Professional Documents
Culture Documents
A- Earlier usually people used to do SA after the bldg is very old or beforedemolishing it
to build a new. Now a days SA after 25yrs first n thereafter every 5yr is
recommended.
A- It depends whether audit is supported with NDT or how. What's a purpose of audit,
size of building etc. Normally people charge Rs. 5000 to 15000 for one bldg.
And about time SA takes about 20 to 30 mins per flat n about 1hr to observe Bldg
from outside, terrace, tanks etc.
To write a good report another one or two days
Q.6)Mumbai has many residential buildings which are over 30 yrs. As per new bmc rules
it is clear that builders will redevelop the buildings in good locality where they will get
handsome rates...so what abt the buildings which r deteriorated? Ndt is allowed only in
the parking area n generally results r devasting i.e If m15 n ph around 8 n velocity very
poor then how to actually repair the buildung?
Epoxy mortar/grouting/jacketing or
steel plate strengthening (very Costly)
Q.8) Do we carry out re analysis based on current Ast (if steel is corroded)?
A-IIT Kanpur (nicee and sefi) people keep suggesting for analysis based SA n R.
Software like SAP etabs are facilities to do so. But large test based inputs are
needed from sites which may incurr additional costs and in some cases restrict the
same/.
Q-11) One another issue fased while Auditing old Bldgs (which were not designed for
EQ) where n how the repair will b done. . .or is just repair adequate or retrofitting needed
?
A- Rectification of damaged walls is yet another area which needs special attention &
Detailing.
Wall of three types
1) load bearing brick masonry
2) infill masonry walls
3) RCC Structural walls (3.a shear wall n 3.b box system)
A- M/s. Afcons had done the work of placing new foundations below existing columns,
and increased one basement below existing. That was for Piramal at Tardeo
They used micropiles to relieve load temporarily from existing columns, did new
foundations, then transferred the load from micropiles to new foundations.
Q-15) what is the limit to which Fibre wrapping can increase Strength?
Q-16) What is the cost for Fibre Wrapping of Columns & Beams?
Q-17) Is there any Break even analysis so as to decide after investing in the usable
Q-18) What is the upper bound limit & minimum adhesive strenght of Adhesives used
for wrapping Fibers?
Q-20) What is the method by which The Old Arch Bridges on Mumbai Pune Expressway
Retroffited by Steel Sections Placed below Arch & Anchored in Overlay Slab ?
Q-21) what is the Liability of Structural stability certificate to Fire & other man made
Hazards like Fire?
References:
ISSE has conducted a couple of short n long seminars on Strucural Audit; they
have also published a (can be purchased from Dadar office)
IRC SP 70-
accommodationtimes.com/structural-audit-of-society-buildings/
Relevant Codes:
Velocity.
Concrete Buildings.
(Fourth Revision).
be helpful.
deflection or corrosion.
10. Leakages & dampness in walls resulting into cracks and corrosion.
12. Status of lift and lift machine room – Type of Maintenance Contract, renewal
of license.
13. Status of electrical wiring from meter room to all the flats. Substation status.
14. Status of overhead & underground water tanks - capacity. Leakages, cracks
15. Plinth protection in the compound including status of drainage, water pipes
& pumps. How much the Ground was flooded during recent monsoons?
16. External paint – When last painted and type of paint.
The following NDT tests are required to be carried out on structural elements.
However,
building/structure :
1. Core tests to determine the estimated equivalent in situ compressive strength &
to
establish correlation between Rebound hammer test & in situ strength of concrete.
concrete.
Description:
_______________________________________________________________
Address:
__________________________________________________________________
Society Name:
_____________________________________________________________
OBSERVATIONS
1. FOUNDATION STRATA
· VISUAL INSPECTION
· SETTLEMENT OF COLMNS
· SETTLEMENT OF WALLS
PLINTH
4. TOILET LEAKAGES,CRACKS,
INSPECTION
FLOOR SLAB
TERRACE
8. INSPECTION OF UNDERGROUND
WATER TANK
· DATE
ENQUIRY
EARTHQUAKE
COMPRESSION TESTING
FOR STEEL
24. CONCLUSION: