You are on page 1of 87

MOSER BA

3X50 MW THERMA

INPUT
(A

FINANCIAL ASSUMPTIONS
UNIT(I,II,III)
Project Cost (Rs.Crores / MW) 4.00
Sale of Infirm Power 0.0
Total Project Cost 600.0
Levelised Tariff (Rs/kWh) Err:522
Capital Structure
Debt(Percentage) 70%
Equity(Percentage) 30%
Debt 420.0
Equity 180.0
Upfront Equity 51%
Upfront Equity Funding 91.8
Assumptions for Capacity Charges
Interest on Loan capital 12%
Interest on Working capital 12%
Return on Equity 15.50%
O&M expenses ( in % of TPC ) 2.00%
O&M Expenses 12.0
O&M Expenses Escalation 5.75%
Maintenance Spares ( % of Project Cost ) 20% of O&M Expense p.a.
Maintenace Spares Cost Escalation 6%
Depreciation (for Tariff Clculation) 5.28%
Depreciation as per IT Act 7.84%
Total number of Years of Operation 25.0
Loan Duration (years) 12.0
Assumptions for Variable Charges
Cost of Coal(Rs./Ton)(Price + Freight) 804.0
Coal consumption(million tonnes) 0.30
Secondary Fuel Prices (Rs./kl) 35250.0
Secondary Fuel Consumptions(ml/kWh) 1.00
Taxes
Basic Tax 30.00%
Development Surcharge 3.00%
Net Corporate Tax 33.00%
Add Edu Cess(3%) 0.99%
Total Tax 33.99%
Dividend Distribution Tax 14.03%
Statutory Reserves 0.00%
MAT 11.33%
Other Miscellaneous Assumptions
Exchange Rate 45.5
Fx Variation 2%
Financing Charges & Upfront Fee 1.00%
Bank Guarantee Charges 2.00%
Avg.Acc.Receivables( in months) 2.0
Upfront Equity Funding 51%
Debt Service Reserve Acc.(in Months) 3%
Margin Money 25%
MOSER BAER PROJECTS LIMITED

3X50 MW THERMAL POWER PLANT FINANCIAL MODEL

INPUT & ASSUMPTION SHEET


(ALL VALUES IN RS. CRORES)

TECHNICAL ASSU

Installed Capacity of single unit


No. of installed units
Total Installed Capacity
Total units generated
Target Availability Factor
(CERC Norms 2009-14) PLF
(CERC Norms 2009-14) Gross Station Heat Rate
GCV of Coal
GCV of Oil
(CERC Norms 2009-14) Auxiliary Consumption
Coal Transit Loss
Energy Delivered ExBus (Million units)
(CERC Norms 2009-14) THE PLANT IS COAL FIRED WIT
(CERC Norms 2009-14)
(CERC Norms 2009-14)
(CERC Norms 2009-14)

(CERC Norms 2009-14)


(CERC Norms 2009-14) IMPORTANT D
(CERC Norms 2009-14) Date of Construction
(CERC Norms 2009-14) COD of unit I
(As per IT Act) CoD of unit II
(CERC Norms 2009-14) CoD of unit III
(CERC Norms 2009-14) Months required for unit I
Months required for unit II
Price-Acc.to Grade of Coal,Freight-Acc.to Min.of Railways Months required for unit III

Ministry of Petroleum & Natural Gas


(CERC Norms 2009-14)

PROJECT SUMM
(CERC Norms 2009-14)
(CERC Norms 2009-14) Total Project Cost
(CERC Norms 2009-14) Equity
(CERC Norms 2009-14) Debt
(CERC Norms 2009-14) Upfront Equity
(CERC Norms 2009-14) IDC for unit I
IDC for unit II
(CERC Norms 2009-14) IDC for unit III
Tariff
Rserve Bank of India website NPV
Rserve Bank of India website IRR
(CERC Norms 2009-14) WACC
State Bank of India Charges DSCR
(CERC Norms 2009-14)
(CERC Norms 2009-14)
(CERC Norms 2009-14)
(CERC Norms 2009-14)
TECHNICAL ASSUMPTIONS
UNIT(I,II& III)
alled Capacity of single unit 50.0 MW
No. of installed units 3.0
Total Installed Capacity 150.0 MW
Total units generated 1314.0 million units
Target Availability Factor 95%
PLF 85% (CERC Norms 2009-14)
Gross Station Heat Rate 2780.0 kcal/kWh (CERC Norms 2009-14)
GCV of Coal 3420.0 kcal/kg Ministry of Coal
GCV of Oil 10.7 kcal/ml Ministry of Petroleum
Auxiliary Consumption 10% (CERC Norms 2009-14)
Coal Transit Loss 0.80% Ministry of Coal
Delivered ExBus (Million units)
PLANT IS COAL FIRED WITH COOLING TOWER

IMPORTANT DATES
Date of Construction 04/01/09 ( MM-DD-YY) Assumption
COD of unit I 07/01/12 ( MM-DD-YY)
CoD of unit II 01/01/13 ( MM-DD-YY)
CoD of unit III 07/01/13 ( MM-DD-YY)
Months required for unit I 39
Months required for unit II 6
Months required for unit III 6
PROJECT SUMMARY

Total Project Cost Err:522 Rs. Cr


Equity Err:522 Rs. Cr
Debt Err:522 Rs. Cr
Upfront Equity Err:522 Rs. Cr
IDC for unit I Err:522 Rs. Cr
IDC for unit II Err:522 Rs. Cr
IDC for unit III Err:522 Rs. Cr
Tariff Err:522 Rs./kwh
NPV Err:522 Rs. Cr
IRR Err:522
WACC 11.57%
DSCR Err:522
3x50 MW THERMAL POWER P
PROJECT
(ALL VALUES I

