
neously. Where fuses are used, obviously a method of overload protection. The RTDs op-
single fuse could open, leaving the other two erate a temperature relay which first gives an
intact. This would cause the motor to keep alarm and then trips the circuit breaker when a
running, but at a reduced output, eventually certain temperature is reached; consequently,
leading to overheating and overloading. Dis- no other protection is required except for short-
connecting the motor in time to prevent damage circuit protection. However, in some process
depends on the setting of the overload trips. The industries the RTDs are wired to the process
limiting factor for overload heating is some- control, giving central control room operators
times the stator and at other times the rotor. temperature information instead of providing a
A more serious single-phase condition will protection function which trips the motor.
exist if an earth fault on a single phase of a Further protection may be provided with
primary feeder to a star-delta transformer blows current-balance relays, which are essentially
the fuse, leaving only two phases feeding the protection for single-phase conditions. This
transformer. This means that the three-phase can also include a phase sequence combination
secondary side will be essentially single-phased if desired.
with currents in each motor branch circuit of For large motors (≥1500 kW) the overload
115, 115, and 230%, respectively, for the three protection is a choice between the inverse-time
phases. This means that every motor connected overcurrent relay and the thermal or electronic
to such a transformer would run the risk of replica (motor heating curve) relay.
being overheated and seriously damaged. The thermal replica type relay tries to imitate
the motor heating curve. At light loads and long
Phase fault protection time overload it gives best performance. At
Phase fault protection can be provided by cur- heavy overloads it tends to be slow. The inverse
rent-limiting fuses specially designed for mo- overcurrent relay works just the opposite, giv-
tor protection. Alternately, instantaneous ing the best protection at heavy loads while
overcurrent relays can be used with settings remaining unsure and therefore not very sensi-
higher than the starting current and feedback tive at light loads. A combination of both gives
current in case of external faults. Instantaneous the best protection, but RTDs should always be
overcurrent devices affected by the DC compo- included for large motors. Both the replica and
nent of the current must be set well above the the inverse overcurrent relays can be equipped
symmetrical value of the starting and fault with instantaneous trips for short-circuit pro-
feedback currents. Modern electronic relays tection. Modern static or microprocessor type
have an instantaneous overcurrent function replica relays are much more versatile and may
which is practically unaffected by the DC com- be set to imitate the motor heating and cooling
ponent of the current. Another alternative is to curves much more closely than earlier thermal
use an inverse time overcurrent relay with a or electromechanical relays. These newer ver-

92

5.6 92 97-03-05, 13.43


INDUSTRIAL POWER SYSTEM
Fault Control

sions depend on motor thermal time constants The rate of decrease (decrement) of the DC
which are sometimes difficult to obtain from component is a function of the X/R ratio of the
the motor manufacturers where international circuit and will probably not be fully asym-
standards for specification of such time con- metrical. Therefore, the setting of the instanta-
stants is still lacking. neous devices should be around 12 to 15 times
rated full load current.
Rotor overheating The setting of the time delay devices is based
In squirrel-cage motor rotors it is not economi- on normal symmetrical starting currents.
cally possible to install detector devices. The Acceleration and deceleration time
methods used for stator overheating detection The motor accelerating time depends on the
will in most cases reflect general overload inertia Wk2 of the motor and the load. This must
conditions, but in the event of locked rotor and be taken into consideration when setting in-
attempted single-phase starting, the current sens- verse time overcurrent relays and replica type
ing thermal devices should be used rather than thermal time constant relays. A motor usually
RTDs. The time lag associated with stator RTDs has a guarantee from the manufacturer of, say,
during starting may not reflect the rotor heating ”3 starts from cold” and ”2 starts from running
at all. As rotor heating on subsequent starts can hot condition”. A motor with water cooling
damage the rotor without the stator current or may have as many as three different time con-
temperature giving a true reflection of the con- stants for heating up when starting, and cooling
dition, it is extremely important to agree with down when cruising down or standing still; one
the manufacturer on the rotor protection if it is time constant for the copper winding, one time
”rotor-limited”. Particularly during the com- constant when iron is counted in and one more
missioning phase, motors are often subject to when the body of the cooling water is included.
excessive starting stresses. See also ”Acceler- If the cooling water pump is still running after
ating time” below. standstill, this will also affect the cooling curve
In synchronous motors a field current is without the replica relay ”knowing” it.
supplied to the rotor, and a connection thus Calculation of the accelerating time is fairly
exists to monitor what is going on in the rotor. simple, providing the loads are known; alter-
By using a replica thermal relay in the field nately, the motor manufacturer can be con-
current, protection can be provided if the motor tacted to obtain acceleration times. However,
fails to start. A further protection is provided by protecting the motor from being ”started to
an out of step device, which will shut down the death”, or preventing shutdown due to spurious
motor for an out-of-step condition (where the trips from a thermal relay that is too conserva-
motor is out of synchronism with the network). tively set or selected, requires a considerable
amount of attention.
Starting current considerations
The symmetrical value of the motor starting Feedback of fault current into the power
current can be anywhere between 3 to 9 times system
rated current. The asymmetrical (offset) cur- During a fault, all motors will supply current
rent can vary between 6 to 16 times, or approxi- into the fault. The amount of feedback is an
mately I.8 of the symmetrical value. The asym- inverse function of the subtransient reactance
metrical current with its DC component is high- (X”d) which is around 15 to 25% for induction
est during the first cycle and then gradually motors, 10 to 25% for high-speed synchronous
decays. The rate of decay (decrement) of the motors, and 25 to 45% for low-speed synchro-
DC component is a function of the ratio X/R of nous motors. During the few cycles while the
the circuit subtransient reactance is in effect, the sym-
Since the asymmetrical current with its DC metrical value of the feedback currents can be
component is highest in the first cycle and then around 4-7 times the full-load current for in-
gradually decays, the instantaneous part of the duction motors, 4-10 times for high-speed syn-
relay will react to the DC component, while the chronous motors, and 2-4 times for low-speed
inertia in an induction relay or thermal element synchronous motors. The setting of the instan-
will only recognise the symmetrical current. taneous overcurrent relay must consider the

93

5.6 93 97-03-05, 13.44


INDUSTRIAL POWER SYSTEM
Fault Control

sensitivity of the relay to the DC component of The alarm option is usually better for continu-
the feedback fault current. ous process plants. If the voltage drops to a
level where contactors are dropping out, then a
Phase-to-earth fault protection major plant problem exists anyway.
The most common type of electrical fault in the
stator circuit is the phase-to-earth fault. In sol- Differential relays
idly earthed or low impedance earthed systems Phase-to-phase short circuits in a motor seldom
an earth fault will result in heavy damage to the occur, but if they do, they generally involve
stator iron. Therefore the best protection (in large currents and can cause severe motor dam-
addition to fast relaying) is a high impedance age. Phase overcurrent relays must have high
system earthing method which will reduce the settings or long time delays to override starting
earth fault current to a no-damage value. A or fault feed-back currents. For motors above,
simple method of detecting phase-to-earth faults say, 500 kW, a differential relay is a sensible
is installing all three phase conductors through consideration. For each phase the differential
a ”window” type current transformer. Normal relay compares the currents on the line side
load currents are self-cancelling due to 120 with the neutral side. In solidly earthed or low
degree phase shift; however, during an earth impedance earthed networks, the differential
fault, zero-sequence currents will flow. These relay also operates for phase-to-phase faults.
are all in phase and therefore combine with
together, producing an output from the current Bearing temperature protection
transformer which is connected to an instanta- Some motors are equipped with bearings that
neous overcurrent relay. It offers sensitive pro- are force-lubricated by a lubrication pump. A
tection and eliminates false tripping due to failure could occur in the oil line rather than in
starting and high inrush currents. the pump motor. Therefore, the only way of
An alternate method is a residual connection preventing overheating or detecting a fault in
with a time overcurrent relay in the neutral of the lube oil system is by installing an RTD in
star-connected current transformers. This uses the bearing and running the conductors back to
a relay with a setting of not more than 10% of a dial thermometer with adjustable trip switch.
the maximum earth fault current. If the maxi- This switch can operate an alarm or shut down
mum earth fault current is more than four times the motor when a certain temperature is reached.
the motor rated current, an additional instanta- An option is the use of a sensor connected to
neous trip could be included with a setting of 3 a relay located at the motor. However , this
to 10 times the rated motor current, depending means running control wires and power to the
on inrush and feedback criteria. motor, which could represent an obstacle, ne-
cessitating an explosion-proof enclosure for
Undervoltage protection the relay if it is in a hazardous area.
Undervoltage protection in a large motor is a
standard consideration. The torque of asyn-
chronous motors is reduced by the square of the TRANSFORMER PROTECTION
voltage, and by the time contactors drop out at OVERVIEW
about 65-70% voltage, motor available torque
In selecting the right transformer protection
is reduced to about 40%. If the voltage is
one must first consider the transformer’s role in
reduced during starting in a direct-on-line ap-
plication, the rotor could overheat faster than the power system:
the stator. Depending on the motor design and 1. The size and importance of the transformer.
winding connection of the motor, the stator Two possibilities:
could also overheat first.
The undervoltage relay or trip device can
• It is an expensive and important part of the
ystem. A transformer failure would result in
also have time-delay functions for transient or loss of production. A spare is not available.
voltage dip override. The connection can be
made as an alarm only, or it can automatically
• It is of moderate size or importance. There is
an alternative supply or a spare transformer
disconnect the motor from the line. available.

94

5.6 94 97-03-05, 13.44


INDUSTRIAL POWER SYSTEM
Fault Control

2. The type of transformer insulation: oil or dry device for the tap-changer compartment. Se-
insulated lective earth fault protection is normally pro-
3. The voltage level and the type of system vided for the primary side and selective or
earthing on the primary and secondary side. differential earth fault protection for the sec-
In some cases even a tertiary winding earth- ondary side.
ing has to be considered. Delayed overvoltage protection is provided
for transformers with a risk of elevated voltage,
Transformer protective relaying is first of all which can cause core magnetic saturation and
provided to limit the consequences of faults and overheating damage if permitted to last.
failures such as a short circuit inside the trans-
former and in the connecting leads. Such faults GAS DETECTION OR BUCHHOLZ
are very rare, but if such a failure should occur, RELAY
it may develop very fast, such that the protec- This type of protection is used with oil-insu-
tion cannot save the transformer from perma- lated transformers with conservator for oil ex-
nent damage. Fast disconnection will, how- pansion. The gas relay is installed in the con-
ever, limit the results preventing a devastating necting pipe between the tank and the conser-
fire or explosion. vator. A slow accumulation of gas in the oil will
Some kind of short-circuit back-up protec- rise through the connecting pipe to the detector
tion is generally provided further out in the relay, and a float will actuate an electrical
supplying network. contact to operate an alarm.
In an isolated neutral system or with high The gas can be released and tested. Flamma-
impedance earthing the earth fault current will ble gas is a serious sign of oil or paper decom-
be small, and therefore sensitivity and selectiv- position, while ordinary air is less alarming.
ity are more important than high speed clear- For a serious internal fault involving arcing
ing. there will be a sudden pressure rise and a surge
Another internal transformer failure is a bro- of oil and gas which will be detected by the
ken circuit or a bad conductor joint, which can Buchholz surge detector. It is a fast and effi-
cause gas build-up or localised overheating cient detector which trips the transformer cir-
with the risk of explosion. cuit breaker instantaneously.
A transformer should also be protected against Transformers with a nitrogen cushion in-
inadvertent overload and high temperatures in stead of conservator are common in North
the winding insulation. America and can be fitted with a sudden pres-
sure relay instead of the Buchholz type.
Below 1000 kVA, transformer protection is
generally provided by primary fuses as short- WINDING TEMPERATURE
circuit protection and overload and earth fault PROTECTION
relays as stipulated in most national wiring This device is more of an overload sensor rather
regulations and electric safety codes. than a fault detector. It measures top oil tem-
perature, but has a compensating device which
Oil-insulated transformers above 1000 kVA reflects the hot-spot temperature rather than the
generally require gas detector devices, usually oil temperature. This also means that the tem-
referred to as Buchholz relays, having two perature-rise curve is closely followed by the
levels of gas detection: gas warning and surge device. It can be made to operate an alarm or a
tripping. Depending on size and voltage, cooling device. This fairly inexpensive protec-
overcurrent relays or fuses provide additional tion pays for itself by allowing operation up to
short-circuit protection. full thermal capacity.

Larger transformers have further protective TRANSFORMER DIFFERENTIAL


arrangements such as redundant or duplicated RELAY
short-circuit protection, underimpedance and This relay operates instantaneously for faults in
differential protection. In the case of on-load the zone between the two sets of current trans-
tap-changers, there may be an overpressure formers (for a two-winding power transformer).

95

5.6 95 97-03-05, 13.44


INDUSTRIAL POWER SYSTEM
Fault Control

In order to be stable for external faults and manufacturer’s recommendations. Therefore,


unsymmetrical events like inrush current dur- it becomes a matter of understanding what the
ing energising, the relay uses a current stabi- generator manufacturer recommends, rather
liser. Harmonic restraint by second and higher than simply making one’s own selection. The
harmonics is often used. following gives an overview of the basic areas
There is also a need to compensate for possi- of generator protection.
ble current transformer differences and for the
phase shift in the transformer to obtain current STATOR WINDING PROTECTION
balance for load and external fault currents. If a fault occurs within the stator winding,
This may be solved by interposing current opening of the main circuit breaker only re-
transformers or adjusted for internally in the moves the fault current supplied from the net-
relay. work. The fault still exists within the generator
and current continues to flow into it. As long as
SPECIAL EARTH FAULT the field is energised, the generator is produc-
PROTECTION ing an e.m.f. (electromotive force) which main-
According to local preferences and practice the tains the fault current. If the field supply is
following types of earth fault protection may be removed, then the time to decay the flux will
used: dictate the current reduction in the fault. This is
A restricted earth fault relay is an instantane- a problem related to winding protection.
ous differential earth fault relay, useful in sol-
idly earthed neutral systems where an earth Phase-to-phase fault
fault will represent a high and destructive cur- This fault requires fast detection and instant
rent. shutdown. Even with the generator breaker
A so-called ”tank protection” is similarly (in opened, the generator will still attempt to feed
a solid neutral earthing system) a current relay the fault if the field is still connected or the
connected to a current transformer between the magnetic flux is still decaying. Relaying must
transformer tank and earth. therefore detect the fault, disconnect the load,
open the field breaker and shut down the prime
mover.
Phase overcurrent or impedance relays must
GENERATOR PROTECTION have a setting above the maximum load current,
OVERVIEW as well as a time setting which gives selectivity
A generator is probably the most important for external faults. Consequently, this relay
item in an industrial electrical power system, does not provide an adequate first line of de-
being either a co-generator running in parallel fence for internal phase faults, only as back-up
with the power company, a standby unit or an protection. Instead, a sensitive differential re-
emergency generating set. Without it the rest of lay is applied, except for very small generators.
the system may be useless, or in great trouble.
Therefore, the reliability and protection of gen- Turn-to-turn fault
erators are of paramount importance. A short This is a short circuit between two coil turns in
repair time is also essential, and this means that one of the phases. This type of fault is not
fast shutdown is required, as well as early detected by phase overcurrent or generator dif-
indication of an impending fault. ferential relays. For generators with split neutrals
The economic justification for maximum the interturn protection consists of a time-lag
possible protection must be weighed against low-set overcurrent relay sensing the current in
the effect on the system of generator shutdown. the connection between the stator neutrals. The
If the fault involves iron damage or requires time delay is short, as the interturn fault current
hard-to-get replacement parts in remote areas, can be high, but must also prevent operation
then the maximum protection may still be rela- due to external fault currents being unbalanced.
tively inexpensive. One method is to use a low-burden ”very in-
The IPS designer will rarely be called upon verse” overcurrent relay with specially designed
to apply protection for generators without the split-phase current transformers.

96

5.6 96 97-03-05, 13.44


INDUSTRIAL POWER SYSTEM
Fault Control

Phase-to-earth fault large unbalance would occur in the magnetic


Neutral earthing and stator earth faults flux. Because of the small air gap in some high-
The phase-to-earth high current fault is the speed turbogenerators with long shafts, distor-
most serious of the stator winding faults be- tion could cause the rotor to rub on the stator,
cause of possible damage to the stator lami- resulting in major damage.
nated steel core. Most generators are Y-con- Again, this problem and the selection of
nected with an earthed neutral. The neutral may appropriate relaying should be co-ordinated
be solidly or impedance-earthed, often resist- with the generator manufacturer.
ance earthed on low voltages 500-690 V or on
medium voltage 3-11 kV generators. Where the GENERATOR MOTORING
earthing is done through low resistance (or When a generator prime mover cannot supply
direct neutral earthing), then a high fault cur- sufficient power to its own losses, then the
rent exists and differential relaying can be used, electric power system will supply energy to the
protecting about 80% of the winding. High prime mover via the generator. This is known
resistance earthing reducing fault currents to as ”motoring”.
some 5-10 A, would preclude differential re- A reverse-power relay can protect against
laying, but also reduces the danger of iron motoring. It can be designed for sensitive op-
damage. In this case a separate earth fault relay eration and will detect reverse power down to
must be considered. about 0.5%. A timer in the relay eliminates
When high-resistance earthing is used, then spurious tripping due to transient surges, which
a current relay may have trouble distinguishing usually occur during synchronising and switch-
between third-harmonic currents and fault cur- ing operations.
rents. The losses and motoring power for prime
movers vary within a wide range for gas tur-
One alternative method of generator earthing bines, diesel units and steam turbines.
(instead of connecting the 5-10 A resistor di-
rectly between the star point and earth) is to NEGATIVE PHASE-SEQUENCE
insert a small distribution transformer in the PROTECTION
neutral with a resistor connected across the ”Negative sequence” is a term used in sym-
secondary. In both cases a voltage relay with metrical-component analysis. It is, in effect, a
third harmonic filter - measuring the voltage three-phase system of vectors but rotating in
across the resistor - will provide reliable stator the opposite direction to the normal “positive
earth fault protection. sequence.” The generator produces positive
If the resistor is selected to limit the earth sequence currents of 50 or 60 Hz. A phase-to-
current to 10 A, the damage to the iron will be phase fault or unbalanced loading of the phases
limited and therefore high speed is not as essen- would produce negative sequence currents. This
tial as if the neutral was solidly earthed. Even negative sequence current produces an addi-
so, it is good practice to have the generator shut tional ampere-turn wave which rotates back-
down as fast as possible on earth faults, taking wards. This means that it rotates relative to the
into consideration the option of the relay in- rotor at twice synchronous speed, producing
stead sounding an alarm in the case of a standby double frequency eddy currents in the rotor
or emergency generator. causing excessive heating in the rotor surface,
but also in the potential damper winding.
FIELD EARTH FAULTS Phase-to-phase faults only allow a few sec-
The generator field is DC and is normally onds before damage can occur. Since the nega-
unearthed. Therefore, if one earth fault occurs, tive sequence currents decrease with distance,
nothing much will happen. If a second earth they are greatest at the fault location and de-
fault occurs, part of the field winding will be crease approaching the generator. This means
short-circuited. The field magnetic flux be- that the closer the fault is to the generator, the
comes unbalanced. If the short circuit occurred less time is available for clearing it. Phase-to-
in close proximity, the unbalance could be phase faults should be cleared in less than 5
minimal. If it occurred at two extreme points, a seconds.

