INNOVATIVE TYRES, HALOL, GUJARAT – UTILITY SCALE SOLAR PV POWER PLANT

+91 8116401052
LOCATION MAP VICINITY MAP GENERAL NOTES

1. THE CONTRACTOR SHALL OBTAIN ALL NECESSARY


PERMITS AND APPROVALS PRIOR TO STARTING ANY WORK.

2. EXISTING UTILITIES SHALL REMAIN IN SERVICE AND IN


PLACE UNLESS NOTED OTHERWISE. INTERRUPTION OF

1MW CAPTIVE SOLAR PV


SERVICE SHALL BE KEPT TO A MINIMUM ANDONLY WITH

INNOVATIVE TYRES –
THE APPROVAL OF THE ENGINEER AND CONTRACTING

HALOL, GUJARAT, INDIA


POWER PLANT
OFFICER.

3. WORK SHALL BE PERFORMED IN ACCORDANCE WITH

PROJECT TITLE:
APPLICABLE OSHA REGULATIONS.

4. CONTRACTOR TO VERIFY AND CHECK THE DIMENSIONS


AND DETAIL PRIOR TO THE START OF CONSTRUCTION. ANY
DISCREPANCY SHALL BE IMMEDIATELY REPORTED TO THE
ENGINEER FOR CLARIFICATIONANBD RESOLUTION.

5. CONTRACTOR SHALL EXERCISE DUE CARE AND DILIGENCE


TO AVOID DAMAGE TO EXISTING UTILITIES, STRUCTURES OR
OTHER SITE IMPROVEMENTS NOT DESIGNATED TO BE
REMOVED OR MODIFIED. ANY DAMAGE TO EXISTING

SHEET TITLE:
IMPROVEMENTS NOT DESIGNATED TO BE REMOVED OR

TITLE SHEET
MODIFIED SHALL BE RESTORED TO THEIR ORIGINAL
CONDITION OR BETTER.

NORMALIZED PRODUCTION PER INSTALLED kWp


(1000kWdc NOMINAL POWER) DRAWING INDEX ABBREVIATION Engineer:
I hereby certify that this drawing was prepared
by me or under my supervision
SHEET NO. DWG NO. DESCRIPTION
1 OF 09 T100 TITLE SHEET
Date Issue

2 OF 09 G101 GENERAL NOTES


Date Marks Revisions
3 OF 09 S101 SITE LAYOUT

4 OF 09 E101 POWER ONE-LINE DIAGRAM (1)


DESIGNED BY
kWh/kWp/day

DRAWN BY:
5 OF 09 E102 POWER ONE-LINE DIAGRAM (2)
CHECKED BY:
SUPERVISED BY:
6 OF 09 E103 POWER ONE-LINE DIAGRAM (3)

7 OF 09 D101 SPV MODULE DATASHEET


Drawing Number

8 OF 09 D102 SOLAR INVERTER DATASHEET T100


9 OF 09 L100 ELECTRICAL LABELS
Scale: Date:
AS SHOWN 02/06/2016
MONTHS Sheet No.

01 OF 09
GENERAL NOTES

omssconsulting@gmail.com
OM SAI SOLAR

BURDWAN, WB, INDIA


CONSULTING

+91 8116401052
GENERAL NOTES:
1.DO NOT SCALE DRAWINGS, IF UNABLE TO LOCATE DIMENSIONS FOR ANY ITEM OF WORK, CONSULT ARCHITECT/
ENGINEER FOR DIRECTIONS BEFORE PROCEEDING.

2.IN THE ABSENCE OF THE EXACT ROOF DIMENSIONS, THE DRAWING WILL BASED ON GOOGLE MAP, THEREFORE THESE
MAY NOT BE ACCURATE. CONTRACTOR ON SITE TO VERIFY ALL OBSTACLES ON THE ROOF AND ENSURE ALL REQUIRED
CLEARENCES WITH AUTHORITY HAVING JURISDICTION(S) PRIOR TO INSTALLATION, ORDERING MATERIAL OR
FABRICATION

3. CONTRACTOR SHALL OBTAIN ELECTRICAL AND OTHER PERMITS PRIOR TO INSTALLATION AND SHALL COORDINATE ALL
INSPECTIONS BY THE CITY INSPECTORS, TESTING/ COMMISSIONING BY THE UTILITY CO. AND ACCEPTANCE BY THE
CLIENT , AS NEEDED.

4.ROUTING OR RACEWAYS MATERIAL SHALL BE AT THE OPTION OF THE CONTRACTOR, WITHIN THE CODE, UNLESS
OTHERWISE NOTED AND SHALL BE COORDINATED WITH OTHER TRADES.