Unit Capacity ( MW) 50.0


No. of Units 3.0
1.HARDCOST Installed Capacity ( MW) 150.0

Land and Site Development

Cost of Land
Cost of Land ( Rs Lakh/Acre)
Plant site (incl Green land & Switch Yard)
Ash Pond
BOP Area
Coal Handling Plant Area
Cooling Tower Area
Sea Water Outfall
Basic Cost of Land

Stamp Duty
Transfer Duty
Registration Fees
Statutory Taxes / Charges
Documentation Charges
Land Related Misc. Charges
Sub Total ( Rs Cr)

Cost of Land : Sub-total

Site Development Expenses


Compound Wall & Fencing
Roads - Internal
Approach Roads
Storm Water Drainage
Levelling & Grading
Investigation
Site Dev. Exp :Sub - total

Total Land & Site Dev


Cost Escalation
Total Land & Site Dev Incl Esc

Civil Works
Rehab & Resettlement( Permanent Township)
Temp Const & Enabling work
Sub Total : R & R

Total Civil Works

EPC Costs(BTG)

BTG Chinese ( Rs Cr / MW )
Indian ( BHEL) ( Rs Cr/ MW )
Choice
According to Chinese (BTG)

Customs Duty : Offshore Sy


Custom Duty : Spare Parts
With Holding Tax : Offshore Engg
Excise Duty & Cess (Local)
Central Sales Tax (Local)
Amount on which CST applicable ( % ) of capital
Duties & Taxes : Sub-total

Total EPC Costs(BTG)

Total EPC Costs(BTG) Incl Esc

EPC Costs (Others)

BoP Incld Civil Works


Chinese ( Rs Cr / MW )
Indian ( BHEL) ( Rs Cr/ MW )
Choice

Customs & Excise


Central Sales Tax (Local) (3%)
Amount on which CST applicable ( % ) of capital
CST ( Rs Cr)
Duties & Taxes : Sub-total

Total EPC Costs (Others)

Misc. Fixed Assets(Incl Washeries)

Washeries
Vehicles
Furnitures & Fixtures
Other Misc Assets
Total Misc. Fixed Assets(Incl Washeries)

Total Misc. Fixed Assets(Incl Washeries) Incl Esc

SOFT COST

Non EPC(Soft Cost)

Operator's Training
Construction Insurance
Startup Fuel & Startup Power
Special T&P
Salary
Consultancy and Legal
Design and Engineering
Development Expenses
Establishment
Aduit & Accounts
Sub-Total of Soft Cost

Contingency

Interest During Construction

Total Project Cost Incl Esc


Cost Per MW
ERMAL POWER PLANT FINANCIAL MODEL
PROJECT COST
(ALL VALUES IN RS. Cr)

Cost ( Rs Crore) Area ( in Acre)


1.5 1.0
2.22 148.20
1.22 81.51
0.98 65.30
0.54 35.80
0.38 25.55
0.19 12.80
5.54 369.16

( %of Basic Cost)


0.36 6.50%
0.33 6%
0.03 0.50%
0.00
0.00
0.00
0.72

6.26

0.85
0.30
0.70
1.10
0.50 40000.0
0.60
4.05

10.31
0.41 4%
10.7

7.50
0.30
7.80

7.8

1.8
2.1

270.0

0.0 0%
0.0 0%
0.0 0%
0.0 0%
0.0 0%
0.0 0%
0.0

270.0

270.0

1.60
0.00
240.00

0.0 0.0
0.0
0.0
0 0.0
0

240.00

1.81
0.90
1.06
3.77

6.6

0.84
3.60
6.90
2.25
1.60
0.75
3.04
3.60
9.50
0.25
32.3

Err:522 4%

Err:522

Err:522
Err:522 Rs.Cr/MW
Area ( in Hectare) According to DPR provided

60.00 According to DPR provided


33.00 According to DPR provided
26.44 According to DPR provided
14.49 According to DPR provided
10.34 According to DPR provided
5.18 According to DPR provided
149.46

According to DPR provided


According to DPR provided
According to DPR provided

According to DPR provided


According to DPR provided
According to DPR provided
According to DPR provided
Rs/Acre According to DPR provided
According to DPR provided
According to DPR provided
According to DPR provided
According to DPR provided
per Annum According to DPR provided
According to DPR provided
According to DPR provided
According to DPR provided

According to DPR provided


According to DPR provided
According to DPR provided

According to DPR provided


According to DPR provided
According to DPR provided
According to DPR provided
According to DPR provided
According to DPR provided

According to DPR provided


According to DPR provided
According to DPR provided
According to DPR provided
According to DPR provided
According to DPR provided
According to DPR provided
According to DPR provided
According to DPR provided
According to DPR provided

According to DPR provided


MOSER BA

3X50 MW THERMAL

INTEREST DUR
ALL V

MONTHS OF YEAR BEFORE COD Total of Total 1


INVESTMENT AS PER THE FOLLOWING HEADS 1st
( % wise) Heads Percentage Apr-09
LAND 10.72 100.00% 75.00%