97

5.6 97 97-03-05, 13.45


INDUSTRIAL POWER SYSTEM
Fault Control

GENERATOR OVERVOLTAGE types rather than anti-friction bearings. As such


Overvoltage at the generator output can be the bearing metal is subject to “flow” at high
produced by overspeed or by a faulty voltage temperatures.
regulator. Both problems are serious enough to Various methods are available to measure
warrant instant shutdown. Therefore, the relay- these temperatures, such as contact-making ther-
ing should ignore transients, accept some volt- mometers, bulb-type thermometers, RTDs (re-
age rise within limits, and shut down instantly sistance temperature detectors), and thermo-
on large increases. A straight overvoltage relay couples.
will provide protection against overspeed due All these options are acceptable, but low-
to a faulty governor on the prime mover, or a mass items such as RTDs and thermocouples
faulty voltage regulator. The time-delay setting should be protected from cold and incorrect
should be around 10% above normal, while the locations which could affect their reading.
instantaneous setting should be slightly above
the expected transient voltage increase due to VIBRATION
load dumping and prior to the regulator correct- Vibration can be caused by electrical as well as
ing the voltage. mechanical faults. Therefore, vibration can also
be a “back-up” indication of an electrical fail-
FIELD WINDING OVERVOLTAGE ure causing unbalanced magnetic forces. The
Overvoltage protection of the field winding is vibration due to the stator becoming “egg-
usual on self-excited, slow-running hydro gen- shaped,” or asymmetrical, is caused by unbal-
erators, which are mostly power company type anced magnetic forces. Loss of dynamic bal-
installations. Therefore, the average industrial ance of the rotor can produce vibration along
power system designer will not encounter this with other possible mechanical faults.
problem. Where the generator unit is a high-speed tur-
LOSS OF EXCITATION bine, vibration recorders with alarm contacts
Loss of excitation will cause the generator to can be used. For other low-speed types of prime
operate as an induction generator. In order to do movers, vibration protection is not usually pro-
this, it must lose synchronism. This can cause vided.
oscillating and temporary instability. There is
time to sound an alarm and allow reapplication OTHER TYPES OF PROTECTION
of the field, providing the system stability is not Cooling water for bearings can sometimes leak
affected and the time to correct the problem did into the bearing oil. An oil level indicator can
not exceed a few seconds, or come up to half a give an alarm if the level suddenly increases.
minute. Creep indicators are limited to the hydro-type
Normally, installing a timer will provide an generators and are used to prevent bearing
alarm to give the operator the chance of correc- damage. A certain speed is required before a
tive action. After this, the unit automatically film of oil covers the bearing. If the generator is
shuts down. allowed to slowly “creep,” bearing damage
The loss of excitation results in numerous could occur due to lack of an oil film. This creep
changes to reactive power, power factor, sys- indicator allows the operator to see if the gen-
tem stability, and real power output, and the erator rotor has actually stopped rotating.
protection can be accomplished by a direc- Potential transformer fuse protection will act
tional distance relay operating from alternating when fuses blow due to ageing and transient
current and potential transformers at the gen- overvoltages.
erator. The relay is a field-loss relay and inevi-
tably a discussion of field loss will involve the EMERGENCY GENERATOR
generator manufacturer, who will also have his PROTECTION
own recommendations, purely as self-defence Emergency or essential generators are usually
against warranty claims. smaller diesel or combustion engine driven
units and may have survival value for many
BEARING TEMPERATURE people (say on an offshore oil or gas platform).
Bearings in large generators are usually sleeve Such generators are started and load-tested

98

5.6 98 97-03-05, 13.45


INDUSTRIAL POWER SYSTEM
Fault Control

fairly regularly, mostly every week, and run for Low voltage cable feeders are protected by fuse
a couple of hours. It is important to recognise and switch combinations, or by moulded case
that the protection requirements during test are circuit breakers (MCCBs) providing short-cir-
quite different from a situation where the gen- cuit and earth fault trips.
erator is called upon in an emergency. Hence it
may be correct to equip the generator with a Overhead line circuits
fairly comprehensive set of protective relays Overhead lines are normally not part of indus-
which are active only during testing, whereas trial complexes, but where distances are cable-
many of these are blocked off with only short- prohibitive, medium or high voltage lines may
circuit protection active during an emergency. be the solution. Lines are protected by circuit
Most important for a small generator is to have breakers with phase short-circuit and earth fault
sufficient short-circuit capacity to operate se- protective relays. When distance protection is
lectively all connected fuses and circuit break- used, it is provided in conjunction with
ers in an emergency. Otherwise, the unit could overcurrent and earth fault protection, the latter
simply shut down due to an uncleared remote serving as back-up protection.
system fault. (Faults are very likely to happen Three-phase auto-reclosing schemes may be
in a catastrophic situation where fire or explo- considered if the geographical location and
sions can occur, but these should not affect the lightning incidence require this.
operation of the emergency power supply.)

Capacitor banks SELECTIVITY IN INDUSTRIAL


High voltage capacitor banks normally have POWER SYSTEMS
their capacitor units individually fused. Large The following is a short description of what a
capacitor banks exceeding 1 MVAr are usually selectivity analysis is, and a set of rules to use
connected in double star. A current relay with in a relay co-ordination study. This guide is also
third harmonic filter connected to a current a check-list for use when auditing selectivity
transformer in the interconnection between the work done by others, performed by hand or by
two neutrals can be used to trip the bank before computer.
fuses disconnect too many individual units. Selectivity means that series-connected
The unbalance protection can also be a volt- overcurrent protection should operate success-
age relay set to operate when the neutral voltage fully during short-circuit and earth faults and
of the capacitor bank exceeds a certain value. isolate as small a part of the system as possible.
Individual capacitors may be switched by con- The rest of the power system should remain
tactors, circuit breakers or, for low voltage operative. In British terminology “Discrimina-
applications, by fused switches. They have to tion” is sometimes used instead of Selectivity.
be rated for at least 1.5 times capacitor rated In U.S. terminology “Coordination of
current, and must withstand transient inrush overcurrent devices” or “Relay coordination”
currents up to 100 times rated current. is also used.
Capacitor bank feeders are normally pro-
tected by fused contactors or switches. In the SETTING THE SELECTIVITY STAGE
case of circuit breakers, phase fault and earth A preliminary selectivity study is often carried
fault protection are provided. out early in the power system planning. This is
followed up during subsequent stages of design
Cable feeders and operation. The analysis consists of drawing
Plain cable feeders for high voltage distribution time-current curves on log-log paper, either by
are protected by phase short-circuit and earth hand or computer, in order to establish type and
fault protective relays. settings of overcurrent protective devices. The
Differential protection is provided on all selectivity study also includes calculating and
high voltage feeders which can be operated in determining how the devices will operate on
parallel, or where instantaneous fault clearance available short-circuit currents, as well as giv-
is required. ing a graphical presentation of the degree of
protection provided.

99

5.6 99 97-03-05, 13.45


INDUSTRIAL POWER SYSTEM
Fault Control

Further, let-through energy (I2t) during the paper, but new computer-aided design simpli-
first half cycle of the short circuit must be fies this process. This preliminary analysis is
considered for current-limiting fuses and cir- normally part of the conceptual study, and the
cuit breakers. short-circuit and fault protection philosophy at
Characteristic operating curves of overcurrent this stage is reviewed together with network
devices are usually published by manufacturers layout and reliability of supply required by the
on log-log paper with time as ordinate and industrial process. An offshore or remote area
current as abscissa. To be useful in selectivity plant may have a much higher priority for
work, such diagrams should contain full infor- protection compared with selectivity. This is
mation on all time and current tolerances and due to the time and expense of bringing in new
ranges of adjustment and settings. There is at equipment if it is damaged, as compared with
present no international standard stating how an industrial plant where transport and access
such data should be presented, and therefore are easy. In addition, a purely radial network is
such diagrams vary considerably.. This is one easy to make selective, whereas a complicated
of the major challenges for anyone engaged in interconnected network may be difficult to co-
selectivity work. ordinate using ordinary overcurrent devices.
The time-current characteristics for electro-
mechanical, thermal or electronic overcurrent DETAILED SELECTIVITY STUDY FOR
releases are usually published in the U.S.A./ A NEW PLANT.
Canada as operating bands including all toler- When all protective devices have been chosen
ances. In Europe, these characteristics are often and time-current characteristics have been de-
published as lines with tolerances given in per termined, a detailed selectivity plan is estab-
cent. lished. The detailed selectivity plan is the basis
The term ”primary relay” is often used for a for setting of relays and overcurrent releases
direct-acting trip device directly mounted on a during commissioning. Commissioning also
low voltage circuit breaker. A ”secondary re- includes calibration and testing of characteris-
lay” is energised by the current or voltage tics as part of the hardware quality control.
derived from an instrument transformer and is These checks and calibrations may also take
installed separately from the CB and consid- place as part of QA witnessing at the manufac-
ered as a ”switchgear relay” or simply ”relay”. turer’s premises.
It is important to realise the difference between
these terms, as these devices are all part of the SELECTIVITY FOR EXISTING
selectivity analysis and co-ordinated with each PLANTS
other at different voltage levels. The selectivity plan for a new plant is an effec-
Inverse or constant time/current relays used tive diagnostic tool for operating personnel when
for overload or short-circuit protection, may be troubleshooting after faults and unscheduled
directional or with voltage restraint. When a outages. The graphical representation on time-
”primary relay” is found to be insufficient for a current charts is the key to understanding the
low voltage circuit breaker, separate ”second- built-in intelligence in the protection during
ary” relays may be added. An example: genera- overload or fault conditions. The familiarity of
tor circuit breakers in low voltage installations. operating personnel with the selectivity plan is
of vital importance to the safety of both people
PRELIMINARY SELECTIVITY STUDY and plant.
FOR A NEW PLANT. It therefore becomes essential to update the
In order to select correct protection which may selectivity plan at regular intervals or whenever
later be co-ordinated, an early selectivity evalu- changes to the electrical system take place. In
ation is necessary. This evaluation is based on older plants so many changes may have occurred
practical experience of how protective devices that a new selectivity study must be carried out.
best fit together, and at the same time give good This usually falls within the responsibility of
protection. preventive maintenance and is often combined
Such an evaluation may be difficult without with other switchgear service during the yearly
the drawing of time-current curves on log-log audit and shutdown in process plants.

100

5.6 100 97-03-05, 13.45


INDUSTRIAL POWER SYSTEM
Fault Control

A TYPICAL SELECTIVITY REPORT


A selectivity report may typically contain the
• When the system neutrals are earthed via
impedances, the selectivity of earth fault
following sections: devices is shown on separate earth fault
charts. Each voltage level is considered a
1. Scope of work. Describing the extent of, and separate circuit.
criteria for, the analysis.
2. Single-line diagram. Overall diagram for the
WRITTEN COMMENTS (see under Item
whole plant 7 above)
3. General criteria for settings and margins
Each time-current chart is accompanied by
4. Short-circuit calculations
separate written comments including:
5. Time-current charts.
6. Tables of device settings • Explanation of each setting chosen (which is
not covered by some general criteria). It is
7. Comments on the time-current charts
important for future revisions and changes
8. Summary and conclusions to know what were the original reasons for
selecting the settings.
TIME-CURRENT CHARTS
(see under Item 5 above) • Comments are made when adequate selec-
tivity or protection cannot be obtained with
These contain the characteristic curves with
existing equipment. Alternative solutions
associated settings of each protective device
are to be proposed (such as replacing equip-
plotted (or drawn) on transparent A3 log-log ment and the practical aspects of each alter-
paper, 4.5 x 5 decades, 5.6 cm per decade.
native evaluated). This applies first of all to
Although there is no international standard for
old installations, but new plants also some-
these graphs, this is a frequently encountered times suffer from difficulties with regard to
and also practical size to ensure sufficient clar-
selective co-ordination. Full selectivity is
ity and legibility.
sometimes impossible to achieve, and may
• Each time-current chart includes a single-
line diagram of the electrical system covered
not be necessary either. These comments are
therefore very important in order to explain
by the chart (for ease of reading). aspects which may not be obvious from just
• Each time-current chart also includes a table
of settings for each protective device on the •
looking at the charts.
The possibility of operating a device or melt-
chart, with associated current transformer ing a fuse with the minimum available short-
ratio (where applicable). circuit current must be evaluated and com-
• Each protective device characteristic should
be clearly identifiable, both in the single-
mented on. This is especially important where
short-circuit currents are so small that trip-
line diagram and in the table. ping may not occur at all, such as in emer-
• There should not be so many protective
devices on a chart that overview and clarity
gency systems, UPS systems or vital auxil-
iary low voltage systems .
are jeopardised. (A small number of charac-
teristics should be aimed at.)
• When the network layout causes difficulties
in respect of obtaining selectivity, this is to
• Maximum and minimum available symmetri-
cal short-circuit currents for three-phase
be commented on. In meshed networks it
may be difficult to see from the time-current
faults are shown on each chart. These cur- curves and the single-line diagram how the
rents apply for the network covered by the protection is supposed to operate. A func-
single-line diagram on the chart. When nec- tional description which includes interlocks
essary, the time-dependent variation of the is then required.
current is shown. • When, as a by-product of the selectivity ana-
• When several voltage levels are represented
on the same chart, the current scale in amps
lysis, equipment is discovered which may
be underrated or misapplied, this is to be
is marked for each voltage level on the commented on. This applies particularly to
abscissa. Alternatively, multiplication fac- old circuit breakers which may have become
tors are given for converting current to the incapable of coping with the current short-
other voltage levels. circuit level.

101

5.6 101 97-03-05, 13.46


INDUSTRIAL POWER SYSTEM
Fault Control

CRITERIA FOR SETTINGS AND older installations) should be noted in the


MARGINS (see under Item 3 above) table.
The report also requires a section where general
criteria for the selectivity work is explained,
• These tables are primarily intended for oper-
ating personnel who can then check that all
such as: settings are correct. The tables must be up-
• Time and/or current margins between relay
curves of inverse time characteristic. This
dated along with the rest of the selectivity
plan.
usually applies to systems for medium or
high voltage where relays and current trans- SINGLE-LINE DIAGRAM
formers are used. The relay may be of differ- (see under Item 2 above)
ent manufacture from the circuit breaker and An overall single-line diagram of the plant
have different operating times which must subject to analysis is to be included in the
be accounted for in the lower time decades. report. When only part of the electric power
• Time and/or current margins used in the
analysis between low voltage characteris-
system is subject to analysis, this is to be clearly
indicated in the single-line diagram.
tics. These margins may be accounted for in
two ways: SHORT-CIRCUIT CALCULATIONS
1. The devices are drawn with their tolerance (see under Item 4 above)
bands including opening or melting times. These are the basis for all selectivity work, and
The margins are thus inherent in the charts are carried out in advance or as part of the study.
themselves. (This is of course easiest to A summary of short-circuit calculations appli-
understand by operating personnel.) cable to the protection is to be presented as a
2. The devices may be drawn as single lines, separate section of the report. All impedances
requiring margins to be specified elsewhere. and time constants used in the calculations are
to be included.
North American and some Japanese manufac-
turers usually provide time-current graphs as
DATA REQUIRED
TOTAL operating bands including all toler-
In order to carry out a selectivity analysis, the
ances. European and other manufacturers may following data are required:
provide graphs drawn as lines only, tolerances
being found elsewhere in their publications. • A single-line diagram of the electrical sys-
tem involved showing: Power, voltage, imped-
• The margins of the device settings are given
with respect to: a) Motor rated current and
ance and connections of all transformers. Nor-
mal and emergency switching conditions.
starting current as well as locked rotor with-
Name-plate ratings and subtransient reactance
stand time. b) Transformer rated inrush cur- of all major motors and generators. Transient
rent and thermal withstand current due to
reactances of synchronous motors and genera-
secondary short circuit. c) Cable thermal
tors. Synchronous reactances of generators.
withstand current or I2t curve. Current forcing of smaller generators during
short circuit. When emergency supply is part of
TABLES OF DEVICE SETTINGS
the study, short-circuit capability of capacitor
(see under Item 6 above) banks and UPS converters must be given. Con-
For each switchgear assembly (MCC, panel,
ductor sizes, types and configurations. Current
etc.) a table covering all overcurrent devices
transformer ratios. Identification of all
should include the following: overcurrent devices.
• Name or number of feeder, or circuit device
identification number/tag number.
• Ratings, time-current characteristics and
ranges of adjustment of all relays, overcurrent
• Type of device (relay, fuse, MCCB, MCB,
etc., or combination of these) manufacturer, •
releases and fuses under consideration.
Complete short-circuit study for both first-
current transformer ratio, setting ranges and cycle and interrupting duties. This includes
recommended settings. maximum and minimum expected currents as
• Any change to a previous setting or com-
plete change of protective device (e.g. for
well as available short-circuit current from all
sources.

