Exploration & Production Operations Company

Haddah Street, Haddah Zone


Sana`a, Yemen

Well: Alif #35

Rig: 101

P & A Cementing Program.

Prepared for: SEPOC Production Eng. Team

December 24th, 2013

Version Description Date:


1.0 P & A Cementing Program For Review & Comments 24.12.2013

Prepared by: Jamal Omar – Field Engineer


Reviewed by: Baggash Qasem

Weatherford Cementing & Pumping Services.


Al-Khamsin Street, Haddah Zone
Sana`a, Yemen
Alif #20
Balanced Plug Job

Wellbore Schematic & Fluids Positions Fluids Summary


Wellbore Thermal & Mud Properties
Fluid Density Volume
Brine/Injecivity Fluid 8.90 Ppg BHST: 144 O
F
Fresh Water Ahead 8.34 Ppg 10.0 Bbl BHCT: 106 O
F
Cement Slurry 15.80 Ppg 30.9 Bbl Gradient: 1.42 O
F/100.Ft
Fresh Water Behind 8.34 Ppg 3.2 Bbl Mud Type: Brine
10 3/4" 45.5 ppf Displacement 8.90 Ppg 32.3 Bbl Mud Desity: 8.90 Ppg
@ 2165 f
Casing & Annulus Capacities
Grade ID (in) Bbl/f f/Bbl

3 1/2 Tubing Casing/Wellbore


7" 23 ppf K-55 6.366 0.0394 25.4010

Tubing/Drill Pipe
3 1/2 J-55 2.992 0.0087 114.990
Balanced Plug Top @ 3714 f
Annulus
3 1/2 7.00 In Casing 0.2746 36.405
7" 23 ppf
Wellbore Fluids Volumetric Calculations
Tubular Top (f) Bottom (f) Height (f) Volume (Bbl)

7" 23 ppf, Casing 3714 4500 786 30.9 Enter Total Vol. Req
Spacer Ahead - - - 10.0
Spacer Behind - - - 3.2

Tubing Displacement: 32.3 Bbl


Casing Volume: 30.9 Bbl
Total Slurry Volume: ± 30.9 Bbl
Quantity of Cement: 151 Sacks
Balanced Plug Bottom @ 4500 f Mix Fluid Volume: 18.2 Bbl

Weatherford Cementing & Pumping Services


Alif #20
Balanced Plug Job

Wellbore Fluids Physical Properties (For Balanced Plug @4500 f)


Slurry Properties
Composition: Dosage:
CLASS G CEMENT 94 Lbs/Sk Slurry Density: 15.8 Ppg
WCAF-51L 0.02 gal/sk Slurry Yield: 1.15 f3/Sk
WCR-31 0.15 % Bwoc Mixing Water: 5.1 Gal/Sk
WCD-20 0.05 % Bwoc

Wellbore Material Summary / Requirement - Estimates


Slurry - Materials

CLASS G CEMENT ± 150 Sacks 6.4 MT


WCAF-51L 3 Gals
WCR-31 21 Lbs
WCD-20 7 Lbs

Weatherford Cementing & Pumping Services


Alif #20
Balanced Plug Job

Safety Moment
Hold a pre job safety meeting to ensure the Rig Crew and Weatherford cementing Team has a thorough understanding
of the following:
• The job procedures (operating limits, precautions and procedures).
• All individual job responsibilities (Weatherford, Rig Foreman and 3rd party personnel).
• All safety/environmental procedures and precautions including availability and use of PPE
• Emergency contingency plans.

Balanced Plug Procedures & Recommendations

1. RIH open ended combination String.


2. Position open ended String at 4500 ft
3. Hold a Tailgate safety and operational meeting to inform and enlighten all participants of the scope of work and
assign job responsibilities as required. Non-essential personnel should not be allowed near the work area or near high
pressure discharge lines.
4. Pressure test WFT discharge line to 5,000 psi using Fresh Water.
5.  Batch mix Cement Slurry in Batch Mixer as per Lab Report recipe.
6. Pump ± 5 Bbl of Fresh Water ahead.
7. Pump Cement Slurry Volume.
8. Shut down and pump ± 5 Bbl of Fresh Water behind the cement slurry. This volume of Fresh Water should be
reconfirmed based upon final drill string configuration.
9. Switch over to start displacement with Brine as per the final calculated volumes.
10. Rig to POOH, slowly as not to swab the plug, sufficient stands (~ 4-5 stands) so that the bottom of drill string has
safely cleared the theoretical top of cement.
11. Dump the Reminder of the Cement Slurry on top of the PCR.
12. Reverse circulate (bottom’s up) to clear drill string of any cement.

Note:
Weatherford Cementing Supervisor is responsible for taking surface representative samples of the slurry once
the required slurry density is reached. Keep the samples away from Vibration areas.

Weatherford Cementing & Pumping Services


#REF!
#REF!
#REF!

12. Pricing Pro Forma


UOM Unit Price Unit(s) Total
Product Charges

SC2 m3 $ 643.55 7 $ 4,504.85


LQ3 m3 $ 1,086.64 #REF! #REF!
Total Products Cost (USD) #REF!
Service Charges (to review)

Total Service Cost (USD) $ 4,500.00


Total Charges Total Job Costs (USD) #REF!