METHOD STATEMENT OF BORED PILE WORKS OF PREK HO BRIDGE

Introduction

This is method statement for present the bored pile works of PREK HO Bridge.
The following articles describe the work items concerning the work procedure, quality control.

1. Scope of Work

Quantity of foundation pile is as follows:

Design Length Excavate Total Design Total Excavate


Item Dia. Q’ty (m) Length (m) Length (m) Length (m)
Location
(m) Dia. Dia. Dia. Dia. Dia. Dia. Dia.1.2 Dia.1.5
No (nr)
1.2m 1.5m 1.2m 1.5m 1.2m 1.2m m m
1 1.2 3 22 - 23.30 - 66 - 69.90 - Abutment A1
2 1.5 3 - 21 - 24.52 - 63 - 73.56 Pier P1
3 1.5 3 - 26 - 31.04 - 78 - 93.12 Pier P2
4 1.5 3 - 24 - 27.67 - 72 - 83.01 Pier P3
5 1.2 3 25 - 26.30 - 75 - 78.9 - Abutment A2
- - 15 - - - - 141 213 147.30 249.69

2. Preparation Work and Mobilization Equipment

- Working area shall be cleared, grubbed, filling, and leveling.


- Preparation Access road and crane way as following the attach drawing
- All necessary Equipments for boring pile works will be arranged to site.

3. Construction Process

1) Set the actual position of pile by surveyor.


2) Install temporary casing by vibro hammer 60kw. to the depth of 6m. Temporary casing
shall be ID.1.30mx t 12 mm. for pile dia.1.20 m. and ID 1.60 m x t 1.2 mm. for pile
dia.1.50 m.
During driving, the position and verticality of casing shall always be confirmed by
plumb blob or theodolite.
After temporary casing has been driven to specified depth, the position of casing shall
be re-confirmed by E.D.M.
3) Soil inside casing shall be excavated by hammer grab.
4) Filling up casing by drilling mud.
The drilling mud shall be properly prepared and the properties shall be controlled
carefully in order to get the good result of drilled hole. The drilling mud shall has
adequate viscosity to prevent caving of bored hole and lost circulation of drilling mud.
Mud cake that causes less friction of pile be minimized by admixture of polymer. The
basis of mix ratio for drilling mud shall be has following:
- Bentonite 3–4%
- Polymer 0.1%
- Viscovity 35 – 45 sec / 960 cc.
- Ph 9 – 11
- Density 1.03 – 1.10
- Sand content less than 5 %
5) Set up TBH drilling machine in position.
6) Drilling the hole Dia.1.20 m and 1.50m by reverse circulation method to specified
depth. The drilling machine of Tone model TBM shall be used. The drilling machine
shall be set on H-beam base which were fixed with derrick high 9 m. Drilling bet shall
be 4 – wing bit ring type of dia. 1.20 and 1.50m .
7) After drilling to specified depth, the drilling mud shall be continued circulation drilling
mud with treated to drilling mud. Then, the depth of bored hole shall be inspected.
8) After that, drilling machine and drilling sting shall be removed.
9) The size and verticality of drilled hole shall be inspected and recorded by ultrasonic
drilling monitor.
10) Install rebar cage. Rebar cage shall be assembled in the yard and delivered to drilling
site by trailer truck. When lifting up the cage, the protection from deformation of cage
shall be special cared. The cage shall be installed with spacers to make sure the
covering of concrete. During the installation, rebar cage shall be support by supporting
beam. After all, the rebar cage shall be hung on the pomporary casing to prevent the
deformation of cage.
11) Install tremie pipe dia. 250 mm . to the depth of about 10 cm. above the bottom of
bored hole. Before installation, the charac teristic of the pipes such as the dent,
bending distortion, concrete debris and damage of O-ring at each tremie pipe shall be
inspected.
12) After installation of tremie pipes, the slime at the bottom of drilling hole shall be clean
up by air lifting through tremie pipe.
13) Concreting.
Concrete shall be supplied from batching plant and be delivered to site by concrete
agitaror truck. Concrete from agitator truck shall be discharged through concrete
hopper which is fixed on top of tremie pipe to drilled hole. During the concreting,
tremie pipe shall be embedded in concrete at least 2m.
14) After concreting to designed level, the temporary casing shall be ret rived.