102

5.6 102 97-03-05, 13.46


INDUSTRIAL POWER SYSTEM
Fault Control

• Expected
considered.
maximum loading on any circuit

• Any special overcurrent protective device


setting requirements stipulated by the sup-
ply company
• When EX(e) motors are included in the
study, it is necessary to include rated current
and starting current as well as thermal time
limit Te.
• When direct-started motors and their protec-
tion are part of the analysis, starting current,
actual starting time and maximum allowable
starting time are to be given.

103

5.6 103 97-03-05, 13.46


INDUSTRIAL POWER SYSTEM
Voltage and frequency control

INDUSTRIAL POWER SYSTEM CONTROL

Contents
page
1 General 104
2 Voltage and frequency control 104
3 Fault control 105
4 Motor control 105
5 System events recorder (SER) 105
6 Central control room (CCR) aspects 106
7 Load management system (LMS) 107
8 Load shedding system 108
9 Reacceleration (RA) and restart (RS) system 108
10 Black start system 109
11 Operation control (where to operate, monitor and alarm) 109

General
There are frequently misconceptions amongst Frequency
project design engineers as to what is to be If the plant is interconnected with a power
”controlled” and by whom or what in an indus- company, frequency is not generally of much
trial power system. Unfortunately, the word concern, since it is wholly looked after by the
”control” has many meanings, and with the generator prime movers in the main grid. How-
advent of fast integrated circuits, microcomput- ever, if the industry has co-generation, or is
ers these days can ”control” just about anything running its generators in island operation, fre-
in a large plant. In the following sections some quency must be corrected to 50 or 60 Hz, with
of the most common power system parame- some small acceptable tolerance. The
ters subject to ”control” will be presented. This generator(s) follow the rotation of the prime
overview will hopefully assist the electrical and movers, and the speed is controlled by the
instrument/automation disciplines in agreeing turbine or diesel engine governor, which comes
on what method and type of equipment will be with the unit as part of the package delivery.
best suited to supervise, regulate, monitor, give Hence frequency is wholly a slave of the prime
alarm and execute action in the power system. mover speed.

Voltage
Voltage and frequency control The voltage normally swings continually within
During normal operation an industrial electri- acceptable limits as loads are connected and
cal system has only two parameters which are disconnected inside the plant and outside in the
subject to regulation, namely frequency and power company network. In-plant generator
voltage. However, both these parameters are voltage regulators will attempt to bring the
controlled by regulators which are delivered voltage back to a predetermined value when it
with and are part of the power equipment itself, falls outside the set values. Otherwise, the large
and which it is not generally considered suit- transformers may be equipped with on-load tap-
able to purchase separately. changers (OLTCs), which also adjust the volt-

104

5.7 104 97-03-05, 13.46


INDUSTRIAL POWER SYSTEM
Voltage and frequency control

age according to a predetermined value. None an assembly of such units is likewise given the
of this equipment is able to cope with fast name ”Motor Control Centre” or MCC. Start-
variations that are due to disturbances such as ing and stopping may only require manual
starting of large motors in a weak network. operation; however, MCCs are normally under
Here it is up to the designer to foresee all the management of a computer, which may
”normal” disturbances and engineer the power execute the start and stop actions without inter-
system such that it can ride through the larger ference from operators. Sometimes the process
voltage swings without connected loads being operator may wish to overrule the computer
interferred with. and start or stop motors manually, providing it
is safe for the process to do so.
Of course, motor control may be more so-
Fault control phisticated and include the variation of speed,
By far the largest and most complex intelligent traditionally done with DC motors, but more
supervisory system in any power supply is the and more often by adjusting the frequency to
fault control system. It is generally not thought either cage-type induction motors or, for larger
of in this way as it is usually termed ”relay units, using synchronous motors all the way
protection” or simply ”protection”. However, up to 40 MW for large compressor drives. For
as microprocessors are becoming steadily faster such large ASDs (adjustable speed drives) it is
and cheaper, relays are gradually incorporating essential to recognise that the speed controller
more and more chips to become like small (or frequency converter) is an integral part of
individual processors with a great number of the motor package, where all parts are finely
protection functions, which previously required tuned to each other. The interface with process
many individual relays to accomplish. How- control is basically only to provide a protocol
ever, there is still some way to go before micro- for an input signal to the frequency converter in
processor-based relays take over industrial pro- order to increase or reduce speed.
tection altogether, particularly in the low volt-
age fuse field where a current-limiting fuse will
take 2 milliseconds to complete the entire fault
sensing, decision making and fault interrupting
System events recorder (SER)
cycle. Control and instrument engineers are When faults or severe disturbances occur in the
generally not aware of the speed and fast opera- industrial power system, it may be of advantage
tion required in a power system to protect to know the sequence of events afterwards in
people and plant against harm and damage order to diagnose the source of the fault or
when short circuits and other faults occur. There- disturbance. With the extremely fast behaviour
fore, fault control or power system protection of power systems, as many as 50 actions may
still remains much like a separate electrical have taken place within a 100 millisecond pe-
discipline with its own engineering rules, some- riod. This is usually too fast for normal process
times being more of an art than an exact tech- control since the industrial process which it is
nology. However, this has been presented in designed to handle is much slower.
rather more detail in the previous section. Here are some reasons for installing an SER
to look after the high and medium voltage
systems:

Motor control 1. When medium voltage motors fail, they may


The starting and stopping of constant speed still be under some form of guarantee. In
asynchronous induction motors, as required by order to prove to the manufacturer, for in-
the manufacturing or plant process, is the most stance, that the failure was due to low quality
common control function in any industry. For stator winding insulation and not maltreat-
this reason, a fused switch combined with a ment of the motor, the recorded sequence of
contactor and some minor protective and aux- temperature, protective relay operation and
iliary relaying is, in some parts of the world, circuit breaker action is a sound basis for
given the name ”motor controller”. Similarly, further discussions.

105

5.7 105 97-03-05, 13.46


INDUSTRIAL POWER SYSTEM
Voltage and frequency control

2. Although a power company should know its


availability at the point of delivery, it may
well happen that it does not include in such
statistics short voltage dips or even complete
outages of less than say 0.2 seconds. These
may cause complete plant shutdown if the
plant has not been designed to ride through
them. A recording of all important power
system events is the only solid proof in
contractual discussions with the power com-
pany in such cases.
3. Some faults or disturbances are very hard to
get to the roots of, especially in the area of
earth faults. A recording of the sequence of Fig. 1. Traditional mimic where the IPS is rep-
events just prior to and following such a fault resented on a sheet steel panel with physical
may give valuable clues. symbols, operating ”handles”, monitoring in-
4. Spurious (nuisance) tripping without any struments and indicating lights.
obvious cause sometimes happens, espe-
cially in a commissioning or early opera-
tional phase. Even if such trips often have
their causes in small wiring or control cir-
cuitry not being monitored by the events
recorder, a record of the main events may
indirectly point to the cause.

Central control room (CCR)


aspects
A process type industry will normally have a
central control room where all process-related
decisions are taken and executed from, either Fig. 2. Single-line diagram, monitoring, indi-
by the operators themselves or by some compu- cation and operating functions represented on a
ter-based logic assisting the operators. There modern video display unit (TV screen).
may be one single or many separate control
systems collected in the CCR, with their asso-
ciated mimic panels or equivalent video screen
graphical pictures. However, the power supply arising which will require partial or total shut-
control and the electrical operators have tradi- down of the entire plant. Gas release in a chemi-
tionally had their location elsewhere, outside cal plant would be such a situation. And if the
the CCR. The reason for this is the traditional gas, in addition, is flammable, all electrical
duties and education of electrical staff, along equipment that is not explosion-proof may be
with the electrical safety codes or regulations in subject to shutdown. The ESD is normally a
most industrial countries having a 100-year- stand-alone control system located in a CCR
old history. However, the electric power supply and is heavily interfaced with all electrical
has a strong interface with all that is going on in supply circuits. However, there is not much
the CCR. influence from the electrical discipline, except
in one respect: the ESD is itself powered from
Interface with emergency shutdown one or several UPS feeders. (If UPS supply is
system (ESD) lost, the ESD usually shuts down as a ”fail-
The safety philosophy of any industry has to safe” mode, and nuisance trips of the UPS can
evaluate the possibility of hazardous situations therefore be rather embarrassing.)

106

5.7 106 97-03-05, 13.47


INDUSTRIAL POWER SYSTEM
Voltage and frequency control

Interface with fire detection Plants in petroleum refining have carried out
All electrical rooms usually have smoke and/or integration programmes where all CCR opera-
fire detectors feeding into an autonomous con- tors have to have full electrical and instrumen-
trol system often located in CCR. This control tation competence (in addition to being famil-
system will sometimes automatically release iar with the plant process). Such programmes
some fire extinguishing agent after smoke or have invariably been in conjunction with in-
fire is detected. This could be detrimental to stalling an entirely new CCR and process con-
electrical switchgear and control electronics, as trol. In this manner the CCR has become the
an electrical ”fire” is seldom anything but a integrated control centre that control engineers
smouldering in cable insulation, which is best have dreamed about for years. Some of the
taken care of by interrupting the faulty circuit. issues involved are:
It may be hard to convince safety engineers
that there is not much point in pouring fire
extinguisher onto a burning arc, as this has only
• Training of electrical and instrument staff is
required to make all CCR operators multi-
the outer appearance of a ”fire”, but is alto- disciplinary. This may involve courses and
gether a different natural phenomenon. A burn- on-the-spot training of two years´ duration.
ing arc consumes no air and will burn in spite of
no oxygen present, contrary to all other fires.
• Integrating the operations and maintenance
functions
The best arc ”extinguisher” is again disconnec-
tion of the circuit. Fresh water, with its cooling
• Reorganising of the electrical and instru-
ment disciplines, and setting up an advisory
effect, has proved to be just about the only engineering department
medium which has any real purpose as a fire
extinguisher in electric power equipment rooms.
• Doing away with the earlier engineering and
maintenance manager positions

Integration of the electrical and instru- Load management system (LMS)


mentation/automation disciplines This is a type of control aimed at saving energy
The impact of modern control equipment is not and costs, and is therefore also termed Energy
so much a technical question as one which ad- Management. It attempts to optimise the run-
dresses old and new ways of organising work. ning of all loads such that they will consume a
The continuous discussion over many years minimum amount of power at all times, without
about what is required to integrate the entire interfering with plant production. A typical
electric power system into process control has load management system (LMS) run by a cen-
an answer which is closely related to what edu- tral processing unit (CPU) and a number of
cation and training is mandatory in each coun- field processing units (FPUs) for a manufactur-
try for electrical and instrument operators. The ing plant may incorporate:
answer to this question will also decide how the
power system (traditionally run by electricians)
can now be operated by ”any” CCR operator.
• HVAC (heating, ventilating and air condi-
tioning) loads are generally serious energy
Such integration makes the CCR into the true wasters if not closely monitored. The high-
plant nerve centre from where ALL plant opera- est cold-duct temperatures and lowest hot-
tional commands are executed, AND from duct temperatures should be set by the CPU
where maintenance work permits are issued. to maintain zone comfort.
Additionally, the CCR may at the same time be
made into a command headquarters from where
• Weekly and holiday scheduling can be set so
as to match the running of equipment to
necessary electrical operations would also be expected occupancy in various buildings.
carried out in an emergency or catastrophic situ- With a large number of buildings, and vari-
ation (similar to the way the CCR functions in ations of occupancy, the switching on and
a nuclear power station). Most manufacturing off the correct amount of lighting, HVAC
industries may not need an integrated CCR of and other energy consuming services is a
this nature, but for large process industries and difficult manual task, even with semi-auto-
offshore petroleum installations, there are real matic devices scattered throughout the com-
benefits to be obtained by such integration. plex.

107

5.7 107 97-03-05, 13.47


INDUSTRIAL POWER SYSTEM
Voltage and frequency control

• Process chilled and hot water monitoring


includes tight control of temperatures and
frequency and for setting the disconnection
times.
cycling in chiggers, heat pumps, cooling 3. The fault duties of switchgear may be ex-
towers, heat exchangers under widely vary- ceeded as a result of plant expansion. Rather
ing seasonal temperatures. Manual control than purchasing and installing new equip-
can waste a great deal of energy. ment, one can choose to disconnect fault
current sources (such as large motors) prior
By controlling the above parameters, a typical to attempting to open a circuit breaker in the
manufacturing plant reduced its 3 MUSD elec-
faulty area in the case of a short circuit. Thus
tric energy bill by 10-15% in the first year of
the fault current is reduced to an acceptable
operation of an LMS. It is obvious that if a plant level before the breaker begins to interrupt
process control system is to be designed and
it.
installed, it is sensible to incorporate load man-
4. Generator overloading may occur if the
agement as well, rather than purchase a sepa- power company supply is lost. Existing in-
rate CPU just for this purpose.
plant generators will attempt to take on the
entire connected load, which causes:
Load shedding system • Frequency drop, resulting in:
Disconnecting loads during faults, or other
abnormal circumstances such as too high a load
• Speed drop on station auxiliaries, which
may be critical on steam turbines, where
or reduced supply, sometimes also falls under pump or fan output is proportional to speed.
the category of ”load management”. However,
it is treated separately here since its main pur-
• Transformer overfluxing, if voltage can be
maintained.
pose is not to reduce costs in the long run, but
rather to avoid total system collapse, or avoid
• Steam turbine blading resonance, which can
shorten blade life to as little as 10 seconds.
penalty clauses in power contracts. Automatic
load shedding equipment is sometimes manu- • Detrimental effects on process control or
computers.
factured under that name by specialist manu- Appropriate load shedding will prevent these
facturers. But due to its generally ”slow” opera- results from happening.
tion, it may also be integrated in some central
process control scheme. The following situa-
tions may call for automatic load shedding in a Reacceleration (RA) and restart
typical large pulp and paper mill with hydro and (RS) system
steam co-generation:
It is important to distinguish between on the
1. Limiting demand may be required if the one hand reacceleration, which takes place af-
mill´s own generation is disconnected and ter a short voltage dip has occurred and all plant
demand exceeds the power company con- motors have slowed down and are now all
tract value. Tripping of load inevitably means trying to regain speed, and on the other hand
restarting, which in case of large motors may restart, which assumes that the voltage dip or
represent a large voltage drop and which outage has lasted for so long that RA is no
may be a nuisance to the rest of the plant. longer possible and an automatic sequential
This may influence the selection of the loads restart has to take place. In the RA case, there
to be shed. may not be enough strength (short-circuit ca-
2. A system instability situation may develop pacity) in the system to manage the large reac-
during a sudden loss of generation or power tive demand from induction motors, which are
supply, or during fault conditions. Only dy- all drawing starting current at the same time.
namic fault studies will indicate if there is a The system voltage would simply collapse if
latent instability which requires disconnec- some load shedding as described above were
tion of loads in order to save the entire not applied. In other words, RA is normally
system from collapse and total shutdown. incorporated with a load shedding scheme.
Such studies will also provide the necessary Similarly, automatic RS may also be com-
time margins for recovery of voltage and bined in a load shedding scheme.

108

5.7 108 97-03-05, 13.47


INDUSTRIAL POWER SYSTEM
Voltage and frequency control

Black start system The locations are:


This is normally not only a control scheme, but CRC = central control room
also a manual or semi-automatic procedure to Gen CP = Generator control panel located close
follow when a complete black-out has occurred. to or adjacent to the generator
It includes the possible depletion of UPS batter- HV SWGR = high or medium voltage switch-
ies and necessary fuel tanks for emergency or room or a local control room adjacent to the
essential power generation. In other words, all outdoor switchyard
plant is now completely dead, including all LOC = local (this may be on the motor skid or
control systems and emergency lighting. generator skid)
This may not be an actual possibility for a ER = system events recorder (located adjacent
land-based plant, but an offshore petroleum to switchgear or in a local electrical control
plant which in an gas explosion or other emer- room)
gency may have evacuated all staff has to be PMCP = prime mover control panel at the skid
designed for such a possibility. Also, if land or in adjacent local control room
plants go through the exercise of envisaging LOCANN = local annunciator at the switch-
how to start up after a complete and total outage board or in an adjacent local control room
at any time of the year, there may be some LOC CP = local switchgear control panel at
unforeseen consequences in store. For instance, the main intake substation
if a chemical plant in a winter climate comes to
a complete halt, how are all the frozen pipes Other abbreviations are:
going to be thawed out after some hours of BS = bus section
standstill? CB = circuit breaker
G/T = generator transformer
OLTC = on-load tap changer.

Operation control (where to


operate, monitor and alarm)
The following is a typical listing of controls,
instruments and meters, status indications and
alarms, both locally and remotely, for some
common types of large electric power equip-
ment. The situation reflected in these tables
represents a plant with a normal autonomous
system of electrical discipline. This is not an
integrated situation as described above in the
CCR section ”Integration of electrical and in-
strument disciplines”. Therefore, a number of
local control rooms and locations are assumed.
Although this may be typical of a chemical or
petroleum type of industry, the lists may also be
applied to other types of plant.

