Thesis 
Proposal
Analysis of Construction Labour Productivity

Proposed by: Dakshesh Patel 
                             UC 2406 
Thesis Proposal 
Analysis of Construction Labour Productivity 

Analysis of Construction Labour Productivity 

Introduction   
India is the second fastest growing economy in the  world today, with extensive progress in all the 
sectors. The construction sector in India is essential in the overall economic growth of the country. 
Understanding changes in construction productivity, or site output, cannot be achieved without site 
information.  This  information  should  relate  both  to  the  calculation  of  productivity  and  to  the  site 
environment  in  which  the  productivity  has  been  achieved.  Explaining  the  variability  in  site  data 
requires  an  understanding  and  quantification  of  the  major  factors  that  affect  labour  output. 
Construction productivity is depending on labour productivity. Labour productivity is a major part of 
project scheduling and project duration.   

Need of the study   
Project  planning  requires  labour  productivity  constant,  and  it  is  different  for  every  region.  For 
Ahmedabad  region,  to  derive  labour  constant  is  required.  It  will  help  in  project  planning,  labour 
requirement. 

Objective of study   
The main objective of this thesis is to analyze construction labour productivity considering influential 
factors in individual situations. The primary purpose of this thesis is to analyze productivity of labour 
coming from different parts of India and their work expertise. An attempt would be made to enable 
project  planning  processes  selecting  appropriate  construction  labour  teams  for  different  activities 
considering their expertise and productivity to achieve quality and cost objectives of the project. 

Scope of study   
The  study  covers  framed  structure  building  constructions  in  and  around  Ahmedabad.  Site  labour 
productivity  was  investigated  for  major  four  activities  Concreting,  Reinforcement,  Formwork  and 
Brickwork for framed structure buildings. 

Parameters to be analyzed ‐ 
 Labour characteristics (Origin, Age, Experience, Training, Wages) 
 Activity characteristics (Tools, Pre construction preparations, Quality requirements) 
 Site characteristics (Labour colony, Safety, Water/electricity, Quality control) 

Methodology   
 
Literature Review: Literature review will be done from the following: 
a. Textbooks 
 Practical Information for Quantity Surveyors, by P T Joglekar. 
 Labour Productivity in Indian Industry, by M. K. Singh. 

Faculty of Technology, CEPT University    Page | 1  
 
Thesis Proposal 
Analysis of Construction Labour Productivity 

 Labour productivity: socio‐economic dimensions, by J. P. Srivastava. 
b. Journals, magazines, internet. 
 
Data  Collection:  Data  will  be  collected  through  case  studies  identified  where  different  region 
labours are working. Work and productivity measured in formats. 
 

Data  Analysis:  Analysis  will  focus  on  deriving  labour  constant  for  different  activities  in 
Ahmedabad region and also focus on which region labour is suitable for particular activity. 

Conclusion & Recommendation: After analysis of labour productivity at the areas under study, 
the constants drawn from it will be presented. 
 

Preparation  of  Thesis  Document:  Thesis  report  will  be  generated  as  per  academic 
requirements of CEPT University. 

Schedule of Methodology   
 

 Literature Review  : 4 weeks  
 Data Collection  : 5 weeks  
 Data Analysis  : 5 weeks  
 Preparation of Thesis Document  : 4 weeks  
Total Duration  : 18 weeks 
 