ANNEX N
QUALITY REQUIREMENTS
ANNEX N
QUALITY REQUIREMENTS
TABLE OF CONTENTS
ANNEX N
QUALITY REQUIREMENTS
Narrative details of controls and verifications to be put in place to assure quality during
each stage of the Engineering, Procurement, Construction and Commissioning.
ANNEX N
QUALITY REQUIREMENTS
submitted to CLIENT together with the CVs of key staff such as QA Managers
and QC Managers for Home Office and field locations as applicable. An
Organization Chart shall be submitted showing reporting lines and manning
levels for the QA and QC operations.
c) Rev. A - Document and Data Control Procedure to control status and ensure
only the latest reviewed revision of data and documents are available for the
work.
d) Rev. A - Procedures and instructions for the control and verification of design
documents and design activities, including design changes at Home Office
and Field locations. Field design changes procedure shall be available to
CLIENT and utilized for all design changes after any document and/or
drawing has been issued for construction. Where field design deviations are
involved, a system shall be established to ensure that each deviation is
traceable to the individual MECHANICAL COMPLETION package so that all
accepted changes are verified as complete.
ANNEX N
QUALITY REQUIREMENTS
l) Methods for the identification and traceability of materials and equipment from
design and throughout installation.
This element shall be incorporated into quality programs; however, for all
pressure containing and load bearing materials, a minimum of EN 10204 3.1b
certification shall be required.
o) Methods for inspection and testing of materials and equipment at the storage
locations and the SITE.
p) Methods for the control, storage, and calibration of inspection, measuring and
test equipment.
q) Methods for tracking the inspection and test status of materials and equipment.
u) Procedure and plan for performing and documenting internal audits of quality
related activities and external audits of SUBCONTRACTORS and
VENDORS.
ANNEX N
QUALITY REQUIREMENTS
z) The PROJECT Quality Plan and related procedures as described above shall
be submitted for review and comment within twenty (20) days of the execution
of the AGREEMENT, otherwise work shall not be allowed to continue.
2.0 AUDITS
QC staff shall not be involved as auditors since they are not independent and the
audits shall include evaluation of performance and effectiveness of QC.
All SUBCONTRACTORS and VENDORS must have previous audit records or quality
verification evidence satisfactory to CLIENT before award of Sub-contracts and/or
Purchase Orders.
ANNEX N
QUALITY REQUIREMENTS
In addition, CLIENT will also perform a minimum of four (4) Quality, Technical, and
Construction compliance audits at CONTRACTOR’S facility or on SITE. CLIENT will
advise CONTRACTOR at least ten (10) days in advance of audits, except for the
occasional spot audit. CONTRACTOR shall provide assistance and access to its
systems and SUBCONTRACTOR and VENDOR systems as required. Any
deficiencies noted shall be immediately rectified by CONTRACTOR.
In order to ensure all the design and specification areas are addressed and meet the
requirements of the PROJECT, CONTRACTOR will be required, after the award of
the AGREEMENT to carry out full criticality assessment exercises on every discipline
area and/or system to enable individual quality programs to be developed.
This will involve development of a procedure to evaluate the risk and consequence of
structure, containment, and equipment or material failure to personnel safety, the
environment and continuous operational availability of the facility.
It shall also take into account, with documentation, new and special manufacturing
considerations, difficulties and requirements for any special controls.
The results of the assessment shall be used to develop the minimum quality
assurance and quality control requirements to be applied during Engineering,
Procurement and Construction activities for each level of criticality.
It should be noted that this may involve higher levels of control above standard code
requirements in high criticality areas and may involve upgrading details from other
areas of the standard project conditions, EXHIBITS, etc.
4.1 GENERAL
Rev. 1 - The execution of VENDOR and SITE Quality Control shall be fully
documented in procedures to be reviewed by CLIENT. These shall include, but not
be limited to, the minimum requirements included in the relevant specifications and in
this ANNEX.