5. IF THE ROOF MATERIAL OR ROOF STRUCTURE IS NOT ADEQUATE FOR PV INSTALLATION, CALL ENGINEER PRIOR TO
INSATLL. THE CONTRACTOR IS RESPONSIBLE TO VERIFY THAT ROOF IS CAPABLE OF WITHSTANDING THE EXTRA WEIGHT.

6.WHENEVER A DISCREPANCY IN QUANTITY OF EQUIPMENT ARISES ON THE DRAWING OR SPECIFICATIONS, THE


CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING AND INSTALLING ALL MATERIAL AND SERVICES REQUIRED BY
STRICTEST CONDITIONS NOTED ON THE DRAWING OR IN THE SPECIFICATIONS TO ENSURE COMPLETE COMPLIANCE AND
LONGEVITY OF THE OPERABLE SYSTEM REQUIRED BY THE ARCHITECT/ENGINEER

7.THIS DESIGN IS FULLY BASED ON THE INFORMATION PROVIDED BY THE DEVELOPER, ANY MODIFICATIONS OR REMOVAL
OF THE LOGO OF THE EPC; "VARIETAS PROJECT MANAGERS & ENGINEERS" IS NOT ALLOWED AND WILL RENDER THIS
DESIGN VOID.

8.THE WORKING CLEARANCE AROUND THE EXISTING ELECTRICAL EQUIPMENTS AS WELL AS THE NEW ELECTRICAL
EQUIPMENT WILL BE MAINTAINED IN ACCORDANCE WITH.

SOLAR PV POWER SYSTEM


9. ADEQUATE SPACING MUST BE MAINTAINED BETWEEN ANY PLUMBING/ SEWER VENTS EXTENDING THROUGH THE ROOF
AND UNDERSIDE OF THE PHOTOVOLTAIC PANELS (6'' MINIMUM RECOMMENDED).

1MW GRID CONNECTED


INNOVATIVE TYRES –
ELECTRICAL NOTES AND STANDARDS TO FOLLOW:
IEC 60050V (826) ELECTRICAL INSTALLATIONS OF BUILDINGS

HALOL, GUJARAT, INDIA


IEC 60068 ENVIRONMENTAL TESTING

IEC 60364-7-712 REQUIREMENTS FOR SPECIAL INSTALLATIONS OR LOCATIONS – SOLAR PHOTOVOLTAIC (PV) POWER SUPPLY SYSTEMS

PROJECT TITLE:
IEC 60439-1 LOW VOLTAGE SWITCHGEAR & CONTROL GEAR ASSEMBLIES

IEC 60755 GENERAL REQUIREMENTS FOR RESIDUAL CURRENT – OPERATED PROTECTIVE DEVICES (OCPD)

IEC 61215 CRYSTALLINE SILICON TERRESTIAL PHOTOVOLTAIC (PV) MODULES – DESIGN QUALIFICATION AND TYPE APPROVAL

IEC 61683 EFFICIENCY MEASUREMENTS AND ENVIRONMENTAL TESTS OF POWER CONDITIONING UNITS (PCUs)

IEC 61701 PV MODULES TO BE USED IN A HIGHLY CORROSIVE ATMOSPHERE

IEC 61724 PHOTOVOLTAIC SYSTEM PERFORMANCE MONITORING – GUIDELINES FOR MEASUREMENT, DATA EXCHANGE AND ANALYSIS

IEC 61730 PART-2 : REQUIREMENTS FOR CONSTRUCTION & PART-2: REQUIREMENTS FOR TESTING, FOR SAFETY QUALIFICATION

IEC 62305 LIGHTING PROTECTION

IEC 62446 GRID CONNECTED PHOTOVOLTAIC SYSTEMS – MINIMUM REQUIREMENTS FOR SYSYTEM DOCUMENTATION, COMMISSIONING TESTS AND INSPECTION

IEC 62548 PHOTOVOLTAIC ARRAYS – DESIGN REQUIREMENTS

IEC 62109-1:2010 SAFETY OF POWER CONVERTERS FOR USE IN PHOTOVOLTAIC POWER SYSTEMS

IEC 62116 UTILITY-INTERCONNECTED PHOTOVOLTAIC INVERTERS – TEST PROCEDURE OF ISLANDING PREVENTION MEASURES

IEC 61727 PHOTOVOLTAIC SYSTEMS -CHARACTERISTICS OF THE UTILITY INTERFACES

IEC 61000 ELECTROMAGNETIC COMPATIBILITY (EMC)