EPC (BTG) 270.00 100.00%

EPC ( OTHER) 240.00 100.00%

NON EPC ( SOFT COST) 32.33 100.00% 1.96%

Civil Works 7.80 100.00%

Construction and Pre-Commissioning Expenses( Misc Asset) 6.6 100.00% 1.96%

Contingency Expenses Err:522 100.00%

Total Expenditure Err:522

MONTHS OF YEAR BEFORE COD Total of Total 1


INVESTMENT AS PER THE FOLLOWING HEADS 1
Heads Apr-09
LAND 10.72 8.04

EPC (BTG) 270.00 0.00

EPC ( OTHER) 240.00 0.00

NON EPC ( SOFT COST) 32.33 0.63


Civil Works 7.80 0.00

Construction and Pre-Commissioning Expenses( Misc Asset) 6.6 0.13

Contingency Expenses Err:522 Err:522

Total Heads Err:522 Err:522

Quarterly Expense
Upfront Equity 51%
Equity 30% Err:522
Cumulative Equity
Debt 70% Err:522
Cumulative Debt
Interest ( Including Financial Charges) 12.25% Err:522
Quarterly Interest 3.06%
Cumulative Interest
Project Cost Including IDC & FC Err:522

Total number of quarters for unit I 13


Total number of quarters for unit II 2
Cumulative Quarters 15
Total number of quarters for unit III 2
Cumulative Quarters 17.00

Debt upto CoD of unit I Err:522 Interest Err:522


Debt upto CoD of unit II Err:522 Interest Err:522
Debt upto CoD of unit III Err:522 Interest Err:522

IDC Err:522 Rs Cr
Total Project Cost Err:522 Rs Cr
MOSER BAER PROJECTS LIMITED

3X50 MW THERMAL POWER PLANT FINANCIAL MODEL

INTEREST DURING CONSTRUCTION


ALL VALUES IN Rs. CRORE

2 3 4 5 6 7 8 9 10 11
1st 2nd 3rd 4th
May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10
25.00%

9.00% 11.00%

1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96%

17.00% 17.00% 20.00%

1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96%

2 3 4 5 6 7 8 9 10 11
1 2 3 4
May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10
0.00 0.00 0.00 2.68 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 21.60 0.00 0.00 0.00 0.00 26.40

0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63
1.33 0.00 0.00 1.33 0.00 0.00 0.00 1.56 0.00 0.00

0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522

Err:522 Err:522 Err:522

Err:522 Err:522 Err:522


Err:522 Err:522 Err:522

Err:522 Err:522 Err:522


Err:522 Err:522 Err:522
12 13 14 15 16 17 18 19 20 21
4th 5th 6th 7th
Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10

15.00% 17.00% 8.00%

12.00%

1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96%

22.00% 12.00% 12.00%

1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96%

12 13 14 15 16 17 18 19 20 21
4 5 6 7
Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 40.50 0.00 0.00 45.90 0.00 0.00 0.00 21.60 0.00

0.00 0.00 0.00 0.00 0.00 0.00 28.80 0.00 0.00 0.00

0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63
1.72 0.00 0.00 0.94 0.00 0.00 0.00 0.94 0.00 0.00

0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522


Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522


Err:522 Err:522 Err:522 Err:522
22 23 24 25 26 27 28 29 30 31
8th 9th 10th 11th
Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11

13.00% 17.00% 14.00%

11.00% 7.00% 19.00%

1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96%

1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96%

22 23 24 25 26 27 28 29 30 31
8 9 10 11
Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 35.10 0.00 0.00 0.00 45.90 0.00 0.00 37.80

26.40 0.00 0.00 0.00 16.80 0.00 0.00 0.00 45.60 0.00

0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522

Err:522 Err:522 Err:522

Err:522 Err:522 Err:522


Err:522 Err:522 Err:522

Err:522 Err:522 Err:522


Err:522 Err:522 Err:522
32 33 34 35 36 37 38 39 40 41
11th 12th 13th 14th
Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12

11.00% 5.00%

9.00% 15.00%

1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96%

1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96%

32 33 34 35 36 37 38 39 40 41
11 12 13 14
Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 29.70 0.00 0.00 0.00 13.50 0.00

0.00 0.00 21.60 0.00 0.00 0.00 0.00 36.00 0.00 0.00

0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522

Err:522 Err:522 Err:522

Err:522 Err:522 Err:522


Err:522 Err:522 Err:522

Err:522 Err:522 Err:522


Err:522 Err:522 Err:522
42 43 44 45 46 47 48 49 50 51
14th 15th 16th 17th
Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

7.00%

1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96%

1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96% 1.96%

25.00% 25.00% 25.00% 25.00%

42 43 44 45 46.00
14 15 16 17
Sep-12 Oct-12 Nov-12 Dec-12
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 16.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522


Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522


Err:522 Err:522 Err:522 Err:522
18 19 20 21.00
21.00
1508.71
3X50 MW THERMAL POWER

FUEL EXPEN
ALL VALUES IN

Total No. of units 1314.00


PLF 85.0%
Actual generated units 1116.90
Units to generate(1st yr) 657.60 million units
Actual generated units(1st yr) 558.96 million units

CALCULATION O

SECONDARY Fuel

Secondary Fuel Consumption 1.00


(in Litre) 0.0010
(in Kg) 0.00093

Secondary Fuel Cost 35250.00


35.25

Secondary Fuel Cost per unit 0.03

Total Secondary Fuel Consumption per Annum 4.32


1225.96

PRIMARY FUEL

GCV of Secondary Fuel 10.72

Heat contribution from sec Fuel to produce 1 unit 10.72

Heat contribution from Primary Fuel 2769.28

Coal required to produce one unit 0.81


Coal Price 0.80

Cost of Coal to produce one unit 0.65

VARIABLE CHARGE FOR A SINGLE UNIT ( Rs./kwh ) 0.68

AUXILIARY CONSUMPTION 10%

RATE OF ENERGY DELIVERED TO EX-BUS ( Rs./kwh )


0.76

Primary Fuel Cost Escalation 6.00%


Secondary Fuel Cost Escalation 7.00%

2012-13 2013-14
Units to be generated ( million units) 657.60 1314.00

Total Coal Cost per Annum 42.81 85.54

Total Sec. Fuel Cost per Annum 2.16 4.32

Cost of COAL for 2 months 7.14 14.26

Cost of Sec. Fuel for 2 months 0.36 0.72

Total Variable Charges 44.97 89.87

Variable Charges/ unit 0.80 0.80

Energy Rate at Bus Bar 0.89 0.89


MW THERMAL POWER PLANT FINANCIAL MODEL

FUEL EXPENSES
ALL VALUES IN RS. Cr.

