Floor plates and beam structures with simple pedestals, recommended stop cast placement not
on the middle of the span, with minimum shear force conditions and maximum moments.
The placement of the cast stop on the floor plate and the continuous beam which is a suspended
structure system, recommended to be placed in 1/3 or 1/4 span (pedestal area).
Treatment of Casting connection
The casting of the casting shall be treated well, to ensure adequate friction and friction
resistance so that the structure can generally be expressed as a unified structure.
- Chipping the surface of the casting joints so that the rough aggregates are visible, to ensure
good attachment and friction with the concrete to be cast later.
- Clean the surface of the casting joints from dust and loose particles.
- Use a good bonding agent as per the instructions in the technical brochure.