The requirements at each location in the tables


are as follows:
M = mandatory
MA = mandatory if applicable
GA = grouped alarm
IA = individual alarm
O = optional
T = close circuit breaker in test position only

109

5.7 109 97-03-05, 13.48


INDUSTRIAL POWER SYSTEM
Voltage and frequency control

MAIN GENERATOR with PRIME MOVER


CCR HVSWB Gen CP PMCP

Generating set controls:


- normal start M
- auto start M
- fast loading MA MA
- normal stop M M
- emergency stop M M
- local/remote M
(control selector switch)
Isochronous/droop control O MA
(selector switch)
Generating set - base/peak MA MA
(load selector switch)
Governor setpoint control M M M
Generator CB control O XT M
G/T OLTC - tap raise/lower MA MA
G/T OLTC - local/remote selector switch MA
Field switch - on/off M
Voltage regulator - auto/manual M
selector switch
Voltage regulator - voltage/P.F. MA MA
selector switch
Voltage setpoint control - auto M M
Voltage setpoint control - manual M M
P.F. setpoint control MA MA
Synchronising selector switch O M

Generator status indications:


Generating set - local/remote control M M
Generating set - base/peak MA MA
load operation
Isochronous/droop operation MA MA
Generator CB - open/closed M M M
Field switch - open/closed O M
Voltage regulator - voltage/P.F. MA MA

Generator instruments and meters:


voltage M M M
frequency M M M
current M M M
real power M MA M
reactive power M M
power factor M M
real energy summated M M
reactive energy summated M
Synchronising instruments O M
Field voltage M
Field current M
Stator temperature M
Hours-run meter M

110

5.7 110 97-03-05, 13.48


INDUSTRIAL POWER SYSTEM
Voltage and frequency control

Generator alarms:
Master trip relay(s) M M M
Stator temperature high alarm M M O
Coolant temperature high alarm M M O
G/T temperature high alarm MA MA O
G/T Buchholz gas alarm MA MA O
Excitation system alarm M M O
Rotor earth fault MA MA O
Auxiliary systems M M O
All protection relays (trip) IA O
Mechanical non-trip alarms IA GA GA
Mechanical trip alarms IA GA GA

POWER COMPANY INTAKE AND MAIN HIGH VOLTAGE SUBSTATION

CCR HV SWBD LOC CP

Controls:
Incoming feeder CB
CB control O XT M
sync relay & selector switch MA M
Incoming transformer OLTC
tap raise/lower O MA
local/remote selector switch MA
AVR setpoint control O MA
auto/manual selector switch MA
Bus tie or Bus coupler CB
CB control O XT M
sync relay & selector switch MA MA
Outgoing feeder CB
CB control O XT M

Status indications:
All CBs - open/closed O M M

Instruments and meters:


Busbars (per section)
voltage O M M
frequency O M M

Incoming feeder
voltage O M M
current O M M
real power O M
reactive power O M
power factor O M
real power summated O M
reactive power summated MA MA
transformer tap position O MA MA

111

5.7 111 97-03-05, 13.48


INDUSTRIAL POWER SYSTEM
Voltage and frequency control

Outgoing feeder
current O M
real power O O
reactive power O O
real energy O O

CCR HV SWBD LOCANN ER

Alarms:
All circuits - master trip relay(s) IA IA IA IA
Switchgear tripping supplies -
battery/charger IA IA O
Switchgear closing supplies -
battery/charger (each) IA IA O
Trip circuit supervision IA IA O
(per busbar section)
Loadshed (per stage) MA MA IA
Annunciator repeat alarms GA
Annunciate fault GA IA
HVAC failure GA IA
Substation temperature
too high/too low GA IA

MEDIUM VOLTAGE SWITCHBOARDS

CCR HVSWBD LOCANN ER

Controls:
Incoming feeder CB close/open M
Bus section CB close/open M
Distribution feeder CB close/open M
Motor CB close/open XT

Status Indications:
Incoming and bus section CBs - M O
open/closed
Distribution feeders - open/closed M O
Motor feeders - open/closed O M
Motor feeders - operations counter M

Instruments and meters:


Busbar voltage (per section) O M
Incoming line voltage M
Incoming line current O M
Bus section current O M
Distribution feeder current O M
Motor feeder current O M
Motor running hours M

112

5.7 112 97-03-05, 13.49


INDUSTRIAL POWER SYSTEM
Voltage and frequency control

Alarms:
All non-motor circuits
master trip relay GA IA IA GA
Motor circuits - protection operated IA IA
Switchgear trip supply
battery/charger (each) IA IA O
Switchgear closing supplies
battery/charger (each) IA IA O
Trip circuit supervision
(per busbar section) IA IA GA
Annunciator repeat alarms GA
Annunciator fault GA IA
Ventilation failure GA IA
Substation temperature
too high/too low GA IA

LARGE MOTORS (Medium Voltage)

CCR HVSWBD LOC CP


Manual controls:
Normal start M M
Normal stop M M
Emergency stop M M M
Local/remote selector switch M
CB control M M
Excitation setpoint control (sync. mach.) M M

Status indications :
Drive stopped M M
Drive running M M
CB - open/closed M M

Instruments and meters:


Stator current M M M
Real power M M
Reactive power M M
Power factor M M
Field voltage (sync. mach.) M
Field current (sync. mach.) M
Stator temperature M
Hours-run meter M

Alarms:
Master trip relay M M
Stator temperature high alarm M M
Coolant temperature high alarm M M
Excitation system alarm (sync. motor) M M
Protection relays on switchgear IA
Electrical non-trip alarms IA IA
Mechanical non-trip alarms IA GA
Mechanical trip alarms IA GA

113

5.7 113 97-03-05, 13.49


INDUSTRIAL POWER SYSTEM
Fault Control

INDUSTRIAL COGENERATION
OF POVER AND HEAT

Contents
page
1 Introduction 114
2 The steam turbine cycle 114
3 The steam turbine 115
4 The VAX steam turbine family 116
5 The gas turbine cycle 117
6 A gas turbine example 120
7 The combined cycle 121
8 Cogeneration with steam or gas turbines 122
9 Electric generators 123
10 Control system 124

Introduction
Power generation by thermal processes in gas continue all the way down to nearly the cooling
turbines and steam turbines involves unavoid- water temperature. Thus, the steam is expanded
able losses. These losses are discharged in the down to a pressure far below atmospheric pres-
form of low grade heat to the environment as sure. It is then condensed into water again in
hot exhaust air or warm cooling water in normal order to reduce the volume of working fluid to
power stations. In industry, however, as well as be put under pressure again for a new cycle.
in areas where heat can be distributed to local High pressure and high steam temperature in-
heat users by district heating, this low grade creases the efficiency of the steam cycle. Addi-
heat can often be used as a full replacement for tional efficiency can be achieved by introduc-
heat from separate heating boilers. The various ing multiple stage preheating of the feed water.
thermal cycles will be explained in some detail
in the following.

The steam turbine cycle


In a conventional steam turbine cycle, water is KOPIA
used as the working fluid. The water is put
under high pressure by a feed pump in order not
to boil at a too low a temperature. In industrial
systems the pressure may be 100 bar or even
higher. The water is heated in a boiler by
burning of fuel. It evaporates into steam, which
is subsequently superheated in a separate sec-
tion of the boiler. The resulting superheated
steam is expanded in a turbine where mechani-
cal power is generated. The expansion may Fig. 1. Elementary diagram of the steam cycle.

114

5.8 114 97-03-05, 13.49


INDUSTRIAL POWER SYSTEM
Fault Control

Steam is then extracted from the turbine at At partial arc admission, steam is introduced at
suitable temperature levels and fed to heat full pressure through several separate valves
exchangers in the feed water stream. and nozzles covering part of the first rotating
Steam cycles operate in the range of 40 % blade row, the governing stage. The load is
efficiency as condensing power plants. The controlled through opening or closing these
limiting temperature for the steam cycle de- valves. At full arc admission, the steam enters
pends on the maximum operating temperature the turbine through one control valve and over
of low- to medium-cost construction steels used the full arc of the first turbine stage. The load is
in the boiler and turbine or on other economic controlled through sliding live steam pressure.
restrictions. The temperature is often in the This arrangement is common for steam tur-
range 450 to 540oC. Industrial steam power bines operating in combined cycles.
plants often operate in the pressure range 60 to Steam for process purposes can be extracted
120 bar. Process related limitations may reduce from the turbine at suitable pressure levels. At
these values, e.g. in waste incineration boilers, the stage of extraction, additional space is pro-
where hot corrosion is a major problem at high vided for between the turbine discs. Holes in
temperature. the turbine casing allow steam to flow into a
The combustion of fuel is separate from the collection chamber integral with the casing and
working steam, and practically any fuel can be further to the extraction steam pipe. The steam
used. Coal is used frequently around the world flow from the extractions may be controlled by
for steam power plants due to its attractive cost means of internal or external devices. The steam
in comparison with other fossil fuels available. turbines can be equipped with a stage of vari-
able stator vanes for extraction control. By
closing the stator vanes downstream of the
extraction, more steam will flow into the ex-
The steam turbine traction pipe. External control is accomplished
The steam turbine transforms the thermal en- by a throttle valve in the extraction pipe.
ergy of the superheated steam into mechanical In district heating turbines the steam flows to
power driving the electric generator. Modern heating condensers, which operate under some
designs feature high efficiency of the steam pressure. Often, two-stage heating is used to
expansion in order to maximise the useful en- increase the overall cycle efficiency. Steam
ergy. then leaves the turbine at two different pressure
Steam enters the turbine through an emer- levels close to each other and condenses in two
gency stop valve and one or more inlet control separate heating condensers.
valves. The valves control the steam flow dur- Steam turbines are tailored to their purpose,
ing operation. Depending on the design, the i.e., the steam channel is designed uniquely for
steam admission can either be full or partial arc. the individual customer’s needs. Modern de-

Fig. 2. Typical configuration of a two-cylinder VAX steam turbine.

115

5.8 115 97-03-05, 13.49


INDUSTRIAL POWER SYSTEM
Fault Control

signs can meet these demands and yet have see Fig. 3. The stator parts are kept together by
many standard parts and components. The VAX means of rings, which build up the package.
steam turbine manufactured by ABB STAL is The HP turbine is geared to the generator,
a typical example. For each module the casing, which can be of a four-pole or two-pole design.
bearings, bearing distances, shaft glands, blade Steam is introduced through four symmetri-
clearances and inlet valves are the same. Also cally located control valves with integral cast
the auxiliaries come in modules, including the nozzle segments. Alternatively, a single inlet
lube oil, hydraulic oil, gland steam and control valve can be used. This is an efficient arrange-
systems. ment for sliding pressure operation or for tur-
bines running with small load variations.

The VAX steam turbine family LP modules


To get the best possible efficiency from the The LP modules normally have an axial ex-
VAX steam turbine, expansion has been split haust with the condenser bolted directly to the
over two turbine casings when admission con- turbine casing. It allows for a simple founda-
ditions are high and the steam expands to tion and a low and compact layout. The blading
vacuum. has a roof in all stages except in the last two,
The following modules are available in the which have free-standing blades. The LP mod-
VAX series: ules are either geared or directly coupled to the
generator. If required, the steam exhaust can
HP modules also be arranged downwards, upwards or to one
The high pressure turbines are of a barrel design side. The casing is horizontally split and fabri-
with a vertically split casing. They accept steam cated from steel plate. Steam up to 20 bar and
up to 140 bar and 540oC. Designs are also 440oC can be used.
available for 180 bar and 560oC. The radially
uniform casing allows for thermal flexibility MP modules
and smaller clearances, which contributes to The MP modules are extremely compact. High
a high efficiency. The rotor and diaphragms efficiency is secured by using advanced ex-
are assembled into a package, which is put into haust blading developed for large power plant
the casing horizontally using a special tool, steam turbines. The smallest MP-modules are

Fig. 3. VAX HP turbine. Assembly of rotor/stator package with casing.

116

5.8 116 97-03-05, 13.50


INDUSTRIAL POWER SYSTEM
Fault Control

nally controlled extraction. Moreover, they can


have pass-in of steam from external sources or
from a multi-pressure steam boiler in a com-
bined cycle. The MP modules can have a maxi-
mum of five different extractions.

Control system
The VAX control system comprises a built-in
turbine governor and electro-hydraulic valve
control, turbine protection and man-machine
communication. The man-machine communi-
cation and automatic equipment for controlling
Fig. 4. Medium pressure module MP24 of the auxiliary equipment can be connected to the
VAX series. corresponding system of other parts of a plant.
The control system is based on wide experi-
of high speed design and is geared to the gen- ence from demanding power plant applica-
erator. Larger modules, however, are directly tions. It has been delivered as a stand-alone
coupled. The MP modules can accommodate system as well as for integration with the over-
steam up to 90 bar and 510°C. MP modules can all decentralised control system for the plant.
accommodate steam up to 90 bar and 510°C.
MP modules are used in combined cycle plants Starting
and in waste-to-energy plants, where the ad- The thermal flexibility of the VAX results in
mission data are lower. short start-up times compared to other designs.
Typically, less than one hour is required from
Extractions and admissions cold machine to full load. A hot start can be
The VAX modules are designed for multiple made in less than 20 minutes. For plants oper-
admissions and extractions with internal or ating in dispatch mode short starts contribute
external control. Two locations are available in additional power.
the HP turbine. In two-casing arrangements,
steam can be extracted from the cross-over pipe
and an additional three extractions can be ar- The gas turbine cycle
ranged in the LP turbine. The LP and MP In a gas turbine the power is generated by
turbine modules can be furnished with inter- compressing air up to a pressure level of ten to
71.9 MJ/s
Natural gas 245,3 MBtu/h
1.013 bar 534°C
48 815 kJ/kg 14,69 psia 993°F
20 987 Btu/Ib
79,2 kg/s
1.013 bar Combustion 174,4 lb/s
15°C
14,69 psis chamber
59°F
7700/1500 rpm
77,7kg/s 14,2 Bar 1112°C 7700/1800 rpm
171 lb/s 2034°F
206 psia

ISO cond., Nat. gas fuel, Base load operation


Output, MW 24,6
Gas generator El. eff., % 34,2
Heat rate, kJ/kWh (Btu/kWh) 10 256 (9 979)
Fuel flow, MJ/s 8MBtu/h) 71,9 (245,3)
10 Stage 2 Stage 2 Stage Exhaust flow, kg/s (pps) 79,2 (174,4)
axial compressor compressor turbine power turbine Exhaust temperature, °C (°F) 534 (993)
Exhaust heat, MJ/s (MBtu/h) 44,7 (152,7)

Fig. 5. Elementary flow diagram. GT10 gas turbine manufactured by ABB STAL.

117

5.8 117 97-03-05, 13.50


INDUSTRIAL POWER SYSTEM
Fault Control

40 bar. The compressed air is further heated by power than the net power output of the gas
combustion of gas or liquid fuel. The resulting turbine. Efficient axial compressor designs were
hot combustion gases then expand through tur- developed after World War II, which made jet
bines, which drive the compressor and the gen- engines a realistic alternative to piston engines.
erator. All combustion products - including One of the reasons for the success was the
ashes - get in contact with the metal surfaces of considerably reduced number of parts com-
the turbine stages. In order to avoid hot corro- pared with a piston engine. This is accompa-
sion, the range of fuels is limited to gas and nied by higher reliability and lower mainte-
relatively clean liquid fuels. nance costs. Modern computer-based calcula-
As air has a larger volume at higher tempera- tion has improved the efficiency and reliability
tures it will be possible to extract more energy of the compressor designs to very high levels.
during expansion than during compression of The compressor is usually made from 12% Cr
the air. The surplus energy is used to drive the steels and the temperature is around 400 to
generator. As a by-product, hot exhaust gas is 500 oC at the exit of the compressor.
emitted. Typically, the temperature of the ex- A compressor based on aerodynamic effects
haust gas will be 375-600 oC. The thermody- is sensitive to surge in contrast to displacement
namic efficiency of gas turbines will be in the compressors. Surge occurs when the real pres-
range 28 to 42 %. Modern industrial machines sure ratio is higher than the pressure ratio the
will have an efficiency of some 35%. compressor is able to deliver at a certain mass
Gas turbines should be seen as standard flow. This can occur at start-up or during tran-
products. Contrary to steam turbines, they are sients. In order to handle these difficulties mov-
seldom changed to fit a process due to the large able guide vanes are used to modify the compres-
development costs involved. The main compo- sor performance. Extraction of air from the com-
nents of the gas turbine are the compressor, the pressor is often necessary in order to safely pass
combustor and the turbine. some difficult operating points during start-up.
The compressor transports very large vol-
The compressor umes of air There is always some particulate
The compressor design is in most cases of the present, which can deposit on the blades in the
axial flow type with 10 to 20 stages. The effi- air channel. Deposits will make the compressor
ciency is critical as the compressor uses more less efficient and may lead to increased risk of

Fig. 6. Cut-away of the GT10 gas turbine.