Rev. A - No VENDOR or construction work shall start without full acceptance of the
relevant QA and QC procedures with all comments incorporated. Reviewed to a
minimum of "Comments Noted" by CLIENT (reviewed with comments) may be
accepted where CONTRACTOR can fully demonstrate to CLIENT that such
documents are distributed and comments complied with at the work locations. This
will need specific written CLIENT agreement if applied.
ANNEX N
QUALITY REQUIREMENTS
CLIENT for review. CLIENT shall mark on the Inspection and Test Plan any activities
they wish to witness. All inspections shall be carried out in accordance with accepted
Inspection and Test Plans.
Hold and Witness points and the notification period associated shall be included
within the CONTRACTORS approved program.
The inspection, testing, traceability, certification, etc., requirements for each item or
activity are given in the relevant specifications.
The level of inspection specified in the Inspection and Test Plan shall reflect the
Criticality Rating subject to the minimum levels given in Attachment 002.
The report pro-forma for each inspection stage shall be attached to the Inspection
and Test Plan.
For all activities Inspection and Test Plans (ITPS) shall be developed and implemented
by CONTRACTOR, SUBCONTRACTORS and VENDORS. These shall detail the
following areas in a matrix format:
The ITP shall cover the major quality related activities in chronological order from
initial drawings through manufacturing, construction, process controls to final testing,
documentation and certification.
Against each activity and/or stage, well planned space shall be created in the
schedule provided for all PARTIES including CLIENT to mark their QC involvement.
Rev. A - CLIENT shall have the right to review all ITPs and related Procedures and
add their comment and actual witness involvement.
ANNEX N
QUALITY REQUIREMENTS
CLIENT shall have the right to witness any test. Where CLIENT has added its
involvement on an ITB it shall be given fourteen (14) days written notice of every
witness or hold point and confirmation of the stage at least forty eight (48) hours prior
to the actual activity. Any delays due to late notification or late cancellation shall be
borne by CONTRACTOR.
The provisions in this ANNEX, and generally throughout Attachments 001 and 002,
apply equally to any THIRD PARTY inspection body that CONTRACTOR may
appoint to carry out inspections on his behalf. If such is the case a procedure shall
be prepared to detail the responsibilities of THIRD PARTY inspection body and
interfaces with CONTRACTOR. This procedure shall be submitted to CLIENT. Any
such employment of a THIRD PARTY inspection body by CONTRACTOR is
separate and distinct from CLIENT employed THIRD PARTY QA/QC Surveillance.
CONTRACTOR shall put in place a release certificate scheme which identifies all
documents that are approved, there are no outstanding technical queries, non-
conformances or concessions not fully closed out and that the release inspector is
fully aware of the final document status.
The release certificate shall be used as the trigger to allow the inspector to release
the materials and equipment if he finds the final inspection acceptable and a copy of
this certificate shall be forwarded to CLIENT before release.
6.0 CONSTRUCTION QC
All activities, except simple activities as agreed upon by the PARTIES, shall be
clearly defined in the procedures and method statement detailing the technical and
actual Scope of work, how it will be performed, where it will be performed, who is
responsible for the activity, who is responsible for verifying the activity and which
record and/or verification document shall be produced.
Rev, A - All Weld Procedure and welder qualification tests shall be subject to witness
by CLIENT or CLIENT THIRD PARTY INSPECTOR.
Rev. A - All other Procedures (e.g. Bolting/Mounting) and qualification tests (e.g.
mechanic) shall be subject to witness by CLIENT or CLIENT THIRD PARTY
INSPECTOR.
ANNEX N
QUALITY REQUIREMENTS
All QC activities and listing status and/or records shall be compiled on a database
referencing the appropriate ITP, procedure and certification so that the QC status can
be continually monitored as work progresses.
CLIENT shall be provided with a weekly update of all QC problems on SITE together
with a regular and brief description of all non-conformances issued. Qualitative as
well as quantitative (schedule impacting) mitigation actions shall be defined and
followed up upon.
As part of their own Quality System, CLIENT will operate their own non-conformance
reporting to CONTRACTOR. On receipt of CLIENT non-conformance reports,
CONTRACTOR shall prepare a corrective action plan within three (3) days. Where
such non-conformances are identified as major, the affected work shall be
suspended.
