ENGINEERING PROCEDURE
PDVSA N° TITLE
APPD.BY Alexis Arévalo DATE NOV.00 APPD.BY Enrique Carmona DATE NOV.00
E1994 ESPECIALISTAS
ENGINEERING PROCEDURE PDVSA L–TP–2.2
PDVSA
REVISION FECHA
PROCUREMENT CHECK LIST FOR
PROGRESSING CAVITY PUMPS (PCP) 0 NOV.00
Página 1
.Menú Principal Indice manual Indice volumen Indice norma
Index
1 OBJETIVE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
2 PROCUREMENT CHECK LIST . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
ENGINEERING PROCEDURE PDVSA L–TP–2.2
PDVSA
REVISION FECHA
PROCUREMENT CHECK LIST FOR
PROGRESSING CAVITY PUMPS (PCP) 0 NOV.00
Página 2
.Menú Principal Indice manual Indice volumen Indice norma
1 OBJETIVE
The purpose of this Procurement Check List is to indicate Vendor Compliance with
PDVSA Engineering Specification GA–205 “General Specifications for
Progressing Cavity Pump (PCP), for Handling Crude Oils”.
PDVSA
REVISION FECHA
PROCUREMENT CHECK LIST FOR
PROGRESSING CAVITY PUMPS (PCP) 0 NOV.00
Página 3
.Menú Principal Indice manual Indice volumen Indice norma
2.8 Does your company have in–country qualified repair shops as specified in PDVSA
GA–205, paragraph 2.8?
Yes ___________Not __________
1. Do the units proposed comply with PDVSA GA–205 ?
Yes ___________Not__________
If the answer is “not”, please include a separate list titled as “Exceptions to
PDVSA’s Specifications”, indicating the exception to PDVSA’s specification and
referencing it to the appropriate paragraph number.
2. Did you include all the information requested in PDVSA GA–205,
paragraphs 6. “a” through “d” .
Yes ___________Not __________
7.5 Please indicate the following radial clearances:
a. Tubing to rod–rotor connection: _________ inches.
b. Tubing to rod couplings: _________ inches
c. Tubing to rotor: _________ inches
Additionally, please specify the minimum recommended radial clearance for safe
installation and operation: __________ inches
8.3 Please indicate the following information:
Minimum rotor chrome coat thickness: ______ inches
Rotor surface final hardness: ________ Rc
8.4 Please indicate estimated stator swelling for the crude oil indicated in the well data
sheets in percentage: _________ %
8.7 Please indicate the mechanical properties of the elastomer of the proposed
pumps:
a. Fatigue resistance > ________ cycles, according to ASTM D–430.
b. Hardness: ______ “Shore A”
c. Tensile resistance > _______ MPa
ENGINEERING PROCEDURE PDVSA L–TP–2.2
PDVSA
REVISION FECHA
PROCUREMENT CHECK LIST FOR
PROGRESSING CAVITY PUMPS (PCP) 0 NOV.00
Página 4
.Menú Principal Indice manual Indice volumen Indice norma
9.1 Did you include centralizers in your proposal to eliminate tubing or rod coupling
wear ?
Yes ___________Not __________
9.2 Did you include a drawing showing the recommended locations of the centralizer,
the rod / tubing side loading and the maximum side loading allowed before a
centralizer is used ?
Yes __________Not _________
9.3 Please indicate the recommended API grade and size of the sucker
rods:_____________
Additionally, please specify the following:
a. Maximum stress to which the sucker rods will be subjected at the design
operating point ____________ psi
b. Maximum allowable stress for the proposed sucker rod ___________ psi
9.4 Did you include a drawing with the dimensions of the proposed tubing anchor ?
Yes ____________Not ___________
9.6 Please include a table with the following information:
a. Well name.
b. Percentage of natural separation efficiency calculated.
c. Free gas by volume (in BPD) to enter the gas separator at design flow.
d. Total fluid volume (in BPD) to enter the gas separator at design flow.
e. Separator efficiency.
f. Free gas by volume (in BPD) to enter to the progressing cavity pump.
ENGINEERING PROCEDURE PDVSA L–TP–2.2
PDVSA
REVISION FECHA
PROCUREMENT CHECK LIST FOR
PROGRESSING CAVITY PUMPS (PCP) 0 NOV.00
Página 5
.Menú Principal Indice manual Indice volumen Indice norma
Additionally, specify the maximum percentage of free gas by volume that can be
handled by the proposed pump : ________________ %
10.1 Please specify the drive head axial load capacity __________ in lbs at ______
RPM
10.2 Please specify the following information for the drive head:
a. Radial bearings L10 life at rated speed _________ hrs
b. Thrust bearing L10 life at rated speed and rated axial load _________ hrs
Please specify the following information:
a. Weight of the proposed rod string _______ lbs
b. Rotor crest to crest diameter: ________ inches
c. Pump suction pressure _________ psig
d. Pump discharge pressure ________ psig
e. Axial load that will be supported by thrust bearing of drive head _______ lbs
10.3 Will the bearings be lubricated by a standard ISO VG mineral oil ?
Yes __________Not _____________
Please indicate the type of oil proposed to lubricate the drive head: __________
10.4 Does the drive head have seals to avoid the entrance of dust or rain water?
Yes _____________Not __________
10.5 Does the proposed drive head has a sight gage to visualize the oil level within the
drive head ?