IEC 62305 LIGHTNING PROTECTION STANDARD

IEC 61643-11 LOW VOLTAGE SURGE PROTECTIVE DEVICES – REQUIREMNETS & TESTS FOR SPDs IN PHOTOVOLTAIC APPLICATIONS

GENERAL NOTES
SHEET TITLE:
TUV 2 PfG 1169 TUV INTERNAL CABLE STANDARD

ELECTRICAL
AS1319 SAFETY SIGNS FOR THE OCCUPATIONAL ENVIRONMENT

APPLICABLE JUNCTION BOX

STANDARDS CREEPAGE DISTANCES AND CLEARANCES

IEC 60664 JUNTION BOXES

IEC 50548 DEGREES OF PROTECTION PROVIDED BY THE ENCLOSURES

IEC 60529 LOW VOLTAGE FUSES

IEC 60269 COPPER BUS BARS /TERMINAL BLOCKS HOUSED IN THE JUNCTION BOX WITH SUITABLE TERMINATION THREADS

IEC 62208 CHROMATED DIN RAIL

EN 60715

APPLICABLE SWITCHBOARD

STANDARDS
IEC 60439
LOW VOLTAGE AC SWITCHGEAR AND CONTROL GEARS SPECIFICATIONS

LOW VOLTAGE AC SWITCHGEAR AND CONTROL GEARS ASSEMBLIES


Engineer:
ICE 60947
IEC GENERAL REQUIREMENTS FOR AC SWITCHGEAR & CONTROL GEAR VOLTAGE <1000V I hereby certify that this drawing was prepared
IEC 60529 DEGREE OF PROTECTION FOR LOW VOLTAGE SWITCHGEAR & CONTROL ENCLOSURES by me or under my supervision
IEC 60404 ELECTROLYTIC COPPER / ALUMINIUM

IEC 62056 AC ELECTRIC METERS

IEC 60364 EARTHING


Date Issue
IEC 60947.2 DANGER NOTIC PALTES

IEC 60439 CIRCUIT BREAKERS VOLTAGE UP TO 1000V

IEC EN 60269-1 AIR BREAK SWITCHES/DISCOONECTS FOR VOLTAGES < 1000VAC & 1200VDC Date Marks Revisions
IEC 60529 MAKING AND ARRANGEMENTS FOR SWITCHGGEAR, BUS BARS, MAIN CONNECTIONS

APPLICABLE STANDARDS FOR LOW

VOLTAGE AC CABLES XLPE INSULATED PVC SHEATHED CABLES FOR WORKING VOLTAGES <1100V

IEC 60840 RECOMMENDED CABLE CURRENT RATINGS

IEC 60502 CONDUCTORS FOR INSULATED CABLES DESIGNED BY


IEC 60227, 60228 DRAWN BY:
APPLICABLE
SP 30 LOCAL STANDARDS NATIONAL ELECTRICAL CODES
CHECKED BY:
IS 875 WIND LOADS ON BUILDINGS AND STRUCTURES

IS 2062: 1992 THE MOUNTING STRUCTURE STEEL


SUPERVISED BY:
IS 2309 PROTECTION OF BUILDINGS AND ALLIED STRUCTURES AGAINST LIGHTING

IS 3043 – 1987 EACH ARRAY STRUCTUTRE OF THE PV YARD

IS 4759 GALVANIZATION OF THE MOUNTING STRUCTURE


Drawing Number

G101
Scale: Date:
AS SHOWN 02/06/2016
Sheet No.

02 OF 09
POWER ONE-LINE DIAGRAM
PV TO STRINGS

omssconsulting@gmail.com
OM SAI SOLAR

BURDWAN, WB, INDIA


CONSULTING

+91 8116401052
STRING #G1, 20 MODULES
6 sq.mm PV WIRE

SOLAR PV POWER SYSTEM


1MW GRID CONNECTED
6 sq.mm PV WIRE

INNOVATIVE TYRES –
+ 1 + + + +
- - - - -

HALOL, GUJARAT, INDIA


6 sq.mm

PROJECT TITLE:
BARE COPPER
RAIL GROUNDING WIRE
....
GROUNDING LUG
-

6 + +
- - - - -

POWER ONE-LINE
RAIL
....