Units to generate(2nd yr) 1206.00 million units


Actual generated units(2nd yr) 1025.10 million units

CALCULATION OF VARIABLE EXPENSES

ml/kwh
litre/kwh
kg/kwh Specific Gravity of Secondary Fuel 0.93

Rs/MT
Rs/kg

Rs/kwh

Rs.Cr
MT

kcal/ml

kcal/kwh

kcal/kwh

kg
Rs/kg

Rs

0.68

0.76

2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24
1314.00 1314.00 1314.00 1314.00 1314.00 1314.00 1314.00 1314.00 1314.00 1314.00

90.68 96.12 101.88 108.00 114.48 121.35 128.63 136.34 144.53 153.20

4.62 4.95 5.29 5.66 6.06 6.49 6.94 7.43 7.94 8.50

15.11 16.02 16.98 18.00 19.08 20.22 21.44 22.72 24.09 25.53

0.77 0.82 0.88 0.94 1.01 1.08 1.16 1.24 1.32 1.42

95.30 101.07 107.18 113.66 120.54 127.83 135.57 143.77 152.47 161.70

0.85 0.90 0.96 1.02 1.08 1.14 1.21 1.29 1.37 1.45

0.95 1.01 1.07 1.13 1.20 1.27 1.35 1.43 1.52 1.61
2024-25 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32 2032-33 2033-34 2034-35
1314.00 1314.00 1314.00 1314.00 1314.00 1314.00 1314.00 1314.00 1314.00 1314.00

162.39 172.13 182.46 193.41 205.01 217.31 230.35 244.17 258.82 274.35

9.10 9.73 10.41 11.14 11.92 12.76 13.65 14.61 15.63 16.72

27.06 28.69 30.41 32.23 34.17 36.22 38.39 40.70 43.14 45.73

1.52 1.62 1.74 1.86 1.99 2.13 2.28 2.43 2.60 2.79

171.49 181.87 192.87 204.55 216.94 230.07 244.00 258.78 274.45 291.08

1.54 1.63 1.73 1.83 1.94 2.06 2.18 2.32 2.46 2.61

1.71 1.81 1.92 2.03 2.16 2.29 2.43 2.57 2.73 2.90
2035-36 2036-37 2037-38
1314.00 1314.00 1314.00

290.81 308.26 326.76

17.89 19.15 20.49

48.47 51.38 54.46

2.98 3.19 3.41

308.71 327.41 347.24

2.76 2.93 3.11

3.07 3.26 3.45


3x50 MW THERMAL POWER PLANT FIN

INTEREST ON WORKING C
ALL VALUES IN Rs. Cr.

YEAR OF OPERATION 1 2 3 4 5
Cost Of Coal For 2 Months 7.14 14.26 15.11 16.02 16.98
Cost Of Secondary Fuel For 2 Months 0.36 0.72 0.77 0.82 0.88
O&M Expenses For 1 Month 1.00 1.06 1.12 1.18 1.25
Maintenance Spares Err:522 Err:522 Err:522 Err:522 Err:522
Receivables Of Two Months Err:522 Err:522 Err:522 Err:522 Err:522
Total Working Capital Err:522 Err:522 Err:522 Err:522 Err:522
Increase in Current Asset Err:522 Err:522 Err:522 Err:522 Err:522
Interest App. Part Of Working Capital Err:522 Err:522 Err:522 Err:522 Err:522
Increase in Working Capital Err:522 Err:522 Err:522 Err:522 Err:522
Interest On Working Capital Err:522 Err:522 Err:522 Err:522 Err:522
Working Capital Margin

Total Project Cost Err:522


Interest on Working Capital 12%
Maintenance Spares (20% of O&M EXPENSES) 1.15%
Escalation of Maintenance Spares 6%
Margin Money for Working Capital 25%
OWER PLANT FINANCIAL MODEL

T ON WORKING CAPITAL
LL VALUES IN Rs. Cr.

6 7 8 9 10 11 12 13 14 15
18.00 19.08 20.22 21.44 22.72 24.09 25.53 27.06 28.69 30.41
0.94 1.01 1.08 1.16 1.24 1.32 1.42 1.52 1.62 1.74
1.32 1.40 1.48 1.56 1.65 1.75 1.85 1.96 2.07 2.19
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
16 17 18 19 20 21 22 23 24 25
32.23 34.17 36.22 38.39 40.70 43.14 45.73 48.47 51.38 54.46
1.86 1.99 2.13 2.28 2.43 2.60 2.79 2.98 3.19 3.41
2.31 2.45 2.59 2.74 2.89 3.06 3.24 3.42 3.62 3.83
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
3x50 MW THERMAL POWER PLA

O & M CHARGE CALCULAT


All VALUES ARE IN RS. Cr.

YEARS OF OPERATION 1.0 2.0 3.0 4.0 5.0 6.0

O&M Expenditure(2%of TPC) 12.00 12.69 13.42 14.19 15.01 15.87

Monthly Expenditure 1.0 1.1 1.1 1.2 1.3 1.3

Total Project Cost Err:522


O&M Expenses( in % of TPC) 2.00%
O&M Expenses per Annum 12.00
Escalation of O&M Charges 5.75%
L POWER PLANT FINANCIAL MODEL

GE CALCULATION
RE IN RS. Cr.