4. Main Machinery

MAJOR EQUIPMENT FOR DIA.1.2m & DIA.1.5m BY REVERSE CIRCULATION DRRILL

Item Description Specification Unit Q’ ty Remark

1 Drilling machine Tone TBH8A Unit 1


2 Drilling accessories
2.1 Drilling pipe 8”x1.5m pcs 30
2.2 Weight rod pcs 2
2.3 Ring stabilizer dia. 1.2m pc 1
2.4 Ring stabilizer dia. 1.5m pc 1
2.5 4-wing bit dia. 1.2m pc 1
2.6 4-wing bit dia. 1.5m pc 1
3 Suction pump unit 1
4 Suction hose 8”x 6m pcs 3
5 Service crane 50 ton unit 1
6 Excavator 0.7m3 unit 1
7 Vibro hammer 60 kw unit 1
8 Drilling monitor KODEN DM-682 unit 1
9 Mud tank 45 m3 unit 2
10 Generator for reverse drilling machine unit 1
and vibro hammer 350 kva
11 Generator for plant 150 kva unit 1
12 Air Compressor 7.5 kg/cm2, 15 m3 unit 1
13 Engine welding machine 400Amp unit 1
14 Circular bender unit 1
15 Electric distribution board unit 2
16 Tremie pipe 10” x 3 m pcs 15
17 Tremie pipe 10” x 2 m pc 1
18 Tremie pipe 10” x 1 m pc 1
19 Tremie pipe hopper pc 1
20 Concrete stand unit 1
21 Concrete hopper unit 1
22 Temporary casing ID 1,300mm, pcs 2
t = 20mm x 6 m
23 Temporary casing ID 1,600mm, pcs 2
t = 20mm x 6 m
24 Steel plate 25 mm, 2 m x 6 m pcs 20
25 Mud plant set 1
26 Desander with accessaries set 1
27 Sand pump 4” pcs 4
28 Sand pump 2” pcs 2
29 Sanny 4” x 100 m pcs 2
30 Sanny 2” x 100 m pcs 2
31 Betonite testing set 1
32 Sling for off loading pcs 10
33 Lifting chain pc 1
34 Shackle pcs 20
35 Hook 5-10 ton pcs 4
36 Air hose 1’x 20 m pcs 2
37 Electric wire lot 1
38 Loading test equipment set 1
39 Tool set 1
5. Flowchart of Construction

TYPE OF WORK INSPECTION EQUIPEMENT

Drive temporary casing Confirm position and Vibro service crane


Verticality EDM or Theodolite

Excavation soil inside Record soil formation Crawler crane 40 ton,


casing by grab hammer Grab hammer

Drilling work by reserse Confirm the supporting Drilling machine 4 wing


circulation formation (end bearing bit Betonite Plant
materials)

Inspection of Dept Check settlement Measuring tape

Cleaning bottom of hole Replace the mud of the Drilling machine


hole Air compressor

Installation of Inspection of cage Service Crane, Hanger,


Reinforced cage confirm joint lap welding machine

Installation of tremie Inspection dept confirm Trimie pipe, Air


pipes clean up the no settlement compressor with hose
bottom by air lift Bentonite plant, serviced
(if necessary) crane

Concreting Slump Test, Take piece Trimie pipe, with hopper


sample for compression Bentonite plant, service
test crane

Take out temporary Inspect the concrete level Vibro service Crane,
casing Measuring tape, DM, or
Theodolite
6. Cycle time

1. Preparation of working area 0.5 hrs.


2. Setting out the position of pile 0.5 hrs.
3. Drive temporary casting by vibro hammer 1 hrs.
4. Excavate inside casing by grab hammer 1 hrs.
5. Set up end preparing of drilling 1 hrs.
6. Drilling 14.5 hrs.
7. Clean up of pile base 0.5 hrs.
8. Installation of rebar cage 1.5 hrs.
9. Installation of tremie pipe 1 hrs.
10. Concreting 1.5 hrs.
11. Cleaning the site and move to next pipe 0.5 hrs.

Total 23.5 hrs.

PREK HO Bridge

Total 15 piles x 22.5 / 20hrs. x 0.8 = 21 days