118

5.8 118 97-03-05, 13.51


INDUSTRIAL POWER SYSTEM
Fault Control

surge. They have to be removed on a regular stability and requires extra arrangements for
basis by washing. Washing is accomplished by some operating points, such as low part load.
spraying cleaning liquid into the compressor In practice most of the air is mixed with fuel
during low load operation or by stopping the before combustion. Cooling of the combustor
machine and soaking the compressor with wa- by leaking cold air films along its walls to
ter for a short period. It will remove most of the reduce metal temperature is no longer possible.
dirt and restore the compressor to its original The combustor has to be cooled by leading
performance. Some deterioration is not possi- combustion air for cooling in channels in the
ble to correct, however. The reason may be combustor.
corrosion causing rough surfaces, or erosion of
particles which changes the blade geometry to
a less efficient form.
Another cause of performance deterioration Combustion air

is increasing blade tip clearances, which may Gas fuel stage 2


occur if rubbing takes place, i.e., contact be-
tween the rotating and stationary parts during Gas fuel stage 1 Flame

operation. Rubbing results from rapid tran- Liquid fuel

sients when the thermal expansion of the rotor Gas fuel stage 2

and the stator reduces the blade tip clearances Atomisation


nozzle Gas injection
to zero. In normal operation it results in in- ports

creased leakage over the blade tips and lower Fig. 7. ABB’s burner for dry low emission
efficiency. This is one of the reasons for keep- (DLE).
ing the transients at reasonably low levels.
The compressor controls the air flow and
thereby the available gas turbine power. The Combustor design is a compromise between
effect of air temperature on performance is different requirements: low NOx formation,
quite marked, as a result of higher air density fuel flexibility and turbine inlet temperature at
at low temperatures. Thus, the gas turbine out- various operation points. Limiting factors are
put is higher at low ambient air temperature. the maximum metal temperature, permissible
A 15 oC increase in temperature may reduce pressure drop, etc.
the available power by some 5%. Today, dry low emission (DLE) combustors
dominate the market now that gas is the main
The combustor fuel. DLE burners for liquid fuel will be based
The combustor is an advanced device for com- on the same principles, but they are not yet
bustion of fuel. The energy density is very high. available on the market.
A major requirement on the combustion proc- ABB has developed a DLE burner, which is
ess is to keep Nox production at a minimum to based on the principle of lean premix combus-
reduce the effects on the environment. tion. The burner is a very simple design with a
The major gas turbine manufacturers are split cone where the two halves are displaced to
striving to reduce Nox formation by develop- form two slots where air can enter. Fuel gas is
ing so-called lean premix combustors. In a introduced in the centre as well as through
traditional combustor the fuel is introduced as small holes along the slots to achieve the de-
a cone of concentrated fuel, which burns in sired premix. The gas-air mixture forms a vor-
contact with the surrounding air flow. Thus, the tex, which breaks down at the end of the cone
temperature passes the theoretical maximum and combustion takes place. Nox formation is
during combustion and dilution of the gases. In reduced to some 25 ppm at 15% O2.
a lean premix burner the fuel is mixed with the
combustion air before it is ignited. The maxi- The turbine.
mum temperature can be kept at a lower level The turbine parts operate at very high tempera-
close to that required at the turbine inlet, and the tures. In fact, the operating gas temperature
NOx-producing peak temperatures are elimi- may exceed the melting point of the materials
nated. Unfortunately, this results in lower flame used. To master the situation the metal parts

119

5.8 119 97-03-05, 13.51


INDUSTRIAL POWER SYSTEM
Fault Control

have to be efficienly cooled. This is done by the grid. It could also be a limit of heat produc-
film cooling and internal convective cooling tion if it is a cogeneration unit or any other
with air bypassing the combustor. The cooling control parameter from the outside or from
air is not used for power generation and repre- design limitations of the installation.
sents a loss. Optimum use of small flows of A simple cycle gas turbine or a condensing
cooling air would give a competitive edge. combined cycle is usually limited by the rated
Due to the high temperatures, the relative maximum power or some grid limitation. A
expansion of different turbine components is cogeneration system is usually limited by the
critical, especially during transients. A good rated maximum power or the need for heat.
design results in low clearances during opera-
tion and low risk of rubbing.
A gas turbine example
Gas turbine operation The ABB STAL GT10 is a modern industrial
The gas turbine must be started by a cranking gas turbine. The machine has a power of 24,600
motor, often electric or diesel. Other means of kW at continuous load. The pressure ratio is
starting are also available, such as gas expand- 13.6, i.e., the compressor raises the pressure
ers or by compressed air. When the air flow almost14 times the ambient pressure. The air
through the combustor is sufficient, the fuel mass flow is 79.2 kg/s. The high exhaust tem-
valve opens and the fuel is ignited by a spark perature of 536 oC makes the unit most suitable
plug. The engine is accelerated to idling speed for combined cycle operation. Further techni-
by the external power in combination with the cal particulars are shown in Fig. 5. The GT10 is
power it generates on its own. Blow-off valves an industrial gas turbine designed and built for
on the compressor are opened during part of the industrial operation.
start-up process to avoid surge due to to low There are two main machine types on the
mass flow. market, the aeroderivative and the industrial
When the turbine is running it will be influ- gas turbine. Both are used in power plants, but
enced by at least one limitation in the control they have different characteristics.
system. It is left to increase its power until it The aeroderivative, as the designation im-
reaches a limit. Such limits could be the maxi- plies, is a jet engine originally developed for
mum generator electric output or a limit from powering aircraft but suitably modified for

Fig. 8. A GT10 gas turbine in the assembly shop at ABB STAL, Finspong.

120

5.8 120 97-03-05, 13.52


INDUSTRIAL POWER SYSTEM
Fault Control

stationary duty. It features compact design,


light weight and high efficiency, but requires
good fuels and frequent maintenance.
The industrial gas turbine has been devel-
oped for industrial use and high continuous
load. Weight is normally not an issue, so more
rugged designs and materials are applied to
ensure reliability in operation. A wider range of
fuels can be burnt, but the simple cycle effi-
ciency is slightly lower. Maintenance intervals
are longer and on-site overhauls can be made.
While the design of a modern jet engine departs
from the optimum path for cogeneration and
combined cycle, the industrial design is nar-
rowing the efficiency gap in such installations.
Both the GT10 and the 17 MW GT35 industrial
gas turbines are equipped with a DLE burner
for NOx abatement. The GT10 has been been Fig. 10. The interior of a KA10-1 combined
used with a DLE burner since 1991. cycle power plant with the steam and gas tur-
bine driving the same generator, providing sim-
Steam Turbine plicity and compactness.
15%
11%
WHR

Unit 80°C Combined cycle power plants have gained popu-


larity for their compactness, short construction
40%
33%
55°C time and environmental friendliness when built
100%
around modern gas turbines with DLE capabil-
Fuel ity. Based on a given heat demand, the com-
Fig. 9. Elementary combined cycle flow chart.
Waste heat recovery unit Steam turbine

The combined cycle


From the cycle descriptions above it appears
that the gas turbine cycle will emit hot gas at a
temperature close to the temperature of live
steam in the steam turbine cycle. It would be
natural to use the hot exhaust gas from a gas
turbine as the heat source for a steam turbine
cycle. Such cycles are called combined cycles.
The exhaust gas is used for steam production
in an exhaust boiler and the total effect will be
that a gas turbine with 33 % efficiency will
produce another 40 % of the recoverable heat as
electricity. The thermal efficiency may reach
50 % or more if the steam turbine runs in
condensing mode.
The steam end of the combined cycle can be
arranged in the same way as a conventional
steam cycle for extraction or back pressure Fig. 11. Combined cycle power plant of type
operation. KA10-2 in Borculo, Holland.

121

5.8 121 97-03-05, 13.54


INDUSTRIAL POWER SYSTEM
Fault Control

bined cycle will produce more electricity thanks If the process requires a fixed temperature, the
to its high efficiency. steam flow is normally throttled in the turbine
The KA10-1 from ABB STAL built around downstream of the extraction. This is a control-
the GT10 gas turbine can serve as an example led extraction. The remaining steam, not bled off
of a modern combined cycle plant. The output to the process, can be used in a low pressure
is about 35 MW in condensing operation. The turbine, where it expands down to the same
gas turbine and the steam turbine drive the pressure level as in a condensing turbine. A pulp
common generator from opposite ends. Steam mill is a typical example, where the digesters will
is raised in a two-pressure boiler to maximise need steam at 12 bar and the dryers at 2 to 3 bar.
the efficiency of the total plant. The machinery The plant may also need heating of buildings in
and boiler are arranged in a compact common the winter with heat at 80 oC.
building. Depending on customer demand, the A similar application is district heating, where
gas turbine and the boiler may be arranged for the heat load usually is at lower temperatures
vertical or side exhaust. The steam turbine and than in a process industry. Often, the peak
gas turbine are connected to the generator by temperature of the hot water is 120 oC and
means of flexible couplings to allow for flex- normal operation is at 80 oC.
ibility in operation.The KA10-1 combined cy- In all these applications the steam turbine has
cle plant may reach a thermal efficiency of to provide the flexibility, be it in a steam turbine
close to 50% in condensing mode. cycle or a combined cycle. In a gas turbine
If higher power is required, two GT10 gas cycle where the heat is recovered directly from
turbines may be combined with one larger the exhaust gas, the temperature level is usually
steam turbine to produce up to 70 MW, forming not changed. A rare exception is when fuel is
the KA10-2 model. burnt in the exhaust to increase the temperature
of the gas. More common, however, is to burn
fuel in the exhaust boiler to get enough heating
energy at extreme conditions or to follow heat
Cogeneration with steam load variations.
or gas turbines
14% Losses
Process industries often have large heat de-
mands as well as demands for power. They may
also generate by-products which can be used as Waste Heat
fuels, such as gas from refineries or black liquor Recover Unit 53% Heat
from sulphate pulp mills. These fuels form the
basis for the application of cogeneration.
In industrial applications where heat is used the 33%
temperature is set by process requirements, and Electric Power
these can vary considerably. The steam cycle is
adapted to such requirements by extracting 100%
steam at a pressure where condensation corre- Fuel
sponds to the temperature required by the proc- Fig. 12. Gas turbine with cogeneration.
ess. The condensation heat of the extracted Waste heat recovery unit Electric power
steam flow is then used to replace heat gener-
ated directly by some fuel in a separate boiler.
Several extractions are often needed to supply Economy of cogeneration
steam at the correct pressure levels set by the The normal thermal efficiency of a steam tur-
process. bine cycle is approximately 40 % and for a gas
In some applications, the total steam flow turbine cycle some 30 to 40 %. The combined
passing the turbine is used for process heat cycle reaches approximately 50% in the size
demands. The turbine is then of the back pres- range used by industries. These values could be
sure type. In most cases, the condensate is compared with the efficiency of a cogeneration
recovered and pumped back to the boiler, and system, where the total efficiency of power and
the residual heat goes back into the system. heat may be in the order of 85 %.

122

5.8 122 97-03-05, 13.54


INDUSTRIAL POWER SYSTEM
Fault Control

The loss of power by heat recovery is negligible


for a gas turbine plant. The power loss in steam
turbines operating in process applications de-
pends on the pressure and flow at the extraction
points. In order to use the heat at the tempera-
ture needed, it is necessary to sacrifice part of
the power production. In a district heating tur-
bine the losses are some 30 % of the power
attainable in condensing mode. The extra pro-
duction of heating energy is often twice the
production of electrical energy.
The ratio between electrical and heating en-
ergy of a cogeneration plant is called the alpha
value. Steam cycles have an alpha value around
0.5, while combined cycle plants may reach 1.0
or even higher. Figure 13: ABB air-cooled turbo-generator-
The loss of power has to be evaluated against type GTL. Typical arrangement for industrial
the value of the additional heat produced and cogeneration with top-mounted coolers, over-
the incremental investment for cogeneration. hung exciter, main terminals on the sides and
In most cases it is very profitable to use shield bearings.
cogeneration when replacing heat produced by
commercial fuels. speed turning of the turboset, the generator can
The structure of the power sector differs be equipped with a turning gear/ motor if the
widely between countries, and the success of a drive arrangement is a single-end drive. The
cogeneration project also depends on how the exciter machine is of the overhung type.
benefits can be shared between the power user, Air/water coolers are normally located on
the heat user and the power supplier. the top and the generator terminals are side-
mounted. This arrangement has been devel-
oped to suit the specific requirements of indus-
Electric generators trial cogeneration where low foundations are
Introduction required in order to minimise civil works.
Generators for industrial cogeneration are ei-
ther of 2-pole or 4-pole type. Cooling
The 2-pole generator, a so-called turbo-gen- For industrial cogeneration applications the
erator, has speeds of 3000 and 3600 rev/min for generators used are predominantly air-cooled.
50 and 60 Hz, respectively. The 4-pole genera- Even though other cooling media than air are
tor has corresponding speeds of 1500 and1800 used at outputs as low as 70 MVA, air cooling
rev/min. The output range is 20-150 MVA, is today the predominant method of cooling.
with 2-pole generators covering the entire range The advantages lie in lower unit cost, less space
and 4-poles covering 20-60 MVA. required, system simplicity, higher safety and
The voltage range is 6 - 20 kV, with standard lower maintenance requirements. In terms of
voltages being 10.5 - 11.5 kV for 50 Hz and size, the air-cooled technology is today used for
13.8 kV for 60 Hz operation. The efficiency is above 300 MVA, and even higher outputs are
> 98 %. The generators comply with the inter- being contemplated.
national standards IEC and ANSI.
There are, in principle, two ways of arranging
Arrangement air cooling:
The turbo-generator is a synchronous machine 1. Air is circulated in the generator internally,
with a horizontal shaft and a cylindrical rotor dissipating the heat collected in the genera-
supported in shield bearings. The shaft can be tor active parts in air/water coolers mounted
connected to a turbine at one end (single-end on the generator body. The coolers can be
drive) or at both (double-end drive). For low arranged as top or side mounted.

123

5.8 123 97-03-05, 13.54


INDUSTRIAL POWER SYSTEM
Fault Control

2. Air is supplied from outside through filter imity (shaft displacement) probes. Tempera-
arrangements, and after collecting heat from tures in windings, cooling air and bearings are
the active parts, it leaves the generator monitored by means of resistance temperature
through an exhaust. detectors (RTDs). To ensure that fluids (oil,
water) do not collect in the interior of the
Inside the generator the air is circulated by generator, leakage detectors are supplied.
means of axial fans mounted on the generator
shaft. The cooling air collects heat from the Excitation
stator winding end turns, the rotor winding and The generator is usually equipped with a
the stator core/ winding. brushless excitation system. In order to guaran-
tee a black start feature, the excitation energy is
The rotor generated in a permanent magnet generator
The cylindrical rotor has radial slots in which (PMG) mounted on the generator shaft. The
the rotor (field) winding of silver-alloyed cop- PMG feeds a thyristor bridge, which feeds the
per is located. The winding is secured in the main exciter with field voltage. The main ex-
rotor slots by means of wedges. The winding is citer armature voltage is converted to generator
cooled with air flowing axially in the rotor rotor DC voltage in a rotating diode bridge. The
slots. diodes are over-sized in order to guarantee
trouble-free operation with minimum mainte-
The stator nance requirements.
The stator housing has three functions: The voltage regulation equipment controls
1. Support for the rotor via the shield bearings the thyristor bridge and thereby the generator
2. Support for the stator active parts, e.g. core voltage.
and winding
3. Directing of the cooling air Control and protection
A generator control and protection cubicle
The stator core consists of silicon-alloyed elec- (GCP) can be supplied with a choice of equip-
troplate which is stamped into segments and ment to be installed in it. It normally contains
stacked inside the stator housing. The core is the voltage regulating equipment, excitation
arranged in a number of axial packages with thyristors, protection relays, synchronising
cooling air flowing radially between the pack- equipment, temperature monitoring and vari-
ages. The core is held together by means of two ous instruments.
preasure plates mounted in the stator housing. The generator voltage is regulated with an
The winding insulation system used is pre- automatic voltage regulator (AVR), see above,
dominantly of the pre-impregnated, resin-rich Excitation). The regulator is of a digital type,
type. ABB generators use the Micarex® sys- based on the ABB Advant Controller ® process
tem. control system and can comprise additional
functions such as synchronising. Other features
Terminals in the AVR are a power system stabiliser, diode
The generator neutral leads are terminated in a monitoring and rotor earth fault detection.
neutral terminal enclosure, equipped with neu- Protective relays of ABB type REG can be
tral grounding devices. The line leads are con- supplied for various protection tasks.
veyed through a line terminal enclosure which
contains surge protection and connection points
for cables or busbars. Both enclosures have Control systems
transformers for generator protection and con- For the control of cogeneration systems, i.e.,
trol. boiler, turbine generator, gas turbine and auxil-
iary equipment, microprocessors have replaced
Instrumentation the old systems based on mechanical relays. A
The generator is equipped with instruments to boiler control system handles the fuel transport
monitor the operation of the unit. Shaft vibra- system, burners, boiler control, safety system
tions are monitored with either seismic or prox- and auxiliary systems. For the turbine a turbine

124

5.8 124 97-03-05, 13.54


INDUSTRIAL POWER SYSTEM
Fault Control

regulator and automatic control are included, as


well as the turbine-related safety systems. The
auxiliary systems are also protected by relays
for transformers, intermediate voltage and low
voltage systems.
Control and monitoring of the unit are based
on man-machine communication where selec-
tion of process pictures and operation is made
directly on a display. Large units usually have
a common control room where all the separate
parts of the power plant are controlled. The
computer-based system includes printout fa-
cilities for alarm list reports, etc.
The industrial process and the cogeneration
unit can be integrated in common control sys-
tems for increased efficiency of the operators in
the control room.
High energy costs and more stringent envi-
ronmental regulations require more complex
control systems, which impose additional re-
sponsibility on the operator. By using micro-
processor systems for control and supervision
the operator is better equipped to meet these
increasing demands.

125

5.8 125 97-03-05, 13.54


INDUSTRIAL POWER SYSTEM
Standby and uninterrupted power supply (UPS)

STANDBY AND UNINTERRUPTED


POWER SUPPLY (UPS)

Contents
page
1 General 126
2 Standby versus uninterrupted power 126
3 Engine driven generating sets as standby power 127
4 Diesel engine versus gas turbine (GT) generating sets 127
5 Generator current ”forcing” 129
6 Uninterrupted power supply (UPS) 132
7 Dublicated invertes 137

General
Many of today’s activities, industrial, commer- operating speed, voltage and frequency before
cial and governmental, require power supply in they can be connected to the load.
addition to, or, of a quality that is better than
normal. Anyone planning to install or operate Uninterrupted power
such equipment should carefully review power implies continuous voltage and frequency within
requirements and determine in advance the qual- the limits of the equipment that is using it. One
ity of electric power he or she will require to type of equipment might supply what could be
operate the plant successfully, efficiently and termed uninterrupted power, even though there
economically. might be a perceptible change in voltage and
frequency, but for a very short period of time. In
another system, there may be little or no dis-
cernible change in voltage or frequency.
Standby versus It is extremely important to realise that there
uninterrupted power. is no perfect continuous power from any source,
An understanding is essential of the difference including the most modern and best-regulated
between these two types of equipment and sup- UPS units available in the market. There will
ply systems. always be instances, although there may be no
discontinuity of power, when there will be
Standby power changes in voltage or frequency unacceptable
is power which is standing by and is not neces- to the equipment being supplied.
sarily immediately available, usually from an Even though power is continuous, intermit-
engine-driven generator. In some cases, the tent changes in voltage of 10% may occur. Such
standby power may actually be running idle, but a change can be acceptable to most equipment
must be switched into the system after main but not acceptable to some. Spikes occurring on
power has failed. This operation requires a time the voltage, or over-harmonic voltages and
interval resulting in an interruption. Generally currents generated by other loads would cause
speaking, all standby systems are idle and must no problem for most equipment, but could be
receive a signal to start up and accelerate to disastrous to other equipment.