7.0 8.0 9.0 10.0 11.0 12.0 13.0

16.78 17.75 18.77 19.85 20.99 22.20 23.47

1.4 1.5 1.6 1.7 1.7 1.8 2.0


14.0 15.0 16.0 17.0 18.0 19.0 20.0 21.0 22.0 23.0

24.82 26.25 27.76 29.35 31.04 32.83 34.71 36.71 38.82 41.05

2.1 2.2 2.3 2.4 2.6 2.7 2.9 3.1 3.2 3.4
24.0 25.0

43.41 45.91

3.6 3.8
3x50 MW THERMAL P

Interest on Loan Capital 12.0% INTEREST


Interest on Loan (Quarterly) 3.0%

Year 2012-13 2013-14


NO. of Quarters 1.0 2.0 3.0 4.0 5.0 6.0
Quarters 1st 2nd 3rd 4th 1st 2nd 3rd
Opening Balance 420.0 420.0 420.0 420.0 420.0 410.5
Interest 12.6 12.6 12.6 12.6 12.6 12.3
Principle Amount 0.0 0.0 0.0 0.0 9.5 9.5
Loan Repayment 12.6 12.6 12.6 12.6 22.1 21.9
Outstanding Balance 420.0 420.0 420.0 420.0 410.5 400.9

Year Months Loan Amount Interest Principle Paid


2012-13 12.0 420.0 50.4 0.000
2013-14 12.0 420.0 48.7 38.2
2014-15 12.0 381.8 44.1 38.2
2015-16 12.0 343.6 39.5 38.2
2016-17 12.0 305.5 34.9 38.2
2017-18 12.0 267.3 30.4 38.2
2018-19 12.0 229.1 25.8 38.2
2019-20 12.0 190.9 21.2 38.2
2020-21 12.0 152.7 16.6 38.2
2021-22 12.0 114.5 12.0 38.2
2022-23 12.0 76.4 7.4 38.2
2023-24 12.0 38.2 2.9 38.2

Total No of Months 48.0

Total Debt 420.0


W THERMAL POWER PLANT FINANCIAL MODEL

INTEREST ON LOAN CALCULATION


ALL VALUES IN RS. Cr.

3-14 2014-15 2015-16


7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0
4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th
400.9 391.4 381.8 372.3 362.7 353.2 343.6 334.1 324.5
12.0 11.7 11.5 11.2 10.9 10.6 10.3 10.0 9.7
9.5 9.5 9.5 9.5 9.5 9.5 9.5 9.5 9.5
21.6 21.3 21.0 20.7 20.4 20.1 19.9 19.6 19.3
391.4 381.8 372.3 362.7 353.2 343.6 334.1 324.5 315.0

Repayment Loan Amount Left Cumulative Repayment


50.4 420.0 50.4
86.9 381.8 137.3
82.3 343.6 219.5
77.7 305.5 297.2
73.1 267.3 370.4
68.5 229.1 438.9
64.0 190.9 502.9
59.4 152.7 562.2
54.8 114.5 617.0
50.2 76.4 667.2
45.6 38.2 717.4
41.0 0.0 758.5
2016-17 2017-18 2018-19
16.0 17.0 18.0 19.0 20.0 21.0 22.0 23.0 24.0 25.0
1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd
315.0 305.5 295.9 286.4 276.8 267.3 257.7 248.2 238.6 229.1
9.5 9.2 8.9 8.6 8.3 8.0 7.7 7.4 7.2 6.9
9.5 9.5 9.5 9.5 9.5 9.5 9.5 9.5 9.5 9.5
19.0 18.7 18.4 18.1 17.9 17.6 17.3 17.0 16.7 16.4
305.5 295.9 286.4 276.8 267.3 257.7 248.2 238.6 229.1 219.5
2018-19 2019-20 2020-21
26.0 27.0 28.0 29.0 30.0 31.0 32.0 33.0 34.0 35.0
3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th
219.5 210.0 200.5 190.9 181.4 171.8 162.3 152.7 143.2 133.6
6.6 6.3 6.0 5.7 5.4 5.2 4.9 4.6 4.3 4.0
9.5 9.5 9.5 9.5 9.5 9.5 9.5 9.5 9.5 9.5
16.1 15.8 15.6 15.3 15.0 14.7 14.4 14.1 13.8 13.6
210.0 200.5 190.9 181.4 171.8 162.3 152.7 143.2 133.6 124.1
2021-22 2022-23 2023-24
36.0 37.0 38.0 39.0 40.0 41.0 42.0 43.0 44.0 45.0
1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd
124.1 114.5 105.0 95.5 85.9 76.4 66.8 57.3 47.7 38.2
3.7 3.4 3.2 2.9 2.6 2.3 2.0 1.7 1.4 1.1
9.5 9.5 9.5 9.5 9.5 9.5 9.5 9.5 9.5 9.5
13.3 13.0 12.7 12.4 12.1 11.8 11.6 11.3 11.0 10.7
114.5 105.0 95.5 85.9 76.4 66.8 57.3 47.7 38.2 28.6
2023-24 2024-25
46.0 47.0 48.0
3rd 4th 1st 2nd 3rd 4th
28.6 19.1 9.5 0.0 0.0 0.0
0.9 0.6 0.3 0.0 0.0 0.0
9.5 9.5 9.5 0.0 0.0 0.0
10.4 10.1 9.8 0.0 0.0 0.0
19.1 9.5 0.0 0.0 0.0 0.0
3X50 MW THERMAL PO

DEPR
ALL VA

YEAR OF OPERATION 1.0 2.0 3.0 4.0 5.0 6.0

Gross Block Err:522 Err:522 Err:522 Err:522 Err:522 Err:522


Depreciation (S.L.M) Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Net Block Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Depreciation after Loan Repayment 0.0 0.0 0.0 0.0 0.0 0.0
Cumulative Repayment 50.4 137.3 219.5 297.2 370.4 438.9
Advance Against Depreciation (AAD) Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Total Project Cost Err:522


Depreciable Cost Err:522

Depreciable Amount 90.0%


Depreciation 5.28% using SLM

No. of years of Operation 25.0 years

Repayement Period 12.0 years


THERMAL POWER PLANT FINANCIAL MODEL

DEPRECIATION
ALL VALUES IN RS. Cr.