Yes _____________Not ___________
10.6 Does the drive head have lifting lugs capable of taking the full string weight?
Yes _____________Not ___________
Please indicate the lifting lugs load capacity: ________ lbs
10.7 Did you include a drawing of the stuffing box of the drive head including a
description of the type of packing used ?
Yes _____________Not ___________
Type of packing: _________________________
10.8 Does the proposed drive head have an anti back–spin device to control any
backward rotation ?
ENGINEERING PROCEDURE PDVSA L–TP–2.2
PDVSA
REVISION FECHA
PROCUREMENT CHECK LIST FOR
PROGRESSING CAVITY PUMPS (PCP) 0 NOV.00
Página 6
.Menú Principal Indice manual Indice volumen Indice norma
PDVSA
REVISION FECHA
PROCUREMENT CHECK LIST FOR
PROGRESSING CAVITY PUMPS (PCP) 0 NOV.00
Página 7
.Menú Principal Indice manual Indice volumen Indice norma
12.3 Please specify the following information for the electric motor:
a. Radial bearings L10 life at rated speed and rated horsepower _______ hrs
b. Thrust bearing L10 life at rated speed and rated horsepower _________ hrs
12.4 Will motor bearings be grease lubricated?
Yes __________Not ___________
Does the proposed motor have grease fitting for lubricating the bearings and a
grease relief valve to avoid overfilling it ?
Yes __________Not __________
Please indicate the type of grease proposed for the electric motor:
Thickener type __________ soap Consistency No. ____________
12.5 Did you select the motor nameplate horsepower according to PDVSA GA–205,
paragraph 12.5 ?
Yes _________Not _________
Please include the following information:
a. Horsepower required by the pump at design operating point __________
HP
b. Horsepower required to move the rod string in the fluid: _________ HP
c. Horsepower required to move the rods through the centralizers _________
HP
d. Horsepower required by drive head _________ HP
e. Horsepower required by speed reducer _________ HP
13.1 Characteristics of the input side of the VFD:
Nominal Voltage: _______ VAC
Voltage Regulation: + _____ %, – _____ %
Operating Frecuency: ________ Hz ± ____ Hz
Number of Phases: ____
Type and characteristics of transient protection devices:_________________
13.2 Rated Capacity: ___________ KVA
Operating Temperature: From _____ to _____ °C
Storage Temperature: From _____ to _____ °C
Humidity: ______ % non–condensing, ______ % condensing
ENGINEERING PROCEDURE PDVSA L–TP–2.2
PDVSA
REVISION FECHA
PROCUREMENT CHECK LIST FOR
PROGRESSING CAVITY PUMPS (PCP) 0 NOV.00
Página 8
.Menú Principal Indice manual Indice volumen Indice norma
13.6.a Does the VFD have a control panel, with a LCD display and keypad, to monitor
and/or set all the parameters considered necessary to operate the VFD?
Yes ____Not ____
13.6.b Please specify below the characteristics of the control panel display and keypad:
Number of lines: _____
Number of characters per line: _____
Option for night–light: _______
Display information: ____________________
ENGINEERING PROCEDURE PDVSA L–TP–2.2
PDVSA
REVISION FECHA
PROCUREMENT CHECK LIST FOR
PROGRESSING CAVITY PUMPS (PCP) 0 NOV.00
Página 9
.Menú Principal Indice manual Indice volumen Indice norma
PDVSA
REVISION FECHA
PROCUREMENT CHECK LIST FOR
PROGRESSING CAVITY PUMPS (PCP) 0 NOV.00
Página 10
.Menú Principal Indice manual Indice volumen Indice norma
13.11.b Does the VFD enclosure has an inner door (120° opening) to access the VFD
directly for maintenance purposes?
Yes ____Not ____
13.11.c Does the input circuit breaker or disconnect fused switch have an external hand
operator with breaker or switch in off position in order to open the inner door?
Yes ____Not ____
13.12 Characteristics of forced ventilation, if needed:
Is the power for the fans from an independent auxiliary transformer?:
Yes ____ Not ____
Do the fan motors have adequate overload and short–circuit protections?:
Yes ___ Not ___
Are metal guards provided to protect fan blades and motors from theft?:
Yes ___ Not ____
Is any special tool required and provided with the VFD?:
Yes ____ Not _____
13.13 Is a thermostat controlled space heater provided according to PDVSA’s
specifications?
Yes ____Not ____
13.14.a Does the VFD have the conduit hubs for the incoming and outgoing power cables?
Yes ____Not ____
13.14.b Are terminals in the input circuit breaker or disconnect switch, as well as in the
output side, rated for the cable gauges required according to VFD rated capacity
(kVA)?
Yes ____Not ____
13.14.c Does the VFD have a stainless steel nameplate containing the information
required in PDVSA’s specifications?
Yes ____Not ____
13.15.a Please specify below the pushbuttons, selector switches, LED–indicating lamps
and any other devices or features provided with the VFD: _________
ENGINEERING PROCEDURE PDVSA L–TP–2.2
PDVSA
REVISION FECHA
PROCUREMENT CHECK LIST FOR
PROGRESSING CAVITY PUMPS (PCP) 0 NOV.00
Página 11
.Menú Principal Indice manual Indice volumen Indice norma
13.15.b Please specify Vendor, model and technology of the proposed VFD:
Vendor: ___________________________________
Model: ____________________________________
Technology: _______________________________
13.15.c Is a completed technical manual of the proposed VFD including with the proposal?
Yes ____Not ____