DIAGRAM
PV to STRINGS
SHEET TITLE:
GROUNDING LUG
-

+ 11 + + + +
- - - - -
Engineer:

RAIL
.... I hereby certify that this drawing was prepared
by me or under my supervision
GROUNDING LUG
- Date Issue

16 + + 20 Date Marks Revisions


PV MODULE RATINGS @ STC
- - - - -
MODULE MFR: JINKO SOLAR
MODEL: JKM250P DESIGNED BY
VOC = 37.7V DRAWN BY:
RAIL VMP = 30.5V CHECKED BY:
.... ISC = 8.85A SUPERVISED BY:

GROUNDING LUG IMP = 8.20A


-
Drawing Number

E101
Scale: Date:
AS SHOWN 02/06/2016
THE CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING Sheet No.
THE WORK AMONG THE VARIOUS TRADES AS NECESSARY TO
AVOID CONFICTS AND TO INSURE THE INSTALLATION OF ALL
WITHIN THE AVAILABLE SPACE.
04 OF 09
POWER ONE-LINE DIAGRAM

omssconsulting@gmail.com
STRINGS TO INVERTER TO SUB-PANEL

BURDWAN, WB, INDIA


OM SAI SOLAR
CONSULTING

+91 8116401052
"INV#1" NEW PV SUB-PANEL, "SP1"
INGETEAM 24TL-U-M480 WITH BOTH DC & AC DISCONNECT 200A BUS MINUMUM, 277/480V 4W
& ARC-FUALT INTEREPTER

DC.1
STRING #A1 , 2 MODULES
+
-
+
1 - .... +
-
.... +
- 20 (n)
200A 3P
RAIL #10 AWG THWN CONDUIT
GROUNDING LUG MODULE/RACKING
EGC
L1 (n)
DC.1
AC DISC. L2
L3 1- ¼ " EMT

+
STRING #B1, 20 MODULES
+ DC DISC. N 40A/3P
1 - .... + .... + G CONDUIT
- - - 21 MPPT MPPT AC.1 40A/3P
+- +- +- +- +- +- +- +- G
1 2
RAIL 1-½" EMT
GROUNDING LUG
#10 AWG THWN
MODULE/RACKING
40A/3P
CONDUIT
DC.1
EGC 40A/3P AC.2
STRING #C1, 20 MODULES
+ + .... + .... +
114" EMT 40A/3P
- 1 - - - 21
RAIL
.... #10 AWG THWN DC.2
-
GROUNDING -
LUG MODULE/RACKING
EGC
NEU G

SOLAR PV POWER SYSTEM


DC.1

1MW GRID CONNECTED


STRING #D1, 20 MODULES

INNOVATIVE TYRES –
+ 1 -
+ .... + .... +
- - - 21
RAIL #10 AWG THWN
-
GROUNDING -
LUG MODULE/RACKING
EGC

HALOL, GUJARAT, INDIA


DC.1
STRING #E1, 20 MODULES

PROJECT TITLE:
+ 1 -
+ .... + .... +
- - - 21
RAIL #10 AWG THWN
GROUNDING LUG MODULE/RACKING CONDUIT
EGC
141" EMT
PV MODULE RATINGS @ STC
DC.2
MODULE MFR: ZINKO SOLAR
MODEL: 250Wp
"INV#2" VOC = 37.7V
INGETEAM 24TL-U-M480 WITH BOTH DC & AC DISCONNECT
& ARC-FUALT INTEREPTER VMP = 30.5V
STRING #A2, 20 MODULES ISC = 8.85A

STRINGS TO INVERTER TO SUB-PANEL


STRING #B2, 20 MODULES
IMP = 8.20A

POWER ONE-LINE
STRING #C2, 20 MODULES

STRING #D2, 20 MODULES

DIAGRAM
STRING #E2, 20 MODULES
PV INVERTER RATINGS

SHEET TITLE:
"INV#3" INVERTER MFR: INGETEAM
INGETEAM 24TL-U-M480 WITH BOTH DC & AC DISCONNECT
& ARC-FUALT INTEREPTER INVERTER MODEL: 24TL U M480
STRING #A3, 20 MODULES DC VOLT RATING = 1000V
STRING #B3, 20 MODULES OPERATING VOLTAGE =580-950V
STRING #C3, 20 MODULES
DC MAX USABLE INPUT CURRENT:
STRING #D3, 20 MODULES
STRING #E3, 20 MODULES
PER MPPT
PER INVERTER
= 27A
= 54A Engineer:
I hereby certify that this drawing was prepared
AC MAX RATED OUTPUT POWER = 24000W
by me or under my supervision
"INV#4" AC MAX OUTPUT CURRENT = 29A
INGETEAM 24TL-U-M480 WITH BOTH DC & AC DISCONNECT
& ARC-FUALT INTEREPTER
STRING #A4, 20 MODULES MIN WIRE SIZE = 29A * 125% = 36.25A Date Issue
STRING #B4, 20 MODULES
STRING #C4, 20 MODULES MIN (OCPD) = 40A, AVAILABLE (OCPD) =40A
STRING #D4, 20 MODULES Date Marks Revisions
STRING #E4, 20 MODULES

