You are on page 1of 286

Name of the Work:- Name of work: GNSS Phase-II – Package No.

10/06 - “Investigation, Design & Formation of Mallemadugu Reservoir and Excavation of Kailasagiri
Canal from Km 0.000 to Km 65.500 including Construction of CM & CD works and distributory system including field channels to be feed an ayacut of 55000 acres in
Chittoor and Nellore Districts"
Name of the the Agency : M/S MAYTAS-NCC (J.V),
FORMATION OF MALLAMADUGU RESERVOIR
GENERAL ABSTRACT OF DEVIATION PROPOSAL
As per TBL is fixed 129.500 as per
As Per Approved I.B.M and Embankment slopes
Slno Descrption Of Item Deviation Amount Remarks
Drawing and other design criteria as per
approved drawing) / I.B.M

Embankment Cut-off Trench Comparde with I.B.M


1 29,591,512 11,923,092 17,668,420
EWE Excavation Quantites
Comparde with TBL is fixed
129.500 as per I.B.M and
2 Formation Embankment 546,622,351 369,783,800 176,838,551 Embankment slopes and
other design criteria as per
approved drawing
Comparde with I.B.M
3 Construction O.T Sluices- 3 No,s 31,980,198 9,000,000 22,980,198
Quantites
Excavation of Surplus course
including protection Comparde with I.B.M
4 93,589,931 5,500,000 88,089,931
arrangements and removal of Quantites
obstruction on D/S.
Total 305,577,100
Deduct Tender Premium
46,791,493
(-15.3125 %)
Net Amount 258,785,607
DEVIATION PROPOSAL
Name of the Work:- Name of work: GNSS Phase-II – Package No.10/06 - “Investigation, Design & Formation of Mallemadugu Reservoir and Excavation of
Kailasagiri Canal from Km 0.000 to Km 65.500 including Construction of CM & CD works and distributory system including field channels to be feed an ayacut of
55000 acres in Chittoor and Nellore Districts"
Name of the the Agency : M/S MAYTAS-NCC (J.V),
FORMATION OF MALLAMADUGU RESERVOIR
Comparative Statement
As per TBL is fixed 129.500 as per I.B.M and
As Per Approved Dwg Embankment slopes and other design
Slno Descrption Of Item Unit criteria as per approved drawing) Remarks

Quantity Rate in RS Amount in RS Quantity Rate in RS Amount in RS

Earth work excavation of soils of approved quality borrowed


from approved quarry and depositing as directed for forming
5 Hearting zone including formation of haul roads watering. Cum 388965 157.00 61067505 199943 157.00 31391051
Including conslidation with 8 to 10 Ton power roller including
seignorage charges soils with an equivalent lead of 3 KM MR.

Earth woek excavation of soils of approved quality borrowed


from approved quarry and depositing as directed for forming
5A Hearting zone including formation of haul roads watering, Cum 388965 168.00 65346120 199943 168.00 33590424
including consolidation with 8 to 10Ton power roller including
seignorage charges soils with an equivalent lead od 5KM MR.

Earth work excavation of soils of approved quality borrowed


from approved quarry and depositing as directed for forming
6 Casing zone including formation of haul roads watering. Cum 1661354 141.00 234250914 1116047 141.00 157362627
Including conslidation with 8 to 10 Ton power roller including
seignorage charges with an equivalent lead of 1 KM MR
Extra watering and consolidation of useful soils obtained from
COT excavation with 8 to 10 Tonne power roller upto 98%
proctor's density incliding breaking clods, sectioning,
7 Cum 20000 47.50 950000 100000 47.50 4750000
conveyance of water with initial lead of 1/2 KM and akk other
incudental charges etc, amd signorage charges for earth
complete dinished item of work.
As per TBL is fixed 129.500 as per I.B.M and
As Per Approved Dwg Embankment slopes and other design
Slno Descrption Of Item Unit criteria as per approved drawing) Remarks

Quantity Rate in RS Amount in RS Quantity Rate in RS Amount in RS

Forming sand filter, sand blanket, filter under revetment toe


wall, toe drain and rock toe with sand of approved quality
borrowed from approved quarries including cost and
8 Cum 127247 324.30 41266202 101111 324.30 32790297
conveyance of sand. Seigniorage charges, labour charges,
leads. Lifts and all other operations necessary to complete the
finished item of work.
Forming inclined sand chimney by cut and fill method using
sand of approved quality borrowed from approved quarries
including excavation of consolidated earth and depositing as
9 Cum 46262 357.00 16515534 42523 357.00 15180711
directed and cost and conveyance of sand seignorage
charges,labour charges, leads, lifts and all other operations
necessary to complete the finished item work
Formation of metal filters under revetment rock Toe, Toe
drain, Toe Well, using 10mm to 75mm size if H.B. metal of
approved quality obtained from approved quarries including
10 Cum 46897 373.30 17506650 37658 373.30 14057731
cost and conveyance of metal, seignorage charges, labour
charges, leads, lifts and all other operations necessary to
complete the finished item of work.
Rough stone dry packing for revetment of 450mm thick using
225mm size of hard stone of approved quality borrowed from
approved quarries including cost and conveyance of all
11 Cum 81695 577.30 47162524 64923 577.30 37480048
materials, leads, lifts seignorage charges, labour chatges and all
other operations necessary to complete the finished item of
work (Rip Rip)
Forming Rock Toe using 225mm - 300mm size hard stone of
approved quality borrowed from approved quarries including
12 cost and conveyance of all materials, labour charges, Cum 25928 420.30 10897538 15315 420.30 6436895
seignorage charges and other operations necessary to complete
the finished item of work.
Forming Rock Toe using 225mm - 300mm size hard stone of
12A Cum 8850 190.81 1688669 15315 190.81 2922255
approved quality from available stone (labour charges only)
As per TBL is fixed 129.500 as per I.B.M and
As Per Approved Dwg Embankment slopes and other design
Slno Descrption Of Item Unit criteria as per approved drawing) Remarks

Quantity Rate in RS Amount in RS Quantity Rate in RS Amount in RS

Earth work excavation in loamy and clayee soils like black


cotton soils and red earth and ordinary gravel (Consilidated
13 bund) and depositing the soil as directed for excavation of Cum 6965 47.10 328052 5606 47.10 264043
foundations toe paraped, chutes etc., complete for finished item
of work.
Laying cement concrete M15 grade for foundation of parapet,
using 40mm H.B metal and of approved quality obtained from
approved quarry including cost and conveyance of all
14 Cum 3671 2584.00 9485864 2956 2584.00 7638304
materials, labour all leads and lifts mixing concrete by
machine, water for work curing charges etc, complete for
finished item of work.
Laying cement concrete M15 grade for chutes and parapet,
using 40mm H.B metal and of approved quality obtained from
approved quarry including cost and conveyance of all
15 materials, labour all leads and lifts mixing concrete by Cum 3671 2584.00 9485864 2956 2584.00 7638304
machine, water for work curing charges, centering charges,
seignorage charges etc., complete for finished item of work for
chutes and parapet
Drilling holes and driving casing pipe 63mm dia in the
consolidated cut off trench upto the bottom off cut of along
16 RM 6741 450.90 3039517 5370 450.90 2421333
bund axis as directed in the soil with drilling machine and
casing bit including cost of casing pipe
Drilling holes into the rock from the bottom of cut off trench
by wagon drill to the specified depth at intervals as directed for
17 washing holes with air jet and water in the drilled holes, RM 22587 832.00 18792384 13524 832.00 11251968
founfation treatment including refilling the holes whereever
necessary
Conducting in situ permeability test at 2Mtr. Zones, using
18 test 1044 232.50 242730 1032 232.50 239940
double packer in the drilled holes
Grouting the holes with cement slurry with specified ratio of
19 MT 1200 5517.00 6620400 508 5517.00 2802636
water cement mix incliding cost of cement
Turfing the D/s of bund including watering for 3 months with
20 Sqm 107385 18.40 1975884 85067 18.40 1565233
initial lead for conveyance of water and grass
546622351 369783800
DEVIATION PROPOSAL
Name of the Work:- Name of work: GNSS Phase-II – Package No.10/06 - “Investigation, Design & Formation of Mallemadugu Reservoir and
Name of the the Agency : M/S MAYTAS-NCC (J.V),
FORMATION OF MALLAMADUGU RESERVOIR
Comparative Statement
As Per IBM As Per Approved Dwg
Slno Descrption Of Item Unit Remarks
Amount in
Quantity Rate in RS Amount in RS Quantity Rate in RS
RS
Cut-Off Trench Earthwork Excavation
Each work excavation in all soils upto and inclistve
of soft disintegrated rock, stone matrix, for stripping
under banks. Excavation of Toe drain, Toe wall and
1 under rock Toe with machinery and depositing the Cum 54500 36.5 1,989,250 54500 36.5 1,989,250
spoils at specified places as directed by the
department and including conveyance with a lead of
0-250M
Earth work excavation in all soils upto and
inclusive of soft disintegrated rock, stone matrix,
for stripping under banks. Excavation of Toe drain
1A Cum 54500 13.5 735,750 54500 13.5 735,750
Toe wall and under rock Toe with machinery and
depositing the spoils at specified places as directed
by the department without conveyance.
Each work excavation in all soils upto and inclistve
of soft disintegrated rock, stone matrix, for
Excavation of Toe drain, Toe wall ,under rock Toe
1B and Cut off excavation with machinery and Cum 0 0 - 183412 56.7 10,399,460
depositing the spoils at specified places as directed
by the department and including conveyance with a
lead of 500M
As Per IBM As Per Approved Dwg
Slno Descrption Of Item Unit Remarks
Amount in
Quantity Rate in RS Amount in RS Quantity Rate in RS
RS
Earth work excavation and depositing on banks
with machinery in Hard disintegrated rock or soft
2 Cum 91235 20.3 1,852,071 20000 20.3 406,000
rock of conglomerate etc in Cut off excavation
without conveyance.
Earth work excavation and depositing on banks
with machinery in Hard disintegrated rock or soft
2A Cum 0 0 - 98106 90.7 8,898,214
rock of conglomerate etc in Cut off excavation with
conveyance of 500 M
Earth work excavation and depositing as directed
with machinery in fissured and fractured rock and
boulders upto 3 Cum in size requiring blasting
3 Cum 45650 115.65 5,279,423 43536 115.65 5,034,938
excluding stacking for cut off excavation and
excavation of leading channel and conveyance with
a lead of 500m including dewatering.
Earth work excavation and depositing as directed
with machinery in fissured and fractured rock and
boulders upto 3 Cum in size requiring blasting
3A Cum 45650 45.2 2,063,380 0 0 -
excluding stacking for cut off excavation and
excavation of leading channel and without
conveyance.
Earth work excavation and depositing as directed
with machinery in hard rock and boulders upto 3
Cum in size requiring blasting excluding stacking
4 Cum 20 160.9 3,218 1961 160.9 315,525
for cut off excavation and excavation of leading
channel and conveyance with a lead of 500m
including dewatering.
As Per IBM As Per Approved Dwg
Slno Descrption Of Item Unit Remarks
Amount in
Quantity Rate in RS Amount in RS Quantity Rate in RS
RS
Earth work excavation and depositing as directed
with machinery in hard rock and boulders upto 3
Cum in size requiring Control blasting excluding
4A Cum 0 0 - 4500 402.75 1,812,375
stacking for cut off excavation and excavation of
leading channel and conveyance with a lead of
500m including dewatering.
Total 11,923,092 29,591,512
Formation of Mallemadugu Reservoir
Quantity statement of formation of embankment-(TBL is fixed 129.500 as per I.B.M and Embankment slopes and other design criteria as per
approved drawing)
Slno Descrption Unit Bund-1 Bund-2 Bund-3 Saddle Bund Total
Earth work excavation of soils of approved quality borrowed
from approved quarry and depositing as directed for forming
Hearting zone including formation of haul roads watering.
5 Cum 78422.00 94218.98 26620.59 681.00 199942.57
Including conslidation with 8 to 10 Ton power roller
including seignorage charges soils with an equivalent lead of
3 KM MR.
Earth woek excavation of soils of approved quality borrowed
from approved quarry and depositing as directed for forming
Hearting zone including formation of haul roads watering,
5A Cum 78422.00 94218.98 26620.59 681.00 199942.57
including consolidation with 8 to 10Ton power roller
including seignorage charges soils with an equivalent lead od
5KM MR.
Earth work excavation of soils of approved quality borrowed
from approved quarry and depositing as directed for forming
Casing zone including formation of haul roads watering.
6 Cum 429869.08 611554.70 172251.84 2371.00 1116046.61
Including conslidation with 8 to 10 Ton power roller
including seignorage charges with an equivalent lead of 1
KM MR
Casing Quanity Cum 432613.44 613349.21 172675.74 2763.50 1221401.88
Deduct Toe Protection Quantity Cum 2744.36 1794.51 423.90 392.50 5355.27
Deuct Use Full Soils obtained From COT Cum 100000.00
Net Casing Quanity Cum 429869.08 611554.70 172251.84 2371.00 1116046.61
Extra watering and consolidation of useful soils obtained
from COT excavation with 8 to 10 Tonne power roller upto
98% proctor's density incliding breaking clods, sectioning,
7 Cum 100000.00
conveyance of water with initial lead of 1/2 KM and akk
other incudental charges etc, amd signorage charges for
earth complete dinished item of work.
Slno Descrption Unit Bund-1 Bund-2 Bund-3 Saddle Bund Total
Forming sand filter, sand blanket, filter under revetment toe
wall, toe drain and rock toe with sand of approved quality
borrowed from approved quarries including cost and
8 Cum 46092.69 43014.34 10607.60 1395.88 101110.51
conveyance of sand. Seigniorage charges, labour charges,
leads. Lifts and all other operations necessary to complete
the finished item of work.
Horizontal Sand Filters ( Sand Blanket) Cum 28845.18 26447.62 6478.28 362.00
Sand-Below Rip Rap Cum 10465.73 11170.48 2793.03 249.25
Sand Filters below Rock Toe Cum 1975.33 1895.08 489.84 188.25
Sand Filters behind Rock Toe Cum 978.61 926.31 237.65 84.00
Sand Filters Behind Toe-Protection Cum 786.60 514.35 121.50 112.50
Sand Filters at Toe Wall (U/S) Cum 1537.96 1077.53 255.12 184.875
Sand Filters at Toe drain (D/S) Cum 1503.28 982.98 232.20 215
Total Cum 46092.69 43014.34 10607.60 1395.88

Forming inclined sand chimney by cut and fill method using


sand of approved quality borrowed from approved quarries
including excavation of consolidated earth and depositing as
9 Cum 17017.27 20247.13 5258.19 42522.58
directed and cost and conveyance of sand seignorage
charges,labour charges, leads, lifts and all other operations
necessary to complete the finished item work
0.00

Formation of metal filters under revetment rock Toe, Toe


drain, Toe Well, using 10mm to 75mm size if H.B. metal of
approved quality obtained from approved quarries including
10 Cum 16579.38 16115.44 4023.80 939.78 37658.39
cost and conveyance of metal, seignorage charges, labour
charges, leads, lifts and all other operations necessary to
complete the finished item of work.
Metal Filters Behind Rock Toe Cum 978.61 926.31 237.65 84.00
Metal Filters Below Rock Toe Cum 1767.07 1759.42 458.94 153.00
Metal Filters below Rip Rap Cum 10465.73 11170.48 2793.03 249.25
Metal Filters behind Toe-Protection Cum 786.60 514.35 121.50 112.50
Meteal Fimters at Toe Wall- U/S Cum 1235.41 864.77 204.79 148.525
Metal Filters at Toe Drain (D/S) Cum 1345.96 880.11 207.90 192.5
Total Cum 16579.38 16115.44 4023.80 939.78
Slno Descrption Unit Bund-1 Bund-2 Bund-3 Saddle Bund Total
Rough stone dry packing for revetment of 450mm thick
using 225mm size of hard stone of approved quality
borrowed from approved quarries including cost and
11 Cum 28324.81 28351.16 7046.29 1200.43 64922.68
conveyance of all materials, leads, lifts seignorage charges,
labour chatges and all other operations necessary to complete
the finished item of work (Rip Rip)
U/S Rip Rap Cum 23548.78 25133.77 6285.65 561.50
Toe Wall Cum 1926.79 1354.30 320.54 231.425
Toe Drain Cum 1678.08 1097.28 259.20 240
Toe Protection Cum 1171.16 765.81 180.90 167.50
Total Cum 28324.81 28351.16 7046.29 1200.43
Forming Rock Toe using 225mm - 300mm size hard stone of
approved quality borrowed from approved quarries including
12 cost and conveyance of all materials, labour charges, Cum 5653.90 7191.50 2131.74 338 15315.13
seignorage charges and other operations necessary to
complete the finished item of work.
Forming Rock Toe using 225mm - 300mm size hard stone of
12A Cum 5653.90 7191.50 2131.74 338 15315.13
approved quality from available stone (labour charges only)
Earth work excavation in loamy and clayee soils like black
cotton soils and red earth and ordinary gravel (Consilidated
13 bund) and depositing the soil as directed for excavation of Cum 2771.58 2068.50 543.78 221.80 5605.66
foundations toe paraped, chutes etc., complete for finished
item of work.
EWE of Profile Wall Cum 167.25 168.65 44.81 5.36
EWE of Guard Stone Cum 13.30 8.70 2.07 1.92
EWE of Parapet Wall Cum 1048.80 685.80 162.00 150.00
EWE of Chute Drains Cum 1542.23 1205.35 334.89 64.52
Total Cum 2771.58 2068.50 543.78 221.80
Laying cement concrete M15 grade for foundation of
parapet, using 40mm H.B metal and of approved quality
obtained from approved quarry including cost and
14 Cum 1431.18 1119.21 291.42 114.67 2956.48
conveyance of all materials, labour all leads and lifts mixing
concrete by machine, water for work curing charges etc,
complete for finished item of work.
Profile Wall Cum 650.36 655.89 174.29 20.8
Slno Descrption Unit Bund-1 Bund-2 Bund-3 Saddle Bund Total
Para Pet Wall Cum 1110.50 726.15 171.53 158.83
Guard Stone Cum 35.46 23.21 5.53 5.12
Chute Drain Cum 1066.04 833.18 231.48 44.59
Total Cum 2862.37 2238.42 582.83 229.34
Take a half Quantity Cum 1431.18 1119.21 291.42 114.67
Laying cement concrete M15 grade for chutes and parapet,
using 40mm H.B metal and of approved quality obtained
from approved quarry including cost and conveyance of all
15 materials, labour all leads and lifts mixing concrete by Cum 1431.18 1119.21 291.42 114.67 2956.48
machine, water for work curing charges, centering charges,
seignorage charges etc., complete for finished item of work
for chutes and parapet
Drilling holes and driving casing pipe 63mm dia in the
consolidated cut off trench upto the bottom off cut of along
16 Rmt 2280.00 2292.00 546.00 5370.00
bund axis as directed in the soil with drilling machine and
casing bit including cost of casing pipe 252
Drilling holes into the rock from the bottom of cut off trench
by wagon drill to the specified depth at intervals as directed
17 for washing holes with air jet and water in the drilled holes, Rmt 6840.00 4584.00 1092.00 13524.00
founfation treatment including refilling the holes whereever
necessary 1008
Conducting in situ permeability test at 2Mtr. Zones, using
18 Rmt 612.00 276.00 72.00 1032.00
double packer in the drilled holes 72
Grouting the holes with cement slurry with specified ratio of
19 MT 257.00 172.00 41.00 508.00
water cement mix incliding cost of cement 38
Turfing the D/s of bund including watering for 3 months with
20 Sqm 38571.14 37129.97 9252.31 114.00 85067.42
initial lead for conveyance of water and grass
FIRST ANGLE PROJECTION
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

(ALL DIMENSIONS ARE IN M)


A
Name of the Work :- GNSS Phase-II-Package No-10/06-"Investigation,Design & Formation of Mallemadugu Reservoir A

Name of the the Agency : M/S MAYTAS-NCC (J.V),

B B

Parpet wall Guard Stone


6.000
TBL-129.500 +129.500
FLOW 450 mm thick Rip Rap 3.000 +128.500
FRL/MWL- +127.500 +129.500 2
200 mm thick metal

1.2
1
C
2.5 C

mt
1

hic
0.5 0.5 H

k in
200 mm thick sand
1 1 omo

clin
5.000 Homogeneous soils gen 5.000
oils

ed
us s eou
With 2% extra moisture

s an
o Content over OMC ss 2
ne
oge oils 1

d fi
D
2.5 m
D

Ho

lter
1
1 m Ht Toe Protection

+113.500-Rock Toe Top Level-Veries

1.567 1.900
E E
GL Stripped Level-110.000 ( Varies) 1.0 m thick Horizontal sand Blanket GL

1. ALL DIMENSIONS ARE IN METRES AND LEVELS IN METRES.


F ONLY FIGURED DIMENSIONS SHALL BE CONSIDERED. F

4.000 Cut-Off Trench 2. THE EARTH DAM HAS BEEN DESIGNED AS HOMOGENEOUS SECTION
WITH EMBANKMENT SOILS AND FOUNDATION SOILS ADOPTED IN
THE DESIGN AS INDICATED IN THE TABLE 1
FOS FOS AS PER APPROVED DRAWING-DWG NO-
CONDITION
G
OBTAINED REQUIRED Cross Section of Earthbund -Maximum Height-21.54 M G

D/S NORMAL 1.5273 1.50


3. THE TOP LEVEL OF THE DAM IS FIXED AS +131.000 BASED ON I.B.M
D/S EARTHQUAKE 1.3164 1.00

U/S NORMAL 1.4152 1.30


H H
U/S EARTHQUAKE 1.2124 1.00

J J

K K
G.N.S.S PROJECT:- PACKAGE-10
MALLIMADUGU RESERVOIR

EARTH DAM SECTION OF MAXIMUM HEIGHT


( Top Level of dam is fixed as +129.500 based on
L L

I.B.M , remaining design as per approved drawing)

Name of the the Agency : M/S MAYTAS-NCC (J.V),


M M

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
FIRST ANGLE PROJECTION
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

(ALL DIMENSIONS ARE IN M)


A
Name of the Work :- GNSS Phase-II-Package No-10/06-"Investigation,Design & Formation of Mallemadugu Reservoir A

Name of the the Agency : M/S MAYTAS-NCC (J.V),

B B

Parpet wall Guard Stone


6.000
TBL-129.500 +129.500
FLOW 450 mm thick Rip Rap 3.000 +128.500
FRL/MWL- +127.500 +129.500 2
200 mm thick metal

1.0
1
C
2 C

mt
1

hic
0.5 0.5 H

k in
200 mm thick sand
1 1 omo

clin
5.000 Homogeneous soils gen 5.000
oils

ed
us s eou
With 2% extra moisture

s an
o Content over OMC ss 2
ne
oge oils 1

d fi
D
2 m
D

Ho

lter
1
1 m Ht Toe Protection

+113.500-Rock Toe Top Level-Veries

1.567 1.900
E E
GL Stripped Level-110.000 ( Varies) 1.0 m thick Horizontal sand Blanket GL

1. ALL DIMENSIONS ARE IN METRES AND LEVELS IN METRES.


F ONLY FIGURED DIMENSIONS SHALL BE CONSIDERED. F

4.000 Cut-Off Trench 2. THE EARTH DAM HAS BEEN DESIGNED AS HOMOGENEOUS SECTION
WITH EMBANKMENT SOILS AND FOUNDATION SOILS ADOPTED IN
THE DESIGN AS INDICATED IN THE TABLE 1
FOS FOS AS PER APPROVED DRAWING-DWG NO-
CONDITION
G
OBTAINED REQUIRED Cross Section of Earthbund -Maximum Height-13.5 M G

D/S NORMAL 1.5273 1.50


3. THE TOP LEVEL OF THE DAM IS FIXED AS +131.000 BASED ON I.B.M
D/S EARTHQUAKE 1.3164 1.00

U/S NORMAL 1.4152 1.30


H H
U/S EARTHQUAKE 1.2124 1.00

J J

K K
G.N.S.S PROJECT:- PACKAGE-10
MALLIMADUGU RESERVOIR

EARTH DAM SECTION OF MAXIMUM HEIGHT


( Top Level of dam is fixed as +129.500 based on
L L

I.B.M , remaining design as per approved drawing)

Name of the the Agency : M/S MAYTAS-NCC (J.V),


M M

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.025 Km
T.B.L = + 129.500 M Avg. G.L = + 126.750 M
Stripped.Level = + 126.450 M Stri.Lev = + 126.450 M
Height of Bund 3.050 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 126.450 )X 4+6+1.717+1.9= 21.82 M
Depth of Stripping ( 126.750 - 126.450 ) = 0.300 M
Area of Stripping ( 21.820 X 0.300 ) = 6.550 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-126.45 )X 20% 0.21 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 126.450 )X 0.5*2+3 = 5.05 M
Top Width = 3M
Arae of Hearting Soils = 3+5.05
X 2.050 = 8.25 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-126.45)X2+3-0.57-4.5 - 5.05/2 = 1.50 M
Top Width = 1.5+1.5 = 3.00 M
Arae of Hearting Soils = 3+1.5
X 1.000 = 2.25 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 127.450
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 0.050 = 0.06 M
Area of Inclined Sand Chimney = 0.06 X 1 = 0.06 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 3.050 = 6.82 M
Arae of 450thk Rip Rap = 6.82X0.45 = 3.07 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 3.050 = 6.82 M
Arae of 200thk Sand = 6.82X0.2 = 1.36 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 3.050 = 6.82 M
Arae of 200thk Sand = 6.82X0.2 = 1.36 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 126.450 )X 4+6 = 18.2 M
Top Width = 6M
Arae of Bund = 6+18.2
X 3.050 = 36.91 Sqm
2
12)Net casing Area = 36.91-3.38-0.42-0.42-8.25-2.25-0.06-3.07-1.36-1.36 = 16.34 Sqm

Slno Descrption Area


1 Stripping = 6.550 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 8.25 Sqm
12 Inclined Sand Chimney = 0.06 Sqm
13 horizontal Sand Filter = 2.25 Sqm
14 450mm thk Rip Rap = 3.07 Sqm
15 200mm thk Metal = 1.36 Sqm
16 200mm thk sand = 1.36 Sqm
17 Net Casing Area = 16.34 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.050 Km
T.B.L = + 129.500 M Avg. G.L = + 123.570 M
Stripped.Level = + 123.270 M Stri.Lev = + 123.270 M
Height of Bund 6.230 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 123.270 )X 4+6+1.717+1.9= 34.54 M
Depth of Stripping ( 123.570 - 123.270 ) = 0.300 M
Area of Stripping ( 34.540 X 0.300 ) = 10.360 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-123.27 )X 20% 0.846 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 123.270 )X 0.5*2+3 = 8.23 M
Top Width = 3M
Arae of Hearting Soils = 3+8.23
X 5.230 = 29.37 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-123.27)X2+3-0.57-4.5 - 8.23/2 = 6.28 M
Top Width = 6.28+1.5 = 7.78 M
Arae of Hearting Soils = 7.78+6.28
X 1.000 = 7.03 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 124.270
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 3.230 = 3.61 M
Area of Inclined Sand Chimney = 3.61 X 1 = 3.61 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 6.230 = 13.93 M
Arae of 450thk Rip Rap = 13.93X0.45 = 6.27 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 6.230 = 13.93 M
Arae of 200thk Sand = 13.93X0.2 = 2.79 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 6.230 = 13.93 M
Arae of 200thk Sand = 13.93X0.2 = 2.79 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 123.270 )X 4+6 = 30.92 M
Top Width = 6M
Arae of Bund = 6+30.92
X 6.230 = 115.01 Sqm
2
12)Net casing Area = 115.01-3.38-0.42-0.42-29.37-7.03-3.61-6.27-2.79-2.79 = 58.93 Sqm

Slno Descrption Area


1 Stripping = 10.360 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 29.37 Sqm
12 Inclined Sand Chimney = 3.61 Sqm
13 horizontal Sand Filter = 7.03 Sqm
14 450mm thk Rip Rap = 6.27 Sqm
15 200mm thk Metal = 2.79 Sqm
16 200mm thk sand = 2.79 Sqm
17 Net Casing Area = 58.93 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.075 Km
T.B.L = + 129.500 M Avg. G.L = + 121.005 M
Stripped.Level = + 120.705 M Stri.Lev = + 120.705 M
Height of Bund 8.795 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 120.705 )X 4+6+1.717+1.9= 44.8 M
Depth of Stripping ( 121.005 - 120.705 ) = 0.300 M
Area of Stripping ( 44.800 X 0.300 ) = 13.440 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-120.705 )X 20% 1.359 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 120.705 )X 0.5*2+3 = 10.8 M
Top Width = 3M
Arae of Hearting Soils = 3+10.8
X 7.795 = 53.79 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-120.705)X2+3-0.57-4.5 - 10.8/2 = 10.12 M
Top Width = 10.12+1.5 = 11.62 M
Arae of Hearting Soils = 11.62+10.12
X 1.000 = 10.87 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 121.705
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 5.795 = 6.48 M
Area of Inclined Sand Chimney = 6.48 X 1 = 6.48 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 8.795 = 19.67 M
Arae of 450thk Rip Rap = 19.67X0.45 = 8.85 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 8.795 = 19.67 M
Arae of 200thk Sand = 19.67X0.2 = 3.93 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 8.795 = 19.67 M
Arae of 200thk Sand = 19.67X0.2 = 3.93 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 120.705 )X 4+6 = 41.18 M
Top Width = 6M
Arae of Bund = 6+41.18
X 8.795 = 207.47 Sqm
2
12)Net casing Area = 207.47-3.38-0.42-0.42-53.79-10.87-6.48-8.85-3.93-3.93 = 115.40 Sqm

