Section 4.7 - Project Weekly & Monthly Quality meetings with Consultants/PMC/Client
27 representative not mentioned
Sections 4.10, 4.11, 4.13, 4.14, 4.16 are general not project specific - All these sections
28 management procedure, Project Numbering systems and Communication protocol
Section 7 - Not only major sub-contractors in the project shall follow the Project Quality
30 Requirements including documentation
Appendix F - Roles & Responsibilities does not include Construction Manager, HSE Manager,
32 QA/QC Engineer/Inspector, M&P Engineers and Sub-Contractors
Appendix M - Overall scope of works is not considered in developing the method statement list
33 (Dry Stack & Car Park works not considered)