VOLTAGE CURRENT
CIRCUIT DESCRIPTION CONDUCTOR SIZE/TYPE CONDUIT SIZE*/QTY 1-WAY WIRE TRAVEL VOLTAGE DROP (%)
@MAX POWER @MAX POWER
(DC) SOLAR STRING
"INV#5" (A)
WIRING
2-CORE 6 sq.mm FA - 622 Vdc 8.53A 0.5%
DESIGNED BY
INGETEAM 24TL-U-M480 WITH BOTH DC & AC DISCONNECT (DC) STRING TO INVERTER (5
& ARC-FUALT INTEREPTER
(B)
STRINGS) (5) 2-CORE 6 sq.mm (2) 1-¼ in 350 ft 622 Vdc 2*8.53A 0.5%
DRAWN BY:
(AC) INVERTER TO
STRING #A5, 20 MODULES (C)
COMBINER BOX (5 INVERTERS) (5) 4-CORE 16 sq.mm (1) 1-¼ in 140 ft 480VAC 29A 0.80% CHECKED BY:
STRING #B5, 20 MODULES
STRING #C5, 20 MODULES (D) (AC) GEC GROUNDING (1) BARE COPPER 10mm (1) 1 in 65 ft 480VAC - - SUPERVISED BY:

STRING #D5, 20 MODULES (E) (DC) GEC GROUNDING (1) BARE COPPER 6mm (1) ½ in 450 ft 622 Vdc - -
STRING #E5, 20 MODULES

Drawing Number

E102
*Please note that the size of the conduit calculated by considering 30% Fill Factor

Scale: Date:
AS SHOWN 02/06/2016
THE CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING Sheet No.
THE WORK AMONG THE VARIOUS TRADES AS NECESSARY TO
AVOID CONFICTS AND TO INSURE THE INSTALLATION OF ALL
WITHIN THE AVAILABLE SPACE.
05 OF 09
POWER ONE-LINE DIAGRAM

omssconsulting@gmail.com
A#1, 20 SPV MODULES NEW PV SUB-PANEL, "SP1"
200A BUS MINUMUM, 277/480V 4W

OM SAI SOLAR

BURDWAN, WB, INDIA


INV#1

CONSULTING
B#1, 20 SPV MODULES

(n)
COMPLETE SOLAR PV SYSTEM

+91 8116401052
C#1, 20 SPV MODULES

200A 3P
D#1, 20 SPV MODULES
(n)

E#1, 20 SPV MODULES 40A/3P


CONDUIT
40A/3P
1-½" EMT
A#2, 20 SPV MODULES 40A/3P
40A/3P AC.2
INV#2
B#2, 20 SPV MODULES 40A/3P

C#2, 20 SPV MODULES

NEU G
D#2, 20 SPV MODULES

E#2, 20 SPV MODULES

A#3, 20 SPV MODULES

B#3, 20 SPV MODULES


INV#3
NEW 1250kVA
C#3, 20 SPV MODULES
TRANSFORMER#1
PRIMARY SECONDARY
D#3, 20 SPV MODULES
480 Wye 14kV Delta
H1 X1
E#3, 20 SPV MODULES

A#4, 20 SPV MODULES

B#4, 20 SPV MODULES


INV#4 H0

SOLAR PV POWER SYSTEM


H3 H2
X2

1MW GRID CONNECTED


C#4, 20 SPV MODULES
X3

INNOVATIVE TYRES –
AC.2
G G (n)
D#4, 20 SPV MODULES

AC.2
E#4, 20 SPV MODULES

HALOL, GUJARAT, INDIA


A#5, 20 SPV MODULES

B#5, 20 SPV MODULES


INV#5

PROJECT TITLE:
C#5, 20 SPV MODULES

D#5, 20 SPV MODULES

E#5, 20 SPV MODULES AC SIDE COMBINER BOX


“CB1”

