Professional Documents
Culture Documents
S/N Material Ratio Weight kg/m3 Total wt kg/m3 Weighted Ratio Material Rqd (kg) Material Reqd (m3) Remarks
S/N Material Ratio Weight kg/m3 Total wt kg/m3 Weighted Ratio Material Rqd (kg) Material Reqd (m3) Remarks
Chipping m3 0.85 11,184.21 9,506.58 0.89 11,184.21 9,953.95 0.92 11,184.21 10,289.47
Water Litres 150 0.91 136.36 150 0.8 120.00 150 0.8 120.00
Labour mixing Bag 6 750 4,500.00 4 750 3,000.00 3.1 750 2,325.00
Mason receiving Bag 6 133.33 800.00 4 133.33 533.33 3.1 133.33 413.33
Concrete mixer + Op (N10,000) Day 6 214.29 1,285.71 4 142.86 571.44 3.1 142.86 442.866
Poker vibrator + Op (N4,500) Day 6 71.43 428.57 4 64.29 257.16 3.1 64.29 199.30
15 Insurance & Bonds 2.00% 683.56 683.56 521.38 521.38 457.99 457.99
16 Job O/h-suprintendent Bag 6 71.43 428.57 4 57.14 228.57 3.1 57.14 177.14
17 General O/h (headquarters) 10% 3,417.79 3,417.79 2,606.90 2,606.90 2,289.96 2,289.96