Alcatel-Lucent University
Section 1
Operations and Maintenance
Module 6
System turnup
TOP30003_V3.0-SG-6.0.0-Ed1 Module 1.6 Edition 1
1830 PSS
6.0.0 WDM Operations and Maintenance
TOP30003_V3.0-SG Edition 1
1 System turn-up 7
2 Exercises 10
Procedure Outline:
1. Provision the NE with the EPT network commissioning file.
2. Demonstrate the shelf view.
3. Provide Wavelength Tracker channel trace view for a specific channel (bar
view and signal flow).
4. Provide A-to-Z and Z-to-A view.
5. Provide path trace view within the shelf.
6. Discuss the Z bars and threshold settings.
7. Show real time channel power view.
8. Add a new channel to existing traffic.
9. Simulate a line side failure between NE’s.
10. Simulate a fiber failure between a TOADM and OT.
WR WR WR WR WR WR
6 3 2 6 7 3
8 4 4 8 8 4
7 2 3 7 6 2
1 1 1 1 1 1 1 4 1 1 1 1 4 1
1 1 1 1 1 1 1 3 1 1 1 1 3 1
Q S Q 2 D D D S S 2 D Q S Q
P T P S P P P T T S P P T P
A A A C M E M X A C E A X A
4 R 4 X 1 1 1 4 R X 1 4 4 4
1 1 2 2 2 P 1 1 2 P
L L 0 L E L 0 E L L
3 9 1 9 1 1 1 3
9 2 9 2 9 9 9 9 9 9 9 9 9 9
3 3 3 1 1 4 1 2 2 2 4 3 2 3
4 0 4 0 9 8 9 0 3 1 8 4 0 4
0 0 0 0 0 0 0 0 0 0 0 0
The auto managed lines on a linear system adjacent to the terminal sites as well
as the terminal sites themselves will not complete using the commissioning wizard
(ass per the loss report). Those lines must have further power adjustments to
complete commissioning.
1 2 3 4
NE A NE B NE C NE D NE E
Static Filter TOADM TOADM TOADM TOADM
Terminal A A A A A A A A Terminal
1. Refer to your 1830 PSS-32/16 Installation Guide, Part V, Chapter 11, and
perform “Perform power adjustments” procedure.