7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 16.0

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 0.0 0.0 0.0 0.0
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
0.0 0.0 0.0 0.0 0.0 0.0 Err:522 Err:522 Err:522 Err:522
502.9 562.2 617.0 667.2 717.4 758.5
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
17.0 18.0 19.0 20.0 21.0 22.0 23.0 24.0 25.0

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522


0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
3x50MW THERMAL POWER PLAN

TARIFF CALCULATIO
ALL VALUES IN Rs.Cr.

YEARS OF OPERATION 1.0 2.0 3.0 4.0


2012-13 2013-14 2014-15 2015-16
Annual capacity(Fixed) Charges:
Interest on Loan Capital 50.40 48.68 44.10 39.52
Depreciation Err:522 Err:522 Err:522 Err:522
Return on Equity 0.16 0.16 0.16 0.16
O&M Expenses 12.00 12.69 13.42 14.19
Interest on Working Capital Err:522 Err:522 Err:522 Err:522
Total Annual Capacity(Fixed) Charges Err:522 Err:522 Err:522 Err:522
Per Unit Capacity Charges(Rs./kwh) Err:522 Err:522 Err:522 Err:522
Energy(Variable) Charges
Coal charges 42.81 85.54 90.68 96.12
Secondary Fuel Charges 2.16 4.32 4.62 4.95
Total Variable Charges 44.97 89.87 95.30 101.07
Per Unit Variable Charges(Rs./kwh)
Energy rate at EX-Bus Bar 0.89 0.89 0.95 1.01
Total Generation Charges Err:522 Err:522 Err:522 Err:522
Per unit Generation Charges ( Nominal Tariff ) Err:522 Err:522 Err:522 Err:522

Total Generation Unit (MU) per Year 1314.0 657.6 1314.0 1314.0 1314.0
PLF 85.0%
Actual Unit Generated (MU) 1116.9 559.0 1116.9 1116.9 1116.9
Monthly Generation Unit (MU) 93.1
Annual Receivables Err:522 Err:522 Err:522 Err:522
Monthly Receivables Err:522 Err:522 Err:522 Err:522

Discount rate 10.19%


Discounting Factor 0.91 0.82 0.75 0.68

∑Discounting Factor 8.95


Nominal Tariif x Discounting Factor Err:522 Err:522 Err:522 Err:522

Levelised Tariff Err:522


OWER PLANT FINANCIAL MODEL

ALCULATION SHEET
ALL VALUES IN Rs.Cr.

5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0
2016-17 2017-18 2018-19 2019-20 2020-2021 2021-22 2022-2023 2023-24 2024-25 2025-26

34.94 30.35 25.77 21.19 16.61 12.03 7.45 2.86 0.00 0.00
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16
15.01 15.87 16.78 17.75 18.77 19.85 20.99 22.20 23.47 24.82
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

101.88 108.00 114.48 121.35 128.63 136.34 144.53 153.20 162.39 172.13
5.29 5.66 6.06 6.49 6.94 7.43 7.94 8.50 9.10 9.73
107.18 113.66 120.54 127.83 135.57 143.77 152.47 161.70 171.49 181.87

1.07 1.13 1.20 1.27 1.35 1.43 1.52 1.61 1.71 1.81
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

1314.0 1314.0 1314.0 1314.0 1314.0 1314.0 1314.0 1314.0 1314.0 1314.0

1116.9 1116.9 1116.9 1116.9 1116.9 1116.9 1116.9 1116.9 1116.9 1116.9

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

0.62 0.56 0.51 0.46 0.42 0.38 0.34 0.31 0.28 0.26
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
15.0 16.0 17.0 18.0 19.0 20.0 21.0 22.0 23.0 24.0
2026-27 2027-28 2028-29 2029-30 2030-31 2031-32 2032-33 2033-34 2034-35 2035-36

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16
26.25 27.76 29.35 31.04 32.83 34.71 36.71 38.82 41.05 43.41
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

182.46 193.41 205.01 217.31 230.35 244.17 258.82 274.35 290.81 308.26
10.41 11.14 11.92 12.76 13.65 14.61 15.63 16.72 17.89 19.15
192.87 204.55 216.94 230.07 244.00 258.78 274.45 291.08 308.71 327.41

1.92 2.03 2.16 2.29 2.43 2.57 2.73 2.90 3.07 3.26
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

1314.0 1314.0 1314.0 1314.0 1314.0 1314.0 1314.0 1314.0 1314.0 1314.0

1116.9 1116.9 1116.9 1116.9 1116.9 1116.9 1116.9 1116.9 1116.9 1116.9

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

0.23 0.21 0.19 0.17 0.16 0.14 0.13 0.12 0.11 0.10
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
25.0
2036-37