126

5.9 126 97-03-05, 13.55


INDUSTRIAL POWER SYSTEM
Standby and uninterrupted power supply (UPS)

Engine driven generating sets • ItperhaskWlowin initial cost (USD 150 to USD 200
the 100-1000-kW rating range —
as standby power this is roughly 15-30% less than a turbine-
Generating sets, where a combustion engine is
driven set).
driving an electric generator, are self-contained
and independent from the mains supply. This • It is capable of operating in extreme environ-
ments — high altitudes and high tempera-
makes them particularly suitable where:
tures, dust, and even extreme cold (if proper
low temperature provisions are made).
• another electric supply would not otherwise
be available, or would be available only at • A good record has been shown for prompt
and competent service facilities almost eve-
unjustifiable cost. rywhere in the world.
• ainreasonably priced power supply is required
addition to the mains supply for the pur- • Frequent opportunities are present to use the
engine’s waste heat in the jacket and stack
pose of covering peak loads. cooling water when the unit is used for long-
• a standby power supply is needed to cover
vital or emergency loads during power com-
term peak-shaving service.
pany supply failures. • There is reduced fuel consumption — roughly
30% less under full load as compared to the
• the equipment and its power requirements
have been analysed and can tolerate a power
single-cycle gas turbine.
interruption of l0 to 15 seconds for diesels Diesel engine disadvantages
and 4-5 minutes for gas turbines, either an
idle/standby system or a continuously run- • The engine is heavy, requiring solid, earth-
based support or expensive structural sup-
ning system can be selected. port if it is above earth. Moving or modify-
In principle, generating sets can be driven by ing such an installation later can be an ex-
steam turbines, gas turbines, gas-engines, gaso- pensive project.
line (petrol) engines and diesel engines as the
prime mover for the electric generator. In prac-
• Engine noise and vibration are in the low
frequency range, which is difficult and ex-
tical use, however, the diesel-engine and gas- pensive to isolate acoustically from nearby
turbine-driven units have gained almost exclu- occupied areas because of the substantial air
sive acceptance in the power ratings from about volume required for both cooling and com-
50 to 5000 kVA. Diesels are most common in bustion.
the lower range and gas turbines become com-
petitive at the high end of the scale. For ratings
• Maintaining the starting reliability for emer-
gency or standby service requires the engine
below 50 kVA, alternative power supplies such to be started and run under at least 30% load
as gasoline engines, fuel cells, solar or wind at least twice a month. Generally this energy
powered generators combined with batteries is wasted if the unit is not equipped with
are in common use. synchronising equipment such that it can be
run in parallel with the main power system.
• Starting in extremely cold weather is reli-
able only if lube oil or water jacket or both
Diesel engine versus gas turbine are kept heated. In cold climates, this supple-
(GT) generating sets mentary heat source, and its maintenance,
The following is an extract from an IEEE evalu- can be expensive.
ation, where the two types of units are com-
pared on a broad basis:
• Speed regulation for isolated machines un-
der load is inferior to that of gas turbine
units. Typically, sudden addition or removal
Diesel engine advantages of half the rated load will change the fre-
• Experience has been gained from vast num-
bers of sets in service
quency by about 3 Hz before the governor
reacts and can compensate.
• The unit has the ability to start within 10 sec.
and accept load while being brought up to Gas turbine advantages
speed. • Weight of a gas-turbine generator package is
127

5.9 127 97-03-05, 13.55


INDUSTRIAL POWER SYSTEM
Standby and uninterrupted power supply (UPS)

typically only about half that of an equiva-


lent diesel unit. Thus, it costs less to mount
• The greater time required for start-up is so
much more (2-4 minutes) that the larger sets
it on the roof or similar locations, or to move cannot be used as the sole emergency power
it if production or building-utilisation plans source (such as in hospital facilities) where
change. life-support needs call for start-up times
• When recommended clearance space is in-
cluded, a gas turbine set may take less than
around 10 seconds or less. However, in a
battery-supported UPS combination that
half the volume of a diesel unit. carries the no-break loads over the starting
• Less air is required. All the turbine’s air is
for combustion, whereas diesels require a
time of the gas turbine, this may be an
excellent combination.
great volume of air for cooling. • Initial costs are generally 20-30% higher
• Turbine vibration and noise are generally
easier to handle. The familiar turbine ”whine”
than for a diesel unit. (Much of this premium
may be offset by reduced installation costs.)
is almost all in the higher frequency ranges,
which are easy to isolate from the building Operating diesel and gas turbine sets
and to attenuate within the air intakes and electrically in parallel
exhaust ducts. A practical example of operating diesel and gas
• Starting reliability is extremely high, even in
the coldest weather. Tens of thousands of
turbine generator sets electrically in parallel in
an emergency power system manifests the re-
turbine starts are made daily, with failures markably different mechanical and control char-
almost unknown, in jet aircraft all over the acteristics as stability problems such as severe
world. transient overloads, voltage drop, and frequency
• Speed regulation is inherently superior be-
cause of the high speed and high inertia
drop, which are likely to cause catastrophic
shutdowns during emergency conditions.
characteristics of the turbine. For instance, To illustrate such a situation, a land-based oil
once full speed is reached, full load can be producing facility has two emergency genera-
instantaneously connected or disconnected tors consisting of a 2.5 MW diesel unit and a 3.5
on a turbine generator set, and the frequency MW gas turbine unit connected electrically in
deviation will remain within 2 Hz. This parallel. Emergency loads includes HVAC
frequency stability is particularly important loads, fire pumps, freeze protection, emergency
where the emergency load consists of large lighting and life support loads. The majority of
motors (e.g. compressors or fans) which are these loads can switch on automatically upon
connected on line intermittently. process demands or safety requirements. Some
• Routine maintenance requirements are sim-
pler. Manufacturers typically recommend
normal loads (also automatic) are mixed with
emergency loads in the same switchgear. Thus
that a turbine for emergency standby be very large load steps, including motor starting
operated unloaded once a month and under as well as static loads, can suddenly be applied
load only at three-month intervals. to the generators.
• Gas turbines offer greater fuel flexibility,
burning lighter fuel oils, including highly
Because of its heavy weight, the diesel en-
gine generator set is quite stable; the inertia
stable kerosene, aviation jet fuel, or residen- WK2 is almost ten times the inertia of the gas
tial fuel oils. turbine. However, the diesel is also less sensi-
tive to system changes. This creates a stability
Gas turbine disadvantages problem on the lighter and more sensitive gas
• Inherently higher fuel costs — typically more
than 30% greater than that of a diesel unit of
turbine unit during large step loading. The gas
turbine, having lower inertia and higher gover-
the same capacity. nor gain constant than the diesel unit attempts
• Limited availability of trained service per-
sonnel. Estimates are that there are only
to assume much of the load while the diesel
engine hardly reacts to a load change. Load-
about 5-10% as many standby and emer- sharing devices used to distribute steady-state
gency power turbine sets in service as there load proportionally between the two machines
are diesel units. have an insignificant effect during the first one

128

5.9 128 97-03-05, 13.55


INDUSTRIAL POWER SYSTEM
Standby and uninterrupted power supply (UPS)

or two seconds of the transient duration. ers in case of fault. Therefore, standby genera-
Transiently exceeding the shaft torque limit of tors are mostly compound-excited from current
the aeroderivative gas turbine may damage the and voltage transformers on the output from the
shaft or reduce its useful life significantly. generator, see Fig. 1. Another way to produce
The diesel generator unit is designed to start the necessary short-circuit current is to provide
and assume load within 10 seconds after the a separate exciter, as in Fig. 2. The requirement
loss of normal power. The gas turbine unit is a in many standby generator specifications (and
very lightweight aeroderivative type, compact even some mandatory government regulations)
and low in cost and designed to take load 120 call for the generator to produce 3 times its
sec. after the loss of normal power. The differ- rated current for at least 10 seconds. Fig. 2
ence in starting time means that the diesel unit shows a comparison between a self-excited
can become heavily overloaded during the pe- machine and current-forcing machines.
riod before the gas turbine unit is ready to
assume load.
The two generators operate with an iso-
chronous (constant speed) control mode. They
start, synchronise, and pick up load automati-
cally after disruption of normal power. The
governor systems of the generator units are also
dissimilar. The gain of the gas turbine governor
is much higher than the gain of the diesel engine
governor. The voltage regulator exciter system
of the gas turbine generator has a faster re-
sponse than that of the diesel-generator unit,
providing fast response under short-circuit or
large motor starting conditions, when the volt-
age is low but the current is high.
The conclusion in this particular case is first
of all that modified load-sequencing and load-
shedding controls have to be provided to avoid
transient stability problems. Secondly, system
stability in general is an important issue in all
planning and design of small emergency power Fig. 1. Compound excited generator.
systems with step loading or intermittent motor
starting. This practical case shows the necessity
for parallel emergency generator sets to have
compatible dynamic responses to system tran-
sient disturbances. The factors which signifi-
cantly influence the dynamic response of a
generator set are: mechanical inertia, governor
system, excitation system, generator subtran-
sient and transient reactance. Parallel genera-
tors with compatible dynamic responses pro-
vide a more reliable emergency power system
and much simpler controls.

Generator current ”forcing”


One disadvantage of small self-excited genera-
tors is that they may have a problem supplying
a sustained short-circuit current which is suffi-
cient to operate fuses, relays and circuit break- Fig. 2. Separately excited generator.

129

5.9 129 97-03-05, 13.56


INDUSTRIAL POWER SYSTEM
Standby and uninterrupted power supply (UPS)

exhaust gases travel at high speed and are


inflexible to rapid changes in direction of flow.
Back pressure then builds up in the exhaust
system with a resultant loss of engine power.)
The first section of exhaust from the engine
manifold should be a flexible section of pipe or
bellow. The next section must be supported to
allow the flexible pipe movement without
putting weight on the engine manifold.
The support brackets on the exhaust should
allow for pipe expansion, and short flexible
sections should be used on long runs between
fixing brackets. Where the exhaust pipe passes
through walls, a sleeve or wall plate should be
fitted, or a clearance hole left. Care should be
taken when deciding on the exhaust point to
Fig. 3. Comparison between available short- atmosphere to ensure that there are no air inlets
circuit current. or windows which could allow exhaust gas to
re-enter the building. On long exhaust runs a
drain point or condensation trap should be
Mechanical hints when designing for fitted near the engine.
standby sets (mostly diesels) Where more than one engine is installed,
Space each should have its own independent exhaust
Where space is a problem, the set should be system. More than one exhaust into a common
sized physically before it is sized electrically. pipe can be dangerous and could cause damage
Ideally, the set should be positioned alongside to various parts of the engine. On long exhaust
two external walls so that the cooling and runs it is nearly always necessary to fit a sec-
discharge air can be easily vented. ondary silencer near the end of the run.

Foundation Cooling and ventilation


To overcome the problem of vibration with Ventilation of the engine room is important,
diesel engines, machines are built on heavy and provision should be made for adequate
bedplates. These must be bolted down on to airflow through the room to replace the air
substantial (and expensive) concrete founda- consumed by the engine and the air pushed out
tions. With the unit construction method — of the room by the engine cooling system.
where the rigidly coupled engine and generator Various types of cooling can be adopted. The
sit on a lightweight subframe attached to a main ones are set-mounted radiator, remotely-
mainframe through resilient mountings — less positioned radiator, heat exchanger cooling or
substantial foundations are needed. cooling tower. The large volume of air required
by a diesel engine for cooling and combustion
Maintenance clearances is not always appreciated, and the total area of
It is important to allow at least 1 metre working incoming air vents should be at least double
clearance at the sides and 1.5 metres at the that of the engine radiator outlet at the opposite
generator end of the machine for maintenance. end of the engine room.
The set can be placed on a level floor, but In cold climates where sets are employed on
maintenance is facilitated if it is raised on two standby duty the room must be kept warm; air
longitudinal plinths. inlets and radiator outlets should be closed
when the set is not in use.
Exhaust systems When using a remote radiator or heat ex-
The exhaust should be as short as site condi- changer cooling system, allowance must still
tions and regulations will permit. Bends should be made for cooling the engine room to remove
be few in number and of a long radius. (Hot radiated heat from the engine/generator. Air for

130

5.9 130 97-03-05, 13.56


INDUSTRIAL POWER SYSTEM
Standby and uninterrupted power supply (UPS)

aspiration in the engine must also be included sufficient maintenance and regular ”exercis-
in this air flow requirement figure. ing” - under load - have not been practised.
Water used in all engine cooling should There are four methods of interconnecting and
preferably be treated irrespective of the quality operating standby generators in parallel with
of the water available. The cost of doing this is main supply to facilitate this routine of exercis-
small compared with the cost of damage result- ing under load:
ing from lack of adequate treatment.
1. Generators continuously running take up in-
house loads without the usual momentary
Fuel oil system
interruption associated with a transfer switch.
With all fuel oil installations, local regulations
have to be checked. When locating the daily 2. If synchronising equipment is installed, any
magnitude of exercising load can be applied
service tank away from the set, care must be
to the generators without the need to select
taken that the engine fuel lift pumps can supply
the fuel pump. For reliability, gravity fuel sup- actual loads for transfer.
3. Generators can double as peak-shaving
ply with the tank at a higher level is to be
equipment, either for the power company’s
preferred. Where bulk storage is required, the
simplest and most economical method is to peak or for the customer’s.
4. In the case of large generators, income from
install the tank adjacent to the engine room. A
power sold back into the power company
typical fuel oil arrangement is shown in Fig. 4.
Authorities who should be consulted during the network may be used to offset the cost of
exercising..
planning of a standby generating set installa-
tion include the local building authorities, the Most emergency generating systems are oper-
fire and environmental authorities, and local ated at low voltage and connected to the emer-
power company. gency loads, when needed, by transfer switch-
ing. The transfer switches are carefully de-
Paralleling standby emergency power with signed to eliminate the possibility of the emer-
main supply gency generators ever being paralleled with the
When lights go out, emergency generators some- power company or main supply. This arrange-
times fail to start. They may have been in the ment has been dictated partly by the power
basement for months, even years, representing companies´ traditional resistance to intercon-
thousands of dollars in capital investment. But nection, and partly by the need to keep the
when the time comes, they may fail to perform emergency system totally separate. Some na-
their vital function. The answer is often that tional safety regulations or codes even require

Fig. 4. Typical fuel oil system.

131

5.9 131 97-03-05, 13.56


INDUSTRIAL POWER SYSTEM
Standby and uninterrupted power supply (UPS)

that no transformer be interposed between the need emergency generation also have multiple
emergency generator and its loads. feeder networks to ensure maximum reliability
One of the problems with the transfer method, of power company supply, even before the
whether done with a transfer switch or with emergency generator is considered.
interlocked circuit breakers, is that one supply It is unlikely that all of the power company
must be dropped before the other is connected. feeders will fail simultaneously. Individual feed-
This causes a brief power interruption to vital ers may fail due to problems at local substa-
systems. The result is that hospital administra- tions, and their loads can usually be taken up by
tors, and industry managers concerned with the the other feeders in the event of a total power
continuous operation of their facilities, may company blackout; the feeders usually go dead
actually resist regular exercising of emergency one after the other as the power company sys-
generators. tem goes down.
It’s interesting to note that power company
thermal generating stations, which must main-
tain emergency power supply to lubrication UNINTERRUPTIBLE POWER
pumps and lighting in the event of a total SUPPLY (UPS)
blackout, never interrupt the prime power source As previously stated, standby power takes some
in order to load the emergency system. They time to come on line after a main power outage
exercise emergency generators regularly by has occurred. This does not satisfy the require-
dumping the power generated into dedicated ments of vital or essential equipment in numer-
resistive loads. However, as power costs con- ous industrial applications, which may require
tinue to increase, more and more emergency AC or DC no-break supply, such as:
generating systems are being built for parallel
operation with main power. But the cost is high.
• emergency lighting and escape route
lighting
Fully protective relays used with a continuous • public address and status alarm
interconnected generator are required, as well
as additional circuit breakers. So the emer-
• SOLAS (safety of life at sea) radio for
offshore plants
gency generating system must either be large, • fire and gas protection systems
or important enough to justify the interconnec-
tion.
• instrument safeguarding/emergency
shutdown systems

Peak shaving
• power supply to process instruments
and analysers
may very well be the cost-cutter that justifies
interconnection. Of course, one can peak-shave
• power supply to process computers and
data processing machines
by switching selected loads over to the emer-
gency generator as total plant load nears its
• lube oil pumps for large generators
and motors
peak, but this is cumbersome and depends on
having switchable loads of the right size. Ide-
• switchgear and relay protection in
substations
ally, the load shaved should be carefully se-
lected to minimise generator running time for Direct current uninterruptible supply.
maximum reduction in peak load. An intercon- This is a power supply derived from a battery-
nected generator can be automatically loaded rectifier combination (DC UPS unit) or from
to keep the total plant load below a predeter- rectifiers energised from one or more AC
mined level, whatever the total plant load. uninterruptible supply sources (AC UPS unit).
Such supplies should be considered for appli-
Power company paralleling adds security cations where the load is relatively small and
Because an emergency generator operates only closely concentrated, or to supplement AC UPS
when power company supply fails, it may be systems (e.g. for switchgear auxiliary circuitry,
thought that there is not much opportunity for fire alarm or communications systems). When
operating the systems in parallel when an emer- designing DC systems, due consideration should
gency actually occurs. But this is not the case. be given to permissible voltage drop at the load
Most industrial and commercial facilities that terminals.

