AUN ENTERPRISES asd proj

Activity ID Activity Name Original Start Finish Total Predecessors 2018


Duration Float
Jul Aug Sep
asd proj 37d 16-Jul-18 07:00 04-Sep-18 06:00 0d
AM PM
Technical specification 13d 16-Jul-18 07:00 AM 01-Aug-18 06:00 PM 0d
A1000 approval to bid 0d 16-Jul-18 07:00 AM 0d
A1010 Determine installation Requirements 4d 16-Jul-18 07:00 AM 19-Jul-18 06:00 PM 0d A1000
A1020 Create Techinical Specification 5d 20-Jul-18 07:00 AM 26-Jul-18 06:00 PM 0d A1010
A1030 identify Supplier Components 2d 27-Jul-18 07:00 AM 30-Jul-18 06:00 PM 0d A1020
A1040 Validate tecchinical Specification 2d 31-Jul-18 07:00 AM 01-Aug-18 06:00 PM 0d A1030
Delivery plan 18d 31-Jul-18 07:00 AM 23-Aug-18 06:00 PM 0d

A1050 Document delivery Methofolgy 3d 02-Aug-18 07:00 AM06-Aug-18 06:00 PM 0d A1040


A1060 Obtain Quotes from Suplpliers 3d 31-Jul-18 07:00 AM 02-Aug-18 06:00 PM 2d A1030
A1070 Calculate the Bid Estimate 4d 07-Aug-18 07:00 AM10-Aug-18 06:00 PM 0d A1050, A1060
A1080 Create the project schedule 8d 13-Aug-18 07:00 AM22-Aug-18 06:00 PM 0d A1070
A1090 Review the delivery plan 1d 23-Aug-18 07:00 AM23-Aug-18 06:00 PM 0d A1080
Bid document 21d 07-Aug-18 07:00 AM04-Sep-18 06:00 PM 0d

A1100 create draft of bid document 4d 07-Aug-18 07:00 AM10-Aug-18 06:00 PM 9d A1050
A1110 Review bid document 0d 23-Aug-18 06:00 PM 0d A1090, A1100
A1120 Finalize and sumbit bid documents 2d 24-Aug-18 07:00 AM27-Aug-18 06:00 PM 0d A1110
A1130 bid documents submitted 6d 28-Aug-18 07:00 AM04-Sep-18 06:00 PM 0d A1120

Remaining Level of Effort % Complete Date Revision Checked Approved


  30-Jun-11 1a PEH
Actual Level of Effort Summary
Actual Work Float Bar
Remaining Work Neg Float Bar
Critical Remaining Work