Rev.A1 - Where CLIENT has concerns over the quality of the WORK, it shall have
the right to re-test. Where work is covered over, the re-test shall include removal of
covering. No work shall be covered without the accepted procedures and ITPs being
followed, therefore MECHANICAL COMPLETION shall not be confirmed until all QC
activities are signed off.
CONTRACTOR shall use its own independent inspectors and not be reliant on
CLIENT’S third party inspectors. CONTRACTOR shall provide adequate QA/QC staff
to identify discrepancies. Large numbers of SITE discrepancies and punch-list items
raised by CLIENT is an indication of inadequate CONTRACTOR QA/QC coverage.
In such a case, it is up to the CLIENT to decide to exchange CONTRACTOR
personnel immediately with more, CLIENT accepted, qualified personnel.
ANNEX N
QUALITY REQUIREMENTS
Develop a list of method statements for all critical activities. Method statements shall
be reviewed and developed into quality control procedures for SITE control, with
input from Engineering and Construction.
CONTRACTOR shall submit, with their QA/QC Plan, their training methodology for
CLIENT’S review and acceptance.
7.1 GENERAL
7.2 CO-ORDINATION
Radiography and NDE work shall be performed in compliance with the requirements
of PROJECT specifications.
ANNEX N
QUALITY REQUIREMENTS
ANNEX N
QUALITY REQUIREMENTS
CONTRACTOR shall ensure that its inspection procedures and plans comply with
these requirements.
This milestone has not been achieved until all QC checks have been completed and
signed off. All punch list items shall be identified and all critical activities (Punch list
A and B items) cleared.
CONTRACTOR shall put in place procedures during the design stage which plan and
identify all system tests required and ensures that each activity is formally verified by
signed documentation and/or certification.
All systems shall be fully punched out by CONTRACTOR before being offered for
MECHANICAL COMPLETION.
Where CLIENT identifies significant extra punch list items, CLIENT staff time shall be
back-charged to CONTRACTOR and if this cannot be resolved, CONTRACTOR shall
employ an approved THIRD PARTY to punch out the remaining work.
CLIENT sign off of all appropriate documents shall be made before any system is
energized for testing.
Rev. A - CONTRACTOR will be given details of the THIRD PARTY and its
involvement once the criticality assessment exercise is complete and accepted.
CONTRACTOR shall provide the THIRD PARTY with copies of all construction SITE
QA and QC documents and keep them regularly updated with all revisions
throughout the course of the WORK.
ANNEX N
QUALITY REQUIREMENTS
The following represent minimum requirements for achieving quality for Engineering
work:
1. Review the basic engineering, including the Basic Design Engineering.
Any deficiencies found after execution of the AGREEMENT shall be
considered as Standard Engineering Development.
2. Review the scope that was used during Basic Design prepare studies,
update and/or prepare new documents and drawings as required for
detailed engineering.
3. Review all existing survey data and carry out additional surveys as
CONTRACTOR deems necessary.
4. CONTRACTOR shall establish and implement procedures to control and
verify the Design Engineering (including HSE-in-Design) and Procurement
phases of the WORK to ensure that all AGREEMENT requirements are
met.
5. Design and engineering deliverables / sets of deliverables shall be
rigorously discipline checked and inter-discipline checked. Documented
evidence shall be kept in file.
6. CONTRACTOR shall develop and execute a schedule of formal multi-
disciplinary / multi-functional design reviews with involvement of all
relevant stakeholders (model reviews, HAZOPs, Constructability reviews
etc.)
7. CONTRACTOR shall document the way site specific codes and standards
will be analyzed in conjunction with the AGREEMENT requirements and
CONTRACTOR’S internal standards to ensure that the engineering
design will comply with the AGREEMENT requirements, sound and
generally accepted practices, and regulatory and authority requirements.
8. CONTRACTOR shall document how the SUPPLIER documents will be
reviewed for being consistent with engineering design and for compliance
with the applicable standards.
9. CONTRACTOR shall define the level of review and approval of all
AGREEMENT design / scope of work documents.