Slno Descrption Area


1 Stripping = 13.440 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 53.79 Sqm
12 Inclined Sand Chimney = 6.48 Sqm
13 horizontal Sand Filter = 10.87 Sqm
14 450mm thk Rip Rap = 8.85 Sqm
15 200mm thk Metal = 3.93 Sqm
16 200mm thk sand = 3.93 Sqm
17 Net Casing Area = 115.40 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.100 Km
T.B.L = + 129.500 M Avg. G.L = + 119.150 M
Stripped.Level = + 118.850 M Stri.Lev = + 118.850 M
Height of Bund 10.650 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 118.850 )X 4+6+10+1.717+1.9= 62.22 M
Depth of Stripping ( 119.150 - 118.850 ) = 0.300 M
Area of Stripping ( 62.220 X 0.300 ) = 18.670 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-118.85 )X 20% 1.73 = 1.73 M
Bottom Width of Rock-Toe = 1.73 X 3 = 5.19 M
Area of Rock -Toe = 1/2X5.19X1.73 = 4.49 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.730 = 2.45 M
Area = 2.45X0.2 = 0.49 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.730 = 2.45 M
Area = 2.45X0.2 = 0.49 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 118.850 )X 0.5*2+3 = 12.65 M
Top Width = 3M
Arae of Hearting Soils = 3+12.65
X 9.650 = 75.51 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-118.85)X2+3+5-0.57-5.19- 12.65/2 = 17.22 M
Top Width = 17.22+1.5 = 18.72 M
Arae of Hearting Soils = 18.72+17.22
X 1.000 = 17.97 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 119.850
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 7.650 = 8.55 M
Area of Inclined Sand Chimney = 8.55 X 1 = 8.55 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 10.650 + 5 = 28.81 M
Arae of 450thk Rip Rap = 28.81X0.45 = 12.96 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 10.650 + 5 = 28.81 M
Arae of 200thk Sand = 28.81X0.2 = 5.76 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 10.650 + 5 = 28.81 M
Arae of 200thk Sand = 28.81X0.2 = 5.76 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 118.850 )X 4+6+10 = 58.6 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6M
Arae of Bund up to Berm = 50.8+58.6
X 1.950 = 106.67 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 310.25 Sqm
12)Net casing Area = 310.25-4.49-0.49-0.49-75.51-17.97-8.55-12.96-5.76-5.76 = 178.27 Sqm
Slno Descrption Area
1 Stripping = 18.670 Sqm
8 Rock-toe = 4.49 Sqm
9 Behind sand Filters = 0.49 Sqm
10 Behind Metal Filters = 0.49 Sqm
11 Hearting = 75.51 Sqm
12 Inclined Sand Chimney = 8.55 Sqm
13 horizontal Sand Filter = 17.97 Sqm
14 450mm thk Rip Rap = 12.96 Sqm
15 200mm thk Metal = 5.76 Sqm
16 200mm thk sand = 5.76 Sqm
17 Net Casing Area = 178.27 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.125 Km
T.B.L = + 129.500 M Avg. G.L = + 116.750 M
Stripped.Level = + 116.450 M Stri.Lev = + 116.450 M
Height of Bund 13.050 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 116.450 )X 4+6+10+1.717+1.9= 71.82 M
Depth of Stripping ( 116.750 - 116.450 ) = 0.300 M
Area of Stripping ( 71.820 X 0.300 ) = 21.550 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-116.45 )X 20% 2.21 = 2.21 M
Bottom Width of Rock-Toe = 2.21 X 3 = 6.63 M
Area of Rock -Toe = 1/2X6.63X2.21 = 7.33 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.210 = 3.13 M
Area = 3.13X0.2 = 0.63 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.210 = 3.13 M
Area = 3.13X0.2 = 0.63 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 116.450 )X 0.5*2+3 = 15.05 M
Top Width = 3 M
Arae of Hearting Soils = 3+15.05
X 12.050 = 108.75 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-116.45)X2+3+5-0.57-6.63- 15.05/2 = 19.38 M
Top Width = 19.38+1.5 = 20.88 M
Arae of Hearting Soils = 20.88+19.38
X 1.000 = 20.13 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 117.450
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 10.050 = 11.24 M
Area of Inclined Sand Chimney = 11.24 X 1 = 11.24 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 13.050 + 5 = 34.18 M
Arae of 450thk Rip Rap = 34.18X0.45 = 15.38 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 13.050 + 5 = 34.18 M
Arae of 200thk Sand = 34.18X0.2 = 6.84 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 13.050 + 5 = 34.18 M
Arae of 200thk Sand = 34.18X0.2 = 6.84 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 116.450 )X 4+6+10 = 68.2 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+68.2
X 4.350 = 258.83 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 462.41 Sqm
12)Net casing Area = 462.41-7.33-0.63-0.63-108.75-20.13-11.24-15.38-6.84-6.84 = 284.64 Sqm
Slno Descrption Area
1 Stripping = 21.550 Sqm
8 Rock-toe = 7.33 Sqm
9 Behind sand Filters = 0.63 Sqm
10 Behind Metal Filters = 0.63 Sqm
11 Hearting = 108.75 Sqm
12 Inclined Sand Chimney = 11.24 Sqm
13 horizontal Sand Filter = 20.13 Sqm
14 450mm thk Rip Rap = 15.38 Sqm
15 200mm thk Metal = 6.84 Sqm
16 200mm thk sand = 6.84 Sqm
17 Net Casing Area = 284.64 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.150 Km
T.B.L = + 129.500 M Avg. G.L = + 115.620 M
Stripped.Level = + 115.320 M Stri.Lev = + 115.320 M
Height of Bund 14.180 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 115.320 )X 4.5+6+10+1.567+2.5= 83.28 M
Depth of Stripping ( 115.620 - 115.320 ) = 0.300 M
Area of Stripping ( 83.280 X 0.300 ) = 24.980 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-115.32 )X 20% 2.436 = 2.44 M
Bottom Width of Rock-Toe = 2.436 X 3 = 7.31 M
Area of Rock -Toe = 1/2X7.31X2.436 = 8.9 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.436 = 3.45 M
Area = 3.45X0.2 = 0.69 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.436 = 3.45 M
Area = 3.45X0.2 = 0.69 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 115.320 )X 0.5*2+3 = 16.18 M
Top Width = 3M
Arae of Hearting Soils = 3+16.18
X 13.180 = 126.40 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-115.32)X2+3+5-0.57-7.31 - 16.18/2 = 20.39 M
Top Width = 20.39+1.5 = 21.89 M
Arae of Hearting Soils = 21.89+20.39
X 1.000 = 21.14 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 116.320
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 11.180 = 12.5 M
Area of Inclined Sand Chimney = 12.5 X 1.2 = 15 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 14.180 + 5 = 43.18 M
Arae of 450thk Rip Rap = 43.18X0.45 = 19.43 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 14.180 + 5 = 43.18 M
Arae of 200thk Sand = 43.18X0.2 = 8.64 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 14.180 + 5 = 43.18 M
Arae of 200thk Sand = 43.18X0.2 = 8.64 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 115.320 )X 4.5+6+10 = 79.81 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+79.81
X 5.480 = 369.79 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 592.29 Sqm
12)Net casing Area = 592.29-8.9-0.69-0.69-126.4-21.14-15-19.43-8.64-8.64 = 382.76 Sqm
Slno Descrption Area
1 Stripping = 24.980 Sqm
8 Rock-toe = 8.9 Sqm
9 Behind sand Filters = 0.69 Sqm
10 Behind Metal Filters = 0.69 Sqm
11 Hearting = 126.40 Sqm
12 Inclined Sand Chimney = 15 Sqm
13 horizontal Sand Filter = 21.14 Sqm
14 450mm thk Rip Rap = 19.43 Sqm
15 200mm thk Metal = 8.64 Sqm
16 200mm thk sand = 8.64 Sqm
17 Net Casing Area = 382.76 Sqm
7.25
2.692582
43.18082
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.175 Km
T.B.L = + 129.500 M Avg. G.L = + 113.500 M
Stripped.Level = + 113.200 M Stri.Lev = + 113.200 M
Height of Bund 16.300 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.200 )X 4.5+6+10+1.567+2.5= 92.82 M
Depth of Stripping ( 113.500 - 113.200 ) = 0.300 M
Area of Stripping ( 92.820 X 0.300 ) = 27.850 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.2 )X 20% 2.86 = 2.86 M
Bottom Width of Rock-Toe = 2.86 X 3 = 8.58 M
Area of Rock -Toe = 1/2X8.58X2.86 = 12.27 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.860 = 4.04 M
Area = 4.04X0.2 = 0.81 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.860 = 4.04 M
Area = 4.04X0.2 = 0.81 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.200 )X 0.5*2+3 = 18.3 M
Top Width = 3M
Arae of Hearting Soils = 3+18.3
X 15.300 = 162.95 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.2)X2+3+5-0.57-8.58 - 18.3/2 = 22.30 M
Top Width = 22.3+1.5 = 23.80 M
Arae of Hearting Soils = 23.8+22.3
X 1.000 = 23.05 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.200
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.300 = 14.87 M
Area of Inclined Sand Chimney = 14.87 X 1.2 = 17.844 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 16.300 + 5 = 48.89 M
Arae of 450thk Rip Rap = 48.89X0.45 = 22 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 16.300 + 5 = 48.89 M
Arae of 200thk Sand = 48.89X0.2 = 9.78 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 16.300 + 5 = 48.89 M
Arae of 200thk Sand = 48.89X0.2 = 9.78 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.200 )X 4.5+6+10 = 89.35 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+89.35
X 7.600 = 549.10 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 771.60 Sqm
12)Net casing Area = 771.6-12.27-0.81-0.81-162.95-23.05-17.844-22-9.78-9.78 = 512.31 Sqm
Slno Descrption Area
1 Stripping = 27.850 Sqm
8 Rock-toe = 12.27 Sqm
9 Behind sand Filters = 0.81 Sqm
10 Behind Metal Filters = 0.81 Sqm
11 Hearting = 162.95 Sqm
12 Inclined Sand Chimney = 17.844 Sqm
13 horizontal Sand Filter = 23.05 Sqm
14 450mm thk Rip Rap = 22 Sqm
15 200mm thk Metal = 9.78 Sqm
16 200mm thk sand = 9.78 Sqm
17 Net Casing Area = 512.31 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.200 Km
T.B.L = + 129.500 M Avg. G.L = + 112.650 M
Stripped.Level = + 112.350 M Stri.Lev = + 112.350 M
Height of Bund 17.150 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 112.350 )X 4.5+6+10+1.567+2.5= 96.64 M
Depth of Stripping ( 112.650 - 112.350 ) = 0.300 M
Area of Stripping ( 96.640 X 0.300 ) = 28.990 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-112.35 )X 20% 3.03 = 3.03 M
Bottom Width of Rock-Toe = 3.03 X 3 = 9.09 M
Area of Rock -Toe = 1/2X9.09X3.03 = 13.77 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.030 = 4.29 M
Area = 4.29X0.2 = 0.86 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.030 = 4.29 M
Area = 4.29X0.2 = 0.86 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 112.350 )X 0.5*2+3 = 19.15 M
Top Width = 3 M
Arae of Hearting Soils = 3+19.15
X 16.150 = 178.86 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-112.35)X2+3+5-0.57-9.09 - 19.15/2 = 23.07 M
Top Width = 23.07+1.5 = 24.57 M
Arae of Hearting Soils = 24.57+23.07
X 1.000 = 23.82 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 113.350
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 14.150 = 15.82 M
Area of Inclined Sand Chimney = 15.82 X 1.2 = 18.984 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 17.150 + 5 = 51.18 M
Arae of 450thk Rip Rap = 51.18X0.45 = 23.03 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 17.150 + 5 = 51.18 M
Arae of 200thk Sand = 51.18X0.2 = 10.24 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 17.150 + 5 = 51.18 M
Arae of 200thk Sand = 51.18X0.2 = 10.24 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 112.350 )X 4.5+6+10 = 93.18 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+93.18
X 8.450 = 626.69 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 849.19 Sqm
12)Net casing Area = 849.19-13.77-0.86-0.86-178.86-23.82-18.984-23.03-10.24-10.24 = 568.53 Sqm
Slno Descrption Area
1 Stripping = 28.990 Sqm
8 Rock-toe = 13.77 Sqm
9 Behind sand Filters = 0.86 Sqm
10 Behind Metal Filters = 0.86 Sqm
11 Hearting = 178.86 Sqm
12 Inclined Sand Chimney = 18.984 Sqm
13 horizontal Sand Filter = 23.82 Sqm
14 450mm thk Rip Rap = 23.03 Sqm
15 200mm thk Metal = 10.24 Sqm
16 200mm thk sand = 10.24 Sqm
17 Net Casing Area = 568.53 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.352 Km
T.B.L = + 131.000 M Avg. G.L = + 109.540 M
Stripped.Level = + 109.240 M Stri.Lev = + 109.240 M
Height of Bund 21.760 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 131.000 - 109.240 )X 4.5+6+10+1.567+2.5= 117.4 M
Depth of Stripping ( 109.540 - 109.240 ) = 0.300 M
Area of Stripping ( 117.390 X 0.300 ) = 35.220 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-109.24 )X 20% 3.652 = 3.65 M
Bottom Width of Rock-Toe = 3.652 X 3 = 10.96 M
Area of Rock -Toe = 1/2X10.96X3.652 = 20.01 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.652 = 5.16 M
Area = 5.16X0.2 = 1.03 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.652 = 5.16 M
Area = 5.16X0.2 = 1.03 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 109.240 )X 0.5*2+3 = 22.26 M
Top Width = 3 M
Arae of Hearting Soils = 3+22.26
X 19.260 = 243.25 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 131-109.24)X2+3+5-0.57-10.96 - 22.26/2 = 28.86 M
Top Width = 28.86+1.5 = 30.36 M
Arae of Hearting Soils = 30.36+28.86
X 1.000 = 29.61 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 110.240
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 17.260 = 19.3 M
Area of Inclined Sand Chimney = 19.3 X 1.2 = 23.16 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 21.760 + 5 = 63.59 M
Arae of 450thk Rip Rap = 63.59X0.45 = 28.62 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 21.760 + 5 = 63.59 M
Arae of 200thk Sand = 63.59X0.2 = 12.72 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 21.760 + 5 = 63.59 M
Arae of 200thk Sand = 63.59X0.2 = 12.72 Sqm
9) Area of Bund
Bottom Width ( 131.000 - 109.240 )X 4.5+6+10 = 113.92 M
At 120.8 Incl Berm ( 131.000 - 120.800 )X 4.5+6+10 61.9 M
Top Width = 6 M
Arae of Bund up to Berm = 61.9+113.92
X 11.560 = 1016.24 Sqm
2
Arae of Bund Berm to TBL = 6+51.9
X 10.200 = 295.29 Sqm
2
Total 1311.53 Sqm
12)Net casing Area = 1311.53-20.01-1.03-1.03-243.25-29.61-23.16-28.62-12.72-12.72 = 939.38 Sqm
Slno Descrption Area
1 Stripping = 35.220 Sqm
8 Rock-toe = 20.01 Sqm
9 Behind sand Filters = 1.03 Sqm
10 Behind Metal Filters = 1.03 Sqm
11 Hearting = 243.25 Sqm
12 Inclined Sand Chimney = 23.16 Sqm
13 horizontal Sand Filter = 29.61 Sqm
14 450mm thk Rip Rap = 28.62 Sqm
15 200mm thk Metal = 12.72 Sqm
16 200mm thk sand = 12.72 Sqm
17 Net Casing Area = 939.38 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.372 Km
T.B.L = + 131.000 M Avg. G.L = + 109.610 M
Stripped.Level = + 109.310 M Stri.Lev = + 109.310 M
Height of Bund 21.690 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 131.000 - 109.310 )X 4.5+6+10+1.567+2.5= 117.1 M
Depth of Stripping ( 109.610 - 109.310 ) = 0.300 M
Area of Stripping ( 117.070 X 0.300 ) = 35.120 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-109.31 )X 20% 3.638 = 3.64 M
Bottom Width of Rock-Toe = 3.638 X 3 = 10.91 M
Area of Rock -Toe = 1/2X10.91X3.638 = 19.85 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.638 = 5.14 M
Area = 5.14X0.2 = 1.03 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.638 = 5.14 M
Area = 5.14X0.2 = 1.03 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 109.310 )X 0.5*2+3 = 22.19 M
Top Width = 3 M
Arae of Hearting Soils = 3+22.19
X 19.190 = 241.70 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 131-109.31)X2+3+5-0.57-10.91 - 22.19/2 = 28.81 M
Top Width = 28.81+1.5 = 30.31 M
Arae of Hearting Soils = 30.31+28.81
X 1.000 = 29.56 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 110.310
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 17.190 = 19.22 M
Area of Inclined Sand Chimney = 19.22 X 1.2 = 23.064 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 21.690 + 5 = 63.4 M
Arae of 450thk Rip Rap = 63.4X0.45 = 28.53 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 21.690 + 5 = 63.4 M
Arae of 200thk Sand = 63.4X0.2 = 12.68 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 21.690 + 5 = 63.4 M
Arae of 200thk Sand = 63.4X0.2 = 12.68 Sqm
9) Area of Bund
Bottom Width ( 131.000 - 109.310 )X 4.5+6+10 = 113.61 M
At 120.8 Incl Berm ( 131.000 - 120.800 )X 4.5+6+10 61.9 M
Top Width = 6 M
Arae of Bund up to Berm = 61.9+113.61
X 11.490 = 1008.30 Sqm
2
Arae of Bund Berm to TBL = 6+51.9
X 10.200 = 295.29 Sqm
2
Total 1303.59 Sqm
12)Net casing Area = 1303.59-19.85-1.03-1.03-241.7-29.56-23.064-28.53-12.68-12.68 = 933.47 Sqm
Slno Descrption Area
1 Stripping = 35.120 Sqm
8 Rock-toe = 19.85 Sqm
9 Behind sand Filters = 1.03 Sqm
10 Behind Metal Filters = 1.03 Sqm
11 Hearting = 241.70 Sqm
12 Inclined Sand Chimney = 23.064 Sqm
13 horizontal Sand Filter = 29.56 Sqm
14 450mm thk Rip Rap = 28.53 Sqm
15 200mm thk Metal = 12.68 Sqm
16 200mm thk sand = 12.68 Sqm
17 Net Casing Area = 933.47 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.400 Km
T.B.L = + 129.500 M Avg. G.L = + 109.110 M
Stripped.Level = + 108.810 M Stri.Lev = + 108.810 M
Height of Bund 20.690 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 108.810 )X 4.5+6+10+1.567+2.5= 112.6 M
Depth of Stripping ( 109.110 - 108.810 ) = 0.300 M
Area of Stripping ( 112.570 X 0.300 ) = 33.770 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-108.81 )X 20% 3.738 = 3.74 M
Bottom Width of Rock-Toe = 3.738 X 3 = 11.21 M
Area of Rock -Toe = 1/2X11.21X3.738 = 20.95 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.738 = 5.29 M
Area = 5.29X0.2 = 1.06 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.738 = 5.29 M
Area = 5.29X0.2 = 1.06 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 108.810 )X 0.5*2+3 = 22.69 M
Top Width = 3 M
Arae of Hearting Soils = 3+22.69
X 19.690 = 252.92 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-108.81)X2+3+5-0.57-11.21- 22.69/2 = 26.26 M
Top Width = 26.26+1.5 = 27.76 M
Arae of Hearting Soils = 27.76+26.26
X 1.000 = 27.01 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 109.810
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 17.690 = 19.78 M
Area of Inclined Sand Chimney = 19.78 X 1.2 = 23.736 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 20.690 + 5 = 60.71 M
Arae of 450thk Rip Rap = 60.71X0.45 = 27.32 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 20.690 + 5 = 60.71 M
Arae of 200thk Sand = 60.71X0.2 = 12.14 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 20.690 + 5 = 60.71 M
Arae of 200thk Sand = 60.71X0.2 = 12.14 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 108.810 )X 4.5+6+10 = 109.11 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+109.11
X 11.990 = 984.74 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 1207.24 Sqm
12)Net casing Area = 1207.24-20.95-1.06-1.06-252.92-27.01-23.736-27.32-12.14-12.14 = 828.90 Sqm
Slno Descrption Area
1 Stripping = 33.770 Sqm
8 Rock-toe = 20.95 Sqm
9 Behind sand Filters = 1.06 Sqm
10 Behind Metal Filters = 1.06 Sqm
11 Hearting = 252.92 Sqm
12 Inclined Sand Chimney = 23.736 Sqm
13 horizontal Sand Filter = 27.01 Sqm
14 450mm thk Rip Rap = 27.32 Sqm
15 200mm thk Metal = 12.14 Sqm
16 200mm thk sand = 12.14 Sqm
17 Net Casing Area = 828.90 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.425 Km
T.B.L = + 129.500 M Avg. G.L = + 110.520 M
Stripped.Level = + 110.220 M Stri.Lev = + 110.220 M
Height of Bund 19.280 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 110.220 )X 4.5+6+10+1.567+2.5= 106.2 M
Depth of Stripping ( 110.520 - 110.220 ) = 0.300 M
Area of Stripping ( 106.230 X 0.300 ) = 31.870 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-110.22 )X 20% 3.456 = 3.46 M
Bottom Width of Rock-Toe = 3.456 X 3 = 10.37 M
Area of Rock -Toe = 1/2X10.37X3.456 = 17.92 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.456 = 4.89 M
Area = 4.89X0.2 = 0.98 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.456 = 4.89 M
Area = 4.89X0.2 = 0.98 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 110.220 )X 0.5*2+3 = 21.28 M
Top Width = 3 M
Arae of Hearting Soils = 3+21.28
X 18.280 = 221.92 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-110.22)X2+3+5-0.57-10.37- 21.28/2 = 24.98 M
Top Width = 24.98+1.5 = 26.48 M
Arae of Hearting Soils = 26.48+24.98
X 1.000 = 25.73 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 111.220
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 16.280 = 18.2 M
Area of Inclined Sand Chimney = 18.2 X 1.2 = 21.84 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 19.280 + 5 = 56.91 M
Arae of 450thk Rip Rap = 56.91X0.45 = 25.61 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 19.280 + 5 = 56.91 M
Arae of 200thk Sand = 56.91X0.2 = 11.38 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 19.280 + 5 = 56.91 M
Arae of 200thk Sand = 56.91X0.2 = 11.38 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 110.220 )X 4.5+6+10 = 102.76 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+102.76
X 10.580 = 835.34 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 1057.84 Sqm
12)Net casing Area = 1057.84-17.92-0.98-0.98-221.92-25.73-21.84-25.61-11.38-11.38 = 720.10 Sqm
Slno Descrption Area
1 Stripping = 31.870 Sqm
8 Rock-toe = 17.92 Sqm
9 Behind sand Filters = 0.98 Sqm
10 Behind Metal Filters = 0.98 Sqm
11 Hearting = 221.92 Sqm
12 Inclined Sand Chimney = 21.84 Sqm
13 horizontal Sand Filter = 25.73 Sqm
14 450mm thk Rip Rap = 25.61 Sqm
15 200mm thk Metal = 11.38 Sqm
16 200mm thk sand = 11.38 Sqm
17 Net Casing Area = 720.10 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.450 Km
T.B.L = + 129.500 M Avg. G.L = + 110.730 M
Stripped.Level = + 110.430 M Stri.Lev = + 110.430 M
Height of Bund 19.070 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 110.430 )X 4.5+6+10+1.567+2.5= 105.3 M
Depth of Stripping ( 110.730 - 110.430 ) = 0.300 M
Area of Stripping ( 105.280 X 0.300 ) = 31.580 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-110.43 )X 20% 3.414 = 3.41 M
Bottom Width of Rock-Toe = 3.414 X 3 = 10.24 M
Area of Rock -Toe = 1/2X10.24X3.414 = 17.48 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.414 = 4.83 M
Area = 4.83X0.2 = 0.97 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.414 = 4.83 M
Area = 4.83X0.2 = 0.97 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 110.430 )X 0.5*2+3 = 21.07 M
Top Width = 3 M
Arae of Hearting Soils = 3+21.07
X 18.070 = 217.47 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-110.43)X2+3+5-0.57-10.24- 21.07/2 = 24.80 M
Top Width = 24.8+1.5 = 26.30 M
Arae of Hearting Soils = 26.3+24.8
X 1.000 = 25.55 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 111.430
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 16.070 = 17.97 M
Area of Inclined Sand Chimney = 17.97 X 1.2 = 21.564 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 19.070 + 5 = 56.35 M
Arae of 450thk Rip Rap = 56.35X0.45 = 25.36 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 19.070 + 5 = 56.35 M
Arae of 200thk Sand = 56.35X0.2 = 11.27 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 19.070 + 5 = 56.35 M
Arae of 200thk Sand = 56.35X0.2 = 11.27 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 110.430 )X 4.5+6+10 = 101.82 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+101.82
X 10.370 = 813.89 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 1036.39 Sqm
12)Net casing Area = 1036.39-17.48-0.97-0.97-217.47-25.55-21.564-25.36-11.27-11.27 = 704.49 Sqm
Slno Descrption Area
1 Stripping = 31.580 Sqm
8 Rock-toe = 17.48 Sqm
9 Behind sand Filters = 0.97 Sqm
10 Behind Metal Filters = 0.97 Sqm
11 Hearting = 217.47 Sqm
12 Inclined Sand Chimney = 21.564 Sqm
13 horizontal Sand Filter = 25.55 Sqm
14 450mm thk Rip Rap = 25.36 Sqm
15 200mm thk Metal = 11.27 Sqm
16 200mm thk sand = 11.27 Sqm
17 Net Casing Area = 704.49 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.475 Km
T.B.L = + 129.500 M Avg. G.L = + 111.100 M
Stripped.Level = + 110.800 M Stri.Lev = + 110.800 M
Height of Bund 18.700 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 110.800 )X 4.5+6+10+1.567+2.5= 103.6 M
Depth of Stripping ( 111.100 - 110.800 ) = 0.300 M
Area of Stripping ( 103.620 X 0.300 ) = 31.090 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-110.8 )X 20% 3.34 = 3.34 M
Bottom Width of Rock-Toe = 3.34 X 3 = 10.02 M
Area of Rock -Toe = 1/2X10.02X3.34 = 16.73 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.340 = 4.72 M
Area = 4.72X0.2 = 0.94 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.340 = 4.72 M
Area = 4.72X0.2 = 0.94 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 110.800 )X 0.5*2+3 = 20.7 M
Top Width = 3M
Arae of Hearting Soils = 3+20.7
X 17.700 = 209.75 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-110.8)X2+3+5-0.57-10.02 - 20.7/2 = 24.46 M
Top Width = 24.46+1.5 = 25.96 M
Arae of Hearting Soils = 25.96+24.46
X 1.000 = 25.21 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 111.800
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 15.700 = 17.55 M
Area of Inclined Sand Chimney = 17.55 X 1.2 = 21.06 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 18.700 + 5 = 55.35 M
Arae of 450thk Rip Rap = 55.35X0.45 = 24.91 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 18.700 + 5 = 55.35 M
Arae of 200thk Sand = 55.35X0.2 = 11.07 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 18.700 + 5 = 55.35 M
Arae of 200thk Sand = 55.35X0.2 = 11.07 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 110.800 )X 4.5+6+10 = 100.15 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+100.15
X 10.000 = 776.50 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 999.00 Sqm
12)Net casing Area = 999-16.73-0.94-0.94-209.75-25.21-21.06-24.91-11.07-11.07 = 677.32 Sqm
Slno Descrption Area
1 Stripping = 31.090 Sqm
8 Rock-toe = 16.73 Sqm
9 Behind sand Filters = 0.94 Sqm
10 Behind Metal Filters = 0.94 Sqm
11 Hearting = 209.75 Sqm
12 Inclined Sand Chimney = 21.06 Sqm
13 horizontal Sand Filter = 25.21 Sqm
14 450mm thk Rip Rap = 24.91 Sqm
15 200mm thk Metal = 11.07 Sqm
16 200mm thk sand = 11.07 Sqm
17 Net Casing Area = 677.32 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.500 Km
T.B.L = + 129.500 M Avg. G.L = + 111.780 M
Stripped.Level = + 111.480 M Stri.Lev = + 111.480 M
Height of Bund 18.020 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 111.480 )X 4.5+6+10+1.567+2.5= 100.6 M
Depth of Stripping ( 111.780 - 111.480 ) = 0.300 M
Area of Stripping ( 100.560 X 0.300 ) = 30.170 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-111.48 )X 20% 3.204 = 3.20 M
Bottom Width of Rock-Toe = 3.204 X 3 = 9.61 M
Area of Rock -Toe = 1/2X9.61X3.204 = 15.4 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.204 = 4.53 M
Area = 4.53X0.2 = 0.91 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.204 = 4.53 M
Area = 4.53X0.2 = 0.91 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 111.480 )X 0.5*2+3 = 20.02 M
Top Width = 3M
Arae of Hearting Soils = 3+20.02
X 17.020 = 195.90 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-111.48)X2+3+5-0.57-9.61 - 20.02/2 = 23.85 M
Top Width = 23.85+1.5 = 25.35 M
Arae of Hearting Soils = 25.35+23.85
X 1.000 = 24.60 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 112.480
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 15.020 = 16.79 M
Area of Inclined Sand Chimney = 16.79 X 1.2 = 20.148 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 18.020 + 5 = 53.52 M
Arae of 450thk Rip Rap = 53.52X0.45 = 24.08 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 18.020 + 5 = 53.52 M
Arae of 200thk Sand = 53.52X0.2 = 10.7 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 18.020 + 5 = 53.52 M
Arae of 200thk Sand = 53.52X0.2 = 10.7 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 111.480 )X 4.5+6+10 = 97.09 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+97.09
X 9.320 = 709.44 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 931.94 Sqm
12)Net casing Area = 931.94-15.4-0.91-0.91-195.9-24.6-20.148-24.08-10.7-10.7 = 628.59 Sqm
Slno Descrption Area
1 Stripping = 30.170 Sqm
8 Rock-toe = 15.4 Sqm
9 Behind sand Filters = 0.91 Sqm
10 Behind Metal Filters = 0.91 Sqm
11 Hearting = 195.90 Sqm
12 Inclined Sand Chimney = 20.148 Sqm
13 horizontal Sand Filter = 24.60 Sqm
14 450mm thk Rip Rap = 24.08 Sqm
15 200mm thk Metal = 10.7 Sqm
16 200mm thk sand = 10.7 Sqm
17 Net Casing Area = 628.59 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.525 Km
T.B.L = + 129.500 M Avg. G.L = + 112.700 M
Stripped.Level = + 112.400 M Stri.Lev = + 112.400 M
Height of Bund 17.100 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 112.400 )X 4.5+6+10+1.567+2.5= 96.42 M
Depth of Stripping ( 112.700 - 112.400 ) = 0.300 M
Area of Stripping ( 96.420 X 0.300 ) = 28.930 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-112.4 )X 20% 3.02 = 3.02 M
Bottom Width of Rock-Toe = 3.02 X 3 = 9.06 M
Area of Rock -Toe = 1/2X9.06X3.02 = 13.68 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.020 = 4.27 M
Area = 4.27X0.2 = 0.85 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.020 = 4.27 M
Area = 4.27X0.2 = 0.85 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 112.400 )X 0.5*2+3 = 19.1 M
Top Width = 3 M
Arae of Hearting Soils = 3+19.1
X 16.100 = 177.91 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-112.4)X2+3+5-0.57-9.06 - 19.1/2 = 23.02 M
Top Width = 23.02+1.5 = 24.52 M
Arae of Hearting Soils = 24.52+23.02
X 1.000 = 23.77 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 113.400
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 14.100 = 15.76 M
Area of Inclined Sand Chimney = 15.76 X 1.2 = 18.912 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 17.100 + 5 = 51.04 M
Arae of 450thk Rip Rap = 51.04X0.45 = 22.97 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 17.100 + 5 = 51.04 M
Arae of 200thk Sand = 51.04X0.2 = 10.21 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 17.100 + 5 = 51.04 M
Arae of 200thk Sand = 51.04X0.2 = 10.21 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 112.400 )X 4.5+6+10 = 92.95 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+92.95
X 8.400 = 622.02 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 844.52 Sqm
12)Net casing Area = 844.52-13.68-0.85-0.85-177.91-23.77-18.912-22.97-10.21-10.21 = 565.16 Sqm
Slno Descrption Area
1 Stripping = 28.930 Sqm
8 Rock-toe = 13.68 Sqm
9 Behind sand Filters = 0.85 Sqm
10 Behind Metal Filters = 0.85 Sqm
11 Hearting = 177.91 Sqm
12 Inclined Sand Chimney = 18.912 Sqm
13 horizontal Sand Filter = 23.77 Sqm
14 450mm thk Rip Rap = 22.97 Sqm
15 200mm thk Metal = 10.21 Sqm
16 200mm thk sand = 10.21 Sqm
17 Net Casing Area = 565.16 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.550 Km
T.B.L = + 129.500 M Avg. G.L = + 113.560 M
Stripped.Level = + 113.260 M Stri.Lev = + 113.260 M
Height of Bund 16.240 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.260 )X 4.5+6+10+1.567+2.5= 92.55 M
Depth of Stripping ( 113.560 - 113.260 ) = 0.300 M
Area of Stripping ( 92.550 X 0.300 ) = 27.760 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.26 )X 20% 2.848 = 2.85 M
Bottom Width of Rock-Toe = 2.848 X 3 = 8.54 M
Area of Rock -Toe = 1/2X8.54X2.848 = 12.16 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.848 = 4.03 M
Area = 4.03X0.2 = 0.81 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.848 = 4.03 M
Area = 4.03X0.2 = 0.81 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.260 )X 0.5*2+3 = 18.24 M
Top Width = 3M
Arae of Hearting Soils = 3+18.24
X 15.240 = 161.85 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.26)X2+3+5-0.57-8.54 - 18.24/2 = 22.25 M
Top Width = 22.25+1.5 = 23.75 M
Arae of Hearting Soils = 23.75+22.25
X 1.000 = 23.00 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.260
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.240 = 14.8 M
Area of Inclined Sand Chimney = 14.8 X 1.2 = 17.76 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 16.240 + 5 = 48.73 M
Arae of 450thk Rip Rap = 48.73X0.45 = 21.93 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 16.240 + 5 = 48.73 M
Arae of 200thk Sand = 48.73X0.2 = 9.75 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 16.240 + 5 = 48.73 M
Arae of 200thk Sand = 48.73X0.2 = 9.75 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.260 )X 4.5+6+10 = 89.08 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+89.08
X 7.540 = 543.75 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 766.25 Sqm
12)Net casing Area = 766.25-12.16-0.81-0.81-161.85-23-17.76-21.93-9.75-9.75 = 508.43 Sqm
Slno Descrption Area
1 Stripping = 27.760 Sqm
8 Rock-toe = 12.16 Sqm
9 Behind sand Filters = 0.81 Sqm
10 Behind Metal Filters = 0.81 Sqm
11 Hearting = 161.85 Sqm
12 Inclined Sand Chimney = 17.76 Sqm
13 horizontal Sand Filter = 23.00 Sqm
14 450mm thk Rip Rap = 21.93 Sqm
15 200mm thk Metal = 9.75 Sqm
16 200mm thk sand = 9.75 Sqm
17 Net Casing Area = 508.43 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.575 Km
T.B.L = + 129.500 M Avg. G.L = + 114.740 M
Stripped.Level = + 114.440 M Stri.Lev = + 114.440 M
Height of Bund 15.060 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 114.440 )X 4.5+6+10+1.567+2.5= 87.24 M
Depth of Stripping ( 114.740 - 114.440 ) = 0.300 M
Area of Stripping ( 87.240 X 0.300 ) = 26.170 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-114.44 )X 20% 2.612 = 2.61 M
Bottom Width of Rock-Toe = 2.612 X 3 = 7.84 M
Area of Rock -Toe = 1/2X7.84X2.612 = 10.24 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.612 = 3.69 M
Area = 3.69X0.2 = 0.74 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.612 = 3.69 M
Area = 3.69X0.2 = 0.74 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 114.440 )X 0.5*2+3 = 17.06 M
Top Width = 3M
Arae of Hearting Soils = 3+17.06
X 14.060 = 141.02 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-114.44)X2+3+5-0.57-7.84 - 17.06/2 = 21.18 M
Top Width = 21.18+1.5 = 22.68 M
Arae of Hearting Soils = 22.68+21.18
X 1.000 = 21.93 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 115.440
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 12.060 = 13.48 M
Area of Inclined Sand Chimney = 13.48 X 1.2 = 16.176 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 15.060 + 5 = 45.55 M
Arae of 450thk Rip Rap = 45.55X0.45 = 20.5 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 15.060 + 5 = 45.55 M
Arae of 200thk Sand = 45.55X0.2 = 9.11 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 15.060 + 5 = 45.55 M
Arae of 200thk Sand = 45.55X0.2 = 9.11 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 114.440 )X 4.5+6+10 = 83.77 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+83.77
X 6.360 = 441.77 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 664.27 Sqm
12)Net casing Area = 664.27-10.24-0.74-0.74-141.02-21.93-16.176-20.5-9.11-9.11 = 434.70 Sqm
Slno Descrption Area
1 Stripping = 26.170 Sqm
8 Rock-toe = 10.24 Sqm
9 Behind sand Filters = 0.74 Sqm
10 Behind Metal Filters = 0.74 Sqm
11 Hearting = 141.02 Sqm
12 Inclined Sand Chimney = 16.176 Sqm
13 horizontal Sand Filter = 21.93 Sqm
14 450mm thk Rip Rap = 20.5 Sqm
15 200mm thk Metal = 9.11 Sqm
16 200mm thk sand = 9.11 Sqm
17 Net Casing Area = 434.70 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.600 Km
T.B.L = + 129.500 M Avg. G.L = + 115.780 M
Stripped.Level = + 115.480 M Stri.Lev = + 115.480 M
Height of Bund 14.020 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 115.480 )X 4.5+6+10+1.567+2.5= 82.56 M
Depth of Stripping ( 115.780 - 115.480 ) = 0.300 M
Area of Stripping ( 82.560 X 0.300 ) = 24.770 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-115.48 )X 20% 2.404 = 2.40 M
Bottom Width of Rock-Toe = 2.404 X 3 = 7.21 M
Area of Rock -Toe = 1/2X7.21X2.404 = 8.67 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.404 = 3.4 M
Area = 3.4X0.2 = 0.68 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.404 = 3.4 M
Area = 3.4X0.2 = 0.68 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 115.480 )X 0.5*2+3 = 16.02 M
Top Width = 3M
Arae of Hearting Soils = 3+16.02
X 13.020 = 123.82 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-115.48)X2+3+5-0.57-7.21 - 16.02/2 = 20.25 M
Top Width = 20.25+1.5 = 21.75 M
Arae of Hearting Soils = 21.75+20.25
X 1.000 = 21.00 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 116.480
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 11.020 = 12.32 M
Area of Inclined Sand Chimney = 12.32 X 1.2 = 14.784 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 14.020 + 5 = 42.75 M
Arae of 450thk Rip Rap = 42.75X0.45 = 19.24 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 14.020 + 5 = 42.75 M
Arae of 200thk Sand = 42.75X0.2 = 8.55 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 14.020 + 5 = 42.75 M
Arae of 200thk Sand = 42.75X0.2 = 8.55 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 115.480 )X 4.5+6+10 = 79.09 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+79.09
X 5.320 = 357.08 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 579.58 Sqm
12)Net casing Area = 579.58-8.67-0.68-0.68-123.82-21-14.784-19.24-8.55-8.55 = 373.61 Sqm
Slno Descrption Area
1 Stripping = 24.770 Sqm
8 Rock-toe = 8.67 Sqm
9 Behind sand Filters = 0.68 Sqm
10 Behind Metal Filters = 0.68 Sqm
11 Hearting = 123.82 Sqm
12 Inclined Sand Chimney = 14.784 Sqm
13 horizontal Sand Filter = 21.00 Sqm
14 450mm thk Rip Rap = 19.24 Sqm
15 200mm thk Metal = 8.55 Sqm
16 200mm thk sand = 8.55 Sqm
17 Net Casing Area = 373.61 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.625 Km
T.B.L = + 129.500 M Avg. G.L = + 117.140 M
Stripped.Level = + 116.840 M Stri.Lev = + 116.840 M
Height of Bund 12.660 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 116.840 )X 4+6+10+1.717+1.9= 70.26 M
Depth of Stripping ( 117.140 - 116.840 ) = 0.300 M
Area of Stripping ( 70.260 X 0.300 ) = 21.080 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-116.84 )X 20% 2.132 = 2.13 M
Bottom Width of Rock-Toe = 2.132 X 3 = 6.40 M
Area of Rock -Toe = 1/2X6.4X2.132 = 6.82 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.132 = 3.02 M
Area = 3.02X0.2 = 0.6 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.132 = 3.02 M
Area = 3.02X0.2 = 0.6 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 116.840 )X 0.5*2+3 = 14.66 M
Top Width = 3M
Arae of Hearting Soils = 3+14.66
X 11.660 = 102.96 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-116.84)X2+3+5-0.57-6.4 - 14.66/2 = 19.02 M
Top Width = 19.02+1.5 = 20.52 M
Arae of Hearting Soils = 20.52+19.02
X 1.000 = 19.77 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 117.840
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 9.660 = 10.8 M
Area of Inclined Sand Chimney = 10.8 X 1.2 = 12.96 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 12.660 + 5 = 33.31 M
Arae of 450thk Rip Rap = 33.31X0.45 = 14.99 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 12.660 + 5 = 33.31 M
Arae of 200thk Sand = 33.31X0.2 = 6.66 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 12.660 + 5 = 33.31 M
Arae of 200thk Sand = 33.31X0.2 = 6.66 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 116.840 )X 4+6+10 = 66.64 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6M
Arae of Bund up to Berm = 50.8+66.64
X 3.960 = 232.53 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 436.11 Sqm
12)Net casing Area = 436.11-6.82-0.6-0.6-102.96-19.77-12.96-14.99-6.66-6.66 = 264.09 Sqm
Slno Descrption Area
1 Stripping = 21.080 Sqm
8 Rock-toe = 6.82 Sqm
9 Behind sand Filters = 0.6 Sqm
10 Behind Metal Filters = 0.6 Sqm
11 Hearting = 102.96 Sqm
12 Inclined Sand Chimney = 12.96 Sqm
13 horizontal Sand Filter = 19.77 Sqm
14 450mm thk Rip Rap = 14.99 Sqm
15 200mm thk Metal = 6.66 Sqm
16 200mm thk sand = 6.66 Sqm
17 Net Casing Area = 264.09 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.650 Km
T.B.L = + 129.500 M Avg. G.L = + 118.340 M
Stripped.Level = + 118.040 M Stri.Lev = + 118.040 M
Height of Bund 11.460 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 118.040 )X 4+6+10+1.717+1.9= 65.46 M
Depth of Stripping ( 118.340 - 118.040 ) = 0.300 M
Area of Stripping ( 65.460 X 0.300 ) = 19.640 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-118.04 )X 20% 1.892 = 1.89 M
Bottom Width of Rock-Toe = 1.892 X 3 = 5.68 M
Area of Rock -Toe = 1/2X5.68X1.892 = 5.37 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.892 = 2.68 M
Area = 2.68X0.2 = 0.54 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.892 = 2.68 M
Area = 2.68X0.2 = 0.54 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 118.040 )X 0.5*2+3 = 13.46 M
Top Width = 3M
Arae of Hearting Soils = 3+13.46
X 10.460 = 86.09 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-118.04)X2+3+5-0.57-5.68 - 13.46/2 = 17.94 M
Top Width = 17.94+1.5 = 19.44 M
Arae of Hearting Soils = 19.44+17.94
X 1.000 = 18.69 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 119.040
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 8.460 = 9.46 M
Area of Inclined Sand Chimney = 9.46 X 1 = 9.46 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 11.460 + 5 = 30.63 M
Arae of 450thk Rip Rap = 30.63X0.45 = 13.78 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 11.460 + 5 = 30.63 M
Arae of 200thk Sand = 30.63X0.2 = 6.13 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 11.460 + 5 = 30.63 M
Arae of 200thk Sand = 30.63X0.2 = 6.13 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 118.040 )X 4+6+10 = 61.84 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6M
Arae of Bund up to Berm = 50.8+61.84
X 2.760 = 155.44 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 359.02 Sqm
12)Net casing Area = 359.02-5.37-0.54-0.54-86.09-18.69-9.46-13.78-6.13-6.13 = 212.29 Sqm
Slno Descrption Area
1 Stripping = 19.640 Sqm
8 Rock-toe = 5.37 Sqm
9 Behind sand Filters = 0.54 Sqm
10 Behind Metal Filters = 0.54 Sqm
11 Hearting = 86.09 Sqm
12 Inclined Sand Chimney = 9.46 Sqm
13 horizontal Sand Filter = 18.69 Sqm
14 450mm thk Rip Rap = 13.78 Sqm
15 200mm thk Metal = 6.13 Sqm
16 200mm thk sand = 6.13 Sqm
17 Net Casing Area = 212.29 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.675 Km
T.B.L = + 129.500 M Avg. G.L = + 119.830 M
Stripped.Level = + 119.530 M Stri.Lev = + 119.530 M
Height of Bund 9.970 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 119.530 )X 4+6+10+1.717+1.9= 59.5 M
Depth of Stripping ( 119.830 - 119.530 ) = 0.300 M
Area of Stripping ( 59.500 X 0.300 ) = 17.850 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-119.53 )X 20% 1.594 = 1.59 M
Bottom Width of Rock-Toe = 1.594 X 3 = 4.78 M
Area of Rock -Toe = 1/2X4.78X1.594 = 3.81 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.594 = 2.25 M
Area = 2.25X0.2 = 0.45 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.594 = 2.25 M
Area = 2.25X0.2 = 0.45 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 119.530 )X 0.5*2+3 = 11.97 M
Top Width = 3 M
Arae of Hearting Soils = 3+11.97
X 8.970 = 67.14 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-119.53)X2+3+5-0.57-4.78 - 11.97/2 = 16.61 M
Top Width = 16.61+1.5 = 18.11 M
Arae of Hearting Soils = 18.11+16.61
X 1.000 = 17.36 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 120.530
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 6.970 = 7.79 M
Area of Inclined Sand Chimney = 7.79 X 1 = 7.79 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 9.970 + 5 = 27.29 M
Arae of 450thk Rip Rap = 27.29X0.45 = 12.28 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 9.970 + 5 = 27.29 M
Arae of 200thk Sand = 27.29X0.2 = 5.46 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 9.970 + 5 = 27.29 M
Arae of 200thk Sand = 27.29X0.2 = 5.46 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 119.530 )X 4+6+10 = 55.88 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+55.88
X 1.270 = 67.74 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 271.32 Sqm
12)Net casing Area = 271.32-3.81-0.45-0.45-67.14-17.36-7.79-12.28-5.46-5.46 = 151.12 Sqm
Slno Descrption Area
1 Stripping = 17.850 Sqm
8 Rock-toe = 3.81 Sqm
9 Behind sand Filters = 0.45 Sqm
10 Behind Metal Filters = 0.45 Sqm
11 Hearting = 67.14 Sqm
12 Inclined Sand Chimney = 7.79 Sqm
13 horizontal Sand Filter = 17.36 Sqm
14 450mm thk Rip Rap = 12.28 Sqm
15 200mm thk Metal = 5.46 Sqm
16 200mm thk sand = 5.46 Sqm
17 Net Casing Area = 151.12 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.700 Km
T.B.L = + 129.500 M Avg. G.L = + 121.750 M
Stripped.Level = + 121.450 M Stri.Lev = + 121.450 M
Height of Bund 8.050 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 121.450 )X 4+6+1.717+1.9= 41.82 M
Depth of Stripping ( 121.750 - 121.450 ) = 0.300 M
Area of Stripping ( 41.820 X 0.300 ) = 12.550 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-121.45 )X 20% 1.21 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 121.450 )X 0.5*2+3 = 10.05 M
Top Width = 3 M
Arae of Hearting Soils = 3+10.05
X 7.050 = 46.00 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-121.45)X2+3-0.57-4.5 - 10.05/2 = 9.00 M
Top Width = 9+1.5 = 10.50 M
Arae of Hearting Soils = 10.5+9
X 1.000 = 9.75 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 122.450
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 5.050 = 5.65 M
Area of Inclined Sand Chimney = 5.65 X 1 = 5.65 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 8.050 = 18 M
Arae of 450thk Rip Rap = 18X0.45 = 8.1 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 8.050 = 18 M
Arae of 200thk Sand = 18X0.2 = 3.6 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 8.050 = 18 M
Arae of 200thk Sand = 18X0.2 = 3.6 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 121.450 )X 4+6 = 38.2 M
Top Width = 6 M
Arae of Bund = 6+38.2
X 8.050 = 177.91 Sqm
2
12)Net casing Area = 177.91-3.38-0.42-0.42-46-9.75-5.65-8.1-3.6-3.6 = 96.99 Sqm

Slno Descrption Area


1 Stripping = 12.550 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 46.00 Sqm
12 Inclined Sand Chimney = 5.65 Sqm
13 horizontal Sand Filter = 9.75 Sqm
14 450mm thk Rip Rap = 8.1 Sqm
15 200mm thk Metal = 3.6 Sqm
16 200mm thk sand = 3.6 Sqm
17 Net Casing Area = 96.99 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.725 Km
T.B.L = + 129.500 M Avg. G.L = + 123.630 M
Stripped.Level = + 123.330 M Stri.Lev = + 123.330 M
Height of Bund 6.170 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 123.330 )X 4+6+1.717+1.9= 34.3 M
Depth of Stripping ( 123.630 - 123.330 ) = 0.300 M
Area of Stripping ( 34.300 X 0.300 ) = 10.290 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-123.33 )X 20% 0.834 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 123.330 )X 0.5*2+3 = 8.17 M
Top Width = 3 M
Arae of Hearting Soils = 3+8.17
X 5.170 = 28.87 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-123.33)X2+3-0.57-4.5 - 8.17/2 = 6.19 M
Top Width = 6.19+1.5 = 7.69 M
Arae of Hearting Soils = 7.69+6.19
X 1.000 = 6.94 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 124.330
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 3.170 = 3.54 M
Area of Inclined Sand Chimney = 3.54 X 1 = 3.54 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 6.170 = 13.8 M
Arae of 450thk Rip Rap = 13.8X0.45 = 6.21 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 6.170 = 13.8 M
Arae of 200thk Sand = 13.8X0.2 = 2.76 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 6.170 = 13.8 M
Arae of 200thk Sand = 13.8X0.2 = 2.76 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 123.330 )X 4+6 = 30.68 M
Top Width = 6 M
Arae of Bund = 6+30.68
X 6.170 = 113.16 Sqm
2
12)Net casing Area = 113.16-3.38-0.42-0.42-28.87-6.94-3.54-6.21-2.76-2.76 = 57.86 Sqm

Slno Descrption Area


1 Stripping = 10.290 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 28.87 Sqm
12 Inclined Sand Chimney = 3.54 Sqm
13 horizontal Sand Filter = 6.94 Sqm
14 450mm thk Rip Rap = 6.21 Sqm
15 200mm thk Metal = 2.76 Sqm
16 200mm thk sand = 2.76 Sqm
17 Net Casing Area = 57.86 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.750 Km
T.B.L = + 129.500 M Avg. G.L = + 126.640 M
Stripped.Level = + 126.340 M Stri.Lev = + 126.340 M
Height of Bund 3.160 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 126.340 )X 4+6+1.717+1.9= 22.26 M
Depth of Stripping ( 126.640 - 126.340 ) = 0.300 M
Area of Stripping ( 22.260 X 0.300 ) = 6.680 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-126.34 )X 20% 0.232 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 126.340 )X 0.5*2+3 = 5.16 M
Top Width = 3 M
Arae of Hearting Soils = 3+5.16
X 2.160 = 8.81 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-126.34)X2+3-0.57-4.5 - 5.16/2 = 1.67 M
Top Width = 1.67+1.5 = 3.17 M
Arae of Hearting Soils = 3.17+1.67
X 1.000 = 2.42 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 127.340
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 0.160 = 0.18 M
Area of Inclined Sand Chimney = 0.18 X 1 = 0.18 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 3.160 = 7.07 M
Arae of 450thk Rip Rap = 7.07X0.45 = 3.18 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 3.160 = 7.07 M
Arae of 200thk Sand = 7.07X0.2 = 1.41 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 3.160 = 7.07 M
Arae of 200thk Sand = 7.07X0.2 = 1.41 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 126.340 )X 4+6 = 18.64 M
Top Width = 6 M
Arae of Bund = 6+18.64
X 3.160 = 38.93 Sqm
2
12)Net casing Area = 38.93-3.38-0.42-0.42-8.81-2.42-0.18-3.18-1.41-1.41 = 17.30 Sqm

Slno Descrption Area


1 Stripping = 6.680 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 8.81 Sqm
12 Inclined Sand Chimney = 0.18 Sqm
13 horizontal Sand Filter = 2.42 Sqm
14 450mm thk Rip Rap = 3.18 Sqm
15 200mm thk Metal = 1.41 Sqm
16 200mm thk sand = 1.41 Sqm
17 Net Casing Area = 17.30 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.775 Km
T.B.L = + 129.500 M Avg. G.L = + 128.700 M
Stripped.Level = + 128.400 M Stri.Lev = + 128.400 M
Height of Bund 1.100 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 128.400 )X 4+6+1.717+1.9= 14.02 M
Depth of Stripping ( 128.700 - 128.400 ) = 0.300 M
Area of Stripping ( 14.020 X 0.300 ) = 4.210 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-128.4 )X 20% -0.18 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 128.400 )X 0.5*2+3 = 3.1 M
Top Width = 3 M
Arae of Hearting Soils = 3+3.1
X 0.100 = 0.31 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-128.4)X2+3-0.57-4.5 - 3.1/2 = 0.00 M
Top Width = 0+1.5 = 0.00 M
Arae of Hearting Soils = 0+0
X 1.000 = 0.00 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 129.400
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X -1.900 = 0 M
Area of Inclined Sand Chimney = 0X 1 = 0 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 1.100 = 2.46 M
Arae of 450thk Rip Rap = 2.46X0.45 = 1.11 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 1.100 = 2.46 M
Arae of 200thk Sand = 2.46X0.2 = 0.49 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 1.100 = 2.46 M
Arae of 200thk Sand = 2.46X0.2 = 0.49 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 128.400 )X 4+6 = 10.4 M
Top Width = 6 M
Arae of Bund = 6+10.4
X 1.100 = 9.02 Sqm
2
12)Net casing Area = 9.02-3.38-0.42-0.42-0.31-0-0-1.11-0.49-0.49 = 2.40 Sqm

Slno Descrption Area


1 Stripping = 4.210 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 0.31 Sqm
12 Inclined Sand Chimney = 0 Sqm
13 horizontal Sand Filter = 0.00 Sqm
14 450mm thk Rip Rap = 1.11 Sqm
15 200mm thk Metal = 0.49 Sqm
16 200mm thk sand = 0.49 Sqm
17 Net Casing Area = 2.40 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.800 Km
T.B.L = + 129.500 M Avg. G.L = + 127.490 M
Stripped.Level = + 127.190 M Stri.Lev = + 127.190 M
Height of Bund 2.310 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 127.190 )X 4+6+1.717+1.9= 18.86 M
Depth of Stripping ( 127.490 - 127.190 ) = 0.300 M
Area of Stripping ( 18.860 X 0.300 ) = 5.660 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-127.19 )X 20% 0.062 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 127.190 )X 0.5*2+3 = 4.31 M
Top Width = 3 M
Arae of Hearting Soils = 3+4.31
X 1.310 = 4.79 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-127.19)X2+3-0.57-4.5 - 4.31/2 = 0.40 M
Top Width = 0.4+1.5 = 1.90 M
Arae of Hearting Soils = 1.9+0.4
X 1.000 = 1.15 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 128.190
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X -0.690 = 0 M
Area of Inclined Sand Chimney = 0X 1 = 0 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 2.310 = 5.17 M
Arae of 450thk Rip Rap = 5.17X0.45 = 2.33 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 2.310 = 5.17 M
Arae of 200thk Sand = 5.17X0.2 = 1.03 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 2.310 = 5.17 M
Arae of 200thk Sand = 5.17X0.2 = 1.03 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 127.190 )X 4+6 = 15.24 M
Top Width = 6 M
Arae of Bund = 6+15.24
X 2.310 = 24.53 Sqm
2
12)Net casing Area = 24.53-3.38-0.42-0.42-4.79-1.15-0-2.33-1.03-1.03 = 9.98 Sqm

Slno Descrption Area


1 Stripping = 5.660 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 4.79 Sqm
12 Inclined Sand Chimney = 0 Sqm
13 horizontal Sand Filter = 1.15 Sqm
14 450mm thk Rip Rap = 2.33 Sqm
15 200mm thk Metal = 1.03 Sqm
16 200mm thk sand = 1.03 Sqm
17 Net Casing Area = 9.98 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.825 Km
T.B.L = + 129.500 M Avg. G.L = + 125.350 M
Stripped.Level = + 125.050 M Stri.Lev = + 125.050 M
Height of Bund 4.450 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 125.050 )X 4+6+1.717+1.9= 27.42 M
Depth of Stripping ( 125.350 - 125.050 ) = 0.300 M
Area of Stripping ( 27.420 X 0.300 ) = 8.230 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-125.05 )X 20% 0.49 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 125.050 )X 0.5*2+3 = 6.45 M
Top Width = 3 M
Arae of Hearting Soils = 3+6.45
X 3.450 = 16.30 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-125.05)X2+3-0.57-4.5 - 6.45/2 = 3.61 M
Top Width = 3.61+1.5 = 5.11 M
Arae of Hearting Soils = 5.11+3.61
X 1.000 = 4.36 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 126.050
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 1.450 = 1.62 M
Area of Inclined Sand Chimney = 1.62 X 1 = 1.62 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 4.450 = 9.95 M
Arae of 450thk Rip Rap = 9.95X0.45 = 4.48 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 4.450 = 9.95 M
Arae of 200thk Sand = 9.95X0.2 = 1.99 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 4.450 = 9.95 M
Arae of 200thk Sand = 9.95X0.2 = 1.99 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 125.050 )X 4+6 = 23.8 M
Top Width = 6 M
Arae of Bund = 6+23.8
X 4.450 = 66.31 Sqm
2
12)Net casing Area = 66.31-3.38-0.42-0.42-16.3-4.36-1.62-4.48-1.99-1.99 = 31.35 Sqm

Slno Descrption Area


1 Stripping = 8.230 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 16.30 Sqm
12 Inclined Sand Chimney = 1.62 Sqm
13 horizontal Sand Filter = 4.36 Sqm
14 450mm thk Rip Rap = 4.48 Sqm
15 200mm thk Metal = 1.99 Sqm
16 200mm thk sand = 1.99 Sqm
17 Net Casing Area = 31.35 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.850 Km
T.B.L = + 129.500 M Avg. G.L = + 123.760 M
Stripped.Level = + 123.460 M Stri.Lev = + 123.460 M
Height of Bund 6.040 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 123.460 )X 4+6+1.717+1.9= 33.78 M
Depth of Stripping ( 123.760 - 123.460 ) = 0.300 M
Area of Stripping ( 33.780 X 0.300 ) = 10.130 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-123.46 )X 20% 0.808 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 123.460 )X 0.5*2+3 = 8.04 M
Top Width = 3 M
Arae of Hearting Soils = 3+8.04
X 5.040 = 27.82 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-123.46)X2+3-0.57-4.5 - 8.04/2 = 5.99 M
Top Width = 5.99+1.5 = 7.49 M
Arae of Hearting Soils = 7.49+5.99
X 1.000 = 6.74 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 124.460
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 3.040 = 3.4 M
Area of Inclined Sand Chimney = 3.4 X 1 = 3.4 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 6.040 = 13.51 M
Arae of 450thk Rip Rap = 13.51X0.45 = 6.08 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 6.040 = 13.51 M
Arae of 200thk Sand = 13.51X0.2 = 2.7 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 6.040 = 13.51 M
Arae of 200thk Sand = 13.51X0.2 = 2.7 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 123.460 )X 4+6 = 30.16 M
Top Width = 6 M
Arae of Bund = 6+30.16
X 6.040 = 109.20 Sqm
2
12)Net casing Area = 109.2-3.38-0.42-0.42-27.82-6.74-3.4-6.08-2.7-2.7 = 55.54 Sqm

Slno Descrption Area


1 Stripping = 10.130 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 27.82 Sqm
12 Inclined Sand Chimney = 3.4 Sqm
13 horizontal Sand Filter = 6.74 Sqm
14 450mm thk Rip Rap = 6.08 Sqm
15 200mm thk Metal = 2.7 Sqm
16 200mm thk sand = 2.7 Sqm
17 Net Casing Area = 55.54 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.875 Km
T.B.L = + 129.500 M Avg. G.L = + 122.260 M
Stripped.Level = + 121.960 M Stri.Lev = + 121.960 M
Height of Bund 7.540 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 121.960 )X 4+6+1.717+1.9= 39.78 M
Depth of Stripping ( 122.260 - 121.960 ) = 0.300 M
Area of Stripping ( 39.780 X 0.300 ) = 11.930 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-121.96 )X 20% 1.108 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 121.960 )X 0.5*2+3 = 9.54 M
Top Width = 3 M
Arae of Hearting Soils = 3+9.54
X 6.540 = 41.01 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-121.96)X2+3-0.57-4.5 - 9.54/2 = 8.24 M
Top Width = 8.24+1.5 = 9.74 M
Arae of Hearting Soils = 9.74+8.24
X 1.000 = 8.99 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 122.960
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 4.540 = 5.08 M
Area of Inclined Sand Chimney = 5.08 X 1 = 5.08 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 7.540 = 16.86 M
Arae of 450thk Rip Rap = 16.86X0.45 = 7.59 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 7.540 = 16.86 M
Arae of 200thk Sand = 16.86X0.2 = 3.37 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 7.540 = 16.86 M
Arae of 200thk Sand = 16.86X0.2 = 3.37 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 121.960 )X 4+6 = 36.16 M
Top Width = 6 M
Arae of Bund = 6+36.16
X 7.540 = 158.94 Sqm
2
12)Net casing Area = 158.94-3.38-0.42-0.42-41.01-8.99-5.08-7.59-3.37-3.37 = 85.31 Sqm

Slno Descrption Area


1 Stripping = 11.930 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 41.01 Sqm
12 Inclined Sand Chimney = 5.08 Sqm
13 horizontal Sand Filter = 8.99 Sqm
14 450mm thk Rip Rap = 7.59 Sqm
15 200mm thk Metal = 3.37 Sqm
16 200mm thk sand = 3.37 Sqm
17 Net Casing Area = 85.31 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.900 Km
T.B.L = + 129.500 M Avg. G.L = + 122.260 M
Stripped.Level = + 121.960 M Stri.Lev = + 121.960 M
Height of Bund 7.540 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 121.960 )X 4+6+1.717+1.9= 39.78 M
Depth of Stripping ( 122.260 - 121.960 ) = 0.300 M
Area of Stripping ( 39.780 X 0.300 ) = 11.930 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-121.96 )X 20% 1.108 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 121.960 )X 0.5*2+3 = 9.54 M
Top Width = 3 M
Arae of Hearting Soils = 3+9.54
X 6.540 = 41.01 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-121.96)X2+3-0.57-4.5 - 9.54/2 = 8.24 M
Top Width = 8.24+1.5 = 9.74 M
Arae of Hearting Soils = 9.74+8.24
X 1.000 = 8.99 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 122.960
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 4.540 = 5.08 M
Area of Inclined Sand Chimney = 5.08 X 1 = 5.08 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 7.540 = 16.86 M
Arae of 450thk Rip Rap = 16.86X0.45 = 7.59 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 7.540 = 16.86 M
Arae of 200thk Sand = 16.86X0.2 = 3.37 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 7.540 = 16.86 M
Arae of 200thk Sand = 16.86X0.2 = 3.37 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 121.960 )X 4+6 = 36.16 M
Top Width = 6 M
Arae of Bund = 6+36.16
X 7.540 = 158.94 Sqm
2
12)Net casing Area = 158.94-3.38-0.42-0.42-41.01-8.99-5.08-7.59-3.37-3.37 = 85.31 Sqm