132

5.9 132 97-03-05, 13.56


INDUSTRIAL POWER SYSTEM
Standby and uninterrupted power supply (UPS)

Common causes of failure Although there are differences from one manu-
Before starting to design DC (and also AC) facturer to another, most chargers are designed
uninterruptible power supply, it may be useful for approximately 40°C maximum ambient
to review some of the most common causes of temperature and 1000 m altitude. Deviations
failure: exceeding these values should be avoided.
Derating of 4% per ambient degree above 40°C
• Poor maintenance and insufficient system
supervision is one of the most frequent causes.
is not uncommon. Therefore, between 40 and
50°C, the battery charger may require a derat-
This includes battery failures or too low
ing of 40%.
capacity due to:
Altitude is a problem that can also affect the
Incorrect charging voltage battery charger application, while not adversely
Battery circuit interruption, such as
affecting the battery. A typical derating of
single-cell failure
approximately 2% applies per 100 metres above
Too high temperature 1000 metres.
• Incorrect design of the distribution system
Non-selective short-circuit protection
In sizing the DC current rating of the charger,
the following applies:
can result in total or partial shutdown of A = (Ich + L) X 1/C1 X 1/C2, where
the system
Insufficient tripping can result in fire or
low voltage • AIch==thethebattery charger rating in amps.
Long cable runs result in high voltage • battery manufacturercurrent
charging according to the
for specified recharg-
drops which can render sensitive loads
ing time at given charging voltage. (As an
inoperative approximation Ich = 1.1 x Ah/T.)
• Incorrect battery or charger sizing
• 1.10 = typical charger conversion factor
• Unsuitable or non-existing redundancy
For certain loads like switchgear relay • Ah = the ampere-hours of recharge
protection and emergency shutdown sys- • T = recharge time in hours,
tems with main and back-up functions, • L = DC continuous load current in amps
it is necessary to have a duplicated sup- • C1 = temperature correction factor
ply with dual batteries, chargers (and • C2 = altitude correction factor
inverter for AC)
DC system supervision
• Incorrect design of charger AC supply (such
as feeder protection that is set too low, which
Although a multitude of options are available
as indications and alarms, the following are
inadvertently may trip the charger and de-
useful and will assist in diagnostic work and
plete the battery) maintenance:
Where an AC UPS is available and the DC load 1. Loss of AC alarm. Most causes of loss of AC
does not exceed 15% of the AC supply capac- are due to temporary power failures affect-
ity, the DC may be derived via a rectifier unit ing the entire plant. But it is also possible
fed from the AC UPS distribution switchboard. that a fuse or breaker on the battery charger
circuit has operated. Without proper alarm,
Sizing the battery charger the loss of AC can result in the loss of the
While the size of the battery will provide defi- entire DC UPS system.
nite constraints on the battery charger, the fol- 2. Low DC voltage alarm (U< and U<<). Nu-
lowing should all be considered when design- merous conditions exist which could create
ing the charger (or DC UPS rectifier): a low DC battery voltage. One of the most
• AC supply, three-phase or single-phase
source and voltage
common is loss of the battery charger. Nor-
mal settings for U< is 1% below float charge
• battery voltage and capacity voltage. U<< is normally set at 85 % of float
• normal DC continuous load current charge voltage.
• battery discharge levels and recharging times 3. Battery earth fault indication and alarm.
• ambient temperature Most critical DC UPS systems are unearthed.
• altitude Therefore, a single earth fault will not result

133

5.9 133 97-03-05, 13.57


INDUSTRIAL POWER SYSTEM
Standby and uninterrupted power supply (UPS)

in operating a breaker or melting a fuse. It is obvious with such varying times that each
However, a second earth fault on another individual application has to be carefully engi-
”phase” may result in the loss of several DC neered with respect to size of the loads and
circuits. An earth fault indicator is normally normal (and worst case) duty cycle.
used to detect a battery earth in order to
locate and remove the earth fault before a Battery types
second one occurs. 1. Vented lead acid
4. High DC voltage alarm (U> and U>>). Like Sometimes this is called ”open type” lead
U<, the U> is set 1% above the float charge acid, and is the most common type of
voltage. Although not common, chargers battery and also the lowest price one. It
may occasionally “run away” into an requires few quick-charges. Some of its
overvoltage condition. Such a condition can disadvantages are:
result in damage to connected loads, severe Sensitive to high temperatures and ripple
gassing from the battery, loss of water to the voltage (harmonics) generated by the
battery, and ultimately a battery failure. To charger (and inverter for AC UPS) as
avoid nuisance alarms, the voltage high alarm well as certain types of load.
(U>>) should be set above the high rate More maintenance is required than for
equalising charge. the two other types.
5. High rate equalising timer. Most batteries Wrong type of float charging influences
require a high rate equalising charge on a its useful life.
periodic basis. While a selector switch from 2. Valve regulated lead acid
”float” to ”equalise” is available on most This type of battery is a more modern
chargers, it does require that a person re- lead acid type sometimes claimed to be
members to return the selector switch back ”maintenance-free” or ”sealed”. Neither
to ”float”. As usual, people are not always of these claims are quite true. Because
perfect, and an equalise rate can be left in the they have a ”solid” type of electrolyte,
“on” position, resulting in possible damage they require no water refill. Having no
to the battery. The use of an equalising timer acids that may spill is an advantage in
will reduce the probability of this occurring. handling and promotes personnel safety.
6. High temperature alarm Since there is little generation of explo-
7. Battery circuit failure sive gases during charging, because of
the regenerative process, there is no need
Battery capacity requirements for a separate battery room as for conven-
The batteries of DC or AC UPS units are sized tional lead acid. The size is relatively
to supply loads for greatly varying time inter- compact.
vals. Assuming that ”normal” load is present On the negative side are the same disad-
during the entire interval, the following are vantages as for freely ventilated lead acid.
some examples of how to size battery ampere- In addition, it is impossible to check the
hours (if load is less than ”normal”, the batter- level of charging by measuring electro-
ies would take longer before depletion): lyte density. The valve may become stuck,
which may cause drying out or explo-
• 301-8minutes for process plant shutdown sion. Further, there are limitations on
• ratinghours for substations and power gene-
plants
charging voltage and current. The battery
cannot be stored without loss of lifetime
• 10-20 minutes for non-process computer
installations
as the gel is included during manufactur-
ing. Finally, there is considerable spread
• 3abandon
hours for offshore plant shutdown and
platform procedures
of cell voltage, which makes monitoring
difficult.
• 8andhours for fire fighting, fire alarm systems
telecommunication systems.
3. Nickel cadmium
This battery has the longest lifetime (ap-
• tional aidsfor(onSOLAS
36 hours equipment or naviga-
offshore plants)
proximately 20 years). It is a mechan-i
cally robust battery which can tolerate

134

5.9 134 97-03-05, 13.57


INDUSTRIAL POWER SYSTEM
Standby and uninterrupted power supply (UPS)

many deep discharges as well as out-of- High end voltage implie low utilisation of the
tolerance charging, which does not affect battery, and therefore high cost. In order to
battery life. There is no risk of so-called achieve a low end voltage, the highest possible
”sudden death”. system voltage should be aimed at, normally
On the negative side there is the high cost 110% of nominal voltage. In addition, the low-
- approximately 2-3 times the cost of lead est possible float charge and the lowest possible
acid. So-called ”voltage depression” system voltage (80-90% of nominal voltage)
means that the battery must be oversized will achieve this result.
or many quick charges may have to be
made. The electrolyte has a tendency to Duty cycle calculation
carbonise.

Battery sizing
Sizing the battery means:

1. Determining the number of cells


2. Determining the rated Ah capacity

The following guidelines may offer some as-


sistance when determining the battery bank
size:
• IEEE Recommended Practice for Sizing
Large Lead Storage Batteries for Generating Fig. 5. Typical basis for battery duty cycle
Stations and Substations ANSI/IEEE Std sizing.
485-1983

• IEEE Recommended Practice for Sizing


Nickel-Cadmium Batteries for Stationary
The above figure illustrates, for a substation
battery, how the capacity must take into ac-
Applications ANSI/IEEE Std 1115-1992 count the base load (such as relay protection),
intermittent load (such as motor operation),
While the calculations for sizing a battery can peak load (busbar trip) over the entire standby
be performed by hand, computer programs are period.
normally used. The battery manufacturer can
assist in choosing and sizing the battery. Here The continuous current = load/min. system
are some simple rules for estimating battery voltage (I = P/Umin)
size:
Required Ah capacity = continuous current x
Maximum system voltage standby period (Ah = A x t)
This is the highest acceptable voltage for the This assumes all loads of constant power type
equipment to be connected to the battery, nor- and battery capacity data based on constant
mally not less than 110% of nominal voltage. current load.

Minimum system voltage Average discharge current for intermittent load


This is the voltage designated by the user to I = S(In x tn)/t
define the lowest acceptable voltage for the where
equipment connected to the battery. In = intermittent load during time interval tn
t = required discharge time (standby period)
Number of cells = max. system voltage/float Required Ah capacity for intermittent load = I
voltage per cell x t (to be added to Ah for continuous load)
End voltage/cell = 0.85-0.90 x Vnom/number For peak loads shorter than 1 minute, the bat-
of cells tery capacity will not be affected. For worst-
case conditions it is assumed that all peak load

135

5.9 135 97-03-05, 13.57


INDUSTRIAL POWER SYSTEM
Standby and uninterrupted power supply (UPS)

takes place at the end of the discharge period. insufficient charging. Further, towards the end
The voltage drop caused by the peak load will of the battery life, the capacity will begin to
influence the rated capacity in the following drop, and to obtain an approved battery test
way: requires 80% of remaining battery capacity. If
Voltage drop per cell DU = Ip x Ri it is below this level, the battery should be
where Ip = peak load replaced. To allow for these capacity variations
Ri = internal resistance given at the actual over the life of the battery, a life margin of
state of charge another 20% should be considered. This means
Then Ubatt + DU ≥ Umin altogether a design factor in the sizing of the
Where Ubatt = Battery voltage per cell after battery of 35-40%, which may appear high.
continuous and intermittent load discharge. Umin But, it is important to consider the application
= minimum system voltage per cell. of the battery and the consequences of failure.
Fig. 6 shows how a large battery can accommo- In most cases, the added margins are well worth
date a peak load at the end of the discharge the added cost.
period without voltage dropping to an unac-
ceptable level (battery 1) Alternating current uninterruptible supply
The principal difference between DC and AC
UPS is that the AC system basically consists of
a DC system with an added inverter to it. In
other words, AC UPS = DC UPS + inverter.
Therefore, all that has previously been said
about rectifier and battery also applies to the
AC UPS.
Over the past two decades, the process con-
trol industry has become one of the major
customers for static AC UPS systems, the main
reason being that the UPS provides for a better
Fig. 6. Effect of peak load applied at the end of quality power supply with less pollution of the
the discharge period. AC sinus wave than the power company can
Min. system voltage provide. In some parts of the world a computer
UPS supply is therefore called a ”power condi-
tioner”. This is, of course, in addition to the
non-interruptability of a UPS.
Temperature correction Further, with the increasing use of real-time,
Under ideal conditions the battery should be on-line data processing, together with associ-
maintained at a temperature near 20°C, which ated data communication, the demand for static
is normally accomplished with HVAC equip- AC UPS systems is growing consistently.
ment. At low temperatures the battery capacity As the technology has developed, various sys-
is reduced significantly tem configurations have emerged catering for
Since most industrial rooms are electrically various levels of operational security. All static
heated, the ambient temperature of the battery UPS systems (as opposed to previously more
room could become quite cold in winter if main common rotating UPS units) are based on the
power is lost. Therefore, the minimum tem- same fundamental principles. Normal AC sup-
perature of the battery room must be considered ply is used to feed a rectifier which provides DC
in battery sizing calculations. During an 8-hour at battery voltage. This DC feeds a static in-
outage in extreme frost conditions, the battery verter which generates the required AC voltage
room could easily drop to less than 0°C. and frequency for the load, see Fig. 7.
A static switch between the inverter and load
Correction factors is normally included. This static switch incor-
A margin of 15-20% is recommended to be porates detection and sensors of any out-of-
added when sizing the battery due to unfore- tolerance situation, such as an inverter fault,
seen additional loads, poor maintenance and and switches the load over to an alternate AC

136

5.9 136 97-03-05, 13.58


INDUSTRIAL POWER SYSTEM
Standby and uninterrupted power supply (UPS)

source. This alternative could be the normal Dublicated Invertes


main supply or some other source of sufficient The two inverters may also be operated paral-
quality. leled, with each sharing 50% of the full load.
In the event of a fault in either inverter, the other
one takes over the full load.
This configuration allows a faulty inverter com-
ponent or unit to be replaced without disabling
the whole system.
Advanced inverter/rectifier designs have dy-
namic response regulation to enable switching
0-100% load changes within acceptable volt-
age variation.
Where even greater security is required, the
main power supply is used as a third power
Fig. 7 Simple AC Uninterruptible Power source. In addition, a redundant rectifier, or
Supply even duplicate batteries, may be included. These
steps would be taken only where exceptionally
high security is required, or where the site
location is remote and unmanned. Further, even
This basic UPS configuration is widely used. a by-pass maintenance switch will permit the
The chance of a static inverter fault coinciding UPS to be taken out of service, where a reliable
with a main power failure is extremely small. by-pass source is available.
However, in some applications, even this small
risk may be unacceptable, and various more Limited short-circuit capacity
sophisticated configurations have been engi- A criticism often levelled at the static UPS
neered to higher degrees of redundancy. inverter as opposed to rotating machine types is
its low short-circuit capability. While rotating
Increased reliability generators supply momentarily 5-10 times its
One of the more popular arrangements for rated current to melt fuses or trip circuit break-
additional reliability is shown in Figure 8 where ers promptly, static UPS can only deliver about
the inverter is duplicated, with the two inverters 1.5 times its rated current into a short circuit.
run in a duty/standby mode, one supplying This represents much tighter restrictions on the
100% of the load and the other on standby. protection equipment and selectivity than if a
rotating generator were used, sometimes re-
quiring an oversized static UPS just to produce
sufficient short-circuit current.
There is a popular misconception about this
which goes as follows: ”The static switch will
switch to mains supply to blow fuses or trip a
circuit breaker in case of a short circuit, and
there is little probability that a mains supply
and short circuit will occur at the same time”.
This is correct for most UPS applications, but
for UPS systems also designed to operate dur-
ing a catastrophe situation, the previous state-
ment is not true. This is because it is exactly
during calamities (fires, earthquakes, gas ex-
Fig. 8. High reliability uninterruptable power plosions, etc.) that short circuits will occur.
supply. Therefore, if the UPS system is supposed to
operate in real emergencies too, the inverters
must be designed to deal with short circuits
without help from the static switch.

137

5.9 137 97-03-05, 13.58


INDUSTRIAL POWER SYSTEM
Standby and uninterrupted power supply (UPS)

Another drawback of the static UPS related to haviour, as well as careful protection and selec-
the small short-circuit capacity is its poor abil- tivity analysis, are essential if surprise outages
ity to cope with harmonics created by non- are to be insured against. Such surprise outages
linear loads. Such harmonics may be created by unfortunately have a tendency to reveal them-
certain types of loads such as switch-mode selves at the most inconvenient times. There
power supplies (see Fig. 9), and if these are of are numerous accounts of failures of vital sup-
large size or several in number, they can create ply to important equipment, including even the
havoc in a system which should be completely total and permanent breakdown of entire power
free from disturbances. stations, which could have been avoided with
only a little attention to the issues mentioned
above.

Fig. 9. Non-linear load - switch-mode power


supply.
Typical video display terminal
Summarised load from 100 VDTs

A combined standby and UPS power


ystem
There is more to vital and essential supply than
just the generators and converters/batteries. In
a large industrial complex there may be many
UPS units, both AC and DC, normally fed from
high priority distribution boards supplied by
standby or emergency generation. One of the
important questions here is whether to central-
ise some or all UPS units into one or two, or to
provide a distributed UPS supply with many
small units.
Secondly, the possibility of fire hazard and
other calamities has to be considered. Impor-
tant loads usually have two independent feeder
cables from the UPS distribution board(s), and
separate paths have to be found such that proc-
ess control or vital communication systems are
not knocked out because both power supply
cables happened to lie on the same cable rack.
Thirdly, the dynamic behaviour of the standby
or UPS power system is no different from large
power systems, and may suffer from the same
disturbances if motors are started, loads are
switched, or when faults happen. Therefore,
system study and calculations of dynamic be-

138

5.9 138 97-03-05, 13.58


INDUSTRIAL POWER SYSTEM
Prefabricated and mobile substations

PREFABRICATED AND MOBILE SUBSTATIONS


Contents
page
1 General 139
2 Secondary substations 139
3 Main or primary substations 141
4 Modular substation buildings (docking type) 141
5 Integral transformer substation 142
6 SF6 compact substation 143

General
Substations are assemblies of primary switch- countries). Although the low voltage fusegear
gear, transformers, and secondary distribution is typical of power company tradition, these
equipment. Many different arrangements are substations are nowadays also customised for
used, with the equipment normally closely con- industrial applications.
nected, although primary or secondary equip- Up to now, transformers have normally been
ment may also be separated from the trans- purchased separately and installed after the
former. substation frame and walls have been erected at
Traditionally, the various components of a site. This is primarily because the substation
substation are shipped as separate items and frame need not then be made so rigid in order to
erected, wired and tested at site in custom- stand up to the heavy transport weight. But
made buildings or rooms by local contractors. more important, procurement tradition has con-
In recent years the trend towards using prefab- sidered distribution transformers as bulk items
ricated or even mobile units and buildings have and purchased them separately. Access to the
led the way to savings in costs, made available equipment is through outside doors or louvres.
by efficient factory assembly methods. Fig. 1 shows a modern typical mini-substation
In the following section the essence of this being hoisted into place.
modular and prefabrication trend is described Over the years the demand has increased for
using the substation definitions and terms as larger, prefabricated, indoor-operated ”walk-
stated in section 5.1 IPS Design. in” type substations, especially in colder cli-
mates, and this has led to the development of
the medium-sized substation.
The philosophy behind this factory-assem-
Secondary substations bled unit was more or less the same as for the
Mini and kiosk type substations earlier ”mini” type:
The European development of factory-assem- • Simple transportation
bled substations started in the 1960s with small
outdoor ”mini” or ”kiosk” type substations
• Flexibility in size through the use of differ-
ent standard sizes of housing. For larger
primarily for the electric power companies. substations two or more housing-modules
Distribution transformers in the range of 300- are coupled into one large substation at site.
1500 kVA, together with medium voltage and • Minimum civil works at site.
low voltage fusegear are installed inside the
same factory-made metal enclosure. Since it is
• Minimum erection and commissioning
at site.
often used in 10-20 kV ring networks, the
medium voltage T-connection is sometimes
• Easy to relocate. Combining housing and
foundation makes it simple to move the
called a ”ring main unit” (in British-influenced substation from one site to another.