0.00
Err:522
0.16
45.91
Err:522
Err:522
Err:522

326.76
20.49
347.24

3.45
Err:522
Err:522

1314.0

1116.9

Err:522
Err:522

0.09
Err:522
3x50 MW THERMAL PO

P
A

1 2 3 4 5
Year of Operation 2012-13 2013-14 2014-15 2015-16 2016-17

Revenue generated from sales Err:522 Err:522 Err:522 Err:522 Err:522


less- Expenses

O&M Expenses 12.0 12.7 13.4 14.2 15.0


Cost of Coal 42.8 85.5 90.7 96.1 101.9
Cost of Secondary Fuel 2.2 4.3 4.6 4.9 5.3
Total Expenses 57.0 102.6 108.7 115.3 122.2

less-Depreciation

Depreciation Err:522 Err:522 Err:522 Err:522 Err:522

PBIT Err:522 Err:522 Err:522 Err:522 Err:522

less- Interest

Interest on Loan 50.4 48.7 44.1 39.5 34.9


Interest on Working Capital Err:522 Err:522 Err:522 Err:522 Err:522

Total interest Err:522 Err:522 Err:522 Err:522 Err:522

PBT Err:522 Err:522 Err:522 Err:522 Err:522


Carry of Loss( if any ) Err:522 Err:522 Err:522 Err:522 Err:522

Calculation of Book Profit

PBT+Depreciation Err:522 Err:522 Err:522 Err:522 Err:522

Initial Book Value Err:522 Err:522 Err:522 Err:522 Err:522


less- Depreciation as per IT Act 7.84% Err:522 50.2 50.2 50.2 50.2
Taxable PBT Err:522 Err:522 Err:522 Err:522 Err:522
Total Corporate Tax Payable 33.99% Err:522 Err:522 Err:522 Err:522 Err:522
Minimum Alternative Tax 11.22% Err:522 Err:522 Err:522 Err:522

PAT Err:522 Err:522 Err:522 Err:522


THERMAL POWER PLANT FINANCIAL MODEL

P&L ACCOUNT
ALL VALUES IN Rs. Cr.

6 7 8 9 10 11 12 13 14 15
2017-18 2018-19 2019-2020 2020-21 2021-22 2022-2023 2023-24 2024-25 2025-26 2026-27

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

15.9 16.8 17.7 18.8 19.8 21.0 22.2 23.5 24.8 26.2
108.0 114.5 121.3 128.6 136.3 144.5 153.2 162.4 172.1 182.5
5.7 6.1 6.5 6.9 7.4 7.9 8.5 9.1 9.7 10.4
129.5 137.3 145.6 154.3 163.6 173.5 183.9 195.0 206.7 219.1

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

30.4 25.8 21.2 16.6 12.0 7.4 2.9


Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 0.0 0.0
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
16 17 18 19 20 21 22 23 24 25
2027-28 2028-29 2029-30 2030-31 2031-32 2032-33 2033-34 2034-35 2035-36 2036-37

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

27.8 29.4 31.0 32.8 34.7 36.7 38.8 41.1 43.4 45.9
193.4 205.0 217.3 230.4 244.2 258.8 274.4 290.8 308.3 326.8
11.1 11.9 12.8 13.7 14.6 15.6 16.7 17.9 19.1 20.5
232.3 246.3 261.1 276.8 293.5 311.2 329.9 349.8 370.8 393.2

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
3x50 MW THERMA

CA

CASH FLOW
Inflow 0 1 2 3 4
PAT Err:522 Err:522 Err:522
Depreciation Err:522 Err:522 Err:522 Err:522
Equity 180.0
Debt 420.0
Increase in Working Capital Err:522 Err:522 Err:522 Err:522

Total Cash Inflow 600.0 Err:522 Err:522 Err:522 Err:522


Outflow
Capital Expenditure 600.0
Loan Repayment 0.0 38.2 38.2 38.2
Increase in Current Asset Err:522 Err:522 Err:522 Err:522

Total Cash Outflows 600.0 Err:522 Err:522 Err:522 Err:522

Opening Balance 0.0 0.0 Err:522 Err:522 Err:522


Net Cashflow 0.0 Err:522 Err:522 Err:522 Err:522
Closing Balance 0.0 Err:522 Err:522 Err:522 Err:522
MW THERMAL POWER PALNT FINANCIAL MODEL

CASH FLOW STATEMENT


ALL VALUES IN Rs. CRORE

5 6 7 8 9 10 11 12 13 14
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

38.2 38.2 38.2 38.2 38.2 38.2 38.2 38.2


Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
15 16 17 18 19 20 21 22 23 24
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
25
Err:522
Err:522

Err:522

Err:522

Err:522

Err:522

Err:522
Err:522
Err:522
3X50 MW THERM

1 2 3 4 5 6
Year of Operation 2012-13 2013-14 2014-15 2015-2016 2016-17 2017-18

Liabilities

EQUITY 180.0 180.0 180.0 180.0 180.0 180.0


RESERVES & SURPLUS Err:522 Err:522 Err:522 Err:522 Err:522
NET WORTH 180.0 Err:522 Err:522 Err:522 Err:522 Err:522
DEBT 420.0 420.0 420.0 420.0 420.0 420.0
WORKING CAPITAL Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

TOTAL LIABILITIES Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Asset

GROSS BLOCK 600.0 Err:522 Err:522 Err:522 Err:522 Err:522


DEPRECIATION Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
NET BLOCK Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
CASH & BANK BALANCE Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
CURRENT ASSET Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

TOTAL ASSET Err:522 Err:522 Err:522 Err:522 Err:522 Err:522


0 MW THERMAL POWER PLANT FINANCIAL MODEL

BALANCE SHEET

7 8 9 10 11 12 13 14 15 16
2018-19 2019-2020 2020-21 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 2027-28