10. CONTRACTOR shall ensure that the individual responsibility for each
level of review and approval will be identified and exercised.
11. Rev. A - CONTRACTOR shall present identified engineering and design
documents to CLIENT for review.
12. Rev. A - CONTRACTOR shall ensure that design documents prepared by
SUBCONTRACTORS and SUPPLIERS that require review by CLIENT
are first reviewed an approved by CONTRACTOR.
13. CONTRACTOR shall provide procedures to control design changes and
to ensure that the level of verification is equal to the original design.
14. CONTRACTOR shall keep a register of all Design Engineering
documents.
ANNEX N
QUALITY REQUIREMENTS
15. CONTRACTOR shall document the flow of QA/QC documents along the
various stakeholders such as CONTRACTOR internal functions, other
CONTRACTORS and CLIENT. Also filing and retrieval shall be
addressed.
16. The document identification shall include a revision number which is
incremented after each change. The revision number shall be included in
the master register to record the current revision of each document.
17. CONTRACTOR shall ensure that users of documents have access to the
latest master register to verify that the document in question is current and
latest revision available.
18. CONTRACTOR shall ensure that all documents for which CONTRACTOR
is responsible can be recognized as approved, or otherwise, and this
without the need to refer to a second listing.
19. CONTRACTOR shall publish the names, signatures and initials of those
responsible for approval of documents and shall state the extent of
authority of each signatory.
20. Documents including data files shall be kept secure and unauthorised
access prevented.
21. Output from computer calculations shall be checked by alternative
calculations methods.
22. The integrity and status of computer models stored on computer media
shall be protected and preserved.
23. A register of design software shall be maintained. Design software for
engineering calculations shall be validated and controlled.
24. Rev. A - Prepare the detailed engineering documents, drawings, design
and purchasing specifications, which shall be in strict accordance with the
specifications. Any deviation between CONTRACTOR’S design and
purchasing specifications and the technical specifications, requires review
by CLIENT.
25. Prepare PROJECT specific Quality Assurance/Quality Control
procedures.
26. Obtain pertinent data and information related to the existing facilities
through SITE visits for developing and verifying drawings and interfaces
with details for all engineering disciplines.
27. Conduct hazardous operations (“HAZOP”) studies and piping and
instrumentation drawing (“P&ID”) reviews in CONTRACTOR’S Home
Offices or other location agreed with CLIENT.
28. Prepare required equipment, line and valve lists. Provide regular monthly
list updates throughout the PROJECT highlighting changes from the
previous issue.
29. Review VENDORS’ and SUBCONTRACTORS’ data, drawings and other
documentation for all goods and services to ensure conformity with the
specifications. Incorporate the relevant details into CONTRACTOR’S own
design deliverables.
30. Witness performance tests at VENDORS’ shops for all major equipment
and packages.
ANNEX N
QUALITY REQUIREMENTS
11.0 ATTACHMENTS
ATTACHMENT 001
1.0 PURPOSE
2.0 SCOPE
5.0 REFERENCES
ATTACHMENT 002
SAMPLE 001 A
Plant No.:
Item No.:
Drawing:
Concrete Type:
Inspection Complete:
Checked By
Contractor:
CLIENT:
QC Inspector:
Date:
SAMPLE 001 B
Area: CIVIL:
Coordinates: E & I:
MECHANICAL:
ITEM CONSTRUCTI QUALITY REMARKS
ON CONTROL
FORM WORK:
Dimensions
Elevations
Chamfer
Clean
REINFORCING STEEL:
Clearances
Spacing of Steel
Bar Size
Proper Lap
Secure
Clean
EMBEDDED ITEMS:
Anchor bolts, angles, channels, etc.
(structural)
INSPECTED CONSTRUCTION DA
BY: TE
QUALITY DA
CONTROL TE
SAMPLE 002
INCLUDED: SAG
FOR OPERATING DRIVE DRIVEN
TEMP: R
SAMPLE 003
SAMPLE 003
SAMPLE 003
SAMPLE 003
SAMPLE 003
SAMPLE 004
SAMPLE 004
SAMPLE 004