Slno Descrption Area


1 Stripping = 11.930 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 41.01 Sqm
12 Inclined Sand Chimney = 5.08 Sqm
13 horizontal Sand Filter = 8.99 Sqm
14 450mm thk Rip Rap = 7.59 Sqm
15 200mm thk Metal = 3.37 Sqm
16 200mm thk sand = 3.37 Sqm
17 Net Casing Area = 85.31 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.925 Km
T.B.L = + 129.500 M Avg. G.L = + 119.760 M
Stripped.Level = + 119.460 M Stri.Lev = + 119.460 M
Height of Bund 10.040 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 119.460 )X 4+6+10+1.717+1.9= 59.78 M
Depth of Stripping ( 119.760 - 119.460 ) = 0.300 M
Area of Stripping ( 59.780 X 0.300 ) = 17.930 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-119.46 )X 20% 1.608 = 1.61 M
Bottom Width of Rock-Toe = 1.608 X 3 = 4.82 M
Area of Rock -Toe = 1/2X4.82X1.608 = 3.88 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.608 = 2.27 M
Area = 2.27X0.2 = 0.45 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.608 = 2.27 M
Area = 2.27X0.2 = 0.45 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 119.460 )X 0.5*2+3 = 12.04 M
Top Width = 3 M
Arae of Hearting Soils = 3+12.04
X 9.040 = 67.98 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-119.46)X2+3+5-0.57-4.82 - 12.04/2 = 16.67 M
Top Width = 16.67+1.5 = 18.17 M
Arae of Hearting Soils = 18.17+16.67
X 1.000 = 17.42 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 120.460
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 7.040 = 7.87 M
Area of Inclined Sand Chimney = 7.87 X 1 = 7.87 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 10.040 + 5 = 27.45 M
Arae of 450thk Rip Rap = 27.45X0.45 = 12.35 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 10.040 + 5 = 27.45 M
Arae of 200thk Sand = 27.45X0.2 = 5.49 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 10.040 + 5 = 27.45 M
Arae of 200thk Sand = 27.45X0.2 = 5.49 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 119.460 )X 4+6+10 = 56.16 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+56.16
X 1.340 = 71.66 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 275.24 Sqm
12)Net casing Area = 275.24-3.88-0.45-0.45-67.98-17.42-7.87-12.35-5.49-5.49 = 153.86 Sqm
Slno Descrption Area
1 Stripping = 17.930 Sqm
8 Rock-toe = 3.88 Sqm
9 Behind sand Filters = 0.45 Sqm
10 Behind Metal Filters = 0.45 Sqm
11 Hearting = 67.98 Sqm
12 Inclined Sand Chimney = 7.87 Sqm
13 horizontal Sand Filter = 17.42 Sqm
14 450mm thk Rip Rap = 12.35 Sqm
15 200mm thk Metal = 5.49 Sqm
16 200mm thk sand = 5.49 Sqm
17 Net Casing Area = 153.86 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.950 Km
T.B.L = + 129.500 M Avg. G.L = + 119.000 M
Stripped.Level = + 118.700 M Stri.Lev = + 118.700 M
Height of Bund 10.800 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 118.700 )X 4+6+10+1.717+1.9= 62.82 M
Depth of Stripping ( 119.000 - 118.700 ) = 0.300 M
Area of Stripping ( 62.820 X 0.300 ) = 18.850 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-118.7 )X 20% 1.76 = 1.76 M
Bottom Width of Rock-Toe = 1.76 X 3 = 5.28 M
Area of Rock -Toe = 1/2X5.28X1.76 = 4.65 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.760 = 2.49 M
Area = 2.49X0.2 = 0.5 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.760 = 2.49 M
Area = 2.49X0.2 = 0.5 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 118.700 )X 0.5*2+3 = 12.8 M
Top Width = 3 M
Arae of Hearting Soils = 3+12.8
X 9.800 = 77.42 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-118.7)X2+3+5-0.57-5.28 - 12.8/2 = 17.35 M
Top Width = 17.35+1.5 = 18.85 M
Arae of Hearting Soils = 18.85+17.35
X 1.000 = 18.10 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 119.700
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 7.800 = 8.72 M
Area of Inclined Sand Chimney = 8.72 X 1 = 8.72 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 10.800 + 5 = 29.15 M
Arae of 450thk Rip Rap = 29.15X0.45 = 13.12 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 10.800 + 5 = 29.15 M
Arae of 200thk Sand = 29.15X0.2 = 5.83 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 10.800 + 5 = 29.15 M
Arae of 200thk Sand = 29.15X0.2 = 5.83 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 118.700 )X 4+6+10 = 59.2 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+59.2
X 2.100 = 115.50 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 319.08 Sqm
12)Net casing Area = 319.08-4.65-0.5-0.5-77.42-18.1-8.72-13.12-5.83-5.83 = 184.41 Sqm
Slno Descrption Area
1 Stripping = 18.850 Sqm
8 Rock-toe = 4.65 Sqm
9 Behind sand Filters = 0.5 Sqm
10 Behind Metal Filters = 0.5 Sqm
11 Hearting = 77.42 Sqm
12 Inclined Sand Chimney = 8.72 Sqm
13 horizontal Sand Filter = 18.10 Sqm
14 450mm thk Rip Rap = 13.12 Sqm
15 200mm thk Metal = 5.83 Sqm
16 200mm thk sand = 5.83 Sqm
17 Net Casing Area = 184.41 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.975 Km
T.B.L = + 129.500 M Avg. G.L = + 118.220 M
Stripped.Level = + 117.920 M Stri.Lev = + 117.920 M
Height of Bund 11.580 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 117.920 )X 4+6+10+1.717+1.9= 65.94 M
Depth of Stripping ( 118.220 - 117.920 ) = 0.300 M
Area of Stripping ( 65.940 X 0.300 ) = 19.780 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-117.92 )X 20% 1.916 = 1.92 M
Bottom Width of Rock-Toe = 1.916 X 3 = 5.75 M
Area of Rock -Toe = 1/2X5.75X1.916 = 5.51 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.916 = 2.71 M
Area = 2.71X0.2 = 0.54 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.916 = 2.71 M
Area = 2.71X0.2 = 0.54 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 117.920 )X 0.5*2+3 = 13.58 M
Top Width = 3 M
Arae of Hearting Soils = 3+13.58
X 10.580 = 87.71 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-117.92)X2+3+5-0.57-5.75 - 13.58/2 = 18.05 M
Top Width = 18.05+1.5 = 19.55 M
Arae of Hearting Soils = 19.55+18.05
X 1.000 = 18.80 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 118.920
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 8.580 = 9.59 M
Area of Inclined Sand Chimney = 9.59 X 1 = 9.59 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 11.580 + 5 = 30.89 M
Arae of 450thk Rip Rap = 30.89X0.45 = 13.9 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 11.580 + 5 = 30.89 M
Arae of 200thk Sand = 30.89X0.2 = 6.18 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 11.580 + 5 = 30.89 M
Arae of 200thk Sand = 30.89X0.2 = 6.18 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 117.920 )X 4+6+10 = 62.32 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+62.32
X 2.880 = 162.89 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 366.47 Sqm
12)Net casing Area = 366.47-5.51-0.54-0.54-87.71-18.8-9.59-13.9-6.18-6.18 = 217.52 Sqm
Slno Descrption Area
1 Stripping = 19.780 Sqm
8 Rock-toe = 5.51 Sqm
9 Behind sand Filters = 0.54 Sqm
10 Behind Metal Filters = 0.54 Sqm
11 Hearting = 87.71 Sqm
12 Inclined Sand Chimney = 9.59 Sqm
13 horizontal Sand Filter = 18.80 Sqm
14 450mm thk Rip Rap = 13.9 Sqm
15 200mm thk Metal = 6.18 Sqm
16 200mm thk sand = 6.18 Sqm
17 Net Casing Area = 217.52 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.000 Km
T.B.L = + 129.500 M Avg. G.L = + 117.650 M
Stripped.Level = + 117.350 M Stri.Lev = + 117.350 M
Height of Bund 12.150 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 117.350 )X 4+6+10+1.717+1.9= 68.22 M
Depth of Stripping ( 117.650 - 117.350 ) = 0.300 M
Area of Stripping ( 68.220 X 0.300 ) = 20.470 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-117.35 )X 20% 2.03 = 2.03 M
Bottom Width of Rock-Toe = 2.03 X 3 = 6.09 M
Area of Rock -Toe = 1/2X6.09X2.03 = 6.18 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.030 = 2.87 M
Area = 2.87X0.2 = 0.57 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.030 = 2.87 M
Area = 2.87X0.2 = 0.57 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 117.350 )X 0.5*2+3 = 14.15 M
Top Width = 3 M
Arae of Hearting Soils = 3+14.15
X 11.150 = 95.61 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-117.35)X2+3+5-0.57-6.09 - 14.15/2 = 18.57 M
Top Width = 18.57+1.5 = 20.07 M
Arae of Hearting Soils = 20.07+18.57
X 1.000 = 19.32 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 118.350
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 9.150 = 10.23 M
Area of Inclined Sand Chimney = 10.23 X 1 = 10.23 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 12.150 + 5 = 32.17 M
Arae of 450thk Rip Rap = 32.17X0.45 = 14.48 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 12.150 + 5 = 32.17 M
Arae of 200thk Sand = 32.17X0.2 = 6.43 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 12.150 + 5 = 32.17 M
Arae of 200thk Sand = 32.17X0.2 = 6.43 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 117.350 )X 4+6+10 = 64.6 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+64.6
X 3.450 = 199.06 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 402.64 Sqm
12)Net casing Area = 402.64-6.18-0.57-0.57-95.61-19.32-10.23-14.48-6.43-6.43 = 242.82 Sqm
Slno Descrption Area
1 Stripping = 20.470 Sqm
8 Rock-toe = 6.18 Sqm
9 Behind sand Filters = 0.57 Sqm
10 Behind Metal Filters = 0.57 Sqm
11 Hearting = 95.61 Sqm
12 Inclined Sand Chimney = 10.23 Sqm
13 horizontal Sand Filter = 19.32 Sqm
14 450mm thk Rip Rap = 14.48 Sqm
15 200mm thk Metal = 6.43 Sqm
16 200mm thk sand = 6.43 Sqm
17 Net Casing Area = 242.82 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.025 Km
T.B.L = + 129.500 M Avg. G.L = + 117.260 M
Stripped.Level = + 116.960 M Stri.Lev = + 116.960 M
Height of Bund 12.540 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 116.960 )X 4+6+10+1.717+1.9= 69.78 M
Depth of Stripping ( 117.260 - 116.960 ) = 0.300 M
Area of Stripping ( 69.780 X 0.300 ) = 20.930 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-116.96 )X 20% 2.108 = 2.11 M
Bottom Width of Rock-Toe = 2.108 X 3 = 6.32 M
Area of Rock -Toe = 1/2X6.32X2.108 = 6.66 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.108 = 2.98 M
Area = 2.98X0.2 = 0.6 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.108 = 2.98 M
Area = 2.98X0.2 = 0.6 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 116.960 )X 0.5*2+3 = 14.54 M
Top Width = 3 M
Arae of Hearting Soils = 3+14.54
X 11.540 = 101.21 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-116.96)X2+3+5-0.57-6.32 - 14.54/2 = 18.92 M
Top Width = 18.92+1.5 = 20.42 M
Arae of Hearting Soils = 20.42+18.92
X 1.000 = 19.67 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 117.960
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 9.540 = 10.67 M
Area of Inclined Sand Chimney = 10.67 X 1 = 10.67 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 12.540 + 5 = 33.04 M
Arae of 450thk Rip Rap = 33.04X0.45 = 14.87 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 12.540 + 5 = 33.04 M
Arae of 200thk Sand = 33.04X0.2 = 6.61 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 12.540 + 5 = 33.04 M
Arae of 200thk Sand = 33.04X0.2 = 6.61 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 116.960 )X 4+6+10 = 66.16 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+66.16
X 3.840 = 224.56 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 428.14 Sqm
12)Net casing Area = 428.14-6.66-0.6-0.6-101.21-19.67-10.67-14.87-6.61-6.61 = 260.64 Sqm
Slno Descrption Area
1 Stripping = 20.930 Sqm
8 Rock-toe = 6.66 Sqm
9 Behind sand Filters = 0.6 Sqm
10 Behind Metal Filters = 0.6 Sqm
11 Hearting = 101.21 Sqm
12 Inclined Sand Chimney = 10.67 Sqm
13 horizontal Sand Filter = 19.67 Sqm
14 450mm thk Rip Rap = 14.87 Sqm
15 200mm thk Metal = 6.61 Sqm
16 200mm thk sand = 6.61 Sqm
17 Net Casing Area = 260.64 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.050 Km
T.B.L = + 129.500 M Avg. G.L = + 117.220 M
Stripped.Level = + 116.920 M Stri.Lev = + 116.920 M
Height of Bund 12.580 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 116.920 )X 4+6+10+1.717+1.9= 69.94 M
Depth of Stripping ( 117.220 - 116.920 ) = 0.300 M
Area of Stripping ( 69.940 X 0.300 ) = 20.980 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-116.92 )X 20% 2.116 = 2.12 M
Bottom Width of Rock-Toe = 2.116 X 3 = 6.35 M
Area of Rock -Toe = 1/2X6.35X2.116 = 6.72 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.116 = 2.99 M
Area = 2.99X0.2 = 0.6 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.116 = 2.99 M
Area = 2.99X0.2 = 0.6 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 116.920 )X 0.5*2+3 = 14.58 M
Top Width = 3 M
Arae of Hearting Soils = 3+14.58
X 11.580 = 101.79 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-116.92)X2+3+5-0.57-6.35 - 14.58/2 = 18.95 M
Top Width = 18.95+1.5 = 20.45 M
Arae of Hearting Soils = 20.45+18.95
X 1.000 = 19.70 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 117.920
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 9.580 = 10.71 M
Area of Inclined Sand Chimney = 10.71 X 1 = 10.71 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 12.580 + 5 = 33.13 M
Arae of 450thk Rip Rap = 33.13X0.45 = 14.91 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 12.580 + 5 = 33.13 M
Arae of 200thk Sand = 33.13X0.2 = 6.63 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 12.580 + 5 = 33.13 M
Arae of 200thk Sand = 33.13X0.2 = 6.63 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 116.920 )X 4+6+10 = 66.32 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+66.32
X 3.880 = 227.21 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 430.79 Sqm
12)Net casing Area = 430.79-6.72-0.6-0.6-101.79-19.7-10.71-14.91-6.63-6.63 = 262.50 Sqm
Slno Descrption Area
1 Stripping = 20.980 Sqm
8 Rock-toe = 6.72 Sqm
9 Behind sand Filters = 0.6 Sqm
10 Behind Metal Filters = 0.6 Sqm
11 Hearting = 101.79 Sqm
12 Inclined Sand Chimney = 10.71 Sqm
13 horizontal Sand Filter = 19.70 Sqm
14 450mm thk Rip Rap = 14.91 Sqm
15 200mm thk Metal = 6.63 Sqm
16 200mm thk sand = 6.63 Sqm
17 Net Casing Area = 262.50 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.075 Km
T.B.L = + 129.500 M Avg. G.L = + 117.490 M
Stripped.Level = + 117.490 M Stri.Lev = + 117.190 M
Height of Bund 12.010 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 117.190 )X 4+6+10+1.717+1.9= 68.86 M
Depth of Stripping ( 117.490 - 117.190 ) = 0.300 M
Area of Stripping ( 68.860 X 0.300 ) = 20.660 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-117.49 )X 20% 2.002 = 2.00 M
Bottom Width of Rock-Toe = 2.002 X 3 = 6.01 M
Area of Rock -Toe = 1/2X6.01X2.002 = 6.02 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.002 = 2.83 M
Area = 2.83X0.2 = 0.57 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.002 = 2.83 M
Area = 2.83X0.2 = 0.57 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 117.490 )X 0.5*2+3 = 14.01 M
Top Width = 3 M
Arae of Hearting Soils = 3+14.01
X 11.010 = 93.64 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-117.49)X2+3+5-0.57-6.01 - 14.01/2 = 18.44 M
Top Width = 18.44+1.5 = 19.94 M
Arae of Hearting Soils = 19.94+18.44
X 1.000 = 19.19 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 118.490
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 9.010 = 10.07 M
Area of Inclined Sand Chimney = 10.07 X 1 = 10.07 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 12.010 + 5 = 31.86 M
Arae of 450thk Rip Rap = 31.86X0.45 = 14.34 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 12.010 + 5 = 31.86 M
Arae of 200thk Sand = 31.86X0.2 = 6.37 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 12.010 + 5 = 31.86 M
Arae of 200thk Sand = 31.86X0.2 = 6.37 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 117.490 )X 4+6+10 = 64.04 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+64.04
X 3.310 = 190.06 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 393.64 Sqm
12)Net casing Area = 393.64-6.02-0.57-0.57-93.64-19.19-10.07-14.34-6.37-6.37 = 236.50 Sqm
Slno Descrption Area
1 Stripping = 20.660 Sqm
8 Rock-toe = 6.02 Sqm
9 Behind sand Filters = 0.57 Sqm
10 Behind Metal Filters = 0.57 Sqm
11 Hearting = 93.64 Sqm
12 Inclined Sand Chimney = 10.07 Sqm
13 horizontal Sand Filter = 19.19 Sqm
14 450mm thk Rip Rap = 14.34 Sqm
15 200mm thk Metal = 6.37 Sqm
16 200mm thk sand = 6.37 Sqm
17 Net Casing Area = 236.50 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.100 Km
T.B.L = + 129.500 M Avg. G.L = + 117.630 M
Stripped.Level = + 117.330 M Stri.Lev = + 117.330 M
Height of Bund 12.170 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 117.330 )X 4+6+10+1.717+1.9= 68.3 M
Depth of Stripping ( 117.630 - 117.330 ) = 0.300 M
Area of Stripping ( 68.300 X 0.300 ) = 20.490 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-117.33 )X 20% 2.034 = 2.03 M
Bottom Width of Rock-Toe = 2.034 X 3 = 6.10 M
Area of Rock -Toe = 1/2X6.1X2.034 = 6.2 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.034 = 2.88 M
Area = 2.88X0.2 = 0.58 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.034 = 2.88 M
Area = 2.88X0.2 = 0.58 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 117.330 )X 0.5*2+3 = 14.17 M
Top Width = 3 M
Arae of Hearting Soils = 3+14.17
X 11.170 = 95.89 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-117.33)X2+3+5-0.57-6.1 - 14.17/2 = 18.59 M
Top Width = 18.59+1.5 = 20.09 M
Arae of Hearting Soils = 20.09+18.59
X 1.000 = 19.34 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 118.330
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 9.170 = 10.25 M
Area of Inclined Sand Chimney = 10.25 X 1 = 10.25 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 12.170 + 5 = 32.21 M
Arae of 450thk Rip Rap = 32.21X0.45 = 14.49 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 12.170 + 5 = 32.21 M
Arae of 200thk Sand = 32.21X0.2 = 6.44 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 12.170 + 5 = 32.21 M
Arae of 200thk Sand = 32.21X0.2 = 6.44 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 117.330 )X 4+6+10 = 64.68 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+64.68
X 3.470 = 200.36 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 403.94 Sqm
12)Net casing Area = 403.94-6.2-0.58-0.58-95.89-19.34-10.25-14.49-6.44-6.44 = 243.73 Sqm
Slno Descrption Area
1 Stripping = 20.490 Sqm
8 Rock-toe = 6.2 Sqm
9 Behind sand Filters = 0.58 Sqm
10 Behind Metal Filters = 0.58 Sqm
11 Hearting = 95.89 Sqm
12 Inclined Sand Chimney = 10.25 Sqm
13 horizontal Sand Filter = 19.34 Sqm
14 450mm thk Rip Rap = 14.49 Sqm
15 200mm thk Metal = 6.44 Sqm
16 200mm thk sand = 6.44 Sqm
17 Net Casing Area = 243.73 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.125 Km
T.B.L = + 129.500 M Avg. G.L = + 117.850 M
Stripped.Level = + 117.550 M Stri.Lev = + 117.550 M
Height of Bund 11.950 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 117.550 )X 4+6+10+1.717+1.9= 67.42 M
Depth of Stripping ( 117.850 - 117.550 ) = 0.300 M
Area of Stripping ( 67.420 X 0.300 ) = 20.230 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-117.55 )X 20% 1.99 = 1.99 M
Bottom Width of Rock-Toe = 1.99 X 3 = 5.97 M
Area of Rock -Toe = 1/2X5.97X1.99 = 5.94 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.990 = 2.81 M
Area = 2.81X0.2 = 0.56 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.990 = 2.81 M
Area = 2.81X0.2 = 0.56 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 117.550 )X 0.5*2+3 = 13.95 M
Top Width = 3 M
Arae of Hearting Soils = 3+13.95
X 10.950 = 92.80 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-117.55)X2+3+5-0.57-5.97 - 13.95/2 = 18.39 M
Top Width = 18.39+1.5 = 19.89 M
Arae of Hearting Soils = 19.89+18.39
X 1.000 = 19.14 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 118.550
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 8.950 = 10.01 M
Area of Inclined Sand Chimney = 10.01 X 1 = 10.01 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 11.950 + 5 = 31.72 M
Arae of 450thk Rip Rap = 31.72X0.45 = 14.27 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 11.950 + 5 = 31.72 M
Arae of 200thk Sand = 31.72X0.2 = 6.34 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 11.950 + 5 = 31.72 M
Arae of 200thk Sand = 31.72X0.2 = 6.34 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 117.550 )X 4+6+10 = 63.8 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+63.8
X 3.250 = 186.23 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 389.81 Sqm
12)Net casing Area = 389.81-5.94-0.56-0.56-92.8-19.14-10.01-14.27-6.34-6.34 = 233.85 Sqm
Slno Descrption Area
1 Stripping = 20.230 Sqm
8 Rock-toe = 5.94 Sqm
9 Behind sand Filters = 0.56 Sqm
10 Behind Metal Filters = 0.56 Sqm
11 Hearting = 92.80 Sqm
12 Inclined Sand Chimney = 10.01 Sqm
13 horizontal Sand Filter = 19.14 Sqm
14 450mm thk Rip Rap = 14.27 Sqm
15 200mm thk Metal = 6.34 Sqm
16 200mm thk sand = 6.34 Sqm
17 Net Casing Area = 233.85 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.150 Km
T.B.L = + 129.500 M Avg. G.L = + 117.960 M
Stripped.Level = + 117.660 M Stri.Lev = + 117.660 M
Height of Bund 11.840 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 117.660 )X 4+6+10+1.717+1.9= 66.98 M
Depth of Stripping ( 117.960 - 117.660 ) = 0.300 M
Area of Stripping ( 66.980 X 0.300 ) = 20.090 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-117.66 )X 20% 1.968 = 1.97 M
Bottom Width of Rock-Toe = 1.968 X 3 = 5.90 M
Area of Rock -Toe = 1/2X5.9X1.968 = 5.81 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.968 = 2.78 M
Area = 2.78X0.2 = 0.56 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.968 = 2.78 M
Area = 2.78X0.2 = 0.56 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 117.660 )X 0.5*2+3 = 13.84 M
Top Width = 3 M
Arae of Hearting Soils = 3+13.84
X 10.840 = 91.27 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-117.66)X2+3+5-0.57-5.9 - 13.84/2 = 18.29 M
Top Width = 18.29+1.5 = 19.79 M
Arae of Hearting Soils = 19.79+18.29
X 1.000 = 19.04 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 118.660
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 8.840 = 9.88 M
Area of Inclined Sand Chimney = 9.88 X 1 = 9.88 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 11.840 + 5 = 31.48 M
Arae of 450thk Rip Rap = 31.48X0.45 = 14.17 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 11.840 + 5 = 31.48 M
Arae of 200thk Sand = 31.48X0.2 = 6.3 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 11.840 + 5 = 31.48 M
Arae of 200thk Sand = 31.48X0.2 = 6.3 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 117.660 )X 4+6+10 = 63.36 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+63.36
X 3.140 = 179.23 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 382.81 Sqm
12)Net casing Area = 382.81-5.81-0.56-0.56-91.27-19.04-9.88-14.17-6.3-6.3 = 228.92 Sqm
Slno Descrption Area
1 Stripping = 20.090 Sqm
8 Rock-toe = 5.81 Sqm
9 Behind sand Filters = 0.56 Sqm
10 Behind Metal Filters = 0.56 Sqm
11 Hearting = 91.27 Sqm
12 Inclined Sand Chimney = 9.88 Sqm
13 horizontal Sand Filter = 19.04 Sqm
14 450mm thk Rip Rap = 14.17 Sqm
15 200mm thk Metal = 6.3 Sqm
16 200mm thk sand = 6.3 Sqm
17 Net Casing Area = 228.92 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.175 Km
T.B.L = + 129.500 M Avg. G.L = + 118.140 M
Stripped.Level = + 117.840 M Stri.Lev = + 117.840 M
Height of Bund 11.660 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 117.840 )X 4+6+10+1.717+1.9= 66.26 M
Depth of Stripping ( 118.140 - 117.840 ) = 0.300 M
Area of Stripping ( 66.260 X 0.300 ) = 19.880 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-117.84 )X 20% 1.932 = 1.93 M
Bottom Width of Rock-Toe = 1.932 X 3 = 5.80 M
Area of Rock -Toe = 1/2X5.8X1.932 = 5.6 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.932 = 2.73 M
Area = 2.73X0.2 = 0.55 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.932 = 2.73 M
Area = 2.73X0.2 = 0.55 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 117.840 )X 0.5*2+3 = 13.66 M
Top Width = 3 M
Arae of Hearting Soils = 3+13.66
X 10.660 = 88.80 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-117.84)X2+3+5-0.57-5.8 - 13.66/2 = 18.12 M
Top Width = 18.12+1.5 = 19.62 M
Arae of Hearting Soils = 19.62+18.12
X 1.000 = 18.87 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 118.840
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 8.660 = 9.68 M
Area of Inclined Sand Chimney = 9.68 X 1 = 9.68 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 11.660 + 5 = 31.07 M
Arae of 450thk Rip Rap = 31.07X0.45 = 13.98 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 11.660 + 5 = 31.07 M
Arae of 200thk Sand = 31.07X0.2 = 6.21 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 11.660 + 5 = 31.07 M
Arae of 200thk Sand = 31.07X0.2 = 6.21 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 117.840 )X 4+6+10 = 62.64 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+62.64
X 2.960 = 167.89 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 371.47 Sqm
12)Net casing Area = 371.47-5.6-0.55-0.55-88.8-18.87-9.68-13.98-6.21-6.21 = 221.02 Sqm
Slno Descrption Area
1 Stripping = 19.880 Sqm
8 Rock-toe = 5.6 Sqm
9 Behind sand Filters = 0.55 Sqm
10 Behind Metal Filters = 0.55 Sqm
11 Hearting = 88.80 Sqm
12 Inclined Sand Chimney = 9.68 Sqm
13 horizontal Sand Filter = 18.87 Sqm
14 450mm thk Rip Rap = 13.98 Sqm
15 200mm thk Metal = 6.21 Sqm
16 200mm thk sand = 6.21 Sqm
17 Net Casing Area = 221.02 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.200 Km
T.B.L = + 131.000 M Avg. G.L = + 118.270 M
Stripped.Level = + 117.970 M Stri.Lev = + 117.970 M
Height of Bund 13.030 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 131.000 - 117.970 )X 4+6+10+1.717+1.9= 71.74 M
Depth of Stripping ( 118.270 - 117.970 ) = 0.300 M
Area of Stripping ( 71.740 X 0.300 ) = 21.520 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-117.97 )X 20% 1.906 = 1.91 M
Bottom Width of Rock-Toe = 1.906 X 3 = 5.72 M
Area of Rock -Toe = 1/2X5.72X1.906 = 5.45 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.906 = 2.7 M
Area = 2.7X0.2 = 0.54 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.906 = 2.7 M
Area = 2.7X0.2 = 0.54 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 117.970 )X 0.5*2+3 = 13.53 M
Top Width = 3 M
Arae of Hearting Soils = 3+13.53
X 10.530 = 87.03 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 131-117.97)X2+3+5-0.57-5.72 - 13.53/2 = 21.01 M
Top Width = 21.01+1.5 = 22.51 M
Arae of Hearting Soils = 22.51+21.01
X 1.000 = 21.76 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 118.970
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 8.530 = 9.54 M
Area of Inclined Sand Chimney = 9.54 X 1 = 9.54 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 13.030 + 5 = 34.14 M
Arae of 450thk Rip Rap = 34.14X0.45 = 15.36 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 13.030 + 5 = 34.14 M
Arae of 200thk Sand = 34.14X0.2 = 6.83 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 13.030 + 5 = 34.14 M
Arae of 200thk Sand = 34.14X0.2 = 6.83 Sqm
9) Area of Bund
Bottom Width ( 131.000 - 117.970 )X 4+6+10 = 68.12 M
At 120.8 Incl Berm ( 131.000 - 120.800 )X 4+6+10 56.8 M
Top Width = 6 M
Arae of Bund up to Berm = 56.8+68.12
X 2.830 = 176.76 Sqm
2
Arae of Bund Berm to TBL = 6+46.8
X 10.200 = 269.28 Sqm
2
Total 446.04 Sqm
12)Net casing Area = 446.04-5.45-0.54-0.54-87.03-21.76-9.54-15.36-6.83-6.83 = 292.16 Sqm
Slno Descrption Area
1 Stripping = 21.520 Sqm
8 Rock-toe = 5.45 Sqm
9 Behind sand Filters = 0.54 Sqm
10 Behind Metal Filters = 0.54 Sqm
11 Hearting = 87.03 Sqm
12 Inclined Sand Chimney = 9.54 Sqm
13 horizontal Sand Filter = 21.76 Sqm
14 450mm thk Rip Rap = 15.36 Sqm
15 200mm thk Metal = 6.83 Sqm
16 200mm thk sand = 6.83 Sqm
17 Net Casing Area = 292.16 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.225 Km
T.B.L = + 129.500 M Avg. G.L = + 118.400 M
Stripped.Level = + 118.100 M Stri.Lev = + 118.100 M
Height of Bund 11.400 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 118.100 )X 4+6+10+1.717+1.9= 65.22 M
Depth of Stripping ( 118.400 - 118.100 ) = 0.300 M
Area of Stripping ( 65.220 X 0.300 ) = 19.570 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-118.1 )X 20% 1.88 = 1.88 M
Bottom Width of Rock-Toe = 1.88 X 3 = 5.64 M
Area of Rock -Toe = 1/2X5.64X1.88 = 5.3 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.880 = 2.66 M
Area = 2.66X0.2 = 0.53 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.880 = 2.66 M
Area = 2.66X0.2 = 0.53 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 118.100 )X 0.5*2+3 = 13.4 M
Top Width = 3 M
Arae of Hearting Soils = 3+13.4
X 10.400 = 85.28 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-118.1)X2+3+5-0.57-5.64 - 13.4/2 = 17.89 M
Top Width = 17.89+1.5 = 19.39 M
Arae of Hearting Soils = 19.39+17.89
X 1.000 = 18.64 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 119.100
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 8.400 = 9.39 M
Area of Inclined Sand Chimney = 9.39 X 1 = 9.39 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 11.400 + 5 = 30.49 M
Arae of 450thk Rip Rap = 30.49X0.45 = 13.72 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 11.400 + 5 = 30.49 M
Arae of 200thk Sand = 30.49X0.2 = 6.1 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 11.400 + 5 = 30.49 M
Arae of 200thk Sand = 30.49X0.2 = 6.1 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 118.100 )X 4+6+10 = 61.6 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+61.6
X 2.700 = 151.74 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 355.32 Sqm
12)Net casing Area = 355.32-5.3-0.53-0.53-85.28-18.64-9.39-13.72-6.1-6.1 = 209.73 Sqm
Slno Descrption Area
1 Stripping = 19.570 Sqm
8 Rock-toe = 5.3 Sqm
9 Behind sand Filters = 0.53 Sqm
10 Behind Metal Filters = 0.53 Sqm
11 Hearting = 85.28 Sqm
12 Inclined Sand Chimney = 9.39 Sqm
13 horizontal Sand Filter = 18.64 Sqm
14 450mm thk Rip Rap = 13.72 Sqm
15 200mm thk Metal = 6.1 Sqm
16 200mm thk sand = 6.1 Sqm
17 Net Casing Area = 209.73 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.250 Km
T.B.L = + 129.500 M Avg. G.L = + 118.440 M
Stripped.Level = + 118.140 M Stri.Lev = + 118.140 M
Height of Bund 11.360 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 118.140 )X 4+6+10+1.717+1.9= 65.06 M
Depth of Stripping ( 118.440 - 118.140 ) = 0.300 M
Area of Stripping ( 65.060 X 0.300 ) = 19.520 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-118.14 )X 20% 1.872 = 1.87 M
Bottom Width of Rock-Toe = 1.872 X 3 = 5.62 M
Area of Rock -Toe = 1/2X5.62X1.872 = 5.26 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.872 = 2.65 M
Area = 2.65X0.2 = 0.53 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.872 = 2.65 M
Area = 2.65X0.2 = 0.53 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 118.140 )X 0.5*2+3 = 13.36 M
Top Width = 3 M
Arae of Hearting Soils = 3+13.36
X 10.360 = 84.74 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-118.14)X2+3+5-0.57-5.62 - 13.36/2 = 17.85 M
Top Width = 17.85+1.5 = 19.35 M
Arae of Hearting Soils = 19.35+17.85
X 1.000 = 18.60 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 119.140
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 8.360 = 9.35 M
Area of Inclined Sand Chimney = 9.35 X 1 = 9.35 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 11.360 + 5 = 30.4 M
Arae of 450thk Rip Rap = 30.4X0.45 = 13.68 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 11.360 + 5 = 30.4 M
Arae of 200thk Sand = 30.4X0.2 = 6.08 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 11.360 + 5 = 30.4 M
Arae of 200thk Sand = 30.4X0.2 = 6.08 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 118.140 )X 4+6+10 = 61.44 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+61.44
X 2.660 = 149.28 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 352.86 Sqm
12)Net casing Area = 352.86-5.26-0.53-0.53-84.74-18.6-9.35-13.68-6.08-6.08 = 208.01 Sqm
Slno Descrption Area
1 Stripping = 19.520 Sqm
8 Rock-toe = 5.26 Sqm
9 Behind sand Filters = 0.53 Sqm
10 Behind Metal Filters = 0.53 Sqm
11 Hearting = 84.74 Sqm
12 Inclined Sand Chimney = 9.35 Sqm
13 horizontal Sand Filter = 18.60 Sqm
14 450mm thk Rip Rap = 13.68 Sqm
15 200mm thk Metal = 6.08 Sqm
16 200mm thk sand = 6.08 Sqm
17 Net Casing Area = 208.01 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.275 Km
T.B.L = + 129.500 M Avg. G.L = + 118.500 M
Stripped.Level = + 118.200 M Stri.Lev = + 118.200 M
Height of Bund 11.300 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 118.200 )X 4+6+10+1.717+1.9= 64.82 M
Depth of Stripping ( 118.500 - 118.200 ) = 0.300 M
Area of Stripping ( 64.820 X 0.300 ) = 19.450 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-118.2 )X 20% 1.86 = 1.86 M
Bottom Width of Rock-Toe = 1.86 X 3 = 5.58 M
Area of Rock -Toe = 1/2X5.58X1.86 = 5.19 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.860 = 2.63 M
Area = 2.63X0.2 = 0.53 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.860 = 2.63 M
Area = 2.63X0.2 = 0.53 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 118.200 )X 0.5*2+3 = 13.3 M
Top Width = 3 M
Arae of Hearting Soils = 3+13.3
X 10.300 = 83.95 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-118.2)X2+3+5-0.57-5.58 - 13.3/2 = 17.80 M
Top Width = 17.8+1.5 = 19.30 M
Arae of Hearting Soils = 19.3+17.8
X 1.000 = 18.55 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 119.200
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 8.300 = 9.28 M
Area of Inclined Sand Chimney = 9.28 X 1 = 9.28 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 11.300 + 5 = 30.27 M
Arae of 450thk Rip Rap = 30.27X0.45 = 13.62 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 11.300 + 5 = 30.27 M
Arae of 200thk Sand = 30.27X0.2 = 6.05 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 11.300 + 5 = 30.27 M
Arae of 200thk Sand = 30.27X0.2 = 6.05 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 118.200 )X 4+6+10 = 61.2 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+61.2
X 2.600 = 145.60 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 349.18 Sqm
12)Net casing Area = 349.18-5.19-0.53-0.53-83.95-18.55-9.28-13.62-6.05-6.05 = 205.43 Sqm
Slno Descrption Area
1 Stripping = 19.450 Sqm
8 Rock-toe = 5.19 Sqm
9 Behind sand Filters = 0.53 Sqm
10 Behind Metal Filters = 0.53 Sqm
11 Hearting = 83.95 Sqm
12 Inclined Sand Chimney = 9.28 Sqm
13 horizontal Sand Filter = 18.55 Sqm
14 450mm thk Rip Rap = 13.62 Sqm
15 200mm thk Metal = 6.05 Sqm
16 200mm thk sand = 6.05 Sqm
17 Net Casing Area = 205.43 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.300 Km
T.B.L = + 131.000 M Avg. G.L = + 118.415 M
Stripped.Level = + 118.115 M Stri.Lev = + 118.115 M
Height of Bund 12.885 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 131.000 - 118.115 )X 4+6+10+1.717+1.9= 71.16 M
Depth of Stripping ( 118.415 - 118.115 ) = 0.300 M
Area of Stripping ( 71.160 X 0.300 ) = 21.350 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-118.115 )X 20% 1.877 = 1.88 M
Bottom Width of Rock-Toe = 1.877 X 3 = 5.63 M
Area of Rock -Toe = 1/2X5.63X1.877 = 5.28 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.877 = 2.65 M
Area = 2.65X0.2 = 0.53 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.877 = 2.65 M
Area = 2.65X0.2 = 0.53 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 118.115 )X 0.5*2+3 = 13.39 M
Top Width = 3 M
Arae of Hearting Soils = 3+13.39
X 10.385 = 85.11 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 131-118.115)X2+3+5-0.57-5.63 - 13.39/2 = 20.88 M
Top Width = 20.88+1.5 = 22.38 M
Arae of Hearting Soils = 22.38+20.88
X 1.000 = 21.63 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 119.115
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 8.385 = 9.37 M
Area of Inclined Sand Chimney = 9.37 X 1 = 9.37 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 12.885 + 5 = 33.81 M
Arae of 450thk Rip Rap = 33.81X0.45 = 15.21 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 12.885 + 5 = 33.81 M
Arae of 200thk Sand = 33.81X0.2 = 6.76 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 12.885 + 5 = 33.81 M
Arae of 200thk Sand = 33.81X0.2 = 6.76 Sqm
9) Area of Bund
Bottom Width ( 131.000 - 118.115 )X 4+6+10 = 67.54 M
At 120.8 Incl Berm ( 131.000 - 120.800 )X 4+6+10 56.8 M
Top Width = 6 M
Arae of Bund up to Berm = 56.8+67.54
X 2.685 = 166.93 Sqm
2
Arae of Bund Berm to TBL = 6+46.8
X 10.200 = 269.28 Sqm
2
Total 436.21 Sqm
12)Net casing Area = 436.21-5.28-0.53-0.53-85.11-21.63-9.37-15.21-6.76-6.76 = 285.03 Sqm
Slno Descrption Area
1 Stripping = 21.350 Sqm
8 Rock-toe = 5.28 Sqm
9 Behind sand Filters = 0.53 Sqm
10 Behind Metal Filters = 0.53 Sqm
11 Hearting = 85.11 Sqm
12 Inclined Sand Chimney = 9.37 Sqm
13 horizontal Sand Filter = 21.63 Sqm
14 450mm thk Rip Rap = 15.21 Sqm
15 200mm thk Metal = 6.76 Sqm
16 200mm thk sand = 6.76 Sqm
17 Net Casing Area = 285.03 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.325 Km
T.B.L = + 129.500 M Avg. G.L = + 118.270 M
Stripped.Level = + 117.970 M Stri.Lev = + 117.970 M
Height of Bund 11.530 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 117.970 )X 4+6+10+1.717+1.9= 65.74 M
Depth of Stripping ( 118.270 - 117.970 ) = 0.300 M
Area of Stripping ( 65.740 X 0.300 ) = 19.720 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-117.97 )X 20% 1.906 = 1.91 M
Bottom Width of Rock-Toe = 1.906 X 3 = 5.72 M
Area of Rock -Toe = 1/2X5.72X1.906 = 5.45 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.906 = 2.7 M
Area = 2.7X0.2 = 0.54 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.906 = 2.7 M
Area = 2.7X0.2 = 0.54 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 117.970 )X 0.5*2+3 = 13.53 M
Top Width = 3 M
Arae of Hearting Soils = 3+13.53
X 10.530 = 87.03 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-117.97)X2+3+5-0.57-5.72 - 13.53/2 = 18.01 M
Top Width = 18.01+1.5 = 19.51 M
Arae of Hearting Soils = 19.51+18.01
X 1.000 = 18.76 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 118.970
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 8.530 = 9.54 M
Area of Inclined Sand Chimney = 9.54 X 1 = 9.54 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 11.530 + 5 = 30.78 M
Arae of 450thk Rip Rap = 30.78X0.45 = 13.85 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 11.530 + 5 = 30.78 M
Arae of 200thk Sand = 30.78X0.2 = 6.16 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 11.530 + 5 = 30.78 M
Arae of 200thk Sand = 30.78X0.2 = 6.16 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 117.970 )X 4+6+10 = 62.12 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+62.12
X 2.830 = 159.78 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 363.36 Sqm
12)Net casing Area = 363.36-5.45-0.54-0.54-87.03-18.76-9.54-13.85-6.16-6.16 = 215.33 Sqm
Slno Descrption Area
1 Stripping = 19.720 Sqm
8 Rock-toe = 5.45 Sqm
9 Behind sand Filters = 0.54 Sqm
10 Behind Metal Filters = 0.54 Sqm
11 Hearting = 87.03 Sqm
12 Inclined Sand Chimney = 9.54 Sqm
13 horizontal Sand Filter = 18.76 Sqm
14 450mm thk Rip Rap = 13.85 Sqm
15 200mm thk Metal = 6.16 Sqm
16 200mm thk sand = 6.16 Sqm
17 Net Casing Area = 215.33 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.350 Km
T.B.L = + 129.500 M Avg. G.L = + 116.475 M
Stripped.Level = + 116.175 M Stri.Lev = + 116.175 M
Height of Bund 13.325 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 116.175 )X 4+6+10+1.717+1.9= 72.92 M
Depth of Stripping ( 116.475 - 116.175 ) = 0.300 M
Area of Stripping ( 72.920 X 0.300 ) = 21.880 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-116.175 )X 20% 2.265 = 2.27 M
Bottom Width of Rock-Toe = 2.265 X 3 = 6.80 M
Area of Rock -Toe = 1/2X6.8X2.265 = 7.7 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.265 = 3.2 M
Area = 3.2X0.2 = 0.64 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.265 = 3.2 M
Area = 3.2X0.2 = 0.64 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 116.175 )X 0.5*2+3 = 15.33 M
Top Width = 3 M
Arae of Hearting Soils = 3+15.33
X 12.325 = 112.96 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-116.175)X2+3+5-0.57-6.8 - 15.33/2 = 19.62 M
Top Width = 19.62+1.5 = 21.12 M
Arae of Hearting Soils = 21.12+19.62
X 1.000 = 20.37 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 117.175
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 10.325 = 11.54 M
Area of Inclined Sand Chimney = 11.54 X 1 = 11.54 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 13.325 + 5 = 34.8 M
Arae of 450thk Rip Rap = 34.8X0.45 = 15.66 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 13.325 + 5 = 34.8 M
Arae of 200thk Sand = 34.8X0.2 = 6.96 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 13.325 + 5 = 34.8 M
Arae of 200thk Sand = 34.8X0.2 = 6.96 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 116.175 )X 4+6+10 = 69.3 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+69.3
X 4.625 = 277.73 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 481.31 Sqm
12)Net casing Area = 481.31-7.7-0.64-0.64-112.96-20.37-11.54-15.66-6.96-6.96 = 297.88 Sqm
Slno Descrption Area
1 Stripping = 21.880 Sqm
8 Rock-toe = 7.7 Sqm
9 Behind sand Filters = 0.64 Sqm
10 Behind Metal Filters = 0.64 Sqm
11 Hearting = 112.96 Sqm
12 Inclined Sand Chimney = 11.54 Sqm
13 horizontal Sand Filter = 20.37 Sqm
14 450mm thk Rip Rap = 15.66 Sqm
15 200mm thk Metal = 6.96 Sqm
16 200mm thk sand = 6.96 Sqm
17 Net Casing Area = 297.88 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.375 Km
T.B.L = + 129.500 M Avg. G.L = + 116.940 M
Stripped.Level = + 116.640 M Stri.Lev = + 116.640 M
Height of Bund 12.860 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 116.640 )X 4+6+10+1.717+1.9= 71.06 M
Depth of Stripping ( 116.940 - 116.640 ) = 0.300 M
Area of Stripping ( 71.060 X 0.300 ) = 21.320 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-116.64 )X 20% 2.172 = 2.17 M
Bottom Width of Rock-Toe = 2.172 X 3 = 6.52 M
Area of Rock -Toe = 1/2X6.52X2.172 = 7.08 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.172 = 3.07 M
Area = 3.07X0.2 = 0.61 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.172 = 3.07 M
Area = 3.07X0.2 = 0.61 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 116.640 )X 0.5*2+3 = 14.86 M
Top Width = 3 M
Arae of Hearting Soils = 3+14.86
X 11.860 = 105.91 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-116.64)X2+3+5-0.57-6.52 - 14.86/2 = 19.20 M
Top Width = 19.2+1.5 = 20.70 M
Arae of Hearting Soils = 20.7+19.2
X 1.000 = 19.95 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 117.640
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 9.860 = 11.02 M
Area of Inclined Sand Chimney = 11.02 X 1 = 11.02 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 12.860 + 5 = 33.76 M
Arae of 450thk Rip Rap = 33.76X0.45 = 15.19 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 12.860 + 5 = 33.76 M
Arae of 200thk Sand = 33.76X0.2 = 6.75 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 12.860 + 5 = 33.76 M
Arae of 200thk Sand = 33.76X0.2 = 6.75 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 116.640 )X 4+6+10 = 67.44 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+67.44
X 4.160 = 245.94 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 449.52 Sqm
12)Net casing Area = 449.52-7.08-0.61-0.61-105.91-19.95-11.02-15.19-6.75-6.75 = 275.65 Sqm
Slno Descrption Area
1 Stripping = 21.320 Sqm
8 Rock-toe = 7.08 Sqm
9 Behind sand Filters = 0.61 Sqm
10 Behind Metal Filters = 0.61 Sqm
11 Hearting = 105.91 Sqm
12 Inclined Sand Chimney = 11.02 Sqm
13 horizontal Sand Filter = 19.95 Sqm
14 450mm thk Rip Rap = 15.19 Sqm
15 200mm thk Metal = 6.75 Sqm
16 200mm thk sand = 6.75 Sqm
17 Net Casing Area = 275.65 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.400 Km
T.B.L = + 129.500 M Avg. G.L = + 117.455 M
Stripped.Level = + 117.155 M Stri.Lev = + 117.155 M
Height of Bund 12.345 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 117.155 )X 4+6+10+1.717+1.9= 69 M
Depth of Stripping ( 117.455 - 117.155 ) = 0.300 M
Area of Stripping ( 69.000 X 0.300 ) = 20.700 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-117.155 )X 20% 2.069 = 2.07 M
Bottom Width of Rock-Toe = 2.069 X 3 = 6.21 M
Area of Rock -Toe = 1/2X6.21X2.069 = 6.42 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.069 = 2.93 M
Area = 2.93X0.2 = 0.59 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.069 = 2.93 M
Area = 2.93X0.2 = 0.59 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 117.155 )X 0.5*2+3 = 14.35 M
Top Width = 3 M
Arae of Hearting Soils = 3+14.35
X 11.345 = 98.42 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-117.155)X2+3+5-0.57-6.21- 14.35/2 = 18.74 M
Top Width = 18.74+1.5 = 20.24 M
Arae of Hearting Soils = 20.24+18.74
X 1.000 = 19.49 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 118.155
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 9.345 = 10.45 M
Area of Inclined Sand Chimney = 10.45 X 1 = 10.45 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 12.345 + 5 = 32.6 M
Arae of 450thk Rip Rap = 32.6X0.45 = 14.67 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 12.345 + 5 = 32.6 M
Arae of 200thk Sand = 32.6X0.2 = 6.52 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 12.345 + 5 = 32.6 M
Arae of 200thk Sand = 32.6X0.2 = 6.52 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 117.155 )X 4+6+10 = 65.38 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+65.38
X 3.645 = 211.74 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 415.32 Sqm
12)Net casing Area = 415.32-6.42-0.59-0.59-98.42-19.49-10.45-14.67-6.52-6.52 = 251.65 Sqm
Slno Descrption Area
1 Stripping = 20.700 Sqm
8 Rock-toe = 6.42 Sqm
9 Behind sand Filters = 0.59 Sqm
10 Behind Metal Filters = 0.59 Sqm
11 Hearting = 98.42 Sqm
12 Inclined Sand Chimney = 10.45 Sqm
13 horizontal Sand Filter = 19.49 Sqm
14 450mm thk Rip Rap = 14.67 Sqm
15 200mm thk Metal = 6.52 Sqm
16 200mm thk sand = 6.52 Sqm
17 Net Casing Area = 251.65 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.425 Km
T.B.L = + 129.500 M Avg. G.L = + 117.935 M
Stripped.Level = + 117.635 M Stri.Lev = + 117.635 M
Height of Bund 11.865 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 117.635 )X 4+6+10+1.717+1.9= 67.08 M
Depth of Stripping ( 117.935 - 117.635 ) = 0.300 M
Area of Stripping ( 67.080 X 0.300 ) = 20.120 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-117.635 )X 20% 1.973 = 1.97 M
Bottom Width of Rock-Toe = 1.973 X 3 = 5.92 M
Area of Rock -Toe = 1/2X5.92X1.973 = 5.84 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.973 = 2.79 M
Area = 2.79X0.2 = 0.56 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.973 = 2.79 M
Area = 2.79X0.2 = 0.56 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 117.635 )X 0.5*2+3 = 13.87 M
Top Width = 3 M
Arae of Hearting Soils = 3+13.87
X 10.865 = 91.65 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-117.635)X2+3+5-0.57-5.92- 13.87/2 = 18.31 M
Top Width = 18.31+1.5 = 19.81 M
Arae of Hearting Soils = 19.81+18.31
X 1.000 = 19.06 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 118.635
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 8.865 = 9.91 M
Area of Inclined Sand Chimney = 9.91 X 1 = 9.91 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 11.865 + 5 = 31.53 M
Arae of 450thk Rip Rap = 31.53X0.45 = 14.19 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 11.865 + 5 = 31.53 M
Arae of 200thk Sand = 31.53X0.2 = 6.31 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 11.865 + 5 = 31.53 M
Arae of 200thk Sand = 31.53X0.2 = 6.31 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 117.635 )X 4+6+10 = 63.46 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+63.46
X 3.165 = 180.82 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 384.40 Sqm
12)Net casing Area = 384.4-5.84-0.56-0.56-91.65-19.06-9.91-14.19-6.31-6.31 = 230.01 Sqm
Slno Descrption Area
1 Stripping = 20.120 Sqm
8 Rock-toe = 5.84 Sqm
9 Behind sand Filters = 0.56 Sqm
10 Behind Metal Filters = 0.56 Sqm
11 Hearting = 91.65 Sqm
12 Inclined Sand Chimney = 9.91 Sqm
13 horizontal Sand Filter = 19.06 Sqm
14 450mm thk Rip Rap = 14.19 Sqm
15 200mm thk Metal = 6.31 Sqm
16 200mm thk sand = 6.31 Sqm
17 Net Casing Area = 230.01 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.450 Km
T.B.L = + 129.500 M Avg. G.L = + 118.110 M
Stripped.Level = + 117.810 M Stri.Lev = + 117.810 M
Height of Bund 11.690 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 117.810 )X 4+6+10+1.717+1.9= 66.38 M
Depth of Stripping ( 118.110 - 117.810 ) = 0.300 M
Area of Stripping ( 66.380 X 0.300 ) = 19.910 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-117.81 )X 20% 1.938 = 1.94 M
Bottom Width of Rock-Toe = 1.938 X 3 = 5.81 M
Area of Rock -Toe = 1/2X5.81X1.938 = 5.63 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.938 = 2.74 M
Area = 2.74X0.2 = 0.55 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.938 = 2.74 M
Area = 2.74X0.2 = 0.55 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 117.810 )X 0.5*2+3 = 13.69 M
Top Width = 3 M
Arae of Hearting Soils = 3+13.69
X 10.690 = 89.21 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-117.81)X2+3+5-0.57-5.81 - 13.69/2 = 18.16 M
Top Width = 18.16+1.5 = 19.66 M
Arae of Hearting Soils = 19.66+18.16
X 1.000 = 18.91 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 118.810
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 8.690 = 9.72 M
Area of Inclined Sand Chimney = 9.72 X 1 = 9.72 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 11.690 + 5 = 31.14 M
Arae of 450thk Rip Rap = 31.14X0.45 = 14.01 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 11.690 + 5 = 31.14 M
Arae of 200thk Sand = 31.14X0.2 = 6.23 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 11.690 + 5 = 31.14 M
Arae of 200thk Sand = 31.14X0.2 = 6.23 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 117.810 )X 4+6+10 = 62.76 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+62.76
X 2.990 = 169.77 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 373.35 Sqm
12)Net casing Area = 373.35-5.63-0.55-0.55-89.21-18.91-9.72-14.01-6.23-6.23 = 222.31 Sqm
Slno Descrption Area
1 Stripping = 19.910 Sqm
8 Rock-toe = 5.63 Sqm
9 Behind sand Filters = 0.55 Sqm
10 Behind Metal Filters = 0.55 Sqm
11 Hearting = 89.21 Sqm
12 Inclined Sand Chimney = 9.72 Sqm
13 horizontal Sand Filter = 18.91 Sqm
14 450mm thk Rip Rap = 14.01 Sqm
15 200mm thk Metal = 6.23 Sqm
16 200mm thk sand = 6.23 Sqm
17 Net Casing Area = 222.31 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.475 Km
T.B.L = + 129.500 M Avg. G.L = + 118.615 M
Stripped.Level = + 118.315 M Stri.Lev = + 118.315 M
Height of Bund 11.185 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 118.315 )X 4+6+10+1.717+1.9= 64.36 M
Depth of Stripping ( 118.615 - 118.315 ) = 0.300 M
Area of Stripping ( 64.360 X 0.300 ) = 19.310 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-118.315 )X 20% 1.837 = 1.84 M
Bottom Width of Rock-Toe = 1.837 X 3 = 5.51 M
Area of Rock -Toe = 1/2X5.51X1.837 = 5.06 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.837 = 2.6 M
Area = 2.6X0.2 = 0.52 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.837 = 2.6 M
Area = 2.6X0.2 = 0.52 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 118.315 )X 0.5*2+3 = 13.19 M
Top Width = 3 M
Arae of Hearting Soils = 3+13.19
X 10.185 = 82.45 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-118.315)X2+3+5-0.57-5.51- 13.19/2 = 17.70 M
Top Width = 17.7+1.5 = 19.20 M
Arae of Hearting Soils = 19.2+17.7
X 1.000 = 18.45 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 119.315
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 8.185 = 9.15 M
Area of Inclined Sand Chimney = 9.15 X 1 = 9.15 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 11.185 + 5 = 30.01 M
Arae of 450thk Rip Rap = 30.01X0.45 = 13.5 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 11.185 + 5 = 30.01 M
Arae of 200thk Sand = 30.01X0.2 = 6 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 11.185 + 5 = 30.01 M
Arae of 200thk Sand = 30.01X0.2 = 6 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 118.315 )X 4+6+10 = 60.74 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+60.74
X 2.485 = 138.59 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 342.17 Sqm
12)Net casing Area = 342.17-5.06-0.52-0.52-82.45-18.45-9.15-13.5-6-6 = 200.52 Sqm
Slno Descrption Area
1 Stripping = 19.310 Sqm
8 Rock-toe = 5.06 Sqm
9 Behind sand Filters = 0.52 Sqm
10 Behind Metal Filters = 0.52 Sqm
11 Hearting = 82.45 Sqm
12 Inclined Sand Chimney = 9.15 Sqm
13 horizontal Sand Filter = 18.45 Sqm
14 450mm thk Rip Rap = 13.5 Sqm
15 200mm thk Metal = 6 Sqm
16 200mm thk sand = 6 Sqm
17 Net Casing Area = 200.52 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.500 Km
T.B.L = + 129.500 M Avg. G.L = + 118.955 M
Stripped.Level = + 118.655 M Stri.Lev = + 118.655 M
Height of Bund 10.845 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 118.655 )X 4+6+10+1.717+1.9= 63 M
Depth of Stripping ( 118.955 - 118.655 ) = 0.300 M
Area of Stripping ( 63.000 X 0.300 ) = 18.900 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-118.655 )X 20% 1.769 = 1.77 M
Bottom Width of Rock-Toe = 1.769 X 3 = 5.31 M
Area of Rock -Toe = 1/2X5.31X1.769 = 4.7 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.769 = 2.5 M
Area = 2.5X0.2 = 0.5 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.769 = 2.5 M
Area = 2.5X0.2 = 0.5 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 118.655 )X 0.5*2+3 = 12.85 M
Top Width = 3 M
Arae of Hearting Soils = 3+12.85
X 9.845 = 78.02 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-118.655)X2+3+5-0.57-5.31- 12.85/2 = 17.39 M
Top Width = 17.39+1.5 = 18.89 M
Arae of Hearting Soils = 18.89+17.39
X 1.000 = 18.14 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 119.655
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 7.845 = 8.77 M
Area of Inclined Sand Chimney = 8.77 X 1 = 8.77 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 10.845 + 5 = 29.25 M
Arae of 450thk Rip Rap = 29.25X0.45 = 13.16 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 10.845 + 5 = 29.25 M
Arae of 200thk Sand = 29.25X0.2 = 5.85 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 10.845 + 5 = 29.25 M
Arae of 200thk Sand = 29.25X0.2 = 5.85 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 118.655 )X 4+6+10 = 59.38 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+59.38
X 2.145 = 118.17 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 321.75 Sqm
12)Net casing Area = 321.75-4.7-0.5-0.5-78.02-18.14-8.77-13.16-5.85-5.85 = 186.26 Sqm
Slno Descrption Area
1 Stripping = 18.900 Sqm
8 Rock-toe = 4.7 Sqm
9 Behind sand Filters = 0.5 Sqm
10 Behind Metal Filters = 0.5 Sqm
11 Hearting = 78.02 Sqm
12 Inclined Sand Chimney = 8.77 Sqm
13 horizontal Sand Filter = 18.14 Sqm
14 450mm thk Rip Rap = 13.16 Sqm
15 200mm thk Metal = 5.85 Sqm
16 200mm thk sand = 5.85 Sqm
17 Net Casing Area = 186.26 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.525 Km
T.B.L = + 129.500 M Avg. G.L = + 119.055 M
Stripped.Level = + 118.755 M Stri.Lev = + 118.755 M
Height of Bund 10.745 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 118.755 )X 4+6+10+1.717+1.9= 62.6 M
Depth of Stripping ( 119.055 - 118.755 ) = 0.300 M
Area of Stripping ( 62.600 X 0.300 ) = 18.780 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-118.755 )X 20% 1.749 = 1.75 M
Bottom Width of Rock-Toe = 1.749 X 3 = 5.25 M
Area of Rock -Toe = 1/2X5.25X1.749 = 4.59 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.749 = 2.47 M
Area = 2.47X0.2 = 0.49 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.749 = 2.47 M
Area = 2.47X0.2 = 0.49 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 118.755 )X 0.5*2+3 = 12.75 M
Top Width = 3 M
Arae of Hearting Soils = 3+12.75
X 9.745 = 76.74 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-118.755)X2+3+5-0.57-5.25- 12.75/2 = 17.30 M
Top Width = 17.3+1.5 = 18.80 M
Arae of Hearting Soils = 18.8+17.3
X 1.000 = 18.05 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 119.755
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 7.745 = 8.66 M
Area of Inclined Sand Chimney = 8.66 X 1 = 8.66 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 10.745 + 5 = 29.03 M
Arae of 450thk Rip Rap = 29.03X0.45 = 13.06 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 10.745 + 5 = 29.03 M
Arae of 200thk Sand = 29.03X0.2 = 5.81 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 10.745 + 5 = 29.03 M
Arae of 200thk Sand = 29.03X0.2 = 5.81 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 118.755 )X 4+6+10 = 58.98 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+58.98
X 2.045 = 112.25 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 315.83 Sqm
12)Net casing Area = 315.83-4.59-0.49-0.49-76.74-18.05-8.66-13.06-5.81-5.81 = 182.13 Sqm
Slno Descrption Area
1 Stripping = 18.780 Sqm
8 Rock-toe = 4.59 Sqm
9 Behind sand Filters = 0.49 Sqm
10 Behind Metal Filters = 0.49 Sqm
11 Hearting = 76.74 Sqm
12 Inclined Sand Chimney = 8.66 Sqm
13 horizontal Sand Filter = 18.05 Sqm
14 450mm thk Rip Rap = 13.06 Sqm
15 200mm thk Metal = 5.81 Sqm
16 200mm thk sand = 5.81 Sqm
17 Net Casing Area = 182.13 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.550 Km
T.B.L = + 129.500 M Avg. G.L = + 119.220 M
Stripped.Level = + 118.920 M Stri.Lev = + 118.920 M
Height of Bund 10.580 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 118.920 )X 4+6+10+1.717+1.9= 61.94 M
Depth of Stripping ( 119.220 - 118.920 ) = 0.300 M
Area of Stripping ( 61.940 X 0.300 ) = 18.580 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-118.92 )X 20% 1.716 = 1.72 M
Bottom Width of Rock-Toe = 1.716 X 3 = 5.15 M
Area of Rock -Toe = 1/2X5.15X1.716 = 4.42 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.716 = 2.43 M
Area = 2.43X0.2 = 0.49 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.716 = 2.43 M
Area = 2.43X0.2 = 0.49 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 118.920 )X 0.5*2+3 = 12.58 M
Top Width = 3 M
Arae of Hearting Soils = 3+12.58
X 9.580 = 74.63 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-118.92)X2+3+5-0.57-5.15 - 12.58/2 = 17.15 M
Top Width = 17.15+1.5 = 18.65 M
Arae of Hearting Soils = 18.65+17.15
X 1.000 = 17.90 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 119.920
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 7.580 = 8.47 M
Area of Inclined Sand Chimney = 8.47 X 1 = 8.47 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 10.580 + 5 = 28.66 M
Arae of 450thk Rip Rap = 28.66X0.45 = 12.9 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 10.580 + 5 = 28.66 M
Arae of 200thk Sand = 28.66X0.2 = 5.73 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 10.580 + 5 = 28.66 M
Arae of 200thk Sand = 28.66X0.2 = 5.73 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 118.920 )X 4+6+10 = 58.32 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+58.32
X 1.880 = 102.57 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 306.15 Sqm
12)Net casing Area = 306.15-4.42-0.49-0.49-74.63-17.9-8.47-12.9-5.73-5.73 = 175.39 Sqm
Slno Descrption Area
1 Stripping = 18.580 Sqm
8 Rock-toe = 4.42 Sqm
9 Behind sand Filters = 0.49 Sqm
10 Behind Metal Filters = 0.49 Sqm
11 Hearting = 74.63 Sqm
12 Inclined Sand Chimney = 8.47 Sqm
13 horizontal Sand Filter = 17.90 Sqm
14 450mm thk Rip Rap = 12.9 Sqm
15 200mm thk Metal = 5.73 Sqm
16 200mm thk sand = 5.73 Sqm
17 Net Casing Area = 175.39 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.575 Km
T.B.L = + 129.500 M Avg. G.L = + 119.460 M
Stripped.Level = + 119.160 M Stri.Lev = + 119.160 M
Height of Bund 10.340 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 119.160 )X 4+6+10+1.717+1.9= 60.98 M
Depth of Stripping ( 119.460 - 119.160 ) = 0.300 M
Area of Stripping ( 60.980 X 0.300 ) = 18.290 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-119.16 )X 20% 1.668 = 1.67 M
Bottom Width of Rock-Toe = 1.668 X 3 = 5.00 M
Area of Rock -Toe = 1/2X5X1.668 = 4.17 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.668 = 2.36 M
Area = 2.36X0.2 = 0.47 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.668 = 2.36 M
Area = 2.36X0.2 = 0.47 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 119.160 )X 0.5*2+3 = 12.34 M
Top Width = 3 M
Arae of Hearting Soils = 3+12.34
X 9.340 = 71.64 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-119.16)X2+3+5-0.57-5 - 12.34/2 = 16.94 M
Top Width = 16.94+1.5 = 18.44 M
Arae of Hearting Soils = 18.44+16.94
X 1.000 = 17.69 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 120.160
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 7.340 = 8.21 M
Area of Inclined Sand Chimney = 8.21 X 1 = 8.21 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 10.340 + 5 = 28.12 M
Arae of 450thk Rip Rap = 28.12X0.45 = 12.65 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 10.340 + 5 = 28.12 M
Arae of 200thk Sand = 28.12X0.2 = 5.62 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 10.340 + 5 = 28.12 M
Arae of 200thk Sand = 28.12X0.2 = 5.62 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 119.160 )X 4+6+10 = 57.36 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+57.36
X 1.640 = 88.69 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 292.27 Sqm
12)Net casing Area = 292.27-4.17-0.47-0.47-71.64-17.69-8.21-12.65-5.62-5.62 = 165.73 Sqm
Slno Descrption Area
1 Stripping = 18.290 Sqm
8 Rock-toe = 4.17 Sqm
9 Behind sand Filters = 0.47 Sqm
10 Behind Metal Filters = 0.47 Sqm
11 Hearting = 71.64 Sqm
12 Inclined Sand Chimney = 8.21 Sqm
13 horizontal Sand Filter = 17.69 Sqm
14 450mm thk Rip Rap = 12.65 Sqm
15 200mm thk Metal = 5.62 Sqm
16 200mm thk sand = 5.62 Sqm
17 Net Casing Area = 165.73 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.600 Km
T.B.L = + 129.500 M Avg. G.L = + 119.715 M
Stripped.Level = + 119.415 M Stri.Lev = + 119.415 M
Height of Bund 10.085 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 119.415 )X 4+6+10+1.717+1.9= 59.96 M
Depth of Stripping ( 119.715 - 119.415 ) = 0.300 M
Area of Stripping ( 59.960 X 0.300 ) = 17.990 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-119.415 )X 20% 1.617 = 1.62 M
Bottom Width of Rock-Toe = 1.617 X 3 = 4.85 M
Area of Rock -Toe = 1/2X4.85X1.617 = 3.92 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.617 = 2.29 M
Area = 2.29X0.2 = 0.46 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.617 = 2.29 M
Area = 2.29X0.2 = 0.46 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 119.415 )X 0.5*2+3 = 12.09 M
Top Width = 3 M
Arae of Hearting Soils = 3+12.09
X 9.085 = 68.55 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-119.415)X2+3+5-0.57-4.85- 12.09/2 = 16.71 M
Top Width = 16.71+1.5 = 18.21 M
Arae of Hearting Soils = 18.21+16.71
X 1.000 = 17.46 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 120.415
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 7.085 = 7.92 M
Area of Inclined Sand Chimney = 7.92 X 1 = 7.92 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 10.085 + 5 = 27.55 M
Arae of 450thk Rip Rap = 27.55X0.45 = 12.4 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 10.085 + 5 = 27.55 M
Arae of 200thk Sand = 27.55X0.2 = 5.51 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 10.085 + 5 = 27.55 M
Arae of 200thk Sand = 27.55X0.2 = 5.51 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 119.415 )X 4+6+10 = 56.34 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+56.34
X 1.385 = 74.19 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 277.77 Sqm
12)Net casing Area = 277.77-3.92-0.46-0.46-68.55-17.46-7.92-12.4-5.51-5.51 = 155.58 Sqm
Slno Descrption Area
1 Stripping = 17.990 Sqm
8 Rock-toe = 3.92 Sqm
9 Behind sand Filters = 0.46 Sqm
10 Behind Metal Filters = 0.46 Sqm
11 Hearting = 68.55 Sqm
12 Inclined Sand Chimney = 7.92 Sqm
13 horizontal Sand Filter = 17.46 Sqm
14 450mm thk Rip Rap = 12.4 Sqm
15 200mm thk Metal = 5.51 Sqm
16 200mm thk sand = 5.51 Sqm
17 Net Casing Area = 155.58 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.625 Km
T.B.L = + 129.500 M Avg. G.L = + 119.885 M
Stripped.Level = + 119.585 M Stri.Lev = + 119.585 M
Height of Bund 9.915 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 119.585 )X 4+6+10+1.717+1.9= 59.28 M
Depth of Stripping ( 119.885 - 119.585 ) = 0.300 M
Area of Stripping ( 59.280 X 0.300 ) = 17.780 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-119.585 )X 20% 1.583 = 1.58 M
Bottom Width of Rock-Toe = 1.583 X 3 = 4.75 M
Area of Rock -Toe = 1/2X4.75X1.583 = 3.76 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.583 = 2.24 M
Area = 2.24X0.2 = 0.45 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.583 = 2.24 M
Area = 2.24X0.2 = 0.45 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 119.585 )X 0.5*2+3 = 11.92 M
Top Width = 3 M
Arae of Hearting Soils = 3+11.92
X 8.915 = 66.51 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-119.585)X2+3+5-0.57-4.75- 11.92/2 = 16.55 M
Top Width = 16.55+1.5 = 18.05 M
Arae of Hearting Soils = 18.05+16.55
X 1.000 = 17.30 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 120.585
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 6.915 = 7.73 M
Area of Inclined Sand Chimney = 7.73 X 1 = 7.73 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 9.915 + 5 = 27.17 M
Arae of 450thk Rip Rap = 27.17X0.45 = 12.23 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 9.915 + 5 = 27.17 M
Arae of 200thk Sand = 27.17X0.2 = 5.43 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 9.915 + 5 = 27.17 M
Arae of 200thk Sand = 27.17X0.2 = 5.43 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 119.585 )X 4+6+10 = 55.66 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+55.66
X 1.215 = 64.67 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 268.25 Sqm
12)Net casing Area = 268.25-3.76-0.45-0.45-66.51-17.3-7.73-12.23-5.43-5.43 = 148.96 Sqm
Slno Descrption Area
1 Stripping = 17.780 Sqm
8 Rock-toe = 3.76 Sqm
9 Behind sand Filters = 0.45 Sqm
10 Behind Metal Filters = 0.45 Sqm
11 Hearting = 66.51 Sqm
12 Inclined Sand Chimney = 7.73 Sqm
13 horizontal Sand Filter = 17.30 Sqm
14 450mm thk Rip Rap = 12.23 Sqm
15 200mm thk Metal = 5.43 Sqm
16 200mm thk sand = 5.43 Sqm
17 Net Casing Area = 148.96 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.650 Km
T.B.L = + 129.500 M Avg. G.L = + 120.040 M
Stripped.Level = + 119.740 M Stri.Lev = + 119.740 M
Height of Bund 9.760 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 119.740 )X 4+6+10+1.717+1.9= 58.66 M
Depth of Stripping ( 120.040 - 119.740 ) = 0.300 M
Area of Stripping ( 58.660 X 0.300 ) = 17.600 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-119.74 )X 20% 1.552 = 1.55 M
Bottom Width of Rock-Toe = 1.552 X 3 = 4.66 M
Area of Rock -Toe = 1/2X4.66X1.552 = 3.62 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.552 = 2.19 M
Area = 2.19X0.2 = 0.44 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.552 = 2.19 M
Area = 2.19X0.2 = 0.44 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 119.740 )X 0.5*2+3 = 11.76 M
Top Width = 3 M
Arae of Hearting Soils = 3+11.76
X 8.760 = 64.65 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-119.74)X2+3+5-0.57-4.66 - 11.76/2 = 16.41 M
Top Width = 16.41+1.5 = 17.91 M
Arae of Hearting Soils = 17.91+16.41
X 1.000 = 17.16 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 120.740
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 6.760 = 7.56 M
Area of Inclined Sand Chimney = 7.56 X 1 = 7.56 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 9.760 + 5 = 26.82 M
Arae of 450thk Rip Rap = 26.82X0.45 = 12.07 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 9.760 + 5 = 26.82 M
Arae of 200thk Sand = 26.82X0.2 = 5.36 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 9.760 + 5 = 26.82 M
Arae of 200thk Sand = 26.82X0.2 = 5.36 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 119.740 )X 4+6+10 = 55.04 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+55.04
X 1.060 = 56.10 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 259.68 Sqm
12)Net casing Area = 259.68-3.62-0.44-0.44-64.65-17.16-7.56-12.07-5.36-5.36 = 143.02 Sqm
Slno Descrption Area
1 Stripping = 17.600 Sqm
8 Rock-toe = 3.62 Sqm
9 Behind sand Filters = 0.44 Sqm
10 Behind Metal Filters = 0.44 Sqm
11 Hearting = 64.65 Sqm
12 Inclined Sand Chimney = 7.56 Sqm
13 horizontal Sand Filter = 17.16 Sqm
14 450mm thk Rip Rap = 12.07 Sqm
15 200mm thk Metal = 5.36 Sqm
16 200mm thk sand = 5.36 Sqm
17 Net Casing Area = 143.02 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.675 Km
T.B.L = + 129.500 M Avg. G.L = + 120.060 M
Stripped.Level = + 119.760 M Stri.Lev = + 119.760 M
Height of Bund 9.740 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 119.760 )X 4+6+10+1.717+1.9= 58.58 M
Depth of Stripping ( 120.060 - 119.760 ) = 0.300 M
Area of Stripping ( 58.580 X 0.300 ) = 17.570 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-119.76 )X 20% 1.548 = 1.55 M
Bottom Width of Rock-Toe = 1.548 X 3 = 4.64 M
Area of Rock -Toe = 1/2X4.64X1.548 = 3.59 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.548 = 2.19 M
Area = 2.19X0.2 = 0.44 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.548 = 2.19 M
Area = 2.19X0.2 = 0.44 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 119.760 )X 0.5*2+3 = 11.74 M
Top Width = 3 M
Arae of Hearting Soils = 3+11.74
X 8.740 = 64.41 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-119.76)X2+3+5-0.57-4.64 - 11.74/2 = 16.40 M
Top Width = 16.4+1.5 = 17.90 M
Arae of Hearting Soils = 17.9+16.4
X 1.000 = 17.15 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 120.760
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 6.740 = 7.54 M
Area of Inclined Sand Chimney = 7.54 X 1 = 7.54 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 9.740 + 5 = 26.78 M
Arae of 450thk Rip Rap = 26.78X0.45 = 12.05 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 9.740 + 5 = 26.78 M
Arae of 200thk Sand = 26.78X0.2 = 5.36 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 9.740 + 5 = 26.78 M
Arae of 200thk Sand = 26.78X0.2 = 5.36 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 119.760 )X 4+6+10 = 54.96 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6 M
Arae of Bund up to Berm = 50.8+54.96
X 1.040 = 55.00 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 258.58 Sqm
12)Net casing Area = 258.58-3.59-0.44-0.44-64.41-17.15-7.54-12.05-5.36-5.36 = 142.24 Sqm
Slno Descrption Area
1 Stripping = 17.570 Sqm
8 Rock-toe = 3.59 Sqm
9 Behind sand Filters = 0.44 Sqm
10 Behind Metal Filters = 0.44 Sqm
11 Hearting = 64.41 Sqm
12 Inclined Sand Chimney = 7.54 Sqm
13 horizontal Sand Filter = 17.15 Sqm
14 450mm thk Rip Rap = 12.05 Sqm
15 200mm thk Metal = 5.36 Sqm
16 200mm thk sand = 5.36 Sqm
17 Net Casing Area = 142.24 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.700 Km
T.B.L = + 129.500 M Avg. G.L = + 120.460 M
Stripped.Level = + 120.160 M Stri.Lev = + 120.160 M
Height of Bund 9.340 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 120.160 )X 4+6+1.717+1.9= 46.98 M
Depth of Stripping ( 120.460 - 120.160 ) = 0.300 M
Area of Stripping ( 46.980 X 0.300 ) = 14.090 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-120.16 )X 20% 1.468 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 120.160 )X 0.5*2+3 = 11.34 M
Top Width = 3 M
Arae of Hearting Soils = 3+11.34
X 8.340 = 59.80 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-120.16)X2+3-0.57-4.5 - 11.34/2 = 10.94 M
Top Width = 10.94+1.5 = 12.44 M
Arae of Hearting Soils = 12.44+10.94
X 1.000 = 11.69 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 121.160
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 6.340 = 7.09 M
Area of Inclined Sand Chimney = 7.09 X 1 = 7.09 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 9.340 = 20.88 M
Arae of 450thk Rip Rap = 20.88X0.45 = 9.4 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 9.340 = 20.88 M
Arae of 200thk Sand = 20.88X0.2 = 4.18 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 9.340 = 20.88 M
Arae of 200thk Sand = 20.88X0.2 = 4.18 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 120.160 )X 4+6 = 43.36 M
Top Width = 6 M
Arae of Bund = 6+43.36
X 9.340 = 230.51 Sqm
2
12)Net casing Area = 230.51-3.38-0.42-0.42-59.8-11.69-7.09-9.4-4.18-4.18 = 129.95 Sqm