INV#6
TOTAL STRING SIZE = 25kWp, NEW PV SUB-PANEL, "SP2"
5x20 SPV 200A BUS MINUMUM, 277/480V 4W

INPUT SIDE
200A 3P (e)
SWITCHBOARD 11000/440V 3PH LOCKABLE & 120A, 11kV FUSED AC CIRCUIT BREAKER
INV#7

M1
TOTAL STRING SIZE = 25kWp,
5x20 SPV 40A/3P 2500A BUS BAR
40A/3P

40A/3P
INV#8
TOTAL STRING SIZE = 25kWp, 40A/3P
5x20 SPV
40A/3P
CONDUIT
INV#9 OUTPUT SIDE
TOTAL STRING SIZE = 25kWp,
5x20 SPV
200A 3P
POINT OF CONNECTION
2" EMT
TOTAL STRING SIZE = 25kWp, INV#10
PER 690.64; 705.12(D)
5x20 SPV

SPLICES & TAPS PER 366.56


AUXILIARY AC.3

POWER LINE
(3) POLARIS STACKED GUTTER
INV#11 CONNECTORS IPLDS

DIAGRAM
TOTAL STRING SIZE = 25kWp, NEW PV SUB-PANEL, "SP3"
5x20 SPV 200A BUS MINUMUM, 277/480V 4W

INPUT SIDE

SHEET TITLE:
INV#12
TOTAL STRING SIZE = 25kWp,
5x20 SPV 40A/3P

40A/3P

40A/3P
INV#13
TOTAL STRING SIZE = 25kWp, 40A/3P
5x20 SPV
40A/3P

N
OUTPUT SIDE G
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#14
LOADS
200A 3P

TOTAL STRING SIZE = 25kWp,


5x20 SPV
INV#15
G NEU
INV#16
TOTAL STRING SIZE = 25kWp, NEW PV SUB-PANEL, "SP4"
5x20 SPV 200A BUS MINUMUM, 277/480V 4W

INPUT SIDE
Engineer:
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#17
40A/3P
3/4"
40A/3P
C-1#4
40A/3P
INV#18
TOTAL STRING SIZE = 25kWp, 40A/3P
5x20 SPV
40A/3P
G G
INV#19 OUTPUT SIDE
(e) I hereby certify that this drawing was prepared
TOTAL STRING SIZE = 25kWp,
5x20 SPV GROUND RODS 6'-0" by me or under my supervision
200A 3P
(2) 3/4" x 10'
TOTAL STRING SIZE = 25kWp, INV#20 APART TYPICAL Date Issue
5x20 SPV

INV#21
TOTAL STRING SIZE = 25kWp,
5x20 SPV
NEW PV SUB-PANEL, "SP5"
200A BUS MINUMUM, 277/480V 4W
Date Marks Revisions
INPUT SIDE
INV#22
TOTAL STRING SIZE = 25kWp,
5x20 SPV 40A/3P

40A/3P INV#31
TOTAL STRING SIZE = 25kWp, NEW PV SUB-PANEL, "SP7"
40A/3P 5x20 SPV 200A BUS MINUMUM, 277/480V 4W
INV#23
TOTAL STRING SIZE = 25kWp, 40A/3P
5x20 SPV INPUT SIDE
40A/3P

INV#32
DESIGNED BY
TOTAL STRING SIZE = 25kWp,
INV#24 OUTPUT SIDE 5x20 SPV 40A/3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
200A 3P
40A/3P DRAWN BY:
40A/3P
INV#33
TOTAL STRING SIZE = 25kWp, 40A/3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#25 5x20 SPV
40A/3P CHECKED BY:
TOTAL STRING SIZE = 25kWp,
INV#34 OUTPUT SIDE SUPERVISED BY:
5x20 SPV
200A 3P

TOTAL STRING SIZE = 25kWp,


5x20 SPV
INV#26
NEW PV SUB-PANEL, "SP6"
200A BUS MINUMUM, 277/480V 4W
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#35 ARRAY CONFIGURATION
TOTAL STRING SIZE = 25kWp,
INV#27
INPUT SIDE

INV#36
No. of Inverters:40 Drawing Number
TOTAL STRING SIZE = 25kWp, NEW PV SUB-PANEL, "SP8"

Strings Per Inverter: 5


5x20 SPV 40A/3P
5x20 SPV 200A BUS MINUMUM, 277/480V 4W

E103
40A/3P

40A/3P INPUT SIDE


INV#28

SPV Modules per String: 20


TOTAL STRING SIZE = 25kWp, 40A/3P
5x20 SPV INV#37
TOTAL STRING SIZE = 25kWp,
40A/3P
5x20 SPV 40A/3P

40A/3P
INV#29 OUTPUT SIDE
TOTAL STRING SIZE = 25kWp,
5x20 SPV
200A 3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#38
40A/3P

40A/3P

40A/3P
String Vmpp @STC: 615Vdc
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#30
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#39 OUTPUT SIDE
String Impp @STC: 8.62A Scale: Date:
200A 3P

TOTAL STRING SIZE = 25kWp,


5x20 SPV
INV#40 Total Array Size: 1000kWdc AS SHOWN 02/06/2016
AC Output (@p.f=1) = 1000kVA Sheet No.