139

5.10 139 97-03-05, 13.59


INDUSTRIAL POWER SYSTEM
Prefabricated and mobile substations

A recent development in the prefabricated line


of substations is the ”container” type. This has
become particularly popular in various process
industries, not only as a substitute for conven-
tional transformer and switchgear rooms, but
also for housing of computer and control equip-
ment, pneumatic and hydraulic auxiliaries and
diesel generator sets.

Fig. 1. Typical mini-substation for outdoor


operation.
Front page photo from Swedish brochure 1WAF
201 (M-Stationen)
The housing itself consists of a painted steel Fig. 2 . Prefabricated ”container”-type substa-
frame with insulated walls and roof. The wall tion installed in a metal processing industry.
cladding may be sheet steel, concrete or hard
pressed reinforced fibre glass with a surface
cover of crushed natural stone.
The substation can accommodate optional
equipment such as:

• Medium voltage indoor switchgear 12-36 kV


• Low voltage indoor switchgear
• Distribution power transformers
• Auxiliary transformers
• Auxiliary AC and DC supply from batteries
• Forced ventilation
Relay and control equipment
• Substation heatingorandairlighting
conditioning

Different layouts may be accomplished almost Fig. 3. Layout of a substation consisting of four
without any limitation of the possible combina- interconnected container modules. Medium vol-
tions of the above equipment. This means that t-age switchgear (1), transformers (2), low volt-
these prefabricated units may be placed both age switchgear (3) and supervisory control (4).
outdoors and indoors in industrial environments.
Particularly in dusty or dirty atmospheres, the
overpressure ventilation or purging will prevent
harmful particles or gas entering the substation Unit substations
and interfering with sensitive relay or control The ”unit” concept for substations was con-
equipment. This is an interesting alternative to ceived of during the enormous industrial ex-
the conventional way of arranging substations pansion that took place in the U.S.A. during and
in permanently built rooms for this purpose, after the Second World War. In order to reduce
with the added work of co-ordinating the design engineering work, standardise manufacturing
between many different disciplines. and simplify erection, the transformer and as-

140

5.10 140 97-03-05, 13.59


INDUSTRIAL POWER SYSTEM
Prefabricated and mobile substations

sociated primary and secondary switchgear were


adapted to each other in such a manner that they
• Insiteremote areas where the cost of sending
personnel is high and where it is difficult
could be bolted together into a single unit. Most to accommodate them.
often the substation was enclosed in such a
manner that it was installed in factory environ-
• Inconditions
areas with difficult terrain and/or climatic

ments without a separate room being required.


This concept was both cost- and space-saving,
• Where a relocation or extension of the sta-
tion may be necessary in future.
introducing the so-called ”load centre” princi-
ple, where the substation was located more or
• Inrequired
an emergency where a new station is
with short notice due to, say, the
less in the centre of a heavy electrical load area. total failure of an old station.
Since the transformer was manufactured with
a bolt-on facility on the primary and secondary
• With standard building modules, design costs
are reduced
side, it became a special transformer, only to be
used in the context of a unit substation. This
• High quality is achieved due to good factory
working conditions, skilled and experienced
concept of the ”unit” substation was not widely personnel and effective quality control
accepted in other parts of the world until many • Easy transport and handling
years later.
Today there are not such large differences
• Co-ordinated and minimised design, trans-
port, civil works, erection and electrical com-
around the world;in the way indoor substation missioning
equipment are arranged; however, European
units more often use cables instead of buswork
• With only one supplier responsible for the
entire substation, co-ordination between sub-
to connect between switchgear and transformer. suppliers is eliminated

Main or primary substations Modular substation buildings


Primary or main industrial substations may be (docking type)
wholly or partly owned by the electric power The concept of prefabricated or modular sub-
company supplying the industrial plant. This is stations is easily extended from the smaller
due to the need of the power company to switch secondary substations to the larger main or
in the high voltage network, in which the indus- primary substations. Concrete or steel enclosed
trial substation may be located in a strategic factory-assembled substation buildings have
position. In some cases the industrial customer been in use in Europe and elsewhere for many
may locate his metering on the low side of the years. A range of substations has been devel-
transformer if there is more than one consumer oped where the prominent features have been
connected to the substation low side. If the simplicity and flexibility. Simplicity is impor-
plant is located at the end of transmission line(s) tant not only to reduce costs, but also because
and no other customers in the future are likely trained operating and maintenance personnel
to connect to the substation, the industrial plant may be scarce in the country of application.
may also own the transformer and high side Flexibility means that different electrical safety
switchgear, which usually results in a better codes and standards must be met without in-
tariff contract. creased costs. Dimensions are kept within the
Due to a restrictive economic climate, both transport limitations by overland truck and as-
electric power and industrial companies may suming that local hoisting facilities are gener-
have reduced their engineering capacity due to ally available.
high personnel costs, and at the same time may Other requirements are: mechanical strength,
need to reduce the total cost for putting a corrosion resistance, personnel safety, aesthetic
substation into commercial operation. The fol- appearance.
lowing are some advantages of modular, fac- The building module consists of a steel frame
tory-assembled substations and buildings in with insulated roof and walls. The walls can
general, pointing out where they may be par- consist of:
ticularly useful:

141

5.10 141 97-03-05, 13.59


INDUSTRIAL POWER SYSTEM
Prefabricated and mobile substations

• Fibre-glass-reinforced polyester panels with


insulation and steel plate inside, or
• Plastic-covered painted steel panels with
insulation and steel plate inside
The advantage of factory assembly versus site
assembly is basically the same as for smaller
units and can be summarised as follows:
1. Less co-ordination at site
2. Integrated civil and electrical engineering
3. Equipment protected against weather and Fig. 4b. Layout of the 4 modules showing
theft during transport and at site switchgear room to the right (2 modules), con-
4. Less application and installation costs trol room (1 module) and pantry/WC in the left
5. Short completion time module.
6. Routine testing at the factory before delivery
7. Minimum of civil work.
A large substation or switchgear building is Integral transformer substation
divided into modules after the substation and By combining a modular building as described
the building layout (according to certain guide- in the above section with conventional outdoor
lines) have been designed electrically and me- equipment mounted directly on the power trans-
chanically. Each module is pre-fabricated and former, an ”integral” transformer substation
pre-assembled in the workshop before ship- (ITS) becomes a unique design compared with
ment. The range of electrical equipment that a conventional substation.
can be erected in this building is similar to that The cable between the transformer and the
described for medium-sized substations. Each medium voltage switchgear can be provided
module is made of concrete and has a cable with either dead break elbow connectors at both
trench under a fireproof false floor. The mod- ends (for fast disconnection) or with conven-
ules are fitted to each other at site using a tional cable terminations.
mobile crane, and afterwards all cables, busbars
and other equipment are installed exactly as
they were before being disconnected before •areasTherequiring
ITS concept is ideal for small allotted
less civil work and less space
shipment. This design requires no concrete for high voltage switchgear, this being erected
foundation, with civil work reduced to a com- either on top of the power transformer or, on the
pacted and drained ground area. The modules substation building
can be used for different purposes for housing
switchgear, control, battery banks, workshop
and office. Complete assemblies with a floor • The factory-assembled building unit is ready
for immediate hook-up of outgoing cables.
area of 150-200 m2 are not uncommon.
• Minimum of erection work at site
• The time span between site delivery and
commercial operation is much shorter than
for conventional substations
• Conventional high voltage apparatus and
indoor switchgear are used

Civil work is limited to:


• Site clearing and levelling
• building supports.
Concrete plinths for power transformer and
Alternatively, skid mount-
Fig. 4a. Site assembly of a 4-module substation ing eliminates plinth requirements.
building with 10 kV switchgear in a double- • Security fencing
bus, front-to-front arrangement. • Earth grid or rods
142

5.10 142 97-03-05, 14.00


INDUSTRIAL POWER SYSTEM
Prefabricated and mobile substations

Common designs are: Each substation has the following features:


One or two transformers each fed from separate
high voltage line circuits. • Designed to meet current demand
Any busbar system can be supplied
Provisions for future busbar arrangements can
• Easily extendible or may be removed and
replaced by a conventional type substation
be made at the design stage when justified by demand.
Flexibility in cable connection between trans-
former with switchgear and the substation al-
• Easy circuit identification as all equipment
is mounted on its associated power trans-
low for considerable ground movement, i.e., former.
clay soil conditions, without detrimental effect
on the equipment.
• Maintenance easily and safely performed.
Disruption of supply may occur unless two
incoming feeds to the medium voltage
switchgear are available.

• Primary voltage 36-145 kV


• Secondary voltage 10-36 kV
• Transformer rating 5-40 MVA

SF6 compact substation


Another compact concept for the primary side
of a main industrial substation is to use SF6
switchgear inside a modular or custom-built
building.
Owing to the compact cubicle shape and the
light weight of SF6 equipment, there is no need
for an overhead crane in the building. A low
building profile of 3.5 m height using 72 kV
switchgear may be achieved due to the absence
of any overhead crane. This is shown in Fig. 6.
Future extension of the substation may be
carried out by providing the addition of a 72 kV
Fig. 5. Example of an 86 kV portal switchgear feeder at either end of the switchboard.
arrangement for two incoming lines and single Although the building layout shows a cable
busbar. The transformer and distribution unit basement, this may not be really necessary, as
are here located at the end of the portal arrange- the HV terminations are at a suitable height
ment. The single-line diagram also shows from above the floor.
right to left: receiving unit, transformer unit This type of substation arrangement is typi-
and distribution unit making up a complete cal of requirements in industrial zones.
substation. Although the 72.5 kV switchgear is shown
located in a separate room, it could also be
placed together with the 11 kV switchgear.
The installation work at site is reduced: Omission of a full cable basement economises
on building costs, but makes cable repair or
• All complex items are prewired and factory-
tested prior to shipment
reinstallation more difficult. In such a case the
72.5 kV cables are brought in at floor level and
• AErection
minimum of specialist staff is required the 11 kV cables are run in a shallow trench.
• tion of equipment
time is reduced due to the elimina-
support structures.
Except for the transformer concrete box, all
rooms in the building have a ceiling clearance
• Secondary earthing and earthing quantities
are considerably reduced.
of only 3.5 m, resulting in a low building profile
and lower costs.

143

5.10 143 97-03-05, 14.00


INDUSTRIAL POWER SYSTEM
Prefabricated and mobile substations

A feeder outage, or even worse the outage of a


whole substation, can lead to blackouts with
very serious economic consequences.
In order to maintain acceptable service it is
often necessary to install standby feeders in each
substation. Such an arrangement may be too
heavy a financial burden and instead it may be
possible to bring in to the site a strategically
located emergency mobile substation. This may
be an interesting alternative for both industrial
plants and power companies. Shared ownership
could also be a viable solution, with some agreed
contract of user priority in case of failure.
A mobile substation may contain a combina-
tion of the following equipment:

• High voltage switchgear


• Transformer
• Medium voltage feeder switchgear
• Trailer or semi-trailer
Relay and control equipment

Depending on the configuration of the incom-
ing line, the primary and secondary voltage, the
number of medium voltage cubicles involved
and the size of the transformer unit, the substa-
tion may consist of one or several trailers.

Fig. 6. Layout of a 72.5 kV SF6/ 11/0.4 kV load


centre substation.
1. Transformer
2. Auxiliary transformer
3. 72.5 kV switchgear
4. 11 kV switchgear
5. LV distribution board Fig. 7. Mobile substation 84/13.8 kV (??)
6. Battery room mounted on a single trailer.
7. Mess room
8. W.C.

Mobile substations The outdoor line receiver switchgear can be up


Interruptions in electric supply, no matter how to 132 kV and indoor up to 36 kV. Medium
short, are a menace to industrial plants which voltage feeder switchgear can be either for
then experience a total shutdown and lost pro- indoor or outdoor use. Switchgear for indoor
duction, unless some reserve feeder or substa- use, relay and control equipment are built into
tion from an alternative source of supply is cubicles or small prefabricated kiosks with
available. insulated roof and walls.

144

5.10 144 97-03-05, 14.01


INDUSTRIAL POWER SYSTEM
Prefabricated and mobile substations

The total weight and overall dimensions finally These factors result in considerable overall
depend on local traffic regulations in each coun- savings for the mobile solution.
try, but a weight of 50 tonnes and a length of 17 Erection and commissioning costs are also
metres are not unusual. much lower for the mobile plant, since the
The limits in power output and voltage level mobile substation is entirely factory-assem-
installed on a single trailer are determined bled and pre-tested.
mainly by the maximum dimensions and the
maximum load per axle imposed by the local Semi-trailer substation
traffic rules. These limitations do not vary In this case the substation equipment is in-
much from one country to another. stalled on a platform coupled to front and rear
The following are some typical industrial with removable rubber-tyre supports for carry-
applications where the advantages of mobile ing the unit to the various sites.
substations are useful: Raising and lowering the platform to the
• In the initial stages of production of a new
plant, the power company may not yet have
ground is performed by a hydraulic system.
Connecting and releasing the support of the
completed its final supply with acceptable platform is a quick and simple operation, in-
reliability. The availability of electric power volving the connecting couplings between sup-
may be substantially increased by using one ports and platform only.
or more mobile substations during this first
period. The main advantages offered by this solution
• In order to maintain acceptable power avail- are:
ability, it is often necessary to install standby
feeders in substations. Such permanent ar-
• a single set of rubber-tyre supports for
several substations
rangements are very costly. A technically
and economically attractive alternative is to
• the rubber-tyre supports can be stored sepa-
rately, away from the influence of sun, sand-
locate one or several emergency mobile sub- storms, etc., when the substations is in serv-
stations which can be brought to site at short ice in tropical or desert areas
notice.
• Earthquakes, landslides and other natural
catastrophes are typical events when inter-
Trailer substation
Selection of the most appropriate trailer is de-
ruption in electricity supply may occur, and termined by the total weight and size of the
which in some countries it may be useful to equipment and the length of the whole plant.
safeguard against. The heaviest substations (over 40 tonnes and
• Temporary power supply to construction
sites, oil drilling fields, mines, construction
over 15 m long) are most conveniently installed
on trailers because of:
camps, etc. better weight distribution and axle loading
the possibility of using steerable wheels at the
Economic advantages rear to permit travel on roads with sharp bends
The overall cost of a mobile substation is usu- by using a large number of wheels, substations
ally lower than the installed cost of a similar, of considerable weight and length will give a
conventionally built substation. lighter weight distribution on soft roads.
For road trailers consisting of a main plat-
form carried at both ends by removable rubber- Skid-mounted substation
tyre supports, a single set of axles and wheels is A special application of a mobile substation is
sufficient for several mobile units, and thus the skid-mounted unit. Fig. 8 shows an example
total cost may be further reduced. of a fully equipped unit for tropical environ-
The cost of the equipment is the same for ments. Skid-mounted substations are particu-
both mobile and conventional arrangements. larly suitable for movable applications in quar-
However, the cost of the platform itself is less rying and open-cast mining.
than that of the supporting structures and foun- The fully enclosed robust sheet steel super-
dations of a permanently built substation, and structure is divided into different compartments,
the plot area required is also greatly reduced. mounted on a solid foundation raft. The rigid

145

5.10 145 97-03-05, 14.01


INDUSTRIAL POWER SYSTEM
Prefabricated and mobile substations

raft enables the unit to be easily repositioned,


either by crane or by means of towing gear or
tractor. The unit may be erected outdoors on
practically any suitable surface without special
foundations. Owing to the size of the raft, the
specific load-carrying capacity of the support-
ing ground need not be particularly high. The
factory-assembled unit contains all electrical
equipment required and it is ready for hook-up.
A special elevated roof protects against sun-
light and prevents overheating in tropical areas.
Incoming and outgoing cable transits are sealed
against vermin, dust, etc.

Fig. 8. Skid-mounted substation fully equipped


for tropical mining environments.

146

5.10 146 97-03-05, 14.01


INDUSTRIAL POWER SYSTEM
Prefabricated and mobile substations

Bibliography

[ABBDSI1316 87E] Switchgear Manual, 8th Edition, Mannheim 1987, ISBN 3-590-
80841-1

[Laz80] Irwin Lazlar. Electrical Systems Analysis and Design for Industrial
Plants, McGraw-Hill , New York 1980, ISBN 0-07-036789-2

[IEEE 141] Electric Power Distribution for Industrial Plants IEEE Red Book - 1986

[IEEE 242] Protection & Coordination of Industrial and Commercial Power Systems
IEEE Buff Book - 1986

[IEEE 739] Energy Conservation and Cost-Effective Planning in Industrial Fascilities


IEEE Bronze Book - 1984

[IEEE 241] Electric Power Systems in Commercial Buildings IEEE Gray Book - 1983

[IEEE 142] Grounding Industrial and Commercial Power Systems


IEEE Green Book - 1982

[IEEE 399] Industrial and Commercial Power System Analysis IEEE Brown
Book -1980

[IEEE 493] Design of Reliable Industrial and Commercial Power Systems IEEE Gold
Book - 1980

[IEEE 446] Emergency and Standby Power for Industrial and Commercial
Applications IEEE Orange Book - 1980

147

5.11 147 97-03-05, 14.02


BOOK No 11
Version 0

Power Systems
for Industry

ABB Transmission and Distribution Management Ltd BU TS / Global LEC Support


BA THS / BU Transmission Systems and Substations C/o ABB Switchgear AB
P. O. Box 8131 SE - 721 58 Västerås
CH - 8050 Zürich Sweden
Switzerland

ReklamCenter AB (99311) Printed in Sweden, ABB Support 1999-06

You might also like