Slno Descrption Area


1 Stripping = 14.090 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 59.80 Sqm
12 Inclined Sand Chimney = 7.09 Sqm
13 horizontal Sand Filter = 11.69 Sqm
14 450mm thk Rip Rap = 9.4 Sqm
15 200mm thk Metal = 4.18 Sqm
16 200mm thk sand = 4.18 Sqm
17 Net Casing Area = 129.95 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.725 Km
T.B.L = + 129.500 M Avg. G.L = + 120.620 M
Stripped.Level = + 120.320 M Stri.Lev = + 120.320 M
Height of Bund 9.180 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 120.320 )X 4+6+1.717+1.9= 46.34 M
Depth of Stripping ( 120.620 - 120.320 ) = 0.300 M
Area of Stripping ( 46.340 X 0.300 ) = 13.900 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-120.32 )X 20% 1.436 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 120.320 )X 0.5*2+3 = 11.18 M
Top Width = 3 M
Arae of Hearting Soils = 3+11.18
X 8.180 = 58.00 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-120.32)X2+3-0.57-4.5 - 11.18/2 = 10.70 M
Top Width = 10.7+1.5 = 12.20 M
Arae of Hearting Soils = 12.2+10.7
X 1.000 = 11.45 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 121.320
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 6.180 = 6.91 M
Area of Inclined Sand Chimney = 6.91 X 1 = 6.91 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 9.180 = 20.53 M
Arae of 450thk Rip Rap = 20.53X0.45 = 9.24 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 9.180 = 20.53 M
Arae of 200thk Sand = 20.53X0.2 = 4.11 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 9.180 = 20.53 M
Arae of 200thk Sand = 20.53X0.2 = 4.11 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 120.320 )X 4+6 = 42.72 M
Top Width = 6 M
Arae of Bund = 6+42.72
X 9.180 = 223.62 Sqm
2
12)Net casing Area = 223.62-3.38-0.42-0.42-58-11.45-6.91-9.24-4.11-4.11 = 125.58 Sqm

Slno Descrption Area


1 Stripping = 13.900 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 58.00 Sqm
12 Inclined Sand Chimney = 6.91 Sqm
13 horizontal Sand Filter = 11.45 Sqm
14 450mm thk Rip Rap = 9.24 Sqm
15 200mm thk Metal = 4.11 Sqm
16 200mm thk sand = 4.11 Sqm
17 Net Casing Area = 125.58 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.750 Km
T.B.L = + 129.500 M Avg. G.L = + 120.940 M
Stripped.Level = + 120.640 M Stri.Lev = + 120.640 M
Height of Bund 8.860 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 120.640 )X 4+6+1.717+1.9= 45.06 M
Depth of Stripping ( 120.940 - 120.640 ) = 0.300 M
Area of Stripping ( 45.060 X 0.300 ) = 13.520 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-120.64 )X 20% 1.372 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 120.640 )X 0.5*2+3 = 10.86 M
Top Width = 3 M
Arae of Hearting Soils = 3+10.86
X 7.860 = 54.47 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-120.64)X2+3-0.57-4.5 - 10.86/2 = 10.22 M
Top Width = 10.22+1.5 = 11.72 M
Arae of Hearting Soils = 11.72+10.22
X 1.000 = 10.97 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 121.640
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 5.860 = 6.55 M
Area of Inclined Sand Chimney = 6.55 X 1 = 6.55 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 8.860 = 19.81 M
Arae of 450thk Rip Rap = 19.81X0.45 = 8.91 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 8.860 = 19.81 M
Arae of 200thk Sand = 19.81X0.2 = 3.96 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 8.860 = 19.81 M
Arae of 200thk Sand = 19.81X0.2 = 3.96 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 120.640 )X 4+6 = 41.44 M
Top Width = 6 M
Arae of Bund = 6+41.44
X 8.860 = 210.16 Sqm
2
12)Net casing Area = 210.16-3.38-0.42-0.42-54.47-10.97-6.55-8.91-3.96-3.96 = 117.12 Sqm

Slno Descrption Area


1 Stripping = 13.520 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 54.47 Sqm
12 Inclined Sand Chimney = 6.55 Sqm
13 horizontal Sand Filter = 10.97 Sqm
14 450mm thk Rip Rap = 8.91 Sqm
15 200mm thk Metal = 3.96 Sqm
16 200mm thk sand = 3.96 Sqm
17 Net Casing Area = 117.12 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.775 Km
T.B.L = + 129.500 M Avg. G.L = + 120.870 M
Stripped.Level = + 120.570 M Stri.Lev = + 120.570 M
Height of Bund 8.930 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 120.570 )X 4+6+1.717+1.9= 45.34 M
Depth of Stripping ( 120.870 - 120.570 ) = 0.300 M
Area of Stripping ( 45.340 X 0.300 ) = 13.600 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-120.57 )X 20% 1.386 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 120.570 )X 0.5*2+3 = 10.93 M
Top Width = 3 M
Arae of Hearting Soils = 3+10.93
X 7.930 = 55.23 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-120.57)X2+3-0.57-4.5 - 10.93/2 = 10.33 M
Top Width = 10.33+1.5 = 11.83 M
Arae of Hearting Soils = 11.83+10.33
X 1.000 = 11.08 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 121.570
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 5.930 = 6.63 M
Area of Inclined Sand Chimney = 6.63 X 1 = 6.63 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 8.930 = 19.97 M
Arae of 450thk Rip Rap = 19.97X0.45 = 8.99 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 8.930 = 19.97 M
Arae of 200thk Sand = 19.97X0.2 = 3.99 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 8.930 = 19.97 M
Arae of 200thk Sand = 19.97X0.2 = 3.99 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 120.570 )X 4+6 = 41.72 M
Top Width = 6 M
Arae of Bund = 6+41.72
X 8.930 = 213.07 Sqm
2
12)Net casing Area = 213.07-3.38-0.42-0.42-55.23-11.08-6.63-8.99-3.99-3.99 = 118.94 Sqm

Slno Descrption Area


1 Stripping = 13.600 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 55.23 Sqm
12 Inclined Sand Chimney = 6.63 Sqm
13 horizontal Sand Filter = 11.08 Sqm
14 450mm thk Rip Rap = 8.99 Sqm
15 200mm thk Metal = 3.99 Sqm
16 200mm thk sand = 3.99 Sqm
17 Net Casing Area = 118.94 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.800 Km
T.B.L = + 129.500 M Avg. G.L = + 121.020 M
Stripped.Level = + 120.720 M Stri.Lev = + 120.720 M
Height of Bund 8.780 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 120.720 )X 4+6+1.717+1.9= 44.74 M
Depth of Stripping ( 121.020 - 120.720 ) = 0.300 M
Area of Stripping ( 44.740 X 0.300 ) = 13.420 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-120.72 )X 20% 1.356 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 120.720 )X 0.5*2+3 = 10.78 M
Top Width = 3 M
Arae of Hearting Soils = 3+10.78
X 7.780 = 53.60 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-120.72)X2+3-0.57-4.5 - 10.78/2 = 10.10 M
Top Width = 10.1+1.5 = 11.60 M
Arae of Hearting Soils = 11.6+10.1
X 1.000 = 10.85 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 121.720
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 5.780 = 6.46 M
Area of Inclined Sand Chimney = 6.46 X 1 = 6.46 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 8.780 = 19.63 M
Arae of 450thk Rip Rap = 19.63X0.45 = 8.83 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 8.780 = 19.63 M
Arae of 200thk Sand = 19.63X0.2 = 3.93 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 8.780 = 19.63 M
Arae of 200thk Sand = 19.63X0.2 = 3.93 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 120.720 )X 4+6 = 41.12 M
Top Width = 6 M
Arae of Bund = 6+41.12
X 8.780 = 206.86 Sqm
2
12)Net casing Area = 206.86-3.38-0.42-0.42-53.6-10.85-6.46-8.83-3.93-3.93 = 115.04 Sqm

Slno Descrption Area


1 Stripping = 13.420 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 53.60 Sqm
12 Inclined Sand Chimney = 6.46 Sqm
13 horizontal Sand Filter = 10.85 Sqm
14 450mm thk Rip Rap = 8.83 Sqm
15 200mm thk Metal = 3.93 Sqm
16 200mm thk sand = 3.93 Sqm
17 Net Casing Area = 115.04 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.825 Km
T.B.L = + 129.500 M Avg. G.L = + 121.050 M
Stripped.Level = + 120.750 M Stri.Lev = + 120.750 M
Height of Bund 8.750 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 120.750 )X 4+6+1.717+1.9= 44.62 M
Depth of Stripping ( 121.050 - 120.750 ) = 0.300 M
Area of Stripping ( 44.620 X 0.300 ) = 13.390 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-120.75 )X 20% 1.35 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 120.750 )X 0.5*2+3 = 10.75 M
Top Width = 3 M
Arae of Hearting Soils = 3+10.75
X 7.750 = 53.28 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-120.75)X2+3-0.57-4.5 - 10.75/2 = 10.06 M
Top Width = 10.06+1.5 = 11.56 M
Arae of Hearting Soils = 11.56+10.06
X 1.000 = 10.81 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 121.750
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 5.750 = 6.43 M
Area of Inclined Sand Chimney = 6.43 X 1 = 6.43 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 8.750 = 19.57 M
Arae of 450thk Rip Rap = 19.57X0.45 = 8.81 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 8.750 = 19.57 M
Arae of 200thk Sand = 19.57X0.2 = 3.91 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 8.750 = 19.57 M
Arae of 200thk Sand = 19.57X0.2 = 3.91 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 120.750 )X 4+6 = 41 M
Top Width = 6 M
Arae of Bund = 6+41
X 8.750 = 205.63 Sqm
2
12)Net casing Area = 205.63-3.38-0.42-0.42-53.28-10.81-6.43-8.81-3.91-3.91 = 114.26 Sqm

Slno Descrption Area


1 Stripping = 13.390 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 53.28 Sqm
12 Inclined Sand Chimney = 6.43 Sqm
13 horizontal Sand Filter = 10.81 Sqm
14 450mm thk Rip Rap = 8.81 Sqm
15 200mm thk Metal = 3.91 Sqm
16 200mm thk sand = 3.91 Sqm
17 Net Casing Area = 114.26 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.850 Km
T.B.L = + 129.500 M Avg. G.L = + 121.780 M
Stripped.Level = + 121.480 M Stri.Lev = + 121.480 M
Height of Bund 8.020 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 121.480 )X 4+6+1.717+1.9= 41.7 M
Depth of Stripping ( 121.780 - 121.480 ) = 0.300 M
Area of Stripping ( 41.700 X 0.300 ) = 12.510 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-121.48 )X 20% 1.204 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 121.480 )X 0.5*2+3 = 10.02 M
Top Width = 3 M
Arae of Hearting Soils = 3+10.02
X 7.020 = 45.70 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-121.48)X2+3-0.57-4.5 - 10.02/2 = 8.96 M
Top Width = 8.96+1.5 = 10.46 M
Arae of Hearting Soils = 10.46+8.96
X 1.000 = 9.71 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 122.480
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 5.020 = 5.61 M
Area of Inclined Sand Chimney = 5.61 X 1 = 5.61 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 8.020 = 17.93 M
Arae of 450thk Rip Rap = 17.93X0.45 = 8.07 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 8.020 = 17.93 M
Arae of 200thk Sand = 17.93X0.2 = 3.59 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 8.020 = 17.93 M
Arae of 200thk Sand = 17.93X0.2 = 3.59 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 121.480 )X 4+6 = 38.08 M
Top Width = 6 M
Arae of Bund = 6+38.08
X 8.020 = 176.76 Sqm
2
12)Net casing Area = 176.76-3.38-0.42-0.42-45.7-9.71-5.61-8.07-3.59-3.59 = 96.27 Sqm

Slno Descrption Area


1 Stripping = 12.510 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 45.70 Sqm
12 Inclined Sand Chimney = 5.61 Sqm
13 horizontal Sand Filter = 9.71 Sqm
14 450mm thk Rip Rap = 8.07 Sqm
15 200mm thk Metal = 3.59 Sqm
16 200mm thk sand = 3.59 Sqm
17 Net Casing Area = 96.27 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.875 Km
T.B.L = + 129.500 M Avg. G.L = + 121.740 M
Stripped.Level = + 121.440 M Stri.Lev = + 121.440 M
Height of Bund 8.060 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 121.440 )X 4+6+1.717+1.9= 41.86 M
Depth of Stripping ( 121.740 - 121.440 ) = 0.300 M
Area of Stripping ( 41.860 X 0.300 ) = 12.560 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-121.44 )X 20% 1.212 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 121.440 )X 0.5*2+3 = 10.06 M
Top Width = 3 M
Arae of Hearting Soils = 3+10.06
X 7.060 = 46.10 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-121.44)X2+3-0.57-4.5 - 10.06/2 = 9.02 M
Top Width = 9.02+1.5 = 10.52 M
Arae of Hearting Soils = 10.52+9.02
X 1.000 = 9.77 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 122.440
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 5.060 = 5.66 M
Area of Inclined Sand Chimney = 5.66 X 1 = 5.66 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 8.060 = 18.02 M
Arae of 450thk Rip Rap = 18.02X0.45 = 8.11 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 8.060 = 18.02 M
Arae of 200thk Sand = 18.02X0.2 = 3.6 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 8.060 = 18.02 M
Arae of 200thk Sand = 18.02X0.2 = 3.6 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 121.440 )X 4+6 = 38.24 M
Top Width = 6 M
Arae of Bund = 6+38.24
X 8.060 = 178.29 Sqm
2
12)Net casing Area = 178.29-3.38-0.42-0.42-46.1-9.77-5.66-8.11-3.6-3.6 = 97.23 Sqm

Slno Descrption Area


1 Stripping = 12.560 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 46.10 Sqm
12 Inclined Sand Chimney = 5.66 Sqm
13 horizontal Sand Filter = 9.77 Sqm
14 450mm thk Rip Rap = 8.11 Sqm
15 200mm thk Metal = 3.6 Sqm
16 200mm thk sand = 3.6 Sqm
17 Net Casing Area = 97.23 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 1.900 Km
T.B.L = + 129.500 M Avg. G.L = + 121.965 M
Stripped.Level = + 121.665 M Stri.Lev = + 121.665 M
Height of Bund 7.835 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 121.665 )X 4+6+1.717+1.9= 40.96 M
Depth of Stripping ( 121.965 - 121.665 ) = 0.300 M
Area of Stripping ( 40.960 X 0.300 ) = 12.290 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-121.665 )X 20% 1.167 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 121.665 )X 0.5*2+3 = 9.83 M
Top Width = 3 M
Arae of Hearting Soils = 3+9.83
X 6.835 = 43.85 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-121.665)X2+3-0.57-4.5 - 9.83/2 = 8.68 M
Top Width = 8.68+1.5 = 10.18 M
Arae of Hearting Soils = 10.18+8.68
X 1.000 = 9.43 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 122.665
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 4.835 = 5.41 M
Area of Inclined Sand Chimney = 5.41 X 1 = 5.41 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 7.835 = 17.52 M
Arae of 450thk Rip Rap = 17.52X0.45 = 7.88 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 7.835 = 17.52 M
Arae of 200thk Sand = 17.52X0.2 = 3.5 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 7.835 = 17.52 M
Arae of 200thk Sand = 17.52X0.2 = 3.5 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 121.665 )X 4+6 = 37.34 M
Top Width = 6 M
Arae of Bund = 6+37.34
X 7.835 = 169.78 Sqm
2
12)Net casing Area = 169.78-3.38-0.42-0.42-43.85-9.43-5.41-7.88-3.5-3.5 = 91.99 Sqm

Slno Descrption Area


1 Stripping = 12.290 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 43.85 Sqm
12 Inclined Sand Chimney = 5.41 Sqm
13 horizontal Sand Filter = 9.43 Sqm
14 450mm thk Rip Rap = 7.88 Sqm
15 200mm thk Metal = 3.5 Sqm
16 200mm thk sand = 3.5 Sqm
17 Net Casing Area = 91.99 Sqm
Formation Mallamadugu Reservoir
BUND-1-Area / Quantity Statement
Behind Metal Inclined Sand horizontal Sand 450mm thk Rip
Stripping Rock-toe Behind sand Filters Hearting 200mm thk Metal 200mm thk sand Net Casing Area
Filters Chimney Filter Rap
Chainge
Slno
in Km
Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity in Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity
Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum

1 0.000 0 0 0 0 0 0 0 0 0 0 0
2 0.025 6.55 81.88 3.38 42.25 0.42 5.25 0.42 5.25 8.25 103.13 0.06 0.75 2.25 28.13 3.07 38.38 1.36 17.00 1.36 17.00 16.34 204.25
3 0.050 10.36 211.38 3.38 84.50 0.42 10.50 0.42 10.50 29.37 470.25 3.61 45.88 7.03 116.00 6.27 116.75 2.79 51.88 2.79 51.88 58.93 940.88
4 0.075 13.44 297.50 3.38 84.50 0.42 10.50 0.42 10.50 53.79 1039.50 6.48 126.13 10.87 223.75 8.85 189.00 3.93 84.00 3.93 84.00 115.40 2179.13
5 0.100 18.67 401.38 4.49 98.38 0.49 11.38 0.49 11.38 75.51 1616.25 8.55 187.88 17.97 360.50 12.96 272.63 5.76 121.13 5.76 121.13 178.27 3670.88
6 0.125 21.55 502.75 7.33 147.75 0.63 14.00 0.63 14.00 108.75 2303.25 11.24 247.38 20.13 476.25 15.38 354.25 6.84 157.50 6.84 157.50 284.64 5786.38
7 0.150 24.98 581.63 8.90 202.88 0.69 16.50 0.69 16.50 126.40 2939.38 15.00 328.00 21.14 515.88 19.43 435.13 8.64 193.50 8.64 193.50 382.76 8342.50
8 0.175 27.85 660.38 12.27 264.63 0.81 18.75 0.81 18.75 162.95 3616.88 17.84 410.55 23.05 552.38 22.00 517.88 9.78 230.25 9.78 230.25 512.31 11188.33
9 0.200 28.99 710.50 13.77 325.50 0.86 20.88 0.86 20.88 178.86 4272.63 18.98 460.35 23.82 585.88 23.03 562.88 10.24 250.25 10.24 250.25 568.53 13510.40

10 0.352 35.22 20.01 1.03 1.03 243.25 23.16 29.61 28.62 12.72 12.72 939.38
11 0.372 35.12 703.40 19.85 398.60 1.03 20.60 1.03 20.60 241.70 4849.50 23.06 462.24 29.56 591.70 28.53 571.50 12.68 254.00 12.68 254.00 933.47 18728.46
12 0.400 33.77 964.46 20.95 571.20 1.06 29.26 1.06 29.26 252.92 6924.68 23.74 655.20 27.01 791.98 27.32 781.90 12.14 347.48 12.14 347.48 828.90 24673.18
13 0.425 31.87 820.50 17.92 485.88 0.98 25.50 0.98 25.50 221.92 5935.50 21.84 569.70 25.73 659.25 25.61 661.63 11.38 294.00 11.38 294.00 720.10 19362.55
14 0.450 31.58 793.13 17.48 442.50 0.97 24.38 0.97 24.38 217.47 5492.38 21.56 542.55 25.55 641.00 25.36 637.13 11.27 283.13 11.27 283.13 704.49 17807.33
15 0.475 31.09 783.38 16.73 427.63 0.94 23.88 0.94 23.88 209.75 5340.25 21.06 532.80 25.21 634.50 24.91 628.38 11.07 279.25 11.07 279.25 677.32 17272.58
16 0.500 30.17 765.75 15.40 401.63 0.91 23.13 0.91 23.13 195.90 5070.63 20.15 515.10 24.60 622.63 24.08 612.38 10.70 272.13 10.70 272.13 628.59 16323.90
17 0.525 28.93 738.75 13.68 363.50 0.85 22.00 0.85 22.00 177.91 4672.63 18.91 488.25 23.77 604.63 22.97 588.13 10.21 261.38 10.21 261.38 565.16 14921.88
18 0.550 27.76 708.63 12.16 323.00 0.81 20.75 0.81 20.75 161.85 4247.00 17.76 458.40 23.00 584.63 21.93 561.25 9.75 249.50 9.75 249.50 508.43 13419.85
19 0.575 26.17 674.13 10.24 280.00 0.74 19.38 0.74 19.38 141.02 3785.88 16.18 424.20 21.93 561.63 20.50 530.38 9.11 235.75 9.11 235.75 434.70 11789.18
20 0.600 24.77 636.75 8.67 236.38 0.68 17.75 0.68 17.75 123.82 3310.50 14.78 387.00 21.00 536.63 19.24 496.75 8.55 220.75 8.55 220.75 373.61 10103.88
21 0.625 21.08 573.13 6.82 193.63 0.60 16.00 0.60 16.00 102.96 2834.75 12.96 346.80 19.77 509.63 14.99 427.88 6.66 190.13 6.66 190.13 264.09 7971.20
22 0.650 19.64 509.00 5.37 152.38 0.54 14.25 0.54 14.25 86.09 2363.13 9.46 280.25 18.69 480.75 13.78 359.63 6.13 159.88 6.13 159.88 212.29 5954.75
23 0.675 17.85 468.63 3.81 114.75 0.45 12.38 0.45 12.38 67.14 1915.38 7.79 215.63 17.36 450.63 12.28 325.75 5.46 144.88 5.46 144.88 151.12 4542.63
24 0.700 12.55 380.00 3.38 89.88 0.42 10.88 0.42 10.88 46.00 1414.25 5.65 168.00 9.75 338.88 8.10 254.75 3.60 113.25 3.60 113.25 96.99 3101.38
25 0.725 10.29 285.50 3.38 84.50 0.42 10.50 0.42 10.50 28.87 935.88 3.54 114.88 6.94 208.63 6.21 178.88 2.76 79.50 2.76 79.50 57.86 1935.63
26 0.750 6.68 212.13 3.38 84.50 0.42 10.50 0.42 10.50 8.81 471.00 0.18 46.50 2.42 117.00 3.18 117.38 1.41 52.13 1.41 52.13 17.30 939.50
27 0.775 4.21 136.13 3.38 84.50 0.42 10.50 0.42 10.50 0.31 114.00 0.00 2.25 0.00 30.25 1.11 53.63 0.49 23.75 0.49 23.75 2.40 246.25
28 0.800 5.66 123.38 3.38 84.50 0.42 10.50 0.42 10.50 4.79 63.75 0.00 0.00 1.15 14.38 2.33 43.00 1.03 19.00 1.03 19.00 9.98 154.75
29 0.825 8.23 173.63 3.38 84.50 0.42 10.50 0.42 10.50 16.30 263.63 1.62 20.25 4.36 68.88 4.48 85.13 1.99 37.75 1.99 37.75 31.35 516.63
30 0.850 10.13 229.50 3.38 84.50 0.42 10.50 0.42 10.50 27.82 551.50 3.40 62.75 6.74 138.75 6.08 132.00 2.70 58.63 2.70 58.63 55.54 1086.13
31 0.875 11.93 275.75 3.38 84.50 0.42 10.50 0.42 10.50 41.01 860.38 5.08 106.00 8.99 196.63 7.59 170.88 3.37 75.88 3.37 75.88 85.31 1760.63
32 0.900 11.93 298.25 3.38 84.50 0.42 10.50 0.42 10.50 41.01 1025.25 5.08 127.00 8.99 224.75 7.59 189.75 3.37 84.25 3.37 84.25 85.31 2132.75
33 0.925 17.93 373.25 3.88 90.75 0.45 10.88 0.45 10.88 67.98 1362.38 7.87 161.88 17.42 330.13 12.35 249.25 5.49 110.75 5.49 110.75 153.86 2989.63
34 0.950 18.85 459.75 4.65 106.63 0.50 11.88 0.50 11.88 77.42 1817.50 8.72 207.38 18.10 444.00 13.12 318.38 5.83 141.50 5.83 141.50 184.41 4228.38
35 0.975 19.78 482.88 5.51 127.00 0.54 13.00 0.54 13.00 87.71 2064.13 9.59 228.88 18.80 461.25 13.90 337.75 6.18 150.13 6.18 150.13 217.52 5024.13
36 1.000 20.47 503.12 6.18 146.12 0.57 13.88 0.57 13.88 95.61 2291.50 10.23 247.75 19.32 476.50 14.48 354.75 6.43 157.62 6.43 157.62 242.82 5754.25
37 1.025 20.93 517.50 6.66 160.50 0.60 14.62 0.60 14.62 101.21 2460.25 10.67 261.25 19.67 487.37 14.87 366.87 6.61 163.00 6.61 163.00 260.64 6293.25
38 1.050 20.98 523.87 6.72 167.25 0.60 15.00 0.60 15.00 101.79 2537.50 10.71 267.25 19.70 492.12 14.91 372.25 6.63 165.50 6.63 165.50 262.50 6539.25
39 1.075 20.66 520.50 6.02 159.25 0.57 14.62 0.57 14.62 93.64 2442.87 10.07 259.75 19.19 486.12 14.34 365.62 6.37 162.50 6.37 162.50 236.50 6237.50
40 1.100 20.49 514.37 6.20 152.75 0.58 14.37 0.58 14.37 95.89 2369.12 10.25 254.00 19.34 481.62 14.49 360.37 6.44 160.12 6.44 160.12 243.73 6002.87
41 1.125 20.23 509.00 5.94 151.75 0.56 14.25 0.56 14.25 92.80 2358.62 10.01 253.25 19.14 481.00 14.27 359.50 6.34 159.75 6.34 159.75 233.85 5969.75
Behind Metal Inclined Sand horizontal Sand 450mm thk Rip
Stripping Rock-toe Behind sand Filters Hearting 200mm thk Metal 200mm thk sand Net Casing Area
Filters Chimney Filter Rap
Chainge
Slno
in Km
Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity in Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity
Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum

42 1.150 20.09 504.00 5.81 146.87 0.56 14.00 0.56 14.00 91.27 2300.87 9.88 248.62 19.04 477.25 14.17 355.50 6.30 158.00 6.30 158.00 228.92 5784.62
43 1.175 19.88 499.62 5.60 142.62 0.55 13.88 0.55 13.88 88.80 2250.87 9.68 244.50 18.87 473.87 13.98 351.87 6.21 156.37 6.21 156.37 221.02 5624.25
44 1.200 21.52 517.50 5.45 138.13 0.54 13.63 0.54 13.63 87.03 2197.87 9.54 240.25 21.76 507.87 15.36 366.75 6.83 163.00 6.83 163.00 292.16 6414.75
45 1.225 19.57 513.62 5.30 134.38 0.53 13.38 0.53 13.38 85.28 2153.87 9.39 236.62 18.64 505.00 13.72 363.50 6.10 161.62 6.10 161.62 209.73 6273.62
46 1.250 19.52 488.62 5.26 132.00 0.53 13.25 0.53 13.25 84.74 2125.25 9.35 234.25 18.60 465.50 13.68 342.50 6.08 152.25 6.08 152.25 208.01 5221.75
47 1.275 19.45 487.12 5.19 130.63 0.53 13.25 0.53 13.25 83.95 2108.62 9.28 232.87 18.55 464.37 13.62 341.25 6.05 151.62 6.05 151.62 205.43 5168.00
48 1.300 21.35 510.00 5.28 130.88 0.53 13.25 0.53 13.25 85.11 2113.25 9.37 233.12 21.63 502.25 15.21 360.37 6.76 160.12 6.76 160.12 285.03 6130.75
49 1.325 19.72 513.37 5.45 134.13 0.54 13.38 0.54 13.38 87.03 2151.75 9.54 236.37 18.76 504.87 13.85 363.25 6.16 161.50 6.16 161.50 215.33 6254.50
50 1.350 21.88 520.00 7.70 164.37 0.64 14.75 0.64 14.75 112.96 2499.87 11.54 263.50 20.37 489.12 15.66 368.87 6.96 164.00 6.96 164.00 297.88 6415.12
51 1.375 21.32 540.00 7.08 184.75 0.61 15.62 0.61 15.62 105.91 2735.87 11.02 282.00 19.95 504.00 15.19 385.62 6.75 171.37 6.75 171.37 275.65 7169.12
52 1.400 20.70 525.25 6.42 168.75 0.59 15.00 0.59 15.00 98.42 2554.12 10.45 268.37 19.49 493.00 14.67 373.25 6.52 165.87 6.52 165.87 251.65 6591.25
53 1.425 20.12 510.25 5.84 153.25 0.56 14.37 0.56 14.37 91.65 2375.87 9.91 254.50 19.06 481.87 14.19 360.75 6.31 160.37 6.31 160.37 230.01 6020.75
54 1.450 19.91 500.37 5.63 143.37 0.55 13.88 0.55 13.88 89.21 2260.75 9.72 245.37 18.91 474.62 14.01 352.50 6.23 156.75 6.23 156.75 222.31 5654.00
55 1.475 19.31 490.25 5.06 133.63 0.52 13.38 0.52 13.38 82.45 2145.75 9.15 235.87 18.45 467.00 13.50 343.87 6.00 152.87 6.00 152.87 200.52 5285.37
56 1.500 18.90 477.62 4.70 122.00 0.50 12.75 0.50 12.75 78.02 2005.87 8.77 224.00 18.14 457.37 13.16 333.25 5.85 148.12 5.85 148.12 186.26 4834.75
57 1.525 18.78 471.00 4.59 116.13 0.49 12.38 0.49 12.38 76.74 1934.50 8.66 217.87 18.05 452.37 13.06 327.75 5.81 145.75 5.81 145.75 182.13 4604.87
58 1.550 18.58 467.00 4.42 112.63 0.49 12.25 0.49 12.25 74.63 1892.12 8.47 214.12 17.90 449.37 12.90 324.50 5.73 144.25 5.73 144.25 175.39 4469.00
59 1.575 18.29 460.87 4.17 107.38 0.47 12.00 0.47 12.00 71.64 1828.37 8.21 208.50 17.69 444.87 12.65 319.37 5.62 141.87 5.62 141.87 165.73 4264.00
60 1.600 17.99 453.50 3.92 101.13 0.46 11.63 0.46 11.63 68.55 1752.37 7.92 201.62 17.46 439.37 12.40 313.12 5.51 139.12 5.51 139.12 155.58 4016.37
61 1.625 17.78 447.12 3.76 96.00 0.45 11.38 0.45 11.38 66.51 1688.25 7.73 195.62 17.30 434.50 12.23 307.87 5.43 136.75 5.43 136.75 148.96 3806.75
62 1.650 17.60 442.25 3.62 92.25 0.44 11.13 0.44 11.13 64.65 1639.50 7.56 191.12 17.16 430.75 12.07 303.75 5.36 134.88 5.36 134.88 143.02 3649.75
63 1.675 17.57 439.62 3.59 90.12 0.44 11.00 0.44 11.00 64.41 1613.25 7.54 188.75 17.15 428.87 12.05 301.50 5.36 134.00 5.36 134.00 142.24 3565.75
64 1.700 14.09 395.75 3.38 87.12 0.42 10.75 0.42 10.75 59.80 1552.62 7.09 182.87 11.69 360.50 9.40 268.12 4.18 119.25 4.18 119.25 129.95 3402.37
65 1.725 13.90 349.87 3.38 84.50 0.42 10.50 0.42 10.50 58.00 1472.50 6.91 175.00 11.45 289.25 9.24 233.00 4.11 103.63 4.11 103.63 125.58 3194.12
66 1.750 13.52 342.75 3.38 84.50 0.42 10.50 0.42 10.50 54.47 1405.87 6.55 168.25 10.97 280.25 8.91 226.87 3.96 100.88 3.96 100.88 117.12 3033.75
67 1.775 13.60 339.00 3.38 84.50 0.42 10.50 0.42 10.50 55.23 1371.25 6.63 164.75 11.08 275.62 8.99 223.75 3.99 99.37 3.99 99.37 118.94 2950.75
68 1.800 13.42 337.75 3.38 84.50 0.42 10.50 0.42 10.50 53.60 1360.38 6.46 163.62 10.85 274.12 8.83 222.75 3.93 99.00 3.93 99.00 115.04 2924.75
69 1.825 13.39 335.12 3.38 84.50 0.42 10.50 0.42 10.50 53.28 1336.00 6.43 161.12 10.81 270.75 8.81 220.50 3.91 98.00 3.91 98.00 114.26 2866.25
70 1.850 12.51 323.75 3.38 84.50 0.42 10.50 0.42 10.50 45.70 1237.25 5.61 150.50 9.71 256.50 8.07 211.00 3.59 93.75 3.59 93.75 96.27 2631.62
71 1.875 12.56 313.37 3.38 84.50 0.42 10.50 0.42 10.50 46.10 1147.50 5.66 140.87 9.77 243.50 8.11 202.25 3.60 89.87 3.60 89.87 97.23 2418.75
72 1.900 12.29 310.62 3.38 84.50 0.42 10.50 0.42 10.50 43.85 1124.38 5.41 138.37 9.43 240.00 7.88 199.87 3.50 88.75 3.50 88.75 91.99 2365.25
Total 32932.49 11307.80 978.61 978.61 156843.56 17017.27 28845.18 23548.78 10465.73 10465.73 432613.44

``
Formation Mallamadugu Reservoir
BUND-1
Detail Estimate of Profile Wall
0.3

Profile wall
450 thk Rip Rap
200 thk Metal
200 thk Sand
0.3 Casing Soils
Area of Earthwork Excavation = 0.3 X 0.3 0.09 Sqm
Area of Concrete = (0.45 +0.2+0.2+0.3) X 0.3 0.35 Sqm

Concrete with
Top of U/S Face Slant Length EWE of Profile Wall
Stripped Height of grade of Mix CC
Slno Chainage the Area Quantity Area Quantity Remarks
Level Bund Details Length
Profile (Sqm) (Cum) (Sqm) (Cum)

1 0.000

2 0.030 124.860 129.500 4.640 sqrt(2.0X2.0+1X1) X4.64 = 10.375 0.09 0.930 0.35 3.630

3 0.060 121.988 129.500 7.512 sqrt(2.0X2.0+1X1) X7.512 = 16.797 0.09 1.510 0.35 5.880

4 0.090 119.778 129.500 9.722 sqrt(2.0X2.0+1X1) +5 X9.722 = 26.739 0.09 2.410 0.35 9.360

5 0.120 117.650 129.500 11.850 sqrt(2.0X2.0+1X1) +5 X11.85 = 31.497 0.09 2.830 0.35 11.020

6 0.150 115.320 129.500 14.180 sqrt(2.5X2.5+1X1) +5 X14.18 = 43.181 0.09 3.890 0.35 15.110

7 0.180 112.775 129.500 16.725 sqrt(2.5X2.5+1X1) +5 X16.725 = 50.033 0.09 4.500 0.35 17.510

8 0.200 112.350 129.500 17.150 sqrt(2.5X2.5+1X1) +5 X17.15 = 51.178 0.09 4.610 0.35 17.910

9 0.352 109.240 129.500 20.260 sqrt(2.5X2.5+1X1) +5 X20.26 = 59.552 0.09 5.360 0.35 20.840

10 0.375 109.310 129.500 20.190 sqrt(2.5X2.5+1X1) +5 X20.19 = 59.363 0.09 5.340 0.35 20.780

11 0.400 108.810 129.500 20.690 sqrt(2.5X2.5+1X1) +5 X20.69 = 60.710 0.09 5.460 0.35 21.250

12 0.430 110.325 129.500 19.175 sqrt(2.5X2.5+1X1) +5 X19.175 = 56.630 0.09 5.100 0.35 19.820

13 0.460 110.615 129.500 18.885 sqrt(2.5X2.5+1X1) +5 X18.885 = 55.849 0.09 5.030 0.35 19.550

14 0.490 111.140 129.500 18.360 sqrt(2.5X2.5+1X1) +5 X18.36 = 54.436 0.09 4.900 0.35 19.050

15 0.520 111.940 129.500 17.560 sqrt(2.5X2.5+1X1) +5 X17.56 = 52.282 0.09 4.710 0.35 18.300

16 0.550 113.260 129.500 16.240 sqrt(2.5X2.5+1X1) +5 X16.24 = 48.728 0.09 4.390 0.35 17.050

17 0.580 114.960 129.500 14.540 sqrt(2.5X2.5+1X1) +5 X14.54 = 44.150 0.09 3.970 0.35 15.450

18 0.610 116.160 129.500 13.340 sqrt(2.0X2.0+1X1) +5 X13.34 = 34.829 0.09 3.130 0.35 12.190

19 0.640 117.440 129.500 12.060 sqrt(2.0X2.0+1X1) +5 X12.06 = 31.967 0.09 2.880 0.35 11.190

20 0.670 118.785 129.500 10.715 sqrt(2.0X2.0+1X1) +5 X10.715 = 28.959 0.09 2.610 0.35 10.140

21 0.700 121.450 129.500 8.050 sqrt(2.0X2.0+1X1) X8.05 = 18.000 0.09 1.620 0.35 6.300

22 0.730 124.835 129.500 4.665 sqrt(2.0X2.0+1X1) X4.665 = 10.431 0.09 0.940 0.35 3.650

23 0.760 127.370 129.500 2.130 sqrt(2.0X2.0+1X1) X2.13 = 4.763 0.09 0.430 0.35 1.670

24 0.790 127.795 129.500 1.705 sqrt(2.0X2.0+1X1) X1.705 = 3.812 0.09 0.340 0.35 1.330

25 0.820 126.120 129.500 3.380 sqrt(2.0X2.0+1X1) X3.38 = 7.558 0.09 0.680 0.35 2.650

26 0.850 123.460 129.500 6.040 sqrt(2.0X2.0+1X1) X6.04 = 13.506 0.09 1.220 0.35 4.730
Concrete with
Top of U/S Face Slant Length EWE of Profile Wall
Stripped Height of grade of Mix CC
Slno Chainage the Area Quantity Area Quantity Remarks
Level Bund Details Length
Profile (Sqm) (Cum) (Sqm) (Cum)

27 0.880 121.960 129.500 7.540 sqrt(2.0X2.0+1X1) X7.54 = 16.860 0.09 1.520 0.35 5.900

28 0.910 120.710 129.500 8.790 sqrt(2.0X2.0+1X1) X8.79 = 19.655 0.09 1.770 0.35 6.880

29 0.940 119.080 129.500 10.420 sqrt(2.0X2.0+1X1) +5 X10.42 = 28.300 0.09 2.550 0.35 9.910

30 0.970 118.310 129.500 11.190 sqrt(2.0X2.0+1X1) +5 X11.19 = 30.022 0.09 2.700 0.35 10.510

31 1.000 117.350 129.500 12.150 sqrt(2.5X2.5+1X1) +5 X12.15 = 32.168 0.09 2.900 0.35 11.260

32 1.030 116.940 129.500 12.560 sqrt(2.5X2.5+1X1) +5 X12.56 = 33.085 0.09 2.980 0.35 11.580

33 1.060 117.055 129.500 12.445 sqrt(2.5X2.5+1X1) +5 X12.445 = 32.828 0.09 2.950 0.35 11.490

34 1.090 117.260 129.500 12.240 sqrt(2.5X2.5+1X1) +5 X12.24 = 32.369 0.09 2.910 0.35 11.330

35 1.120 117.440 129.500 12.060 sqrt(2.5X2.5+1X1) +5 X12.06 = 31.967 0.09 2.880 0.35 11.190

36 1.150 117.660 129.500 11.840 sqrt(2.0X2.0+1X1) +5 X11.84 = 31.475 0.09 2.830 0.35 11.020

37 1.180 117.905 129.500 11.595 sqrt(2.0X2.0+1X1) +5 X11.595 = 30.927 0.09 2.780 0.35 10.820

38 1.210 118.035 129.500 11.465 sqrt(2.0X2.0+1X1) +5 X11.465 = 30.637 0.09 2.760 0.35 10.720

39 1.240 118.120 129.500 11.380 sqrt(2.0X2.0+1X1) +5 X11.38 = 30.446 0.09 2.740 0.35 10.660

40 1.270 118.170 129.500 11.330 sqrt(2.0X2.0+1X1) +5 X11.33 = 30.335 0.09 2.730 0.35 10.620

41 1.300 118.115 129.500 11.385 sqrt(2.0X2.0+1X1) +5 X11.385 = 30.458 0.09 2.740 0.35 10.660

42 1.330 117.073 129.500 12.427 sqrt(2.0X2.0+1X1) +5 X12.427 = 32.788 0.09 2.950 0.35 11.480

43 1.360 116.408 129.500 13.092 sqrt(2.0X2.0+1X1) +5 X13.092 = 34.275 0.09 3.080 0.35 12.000

44 1.390 116.898 129.500 12.602 sqrt(2.0X2.0+1X1) +5 X12.602 = 33.179 0.09 2.990 0.35 11.610

45 1.420 117.395 129.500 12.105 sqrt(2.0X2.0+1X1) +5 X12.105 = 32.068 0.09 2.890 0.35 11.220

46 1.450 117.810 129.500 11.690 sqrt(2.0X2.0+1X1) +5 X11.69 = 31.140 0.09 2.800 0.35 10.900

47 1.480 118.485 129.500 11.015 sqrt(2.0X2.0+1X1) +5 X11.015 = 29.630 0.09 2.670 0.35 10.370

48 1.510 118.705 129.500 10.795 sqrt(2.0X2.0+1X1) +5 X10.795 = 29.138 0.09 2.620 0.35 10.200

49 1.540 118.838 129.500 10.662 sqrt(2.0X2.0+1X1) +5 X10.662 = 28.841 0.09 2.600 0.35 10.090

50 1.570 119.040 129.500 10.460 sqrt(2.0X2.0+1X1) +5 X10.46 = 28.389 0.09 2.560 0.35 9.940

51 1.600 119.415 129.500 10.085 sqrt(2.0X2.0+1X1) +5 X10.085 = 27.551 0.09 2.480 0.35 9.640

52 1.630 119.663 129.500 9.837 sqrt(2.0X2.0+1X1) +5 X9.837 = 26.996 0.09 2.430 0.35 9.450

53 1.660 119.750 129.500 9.750 sqrt(2.0X2.0+1X1) +5 X9.75 = 26.802 0.09 2.410 0.35 9.380

54 1.690 119.960 129.500 9.540 sqrt(2.0X2.0+1X1) +5 X9.54 = 26.332 0.09 2.370 0.35 9.220

55 1.720 120.240 129.500 9.260 sqrt(2.0X2.0+1X1) +5 X9.26 = 25.706 0.09 2.310 0.35 9.000