06 OF 09
SITE LAYOUT

omssconsulting@gmail.com
WITH SUGGESTED PV ARRAY LAYOUT

OM SAI SOLAR

BURDWAN, WB, INDIA


CONSULTING

+91 8116401052
SOLAR PV POWER SYSTEM
1MW GRID CONNECTED
INNOVATIVE TYRES –

HALOL, GUJARAT, INDIA


PROJECT TITLE:

SUGGESTED PV ARRAY LAYOUT


SITE LAYOUT
SHEET TITLE:
Engineer:

I hereby certify that this drawing was prepared


by me or under my supervision
Date Issue

Date Marks Revisions

DESIGNED BY

DRAWN BY:

CHECKED BY:
SUPERVISED BY:

Drawing Number

S101
Scale: Date:
AS SHOWN 02/06/2016
THE CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING Sheet No.
THE WORK AMONG THE VARIOUS TRADES AS NECESSARY TO
AVOID CONFICTS AND TO INSURE THE INSTALLATION OF ALL
WITHIN THE AVAILABLE SPACE.
03 OF 09
omssconsulting@gmail.com
BURDWAN, WB, INDIA
OM SAI SOLAR

+91 8116401052
CONSULTING
SOLAR PHOTOVOLTAIC MODULE – DATA SHEET

SOLAR PV POWER SYSTEM


1MW GRID CONNECTED
INNOVATIVE TYRES –

HALOL, GUJARAT, INDIA


PROJECT TITLE:

PHOTO VOLTAIC
DATASHEET –

MODULE
SOLAR
SHEET TITLE:
Engineer:
I hereby certify that this drawing was prepared
by me or under my supervision

Date Issue

Date Marks Revisions

DESIGNED BY

DRAWN BY:

CHECKED BY:
SUPERVISED BY:

Drawing Number

D101
Scale: Date:
AS SHOWN 02/06/2016
Sheet No.

07 OF 09
omssconsulting@gmail.com
BURDWAN, WB, INDIA
OM SAI SOLAR
SOLAR INVERTER – DATA SHEET

+91 8116401052
CONSULTING

SOLAR PV POWER SYSTEM


1MW GRID CONNECTED
INNOVATIVE TYRES –

HALOL, GUJARAT, INDIA


PROJECT TITLE:

SHEET TITLE:
SOLAR INVERTER
DATA SHEET –
Engineer:
I hereby certify that this drawing was prepared
by me or under my supervision

Date Issue

Date Marks Revisions

DESIGNED BY

DRAWN BY:

CHECKED BY:
SUPERVISED BY:

Drawing Number

D102
Scale: Date:
AS SHOWN 02/06/2016
Sheet No.

08 OF 09
omssconsulting@gmail.com
WB, INDIA

+91 8116401052
, BURDWAN
LABEL AND MARKINGS LEGEND:
SYSTEM OWNER PHOTOVOLTAIC
PROVIDES THE LOCATION OF THE SERVICE
GENERATION METER AC DISCONNECT
CAUTION
POWER TO THIS SERVICE IS ALSO
DISCONNECTING MEANS AND THE
PHOTOVOLTAIC DISCONNECTING MEANS. THIS
PLAQUE SHALL BE APPLIED TO THE MAIN
SERVICE DISCONNECTING MEANS AND THE
SUPPLIED FROM THE FOLLOWING AC DISCONNECT RATINGS: PHOTOVOLTAIC DISCONNECTING MEANS; (2
TOTAL)
SOURCES WITH DISCONNECTS OPERATING CURRENT: 1600 AMPS
FACILITY NET OPERATING VOLTAGE: 480 VOLTS AC LABEL FOR UTILITY AC DISCONNECT; 1 PER AC
LOCATED AS SHOWN DISCONNECT.
GENERATION METER MAXIMUM CURRENT: 1000 AMPS/POLE
MAXIMUM VOLTAGE: 480 VOLTS AC UTILITY AC DISCONNECT WARNING LABEL. 1
PER AC DISCONNECT AND ALL 3 AC LOAD
CENTERS.
SOLAR PHOTOVOLTAIC
ARRAYLOCATION
LOCATION OF THIS LABEL IS ON THE AC DISCONNECT PLACED UTILITY AC DISCONNECT OPERATING