180.0 180.0 180.0 180.0 180.0 180.0 180.0 180.0 180.0 180.0
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
420.0 420.0 420.0 420.0 420.0
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
17 18 19 20 21 22 23 24 25
2028-29 2029-30 2030-31 2031-32 2032-33 2033-34 2034-35 2035-36 2036-37

180.0 180.0 180.0 180.0 180.0 180.0 180.0 180.0 180.0


Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522


Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522


3x50MW THER

0 1 2 3 4
Year of Operation
2011-12 2012-13 2013-14 2014-15 2015-16

Total (Cash Inflow - Cash Outflow)

PAT 0.0 Err:522 Err:522 Err:522


DEPRECIATION 0.0 Err:522 Err:522 Err:522 Err:522
INTEREST 0.0 Err:522 Err:522 Err:522 Err:522
PAT+DEPRECIATION+INTEREST -600.0 Err:522 Err:522 Err:522 Err:522

-600.0 Err:522 Err:522 Err:522 Err:522


DISCOUNT RATE 10.19%
NPV Err:522
IRR Err:522

CALCULATION OF WACC 0 1 2 3 4
2011-12 2012-13 2013-14 2014-15 2015-16

Weight of Debt 0.70 0.70 0.70 0.70


Weight of Equity 0.30 0.30 0.30 0.30
Cost of Debt ( Repayment Period ) 0.12 0.12 0.12 0.12
Cost of Equity 0.16 0.16 0.16 0.16
Cost of Debt ( After Repayment )
Cost of Capital 0.13 0.13 0.13 0.13

WACC 0.12

33.99%

DSCR CALCULATION
Year 0.0 1.0 2.0 3.0 4.0
DEPRECIATION 0.0 Err:522 Err:522 Err:522 Err:522
INTEREST ON LOAN 0.0 50.4 48.7 44.1 39.5
PAT 0.0 0.0 Err:522 Err:522 Err:522
REPAYEMENT OF LOAN 0.0 0.0 38.2 38.2 38.2
NET OPERATING INCOME (NOI) 0.0 Err:522 Err:522 Err:522 Err:522
TOTAL DEBT SERVICE 0.0 50.4 86.9 82.3 77.7
DSCR (Debt Service Coverage Ratio) 0.0 Err:522 Err:522 Err:522 Err:522
AVERAGE DSCR Err:522

Loan Duration 12.0 years


3x50MW THERMAL POWER PLANT FINANCIAL MODEL

NPV & IRR CALCULATION


ALL VALUES IN RS. Cr

5 6 7 8 9 10 11 12 13 14
2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24 2024-25 2025-26

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

5 6 7 8 9 10 11 12 13 14
2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24 2024-25 2025-26

0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70
0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30
0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12
0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16
0.08 0.08
0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.10 0.10

5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
34.9 30.4 25.8 21.2 16.6 12.0 7.4 2.9 0.0 0.0
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
38.2 38.2 38.2 38.2 38.2 38.2 38.2 38.2 0.0 0.0
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
73.1 68.5 64.0 59.4 54.8 50.2 45.6 41.0 0.0 0.0
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 0.0 0.0
15 16 17 18 19 20 21 22 23 24
2026-27 2027-28 2028-29 2029-30 2030-31 2031-32 2032-33 2033-34 2034-35 2035-36

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

15 16 17 18 19 20 21 22 23 24
2026-27 2027-28 2028-29 2029-30 2030-31 2031-32 2032-33 2033-34 2034-35 2035-36

0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70
0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30

0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16
0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08
0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10

15.0 16.0 17.0 18.0 19.0 20.0 21.0 22.0 23.0 24.0
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
25
2036-37

Err:522
Err:522
Err:522
Err:522

Err:522

25
2036-37

0.70
0.30

0.16
0.08
0.10

25.0
Err:522
0.0
Err:522
0.0
Err:522
0.0
0.0
Years of Operation 1 2 3 4 5 6
Variable Cost 44.97 89.87 95.30 101.07 107.18 113.66
Fixed Cost Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Average Fixed Cost 73.33 73.33 73.33 73.33 73.33 73.33
Total Cost Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Total Revenue Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Actual Generated MU 558.96 1116.90 1116.90 1116.90 1116.90 1116.90
Cumulative Actual Generated MU 558.96 1675.86 2792.76 3909.66 5026.56 6143.46
Cumulative Total Cost Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Cumulative Total Revenue Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

1.00
Cumulative Total Cost

0.90

0.80

0.70

0.60

0.50

0.40

0.30

0.20

0.10

0.00 0.00 0.00 0.00 0.00 0


558.96 1675.86 2792.76 3909.66 5026
7 8 9 10 11 12 13 14 15 16
120.54 127.83 135.57 143.77 152.47 161.70 171.49 181.87 192.87 204.55
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
73.33 73.33 73.33 73.33 73.33 73.33 73.33 73.33 73.33 73.33
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
1116.90 1116.90 1116.90 1116.90 1116.90 1116.90 1116.90 1116.90 1116.90 1116.90
7260.36 8377.26 9494.16 10611.06 11727.96 12844.86 13961.76 15078.66 16195.56 17312.46
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

BEP

0.00 0.00 0.00 0.00 0.00 0.00


3909.66 5026.56 6143.46 7260.36 8377.26 9494.16
17 18 19 20 21 22 23 24 25
216.94 230.07 244.00 258.78 274.45 291.08 308.71 327.41 347.24
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
73.33 73.33 73.33 73.33 73.33 73.33 73.33 73.33 73.33
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
1116.90 1116.90 1116.90 1116.90 1116.90 1116.90 1116.90 1116.90 1116.90
18429.36 19546.26 20663.16 21780.06 22896.96 24013.86 25130.76 26247.66 27364.56
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522
Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522 Err:522

0.00 0.00
9494.16 10611.06

You might also like