56 1.750 120.640 129.500 8.860 sqrt(2.0X2.0+1X1) +5 X8.86 = 24.812 0.09 2.230 0.35 8.680

57 1.780 120.645 129.500 8.855 sqrt(2.0X2.0+1X1) +5 X8.855 = 24.800 0.09 2.230 0.35 8.680

58 1.810 120.735 129.500 8.765 sqrt(2.0X2.0+1X1) +5 X8.765 = 24.599 0.09 2.210 0.35 8.610

59 1.840 121.115 129.500 8.385 sqrt(2.0X2.0+1X1) X8.385 = 18.749 0.09 1.690 0.35 6.560

60 1.870 121.460 129.500 8.040 sqrt(2.0X2.0+1X1) X8.04 = 17.978 0.09 1.620 0.35 6.290

61 1.900 121.665 129.500 7.835 sqrt(2.0X2.0+1X1) X7.835 = 17.520 0.09 1.580 0.35 6.130

Total Quantity 167.250 Cum 650.360 Cum


Formation Mallamadugu Reservoir
BUND-1
Detail Estimate of Drilling & Grouting
Drilling holes and driving casing pipe 63mm dia in the
consolidated cut off trench upto the bottom off cut of
1
along bund axis as directed in the soil with drilling
machine and casing bit including cost of casing pipe

Length of dam 1708 meters


Interval of Grouting holes 3 meters
Total no of holes 570 meters
Depth of Casing Pipe 4 meters
Total length of the Pipe 2280 meters
Drilling holes into the rock from the bottom of cut off
trench by wagon drill to the specified depth at
2 intervals as directed for washing holes with air jet and
water in the drilled holes, founfation treatment
including refilling the holes whereever necessary
Length of dam 1708 meters
Interval of Grouting holes 3 meters
Total no of holes 570 meters
Depth of each Hole 12 meters
Total length of the Drilling holes into the rock from the
6840 meters
bottom of cut off trench

Conducting in situ permeability test at 2Mtr. Zones,


3
using double packer in the drilled holes

Length of dam 2508 meters


Interval of testing holes 50 meters
Total no of holes 51 meters
Depth of each Hole 12 meters
Total length of the Pipe 612 meters

Grouting the holes with cement slurry with specified


4 MT
ratio of water cement mix incliding cost of cement

Total length of the Drilling holes into the rock from the
6840 meters
bottom of cut off trench
Cement consumption 0.75 Bag for one RMT
Total Cement Consumption 5130 Bags
Total Cement Consumption 257 MT
Formation Mallamadugu Reservoir
BUND-1
Detailed Es mate for 'Parpet wall' on U/S
150

CC M15-40 MSA
600
T BL .+131.000

1000

CC M 15 40 MSA 200
600
Details of Parapet

S.No Description of Item Nos Length Width Depth Quantity


1 2 3 4 5 6 7
Earth work excavation for
1 1 1748.00 0.60 1.00 1048.80 Cum
Deflector wall
Levelling course in CC
2 M15 with 40 MSA 1 1748.00 0.60 0.20 209.76 Cum
Deflector wall
CC M15 with 40 MSA for
3 1 1748.00 1.60 0.30 839.04 Cum
Parpet wall
(∏ X 0.15
4 Top Curve Portion 1 1748.00 0.0353 61.70 Cum
X 0.15) /2

Detailed Es mate for 'Guard Stone' @ 3M C/C on D/S


225

750
TBL-131.000

2
450
1

Guard Stone @ 3 m C/C

S.No Description of Item Nos Length Width Depth Quantity


1 2 3 4 5 6 7
Earth work excavation for
1 584 0.225 0.225 0.45 13.30 Cum
Deflector wall
CC M15 with 40 MSA for
2 584 0.225 0.225 1.20 35.46 Cum
Parpet wall
Bund-3 270 Meters
Saddle Bund 250 Meters
Bund-2 1143 Meters
Bund-1 1900 Meters
Details Estimate of Rock Toe of Bund-1
T.B.L = + 129.500 M Height of Rock-Toe = 20 % of Hydraluical Head= (FRL-Stipped Levels) X 20%
F.R.L = + 127.500 M Minimum Height of Rock -Toe = 1.5 Meters
M.W.L = + 127.500 M Maximum Height of Rock -Toe = 6 Meters
Bottom
Height of Rock- Top Level of Mean Area Quantity
Slno Chainage Stripped Level Width of Area (Sqm) Remarks
Toe (M) Rock -Toe (Sqm) (Cum)
Rock-Toe (M)

1 0.000 0.00 0.000 0.00 0.00


2 0.025 126.450 1.50 127.950 4.50 3.38 1.69 42.25
3 0.050 123.270 1.50 124.770 4.50 3.38 3.38 84.50
4 0.075 120.705 1.50 122.205 4.50 3.38 3.38 84.50
5 0.100 118.850 1.73 120.580 5.19 4.49 3.94 98.38
6 0.125 116.450 2.21 118.660 6.63 7.33 5.91 147.75
7 0.150 115.320 2.44 117.756 7.31 8.91 8.12 203.00
8 0.175 113.200 2.86 116.060 8.58 12.27 10.59 264.75
9 0.180 112.775 2.95 115.720 8.84 13.01 12.64 63.20
10 0.200 112.350 3.03 115.380 9.09 13.78 13.40 267.90

11 0.352 109.240 3.65 112.892 10.96 20.01 20.01


12 0.377 109.310 3.64 112.948 10.91 19.86 16.67 416.63
13 0.400 108.810 3.74 112.548 11.21 20.96 20.41 469.43
14 0.425 110.220 3.46 113.676 10.37 17.92 19.44 486.00
15 0.450 110.430 3.41 113.844 10.24 17.49 17.71 442.63
16 0.475 110.800 3.34 114.140 10.02 16.74 17.12 427.88
17 0.500 111.480 3.20 114.684 9.61 15.40 16.07 401.75
18 0.525 112.400 3.02 115.420 9.06 13.69 14.55 363.63
19 0.550 113.260 2.85 116.108 8.54 12.17 12.93 323.25
20 0.575 114.440 2.61 117.052 7.84 10.24 11.21 280.13
21 0.600 115.480 2.40 117.884 7.21 8.67 9.46 236.38
22 0.625 116.840 2.13 118.972 6.40 6.82 7.75 193.63
23 0.650 118.040 1.89 119.932 5.68 5.37 6.10 152.38
24 0.675 119.530 1.59 121.124 4.78 3.82 4.60 114.88
25 0.700 121.450 1.50 122.950 4.50 3.38 3.60 90.00
26 0.725 123.330 1.50 124.830 4.50 3.38 3.38 84.50
27 0.750 126.340 1.50 127.840 4.50 3.38 3.38 84.50
28 0.775 128.400 1.50 129.900 4.50 3.38 3.38 84.50
29 0.800 127.190 1.50 128.690 4.50 3.38 3.38 84.50
30 0.825 125.050 1.50 126.550 4.50 3.38 3.38 84.50
31 0.850 123.460 1.50 124.960 4.50 3.38 3.38 84.50
32 0.875 121.960 1.50 123.460 4.50 3.38 3.38 84.50
33 0.900 121.960 1.50 123.460 4.50 3.38 3.38 84.50
34 0.925 119.460 1.61 121.068 4.82 3.88 3.63 90.75
35 0.950 118.700 1.76 120.460 5.28 4.65 4.27 106.63
36 0.975 117.920 1.92 119.836 5.75 5.51 5.08 127.00
37 1.000 117.350 2.03 119.380 6.09 6.19 5.85 146.25
38 1.025 116.960 2.11 119.068 6.32 6.67 6.43 160.75
39 1.050 116.920 2.12 119.036 6.35 6.72 6.70 167.37
40 1.075 117.190 2.06 119.252 6.19 6.38 6.55 163.75
41 1.100 117.330 2.03 119.364 6.10 6.21 6.30 157.37
42 1.125 117.550 1.99 119.540 5.97 5.95 6.08 152.00
43 1.150 117.660 1.97 119.628 5.90 5.81 5.88 147.00
44 1.175 117.840 1.93 119.772 5.80 5.60 5.71 142.62
45 1.200 117.970 1.91 119.876 5.72 5.45 5.53 138.13
46 1.225 118.100 1.88 119.980 5.64 5.31 5.38 134.50
47 1.250 118.140 1.87 120.012 5.62 5.26 5.29 132.13
48 1.275 118.200 1.86 120.060 5.58 5.19 5.23 130.63
49 1.300 118.115 1.88 119.992 5.63 5.29 5.24 131.00
50 1.325 117.970 1.91 119.876 5.72 5.45 5.37 134.25
51 1.350 116.175 2.27 118.440 6.80 7.70 6.58 164.37
52 1.375 116.640 2.17 118.812 6.52 7.08 7.39 184.75
53 1.400 117.155 2.07 119.224 6.21 6.43 6.76 168.87
54 1.425 117.635 1.97 119.608 5.92 5.84 6.14 153.37
55 1.450 117.810 1.94 119.748 5.81 5.64 5.74 143.50
56 1.475 118.315 1.84 120.152 5.51 5.07 5.36 133.88
57 1.500 118.655 1.77 120.424 5.31 4.70 4.89 122.13
58 1.525 118.755 1.75 120.504 5.25 4.59 4.65 116.13
59 1.550 118.920 1.72 120.636 5.15 4.42 4.51 112.63
60 1.575 119.160 1.67 120.828 5.00 4.18 4.30 107.50
61 1.600 119.415 1.62 121.032 4.85 3.93 4.06 101.38
62 1.625 119.585 1.58 121.168 4.75 3.76 3.85 96.12
63 1.650 119.740 1.55 121.292 4.66 3.62 3.69 92.25
64 1.675 119.760 1.55 121.308 4.64 3.60 3.61 90.25
65 1.700 120.160 1.50 121.660 4.50 3.38 3.49 87.25
66 1.725 120.320 1.50 121.820 4.50 3.38 3.38 84.50
67 1.750 120.640 1.50 122.140 4.50 3.38 3.38 84.50
68 1.775 120.570 1.50 122.070 4.50 3.38 3.38 84.50
69 1.800 120.720 1.50 122.220 4.50 3.38 3.38 84.50
70 1.825 120.750 1.50 122.250 4.50 3.38 3.38 84.50
71 1.850 121.480 1.50 122.980 4.50 3.38 3.38 84.50
72 1.875 121.440 1.50 122.940 4.50 3.38 3.38 84.50
73 1.900 121.665 1.50 123.165 4.50 3.38 3.38 84.50
Total Quantity 11243.28 Cum
Grand Total 11243.28 Cum
Filters Below Rock-Toe
200 mm thick Sand Filters
Bottom Top Width
Height of Rock- Top Level of Avg Width of Mean Area
Slno Chainage Stripped Level Width of of Sand Area (Sqm) Quantity (Cum) Remarks
Toe (M) Rock -Toe Sand Filter (Sqm)
Sand Filter Filter
1 0.000 0.0 0.000 0.00 0.00 0.00 0.00
2 0.025 126.450 1.5 127.950 4.50 3.90 4.20 0.84 0.42 10.50
3 0.050 123.270 1.5 124.770 4.50 3.90 4.20 0.84 0.84 21.00
4 0.075 120.705 1.5 122.205 4.50 3.90 4.20 0.84 0.84 21.00
5 0.100 118.850 1.7 120.580 5.19 4.59 4.89 0.98 0.91 22.73
6 0.125 116.450 2.2 118.660 6.63 6.03 6.33 1.27 1.12 28.05
7 0.150 115.320 2.4 117.756 7.31 6.71 7.01 1.40 1.33 33.35
8 0.175 113.200 2.9 116.060 8.58 7.98 8.28 1.66 1.53 38.22
9 0.180 112.775 2.9 115.720 8.84 8.24 8.54 1.71 1.68 8.41
10 0.200 112.350 3.0 115.380 9.09 8.49 8.79 1.76 1.73 34.65
0
11 0.352 109.240 3.7 112.892 10.96 10.36 10.66 2.13 2.13
12 0.377 109.310 3.6 112.948 10.91 10.31 10.61 2.12 2.13 53.18
13 0.400 108.810 3.7 112.548 11.21 10.61 10.91 2.18 2.15 49.51
14 0.425 110.220 3.5 113.676 10.37 9.77 10.07 2.01 2.10 52.46
15 0.450 110.430 3.4 113.844 10.24 9.64 9.94 1.99 2.00 50.03
16 0.475 110.800 3.3 114.140 10.02 9.42 9.72 1.94 1.97 49.16
17 0.500 111.480 3.2 114.684 9.61 9.01 9.31 1.86 1.90 47.58
18 0.525 112.400 3.0 115.420 9.06 8.46 8.76 1.75 1.81 45.18
19 0.550 113.260 2.8 116.108 8.54 7.94 8.24 1.65 1.70 42.51
20 0.575 114.440 2.6 117.052 7.84 7.24 7.54 1.51 1.58 39.45
21 0.600 115.480 2.4 117.884 7.21 6.61 6.91 1.38 1.44 36.12
22 0.625 116.840 2.1 118.972 6.40 5.80 6.10 1.22 1.30 32.52
23 0.650 118.040 1.9 119.932 5.68 5.08 5.38 1.08 1.15 28.68
24 0.675 119.530 1.6 121.124 4.78 4.18 4.48 0.90 0.99 24.65
25 0.700 121.450 1.5 122.950 4.50 3.90 4.20 0.84 0.87 21.71
26 0.725 123.330 1.5 124.830 4.50 3.90 4.20 0.84 0.84 21.00
27 0.750 126.340 1.5 127.840 4.50 3.90 4.20 0.84 0.84 21.00
28 0.775 128.400 1.5 129.900 4.50 3.90 4.20 0.84 0.84 21.00
29 0.800 127.190 1.5 128.690 4.50 3.90 4.20 0.84 0.84 21.00
30 0.825 125.050 1.5 126.550 4.50 3.90 4.20 0.84 0.84 21.00
31 0.850 123.460 1.5 124.960 4.50 3.90 4.20 0.84 0.84 21.00
32 0.875 121.960 1.5 123.460 4.50 3.90 4.20 0.84 0.84 21.00
33 0.900 121.960 1.5 123.460 4.50 3.90 4.20 0.84 0.84 21.00
34 0.925 119.460 1.6 121.068 4.82 4.22 4.52 0.90 0.87 21.81
35 0.950 118.700 1.8 120.460 5.28 4.68 4.98 1.00 0.95 23.76
36 0.975 117.920 1.9 119.836 5.75 5.15 5.45 1.09 1.04 26.07
37 1.000 117.350 2.0 119.380 6.09 5.49 5.79 1.16 1.12 28.09
38 1.025 116.960 2.1 119.068 6.32 5.72 6.02 1.20 1.18 29.53
39 1.050 116.920 2.1 119.036 6.35 5.75 6.05 1.21 1.21 30.18
40 1.075 117.190 2.1 119.252 6.19 5.59 5.89 1.18 1.19 29.83
41 1.100 117.330 2.0 119.364 6.10 5.50 5.80 1.16 1.17 29.22
42 1.125 117.550 2.0 119.540 5.97 5.37 5.67 1.13 1.15 28.68
43 1.150 117.660 2.0 119.628 5.90 5.30 5.60 1.12 1.13 28.18
44 1.175 117.840 1.9 119.772 5.80 5.20 5.50 1.10 1.11 27.75
45 1.200 117.970 1.9 119.876 5.72 5.12 5.42 1.08 1.09 27.28
46 1.225 118.100 1.9 119.980 5.64 5.04 5.34 1.07 1.08 26.89
47 1.250 118.140 1.9 120.012 5.62 5.02 5.32 1.06 1.07 26.64
48 1.275 118.200 1.9 120.060 5.58 4.98 5.28 1.06 1.06 26.49
49 1.300 118.115 1.9 119.992 5.63 5.03 5.33 1.07 1.06 26.53
50 1.325 117.970 1.9 119.876 5.72 5.12 5.42 1.08 1.07 26.87
51 1.350 116.175 2.3 118.440 6.80 6.20 6.50 1.30 1.19 29.78
52 1.375 116.640 2.2 118.812 6.52 5.92 6.22 1.24 1.27 31.78
53 1.400 117.155 2.1 119.224 6.21 5.61 5.91 1.18 1.21 30.31
54 1.425 117.635 2.0 119.608 5.92 5.32 5.62 1.12 1.15 28.81
55 1.450 117.810 1.9 119.748 5.81 5.21 5.51 1.10 1.11 27.83
56 1.475 118.315 1.8 120.152 5.51 4.91 5.21 1.04 1.07 26.81
57 1.500 118.655 1.8 120.424 5.31 4.71 5.01 1.00 1.02 25.54
58 1.525 118.755 1.7 120.504 5.25 4.65 4.95 0.99 1.00 24.88
59 1.550 118.920 1.7 120.636 5.15 4.55 4.85 0.97 0.98 24.49
60 1.575 119.160 1.7 120.828 5.00 4.40 4.70 0.94 0.96 23.88
61 1.600 119.415 1.6 121.032 4.85 4.25 4.55 0.91 0.93 23.14
62 1.625 119.585 1.6 121.168 4.75 4.15 4.45 0.89 0.90 22.50
63 1.650 119.740 1.6 121.292 4.66 4.06 4.36 0.87 0.88 22.01
64 1.675 119.760 1.5 121.308 4.64 4.04 4.34 0.87 0.87 21.75
65 1.700 120.160 1.5 121.660 4.50 3.90 4.20 0.84 0.85 21.36
66 1.725 120.320 1.5 121.820 4.50 3.90 4.20 0.84 0.84 21.00
67 1.750 120.640 1.5 122.140 4.50 3.90 4.20 0.84 0.84 21.00
68 1.775 120.570 1.5 122.070 4.50 3.90 4.20 0.84 0.84 21.00
69 1.800 120.720 1.5 122.220 4.50 3.90 4.20 0.84 0.84 21.00
70 1.825 120.750 1.5 122.250 4.50 3.90 4.20 0.84 0.84 21.00
71 1.850 121.480 1.5 122.980 4.50 3.90 4.20 0.84 0.84 21.00
72 1.875 121.440 1.5 122.940 4.50 3.90 4.20 0.84 0.84 21.00
73 1.900 121.665 1.5 123.165 4.50 3.90 4.20 0.84 0.84 21.00
Total Quantity 1975.33 Cum
200 mm thick Metal Filters

Bottom Top Width


Height of Rock- Top Level of Avg Width of Mean Area
Slno Chainage Stripped Level Width of of Metal Area (Sqm) Quantity (Cum) Remarks
Toe (M) Rock -Toe Metal Filter (Sqm)
Metal Filter Filter
1 0.000 0.000 0.000 0.000 0.00 0.00 0.00 0.00
2 0.025 126.450 1.500 127.950 3.90 3.30 3.60 0.72 0.36 9.00
3 0.050 123.270 1.500 124.770 3.90 3.30 3.60 0.72 0.72 18.00
4 0.075 120.705 1.500 122.205 3.90 3.30 3.60 0.72 0.72 18.00
5 0.100 118.850 1.730 120.580 4.59 3.99 4.29 0.86 0.79 19.73
6 0.125 116.450 2.210 118.660 6.03 5.43 5.73 1.15 1.00 25.05
7 0.150 115.320 2.436 117.756 6.71 6.11 6.41 1.28 1.21 30.35
8 0.175 113.200 2.860 116.060 7.98 7.38 7.68 1.54 1.41 35.22
9 0.180 112.775 2.945 115.720 8.24 7.64 7.94 1.59 1.56 7.81
10 0.200 112.350 3.030 115.380 8.49 7.89 8.19 1.64 1.61 32.25

11 0.352 109.240 3.652 112.892 10.36 9.76 10.06 2.01 2.01


12 0.377 109.310 3.638 112.948 10.31 9.71 10.01 2.00 2.01 50.18
13 0.400 108.810 3.738 112.548 10.61 10.01 10.31 2.06 2.03 46.75
14 0.425 110.220 3.456 113.676 9.77 9.17 9.47 1.89 1.98 49.46
15 0.450 110.430 3.414 113.844 9.64 9.04 9.34 1.87 1.88 47.03
16 0.475 110.800 3.340 114.140 9.42 8.82 9.12 1.82 1.85 46.16
17 0.500 111.480 3.204 114.684 9.01 8.41 8.71 1.74 1.78 44.58
18 0.525 112.400 3.020 115.420 8.46 7.86 8.16 1.63 1.69 42.18
19 0.550 113.260 2.848 116.108 7.94 7.34 7.64 1.53 1.58 39.51
20 0.575 114.440 2.612 117.052 7.24 6.64 6.94 1.39 1.46 36.45
21 0.600 115.480 2.404 117.884 6.61 6.01 6.31 1.26 1.32 33.12
22 0.625 116.840 2.132 118.972 5.80 5.20 5.50 1.10 1.18 29.52
23 0.650 118.040 1.892 119.932 5.08 4.48 4.78 0.96 1.03 25.68
24 0.675 119.530 1.594 121.124 4.18 3.58 3.88 0.78 0.87 21.65
25 0.700 121.450 1.500 122.950 3.90 3.30 3.60 0.72 0.75 18.71
26 0.725 123.330 1.500 124.830 3.90 3.30 3.60 0.72 0.72 18.00
27 0.750 126.340 1.500 127.840 3.90 3.30 3.60 0.72 0.72 18.00
28 0.775 128.400 1.500 129.900 3.90 3.30 3.60 0.72 0.72 18.00
29 0.800 127.190 1.500 128.690 3.90 3.30 3.60 0.72 0.72 18.00
30 0.825 125.050 1.500 126.550 3.90 3.30 3.60 0.72 0.72 18.00
31 0.850 123.460 1.500 124.960 3.90 3.30 3.60 0.72 0.72 18.00
32 0.875 121.960 1.500 123.460 3.90 3.30 3.60 0.72 0.72 18.00
33 0.900 121.960 1.500 123.460 3.90 3.30 3.60 0.72 0.72 18.00
34 0.925 119.460 1.608 121.068 4.22 3.62 3.92 0.78 0.75 18.81
35 0.950 118.700 1.760 120.460 4.68 4.08 4.38 0.88 0.83 20.76
36 0.975 117.920 1.916 119.836 5.15 4.55 4.85 0.97 0.92 23.07
37 1.000 117.350 2.030 119.380 5.49 4.89 5.19 1.04 1.00 25.09
38 1.025 116.960 2.108 119.068 5.72 5.12 5.42 1.08 1.06 26.53
39 1.050 116.920 2.116 119.036 5.75 5.15 5.45 1.09 1.09 27.18
40 1.075 117.190 2.062 119.252 5.59 4.99 5.29 1.06 1.07 26.83
41 1.100 117.330 2.034 119.364 5.50 4.90 5.20 1.04 1.05 26.22
42 1.125 117.550 1.990 119.540 5.37 4.77 5.07 1.01 1.03 25.68
43 1.150 117.660 1.968 119.628 5.30 4.70 5.00 1.00 1.01 25.18
44 1.175 117.840 1.932 119.772 5.20 4.60 4.90 0.98 0.99 24.75
45 1.200 117.970 1.906 119.876 5.12 4.52 4.82 0.96 0.97 24.28
46 1.225 118.100 1.880 119.980 5.04 4.44 4.74 0.95 0.96 23.89
47 1.250 118.140 1.872 120.012 5.02 4.42 4.72 0.94 0.95 23.64
48 1.275 118.200 1.860 120.060 4.98 4.38 4.68 0.94 0.94 23.49
49 1.300 118.115 1.877 119.992 5.03 4.43 4.73 0.95 0.94 23.53
50 1.325 117.970 1.906 119.876 5.12 4.52 4.82 0.96 0.95 23.87
51 1.350 116.175 2.265 118.440 6.20 5.60 5.90 1.18 1.07 26.78
52 1.375 116.640 2.172 118.812 5.92 5.32 5.62 1.12 1.15 28.78
53 1.400 117.155 2.069 119.224 5.61 5.01 5.31 1.06 1.09 27.31
54 1.425 117.635 1.973 119.608 5.32 4.72 5.02 1.00 1.03 25.81
55 1.450 117.810 1.938 119.748 5.21 4.61 4.91 0.98 0.99 24.83
56 1.475 118.315 1.837 120.152 4.91 4.31 4.61 0.92 0.95 23.81
57 1.500 118.655 1.769 120.424 4.71 4.11 4.41 0.88 0.90 22.54
58 1.525 118.755 1.749 120.504 4.65 4.05 4.35 0.87 0.88 21.88
59 1.550 118.920 1.716 120.636 4.55 3.95 4.25 0.85 0.86 21.49
60 1.575 119.160 1.668 120.828 4.40 3.80 4.10 0.82 0.84 20.88
61 1.600 119.415 1.617 121.032 4.25 3.65 3.95 0.79 0.81 20.14
62 1.625 119.585 1.583 121.168 4.15 3.55 3.85 0.77 0.78 19.50
63 1.650 119.740 1.552 121.292 4.06 3.46 3.76 0.75 0.76 19.01
64 1.675 119.760 1.548 121.308 4.04 3.44 3.74 0.75 0.75 18.75
65 1.700 120.160 1.500 121.660 3.90 3.30 3.60 0.72 0.73 18.36
66 1.725 120.320 1.500 121.820 3.90 3.30 3.60 0.72 0.72 18.00
67 1.750 120.640 1.500 122.140 3.90 3.30 3.60 0.72 0.72 18.00
68 1.775 120.570 1.500 122.070 3.90 3.30 3.60 0.72 0.72 18.00
69 1.800 120.720 1.500 122.220 3.90 3.30 3.60 0.72 0.72 18.00
70 1.825 120.750 1.500 122.250 3.90 3.30 3.60 0.72 0.72 18.00
71 1.850 121.480 1.500 122.980 3.90 3.30 3.60 0.72 0.72 18.00
72 1.875 121.440 1.500 122.940 3.90 3.30 3.60 0.72 0.72 18.00
73 1.900 121.665 1.500 123.165 3.90 3.30 3.60 0.72 0.72 18.00
Total Quantity 1767.07 Cum
Details for Chute Drain on D/S of BUND-1
EARTH WORK EXCAVATION:

1). Cross sectional Area at Transition starting point 0.855 Sqm.


=
2). Cross sectional Area at Transition ending point 0.583 Sqm.
=
CC M15 GRADE CONCRE WITH 40 MSA:

3). Cross sectional Area at Transition starting point = 0.585 Sqm.

4). Cross sectional Area at Transition ending point = 0.403 Sqm.

5). Transition length = 0.500 Rmt.

0.45 1.50 0.45


0.23
1.329 TW of Bed
2:1 2:1 0.409 BW of Bed
0.07 0.200 Bed Area
0.30 0.072 Sides Area
0.23 0.313 Lugs Area
All Dimensions in m 0.409 0.585 Total Area

0.30 0.90 0.30


0.23 0.950 TW of Bed
0.490 BW of Bed
1:1 1:1 0.166 Bed Area
0.07 0.046 Sides Area
0.30 0.191 Lugs Area
0.23 0.403 Total Area
0.490
DETAILED ESTIMATE OF CHUTE DRAIN @ EVERY 45 m INTERVAL ON D/S OF BUND -1

Height Slope length of Chute Drain Earth work Excavation CC M15 Quantity
Rock of Bund
Chainag Stripped
S.No. Toe Top above
e Level Length Quantity Quantity
level rock toe Details Details Details
in m in m in Cum in Cum

1 2 5 6 7 8

1 0.000

2 0.045 124.860 126.360 3.14 (3.14x2.236) 7.02 0.5X(0.855+0.583)/2+(7.02-0.5)X0.583 4.16 0.5X(0.585+0.403)/2+(7.02-0.5)X0.403 2.87

3 0.090 119.778 121.322 8.18 (8.18x2.236) 18.29 0.5X(0.855+0.583)/2+(18.29-0.5)X0.583 10.73 0.5X(0.585+0.403)/2+(18.29-0.5)X0.403 7.42

4 0.135 115.885 118.208 11.29 (11.29x2.236) 25.25 0.5X(0.855+0.583)/2+(25.25-0.5)X0.583 14.79 0.5X(0.585+0.403)/2+(25.25-0.5)X0.403 10.22

5 0.180 112.775 115.720 13.78 (13.78x2.236) 30.81 0.5X(0.855+0.583)/2+(30.81-0.5)X0.583 18.03 0.5X(0.585+0.403)/2+(30.81-0.5)X0.403 12.46

6 0.200 112.350 115.380 14.12 (14.12x2.236) 31.57 0.5X(0.855+0.583)/2+(31.57-0.5)X0.583 18.47 0.5X(0.585+0.403)/2+(31.57-0.5)X0.403 12.77

7 0.352 109.240 112.892 16.61 (16.61x2.236) 37.14 0.5X(0.855+0.583)/2+(37.14-0.5)X0.583 21.72 0.5X(0.585+0.403)/2+(37.14-0.5)X0.403 15.01

8 0.377 109.310 112.948 16.55 (16.55x2.236) 37.01 0.5X(0.855+0.583)/2+(37.01-0.5)X0.583 21.64 0.5X(0.585+0.403)/2+(37.01-0.5)X0.403 14.96

9 0.400 108.810 112.548 16.95 (16.95x2.236) 37.90 0.5X(0.855+0.583)/2+(37.9-0.5)X0.583 22.16 0.5X(0.585+0.403)/2+(37.9-0.5)X0.403 15.32

10 0.445 110.325 113.760 15.74 (15.74x2.236) 35.19 0.5X(0.855+0.583)/2+(35.19-0.5)X0.583 20.58 0.5X(0.585+0.403)/2+(35.19-0.5)X0.403 14.23

11 0.490 111.140 114.412 15.09 (15.09x2.236) 33.74 0.5X(0.855+0.583)/2+(33.74-0.5)X0.583 19.74 0.5X(0.585+0.403)/2+(33.74-0.5)X0.403 13.64

12 0.535 112.830 115.764 13.74 (13.74x2.236) 30.71 0.5X(0.855+0.583)/2+(30.71-0.5)X0.583 17.97 0.5X(0.585+0.403)/2+(30.71-0.5)X0.403 12.42

13 0.580 114.960 117.468 12.03 (12.03x2.236) 26.90 0.5X(0.855+0.583)/2+(26.9-0.5)X0.583 15.75 0.5X(0.585+0.403)/2+(26.9-0.5)X0.403 10.89

14 0.625 116.840 118.972 10.53 (10.53x2.236) 23.54 0.5X(0.855+0.583)/2+(23.54-0.5)X0.583 13.79 0.5X(0.585+0.403)/2+(23.54-0.5)X0.403 9.53

15 0.670 118.785 120.528 8.97 (8.97x2.236) 20.06 0.5X(0.855+0.583)/2+(20.06-0.5)X0.583 11.76 0.5X(0.585+0.403)/2+(20.06-0.5)X0.403 8.13

16 0.715 122.390 123.890 5.61 (5.61x2.236) 12.54 0.5X(0.855+0.583)/2+(12.54-0.5)X0.583 7.38 0.5X(0.585+0.403)/2+(12.54-0.5)X0.403 5.10

17 0.760 127.370 128.870 0.63 (0.63x2.236) 1.41 0.5X(0.855+0.583)/2+(1.41-0.5)X0.583 0.89 0.5X(0.585+0.403)/2+(1.41-0.5)X0.403 0.61

18 0.805 126.120 127.620 1.88 (1.88x2.236) 4.20 0.5X(0.855+0.583)/2+(4.2-0.5)X0.583 2.52 0.5X(0.585+0.403)/2+(4.2-0.5)X0.403 1.74
Height Slope length of Chute Drain Earth work Excavation CC M15 Quantity
Rock of Bund
Chainag Stripped
S.No. Toe Top above
e Level Length Quantity Quantity
level rock toe Details Details Details
in m in m in Cum in Cum

19 0.850 123.460 124.960 4.54 (4.54x2.236) 10.15 0.5X(0.855+0.583)/2+(10.15-0.5)X0.583 5.99 0.5X(0.585+0.403)/2+(10.15-0.5)X0.403 4.14

20 0.895 121.960 123.460 6.04 (6.04x2.236) 13.51 0.5X(0.855+0.583)/2+(13.51-0.5)X0.583 7.94 0.5X(0.585+0.403)/2+(13.51-0.5)X0.403 5.49

21 0.940 119.080 120.764 8.74 (8.74x2.236) 19.53 0.5X(0.855+0.583)/2+(19.53-0.5)X0.583 11.45 0.5X(0.585+0.403)/2+(19.53-0.5)X0.403 7.92

22 0.985 117.635 119.608 9.89 (9.89x2.236) 22.12 0.5X(0.855+0.583)/2+(22.12-0.5)X0.583 12.96 0.5X(0.585+0.403)/2+(22.12-0.5)X0.403 8.96

23 1.030 116.940 119.052 10.45 (10.45x2.236) 23.36 0.5X(0.855+0.583)/2+(23.36-0.5)X0.583 13.69 0.5X(0.585+0.403)/2+(23.36-0.5)X0.403 9.46

24 1.075 117.190 119.252 10.25 (10.25x2.236) 22.91 0.5X(0.855+0.583)/2+(22.91-0.5)X0.583 13.42 0.5X(0.585+0.403)/2+(22.91-0.5)X0.403 9.28

25 1.120 117.440 119.452 10.05 (10.05x2.236) 22.47 0.5X(0.855+0.583)/2+(22.47-0.5)X0.583 13.17 0.5X(0.585+0.403)/2+(22.47-0.5)X0.403 9.10

26 1.165 117.750 119.700 9.80 (9.8x2.236) 21.91 0.5X(0.855+0.583)/2+(21.91-0.5)X0.583 12.84 0.5X(0.585+0.403)/2+(21.91-0.5)X0.403 8.88

27 1.210 118.035 119.928 9.57 (9.57x2.236) 21.40 0.5X(0.855+0.583)/2+(21.4-0.5)X0.583 12.54 0.5X(0.585+0.403)/2+(21.4-0.5)X0.403 8.67

28 1.255 118.170 120.036 9.46 (9.46x2.236) 21.16 0.5X(0.855+0.583)/2+(21.16-0.5)X0.583 12.40 0.5X(0.585+0.403)/2+(21.16-0.5)X0.403 8.57

29 1.300 118.115 119.992 9.51 (9.51x2.236) 21.26 0.5X(0.855+0.583)/2+(21.26-0.5)X0.583 12.46 0.5X(0.585+0.403)/2+(21.26-0.5)X0.403 8.61

30 1.345 117.073 119.158 10.34 (10.34x2.236) 23.12 0.5X(0.855+0.583)/2+(23.12-0.5)X0.583 13.55 0.5X(0.585+0.403)/2+(23.12-0.5)X0.403 9.36

31 1.390 116.898 119.018 10.48 (10.48x2.236) 23.44 0.5X(0.855+0.583)/2+(23.44-0.5)X0.583 13.73 0.5X(0.585+0.403)/2+(23.44-0.5)X0.403 9.49

32 1.435 117.723 119.678 9.82 (9.82x2.236) 21.96 0.5X(0.855+0.583)/2+(21.96-0.5)X0.583 12.87 0.5X(0.585+0.403)/2+(21.96-0.5)X0.403 8.90

33 1.480 118.485 120.288 9.21 (9.21x2.236) 20.60 0.5X(0.855+0.583)/2+(20.6-0.5)X0.583 12.08 0.5X(0.585+0.403)/2+(20.6-0.5)X0.403 8.35

34 1.525 118.755 120.504 9.00 (9x2.236) 20.12 0.5X(0.855+0.583)/2+(20.12-0.5)X0.583 11.80 0.5X(0.585+0.403)/2+(20.12-0.5)X0.403 8.15

35 1.570 119.040 120.732 8.77 (8.77x2.236) 19.61 0.5X(0.855+0.583)/2+(19.61-0.5)X0.583 11.50 0.5X(0.585+0.403)/2+(19.61-0.5)X0.403 7.95

36 1.615 119.500 121.100 8.40 (8.4x2.236) 18.78 0.5X(0.855+0.583)/2+(18.78-0.5)X0.583 11.02 0.5X(0.585+0.403)/2+(18.78-0.5)X0.403 7.61

37 1.660 119.750 121.300 8.20 (8.2x2.236) 18.34 0.5X(0.855+0.583)/2+(18.34-0.5)X0.583 10.76 0.5X(0.585+0.403)/2+(18.34-0.5)X0.403 7.44

38 1.705 120.240 121.740 7.76 (7.76x2.236) 17.35 0.5X(0.855+0.583)/2+(17.35-0.5)X0.583 10.18 0.5X(0.585+0.403)/2+(17.35-0.5)X0.403 7.04
Height Slope length of Chute Drain Earth work Excavation CC M15 Quantity
Rock of Bund
Chainag Stripped
S.No. Toe Top above
e Level Length Quantity Quantity
level rock toe Details Details Details
in m in m in Cum in Cum

39 1.750 120.640 122.140 7.36 (7.36x2.236) 16.46 0.5X(0.855+0.583)/2+(16.46-0.5)X0.583 9.66 0.5X(0.585+0.403)/2+(16.46-0.5)X0.403 6.68

40 1.795 120.645 122.145 7.36 (7.36x2.236) 16.45 0.5X(0.855+0.583)/2+(16.45-0.5)X0.583 9.66 0.5X(0.585+0.403)/2+(16.45-0.5)X0.403 6.67

41 1.840 121.115 122.615 6.89 (6.89x2.236) 15.39 0.5X(0.855+0.583)/2+(15.39-0.5)X0.583 9.04 0.5X(0.585+0.403)/2+(15.39-0.5)X0.403 6.25

42 1.885 121.553 123.053 6.45 (6.45x2.236) 14.42 0.5X(0.855+0.583)/2+(14.42-0.5)X0.583 8.47 0.5X(0.585+0.403)/2+(14.42-0.5)X0.403 5.86

43 1.900 122.000 123.500 6.00 (6x2.236) 13.42 0.5X(0.855+0.583)/2+(13.42-0.5)X0.583 7.89 0.5X(0.585+0.403)/2+(13.42-0.5)X0.403 5.45

Total Total Quantity 523.15 Total Quantity 361.60

Longitudinal Chute Drain

Length = 1.748 Km
Cross sectional Area at EWE= 0.583 Sqm

Cross sectional Area Concrete= 0.403 Sqm

EWE Quanity 1019.084 Cum

Concrete Quanity- M15-40 MSA 704.444 Cum

Total EWE Quantity 1019.084+523.15 1542.23 Cum

Total Concrete Quantity 704.444+361.6 1066.04 Cum


Formation of Mallamadugu Reservoir
BUND-1
Details Estimate of D/S Turfing
Rock Top
Length Stripped Height of Slope length of Turfing Avg
Slno Chiange Level+1 meter Area (Sqm) Remarks
(M) Level Turfing Length
protection Details Length in m
1 0.000 0.00
2 0.025 25 126.450 128.950 0.550 (0.55x2.236) 1.23 0.62 15.38
3 0.050 25 123.270 125.770 3.730 (3.73x2.236) 8.34 4.79 119.63
4 0.075 25 120.705 123.205 6.295 (6.3x2.236) 14.08 11.21 280.25
5 0.100 25 118.850 121.580 7.920 (7.92x2.236)+5 22.71 18.40 459.88
6 0.125 25 116.450 119.660 9.840 (9.84x2.236)+5 27.00 24.86 621.38
7 0.150 25 115.320 118.756 10.744 (10.74x2.236)+5 29.02 28.01 700.25
8 0.175 25 113.200 117.060 12.440 (12.44x2.236)+5 32.82 30.92 773.00
9 0.200 25 112.775 116.720 12.780 (12.78x2.236)+5 33.58 33.20 830.00

10 0.352 109.240 113.892 15.608 (15.61x2.236)+5 39.90 36.74


11 0.377 25 109.310 113.948 15.552 (15.55x2.236)+5 39.77 39.84 995.88
12 0.400 23 108.810 113.548 15.952 (15.95x2.236)+5 40.67 40.22 925.06
13 0.425 25 110.220 114.676 14.824 (14.82x2.236)+5 38.15 39.41 985.25
14 0.450 25 110.430 114.844 14.656 (14.66x2.236)+5 37.77 37.96 949.00
15 0.475 25 110.800 115.140 14.360 (14.36x2.236)+5 37.11 37.44 936.00
16 0.500 25 111.480 115.684 13.816 (13.82x2.236)+5 35.89 36.50 912.50
17 0.525 25 112.400 116.420 13.080 (13.08x2.236)+5 34.25 35.07 876.75
18 0.550 25 113.260 117.108 12.392 (12.39x2.236)+5 32.71 33.48 837.00
19 0.575 25 114.440 118.052 11.448 (11.45x2.236)+5 30.60 31.66 791.38
20 0.600 25 115.480 118.884 10.616 (10.62x2.236)+5 28.74 29.67 741.75
21 0.625 25 116.840 119.972 9.528 (9.53x2.236)+5 26.30 27.52 688.00
22 0.650 25 118.040 120.932 8.568 (8.57x2.236)+5 24.16 25.23 630.75
23 0.675 25 119.530 122.124 7.376 (7.38x2.236)+5 21.49 22.83 570.63
24 0.700 25 121.450 123.950 5.550 (5.55x2.236) 12.41 16.95 423.75
25 0.725 25 123.330 125.830 3.670 (3.67x2.236) 8.21 10.31 257.75
26 0.750 25 126.340 128.840 0.660 (0.66x2.236) 1.48 4.85 121.13
27 0.775 25 128.400 130.900 -1.400 (-1.4x2.236) -3.13 -0.83 -20.63
28 0.800 25 127.190 129.690 -0.190 (-0.19x2.236) -0.42 -1.78 -44.38
29 0.825 25 125.050 127.550 1.950 (1.95x2.236) 4.36 1.97 49.25
30 0.850 25 123.460 125.960 3.540 (3.54x2.236) 7.92 6.14 153.50
31 0.875 25 121.960 124.460 5.040 (5.04x2.236) 11.27 9.60 239.88
32 0.900 25 121.960 124.460 5.040 (5.04x2.236) 11.27 11.27 281.75
33 0.925 25 119.460 122.068 7.432 (7.43x2.236)+5 21.62 16.45 411.13
34 0.950 25 118.700 121.460 8.040 (8.04x2.236)+5 22.98 22.30 557.50
35 0.975 25 117.920 120.836 8.664 (8.66x2.236)+5 24.37 23.68 591.88
36 1.000 25 117.350 120.380 9.120 (9.12x2.236)+5 25.39 24.88 622.00
37 1.025 25 116.960 120.068 9.432 (9.43x2.236)+5 26.09 25.74 643.50
38 1.050 25 116.920 120.036 9.464 (9.46x2.236)+5 26.16 26.13 653.12
39 1.075 25 117.190 120.252 9.248 (9.25x2.236)+5 25.68 25.92 648.00
40 1.100 25 117.330 120.364 9.136 (9.14x2.236)+5 25.43 25.56 638.87
41 1.125 25 117.550 120.540 8.960 (8.96x2.236)+5 25.03 25.23 630.75
42 1.150 25 117.660 120.628 8.872 (8.87x2.236)+5 24.84 24.94 623.37
43 1.175 25 117.840 120.772 8.728 (8.73x2.236)+5 24.52 24.68 617.00
44 1.200 25 117.970 120.876 8.624 (8.62x2.236)+5 24.28 24.40 610.00
45 1.225 25 118.100 120.980 8.520 (8.52x2.236)+5 24.05 24.17 604.12
46 1.250 25 118.140 121.012 8.488 (8.49x2.236)+5 23.98 24.02 600.37
47 1.275 25 118.200 121.060 8.440 (8.44x2.236)+5 23.87 23.93 598.12
48 1.300 25 118.115 120.992 8.508 (8.51x2.236)+5 24.02 23.95 598.62
49 1.325 25 117.970 120.876 8.624 (8.62x2.236)+5 24.28 24.15 603.75
50 1.350 25 116.175 119.440 10.060 (10.06x2.236)+5 27.49 25.89 647.12
51 1.375 25 116.640 119.812 9.688 (9.69x2.236)+5 26.66 27.08 676.87
52 1.400 25 117.155 120.224 9.276 (9.28x2.236)+5 25.74 26.20 655.00
53 1.425 25 117.635 120.608 8.892 (8.89x2.236)+5 24.88 25.31 632.75
54 1.450 25 117.810 120.748 8.752 (8.75x2.236)+5 24.57 24.73 618.12
55 1.475 25 118.315 121.152 8.348 (8.35x2.236)+5 23.67 24.12 603.00
56 1.500 25 118.655 121.424 8.076 (8.08x2.236)+5 23.06 23.37 584.12
57 1.525 25 118.755 121.504 7.996 (8x2.236)+5 22.88 22.97 574.25
58 1.550 25 118.920 121.636 7.864 (7.86x2.236)+5 22.58 22.73 568.25
59 1.575 25 119.160 121.828 7.672 (7.67x2.236)+5 22.15 22.37 559.12
60 1.600 25 119.415 122.032 7.468 (7.47x2.236)+5 21.70 21.93 548.12
61 1.625 25 119.585 122.168 7.332 (7.33x2.236)+5 21.39 21.55 538.62
62 1.650 25 119.740 122.292 7.208 (7.21x2.236)+5 21.12 21.26 531.37
63 1.675 25 119.760 122.308 7.192 (7.19x2.236)+5 21.08 21.10 527.50
64 1.700 25 120.160 122.660 6.840 (6.84x2.236)+5 20.29 20.69 517.12
65 1.725 25 120.320 122.820 6.680 (6.68x2.236)+5 19.94 20.12 502.87
66 1.750 25 120.640 123.140 6.360 (6.36x2.236)+5 19.22 19.58 489.50
67 1.775 25 120.570 123.070 6.430 (6.43x2.236)+5 19.38 19.30 482.50
68 1.800 25 120.720 123.220 6.280 (6.28x2.236)+5 19.04 19.21 480.25
69 1.825 25 120.750 123.250 6.250 (6.25x2.236)+5 18.98 19.01 475.25
70 1.850 25 121.480 123.980 5.520 (5.52x2.236) 12.34 15.66 391.50
71 1.875 25 121.440 123.940 5.560 (5.56x2.236) 12.43 12.39 309.62
72 1.900 25 121.665 124.165 5.335 (5.33x2.236) 11.93 12.18 304.50
Total Quantity 38571.14 Cum
Formation of Mallamadugu Reservoir
BUND-1
Detail Estimate U/S Toe Wall
Rip Rap
4.605
3.784
2.963
0.675
0.875
1.075

0.6
1 in 1 0.722 2.5 in 1
0.843

200mm thk Sand Above 13.5 m Height 200 mm thk Metal

Rip Rap
4.085
3.355
2.625
0.675
0.875
1.075

0.6
1 in 1 0.730 2 in 1
0.860

200mm thk Sand Below 13.5 m Height 200 mm thk Metal

EWE of Toe Wall


Stripped Height of Bottom Avg Mean
Slno Chainge Top Width Depth Area Quantity
Level Bund Width Width Area
1 0.000 0.000 0.000 0.000 0 0 1.075 0
2 0.025 126.450 3.050 0.860 4.085 2.473 1.075 2.658 1.329 33.225
3 0.050 123.270 6.230 0.860 4.085 2.473 1.075 2.658 2.658 66.450
4 0.075 120.705 8.795 0.860 4.085 2.473 1.075 2.658 2.658 66.450
5 0.100 118.850 10.650 0.860 4.085 2.473 1.075 2.658 2.658 66.450
6 0.125 116.450 13.050 0.860 4.085 2.473 1.075 2.658 2.658 66.450
7 0.150 115.320 14.180 0.843 4.605 2.724 1.075 2.928 2.793 69.825
8 0.175 113.200 16.300 0.843 4.605 2.724 1.075 2.928 2.928 73.200
9 0.180 112.775 16.725 0.843 4.605 2.724 1.075 2.928 2.928 14.640
10 0.200 112.350 17.150 0.843 4.605 2.724 1.075 2.928 2.928 58.560

11 0.352 109.240 20.260 0.843 4.605 2.724 1.075 2.928 2.928


12 0.372 109.310 20.190 0.843 4.605 2.724 1.075 2.928 2.928 58.560
13 0.400 108.810 20.690 0.843 4.605 2.724 1.075 2.928 2.928 81.984
14 0.425 110.220 19.280 0.843 4.605 2.724 1.075 2.928 2.928 73.200
15 0.450 110.430 19.070 0.843 4.605 2.724 1.075 2.928 2.928 73.200
16 0.475 110.800 18.700 0.843 4.605 2.724 1.075 2.928 2.928 73.200
17 0.500 111.480 18.020 0.843 4.605 2.724 1.075 2.928 2.928 73.200
18 0.525 112.400 17.100 0.843 4.605 2.724 1.075 2.928 2.928 73.200
19 0.550 113.260 16.240 0.843 4.605 2.724 1.075 2.928 2.928 73.200
20 0.575 114.440 15.060 0.843 4.605 2.724 1.075 2.928 2.928 73.200
21 0.600 115.480 14.020 0.843 4.605 2.724 1.075 2.928 2.928 73.200
22 0.625 116.840 12.660 0.860 4.085 2.473 1.075 2.658 2.793 69.825
23 0.650 118.040 11.460 0.860 4.085 2.473 1.075 2.658 2.658 66.450
24 0.675 119.530 9.970 0.860 4.085 2.473 1.075 2.658 2.658 66.450
25 0.700 121.450 8.050 0.860 4.085 2.473 1.075 2.658 2.658 66.450
26 0.725 123.330 6.170 0.860 4.085 2.473 1.075 2.658 2.658 66.450
27 0.750 126.340 3.160 0.860 4.085 2.473 1.075 2.658 2.658 66.450
28 0.775 128.400 1.100 0.860 4.085 2.473 1.075 2.658 2.658 66.450
29 0.800 127.190 2.310 0.860 4.085 2.473 1.075 2.658 2.658 66.450
30 0.825 125.050 4.450 0.860 4.085 2.473 1.075 2.658 2.658 66.450
31 0.850 123.460 6.040 0.860 4.085 2.473 1.075 2.658 2.658 66.450
32 0.875 121.960 7.540 0.860 4.085 2.473 1.075 2.658 2.658 66.450
33 0.900 121.960 7.540 0.860 4.085 2.473 1.075 2.658 2.658 66.450
34 0.925 119.460 10.040 0.860 4.085 2.473 1.075 2.658 2.658 66.450
35 0.950 118.700 10.800 0.860 4.085 2.473 1.075 2.658 2.658 66.450
36 0.975 117.920 11.580 0.860 4.085 2.473 1.075 2.658 2.658 66.450
37 1.000 117.350 12.150 0.860 4.085 2.473 1.075 2.658 2.658 66.450
38 1.025 116.960 12.540 0.860 4.085 2.473 1.075 2.658 2.658 66.450
39 1.050 116.920 12.580 0.860 4.085 2.473 1.075 2.658 2.658 66.450
40 1.075 117.190 12.310 0.860 4.085 2.473 1.075 2.658 2.658 66.450
41 1.100 117.330 12.170 0.860 4.085 2.473 1.075 2.658 2.658 66.450
42 1.125 117.550 11.950 0.860 4.085 2.473 1.075 2.658 2.658 66.450
43 1.150 117.660 11.840 0.860 4.085 2.473 1.075 2.658 2.658 66.450
44 1.175 117.840 11.660 0.860 4.085 2.473 1.075 2.658 2.658 66.450
45 1.200 117.970 11.530 0.860 4.085 2.473 1.075 2.658 2.658 66.450
46 1.225 118.100 11.400 0.860 4.085 2.473 1.075 2.658 2.658 66.450
47 1.250 118.140 11.360 0.860 4.085 2.473 1.075 2.658 2.658 66.450
48 1.275 118.200 11.300 0.860 4.085 2.473 1.075 2.658 2.658 66.450
49 1.300 118.115 11.385 0.860 4.085 2.473 1.075 2.658 2.658 66.450
50 1.325 117.970 11.530 0.860 4.085 2.473 1.075 2.658 2.658 66.450
51 1.350 116.175 13.325 0.860 4.085 2.473 1.075 2.658 2.658 66.450
52 1.375 116.640 12.860 0.860 4.085 2.473 1.075 2.658 2.658 66.450
53 1.400 117.155 12.345 0.860 4.085 2.473 1.075 2.658 2.658 66.450
54 1.425 117.635 11.865 0.860 4.085 2.473 1.075 2.658 2.658 66.450
55 1.450 117.810 11.690 0.860 4.085 2.473 1.075 2.658 2.658 66.450
56 1.475 118.315 11.185 0.860 4.085 2.473 1.075 2.658 2.658 66.450
57 1.500 118.655 10.845 0.860 4.085 2.473 1.075 2.658 2.658 66.450
58 1.525 118.755 10.745 0.860 4.085 2.473 1.075 2.658 2.658 66.450
59 1.550 118.920 10.580 0.860 4.085 2.473 1.075 2.658 2.658 66.450
60 1.575 119.160 10.340 0.860 4.085 2.473 1.075 2.658 2.658 66.450
61 1.600 119.415 10.085 0.860 4.085 2.473 1.075 2.658 2.658 66.450
62 1.625 119.585 9.915 0.860 4.085 2.473 1.075 2.658 2.658 66.450
63 1.650 119.740 9.760 0.860 4.085 2.473 1.075 2.658 2.658 66.450
64 1.675 119.760 9.740 0.860 4.085 2.473 1.075 2.658 2.658 66.450
65 1.700 120.160 9.340 0.860 4.085 2.473 1.075 2.658 2.658 66.450
66 1.725 120.320 9.180 0.860 4.085 2.473 1.075 2.658 2.658 66.450
67 1.750 120.640 8.860 0.860 4.085 2.473 1.075 2.658 2.658 66.450
68 1.775 120.570 8.930 0.860 4.085 2.473 1.075 2.658 2.658 66.450
69 1.800 120.720 8.780 0.860 4.085 2.473 1.075 2.658 2.658 66.450
70 1.825 120.750 8.750 0.860 4.085 2.473 1.075 2.658 2.658 66.450
71 1.850 121.480 8.020 0.860 4.085 2.473 1.075 2.658 2.658 66.450
72 1.875 121.440 8.060 0.860 4.085 2.473 1.075 2.658 2.658 66.450
73 1.900 121.665 7.835 0.860 4.085 2.473 1.075 2.658 2.658 66.450
Total Quantity 4700.169
Rip rap
Stripped Height of Bottom Avg Mean
Slno Chainge Top Width Depth Area Quantity
Level Bund Width Width Area
1 0.000 0.000 0.000 0.000 0 0 0 0
2 0.025 126.450 3.050 0.600 2.625 1.613 0.675 1.089 0.545 13.625
3 0.050 123.270 6.230 0.600 2.625 1.613 0.675 1.089 1.089 27.225
4 0.075 120.705 8.795 0.600 2.625 1.613 0.675 1.089 1.089 27.225
5 0.100 118.850 10.650 0.600 2.625 1.613 0.675 1.089 1.089 27.225
6 0.125 116.450 13.050 0.600 2.625 1.613 0.675 1.089 1.089 27.225
7 0.150 115.320 14.180 0.600 2.963 1.782 0.675 1.203 1.146 28.650
8 0.175 113.200 16.300 0.600 2.963 1.782 0.675 1.203 1.203 30.075
9 0.180 112.775 16.725 0.600 2.963 1.782 0.675 1.203 1.203 6.015
10 0.200 112.350 17.150 0.600 2.963 1.782 0.675 1.203 1.203 24.060