MIDC, HALOL, GUJARAT, INDIA


INNOVATIVE TYRES, HALOL, GUJARAT
SPECIFICATIONS. 1 PER AC DISCONNECT SITUATED

GRID-CONNECTED SOLAR PV SYSTEM


BETWEEN COMBINER BOX AND TRANSFOMER
BETWEEN SUB-PANEL AND COMBINER BOX
LABEL FOR SYSTEM OWNER'S KWH GENERATION
METER; 1 PER OWNER METER.
! DANGER
LABEL FOR FACILITY NET GENERATION METER; 1
Arc flash and PER FACILITY GENERATION METER.
shock hazard. LABEL FOR ARC FLASH WARNING. 1 PER
Appropriate PPE ENERGIZED ENCLOSURE WITH ACCESS TO LIVE
required. PARTS.

ONE PER INVERTER. NUMBER SEQUENTIALLY

PROJECT TITLE:

1000 kWdc

SITE ADDRESS:
,

SYSTEM SIZE:
UTILITY AC DISCONNECT CONDUIT RUN FROM SOURCE CIRCUT TO
INVERTER. (AS NEEDED)

CONDUIT RUN FROM INVERTER TO POCC. (AS

PHOTOVOLTAIC
AC DISCONNECT
INV.XX NEEDED)

CAUTION LABEL

UV RESISTANT, REFLECTIVE MARKINGS


REQUIRED ON ALL INTERIOR AND EXTERIOR DC
WARNING: CONDUIT, RACEWAYS, ENCLOSURES, CABLE

LABELS
SHEET TITLE:
ELECTRIC SHOCK HAZARD, DO NOT ASSEMBLIES AND JUNCTION BOXES TO ALERT
FIRE SERVICE. MARKINGS SHALL BE PLACED
TOUCH TERMINALS. TERMINALS ON EVERY 10 FEET, AT TURNS, ADJACENT TO
PENETRATIONS, AT ALL DC COMBINER BOXES,
BOTH THE LINE AND LOAD SIDES MAY AND AT ALL DC JUNCTION BOXES. MARKING
BE ENERGIZED IN TH OPEN POSITION 1000 VOLTS DC CONTENT SHALL READ, "CAUTION: SOLAR
CIRCUIT" IN NON-BOLD ARIAL OR SIMILAR FONT
WITH 3/8" ALL CAPS WHITE LETTERING ON RED
BACKGROUND
GENERAL NOTES FOR LABELS AND
MARKINGS:
PHOTOVOLTAIC
AC DISCONNECT 208 VOLTS AC 1. LABELS AND MARKINGS SHALL BE APPLIED TO
THE APPROPRIATE COMPONENTS IN Engineer:
ACCORDANCE WITH THE NEC.
I hereby certify that this drawing was
2. SOLAR MODULES ARE SUPPLIED FROM THE prepared by me or under my supervision
AC DISCONNECT RATINGS: MANUFACTURER WITH MARKINGS PRE-APPLIED TO
MEET THE REQUIREMENTS OF THE NEC.
OPERATING CURRENT: 200 AMPS
OPERATING VOLTAGE: 480 VOLTS AC 3. NEXTRONEX AND SOLAR EDGE INVERTERS ARE
SUPPLIED FROM THE MANUFACTURER WITH THE
MAXIMUM CURRENT: 1000 AMPS/POLE APPROPRIATE LABELS AND MARKINGS TO MEET
Date Issue
THE REQUIREMENTS OF THE NEC.
MAXIMUM VOLTAGE: 480 VOLTS AC
4. TEXT LABELS WILL BE ETCHED WITH WHITE
GRAPHICS ONTO 1/16" RED PLASTIC PLACARDS.
Date Marks Revisions
THE LABEL WILL BE MECHANICALLY ATTACHED TO
THE APPROPRIATE COMPONENT ENCLOSURES IN
CONSPICUOUS PLACES.

5. LABEL "A" WILL BE ETCHED WITH WHITE


GRAPHICS ONTO 1/16" RED PLASTIC PLACARD. DESIGNED BY
THE LABEL WILL BE EFFECTIVELY BONDED TO THE
EXISTING FACILITY SWITCHBOARD AND THE NEW DRAWN BY:
PHOTOVOLTAIC SYSTEM DISCONNECT.
CHECKED BY:
SUPERVISED BY:

Drawing Number

L100
Scale: Date:
AS SHOWN 02/06/2016
Sheet No.
09 OF 09

You might also like