Floor Slab at grade strip of forms 5.60 MH/SM 2.80 MH/SM 2.24 MH/SM
Earthworks Pages 6 of 10
EARTHWORKS
Man-hour per quantity
DESCRIPTION LOW AVERAGE HIGH
Qty Unit Qty Unit Qty Unit
Clay and Heavy Soil 3.28 MH/CM 1.64 MH/CM 1.31 MH/CM
Rock 5.26 MH/CM 2.63 MH/CM 2.10 MH/CM
2.3 Mechanical Excavation
Common Earth 13.34 MH/CM 6.67 MH/CM 5.34 MH/CM
Rock w/ Jackhammer 33.34 MH/CM 16.67 MH/CM 13.34 MH/CM
2.4 Backfilling
Common Manual 1.64 MH/CM 0.82 MH/CM 0.66 MH/CM
Gravel Fill Manual 10.00 MH/CM 5.00 MH/CM 4.00 MH/CM
2.5 Trenching and Backfilling of Underground
2.6 piping using excavation materials manual
from 0 - 2mtrs depth 2.50 MH/LM 1.25 MH/LM 1.00 MH/LM
2 - 3mtrs depth 3.34 MH/LM 1.67 MH/LM 1.34 MH/LM
3 - 4mtrs depth 5.00 MH/LM 2.50 MH/LM 2.00 MH/LM
4 - 5mtrs depth 6.66 MH/LM 3.33 MH/LM 2.66 MH/LM
2.7 Placing Binder - Gravel 0.21 MH/CM 0.11 MH/CM 0.08 MH/CM
2.8 Escombro Backfilling 0.42 MH/CM 0.21 MH/CM 0.17 MH/CM
2.9 Spreading, Tamping, and Grading 0.96 MH/SM 0.48 MH/SM 0.38 MH/SM
3 Mechanical Compaction, Plate Compaction 0.11 MH/CM 0.06 MH/CM 0.04 MH/CM
3.1 Manual Clearing and Grubbing
Clearing undergrowth and tress 12" 0.10 MH/SM 0.05 MH/SM 0.04 MH/SM
Clearing undergrowth and scrubs 0.06 MH/SM 0.03 MH/SM 0.02 MH/SM
3.2 Disposal of Soil 3.38 MH/CM 1.69 MH/CM 1.35 MH/CM
3.3 Hauling of Soil 2.00 MH/CM 1.00 MH/CM 0.80 MH/CM
3.4 Gravel Fill 4.14 MH/CM 2.07 MH/CM 1.66 MH/CM
3.5 Excavation - crane and Clampshell
with 8-men and 2-carpenters 2.14 MH/CM 1.07 MH/CM 0.86 MH/CM
Earthworks Pages 7 of 10
PLUMBING WORKS
Man-hour per quantity
DESCRIPTION LOW AVERAGE HIGH
Qty Unit Qty Unit Qty Unit
1.1 Laying Asbestos Pipe
1/2" Dia 1.32 MH/LM 0.66 MH/LM 0.53 MH/LM
3/4" Dia 1.32 MH/LM 0.66 MH/LM 0.53 MH/LM
1-1/4" Dia 1.48 MH/LM 0.74 MH/LM 0.59 MH/LM
1 1/2" - 2" Dia 1.64 MH/LM 0.82 MH/LM 0.66 MH/LM
2 1/2" Dia 1.97 MH/LM 0.99 MH/LM 0.79 MH/LM
3" 2.16 MH/LM 1.08 MH/LM 0.86 MH/LM
3 1/2" Dia 2.30 MH/LM 1.15 MH/LM 0.92 MH/LM
4" 2.64 MH/LM 1.32 MH/LM 1.06 MH/LM
1.2 Cast Iron Pipe
2" 4.38 MH/LM 2.19 MH/LM 1.75 MH/LM
4" 6.58 MH/LM 3.29 MH/LM 2.63 MH/LM
6" 9.84 MH/LM 4.92 MH/LM 3.94 MH/LM
8" 13.14 MH/LM 6.57 MH/LM 5.26 MH/LM
10" 19.70 MH/LM 9.85 MH/LM 7.88 MH/LM
12" 20.62 MH/LM 10.31 MH/LM 8.25 MH/LM
14" 24.10 MH/LM 12.05 MH/LM 9.64 MH/LM
16" 27.38 MH/LM 13.69 MH/LM 10.95 MH/LM
18" 30.68 MH/LM 15.34 MH/LM 12.27 MH/LM
20" 32.86 MH/LM 16.43 MH/LM 13.14 MH/LM
24" 36.14 MH/LM 18.07 MH/LM 14.46 MH/LM
30" 41.08 MH/LM 20.54 MH/LM 16.43 MH/LM
1.3 Laying of PVC Pipe
1/2" - 3/4" Dia 0.38 MH/LM 0.19 MH/LM 0.15 MH/LM
1" - 1 1/4" Dia 1.48 MH/LM 0.74 MH/LM 0.59 MH/LM
1 1/2" - 2" Dia 1.64 MH/LM 0.82 MH/LM 0.66 MH/LM
2 1/2" Dia 1.96 MH/LM 0.98 MH/LM 0.78 MH/LM
3" 2.16 MH/LM 1.08 MH/LM 0.86 MH/LM
4" 2.62 MH/LM 1.31 MH/LM 1.05 MH/LM
5" 3.28 MH/LM 1.64 MH/LM 1.31 MH/LM
6" 4.92 MH/LM 2.46 MH/LM 1.97 MH/LM
1.4 Laying RCP 8men (1 team)
24" 8.00 MH/LM 4.00 MH/LM 3.20 MH/LM
36" 12.80 MH/LM 6.40 MH/LM 5.12 MH/LM
48" 21.34 MH/LM 10.67 MH/LM 8.54 MH/LM
6' - 18" 2.66 MH/LM 1.33 MH/LM 1.06 MH/LM
1.5 Lavatory 16.00 MH/LM 8.00 MH/LM 6.40 MH/LM
1.6 Water Closet 24.00 MH/LM 12.00 MH/LM 9.60 MH/LM
1.7 Urinal Utility Stall 48.00 MH/LM 24.00 MH/LM 19.20 MH/LM
1.8 Urinal, Pedestal Type 32.00 MH/LM 16.00 MH/LM 12.80 MH/LM
1.9 Shower and Stall 20.00 MH/LM 10.00 MH/LM 8.00 MH/LM
2 5-man Group Shower 72.00 MH/LM 36.00 MH/LM 28.80 MH/LM
2.1 Bath Tubs 48.00 MH/LM 24.00 MH/LM 19.20 MH/LM
2.2 Slope Sink 28.00 MH/LM 14.00 MH/LM 11.20 MH/LM
2.3 Hot Water Heater 28.00 MH/LM 14.00 MH/LM 11.20 MH/LM
2.4 6-person Wash Sink 52.00 MH/LM 26.00 MH/LM 20.80 MH/LM
Insulation Pages 10 of 10