11 0.352 109.240 20.260 0.600 2.963 1.782 0.675 1.203 1.203


12 0.372 109.310 20.190 0.600 2.963 1.782 0.675 1.203 1.203 24.060
13 0.400 108.810 20.690 0.600 2.963 1.782 0.675 1.203 1.203 33.684
14 0.425 110.220 19.280 0.600 2.963 1.782 0.675 1.203 1.203 30.075
15 0.450 110.430 19.070 0.600 2.963 1.782 0.675 1.203 1.203 30.075
16 0.475 110.800 18.700 0.600 2.963 1.782 0.675 1.203 1.203 30.075
17 0.500 111.480 18.020 0.600 2.963 1.782 0.675 1.203 1.203 30.075
18 0.525 112.400 17.100 0.600 2.963 1.782 0.675 1.203 1.203 30.075
19 0.550 113.260 16.240 0.600 2.963 1.782 0.675 1.203 1.203 30.075
20 0.575 114.440 15.060 0.600 2.963 1.782 0.675 1.203 1.203 30.075
21 0.600 115.480 14.020 0.600 2.963 1.782 0.675 1.203 1.203 30.075
22 0.625 116.840 12.660 0.600 2.625 1.613 0.675 1.089 1.146 28.650
23 0.650 118.040 11.460 0.600 2.625 1.613 0.675 1.089 1.089 27.225
24 0.675 119.530 9.970 0.600 2.625 1.613 0.675 1.089 1.089 27.225
25 0.700 121.450 8.050 0.600 2.625 1.613 0.675 1.089 1.089 27.225
26 0.725 123.330 6.170 0.600 2.625 1.613 0.675 1.089 1.089 27.225
27 0.750 126.340 3.160 0.600 2.625 1.613 0.675 1.089 1.089 27.225
28 0.775 128.400 1.100 0.600 2.625 1.613 0.675 1.089 1.089 27.225
29 0.800 127.190 2.310 0.600 2.625 1.613 0.675 1.089 1.089 27.225
30 0.825 125.050 4.450 0.600 2.625 1.613 0.675 1.089 1.089 27.225
31 0.850 123.460 6.040 0.600 2.625 1.613 0.675 1.089 1.089 27.225
32 0.875 121.960 7.540 0.600 2.625 1.613 0.675 1.089 1.089 27.225
33 0.900 121.960 7.540 0.600 2.625 1.613 0.675 1.089 1.089 27.225
34 0.925 119.460 10.040 0.600 2.625 1.613 0.675 1.089 1.089 27.225
35 0.950 118.700 10.800 0.600 2.625 1.613 0.675 1.089 1.089 27.225
36 0.975 117.920 11.580 0.600 2.625 1.613 0.675 1.089 1.089 27.225
37 1.000 117.350 12.150 0.600 2.625 1.613 0.675 1.089 1.089 27.225
38 1.025 116.960 12.540 0.600 2.625 1.613 0.675 1.089 1.089 27.225
39 1.050 116.920 12.580 0.600 2.625 1.613 0.675 1.089 1.089 27.225
40 1.075 117.190 12.310 0.600 2.625 1.613 0.675 1.089 1.089 27.225
41 1.100 117.330 12.170 0.600 2.625 1.613 0.675 1.089 1.089 27.225
42 1.125 117.550 11.950 0.600 2.625 1.613 0.675 1.089 1.089 27.225
43 1.150 117.660 11.840 0.600 2.625 1.613 0.675 1.089 1.089 27.225
44 1.175 117.840 11.660 0.600 2.625 1.613 0.675 1.089 1.089 27.225
45 1.200 117.970 11.530 0.600 2.625 1.613 0.675 1.089 1.089 27.225
46 1.225 118.100 11.400 0.600 2.625 1.613 0.675 1.089 1.089 27.225
47 1.250 118.140 11.360 0.600 2.625 1.613 0.675 1.089 1.089 27.225
48 1.275 118.200 11.300 0.600 2.625 1.613 0.675 1.089 1.089 27.225
49 1.300 118.115 11.385 0.600 2.625 1.613 0.675 1.089 1.089 27.225
50 1.325 117.970 11.530 0.600 2.625 1.613 0.675 1.089 1.089 27.225
51 1.350 116.175 13.325 0.600 2.625 1.613 0.675 1.089 1.089 27.225
52 1.375 116.640 12.860 0.600 2.625 1.613 0.675 1.089 1.089 27.225
53 1.400 117.155 12.345 0.600 2.625 1.613 0.675 1.089 1.089 27.225
54 1.425 117.635 11.865 0.600 2.625 1.613 0.675 1.089 1.089 27.225
55 1.450 117.810 11.690 0.600 2.625 1.613 0.675 1.089 1.089 27.225
56 1.475 118.315 11.185 0.600 2.625 1.613 0.675 1.089 1.089 27.225
57 1.500 118.655 10.845 0.600 2.625 1.613 0.675 1.089 1.089 27.225
58 1.525 118.755 10.745 0.600 2.625 1.613 0.675 1.089 1.089 27.225
59 1.550 118.920 10.580 0.600 2.625 1.613 0.675 1.089 1.089 27.225
60 1.575 119.160 10.340 0.600 2.625 1.613 0.675 1.089 1.089 27.225
61 1.600 119.415 10.085 0.600 2.625 1.613 0.675 1.089 1.089 27.225
62 1.625 119.585 9.915 0.600 2.625 1.613 0.675 1.089 1.089 27.225
63 1.650 119.740 9.760 0.600 2.625 1.613 0.675 1.089 1.089 27.225
64 1.675 119.760 9.740 0.600 2.625 1.613 0.675 1.089 1.089 27.225
65 1.700 120.160 9.340 0.600 2.625 1.613 0.675 1.089 1.089 27.225
66 1.725 120.320 9.180 0.600 2.625 1.613 0.675 1.089 1.089 27.225
67 1.750 120.640 8.860 0.600 2.625 1.613 0.675 1.089 1.089 27.225
68 1.775 120.570 8.930 0.600 2.625 1.613 0.675 1.089 1.089 27.225
69 1.800 120.720 8.780 0.600 2.625 1.613 0.675 1.089 1.089 27.225
70 1.825 120.750 8.750 0.600 2.625 1.613 0.675 1.089 1.089 27.225
71 1.850 121.480 8.020 0.600 2.625 1.613 0.675 1.089 1.089 27.225
72 1.875 121.440 8.060 0.600 2.625 1.613 0.675 1.089 1.089 27.225
73 1.900 121.665 7.835 0.600 2.625 1.613 0.675 1.089 1.089 27.225
Total Quantity 1926.794
Metal Filters
Metal Filters including Rip rap
Stripped Height of Bottom Avg Mean
Slno Chainge Top Width Depth Area Quantity
Level Bund Width Width Area
1 0.000 0.000 0.000 0.000 0 0 0.875 0
2 0.025 126.450 3.050 0.730 3.355 2.043 0.875 1.788 0.894 22.350
3 0.050 123.270 6.230 0.730 3.355 2.043 0.875 1.788 1.788 44.700
4 0.075 120.705 8.795 0.730 3.355 2.043 0.875 1.788 1.788 44.700
5 0.100 118.850 10.650 0.730 3.355 2.043 0.875 1.788 1.788 44.700
6 0.125 116.450 13.050 0.730 3.355 2.043 0.875 1.788 1.788 44.700
7 0.150 115.320 14.180 0.722 3.784 2.253 0.875 1.971 1.88 47.000
8 0.175 113.200 16.300 0.722 3.784 2.253 0.875 1.971 1.971 49.275
9 0.180 112.775 16.725 0.722 3.784 2.253 0.875 1.971 1.971 9.855
10 0.200 112.350 17.150 0.722 3.784 2.253 0.875 1.971 1.971 39.420

11 0.352 109.240 20.260 0.722 3.784 2.253 0.875 1.971 1.971


12 0.372 109.310 20.190 0.722 3.784 2.253 0.875 1.971 1.971 39.420
13 0.400 108.810 20.690 0.722 3.784 2.253 0.875 1.971 1.971 55.188
14 0.425 110.220 19.280 0.722 3.784 2.253 0.875 1.971 1.971 49.275
15 0.450 110.430 19.070 0.722 3.784 2.253 0.875 1.971 1.971 49.275
16 0.475 110.800 18.700 0.722 3.784 2.253 0.875 1.971 1.971 49.275
17 0.500 111.480 18.020 0.722 3.784 2.253 0.875 1.971 1.971 49.275
18 0.525 112.400 17.100 0.722 3.784 2.253 0.875 1.971 1.971 49.275
19 0.550 113.260 16.240 0.722 3.784 2.253 0.875 1.971 1.971 49.275
20 0.575 114.440 15.060 0.722 3.784 2.253 0.875 1.971 1.971 49.275
21 0.600 115.480 14.020 0.722 3.784 2.253 0.875 1.971 1.971 49.275
22 0.625 116.840 12.660 0.730 3.355 2.043 0.875 1.788 1.88 47.000
23 0.650 118.040 11.460 0.730 3.355 2.043 0.875 1.788 1.788 44.700
24 0.675 119.530 9.970 0.730 3.355 2.043 0.875 1.788 1.788 44.700
25 0.700 121.450 8.050 0.730 3.355 2.043 0.875 1.788 1.788 44.700
26 0.725 123.330 6.170 0.730 3.355 2.043 0.875 1.788 1.788 44.700
27 0.750 126.340 3.160 0.730 3.355 2.043 0.875 1.788 1.788 44.700
28 0.775 128.400 1.100 0.730 3.355 2.043 0.875 1.788 1.788 44.700
29 0.800 127.190 2.310 0.730 3.355 2.043 0.875 1.788 1.788 44.700
30 0.825 125.050 4.450 0.730 3.355 2.043 0.875 1.788 1.788 44.700
31 0.850 123.460 6.040 0.730 3.355 2.043 0.875 1.788 1.788 44.700
32 0.875 121.960 7.540 0.730 3.355 2.043 0.875 1.788 1.788 44.700
33 0.900 121.960 7.540 0.730 3.355 2.043 0.875 1.788 1.788 44.700
34 0.925 119.460 10.040 0.730 3.355 2.043 0.875 1.788 1.788 44.700
35 0.950 118.700 10.800 0.730 3.355 2.043 0.875 1.788 1.788 44.700
36 0.975 117.920 11.580 0.730 3.355 2.043 0.875 1.788 1.788 44.700
37 1.000 117.350 12.150 0.730 3.355 2.043 0.875 1.788 1.788 44.700
38 1.025 116.960 12.540 0.730 3.355 2.043 0.875 1.788 1.788 44.700
39 1.050 116.920 12.580 0.730 3.355 2.043 0.875 1.788 1.788 44.700
40 1.075 117.190 12.310 0.730 3.355 2.043 0.875 1.788 1.788 44.700
41 1.100 117.330 12.170 0.730 3.355 2.043 0.875 1.788 1.788 44.700
42 1.125 117.550 11.950 0.730 3.355 2.043 0.875 1.788 1.788 44.700
43 1.150 117.660 11.840 0.730 3.355 2.043 0.875 1.788 1.788 44.700
44 1.175 117.840 11.660 0.730 3.355 2.043 0.875 1.788 1.788 44.700
45 1.200 117.970 11.530 0.730 3.355 2.043 0.875 1.788 1.788 44.700
46 1.225 118.100 11.400 0.730 3.355 2.043 0.875 1.788 1.788 44.700
47 1.250 118.140 11.360 0.730 3.355 2.043 0.875 1.788 1.788 44.700
48 1.275 118.200 11.300 0.730 3.355 2.043 0.875 1.788 1.788 44.700
49 1.300 118.115 11.385 0.730 3.355 2.043 0.875 1.788 1.788 44.700
50 1.325 117.970 11.530 0.730 3.355 2.043 0.875 1.788 1.788 44.700
51 1.350 116.175 13.325 0.730 3.355 2.043 0.875 1.788 1.788 44.700
52 1.375 116.640 12.860 0.730 3.355 2.043 0.875 1.788 1.788 44.700
53 1.400 117.155 12.345 0.730 3.355 2.043 0.875 1.788 1.788 44.700
54 1.425 117.635 11.865 0.730 3.355 2.043 0.875 1.788 1.788 44.700
55 1.450 117.810 11.690 0.730 3.355 2.043 0.875 1.788 1.788 44.700
56 1.475 118.315 11.185 0.730 3.355 2.043 0.875 1.788 1.788 44.700
57 1.500 118.655 10.845 0.730 3.355 2.043 0.875 1.788 1.788 44.700
58 1.525 118.755 10.745 0.730 3.355 2.043 0.875 1.788 1.788 44.700
59 1.550 118.920 10.580 0.730 3.355 2.043 0.875 1.788 1.788 44.700
60 1.575 119.160 10.340 0.730 3.355 2.043 0.875 1.788 1.788 44.700
61 1.600 119.415 10.085 0.730 3.355 2.043 0.875 1.788 1.788 44.700
62 1.625 119.585 9.915 0.730 3.355 2.043 0.875 1.788 1.788 44.700
63 1.650 119.740 9.760 0.730 3.355 2.043 0.875 1.788 1.788 44.700
64 1.675 119.760 9.740 0.730 3.355 2.043 0.875 1.788 1.788 44.700
65 1.700 120.160 9.340 0.730 3.355 2.043 0.875 1.788 1.788 44.700
66 1.725 120.320 9.180 0.730 3.355 2.043 0.875 1.788 1.788 44.700
67 1.750 120.640 8.860 0.730 3.355 2.043 0.875 1.788 1.788 44.700
68 1.775 120.570 8.930 0.730 3.355 2.043 0.875 1.788 1.788 44.700
69 1.800 120.720 8.780 0.730 3.355 2.043 0.875 1.788 1.788 44.700
70 1.825 120.750 8.750 0.730 3.355 2.043 0.875 1.788 1.788 44.700
71 1.850 121.480 8.020 0.730 3.355 2.043 0.875 1.788 1.788 44.700
72 1.875 121.440 8.060 0.730 3.355 2.043 0.875 1.788 1.788 44.700
73 1.900 121.665 7.835 0.730 3.355 2.043 0.875 1.788 1.788 44.700
Total Quantity Metal Filters including Rip Rap 3162.208
Deduct Rip Rap Quantity 1926.794
Total Quantity of Metal Filters 1235.414
Sand Filters
Sand Filters including Rip rap and Metal Filters
Stripped Height of Bottom Avg Mean
Slno Chainge Top Width Depth Area Quantity
Level Bund Width Width Area
1 0.000 0.000 0.000 0.000 0 0 1.075 0
2 0.025 126.450 3.050 0.860 4.085 2.473 1.075 2.658 1.329 33.225
3 0.050 123.270 6.230 0.860 4.085 2.473 1.075 2.658 2.658 66.450
4 0.075 120.705 8.795 0.860 4.085 2.473 1.075 2.658 2.658 66.450
5 0.100 118.850 10.650 0.860 4.085 2.473 1.075 2.658 2.658 66.450
6 0.125 116.450 13.050 0.860 4.085 2.473 1.075 2.658 2.658 66.450
7 0.150 115.320 14.180 0.843 4.605 2.724 1.075 2.928 2.793 69.825
8 0.175 113.200 16.300 0.843 4.605 2.724 1.075 2.928 2.928 73.200
9 0.180 112.775 16.725 0.843 4.605 2.724 1.075 2.928 2.928 14.640
10 0.200 112.350 17.150 0.843 4.605 2.724 1.075 2.928 2.928 58.560

11 0.352 109.240 20.260 0.843 4.605 2.724 1.075 2.928 2.928


12 0.372 109.310 20.190 0.843 4.605 2.724 1.075 2.928 2.928 58.560
13 0.400 108.810 20.690 0.843 4.605 2.724 1.075 2.928 2.928 81.984
14 0.425 110.220 19.280 0.843 4.605 2.724 1.075 2.928 2.928 73.200
15 0.450 110.430 19.070 0.843 4.605 2.724 1.075 2.928 2.928 73.200
16 0.475 110.800 18.700 0.843 4.605 2.724 1.075 2.928 2.928 73.200
17 0.500 111.480 18.020 0.843 4.605 2.724 1.075 2.928 2.928 73.200
18 0.525 112.400 17.100 0.843 4.605 2.724 1.075 2.928 2.928 73.200
19 0.550 113.260 16.240 0.843 4.605 2.724 1.075 2.928 2.928 73.200
20 0.575 114.440 15.060 0.843 4.605 2.724 1.075 2.928 2.928 73.200
21 0.600 115.480 14.020 0.843 4.605 2.724 1.075 2.928 2.928 73.200
22 0.625 116.840 12.660 0.860 4.085 2.473 1.075 2.658 2.793 69.825
23 0.650 118.040 11.460 0.860 4.085 2.473 1.075 2.658 2.658 66.450
24 0.675 119.530 9.970 0.860 4.085 2.473 1.075 2.658 2.658 66.450
25 0.700 121.450 8.050 0.860 4.085 2.473 1.075 2.658 2.658 66.450
26 0.725 123.330 6.170 0.860 4.085 2.473 1.075 2.658 2.658 66.450
27 0.750 126.340 3.160 0.860 4.085 2.473 1.075 2.658 2.658 66.450
28 0.775 128.400 1.100 0.860 4.085 2.473 1.075 2.658 2.658 66.450
29 0.800 127.190 2.310 0.860 4.085 2.473 1.075 2.658 2.658 66.450
30 0.825 125.050 4.450 0.860 4.085 2.473 1.075 2.658 2.658 66.450
31 0.850 123.460 6.040 0.860 4.085 2.473 1.075 2.658 2.658 66.450
32 0.875 121.960 7.540 0.860 4.085 2.473 1.075 2.658 2.658 66.450
33 0.900 121.960 7.540 0.860 4.085 2.473 1.075 2.658 2.658 66.450
34 0.925 119.460 10.040 0.860 4.085 2.473 1.075 2.658 2.658 66.450
35 0.950 118.700 10.800 0.860 4.085 2.473 1.075 2.658 2.658 66.450
36 0.975 117.920 11.580 0.860 4.085 2.473 1.075 2.658 2.658 66.450
37 1.000 117.350 12.150 0.860 4.085 2.473 1.075 2.658 2.658 66.450
38 1.025 116.960 12.540 0.860 4.085 2.473 1.075 2.658 2.658 66.450
39 1.050 116.920 12.580 0.860 4.085 2.473 1.075 2.658 2.658 66.450
40 1.075 117.190 12.310 0.860 4.085 2.473 1.075 2.658 2.658 66.450
41 1.100 117.330 12.170 0.860 4.085 2.473 1.075 2.658 2.658 66.450
42 1.125 117.550 11.950 0.860 4.085 2.473 1.075 2.658 2.658 66.450
43 1.150 117.660 11.840 0.860 4.085 2.473 1.075 2.658 2.658 66.450
44 1.175 117.840 11.660 0.860 4.085 2.473 1.075 2.658 2.658 66.450
45 1.200 117.970 11.530 0.860 4.085 2.473 1.075 2.658 2.658 66.450
46 1.225 118.100 11.400 0.860 4.085 2.473 1.075 2.658 2.658 66.450
47 1.250 118.140 11.360 0.860 4.085 2.473 1.075 2.658 2.658 66.450
48 1.275 118.200 11.300 0.860 4.085 2.473 1.075 2.658 2.658 66.450
49 1.300 118.115 11.385 0.860 4.085 2.473 1.075 2.658 2.658 66.450
50 1.325 117.970 11.530 0.860 4.085 2.473 1.075 2.658 2.658 66.450
51 1.350 116.175 13.325 0.860 4.085 2.473 1.075 2.658 2.658 66.450
52 1.375 116.640 12.860 0.860 4.085 2.473 1.075 2.658 2.658 66.450
53 1.400 117.155 12.345 0.860 4.085 2.473 1.075 2.658 2.658 66.450
54 1.425 117.635 11.865 0.860 4.085 2.473 1.075 2.658 2.658 66.450
55 1.450 117.810 11.690 0.860 4.085 2.473 1.075 2.658 2.658 66.450
56 1.475 118.315 11.185 0.860 4.085 2.473 1.075 2.658 2.658 66.450
57 1.500 118.655 10.845 0.860 4.085 2.473 1.075 2.658 2.658 66.450
58 1.525 118.755 10.745 0.860 4.085 2.473 1.075 2.658 2.658 66.450
59 1.550 118.920 10.580 0.860 4.085 2.473 1.075 2.658 2.658 66.450
60 1.575 119.160 10.340 0.860 4.085 2.473 1.075 2.658 2.658 66.450
61 1.600 119.415 10.085 0.860 4.085 2.473 1.075 2.658 2.658 66.450
62 1.625 119.585 9.915 0.860 4.085 2.473 1.075 2.658 2.658 66.450
63 1.650 119.740 9.760 0.860 4.085 2.473 1.075 2.658 2.658 66.450
64 1.675 119.760 9.740 0.860 4.085 2.473 1.075 2.658 2.658 66.450
65 1.700 120.160 9.340 0.860 4.085 2.473 1.075 2.658 2.658 66.450
66 1.725 120.320 9.180 0.860 4.085 2.473 1.075 2.658 2.658 66.450
67 1.750 120.640 8.860 0.860 4.085 2.473 1.075 2.658 2.658 66.450
68 1.775 120.570 8.930 0.860 4.085 2.473 1.075 2.658 2.658 66.450
69 1.800 120.720 8.780 0.860 4.085 2.473 1.075 2.658 2.658 66.450
70 1.825 120.750 8.750 0.860 4.085 2.473 1.075 2.658 2.658 66.450
71 1.850 121.480 8.020 0.860 4.085 2.473 1.075 2.658 2.658 66.450
72 1.875 121.440 8.060 0.860 4.085 2.473 1.075 2.658 2.658 66.450
73 1.900 121.665 7.835 0.860 4.085 2.473 1.075 2.658 2.658 66.450
Total Quantity Metal Filters including Rip Rap 4700.169
Deduct Rip Rap Quantity 1926.794
Deduct Metal Filters Quantity 1235.414
Total Quantity of Sand Filters 1537.961
Remarks
Cum
Remarks
Cum

Remarks
Cum
Cum
Cum
Remarks
Cum
Cum
Cum
Cum
Formation of Mallamadugu Reservoir
BUND-1
Detail Estimate D/S Toe Drain

0.5 M GL
2 in 1 1 in 1 300 mm Thk Rip Rap.
0.5 M 200 mm thk Metal
0.5 M 200 mm thk Sand
0.695
2 in1 0.825 1in1
0.955

D/S Toe Wall


Earthwork Excavation
Top wodth of Toe Wall at Stripped Level = 3.47 M
Bottom Width of Toe Wall = 0.955 M
Height = 1.2 M
3.47+0.955
Area of EWE X 1.2 = 2.66 Sqm
2

Area of Rip rap


Bottom Width of Toe Drain = 0.5 M
Bed Level of The Toe drain = (GL-0.5)
Top Width of the Lug = 0.5 M

300 MM thk Rip Rap


BED
Bottom Width of Rip rap = 0.695 M
Top Width 0.695+0.3X3 = 1.595 M
1.595+0.695
Area of Bed X 0.3 = 0.34 Sqm
2
R/S Slope= (sqrt(1X1+1X1) X 0.3) X0.2 = 0.08 Sqm
L/S Slope (sqrt(2X1+2X1) X 0.3) X0.5 = 0.34 Sqm
Lug
Top Width = 0.5 M
Bottom Width 0.5+0.3X1 = 0.8 M
0.8+0.5
Area of Lug X 0.3 = 0.2 Sqm
2
0.34+0.08+0.34+0.2 = 0.96 Sqm
Total Area of Rip Rap

200 mm Thk Metal


BED
Bottom Width = 0.825 M
Top Width 0.825+0.2X3 = 1.425 M
1.425+0.825
Area of Bed X 0.2 = 0.23 Sqm
2
R/S Slope= (sqrt(1X1+1X1) X 0.2) X0.3 = 0.08 Sqm
L/S Slope (sqrt(2X1+2X1) X 0.2) X0.8 = 0.36 Sqm
Lug
Top Width = 0.38 M
Bottom Width 0.38+0.2X1 = 0.58 M
0.58+0.38
Area of Lug X 0.2 = 0.1 Sqm
2
Total Area of Metal 0.23+0.08+0.36+0.1 = 0.77 Sqm
Filter
200 mm Thk Sand
BED
Bottom Width = 0.955 M
Top Width 0.955+0.2X3 = 1.555 M
1.555+0.955
Area of Bed X 0.2 = 0.25 Sqm
2
R/S Slope= (sqrt(1X1+1X1) X 0.2) X0.3 = 0.08 Sqm
L/S Slope (sqrt(2X1+2X1) X 0.2) X1 = 0.45 Sqm
Lug
Top Width = 0.29 M
Bottom Width 0.29+0.2X1 = 0.49 M
0.49+0.29
Area of Lug X 0.2 = 0.08 Sqm
2
Total Area of Sand 0.25+0.08+0.45+0.08 = 0.86 Sqm
Filter

Length Area Quanitty


Slno Descrption of item Remarks
(M) (Sqm) (Cum)
1 Eath work Excavation 1748 2.66 4649.68
2 Rip Rap 1748 0.96 1678.08
3 Metal Filters 1748 0.77 1345.96
5 Sand Filters 1748 0.86 1503.28
Formation of Mallamadugu Reservoir
BUND-1
Detail Estimate D/S Rock- Toe Protection

300 mm Thick Rip Rap

1M

200 mm thick Metal Filter

200 mm thick Sand Filter

Height of Toe Protection = 1 M


Incliend Height of Toe protection Sqrt(2X2+1X1) x 1 m = 2.24 M
Thick ness of Rip Rap = 0.3 M
Thickness of Metal Filter = 0.2 M
Thickness of Sand Filter = 0.2 M
Area of Rip Rap = 2.24X0.3 = 0.67 Sqm
Area of Metal Filter = 2.24X0.2 = 0.45 Sqm
Area of Sand Filter = 2.24X0.2 = 0.45 Sqm

Length of Area in Quantity


Slno Descrption of item Remarks
Bund in M Sqm in Cum

1 Rip Rap 1748 0.67 1171.16


2 Metal Fiters 1748 0.45 786.60
3 Sand Filters 1748 0.45 786.60
Formation Mallamadugu Reservoir
Bund-2-Area / Quantity Statement
Behind Metal Inclined Sand horizontal Sand 450mm thk Rip
Stripping Rock-toe Behind sand Filters Hearting 200mm thk Metal 200mm thk sand Net Casing Area
Filters Chimney Filter Rap
Chainge
Slno
in Km
Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity in Area in Quantity in Area in Quantity in Area in Quantity Area in Quantity in Area in Quantity Area in Quantity
Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm Cum Sqm Cum Sqm Cum Sqm in Cum Sqm Cum Sqm in Cum Sqm in Cum

1 0.000 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 0.025 10.30 128.75 3.38 42.25 0.42 5.25 0.42 5.25 28.93 361.63 3.55 44.38 6.94 86.75 6.21 77.63 2.76 34.50 2.76 34.50 57.94 724.25
3 0.050 20.80 388.75 6.53 123.88 0.59 12.63 0.59 12.63 99.61 1606.75 10.54 176.13 19.57 331.38 14.76 262.13 6.56 116.50 6.56 116.50 255.58 3919.00
4 0.075 28.09 611.13 12.59 239.00 0.82 17.63 0.82 17.63 166.39 3325.00 18.10 357.95 23.22 534.88 22.23 462.38 9.88 205.50 9.88 205.50 524.27 9748.18
5 0.100 27.60 696.13 11.96 306.88 0.80 20.25 0.80 20.25 159.67 4075.75 17.60 446.25 22.89 576.38 21.78 550.13 9.68 244.50 9.68 244.50 500.73 12812.50
6 0.125 28.28 698.50 12.82 309.75 0.83 20.38 0.83 20.38 168.85 4106.50 18.28 448.50 23.34 577.88 22.39 552.13 9.95 245.38 9.95 245.38 533.18 12923.88
7 0.150 28.28 707.00 12.82 320.50 0.83 20.75 0.83 20.75 168.85 4221.25 18.28 456.90 23.34 583.50 22.39 559.75 9.95 248.75 9.95 248.75 533.18 13329.60
8 0.175 30.19 730.88 12.67 318.63 0.82 20.63 0.82 20.63 167.31 4202.00 18.16 455.40 26.26 620.00 24.10 581.13 10.71 258.25 10.71 258.25 646.85 14750.48
9 0.200 28.13 729.00 12.64 316.38 0.82 20.50 0.82 20.50 166.81 4176.50 18.12 453.45 23.24 618.75 22.25 579.38 9.89 257.50 9.89 257.50 526.00 14660.68
10 0.225 27.82 699.38 12.24 311.00 0.81 20.38 0.81 20.38 162.58 4117.38 17.82 449.25 23.03 578.38 21.98 552.88 9.77 245.75 9.77 245.75 511.00 12962.50
11 0.250 27.71 694.13 12.10 304.25 0.80 20.13 0.80 20.13 161.12 4046.25 17.71 444.15 22.96 574.88 21.88 548.25 9.72 243.63 9.72 243.63 505.88 12710.98
12 0.275 27.66 692.13 12.04 301.75 0.80 20.00 0.80 20.00 160.52 4020.50 17.66 442.20 22.93 573.63 21.84 546.50 9.71 242.88 9.71 242.88 503.56 12617.93
13 0.300 27.24 686.25 11.51 294.38 0.78 19.75 0.78 19.75 154.94 3943.25 17.24 436.35 22.65 569.75 21.46 541.25 9.54 240.63 9.54 240.63 483.85 12342.53
14 0.325 27.05 678.63 11.28 284.88 0.78 19.50 0.78 19.50 152.32 3840.75 17.05 428.70 22.52 564.63 21.29 534.38 9.46 237.50 9.46 237.50 474.74 11982.30
15 0.350 26.93 674.75 11.13 280.13 0.77 19.38 0.77 19.38 150.73 3788.13 16.93 424.80 22.44 562.00 21.18 530.88 9.41 235.88 9.41 235.88 469.11 11798.08
16 0.375 26.94 673.38 11.15 278.50 0.77 19.25 0.77 19.25 150.91 3770.50 16.94 423.45 22.45 561.13 21.19 529.63 9.42 235.38 9.42 235.38 469.74 11735.55
17 0.400 26.89 672.88 11.09 278.00 0.77 19.25 0.77 19.25 150.33 3765.50 16.90 423.00 22.41 560.75 21.15 529.25 9.40 235.25 9.40 235.25 467.52 11715.75
18 0.425 26.83 671.50 11.02 276.38 0.77 19.25 0.77 19.25 149.50 3747.88 16.84 421.65 22.38 559.88 21.09 528.00 9.37 234.63 9.37 234.63 464.76 11653.60
19 0.450 26.86 671.13 11.06 276.00 0.77 19.25 0.77 19.25 149.98 3743.50 16.87 421.35 22.39 559.63 21.12 527.63 9.39 234.50 9.39 234.50 466.27 11637.90
20 0.475 26.96 672.75 11.18 278.00 0.77 19.25 0.77 19.25 151.21 3764.88 16.97 423.00 22.46 560.63 21.21 529.13 9.43 235.25 9.43 235.25 470.60 11710.88
21 0.500 27.10 675.75 11.34 281.50 0.78 19.38 0.78 19.38 152.98 3802.37 17.10 425.85 22.55 562.62 21.33 531.75 9.48 236.38 9.48 236.38 476.87 11843.40
22 0.525 27.20 678.75 11.46 285.00 0.78 19.50 0.78 19.50 154.28 3840.75 17.20 428.70 22.62 564.63 21.42 534.38 9.52 237.50 9.52 237.50 481.65 11981.55
23 0.550 27.29 681.13 11.57 287.88 0.79 19.63 0.79 19.63 155.53 3872.63 17.29 431.10 22.69 566.38 21.51 536.63 9.56 238.50 9.56 238.50 486.07 12096.53
24 0.575 27.38 683.38 11.68 290.63 0.79 19.75 0.79 19.75 156.73 3903.25 17.38 433.35 22.74 567.88 21.58 538.63 9.59 239.38 9.59 239.38 490.18 12203.15
25 0.600 27.38 684.50 11.68 292.00 0.79 19.75 0.79 19.75 156.73 3918.25 17.38 434.40 22.74 568.50 21.58 539.50 9.59 239.75 9.59 239.75 490.18 12254.60
26 0.625 27.52 686.25 11.87 294.38 0.80 19.88 0.80 19.88 158.58 3941.38 17.52 436.20 22.83 569.63 21.71 541.13 9.65 240.50 9.65 240.50 496.88 12338.30
27 0.650 27.58 688.75 11.93 297.50 0.80 20.00 0.80 20.00 159.31 3973.63 17.58 438.75 22.87 571.25 21.76 543.38 9.67 241.50 9.67 241.50 499.43 12453.88
28 0.675 27.58 689.50 11.93 298.25 0.80 20.00 0.80 20.00 159.43 3984.25 17.58 439.50 22.88 571.88 21.76 544.00 9.67 241.75 9.67 241.75 499.73 12489.50
29 0.700 27.79 692.13 12.21 301.75 0.81 20.13 0.81 20.13 162.21 4020.50 17.80 442.20 23.01 573.63 21.95 546.38 9.76 242.88 9.76 242.88 509.71 12618.05
30 0.725 27.88 695.88 12.32 306.63 0.81 20.25 0.81 20.25 163.44 4070.63 17.88 445.95 23.07 576.00 22.03 549.75 9.79 244.38 9.79 244.38 513.89 12795.05
31 0.750 28.01 698.63 12.47 309.88 0.82 20.38 0.82 20.38 165.15 4107.38 18.00 448.50 23.16 577.88 22.14 552.13 9.84 245.38 9.84 245.38 520.11 12925.00
32 0.775 28.06 700.88 12.55 312.75 0.82 20.50 0.82 20.50 165.89 4138.00 18.06 450.75 23.19 579.38 22.19 554.13 9.86 246.25 9.86 246.25 522.71 13035.25
33 0.800 28.44 706.25 13.03 319.75 0.83 20.63 0.83 20.63 171.09 4212.25 18.43 456.15 23.45 583.00 22.53 559.00 10.01 248.38 10.01 248.38 541.14 13298.10
34 0.825 30.61 738.13 13.23 328.25 0.84 20.88 0.84 20.88 173.11 4302.50 18.58 462.60 26.54 624.88 24.48 587.63 10.88 261.13 10.88 261.13 669.34 15131.03
35 0.850 28.92 744.13 13.68 336.38 0.85 21.13 0.85 21.13 177.85 4387.00 18.91 468.60 23.76 628.75 22.96 593.00 10.21 263.63 10.21 263.63 564.79 15426.65
36 0.875 30.98 748.75 13.73 342.63 0.86 21.38 0.86 21.38 178.42 4453.38 18.95 473.25 26.79 631.88 24.82 597.25 11.03 265.50 11.03 265.50 690.00 15684.88
37 0.900 31.60 782.25 14.57 353.75 0.88 21.75 0.88 21.75 187.19 4570.13 19.56 481.35 27.20 674.88 25.37 627.38 11.27 278.75 11.27 278.75 724.19 17677.40
38 0.925 29.87 768.38 14.98 369.38 0.89 22.13 0.89 22.13 191.52 4733.88 19.86 492.75 24.40 645.00 23.82 614.88 10.59 273.25 10.59 273.25 613.15 16716.75
39 0.950 30.25 751.50 15.52 381.25 0.91 22.50 0.91 22.50 197.10 4857.75 20.23 501.15 24.65 613.13 24.16 599.75 10.74 266.63 10.74 266.63 632.81 15574.48
40 0.975 30.66 761.38 16.11 395.38 0.93 23.00 0.93 23.00 203.32 5005.25 20.64 510.90 24.93 619.75 24.53 608.63 10.90 270.50 10.90 270.50 654.47 16090.98
41 1.000 30.86 769.00 16.40 406.37 0.94 23.37 0.94 23.37 206.39 5121.37 20.84 518.55 25.06 624.87 24.71 615.50 10.98 273.50 10.98 273.50 665.31 16497.20
42 1.025 32.98 798.00 16.54 411.75 0.94 23.50 0.94 23.50 207.83 5177.75 20.94 522.30 28.13 664.87 26.61 641.50 11.83 285.12 11.83 285.12 803.55 18360.70
43 1.050 31.36 804.25 17.14 421.00 0.96 23.75 0.96 23.75 214.05 5273.50 21.34 528.45 25.40 669.12 25.16 647.12 11.18 287.62 11.18 287.62 692.24 18697.42
Behind Metal Inclined Sand horizontal Sand 450mm thk Rip
Stripping Rock-toe Behind sand Filters Hearting 200mm thk Metal 200mm thk sand Net Casing Area
Filters Chimney Filter Rap
Chainge
Slno
in Km
Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity in Area in Quantity in Area in Quantity in Area in Quantity Area in Quantity in Area in Quantity Area in Quantity
Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm Cum Sqm Cum Sqm Cum Sqm in Cum Sqm Cum Sqm in Cum Sqm in Cum

44 1.075 30.92 778.50 16.50 420.50 0.94 23.75 0.94 23.75 207.27 5266.50 20.90 528.00 25.10 631.25 24.76 624.00 11.01 277.37 11.01 277.37 668.58 17010.25
45 1.100 31.87 784.87 17.92 430.25 0.98 24.00 0.98 24.00 221.92 5364.87 21.84 534.30 25.73 635.37 25.61 629.62 11.38 279.87 11.38 279.87 720.10 17358.45
46 1.125 34.55 830.25 18.94 460.75 1.01 24.87 1.01 24.87 232.47 5679.87 22.50 554.25 29.18 686.37 28.02 670.37 12.45 297.87 12.45 297.87 898.25 20229.37
47 1.143 32.04 599.31 15.17 306.99 0.90 17.19 0.90 17.19 193.65 3835.08 19.99 382.43 27.50 510.12 25.76 484.02 11.45 215.10 11.45 215.10 748.95 14824.78
Total 31797.44 14382.99 926.31 926.31 188437.96 20247.13 26447.62 25133.77 11170.48 11170.48 613349.21
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.025 Km
T.B.L = + 129.500 M Avg. G.L = + 123.625 M
Stripped.Level = + 123.325 M Stri.Lev = + 123.325 M
Height of Bund 6.175 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 123.325 )X 4+6+1.717+1.9= 34.32 M
Depth of Stripping ( 123.625 - 123.325 ) = 0.300 M
Area of Stripping ( 34.320 X 0.300 ) = 10.300 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-123.325 )X 20% 0.835 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 123.325 )X 0.5*2+3 = 8.18 M
Top Width = 3M
Arae of Hearting Soils = 3+8.18
X 5.175 = 28.93 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-123.325)X2+3-0.57-4.5 - 8.18/2 = 6.19 M
Top Width = 6.19+1.5 = 7.69 M
Arae of Hearting Soils = 7.69+6.19
X 1.000 = 6.94 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 124.325
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 3.175 = 3.55 M
Area of Inclined Sand Chimney = 3.55 X 1 = 3.55 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 6.175 = 13.81 M
Arae of 450thk Rip Rap = 13.81X0.45 = 6.21 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 6.175 = 13.81 M
Arae of 200thk Sand = 13.81X0.2 = 2.76 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 6.175 = 13.81 M
Arae of 200thk Sand = 13.81X0.2 = 2.76 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 123.325 )X 4+6 = 30.7 M
Top Width = 6M
Arae of Bund = 6+30.7
X 6.175 = 113.31 Sqm
2
12)Net casing Area = 113.31-3.38-0.42-0.42-28.93-6.94-3.55-6.21-2.76-2.76 = 57.94 Sqm

Slno Descrption Area


1 Stripping = 10.300 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 28.93 Sqm
12 Inclined Sand Chimney = 3.55 Sqm
13 horizontal Sand Filter = 6.94 Sqm
14 450mm thk Rip Rap = 6.21 Sqm
15 200mm thk Metal = 2.76 Sqm
16 200mm thk sand = 2.76 Sqm
17 Net Casing Area = 57.94 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.050 Km
T.B.L = + 129.500 M Avg. G.L = + 117.370 M
Stripped.Level = + 117.070 M Stri.Lev = + 117.070 M
Height of Bund 12.430 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 117.070 )X 4+6+10+1.717+1.9= 69.34 M
Depth of Stripping ( 117.370 - 117.070 ) = 0.300 M
Area of Stripping ( 69.340 X 0.300 ) = 20.800 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-117.07 )X 20% 2.086 = 2.09 M
Bottom Width of Rock-Toe = 2.086 X 3 = 6.26 M
Area of Rock -Toe =1/2X6.26X2.086 = 6.53 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.086 = 2.95 M
Area = 2.95X0.2 = 0.59 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.086 = 2.95 M
Area = 2.95X0.2 = 0.59 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 117.070 )X 0.5*2+3 = 14.43 M
Top Width = 3M
Arae of Hearting Soils = 3+14.43
X 11.430 = 99.61 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-117.07)X2+3+5-0.57-6.26- 14.43/2 = 18.82 M
Top Width = 18.82+1.5 = 20.32 M
Arae of Hearting Soils = 20.32+18.82
X 1.000 = 19.57 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 118.070
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 9.430 = 10.54 M
Area of Inclined Sand Chimney = 10.54 X 1 = 10.54 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 12.430 + 5 = 32.79 M
Arae of 450thk Rip Rap = 32.79X0.45 = 14.76 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 12.430 + 5 = 32.79 M
Arae of 200thk Sand = 32.79X0.2 = 6.56 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 12.430 + 5 = 32.79 M
Arae of 200thk Sand = 32.79X0.2 = 6.56 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 117.070 )X 4+6+10 = 65.72 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4+6+10 50.8 M
Top Width = 6M
Arae of Bund up to Berm = 50.8+65.72
X 3.730 = 217.31 Sqm
2
Arae of Bund Berm to TBL = 6+40.8
X 8.700 = 203.58 Sqm
2
Total 420.89 Sqm
12)Net casing Area = 420.89-6.53-0.59-0.59-99.61-19.57-10.54-14.76-6.56-6.56 = 255.58 Sqm
Slno Descrption Area
1 Stripping = 20.800 Sqm
8 Rock-toe = 6.53 Sqm
9 Behind sand Filters = 0.59 Sqm
10 Behind Metal Filters = 0.59 Sqm
11 Hearting = 99.61 Sqm
12 Inclined Sand Chimney = 10.54 Sqm
13 horizontal Sand Filter = 19.57 Sqm
14 450mm thk Rip Rap = 14.76 Sqm
15 200mm thk Metal = 6.56 Sqm
16 200mm thk sand = 6.56 Sqm
17 Net Casing Area = 255.58 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.075 Km
T.B.L = + 129.500 M Avg. G.L = + 113.315 M
Stripped.Level = + 113.015 M Stri.Lev = + 113.015 M
Height of Bund 16.485 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.015 )X 4.5+6+10+1.567+2.5= 93.65 M
Depth of Stripping ( 113.315 - 113.015 ) = 0.300 M
Area of Stripping ( 93.650 X 0.300 ) = 28.090 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.015 )X 20% 2.897 = 2.90 M
Bottom Width of Rock-Toe = 2.897 X 3 = 8.69 M
Area of Rock -Toe = 1/2X8.69X2.897 = 12.59 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.897 = 4.1 M
Area = 4.1X0.2 = 0.82 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.897 = 4.1 M
Area = 4.1X0.2 = 0.82 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.015 )X 0.5*2+3 = 18.49 M
Top Width = 3 M
Arae of Hearting Soils = 3+18.49
X 15.485 = 166.39 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.015)X2+3+5-0.57-8.69- 18.49/2 = 22.47 M
Top Width = 22.47+1.5 = 23.97 M
Arae of Hearting Soils = 23.97+22.47
X 1.000 = 23.22 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.015
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.485 = 15.08 M
Area of Inclined Sand Chimney = 15.08 X 1.2 = 18.096 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)X 16.485 + 5 = 49.39 M
Arae of 450thk Rip Rap = 49.39X0.45 = 22.23 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)X 16.485 + 5 = 49.39 M
Arae of 200thk Sand = 49.39X0.2 = 9.88 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)X 16.485 + 5 = 49.39 M
Arae of 200thk Sand = 49.39X0.2 = 9.88 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.015 )X 4.5+6+10 = 90.18 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+90.18
X 7.785 = 565.70 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 788.20 Sqm
12)Net casing Area = 788.2-12.59-0.82-0.82-166.39-23.22-18.096-22.23-9.88-9.88 = 524.27 Sqm
Slno Descrption Area
1 Stripping = 28.090 Sqm
8 Rock-toe = 12.59 Sqm
9 Behind sand Filters = 0.82 Sqm
10 Behind Metal Filters = 0.82 Sqm
11 Hearting = 166.39 Sqm
12 Inclined Sand Chimney = 18.096 Sqm
13 horizontal Sand Filter = 23.22 Sqm
14 450mm thk Rip Rap = 22.23 Sqm
15 200mm thk Metal = 9.88 Sqm
16 200mm thk sand = 9.88 Sqm
17 Net Casing Area = 524.27 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.100 Km
T.B.L = + 129.500 M Avg. G.L = + 113.680 M
Stripped.Level = + 113.380 M Stri.Lev = + 113.380 M
Height of Bund 16.120 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.380 )X 4.5+6+10+1.567+2.5= 92.01 M
Depth of Stripping ( 113.680 - 113.380 ) = 0.300 M
Area of Stripping ( 92.010 X 0.300 ) = 27.600 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.38 )X 20% 2.824 = 2.82 M
Bottom Width of Rock-Toe = 2.824 X 3 = 8.47 M
Area of Rock -Toe = 1/2X8.47X2.824 = 11.96 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.824 = 3.99 M
Area = 3.99X0.2 = 0.8 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.824 = 3.99 M
Area = 3.99X0.2 = 0.8 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.380 )X 0.5*2+3 = 18.12 M
Top Width = 3 M
Arae of Hearting Soils = 3+18.12
X 15.120 = 159.67 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.38)X2+3+5-0.57-8.47- 18.12/2 = 22.14 M
Top Width = 22.14+1.5 = 23.64 M
Arae of Hearting Soils = 23.64+22.14
X 1.000 = 22.89 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.380
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.120 = 14.67 M
Area of Inclined Sand Chimney = 14.67 X 1.2 = 17.604 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)X 16.120 + 5 = 48.4 M
Arae of 450thk Rip Rap = 48.4X0.45 = 21.78 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)X 16.120 + 5 = 48.4 M
Arae of 200thk Sand = 48.4X0.2 = 9.68 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)X 16.120 + 5 = 48.4 M
Arae of 200thk Sand = 48.4X0.2 = 9.68 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.380 )X 4.5+6+10 = 88.54 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+88.54
X 7.420 = 533.09 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 755.59 Sqm
12)Net casing Area = 755.59-11.96-0.8-0.8-159.67-22.89-17.604-21.78-9.68-9.68 = 500.73 Sqm
Slno Descrption Area
1 Stripping = 27.600 Sqm
8 Rock-toe = 11.96 Sqm
9 Behind sand Filters = 0.8 Sqm
10 Behind Metal Filters = 0.8 Sqm
11 Hearting = 159.67 Sqm
12 Inclined Sand Chimney = 17.604 Sqm
13 horizontal Sand Filter = 22.89 Sqm
14 450mm thk Rip Rap = 21.78 Sqm
15 200mm thk Metal = 9.68 Sqm
16 200mm thk sand = 9.68 Sqm
17 Net Casing Area = 500.73 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.125 Km
T.B.L = + 129.500 M Avg. G.L = + 113.180 M
Stripped.Level = + 112.880 M Stri.Lev = + 112.880 M
Height of Bund 16.620 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 112.880 )X 4.5+6+10+1.567+2.5= 94.26 M
Depth of Stripping ( 113.180 - 112.880 ) = 0.300 M
Area of Stripping ( 94.260 X 0.300 ) = 28.280 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-112.88 )X 20% 2.924 = 2.92 M
Bottom Width of Rock-Toe = 2.924 X 3 = 8.77 M
Area of Rock -Toe = 1/2X8.77X2.924 = 12.82 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.924 = 4.14 M
Area = 4.14X0.2 = 0.83 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.924 = 4.14 M
Area = 4.14X0.2 = 0.83 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 112.880 )X 0.5*2+3 = 18.62 M
Top Width = 3 M
Arae of Hearting Soils = 3+18.62
X 15.620 = 168.85 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-112.88)X2+3+5-0.57-8.77- 18.62/2 = 22.59 M
Top Width = 22.59+1.5 = 24.09 M
Arae of Hearting Soils = 24.09+22.59
X 1.000 = 23.34 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 113.880
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.620 = 15.23 M
Area of Inclined Sand Chimney = 15.23 X 1.2 = 18.276 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.620 + 5 = 49.75 M
Arae of 450thk Rip Rap = 49.75X0.45 = 22.39 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.620 + 5 = 49.75 M
Arae of 200thk Sand = 49.75X0.2 = 9.95 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.620 + 5 = 49.75 M
Arae of 200thk Sand = 49.75X0.2 = 9.95 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 112.880 )X 4.5+6+10 = 90.79 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+90.79
X 7.920 = 577.92 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 800.42 Sqm
12)Net casing Area = 800.42-12.82-0.83-0.83-168.85-23.34-18.276-22.39-9.95-9.95 = 533.18 Sqm
Slno Descrption Area
1 Stripping = 28.280 Sqm
8 Rock-toe = 12.82 Sqm
9 Behind sand Filters = 0.83 Sqm
10 Behind Metal Filters = 0.83 Sqm
11 Hearting = 168.85 Sqm
12 Inclined Sand Chimney = 18.276 Sqm
13 horizontal Sand Filter = 23.34 Sqm
14 450mm thk Rip Rap = 22.39 Sqm
15 200mm thk Metal = 9.95 Sqm
16 200mm thk sand = 9.95 Sqm
17 Net Casing Area = 533.18 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.150 Km
T.B.L = + 129.500 M Avg. G.L = + 113.180 M
Stripped.Level = + 112.880 M Stri.Lev = + 112.880 M
Height of Bund 16.620 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 112.880 )X 4.5+6+10+1.567+2.5= 94.26 M
Depth of Stripping ( 113.180 - 112.880 ) = 0.300 M
Area of Stripping ( 94.260 X 0.300 ) = 28.280 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-112.88 )X 20% 2.924 = 2.92 M
Bottom Width of Rock-Toe = 2.924 X 3 = 8.77 M
Area of Rock -Toe = 1/2X8.77X2.924 = 12.82 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.924 = 4.14 M
Area = 4.14X0.2 = 0.83 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.924 = 4.14 M
Area = 4.14X0.2 = 0.83 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 112.880 )X 0.5*2+3 = 18.62 M
Top Width = 3 M
Arae of Hearting Soils = 3+18.62
X 15.620 = 168.85 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-112.88)X2+3+5-0.57-8.77- 18.62/2 = 22.59 M
Top Width = 22.59+1.5 = 24.09 M
Arae of Hearting Soils = 24.09+22.59
X 1.000 = 23.34 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 113.880
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.620 = 15.23 M
Area of Inclined Sand Chimney = 15.23 X 1.2 = 18.276 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.620 + 5 = 49.75 M
Arae of 450thk Rip Rap = 49.75X0.45 = 22.39 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.620 + 5 = 49.75 M
Arae of 200thk Sand = 49.75X0.2 = 9.95 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.620 + 5 = 49.75 M
Arae of 200thk Sand = 49.75X0.2 = 9.95 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 112.880 )X 4.5+6+10 = 90.79 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+90.79
X 7.920 = 577.92 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 800.42 Sqm
12)Net casing Area = 800.42-12.82-0.83-0.83-168.85-23.34-18.276-22.39-9.95-9.95 = 533.18 Sqm
Slno Descrption Area
1 Stripping = 28.280 Sqm
8 Rock-toe = 12.82 Sqm
9 Behind sand Filters = 0.83 Sqm
10 Behind Metal Filters = 0.83 Sqm
11 Hearting = 168.85 Sqm
12 Inclined Sand Chimney = 18.276 Sqm
13 horizontal Sand Filter = 23.34 Sqm
14 450mm thk Rip Rap = 22.39 Sqm
15 200mm thk Metal = 9.95 Sqm
16 200mm thk sand = 9.95 Sqm
17 Net Casing Area = 533.18 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.175 Km
T.B.L = + 131.000 M Avg. G.L = + 113.265 M
Stripped.Level = + 112.965 M Stri.Lev = + 112.965 M
Height of Bund 18.035 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 131.000 - 112.965 )X 4.5+6+10+1.567+2.5= 100.6 M
Depth of Stripping ( 113.265 - 112.965 ) = 0.300 M
Area of Stripping ( 100.620 X 0.300 ) = 30.190 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-112.965 )X 20% 2.907 = 2.91 M
Bottom Width of Rock-Toe = 2.907 X 3 = 8.72 M
Area of Rock -Toe = 1/2X8.72X2.907 = 12.67 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.907 = 4.11 M
Area = 4.11X0.2 = 0.82 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.907 = 4.11 M
Area = 4.11X0.2 = 0.82 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 112.965 )X 0.5*2+3 = 18.54 M
Top Width = 3 M
Arae of Hearting Soils = 3+18.54
X 15.535 = 167.31 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 131-112.965)X2+3+5-0.57-8.72- 18.54/2 = 25.51 M
Top Width = 25.51+1.5 = 27.01 M
Arae of Hearting Soils = 27.01+25.51
X 1.000 = 26.26 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 113.965
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.535 = 15.13 M
Area of Inclined Sand Chimney = 15.13 X 1.2 = 18.156 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.035 + 5 = 53.56 M
Arae of 450thk Rip Rap = 53.56X0.45 = 24.1 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.035 + 5 = 53.56 M
Arae of 200thk Sand = 53.56X0.2 = 10.71 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.035 + 5 = 53.56 M
Arae of 200thk Sand = 53.56X0.2 = 10.71 Sqm
9) Area of Bund
Bottom Width ( 131.000 - 112.965 )X 4.5+6+10 = 97.16 M
At 120.8 Incl Berm ( 131.000 - 120.800 )X 4.5+6+10 61.9 M
Top Width = 6 M
Arae of Bund up to Berm = 61.9+97.16
X 7.835 = 623.12 Sqm
2
Arae of Bund Berm to TBL = 6+51.9
X 10.200 = 295.29 Sqm
2
Total 918.41 Sqm
12)Net casing Area = 918.41-12.67-0.82-0.82-167.31-26.26-18.156-24.1-10.71-10.71 = 646.85 Sqm
Slno Descrption Area
1 Stripping = 30.190 Sqm
8 Rock-toe = 12.67 Sqm
9 Behind sand Filters = 0.82 Sqm
10 Behind Metal Filters = 0.82 Sqm
11 Hearting = 167.31 Sqm
12 Inclined Sand Chimney = 18.156 Sqm
13 horizontal Sand Filter = 26.26 Sqm
14 450mm thk Rip Rap = 24.1 Sqm
15 200mm thk Metal = 10.71 Sqm
16 200mm thk sand = 10.71 Sqm
17 Net Casing Area = 646.85 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.200 Km
T.B.L = + 129.500 M Avg. G.L = + 113.290 M
Stripped.Level = + 112.990 M Stri.Lev = + 112.990 M
Height of Bund 16.510 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 112.990 )X 4.5+6+10+1.567+2.5= 93.76 M
Depth of Stripping ( 113.290 - 112.990 ) = 0.300 M
Area of Stripping ( 93.760 X 0.300 ) = 28.130 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-112.99 )X 20% 2.902 = 2.90 M
Bottom Width of Rock-Toe = 2.902 X 3 = 8.71 M
Area of Rock -Toe = 1/2X8.71X2.902 = 12.64 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.902 = 4.1 M
Area = 4.1X0.2 = 0.82 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.902 = 4.1 M
Area = 4.1X0.2 = 0.82 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 112.990 )X 0.5*2+3 = 18.51 M
Top Width = 3 M
Arae of Hearting Soils = 3+18.51
X 15.510 = 166.81 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-112.99)X2+3+5-0.57-8.71- 18.51/2 = 22.49 M
Top Width = 22.49+1.5 = 23.99 M
Arae of Hearting Soils = 23.99+22.49
X 1.000 = 23.24 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 113.990
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.510 = 15.1 M
Area of Inclined Sand Chimney = 15.1 X 1.2 = 18.12 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.510 + 5 = 49.45 M
Arae of 450thk Rip Rap = 49.45X0.45 = 22.25 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.510 + 5 = 49.45 M
Arae of 200thk Sand = 49.45X0.2 = 9.89 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.510 + 5 = 49.45 M
Arae of 200thk Sand = 49.45X0.2 = 9.89 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 112.990 )X 4.5+6+10 = 90.3 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+90.3
X 7.810 = 567.98 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 790.48 Sqm
12)Net casing Area = 790.48-12.64-0.82-0.82-166.81-23.24-18.12-22.25-9.89-9.89 = 526.00 Sqm
Slno Descrption Area
1 Stripping = 28.130 Sqm
8 Rock-toe = 12.64 Sqm
9 Behind sand Filters = 0.82 Sqm
10 Behind Metal Filters = 0.82 Sqm
11 Hearting = 166.81 Sqm
12 Inclined Sand Chimney = 18.12 Sqm
13 horizontal Sand Filter = 23.24 Sqm
14 450mm thk Rip Rap = 22.25 Sqm
15 200mm thk Metal = 9.89 Sqm
16 200mm thk sand = 9.89 Sqm
17 Net Casing Area = 526.00 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.225 Km
T.B.L = + 129.500 M Avg. G.L = + 113.520 M
Stripped.Level = + 113.220 M Stri.Lev = + 113.220 M
Height of Bund 16.280 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.220 )X 4.5+6+10+1.567+2.5= 92.73 M
Depth of Stripping ( 113.520 - 113.220 ) = 0.300 M
Area of Stripping ( 92.730 X 0.300 ) = 27.820 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.22 )X 20% 2.856 = 2.86 M
Bottom Width of Rock-Toe = 2.856 X 3 = 8.57 M
Area of Rock -Toe = 1/2X8.57X2.856 = 12.24 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.856 = 4.04 M
Area = 4.04X0.2 = 0.81 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.856 = 4.04 M
Area = 4.04X0.2 = 0.81 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.220 )X 0.5*2+3 = 18.28 M
Top Width = 3 M
Arae of Hearting Soils = 3+18.28
X 15.280 = 162.58 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.22)X2+3+5-0.57-8.57- 18.28/2 = 22.28 M
Top Width = 22.28+1.5 = 23.78 M
Arae of Hearting Soils = 23.78+22.28
X 1.000 = 23.03 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.220
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.280 = 14.85 M
Area of Inclined Sand Chimney = 14.85 X 1.2 = 17.82 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)X 16.280 + 5 = 48.84 M
Arae of 450thk Rip Rap = 48.84X0.45 = 21.98 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)X 16.280 + 5 = 48.84 M
Arae of 200thk Sand = 48.84X0.2 = 9.77 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)X 16.280 + 5 = 48.84 M
Arae of 200thk Sand = 48.84X0.2 = 9.77 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.220 )X 4.5+6+10 = 89.26 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+89.26
X 7.580 = 547.31 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 769.81 Sqm
12)Net casing Area = 769.81-12.24-0.81-0.81-162.58-23.03-17.82-21.98-9.77-9.77 = 511.00 Sqm
Slno Descrption Area
1 Stripping = 27.820 Sqm
8 Rock-toe = 12.24 Sqm
9 Behind sand Filters = 0.81 Sqm
10 Behind Metal Filters = 0.81 Sqm
11 Hearting = 162.58 Sqm
12 Inclined Sand Chimney = 17.82 Sqm
13 horizontal Sand Filter = 23.03 Sqm
14 450mm thk Rip Rap = 21.98 Sqm
15 200mm thk Metal = 9.77 Sqm
16 200mm thk sand = 9.77 Sqm
17 Net Casing Area = 511.00 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.250 Km
T.B.L = + 129.500 M Avg. G.L = + 113.600 M
Stripped.Level = + 113.300 M Stri.Lev = + 113.300 M
Height of Bund 16.200 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.300 )X 4.5+6+10+1.567+2.5= 92.37 M
Depth of Stripping ( 113.600 - 113.300 ) = 0.300 M
Area of Stripping ( 92.370 X 0.300 ) = 27.710 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.3 )X 20% 2.84 = 2.84 M
Bottom Width of Rock-Toe = 2.84 X 3 = 8.52 M
Area of Rock -Toe = 1/2X8.52X2.84 = 12.1 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.840 = 4.02 M
Area = 4.02X0.2 = 0.8 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.840 = 4.02 M
Area = 4.02X0.2 = 0.8 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.300 )X 0.5*2+3 = 18.2 M
Top Width = 3M
Arae of Hearting Soils = 3+18.2
X 15.200 = 161.12 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.3)X2+3+5-0.57-8.52- 18.2/2 = 22.21 M
Top Width = 22.21+1.5 = 23.71 M
Arae of Hearting Soils = 23.71+22.21
X 1.000 = 22.96 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.300
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.200 = 14.76 M
Area of Inclined Sand Chimney = 14.76 X 1.2 = 17.712 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.200 + 5 = 48.62 M
Arae of 450thk Rip Rap = 48.62X0.45 = 21.88 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.200 + 5 = 48.62 M
Arae of 200thk Sand = 48.62X0.2 = 9.72 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.200 + 5 = 48.62 M
Arae of 200thk Sand = 48.62X0.2 = 9.72 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.300 )X 4.5+6+10 = 88.9 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+88.9
X 7.500 = 540.19 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 762.69 Sqm
12)Net casing Area = 762.69-12.1-0.8-0.8-161.12-22.96-17.712-21.88-9.72-9.72 = 505.88 Sqm
Slno Descrption Area
1 Stripping = 27.710 Sqm
8 Rock-toe = 12.1 Sqm
9 Behind sand Filters = 0.8 Sqm
10 Behind Metal Filters = 0.8 Sqm
11 Hearting = 161.12 Sqm
12 Inclined Sand Chimney = 17.712 Sqm
13 horizontal Sand Filter = 22.96 Sqm
14 450mm thk Rip Rap = 21.88 Sqm
15 200mm thk Metal = 9.72 Sqm
16 200mm thk sand = 9.72 Sqm
17 Net Casing Area = 505.88 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.275 Km
T.B.L = + 129.500 M Avg. G.L = + 113.635 M
Stripped.Level = + 113.335 M Stri.Lev = + 113.335 M
Height of Bund 16.165 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.335 )X 4.5+6+10+1.567+2.5= 92.21 M
Depth of Stripping ( 113.635 - 113.335 ) = 0.300 M
Area of Stripping ( 92.210 X 0.300 ) = 27.660 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.335 )X 20% 2.833 = 2.83 M
Bottom Width of Rock-Toe = 2.833 X 3 = 8.50 M
Area of Rock -Toe = 1/2X8.5X2.833 = 12.04 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.833 = 4.01 M
Area = 4.01X0.2 = 0.8 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.833 = 4.01 M
Area = 4.01X0.2 = 0.8 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.335 )X 0.5*2+3 = 18.17 M
Top Width = 3 M
Arae of Hearting Soils = 3+18.17
X 15.165 = 160.52 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.335)X2+3+5-0.57-8.5- 18.17/2 = 22.18 M
Top Width = 22.18+1.5 = 23.68 M
Arae of Hearting Soils = 23.68+22.18
X 1.000 = 22.93 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.335
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.165 = 14.72 M
Area of Inclined Sand Chimney = 14.72 X 1.2 = 17.664 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)X 16.165 + 5 = 48.53 M
Arae of 450thk Rip Rap = 48.53X0.45 = 21.84 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)X 16.165 + 5 = 48.53 M
Arae of 200thk Sand = 48.53X0.2 = 9.71 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)X 16.165 + 5 = 48.53 M
Arae of 200thk Sand = 48.53X0.2 = 9.71 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.335 )X 4.5+6+10 = 88.74 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+88.74
X 7.465 = 537.07 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 759.57 Sqm
12)Net casing Area = 759.57-12.04-0.8-0.8-160.52-22.93-17.664-21.84-9.71-9.71 = 503.56 Sqm
Slno Descrption Area
1 Stripping = 27.660 Sqm
8 Rock-toe = 12.04 Sqm
9 Behind sand Filters = 0.8 Sqm
10 Behind Metal Filters = 0.8 Sqm
11 Hearting = 160.52 Sqm
12 Inclined Sand Chimney = 17.664 Sqm
13 horizontal Sand Filter = 22.93 Sqm
14 450mm thk Rip Rap = 21.84 Sqm
15 200mm thk Metal = 9.71 Sqm
16 200mm thk sand = 9.71 Sqm
17 Net Casing Area = 503.56 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.300 Km
T.B.L = + 129.500 M Avg. G.L = + 113.945 M
Stripped.Level = + 113.645 M Stri.Lev = + 113.645 M
Height of Bund 15.855 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.645 )X 4.5+6+10+1.567+2.5= 90.81 M
Depth of Stripping ( 113.945 - 113.645 ) = 0.300 M
Area of Stripping ( 90.810 X 0.300 ) = 27.240 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.645 )X 20% 2.771 = 2.77 M
Bottom Width of Rock-Toe = 2.771 X 3 = 8.31 M
Area of Rock -Toe = 1/2X8.31X2.771 = 11.51 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.771 = 3.92 M
Area = 3.92X0.2 = 0.78 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.771 = 3.92 M
Area = 3.92X0.2 = 0.78 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.645 )X 0.5*2+3 = 17.86 M
Top Width = 3M
Arae of Hearting Soils = 3+17.86
X 14.855 = 154.94 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.645)X2+3+5-0.57-8.31- 17.86/2 = 21.90 M
Top Width = 21.9+1.5 = 23.40 M
Arae of Hearting Soils = 23.4+21.9
X 1.000 = 22.65 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.645
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 12.855 = 14.37 M
Area of Inclined Sand Chimney = 14.37 X 1.2 = 17.244 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)X 15.855 + 5 = 47.69 M
Arae of 450thk Rip Rap = 47.69X0.45 = 21.46 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)X 15.855 + 5 = 47.69 M
Arae of 200thk Sand = 47.69X0.2 = 9.54 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)X 15.855 + 5 = 47.69 M
Arae of 200thk Sand = 47.69X0.2 = 9.54 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.645 )X 4.5+6+10 = 87.35 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+87.35
X 7.155 = 509.79 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 732.29 Sqm
12)Net casing Area = 732.29-11.51-0.78-0.78-154.94-22.65-17.244-21.46-9.54-9.54 = 483.85 Sqm
Slno Descrption Area
1 Stripping = 27.240 Sqm
8 Rock-toe = 11.51 Sqm
9 Behind sand Filters = 0.78 Sqm
10 Behind Metal Filters = 0.78 Sqm
11 Hearting = 154.94 Sqm
12 Inclined Sand Chimney = 17.244 Sqm
13 horizontal Sand Filter = 22.65 Sqm
14 450mm thk Rip Rap = 21.46 Sqm
15 200mm thk Metal = 9.54 Sqm
16 200mm thk sand = 9.54 Sqm
17 Net Casing Area = 483.85 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.325 Km
T.B.L = + 129.500 M Avg. G.L = + 114.090 M
Stripped.Level = + 113.790 M Stri.Lev = + 113.790 M
Height of Bund 15.710 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.790 )X 4.5+6+10+1.567+2.5= 90.16 M
Depth of Stripping ( 114.090 - 113.790 ) = 0.300 M
Area of Stripping ( 90.160 X 0.300 ) = 27.050 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.79 )X 20% 2.742 = 2.74 M
Bottom Width of Rock-Toe = 2.742 X 3 = 8.23 M
Area of Rock -Toe = 1/2X8.23X2.742 = 11.28 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.742 = 3.88 M
Area = 3.88X0.2 = 0.78 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.742 = 3.88 M
Area = 3.88X0.2 = 0.78 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.790 )X 0.5*2+3 = 17.71 M
Top Width = 3 M
Arae of Hearting Soils = 3+17.71
X 14.710 = 152.32 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.79)X2+3+5-0.57-8.23- 17.71/2 = 21.77 M
Top Width = 21.77+1.5 = 23.27 M
Arae of Hearting Soils = 23.27+21.77
X 1.000 = 22.52 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.790
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 12.710 = 14.21 M
Area of Inclined Sand Chimney = 14.21 X 1.2 = 17.052 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.710 + 5 = 47.3 M
Arae of 450thk Rip Rap = 47.3X0.45 = 21.29 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.710 + 5 = 47.3 M
Arae of 200thk Sand = 47.3X0.2 = 9.46 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.710 + 5 = 47.3 M
Arae of 200thk Sand = 47.3X0.2 = 9.46 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.790 )X 4.5+6+10 = 86.7 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+86.7
X 7.010 = 497.18 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 719.68 Sqm
12)Net casing Area = 719.68-11.28-0.78-0.78-152.32-22.52-17.052-21.29-9.46-9.46 = 474.74 Sqm
Slno Descrption Area
1 Stripping = 27.050 Sqm
8 Rock-toe = 11.28 Sqm
9 Behind sand Filters = 0.78 Sqm
10 Behind Metal Filters = 0.78 Sqm
11 Hearting = 152.32 Sqm
12 Inclined Sand Chimney = 17.052 Sqm
13 horizontal Sand Filter = 22.52 Sqm
14 450mm thk Rip Rap = 21.29 Sqm
15 200mm thk Metal = 9.46 Sqm
16 200mm thk sand = 9.46 Sqm
17 Net Casing Area = 474.74 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.350 Km
T.B.L = + 129.500 M Avg. G.L = + 114.180 M
Stripped.Level = + 113.880 M Stri.Lev = + 113.880 M
Height of Bund 15.620 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.880 )X 4.5+6+10+1.567+2.5= 89.76 M
Depth of Stripping ( 114.180 - 113.880 ) = 0.300 M
Area of Stripping ( 89.760 X 0.300 ) = 26.930 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.88 )X 20% 2.724 = 2.72 M
Bottom Width of Rock-Toe = 2.724 X 3 = 8.17 M
Area of Rock -Toe = 1/2X8.17X2.724 = 11.13 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.724 = 3.85 M
Area = 3.85X0.2 = 0.77 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.724 = 3.85 M
Area = 3.85X0.2 = 0.77 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.880 )X 0.5*2+3 = 17.62 M
Top Width = 3M
Arae of Hearting Soils = 3+17.62
X 14.620 = 150.73 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.88)X2+3+5-0.57-8.17- 17.62/2 = 21.69 M
Top Width = 21.69+1.5 = 23.19 M
Arae of Hearting Soils = 23.19+21.69
X 1.000 = 22.44 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.880
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 12.620 = 14.11 M
Area of Inclined Sand Chimney = 14.11 X 1.2 = 16.932 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.620 + 5 = 47.06 M
Arae of 450thk Rip Rap = 47.06X0.45 = 21.18 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.620 + 5 = 47.06 M
Arae of 200thk Sand = 47.06X0.2 = 9.41 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.620 + 5 = 47.06 M
Arae of 200thk Sand = 47.06X0.2 = 9.41 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.880 )X 4.5+6+10 = 86.29 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+86.29
X 6.920 = 489.38 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 711.88 Sqm
12)Net casing Area = 711.88-11.13-0.77-0.77-150.73-22.44-16.932-21.18-9.41-9.41 = 469.11 Sqm
Slno Descrption Area
1 Stripping = 26.930 Sqm
8 Rock-toe = 11.13 Sqm
9 Behind sand Filters = 0.77 Sqm
10 Behind Metal Filters = 0.77 Sqm
11 Hearting = 150.73 Sqm
12 Inclined Sand Chimney = 16.932 Sqm
13 horizontal Sand Filter = 22.44 Sqm
14 450mm thk Rip Rap = 21.18 Sqm
15 200mm thk Metal = 9.41 Sqm
16 200mm thk sand = 9.41 Sqm
17 Net Casing Area = 469.11 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.375 Km
T.B.L = + 129.500 M Avg. G.L = + 114.170 M
Stripped.Level = + 113.870 M Stri.Lev = + 113.870 M
Height of Bund 15.630 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.870 )X 4.5+6+10+1.567+2.5= 89.8 M
Depth of Stripping ( 114.170 - 113.870 ) = 0.300 M
Area of Stripping ( 89.800 X 0.300 ) = 26.940 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.87 )X 20% 2.726 = 2.73 M
Bottom Width of Rock-Toe = 2.726 X 3 = 8.18 M
Area of Rock -Toe = 1/2X8.18X2.726 = 11.15 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.726 = 3.86 M
Area = 3.86X0.2 = 0.77 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.726 = 3.86 M
Area = 3.86X0.2 = 0.77 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.870 )X 0.5*2+3 = 17.63 M
Top Width = 3 M
Arae of Hearting Soils = 3+17.63
X 14.630 = 150.91 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.87)X2+3+5-0.57-8.18 - 17.63/2 = 21.70 M
Top Width = 21.7+1.5 = 23.20 M
Arae of Hearting Soils = 23.2+21.7
X 1.000 = 22.45 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.870
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 12.630 = 14.12 M
Area of Inclined Sand Chimney = 14.12 X 1.2 = 16.944 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)X 15.630 + 5 = 47.09 M
Arae of 450thk Rip Rap = 47.09X0.45 = 21.19 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)X 15.630 + 5 = 47.09 M
Arae of 200thk Sand = 47.09X0.2 = 9.42 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)X 15.630 + 5 = 47.09 M
Arae of 200thk Sand = 47.09X0.2 = 9.42 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.870 )X 4.5+6+10 = 86.34 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+86.34
X 6.930 = 490.26 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 712.76 Sqm
12)Net casing Area = 712.76-11.15-0.77-0.77-150.91-22.45-16.944-21.19-9.42-9.42 = 469.74 Sqm
Slno Descrption Area
1 Stripping = 26.940 Sqm
8 Rock-toe = 11.15 Sqm
9 Behind sand Filters = 0.77 Sqm
10 Behind Metal Filters = 0.77 Sqm
11 Hearting = 150.91 Sqm
12 Inclined Sand Chimney = 16.944 Sqm
13 horizontal Sand Filter = 22.45 Sqm
14 450mm thk Rip Rap = 21.19 Sqm
15 200mm thk Metal = 9.42 Sqm
16 200mm thk sand = 9.42 Sqm
17 Net Casing Area = 469.74 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.400 Km
T.B.L = + 129.500 M Avg. G.L = + 114.205 M
Stripped.Level = + 113.905 M Stri.Lev = + 113.905 M
Height of Bund 15.595 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.905 )X 4.5+6+10+1.567+2.5= 89.64 M
Depth of Stripping ( 114.205 - 113.905 ) = 0.300 M
Area of Stripping ( 89.640 X 0.300 ) = 26.890 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.905 )X 20% 2.719 = 2.72 M
Bottom Width of Rock-Toe = 2.719 X 3 = 8.16 M
Area of Rock -Toe = 1/2X8.16X2.719 = 11.09 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.719 = 3.85 M
Area = 3.85X0.2 = 0.77 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.719 = 3.85 M
Area = 3.85X0.2 = 0.77 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.905 )X 0.5*2+3 = 17.6 M
Top Width = 3 M
Arae of Hearting Soils = 3+17.6
X 14.595 = 150.33 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.905)X2+3+5-0.57-8.16
- 17.6/2 = 21.66 M
Top Width = 21.66+1.5 = 23.16 M
Arae of Hearting Soils = 23.16+21.66
X 1.000 = 22.41 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.905
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 12.595 = 14.08 M
Area of Inclined Sand Chimney = 14.08 X 1.2 = 16.896 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.595 + 5 = 46.99 M
Arae of 450thk Rip Rap = 46.99X0.45 = 21.15 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.595 + 5 = 46.99 M
Arae of 200thk Sand = 46.99X0.2 = 9.4 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.595 + 5 = 46.99 M
Arae of 200thk Sand = 46.99X0.2 = 9.4 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.905 )X 4.5+6+10 = 86.18 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+86.18
X 6.895 = 487.24 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 709.74 Sqm
12)Net casing Area = 709.74-11.09-0.77-0.77-150.33-22.41-16.896-21.15-9.4-9.4 = 467.52 Sqm
Slno Descrption Area
1 Stripping = 26.890 Sqm
8 Rock-toe = 11.09 Sqm
9 Behind sand Filters = 0.77 Sqm
10 Behind Metal Filters = 0.77 Sqm
11 Hearting = 150.33 Sqm
12 Inclined Sand Chimney = 16.896 Sqm
13 horizontal Sand Filter = 22.41 Sqm
14 450mm thk Rip Rap = 21.15 Sqm
15 200mm thk Metal = 9.4 Sqm
16 200mm thk sand = 9.4 Sqm
17 Net Casing Area = 467.52 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.425 Km
T.B.L = + 129.500 M Avg. G.L = + 114.250 M
Stripped.Level = + 113.950 M Stri.Lev = + 113.950 M
Height of Bund 15.550 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.950 )X 4.5+6+10+1.567+2.5= 89.44 M
Depth of Stripping ( 114.250 - 113.950 ) = 0.300 M
Area of Stripping ( 89.440 X 0.300 ) = 26.830 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.95 )X 20% 2.71 = 2.71 M
Bottom Width of Rock-Toe = 2.71 X 3 = 8.13 M
Area of Rock -Toe = 1/2X8.13X2.71 = 11.02 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.710 = 3.83 M
Area = 3.83X0.2 = 0.77 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.710 = 3.83 M
Area = 3.83X0.2 = 0.77 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.950 )X 0.5*2+3 = 17.55 M
Top Width = 3 M
Arae of Hearting Soils = 3+17.55
X 14.550 = 149.50 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.95)X2+3+5-0.57-8.13- 17.55/2 = 21.63 M
Top Width = 21.63+1.5 = 23.13 M
Arae of Hearting Soils = 23.13+21.63
X 1.000 = 22.38 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.950
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 12.550 = 14.03 M
Area of Inclined Sand Chimney = 14.03 X 1.2 = 16.836 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.550 + 5 = 46.87 M
Arae of 450thk Rip Rap = 46.87X0.45 = 21.09 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.550 + 5 = 46.87 M
Arae of 200thk Sand = 46.87X0.2 = 9.37 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.550 + 5 = 46.87 M
Arae of 200thk Sand = 46.87X0.2 = 9.37 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.950 )X 4.5+6+10 = 85.98 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+85.98
X 6.850 = 483.37 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 705.87 Sqm
12)Net casing Area = 705.87-11.02-0.77-0.77-149.5-22.38-16.836-21.09-9.37-9.37 = 464.76 Sqm
Slno Descrption Area
1 Stripping = 26.830 Sqm
8 Rock-toe = 11.02 Sqm
9 Behind sand Filters = 0.77 Sqm
10 Behind Metal Filters = 0.77 Sqm
11 Hearting = 149.50 Sqm
12 Inclined Sand Chimney = 16.836 Sqm
13 horizontal Sand Filter = 22.38 Sqm
14 450mm thk Rip Rap = 21.09 Sqm
15 200mm thk Metal = 9.37 Sqm
16 200mm thk sand = 9.37 Sqm
17 Net Casing Area = 464.76 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.450 Km
T.B.L = + 129.500 M Avg. G.L = + 114.225 M
Stripped.Level = + 113.925 M Stri.Lev = + 113.925 M
Height of Bund 15.575 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.925 )X 4.5+6+10+1.567+2.5= 89.55 M
Depth of Stripping ( 114.225 - 113.925 ) = 0.300 M
Area of Stripping ( 89.550 X 0.300 ) = 26.860 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.925 )X 20% 2.715 = 2.72 M
Bottom Width of Rock-Toe = 2.715 X 3 = 8.15 M
Area of Rock -Toe = 1/2X8.15X2.715 = 11.06 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.715 = 3.84 M
Area = 3.84X0.2 = 0.77 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.715 = 3.84 M
Area = 3.84X0.2 = 0.77 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.925 )X 0.5*2+3 = 17.58 M
Top Width = 3 M
Arae of Hearting Soils = 3+17.58
X 14.575 = 149.98 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.925)X2+3+5-0.57-8.15
- 17.58/2 = 21.64 M
Top Width = 21.64+1.5 = 23.14 M
Arae of Hearting Soils = 23.14+21.64
X 1.000 = 22.39 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.925
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 12.575 = 14.06 M
Area of Inclined Sand Chimney = 14.06 X 1.2 = 16.872 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.575 + 5 = 46.94 M
Arae of 450thk Rip Rap = 46.94X0.45 = 21.12 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.575 + 5 = 46.94 M
Arae of 200thk Sand = 46.94X0.2 = 9.39 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.575 + 5 = 46.94 M
Arae of 200thk Sand = 46.94X0.2 = 9.39 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.925 )X 4.5+6+10 = 86.09 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+86.09
X 6.875 = 485.51 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 708.01 Sqm
12)Net casing Area = 708.01-11.06-0.77-0.77-149.98-22.39-16.872-21.12-9.39-9.39 = 466.27 Sqm
Slno Descrption Area
1 Stripping = 26.860 Sqm
8 Rock-toe = 11.06 Sqm
9 Behind sand Filters = 0.77 Sqm
10 Behind Metal Filters = 0.77 Sqm
11 Hearting = 149.98 Sqm
12 Inclined Sand Chimney = 16.872 Sqm
13 horizontal Sand Filter = 22.39 Sqm
14 450mm thk Rip Rap = 21.12 Sqm
15 200mm thk Metal = 9.39 Sqm
16 200mm thk sand = 9.39 Sqm
17 Net Casing Area = 466.27 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.475 Km
T.B.L = + 129.500 M Avg. G.L = + 114.155 M
Stripped.Level = + 113.855 M Stri.Lev = + 113.855 M
Height of Bund 15.645 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.855 )X 4.5+6+10+1.567+2.5= 89.87 M
Depth of Stripping ( 114.155 - 113.855 ) = 0.300 M
Area of Stripping ( 89.870 X 0.300 ) = 26.960 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.855 )X 20% 2.729 = 2.73 M
Bottom Width of Rock-Toe = 2.729 X 3 = 8.19 M
Area of Rock -Toe = 1/2X8.19X2.729 = 11.18 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.729 = 3.86 M
Area = 3.86X0.2 = 0.77 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.729 = 3.86 M
Area = 3.86X0.2 = 0.77 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.855 )X 0.5*2+3 = 17.65 M
Top Width = 3 M
Arae of Hearting Soils = 3+17.65
X 14.645 = 151.21 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.855)X2+3+5-0.57-8.19
- 17.65/2 = 21.71 M
Top Width = 21.71+1.5 = 23.21 M
Arae of Hearting Soils = 23.21+21.71
X 1.000 = 22.46 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.855
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 12.645 = 14.14 M
Area of Inclined Sand Chimney = 14.14 X 1.2 = 16.968 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.645 + 5 = 47.13 M
Arae of 450thk Rip Rap = 47.13X0.45 = 21.21 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.645 + 5 = 47.13 M
Arae of 200thk Sand = 47.13X0.2 = 9.43 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.645 + 5 = 47.13 M
Arae of 200thk Sand = 47.13X0.2 = 9.43 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.855 )X 4.5+6+10 = 86.4 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+86.4
X 6.945 = 491.53 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 714.03 Sqm
12)Net casing Area = 714.03-11.18-0.77-0.77-151.21-22.46-16.968-21.21-9.43-9.43 = 470.60 Sqm
Slno Descrption Area
1 Stripping = 26.960 Sqm
8 Rock-toe = 11.18 Sqm
9 Behind sand Filters = 0.77 Sqm
10 Behind Metal Filters = 0.77 Sqm
11 Hearting = 151.21 Sqm
12 Inclined Sand Chimney = 16.968 Sqm
13 horizontal Sand Filter = 22.46 Sqm
14 450mm thk Rip Rap = 21.21 Sqm
15 200mm thk Metal = 9.43 Sqm
16 200mm thk sand = 9.43 Sqm
17 Net Casing Area = 470.60 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.500 Km
T.B.L = + 129.500 M Avg. G.L = + 114.055 M
Stripped.Level = + 113.755 M Stri.Lev = + 113.755 M
Height of Bund 15.745 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.755 )X 4.5+6+10+1.567+2.5= 90.32 M
Depth of Stripping ( 114.055 - 113.755 ) = 0.300 M
Area of Stripping ( 90.320 X 0.300 ) = 27.100 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.755 )X 20% 2.749 = 2.75 M
Bottom Width of Rock-Toe = 2.749 X 3 = 8.25 M
Area of Rock -Toe = 1/2X8.25X2.749 = 11.34 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.749 = 3.89 M
Area = 3.89X0.2 = 0.78 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.749 = 3.89 M
Area = 3.89X0.2 = 0.78 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.755 )X 0.5*2+3 = 17.75 M
Top Width = 3 M
Arae of Hearting Soils = 3+17.75
X 14.745 = 152.98 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.755)X2+3+5-0.57-8.25- 17.75/2 = 21.80 M
Top Width = 21.8+1.5 = 23.30 M
Arae of Hearting Soils = 23.3+21.8
X 1.000 = 22.55 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.755
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 12.745 = 14.25 M
Area of Inclined Sand Chimney = 14.25 X 1.2 = 17.1 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)X 15.745 + 5 = 47.39 M
Arae of 450thk Rip Rap = 47.39X0.45 = 21.33 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)X 15.745 + 5 = 47.39 M
Arae of 200thk Sand = 47.39X0.2 = 9.48 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)X 15.745 + 5 = 47.39 M
Arae of 200thk Sand = 47.39X0.2 = 9.48 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.755 )X 4.5+6+10 = 86.85 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+86.85
X 7.045 = 500.19 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 722.69 Sqm
12)Net casing Area = 722.69-11.34-0.78-0.78-152.98-22.55-17.1-21.33-9.48-9.48 = 476.87 Sqm
Slno Descrption Area
1 Stripping = 27.100 Sqm
8 Rock-toe = 11.34 Sqm
9 Behind sand Filters = 0.78 Sqm
10 Behind Metal Filters = 0.78 Sqm
11 Hearting = 152.98 Sqm
12 Inclined Sand Chimney = 17.1 Sqm
13 horizontal Sand Filter = 22.55 Sqm
14 450mm thk Rip Rap = 21.33 Sqm
15 200mm thk Metal = 9.48 Sqm
16 200mm thk sand = 9.48 Sqm
17 Net Casing Area = 476.87 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.525 Km
T.B.L = + 129.500 M Avg. G.L = + 113.980 M
Stripped.Level = + 113.680 M Stri.Lev = + 113.680 M
Height of Bund 15.820 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.680 )X 4.5+6+10+1.567+2.5= 90.66 M
Depth of Stripping ( 113.980 - 113.680 ) = 0.300 M
Area of Stripping ( 90.660 X 0.300 ) = 27.200 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.68 )X 20% 2.764 = 2.76 M
Bottom Width of Rock-Toe = 2.764 X 3 = 8.29 M
Area of Rock -Toe = 1/2X8.29X2.764 = 11.46 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.764 = 3.91 M
Area = 3.91X0.2 = 0.78 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.764 = 3.91 M
Area = 3.91X0.2 = 0.78 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.680 )X 0.5*2+3 = 17.82 M
Top Width = 3 M
Arae of Hearting Soils = 3+17.82
X 14.820 = 154.28 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.68)X2+3+5-0.57-8.29- 17.82/2 = 21.87 M
Top Width = 21.87+1.5 = 23.37 M
Arae of Hearting Soils = 23.37+21.87
X 1.000 = 22.62 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.680
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 12.820 = 14.33 M
Area of Inclined Sand Chimney = 14.33 X 1.2 = 17.196 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.820 + 5 = 47.6 M
Arae of 450thk Rip Rap = 47.6X0.45 = 21.42 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.820 + 5 = 47.6 M
Arae of 200thk Sand = 47.6X0.2 = 9.52 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.820 + 5 = 47.6 M
Arae of 200thk Sand = 47.6X0.2 = 9.52 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.680 )X 4.5+6+10 = 87.19 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+87.19
X 7.120 = 506.73 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 729.23 Sqm
12)Net casing Area = 729.23-11.46-0.78-0.78-154.28-22.62-17.196-21.42-9.52-9.52 = 481.65 Sqm
Slno Descrption Area
1 Stripping = 27.200 Sqm
8 Rock-toe = 11.46 Sqm
9 Behind sand Filters = 0.78 Sqm
10 Behind Metal Filters = 0.78 Sqm
11 Hearting = 154.28 Sqm
12 Inclined Sand Chimney = 17.196 Sqm
13 horizontal Sand Filter = 22.62 Sqm
14 450mm thk Rip Rap = 21.42 Sqm
15 200mm thk Metal = 9.52 Sqm
16 200mm thk sand = 9.52 Sqm
17 Net Casing Area = 481.65 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.550 Km
T.B.L = + 129.500 M Avg. G.L = + 113.910 M
Stripped.Level = + 113.610 M Stri.Lev = + 113.610 M
Height of Bund 15.890 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.610 )X 4.5+6+10+1.567+2.5= 90.97 M
Depth of Stripping ( 113.910 - 113.610 ) = 0.300 M
Area of Stripping ( 90.970 X 0.300 ) = 27.290 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.61 )X 20% 2.778 = 2.78 M
Bottom Width of Rock-Toe = 2.778 X 3 = 8.33 M
Area of Rock -Toe = 1/2X8.33X2.778 = 11.57 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.778 = 3.93 M
Area = 3.93X0.2 = 0.79 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.778 = 3.93 M
Area = 3.93X0.2 = 0.79 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.610 )X 0.5*2+3 = 17.89 M
Top Width = 3 M
Arae of Hearting Soils = 3+17.89
X 14.890 = 155.53 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.61)X2+3+5-0.57-8.33- 17.89/2 = 21.94 M
Top Width = 21.94+1.5 = 23.44 M
Arae of Hearting Soils = 23.44+21.94
X 1.000 = 22.69 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.610
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 12.890 = 14.41 M
Area of Inclined Sand Chimney = 14.41 X 1.2 = 17.292 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.890 + 5 = 47.79 M
Arae of 450thk Rip Rap = 47.79X0.45 = 21.51 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.890 + 5 = 47.79 M
Arae of 200thk Sand = 47.79X0.2 = 9.56 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.890 + 5 = 47.79 M
Arae of 200thk Sand = 47.79X0.2 = 9.56 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.610 )X 4.5+6+10 = 87.51 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+87.51
X 7.190 = 512.86 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 735.36 Sqm
12)Net casing Area = 735.36-11.57-0.79-0.79-155.53-22.69-17.292-21.51-9.56-9.56 = 486.07 Sqm
Slno Descrption Area
1 Stripping = 27.290 Sqm
8 Rock-toe = 11.57 Sqm
9 Behind sand Filters = 0.79 Sqm
10 Behind Metal Filters = 0.79 Sqm
11 Hearting = 155.53 Sqm
12 Inclined Sand Chimney = 17.292 Sqm
13 horizontal Sand Filter = 22.69 Sqm
14 450mm thk Rip Rap = 21.51 Sqm
15 200mm thk Metal = 9.56 Sqm
16 200mm thk sand = 9.56 Sqm
17 Net Casing Area = 486.07 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.575 Km
T.B.L = + 129.500 M Avg. G.L = + 113.845 M
Stripped.Level = + 113.545 M Stri.Lev = + 113.545 M
Height of Bund 15.955 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.545 )X 4.5+6+10+1.567+2.5= 91.26 M
Depth of Stripping ( 113.845 - 113.545 ) = 0.300 M
Area of Stripping ( 91.260 X 0.300 ) = 27.380 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.545 )X 20% 2.791 = 2.79 M
Bottom Width of Rock-Toe = 2.791 X 3 = 8.37 M
Area of Rock -Toe = 1/2X8.37X2.791 = 11.68 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.791 = 3.95 M
Area = 3.95X0.2 = 0.79 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.791 = 3.95 M
Area = 3.95X0.2 = 0.79 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.545 )X 0.5*2+3 = 17.96 M
Top Width = 3M
Arae of Hearting Soils = 3+17.96
X 14.955 = 156.73 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.545)X2+3+5-0.57-8.37
- 17.96/2 = 21.99 M
Top Width = 21.99+1.5 = 23.49 M
Arae of Hearting Soils = 23.49+21.99
X 1.000 = 22.74 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.545
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 12.955 = 14.48 M
Area of Inclined Sand Chimney = 14.48 X 1.2 = 17.376 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.955 + 5 = 47.96 M
Arae of 450thk Rip Rap = 47.96X0.45 = 21.58 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.955 + 5 = 47.96 M
Arae of 200thk Sand = 47.96X0.2 = 9.59 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.955 + 5 = 47.96 M
Arae of 200thk Sand = 47.96X0.2 = 9.59 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.545 )X 4.5+6+10 = 87.8 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+87.8
X 7.255 = 518.55 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 741.05 Sqm
12)Net casing Area = 741.05-11.68-0.79-0.79-156.73-22.74-17.376-21.58-9.59-9.59 = 490.18 Sqm
Slno Descrption Area
1 Stripping = 27.380 Sqm
8 Rock-toe = 11.68 Sqm
9 Behind sand Filters = 0.79 Sqm
10 Behind Metal Filters = 0.79 Sqm
11 Hearting = 156.73 Sqm
12 Inclined Sand Chimney = 17.376 Sqm
13 horizontal Sand Filter = 22.74 Sqm
14 450mm thk Rip Rap = 21.58 Sqm
15 200mm thk Metal = 9.59 Sqm
16 200mm thk sand = 9.59 Sqm
17 Net Casing Area = 490.18 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.600 Km
T.B.L = + 129.500 M Avg. G.L = + 113.845 M
Stripped.Level = + 113.545 M Stri.Lev = + 113.545 M
Height of Bund 15.955 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.545 )X 4.5+6+10+1.567+2.5= 91.26 M
Depth of Stripping ( 113.845 - 113.545 ) = 0.300 M
Area of Stripping ( 91.260 X 0.300 ) = 27.380 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.545 )X 20% 2.791 = 2.79 M
Bottom Width of Rock-Toe = 2.791 X 3 = 8.37 M
Area of Rock -Toe = 1/2X8.37X2.791 = 11.68 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.791 = 3.95 M
Area = 3.95X0.2 = 0.79 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.791 = 3.95 M
Area = 3.95X0.2 = 0.79 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.545 )X 0.5*2+3 = 17.96 M
Top Width = 3M
Arae of Hearting Soils = 3+17.96
X 14.955 = 156.73 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.545)X2+3+5-0.57-8.37
- 17.96/2 = 21.99 M
Top Width = 21.99+1.5 = 23.49 M
Arae of Hearting Soils = 23.49+21.99
X 1.000 = 22.74 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.545
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 12.955 = 14.48 M
Area of Inclined Sand Chimney = 14.48 X 1.2 = 17.376 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.955 + 5 = 47.96 M
Arae of 450thk Rip Rap = 47.96X0.45 = 21.58 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.955 + 5 = 47.96 M
Arae of 200thk Sand = 47.96X0.2 = 9.59 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 15.955 + 5 = 47.96 M
Arae of 200thk Sand = 47.96X0.2 = 9.59 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.545 )X 4.5+6+10 = 87.8 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+87.8
X 7.255 = 518.55 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 741.05 Sqm
12)Net casing Area = 741.05-11.68-0.79-0.79-156.73-22.74-17.376-21.58-9.59-9.59 = 490.18 Sqm
Slno Descrption Area
1 Stripping = 27.380 Sqm
8 Rock-toe = 11.68 Sqm
9 Behind sand Filters = 0.79 Sqm
10 Behind Metal Filters = 0.79 Sqm
11 Hearting = 156.73 Sqm
12 Inclined Sand Chimney = 17.376 Sqm
13 horizontal Sand Filter = 22.74 Sqm
14 450mm thk Rip Rap = 21.58 Sqm
15 200mm thk Metal = 9.59 Sqm
16 200mm thk sand = 9.59 Sqm
17 Net Casing Area = 490.18 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.625 Km
T.B.L = + 129.500 M Avg. G.L = + 113.740 M
Stripped.Level = + 113.440 M Stri.Lev = + 113.440 M
Height of Bund 16.060 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.440 )X 4.5+6+10+1.567+2.5= 91.74 M
Depth of Stripping ( 113.740 - 113.440 ) = 0.300 M
Area of Stripping ( 91.740 X 0.300 ) = 27.520 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.44 )X 20% 2.812 = 2.81 M
Bottom Width of Rock-Toe = 2.812 X 3 = 8.44 M
Area of Rock -Toe = 1/2X8.44X2.812 = 11.87 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.812 = 3.98 M
Area = 3.98X0.2 = 0.8 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.812 = 3.98 M
Area = 3.98X0.2 = 0.8 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.440 )X 0.5*2+3 = 18.06 M
Top Width = 3 M
Arae of Hearting Soils = 3+18.06
X 15.060 = 158.58 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.44)X2+3+5-0.57-8.44- 18.06/2 = 22.08 M
Top Width = 22.08+1.5 = 23.58 M
Arae of Hearting Soils = 23.58+22.08
X 1.000 = 22.83 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.440
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.060 = 14.6 M
Area of Inclined Sand Chimney = 14.6 X 1.2 = 17.52 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.060 + 5 = 48.24 M
Arae of 450thk Rip Rap = 48.24X0.45 = 21.71 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.060 + 5 = 48.24 M
Arae of 200thk Sand = 48.24X0.2 = 9.65 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.060 + 5 = 48.24 M
Arae of 200thk Sand = 48.24X0.2 = 9.65 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.440 )X 4.5+6+10 = 88.27 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+88.27
X 7.360 = 527.79 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 750.29 Sqm
12)Net casing Area = 750.29-11.87-0.8-0.8-158.58-22.83-17.52-21.71-9.65-9.65 = 496.88 Sqm
Slno Descrption Area
1 Stripping = 27.520 Sqm
8 Rock-toe = 11.87 Sqm
9 Behind sand Filters = 0.8 Sqm
10 Behind Metal Filters = 0.8 Sqm
11 Hearting = 158.58 Sqm
12 Inclined Sand Chimney = 17.52 Sqm
13 horizontal Sand Filter = 22.83 Sqm
14 450mm thk Rip Rap = 21.71 Sqm
15 200mm thk Metal = 9.65 Sqm
16 200mm thk sand = 9.65 Sqm
17 Net Casing Area = 496.88 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.650 Km
T.B.L = + 129.500 M Avg. G.L = + 113.700 M
Stripped.Level = + 113.400 M Stri.Lev = + 113.400 M
Height of Bund 16.100 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.400 )X 4.5+6+10+1.567+2.5= 91.92 M
Depth of Stripping ( 113.700 - 113.400 ) = 0.300 M
Area of Stripping ( 91.920 X 0.300 ) = 27.580 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.4 )X 20% 2.82 = 2.82 M
Bottom Width of Rock-Toe = 2.82 X 3 = 8.46 M
Area of Rock -Toe = 1/2X8.46X2.82 = 11.93 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.820 = 3.99 M
Area = 3.99X0.2 = 0.8 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.820 = 3.99 M
Area = 3.99X0.2 = 0.8 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.400 )X 0.5*2+3 = 18.1 M
Top Width = 3 M
Arae of Hearting Soils = 3+18.1
X 15.100 = 159.31 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.4)X2+3+5-0.57-8.46- 18.1/2 = 22.12 M
Top Width = 22.12+1.5 = 23.62 M
Arae of Hearting Soils = 23.62+22.12
X 1.000 = 22.87 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.400
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.100 = 14.65 M
Area of Inclined Sand Chimney = 14.65 X 1.2 = 17.58 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.100 + 5 = 48.35 M
Arae of 450thk Rip Rap = 48.35X0.45 = 21.76 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.100 + 5 = 48.35 M
Arae of 200thk Sand = 48.35X0.2 = 9.67 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.100 + 5 = 48.35 M
Arae of 200thk Sand = 48.35X0.2 = 9.67 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.400 )X 4.5+6+10 = 88.45 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+88.45
X 7.400 = 531.32 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 753.82 Sqm
12)Net casing Area = 753.82-11.93-0.8-0.8-159.31-22.87-17.58-21.76-9.67-9.67 = 499.43 Sqm
Slno Descrption Area
1 Stripping = 27.580 Sqm
8 Rock-toe = 11.93 Sqm
9 Behind sand Filters = 0.8 Sqm
10 Behind Metal Filters = 0.8 Sqm
11 Hearting = 159.31 Sqm
12 Inclined Sand Chimney = 17.58 Sqm
13 horizontal Sand Filter = 22.87 Sqm
14 450mm thk Rip Rap = 21.76 Sqm
15 200mm thk Metal = 9.67 Sqm
16 200mm thk sand = 9.67 Sqm
17 Net Casing Area = 499.43 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.675 Km
T.B.L = + 129.500 M Avg. G.L = + 113.695 M
Stripped.Level = + 113.395 M Stri.Lev = + 113.395 M
Height of Bund 16.105 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.395 )X 4.5+6+10+1.567+2.5= 91.94 M
Depth of Stripping ( 113.695 - 113.395 ) = 0.300 M
Area of Stripping ( 91.940 X 0.300 ) = 27.580 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.395 )X 20% 2.821 = 2.82 M
Bottom Width of Rock-Toe = 2.821 X 3 = 8.46 M
Area of Rock -Toe = 1/2X8.46X2.821 = 11.93 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.821 = 3.99 M
Area = 3.99X0.2 = 0.8 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.821 = 3.99 M
Area = 3.99X0.2 = 0.8 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.395 )X 0.5*2+3 = 18.11 M
Top Width = 3 M
Arae of Hearting Soils = 3+18.11
X 15.105 = 159.43 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.395)X2+3+5-0.57-8.46
- 18.11/2 = 22.13 M
Top Width = 22.13+1.5 = 23.63 M
Arae of Hearting Soils = 23.63+22.13
X 1.000 = 22.88 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.395
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.105 = 14.65 M
Area of Inclined Sand Chimney = 14.65 X 1.2 = 17.58 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.105 + 5 = 48.36 M
Arae of 450thk Rip Rap = 48.36X0.45 = 21.76 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.105 + 5 = 48.36 M
Arae of 200thk Sand = 48.36X0.2 = 9.67 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.105 + 5 = 48.36 M
Arae of 200thk Sand = 48.36X0.2 = 9.67 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.395 )X 4.5+6+10 = 88.47 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+88.47
X 7.405 = 531.75 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 754.25 Sqm
12)Net casing Area = 754.25-11.93-0.8-0.8-159.43-22.88-17.58-21.76-9.67-9.67 = 499.73 Sqm
Slno Descrption Area
1 Stripping = 27.580 Sqm
8 Rock-toe = 11.93 Sqm
9 Behind sand Filters = 0.8 Sqm
10 Behind Metal Filters = 0.8 Sqm
11 Hearting = 159.43 Sqm
12 Inclined Sand Chimney = 17.58 Sqm
13 horizontal Sand Filter = 22.88 Sqm
14 450mm thk Rip Rap = 21.76 Sqm
15 200mm thk Metal = 9.67 Sqm
16 200mm thk sand = 9.67 Sqm
17 Net Casing Area = 499.73 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.700 Km
T.B.L = + 129.500 M Avg. G.L = + 113.540 M
Stripped.Level = + 113.240 M Stri.Lev = + 113.240 M
Height of Bund 16.260 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.240 )X 4.5+6+10+1.567+2.5= 92.64 M
Depth of Stripping ( 113.540 - 113.240 ) = 0.300 M
Area of Stripping ( 92.640 X 0.300 ) = 27.790 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.24 )X 20% 2.852 = 2.85 M
Bottom Width of Rock-Toe = 2.852 X 3 = 8.56 M
Area of Rock -Toe = 1/2X8.56X2.852 = 12.21 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.852 = 4.03 M
Area = 4.03X0.2 = 0.81 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.852 = 4.03 M
Area = 4.03X0.2 = 0.81 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.240 )X 0.5*2+3 = 18.26 M
Top Width = 3M
Arae of Hearting Soils = 3+18.26
X 15.260 = 162.21 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.24)X2+3+5-0.57-8.56- 18.26/2 = 22.26 M
Top Width = 22.26+1.5 = 23.76 M
Arae of Hearting Soils = 23.76+22.26
X 1.000 = 23.01 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.240
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.260 = 14.83 M
Area of Inclined Sand Chimney = 14.83 X 1.2 = 17.796 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.260 + 5 = 48.78 M
Arae of 450thk Rip Rap = 48.78X0.45 = 21.95 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.260 + 5 = 48.78 M
Arae of 200thk Sand = 48.78X0.2 = 9.76 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.260 + 5 = 48.78 M
Arae of 200thk Sand = 48.78X0.2 = 9.76 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.240 )X 4.5+6+10 = 89.17 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+89.17
X 7.560 = 545.53 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 768.03 Sqm
12)Net casing Area = 768.03-12.21-0.81-0.81-162.21-23.01-17.796-21.95-9.76-9.76 = 509.71 Sqm
Slno Descrption Area
1 Stripping = 27.790 Sqm
8 Rock-toe = 12.21 Sqm
9 Behind sand Filters = 0.81 Sqm
10 Behind Metal Filters = 0.81 Sqm
11 Hearting = 162.21 Sqm
12 Inclined Sand Chimney = 17.796 Sqm
13 horizontal Sand Filter = 23.01 Sqm
14 450mm thk Rip Rap = 21.95 Sqm
15 200mm thk Metal = 9.76 Sqm
16 200mm thk sand = 9.76 Sqm
17 Net Casing Area = 509.71 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.725 Km
T.B.L = + 129.500 M Avg. G.L = + 113.475 M
Stripped.Level = + 113.175 M Stri.Lev = + 113.175 M
Height of Bund 16.325 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.175 )X 4.5+6+10+1.567+2.5= 92.93 M
Depth of Stripping ( 113.475 - 113.175 ) = 0.300 M
Area of Stripping ( 92.930 X 0.300 ) = 27.880 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.175 )X 20% 2.865 = 2.87 M
Bottom Width of Rock-Toe = 2.865 X 3 = 8.60 M
Area of Rock -Toe = 1/2X8.6X2.865 = 12.32 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.865 = 4.05 M
Area = 4.05X0.2 = 0.81 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.865 = 4.05 M
Area = 4.05X0.2 = 0.81 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.175 )X 0.5*2+3 = 18.33 M
Top Width = 3M
Arae of Hearting Soils = 3+18.33
X 15.325 = 163.44 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.175)X2+3+5-0.57-8.6- 18.33/2 = 22.32 M
Top Width = 22.32+1.5 = 23.82 M
Arae of Hearting Soils = 23.82+22.32
X 1.000 = 23.07 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.175
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.325 = 14.9 M
Area of Inclined Sand Chimney = 14.9 X 1.2 = 17.88 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.325 + 5 = 48.96 M
Arae of 450thk Rip Rap = 48.96X0.45 = 22.03 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.325 + 5 = 48.96 M
Arae of 200thk Sand = 48.96X0.2 = 9.79 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.325 + 5 = 48.96 M
Arae of 200thk Sand = 48.96X0.2 = 9.79 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.175 )X 4.5+6+10 = 89.46 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+89.46
X 7.625 = 551.33 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 773.83 Sqm
12)Net casing Area = 773.83-12.32-0.81-0.81-163.44-23.07-17.88-22.03-9.79-9.79 = 513.89 Sqm
Slno Descrption Area
1 Stripping = 27.880 Sqm
8 Rock-toe = 12.32 Sqm
9 Behind sand Filters = 0.81 Sqm
10 Behind Metal Filters = 0.81 Sqm
11 Hearting = 163.44 Sqm
12 Inclined Sand Chimney = 17.88 Sqm
13 horizontal Sand Filter = 23.07 Sqm
14 450mm thk Rip Rap = 22.03 Sqm
15 200mm thk Metal = 9.79 Sqm
16 200mm thk sand = 9.79 Sqm
17 Net Casing Area = 513.89 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.750 Km
T.B.L = + 129.500 M Avg. G.L = + 113.380 M
Stripped.Level = + 113.080 M Stri.Lev = + 113.080 M
Height of Bund 16.420 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.080 )X 4.5+6+10+1.567+2.5= 93.36 M
Depth of Stripping ( 113.380 - 113.080 ) = 0.300 M
Area of Stripping ( 93.360 X 0.300 ) = 28.010 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.08 )X 20% 2.884 = 2.88 M
Bottom Width of Rock-Toe = 2.884 X 3 = 8.65 M
Area of Rock -Toe = 1/2X8.65X2.884 = 12.47 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.884 = 4.08 M
Area = 4.08X0.2 = 0.82 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.884 = 4.08 M
Area = 4.08X0.2 = 0.82 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.080 )X 0.5*2+3 = 18.42 M
Top Width = 3 M
Arae of Hearting Soils = 3+18.42
X 15.420 = 165.15 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.08)X2+3+5-0.57-8.65- 18.42/2 = 22.41 M
Top Width = 22.41+1.5 = 23.91 M
Arae of Hearting Soils = 23.91+22.41
X 1.000 = 23.16 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.080
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.420 = 15 M
Area of Inclined Sand Chimney = 15 X 1.2 = 18 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.420 + 5 = 49.21 M
Arae of 450thk Rip Rap = 49.21X0.45 = 22.14 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.420 + 5 = 49.21 M
Arae of 200thk Sand = 49.21X0.2 = 9.84 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.420 + 5 = 49.21 M
Arae of 200thk Sand = 49.21X0.2 = 9.84 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.080 )X 4.5+6+10 = 89.89 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+89.89
X 7.720 = 559.85 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 782.35 Sqm
12)Net casing Area = 782.35-12.47-0.82-0.82-165.15-23.16-18-22.14-9.84-9.84 = 520.11 Sqm
Slno Descrption Area
1 Stripping = 28.010 Sqm
8 Rock-toe = 12.47 Sqm
9 Behind sand Filters = 0.82 Sqm
10 Behind Metal Filters = 0.82 Sqm
11 Hearting = 165.15 Sqm
12 Inclined Sand Chimney = 18 Sqm
13 horizontal Sand Filter = 23.16 Sqm
14 450mm thk Rip Rap = 22.14 Sqm
15 200mm thk Metal = 9.84 Sqm
16 200mm thk sand = 9.84 Sqm
17 Net Casing Area = 520.11 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.775 Km
T.B.L = + 129.500 M Avg. G.L = + 113.340 M
Stripped.Level = + 113.040 M Stri.Lev = + 113.040 M
Height of Bund 16.460 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 113.040 )X 4.5+6+10+1.567+2.5= 93.54 M
Depth of Stripping ( 113.340 - 113.040 ) = 0.300 M
Area of Stripping ( 93.540 X 0.300 ) = 28.060 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-113.04 )X 20% 2.892 = 2.89 M
Bottom Width of Rock-Toe = 2.892 X 3 = 8.68 M
Area of Rock -Toe = 1/2X8.68X2.892 = 12.55 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.892 = 4.09 M
Area = 4.09X0.2 = 0.82 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.892 = 4.09 M
Area = 4.09X0.2 = 0.82 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 113.040 )X 0.5*2+3 = 18.46 M
Top Width = 3M
Arae of Hearting Soils = 3+18.46
X 15.460 = 165.89 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-113.04)X2+3+5-0.57-8.68- 18.46/2 = 22.44 M
Top Width = 22.44+1.5 = 23.94 M
Arae of Hearting Soils = 23.94+22.44
X 1.000 = 23.19 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 114.040
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.460 = 15.05 M
Area of Inclined Sand Chimney = 15.05 X 1.2 = 18.06 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.460 + 5 = 49.32 M
Arae of 450thk Rip Rap = 49.32X0.45 = 22.19 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.460 + 5 = 49.32 M
Arae of 200thk Sand = 49.32X0.2 = 9.86 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 16.460 + 5 = 49.32 M
Arae of 200thk Sand = 49.32X0.2 = 9.86 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 113.040 )X 4.5+6+10 = 90.07 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+90.07
X 7.760 = 563.45 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 785.95 Sqm
12)Net casing Area = 785.95-12.55-0.82-0.82-165.89-23.19-18.06-22.19-9.86-9.86 = 522.71 Sqm
Slno Descrption Area
1 Stripping = 28.060 Sqm
8 Rock-toe = 12.55 Sqm
9 Behind sand Filters = 0.82 Sqm
10 Behind Metal Filters = 0.82 Sqm
11 Hearting = 165.89 Sqm
12 Inclined Sand Chimney = 18.06 Sqm
13 horizontal Sand Filter = 23.19 Sqm
14 450mm thk Rip Rap = 22.19 Sqm
15 200mm thk Metal = 9.86 Sqm
16 200mm thk sand = 9.86 Sqm
17 Net Casing Area = 522.71 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.800 Km
T.B.L = + 129.500 M Avg. G.L = + 113.060 M
Stripped.Level = + 112.760 M Stri.Lev = + 112.760 M
Height of Bund 16.740 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 112.760 )X 4.5+6+10+1.567+2.5= 94.8 M
Depth of Stripping ( 113.060 - 112.760 ) = 0.300 M
Area of Stripping ( 94.800 X 0.300 ) = 28.440 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-112.76 )X 20% 2.948 = 2.95 M
Bottom Width of Rock-Toe = 2.948 X 3 = 8.84 M
Area of Rock -Toe = 1/2X8.84X2.948 = 13.03 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.948 = 4.17 M
Area = 4.17X0.2 = 0.83 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.948 = 4.17 M
Area = 4.17X0.2 = 0.83 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 112.760 )X 0.5*2+3 = 18.74 M
Top Width = 3M
Arae of Hearting Soils = 3+18.74
X 15.740 = 171.09 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-112.76)X2+3+5-0.57-8.84 - 18.74/2 = 22.70 M
Top Width = 22.7+1.5 = 24.20 M
Arae of Hearting Soils = 24.2+22.7
X 1.000 = 23.45 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 113.760
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.740 = 15.36 M
Area of Inclined Sand Chimney = 15.36 X 1.2 = 18.432 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)X 16.740 + 5 = 50.07 M
Arae of 450thk Rip Rap = 50.07X0.45 = 22.53 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)X 16.740 + 5 = 50.07 M
Arae of 200thk Sand = 50.07X0.2 = 10.01 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)X 16.740 + 5 = 50.07 M
Arae of 200thk Sand = 50.07X0.2 = 10.01 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 112.760 )X 4.5+6+10 = 91.33 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+91.33
X 8.040 = 588.85 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 811.35 Sqm
12)Net casing Area = 811.35-13.03-0.83-0.83-171.09-23.45-18.432-22.53-10.01-10.01 = 541.14 Sqm
Slno Descrption Area
1 Stripping = 28.440 Sqm
8 Rock-toe = 13.03 Sqm
9 Behind sand Filters = 0.83 Sqm
10 Behind Metal Filters = 0.83 Sqm
11 Hearting = 171.09 Sqm
12 Inclined Sand Chimney = 18.432 Sqm
13 horizontal Sand Filter = 23.45 Sqm
14 450mm thk Rip Rap = 22.53 Sqm
15 200mm thk Metal = 10.01 Sqm
16 200mm thk sand = 10.01 Sqm
17 Net Casing Area = 541.14 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.825 Km
T.B.L = + 131.000 M Avg. G.L = + 112.955 M
Stripped.Level = + 112.655 M Stri.Lev = + 112.655 M
Height of Bund 18.345 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 131.000 - 112.655 )X 4.5+6+10+1.567+2.5= 102 M
Depth of Stripping ( 112.955 - 112.655 ) = 0.300 M
Area of Stripping ( 102.020 X 0.300 ) = 30.610 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-112.655 )X 20% 2.969 = 2.97 M
Bottom Width of Rock-Toe = 2.969 X 3 = 8.91 M
Area of Rock -Toe = 1/2X8.91X2.969 = 13.23 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.969 = 4.2 M
Area = 4.2X0.2 = 0.84 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 2.969 = 4.2 M
Area = 4.2X0.2 = 0.84 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 112.655 )X 0.5*2+3 = 18.85 M
Top Width = 3M
Arae of Hearting Soils = 3+18.85
X 15.845 = 173.11 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 131-112.655)X2+3+5-0.57-8.91- 18.85/2 = 25.79 M
Top Width = 25.79+1.5 = 27.29 M
Arae of Hearting Soils = 27.29+25.79
X 1.000 = 26.54 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 113.655
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 13.845 = 15.48 M
Area of Inclined Sand Chimney = 15.48 X 1.2 = 18.576 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.345 + 5 = 54.4 M
Arae of 450thk Rip Rap = 54.4X0.45 = 24.48 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.345 + 5 = 54.4 M
Arae of 200thk Sand = 54.4X0.2 = 10.88 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.345 + 5 = 54.4 M
Arae of 200thk Sand = 54.4X0.2 = 10.88 Sqm
9) Area of Bund
Bottom Width ( 131.000 - 112.655 )X 4.5+6+10 = 98.55 M
At 120.8 Incl Berm ( 131.000 - 120.800 )X 4.5+6+10 61.9 M
Top Width = 6M
Arae of Bund up to Berm = 61.9+98.55
X 8.145 = 653.43 Sqm
2
Arae of Bund Berm to TBL = 6+51.9
X 10.200 = 295.29 Sqm
2
Total 948.72 Sqm
12)Net casing Area = 948.72-13.23-0.84-0.84-173.11-26.54-18.576-24.48-10.88-10.88 = 669.34 Sqm
Slno Descrption Area
1 Stripping = 30.610 Sqm
8 Rock-toe = 13.23 Sqm
9 Behind sand Filters = 0.84 Sqm
10 Behind Metal Filters = 0.84 Sqm
11 Hearting = 173.11 Sqm
12 Inclined Sand Chimney = 18.576 Sqm
13 horizontal Sand Filter = 26.54 Sqm
14 450mm thk Rip Rap = 24.48 Sqm
15 200mm thk Metal = 10.88 Sqm
16 200mm thk sand = 10.88 Sqm
17 Net Casing Area = 669.34 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.850 Km
T.B.L = + 129.500 M Avg. G.L = + 112.705 M
Stripped.Level = + 112.405 M Stri.Lev = + 112.405 M
Height of Bund 17.095 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 112.405 )X 4.5+6+10+1.567+2.5= 96.39 M
Depth of Stripping ( 112.705 - 112.405 ) = 0.300 M
Area of Stripping ( 96.390 X 0.300 ) = 28.920 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-112.405 )X 20% 3.019 = 3.02 M
Bottom Width of Rock-Toe = 3.019 X 3 = 9.06 M
Area of Rock -Toe = 1/2X9.06X3.019 = 13.68 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.019 = 4.27 M
Area = 4.27X0.2 = 0.85 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.019 = 4.27 M
Area = 4.27X0.2 = 0.85 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 112.405 )X 0.5*2+3 = 19.1 M
Top Width = 3M
Arae of Hearting Soils = 3+19.1
X 16.095 = 177.85 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-112.405)X2+3+5-0.57-9.06
- 19.1/2 = 23.01 M
Top Width = 23.01+1.5 = 24.51 M
Arae of Hearting Soils = 24.51+23.01
X 1.000 = 23.76 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 113.405
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 14.095 = 15.76 M
Area of Inclined Sand Chimney = 15.76 X 1.2 = 18.912 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 17.095 + 5 = 51.03 M
Arae of 450thk Rip Rap = 51.03X0.45 = 22.96 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 17.095 + 5 = 51.03 M
Arae of 200thk Sand = 51.03X0.2 = 10.21 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 17.095 + 5 = 51.03 M
Arae of 200thk Sand = 51.03X0.2 = 10.21 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 112.405 )X 4.5+6+10 = 92.93 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+92.93
X 8.395 = 621.57 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 844.07 Sqm
12)Net casing Area = 844.07-13.68-0.85-0.85-177.85-23.76-18.912-22.96-10.21-10.21 = 564.79 Sqm
Slno Descrption Area
1 Stripping = 28.920 Sqm
8 Rock-toe = 13.68 Sqm
9 Behind sand Filters = 0.85 Sqm
10 Behind Metal Filters = 0.85 Sqm
11 Hearting = 177.85 Sqm
12 Inclined Sand Chimney = 18.912 Sqm
13 horizontal Sand Filter = 23.76 Sqm
14 450mm thk Rip Rap = 22.96 Sqm
15 200mm thk Metal = 10.21 Sqm
16 200mm thk sand = 10.21 Sqm
17 Net Casing Area = 564.79 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.875 Km
T.B.L = + 131.000 M Avg. G.L = + 112.675 M
Stripped.Level = + 112.375 M Stri.Lev = + 112.375 M
Height of Bund 18.625 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 131.000 - 112.375 )X 4.5+6+10+1.567+2.5= 103.3 M
Depth of Stripping ( 112.675 - 112.375 ) = 0.300 M
Area of Stripping ( 103.280 X 0.300 ) = 30.980 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-112.375 )X 20% 3.025 = 3.03 M
Bottom Width of Rock-Toe = 3.025 X 3 = 9.08 M
Area of Rock -Toe = 1/2X9.08X3.025 = 13.73 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.025 = 4.28 M
Area = 4.28X0.2 = 0.86 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.025 = 4.28 M
Area = 4.28X0.2 = 0.86 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 112.375 )X 0.5*2+3 = 19.13 M
Top Width = 3M
Arae of Hearting Soils = 3+19.13
X 16.125 = 178.42 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 131-112.375)X2+3+5-0.57-9.08- 19.13/2 = 26.04 M
Top Width = 26.04+1.5 = 27.54 M
Arae of Hearting Soils = 27.54+26.04
X 1.000 = 26.79 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 113.375
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 14.125 = 15.79 M
Area of Inclined Sand Chimney = 15.79 X 1.2 = 18.948 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.625 + 5 = 55.15 M
Arae of 450thk Rip Rap = 55.15X0.45 = 24.82 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.625 + 5 = 55.15 M
Arae of 200thk Sand = 55.15X0.2 = 11.03 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.625 + 5 = 55.15 M
Arae of 200thk Sand = 55.15X0.2 = 11.03 Sqm
9) Area of Bund
Bottom Width ( 131.000 - 112.375 )X 4.5+6+10 = 99.81 M
At 120.8 Incl Berm ( 131.000 - 120.800 )X 4.5+6+10 61.9 M
Top Width = 6M
Arae of Bund up to Berm = 61.9+99.81
X 8.425 = 681.20 Sqm
2
Arae of Bund Berm to TBL = 6+51.9
X 10.200 = 295.29 Sqm
2
Total 976.49 Sqm
12)Net casing Area = 976.49-13.73-0.86-0.86-178.42-26.79-18.948-24.82-11.03-11.03 = 690.00 Sqm
Slno Descrption Area
1 Stripping = 30.980 Sqm
8 Rock-toe = 13.73 Sqm
9 Behind sand Filters = 0.86 Sqm
10 Behind Metal Filters = 0.86 Sqm
11 Hearting = 178.42 Sqm
12 Inclined Sand Chimney = 18.948 Sqm
13 horizontal Sand Filter = 26.79 Sqm
14 450mm thk Rip Rap = 24.82 Sqm
15 200mm thk Metal = 11.03 Sqm
16 200mm thk sand = 11.03 Sqm
17 Net Casing Area = 690.00 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.900 Km
T.B.L = + 131.000 M Avg. G.L = + 112.220 M
Stripped.Level = + 111.920 M Stri.Lev = + 111.920 M
Height of Bund 19.080 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 131.000 - 111.920 )X 4.5+6+10+1.567+2.5= 105.3 M
Depth of Stripping ( 112.220 - 111.920 ) = 0.300 M
Area of Stripping ( 105.330 X 0.300 ) = 31.600 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-111.92 )X 20% 3.116 = 3.12 M
Bottom Width of Rock-Toe = 3.116 X 3 = 9.35 M
Area of Rock -Toe = 1/2X9.35X3.116 = 14.57 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.116 = 4.41 M
Area = 4.41X0.2 = 0.88 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.116 = 4.41 M
Area = 4.41X0.2 = 0.88 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 111.920 )X 0.5*2+3 = 19.58 M
Top Width = 3M
Arae of Hearting Soils = 3+19.58
X 16.580 = 187.19 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 131-111.92)X2+3+5-0.57-9.35 - 19.58/2 = 26.45 M
Top Width = 26.45+1.5 = 27.95 M
Arae of Hearting Soils = 27.95+26.45
X 1.000 = 27.20 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 112.920
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 14.580 = 16.3 M
Area of Inclined Sand Chimney = 16.3 X 1.2 = 19.56 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 19.080 + 5 = 56.37 M
Arae of 450thk Rip Rap = 56.37X0.45 = 25.37 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 19.080 + 5 = 56.37 M
Arae of 200thk Sand = 56.37X0.2 = 11.27 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 19.080 + 5 = 56.37 M
Arae of 200thk Sand = 56.37X0.2 = 11.27 Sqm
9) Area of Bund
Bottom Width ( 131.000 - 111.920 )X 4.5+6+10 = 101.86 M
At 120.8 Incl Berm ( 131.000 - 120.800 )X 4.5+6+10 61.9 M
Top Width = 6M
Arae of Bund up to Berm = 61.9+101.86
X 8.880 = 727.09 Sqm
2
Arae of Bund Berm to TBL = 6+51.9
X 10.200 = 295.29 Sqm
2
Total 1022.38 Sqm
12)Net casing Area = 1022.38-14.57-0.88-0.88-187.19-27.2-19.56-25.37-11.27-11.27 = 724.19 Sqm
Slno Descrption Area
1 Stripping = 31.600 Sqm
8 Rock-toe = 14.57 Sqm
9 Behind sand Filters = 0.88 Sqm
10 Behind Metal Filters = 0.88 Sqm
11 Hearting = 187.19 Sqm
12 Inclined Sand Chimney = 19.56 Sqm
13 horizontal Sand Filter = 27.20 Sqm
14 450mm thk Rip Rap = 25.37 Sqm
15 200mm thk Metal = 11.27 Sqm
16 200mm thk sand = 11.27 Sqm
17 Net Casing Area = 724.19 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.925 Km
T.B.L = + 129.500 M Avg. G.L = + 112.000 M
Stripped.Level = + 111.700 M Stri.Lev = + 111.700 M
Height of Bund 17.800 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 111.700 )X 4.5+6+10+1.567+2.5= 99.57 M
Depth of Stripping ( 112.000 - 111.700 ) = 0.300 M
Area of Stripping ( 99.570 X 0.300 ) = 29.870 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-111.7 )X 20% 3.16 = 3.16 M
Bottom Width of Rock-Toe = 3.16 X 3 = 9.48 M
Area of Rock -Toe = 1/2X9.48X3.16 = 14.98 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.160 = 4.47 M
Area = 4.47X0.2 = 0.89 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.160 = 4.47 M
Area = 4.47X0.2 = 0.89 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 111.700 )X 0.5*2+3 = 19.8 M
Top Width = 3M
Arae of Hearting Soils = 3+19.8
X 16.800 = 191.52 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-111.7)X2+3+5-0.57-9.48- 19.8/2 = 23.65 M
Top Width = 23.65+1.5 = 25.15 M
Arae of Hearting Soils = 25.15+23.65
X 1.000 = 24.40 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 112.700
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 14.800 = 16.55 M
Area of Inclined Sand Chimney = 16.55 X 1.2 = 19.86 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 17.800 + 5 = 52.93 M
Arae of 450thk Rip Rap = 52.93X0.45 = 23.82 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 17.800 + 5 = 52.93 M
Arae of 200thk Sand = 52.93X0.2 = 10.59 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 17.800 + 5 = 52.93 M
Arae of 200thk Sand = 52.93X0.2 = 10.59 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 111.700 )X 4.5+6+10 = 96.1 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+96.1
X 9.100 = 688.19 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 910.69 Sqm
12)Net casing Area = 910.69-14.98-0.89-0.89-191.52-24.4-19.86-23.82-10.59-10.59 = 613.15 Sqm
Slno Descrption Area
1 Stripping = 29.870 Sqm
8 Rock-toe = 14.98 Sqm
9 Behind sand Filters = 0.89 Sqm
10 Behind Metal Filters = 0.89 Sqm
11 Hearting = 191.52 Sqm
12 Inclined Sand Chimney = 19.86 Sqm
13 horizontal Sand Filter = 24.40 Sqm
14 450mm thk Rip Rap = 23.82 Sqm
15 200mm thk Metal = 10.59 Sqm
16 200mm thk sand = 10.59 Sqm
17 Net Casing Area = 613.15 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.950 Km
T.B.L = + 129.500 M Avg. G.L = + 111.720 M
Stripped.Level = + 111.420 M Stri.Lev = + 111.420 M
Height of Bund 18.080 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 111.420 )X 4.5+6+10+1.567+2.5= 100.8 M
Depth of Stripping ( 111.720 - 111.420 ) = 0.300 M
Area of Stripping ( 100.830 X 0.300 ) = 30.250 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-111.42 )X 20% 3.216 = 3.22 M
Bottom Width of Rock-Toe = 3.216 X 3 = 9.65 M
Area of Rock -Toe = 1/2X9.65X3.216 = 15.52 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.216 = 4.55 M
Area = 4.55X0.2 = 0.91 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.216 = 4.55 M
Area = 4.55X0.2 = 0.91 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 111.420 )X 0.5*2+3 = 20.08 M
Top Width = 3M
Arae of Hearting Soils = 3+20.08
X 17.080 = 197.10 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-111.42)X2+3+5-0.57-9.65 - 20.08/2 = 23.90 M
Top Width = 23.9+1.5 = 25.40 M
Arae of Hearting Soils = 25.4+23.9
X 1.000 = 24.65 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 112.420
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 15.080 = 16.86 M
Area of Inclined Sand Chimney = 16.86 X 1.2 = 20.232 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)X 18.080 + 5 = 53.68 M
Arae of 450thk Rip Rap = 53.68X0.45 = 24.16 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)X 18.080 + 5 = 53.68 M
Arae of 200thk Sand = 53.68X0.2 = 10.74 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)X 18.080 + 5 = 53.68 M
Arae of 200thk Sand = 53.68X0.2 = 10.74 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 111.420 )X 4.5+6+10 = 97.36 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+97.36
X 9.380 = 715.27 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 937.77 Sqm
12)Net casing Area = 937.77-15.52-0.91-0.91-197.1-24.65-20.232-24.16-10.74-10.74 = 632.81 Sqm
Slno Descrption Area
1 Stripping = 30.250 Sqm
8 Rock-toe = 15.52 Sqm
9 Behind sand Filters = 0.91 Sqm
10 Behind Metal Filters = 0.91 Sqm
11 Hearting = 197.10 Sqm
12 Inclined Sand Chimney = 20.232 Sqm
13 horizontal Sand Filter = 24.65 Sqm
14 450mm thk Rip Rap = 24.16 Sqm
15 200mm thk Metal = 10.74 Sqm
16 200mm thk sand = 10.74 Sqm
17 Net Casing Area = 632.81 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 0.975 Km
T.B.L = + 129.500 M Avg. G.L = + 111.415 M
Stripped.Level = + 111.115 M Stri.Lev = + 111.115 M
Height of Bund 18.385 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 111.115 )X 4.5+6+10+1.567+2.5= 102.2 M
Depth of Stripping ( 111.415 - 111.115 ) = 0.300 M
Area of Stripping ( 102.200 X 0.300 ) = 30.660 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-111.115 )X 20% 3.277 = 3.28 M
Bottom Width of Rock-Toe = 3.277 X 3 = 9.83 M
Area of Rock -Toe = 1/2X9.83X3.277 = 16.11 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.277 = 4.63 M
Area = 4.63X0.2 = 0.93 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.277 = 4.63 M
Area = 4.63X0.2 = 0.93 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 111.115 )X 0.5*2+3 = 20.39 M
Top Width = 3M
Arae of Hearting Soils = 3+20.39
X 17.385 = 203.32 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-111.115)X2+3+5-0.57-9.83
- 20.39/2 = 24.18 M
Top Width = 24.18+1.5 = 25.68 M
Arae of Hearting Soils = 25.68+24.18
X 1.000 = 24.93 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 112.115
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 15.385 = 17.2 M
Area of Inclined Sand Chimney = 17.2 X 1.2 = 20.64 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.385 + 5 = 54.5 M
Arae of 450thk Rip Rap = 54.5X0.45 = 24.53 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.385 + 5 = 54.5 M
Arae of 200thk Sand = 54.5X0.2 = 10.9 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.385 + 5 = 54.5 M
Arae of 200thk Sand = 54.5X0.2 = 10.9 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 111.115 )X 4.5+6+10 = 98.73 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+98.73
X 9.685 = 745.16 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 967.66 Sqm
12)Net casing Area = 967.66-16.11-0.93-0.93-203.32-24.93-20.64-24.53-10.9-10.9 = 654.47 Sqm
Slno Descrption Area
1 Stripping = 30.660 Sqm
8 Rock-toe = 16.11 Sqm
9 Behind sand Filters = 0.93 Sqm
10 Behind Metal Filters = 0.93 Sqm
11 Hearting = 203.32 Sqm
12 Inclined Sand Chimney = 20.64 Sqm
13 horizontal Sand Filter = 24.93 Sqm
14 450mm thk Rip Rap = 24.53 Sqm
15 200mm thk Metal = 10.9 Sqm
16 200mm thk sand = 10.9 Sqm
17 Net Casing Area = 654.47 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 1.000 Km
T.B.L = + 129.500 M Avg. G.L = + 111.265 M
Stripped.Level = + 110.965 M Stri.Lev = + 110.965 M
Height of Bund 18.535 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 110.965 )X 4.5+6+10+1.567+2.5= 102.9 M
Depth of Stripping ( 111.265 - 110.965 ) = 0.300 M
Area of Stripping ( 102.870 X 0.300 ) = 30.860 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-110.965 )X 20% 3.307 = 3.31 M
Bottom Width of Rock-Toe = 3.307 X 3 = 9.92 M
Area of Rock -Toe = 1/2X9.92X3.307 = 16.4 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.307 = 4.68 M
Area = 4.68X0.2 = 0.94 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.307 = 4.68 M
Area = 4.68X0.2 = 0.94 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 110.965 )X 0.5*2+3 = 20.54 M
Top Width = 3M
Arae of Hearting Soils = 3+20.54
X 17.535 = 206.39 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-110.965)X2+3+5-0.57-9.92
- 20.54/2 = 24.31 M
Top Width = 24.31+1.5 = 25.81 M
Arae of Hearting Soils = 25.81+24.31
X 1.000 = 25.06 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 111.965
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 15.535 = 17.37 M
Area of Inclined Sand Chimney = 17.37 X 1.2 = 20.844 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.535 + 5 = 54.91 M
Arae of 450thk Rip Rap = 54.91X0.45 = 24.71 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.535 + 5 = 54.91 M
Arae of 200thk Sand = 54.91X0.2 = 10.98 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.535 + 5 = 54.91 M
Arae of 200thk Sand = 54.91X0.2 = 10.98 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 110.965 )X 4.5+6+10 = 99.41 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+99.41
X 9.835 = 760.05 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 982.55 Sqm
12)Net casing Area = 982.55-16.4-0.94-0.94-206.39-25.06-20.844-24.71-10.98-10.98 = 665.31 Sqm
Slno Descrption Area
1 Stripping = 30.860 Sqm
8 Rock-toe = 16.4 Sqm
9 Behind sand Filters = 0.94 Sqm
10 Behind Metal Filters = 0.94 Sqm
11 Hearting = 206.39 Sqm
12 Inclined Sand Chimney = 20.844 Sqm
13 horizontal Sand Filter = 25.06 Sqm
14 450mm thk Rip Rap = 24.71 Sqm
15 200mm thk Metal = 10.98 Sqm
16 200mm thk sand = 10.98 Sqm
17 Net Casing Area = 665.31 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 1.025 Km
T.B.L = + 131.000 M Avg. G.L = + 111.195 M
Stripped.Level = + 110.895 M Stri.Lev = + 110.895 M
Height of Bund 20.105 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 131.000 - 110.895 )X 4.5+6+10+1.567+2.5= 109.9 M
Depth of Stripping ( 111.195 - 110.895 ) = 0.300 M
Area of Stripping ( 109.940 X 0.300 ) = 32.980 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-110.895 )X 20% 3.321 = 3.32 M
Bottom Width of Rock-Toe = 3.321 X 3 = 9.96 M
Area of Rock -Toe = 1/2X9.96X3.321 = 16.54 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.321 = 4.7 M
Area = 4.7X0.2 = 0.94 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.321 = 4.7 M
Area = 4.7X0.2 = 0.94 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 110.895 )X 0.5*2+3 = 20.61 M
Top Width = 3M
Arae of Hearting Soils = 3+20.61
X 17.605 = 207.83 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 131-110.895)X2+3+5-0.57-9.96- 20.61/2 = 27.38 M
Top Width = 27.38+1.5 = 28.88 M
Arae of Hearting Soils = 28.88+27.38
X 1.000 = 28.13 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 111.895
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 15.605 = 17.45 M
Area of Inclined Sand Chimney = 17.45 X 1.2 = 20.94 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 20.105 + 5 = 59.13 M
Arae of 450thk Rip Rap = 59.13X0.45 = 26.61 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 20.105 + 5 = 59.13 M
Arae of 200thk Sand = 59.13X0.2 = 11.83 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 20.105 + 5 = 59.13 M
Arae of 200thk Sand = 59.13X0.2 = 11.83 Sqm
9) Area of Bund
Bottom Width ( 131.000 - 110.895 )X 4.5+6+10 = 106.47 M
At 120.8 Incl Berm ( 131.000 - 120.800 )X 4.5+6+10 61.9 M
Top Width = 6M
Arae of Bund up to Berm = 61.9+106.47
X 9.905 = 833.85 Sqm
2
Arae of Bund Berm to TBL = 6+51.9
X 10.200 = 295.29 Sqm
2
Total 1129.14 Sqm
12)Net casing Area = 1129.14-16.54-0.94-0.94-207.83-28.13-20.94-26.61-11.83-11.83 = 803.55 Sqm
Slno Descrption Area
1 Stripping = 32.980 Sqm
8 Rock-toe = 16.54 Sqm
9 Behind sand Filters = 0.94 Sqm
10 Behind Metal Filters = 0.94 Sqm
11 Hearting = 207.83 Sqm
12 Inclined Sand Chimney = 20.94 Sqm
13 horizontal Sand Filter = 28.13 Sqm
14 450mm thk Rip Rap = 26.61 Sqm
15 200mm thk Metal = 11.83 Sqm
16 200mm thk sand = 11.83 Sqm
17 Net Casing Area = 803.55 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 1.050 Km
T.B.L = + 129.500 M Avg. G.L = + 110.895 M
Stripped.Level = + 110.595 M Stri.Lev = + 110.595 M
Height of Bund 18.905 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 110.595 )X 4.5+6+10+1.567+2.5= 104.5 M
Depth of Stripping ( 110.895 - 110.595 ) = 0.300 M
Area of Stripping ( 104.540 X 0.300 ) = 31.360 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-110.595 )X 20% 3.381 = 3.38 M
Bottom Width of Rock-Toe = 3.381 X 3 = 10.14 M
Area of Rock -Toe = 1/2X10.14X3.381 = 17.14 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.381 = 4.78 M
Area = 4.78X0.2 = 0.96 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.381 = 4.78 M
Area = 4.78X0.2 = 0.96 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 110.595 )X 0.5*2+3 = 20.91 M
Top Width = 3M
Arae of Hearting Soils = 3+20.91
X 17.905 = 214.05 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-110.595)X2+3+5-0.57-10.14
- 20.91/2 = 24.65 M
Top Width = 24.65+1.5 = 26.15 M
Arae of Hearting Soils = 26.15+24.65
X 1.000 = 25.40 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 111.595
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 15.905 = 17.78 M
Area of Inclined Sand Chimney = 17.78 X 1.2 = 21.336 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.905 + 5 = 55.9 M
Arae of 450thk Rip Rap = 55.9X0.45 = 25.16 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.905 + 5 = 55.9 M
Arae of 200thk Sand = 55.9X0.2 = 11.18 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.905 + 5 = 55.9 M
Arae of 200thk Sand = 55.9X0.2 = 11.18 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 110.595 )X 4.5+6+10 = 101.07 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+101.07
X 10.205 = 797.11 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 1019.61 Sqm
12)Net casing Area = 1019.61-17.14-0.96-0.96-214.05-25.4-21.336-25.16-11.18-11.18 = 692.24 Sqm
Slno Descrption Area
1 Stripping = 31.360 Sqm
8 Rock-toe = 17.14 Sqm
9 Behind sand Filters = 0.96 Sqm
10 Behind Metal Filters = 0.96 Sqm
11 Hearting = 214.05 Sqm
12 Inclined Sand Chimney = 21.336 Sqm
13 horizontal Sand Filter = 25.40 Sqm
14 450mm thk Rip Rap = 25.16 Sqm
15 200mm thk Metal = 11.18 Sqm
16 200mm thk sand = 11.18 Sqm
17 Net Casing Area = 692.24 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 1.075 Km
T.B.L = + 129.500 M Avg. G.L = + 111.220 M
Stripped.Level = + 110.920 M Stri.Lev = + 110.920 M
Height of Bund 18.580 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 110.920 )X 4.5+6+10+1.567+2.5= 103.1 M
Depth of Stripping ( 111.220 - 110.920 ) = 0.300 M
Area of Stripping ( 103.080 X 0.300 ) = 30.920 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-110.92 )X 20% 3.316 = 3.32 M
Bottom Width of Rock-Toe = 3.316 X 3 = 9.95 M
Area of Rock -Toe = 1/2X9.95X3.316 = 16.5 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.316 = 4.69 M
Area = 4.69X0.2 = 0.94 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.316 = 4.69 M
Area = 4.69X0.2 = 0.94 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 110.920 )X 0.5*2+3 = 20.58 M
Top Width = 3M
Arae of Hearting Soils = 3+20.58
X 17.580 = 207.27 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-110.92)X2+3+5-0.57-9.95- 20.58/2 = 24.35 M
Top Width = 24.35+1.5 = 25.85 M
Arae of Hearting Soils = 25.85+24.35
X 1.000 = 25.10 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 111.920
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 15.580 = 17.42 M
Area of Inclined Sand Chimney = 17.42 X 1.2 = 20.904 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.580 + 5 = 55.03 M
Arae of 450thk Rip Rap = 55.03X0.45 = 24.76 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.580 + 5 = 55.03 M
Arae of 200thk Sand = 55.03X0.2 = 11.01 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 18.580 + 5 = 55.03 M
Arae of 200thk Sand = 55.03X0.2 = 11.01 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 110.920 )X 4.5+6+10 = 99.61 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+99.61
X 9.880 = 764.51 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 987.01 Sqm
12)Net casing Area = 987.01-16.5-0.94-0.94-207.27-25.1-20.904-24.76-11.01-11.01 = 668.58 Sqm
Slno Descrption Area
1 Stripping = 30.920 Sqm
8 Rock-toe = 16.5 Sqm
9 Behind sand Filters = 0.94 Sqm
10 Behind Metal Filters = 0.94 Sqm
11 Hearting = 207.27 Sqm
12 Inclined Sand Chimney = 20.904 Sqm
13 horizontal Sand Filter = 25.10 Sqm
14 450mm thk Rip Rap = 24.76 Sqm
15 200mm thk Metal = 11.01 Sqm
16 200mm thk sand = 11.01 Sqm
17 Net Casing Area = 668.58 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 1.100 Km
T.B.L = + 129.500 M Avg. G.L = + 110.520 M
Stripped.Level = + 110.220 M Stri.Lev = + 110.220 M
Height of Bund 19.280 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 110.220 )X 4.5+6+10+1.567+2.5= 106.2 M
Depth of Stripping ( 110.520 - 110.220 ) = 0.300 M
Area of Stripping ( 106.230 X 0.300 ) = 31.870 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-110.22 )X 20% 3.456 = 3.46 M
Bottom Width of Rock-Toe = 3.456 X 3 = 10.37 M
Area of Rock -Toe = 1/2X10.37X3.456 = 17.92 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.456 = 4.89 M
Area = 4.89X0.2 = 0.98 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.456 = 4.89 M
Area = 4.89X0.2 = 0.98 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 110.220 )X 0.5*2+3 = 21.28 M
Top Width = 3M
Arae of Hearting Soils = 3+21.28
X 18.280 = 221.92 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-110.22)X2+3+5-0.57-10.37
- 21.28/2 = 24.98 M
Top Width = 24.98+1.5 = 26.48 M
Arae of Hearting Soils = 26.48+24.98
X 1.000 = 25.73 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 111.220
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 16.280 = 18.2 M
Area of Inclined Sand Chimney = 18.2 X 1.2 = 21.84 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 19.280 + 5 = 56.91 M
Arae of 450thk Rip Rap = 56.91X0.45 = 25.61 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 19.280 + 5 = 56.91 M
Arae of 200thk Sand = 56.91X0.2 = 11.38 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 19.280 + 5 = 56.91 M
Arae of 200thk Sand = 56.91X0.2 = 11.38 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 110.220 )X 4.5+6+10 = 102.76 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+102.76
X 10.580 = 835.34 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 1057.84 Sqm
12)Net casing Area = 1057.84-17.92-0.98-0.98-221.92-25.73-21.84-25.61-11.38-11.38 = 720.10 Sqm
Slno Descrption Area
1 Stripping = 31.870 Sqm
8 Rock-toe = 17.92 Sqm
9 Behind sand Filters = 0.98 Sqm
10 Behind Metal Filters = 0.98 Sqm
11 Hearting = 221.92 Sqm
12 Inclined Sand Chimney = 21.84 Sqm
13 horizontal Sand Filter = 25.73 Sqm
14 450mm thk Rip Rap = 25.61 Sqm
15 200mm thk Metal = 11.38 Sqm
16 200mm thk sand = 11.38 Sqm
17 Net Casing Area = 720.10 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 1.125 Km
T.B.L = + 131.000 M Avg. G.L = + 110.030 M
Stripped.Level = + 109.730 M Stri.Lev = + 109.730 M
Height of Bund 21.270 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 131.000 - 109.730 )X 4.5+6+10+1.567+2.5= 115.2 M
Depth of Stripping ( 110.030 - 109.730 ) = 0.300 M
Area of Stripping ( 115.180 X 0.300 ) = 34.550 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-109.73 )X 20% 3.554 = 3.55 M
Bottom Width of Rock-Toe = 3.554 X 3 = 10.66 M
Area of Rock -Toe = 1/2X10.66X3.554 = 18.94 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.554 = 5.03 M
Area = 5.03X0.2 = 1.01 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.554 = 5.03 M
Area = 5.03X0.2 = 1.01 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 109.730 )X 0.5*2+3 = 21.77 M
Top Width = 3M
Arae of Hearting Soils = 3+21.77
X 18.770 = 232.47 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 131-109.73)X2+3+5-0.57-10.66- 21.77/2 = 28.43 M
Top Width = 28.43+1.5 = 29.93 M
Arae of Hearting Soils = 29.93+28.43
X 1.000 = 29.18 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 110.730
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 16.770 = 18.75 M
Area of Inclined Sand Chimney = 18.75 X 1.2 = 22.5 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 21.270 + 5 = 62.27 M
Arae of 450thk Rip Rap = 62.27X0.45 = 28.02 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 21.270 + 5 = 62.27 M
Arae of 200thk Sand = 62.27X0.2 = 12.45 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 21.270 + 5 = 62.27 M
Arae of 200thk Sand = 62.27X0.2 = 12.45 Sqm
9) Area of Bund
Bottom Width ( 131.000 - 109.730 )X 4.5+6+10 = 111.72 M
At 120.8 Incl Berm ( 131.000 - 120.800 )X 4.5+6+10 61.9 M
Top Width = 6M
Arae of Bund up to Berm = 61.9+111.72
X 11.070 = 960.99 Sqm
2
Arae of Bund Berm to TBL = 6+51.9
X 10.200 = 295.29 Sqm
2
Total 1256.28 Sqm
12)Net casing Area = 1256.28-18.94-1.01-1.01-232.47-29.18-22.5-28.02-12.45-12.45 = 898.25 Sqm
Slno Descrption Area
1 Stripping = 34.550 Sqm
8 Rock-toe = 18.94 Sqm
9 Behind sand Filters = 1.01 Sqm
10 Behind Metal Filters = 1.01 Sqm
11 Hearting = 232.47 Sqm
12 Inclined Sand Chimney = 22.5 Sqm
13 horizontal Sand Filter = 29.18 Sqm
14 450mm thk Rip Rap = 28.02 Sqm
15 200mm thk Metal = 12.45 Sqm
16 200mm thk sand = 12.45 Sqm
17 Net Casing Area = 898.25 Sqm
Formation Mallamadugu Reservoir
BUND-2
Cross Section 1.143 Km
T.B.L = + 131.000 M Avg. G.L = + 111.895 M
Stripped.Level = + 111.595 M Stri.Lev = + 111.595 M
Height of Bund 19.405 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 131.000 - 111.595 )X 4.5+6+10+1.567+2.5= 106.8 M
Depth of Stripping ( 111.895 - 111.595 ) = 0.300 M
Area of Stripping ( 106.790 X 0.300 ) = 32.040 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-111.595 )X 20% 3.181 = 3.18 M
Bottom Width of Rock-Toe = 3.181 X 3 = 9.54 M
Area of Rock -Toe = 1/2X9.54X3.181 = 15.17 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.181 = 4.5 M
Area = 4.5X0.2 = 0.9 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.181 = 4.5 M
Area = 4.5X0.2 = 0.9 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 111.595 )X 0.5*2+3 = 19.91 M
Top Width = 3M
Arae of Hearting Soils = 3+19.91
X 16.905 = 193.65 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 131-111.595)X2+3+5-0.57-9.54- 19.91/2 = 26.75 M
Top Width = 26.75+1.5 = 28.25 M
Arae of Hearting Soils = 28.25+26.75
X 1.000 = 27.50 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 112.595
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 14.905 = 16.66 M
Area of Inclined Sand Chimney = 16.66 X 1.2 = 19.992 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1)
X 19.405 + 5 = 57.25 M
Arae of 450thk Rip Rap = 57.25X0.45 = 25.76 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1)
X 19.405 + 5 = 57.25 M
Arae of 200thk Sand = 57.25X0.2 = 11.45 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1)
X 19.405 + 5 = 57.25 M
Arae of 200thk Sand = 57.25X0.2 = 11.45 Sqm
9) Area of Bund
Bottom Width ( 131.000 - 111.595 )X 4.5+6+10 = 103.32 M
At 120.8 Incl Berm ( 131.000 - 120.800 )X 4.5+6+10 61.9 M
Top Width = 6M
Arae of Bund up to Berm = 61.9+103.32
X 9.205 = 760.43 Sqm
2
Arae of Bund Berm to TBL = 6+51.9
X 10.200 = 295.29 Sqm
2
Total 1055.72 Sqm
12)Net casing Area = 1055.72-15.17-0.9-0.9-193.65-27.5-19.992-25.76-11.45-11.45 = 748.95 Sqm
Slno Descrption Area
1 Stripping = 32.040 Sqm
8 Rock-toe = 15.17 Sqm
9 Behind sand Filters = 0.9 Sqm
10 Behind Metal Filters = 0.9 Sqm
11 Hearting = 193.65 Sqm
12 Inclined Sand Chimney = 19.992 Sqm
13 horizontal Sand Filter = 27.50 Sqm
14 450mm thk Rip Rap = 25.76 Sqm
15 200mm thk Metal = 11.45 Sqm
16 200mm thk sand = 11.45 Sqm
17 Net Casing Area = 748.95 Sqm
Formation Mallamadugu Reservoir
BUND-2
Detail Estimate of Profile Wall
0.3

Profile wall
450 thk Rip Rap
200 thk Metal
200 thk Sand
0.3 Casing Soils
Area of Earthwork Excavation = 0.3 X 0.3 0.09 Sqm
Area of Concrete = (0.45 +0.2+0.2+0.3) X 0.3 0.35 Sqm

Concrete with
Top of U/S Face Slant Length EWE of Profile Wall
Stripped Height of grade of Mix CC
Slno Chainage the Area Quantity Area Quantity Remarks
Level Bund Details Length
Profile (Sqm) (Cum) (Sqm) (Cum)

1 0.000

2 0.030 120.198 129.500 9.302 sqrt(2.0X2.0+1X1) +5 X9.302 = 25.800 0.09 2.320 0.35 9.030

3 0.060 115.043 129.500 14.457 sqrt(2.5X2.5+1X1) +5 X14.457 = 43.927 0.09 3.950 0.35 15.370

4 0.090 113.198 129.500 16.302 sqrt(2.5X2.5+1X1) +5 X16.302 = 48.894 0.09 4.400 0.35 17.110

5 0.120 113.130 129.500 16.370 sqrt(2.5X2.5+1X1) +5 X16.37 = 49.078 0.09 4.420 0.35 17.180

6 0.150 112.880 129.500 16.620 sqrt(2.5X2.5+1X1) +5 X16.62 = 49.751 0.09 4.480 0.35 17.410

7 0.180 112.978 129.500 16.522 sqrt(2.5X2.5+1X1) +5 X16.522 = 49.487 0.09 4.450 0.35 17.320

8 0.210 113.105 129.500 16.395 sqrt(2.5X2.5+1X1) +5 X16.395 = 49.145 0.09 4.420 0.35 17.200

9 0.240 113.260 129.500 16.240 sqrt(2.5X2.5+1X1) +5 X16.24 = 48.728 0.09 4.390 0.35 17.050

10 0.270 113.318 129.500 16.182 sqrt(2.5X2.5+1X1) +5 X16.182 = 48.571 0.09 4.370 0.35 17.000

11 0.300 113.645 129.500 15.855 sqrt(2.5X2.5+1X1) +5 X15.855 = 47.691 0.09 4.290 0.35 16.690

12 0.330 113.835 129.500 15.665 sqrt(2.5X2.5+1X1) +5 X15.665 = 47.179 0.09 4.250 0.35 16.510

13 0.360 113.875 129.500 15.625 sqrt(2.5X2.5+1X1) +5 X15.625 = 47.072 0.09 4.240 0.35 16.480

14 0.390 113.888 129.500 15.612 sqrt(2.5X2.5+1X1) +5 X15.612 = 47.037 0.09 4.230 0.35 16.460

15 0.420 113.928 129.500 15.572 sqrt(2.5X2.5+1X1) +5 X15.572 = 46.929 0.09 4.220 0.35 16.430

16 0.450 113.925 129.500 15.575 sqrt(2.5X2.5+1X1) +5 X15.575 = 46.937 0.09 4.220 0.35 16.430

17 0.480 113.805 129.500 15.695 sqrt(2.5X2.5+1X1) +5 X15.695 = 47.260 0.09 4.250 0.35 16.540

18 0.510 113.718 129.500 15.782 sqrt(2.5X2.5+1X1) +5 X15.782 = 47.494 0.09 4.270 0.35 16.620

19 0.540 113.645 129.500 15.855 sqrt(2.5X2.5+1X1) +5 X15.855 = 47.691 0.09 4.290 0.35 16.690

20 0.570 113.578 129.500 15.922 sqrt(2.5X2.5+1X1) +5 X15.922 = 47.871 0.09 4.310 0.35 16.750

21 0.600 113.545 129.500 15.955 sqrt(2.5X2.5+1X1) +5 X15.955 = 47.960 0.09 4.320 0.35 16.790

22 0.630 113.420 129.500 16.080 sqrt(2.5X2.5+1X1) +5 X16.08 = 48.297 0.09 4.350 0.35 16.900

23 0.660 113.398 129.500 16.102 sqrt(2.5X2.5+1X1) +5 X16.102 = 48.356 0.09 4.350 0.35 16.920

24 0.690 113.318 129.500 16.182 sqrt(2.5X2.5+1X1) +5 X16.182 = 48.571 0.09 4.370 0.35 17.000

25 0.720 113.208 129.500 16.292 sqrt(2.5X2.5+1X1) +5 X16.292 = 48.868 0.09 4.400 0.35 17.100

26 0.750 113.080 129.500 16.420 sqrt(2.5X2.5+1X1) +5 X16.42 = 49.212 0.09 4.430 0.35 17.220

27 0.780 112.900 129.500 16.600 sqrt(2.5X2.5+1X1) +5 X16.6 = 49.697 0.09 4.470 0.35 17.390
Concrete with
Top of U/S Face Slant Length EWE of Profile Wall
Stripped Height of grade of Mix CC
Slno Chainage the Area Quantity Area Quantity Remarks
Level Bund Details Length
Profile (Sqm) (Cum) (Sqm) (Cum)

28 0.810 112.708 129.500 16.792 sqrt(2.5X2.5+1X1) +5 X16.792 = 50.214 0.09 4.520 0.35 17.570

29 0.840 112.530 129.500 16.970 sqrt(2.5X2.5+1X1) +5 X16.97 = 50.693 0.09 4.560 0.35 17.740

30 0.870 112.390 129.500 17.110 sqrt(2.5X2.5+1X1) +5 X17.11 = 51.070 0.09 4.600 0.35 17.870

31 0.900 111.920 129.500 17.580 sqrt(2.5X2.5+1X1) +5 X17.58 = 52.336 0.09 4.710 0.35 18.320

32 0.930 111.560 129.500 17.940 sqrt(2.5X2.5+1X1) +5 X17.94 = 53.305 0.09 4.800 0.35 18.660

33 0.960 111.268 129.500 18.232 sqrt(2.5X2.5+1X1) +5 X18.232 = 54.091 0.09 4.870 0.35 18.930

34 0.990 111.040 129.500 18.460 sqrt(2.5X2.5+1X1) +5 X18.46 = 54.705 0.09 4.920 0.35 19.150

35 1.020 110.930 129.500 18.570 sqrt(2.5X2.5+1X1) +5 X18.57 = 55.001 0.09 4.950 0.35 19.250

36 1.050 110.595 129.500 18.905 sqrt(2.5X2.5+1X1) +5 X18.905 = 55.903 0.09 5.030 0.35 19.570

37 1.080 110.570 129.500 18.930 sqrt(2.5X2.5+1X1) +5 X18.93 = 55.971 0.09 5.040 0.35 19.590

38 1.110 109.975 129.500 19.525 sqrt(2.5X2.5+1X1) +5 X19.525 = 57.573 0.09 5.180 0.35 20.150

39 1.143 110.663 129.500 18.837 sqrt(2.5X2.5+1X1) +5 X18.837 = 55.720 0.09 5.010 0.35 19.500

Total Quantity 168.650 Cum 655.890 Cum


Formation Mallamadugu Reservoir
BUND-2
Detail Estimate of Drilling & Grouting
Drilling holes and driving casing pipe 63mm dia in the
consolidated cut off trench upto the bottom off cut of
1
along bund axis as directed in the soil with drilling
machine and casing bit including cost of casing pipe

Length of dam 1143 meters


Interval of Grouting holes 3 meters
Total no of holes 382 meters
Depth of Casing Pipe 6 meters
Total length of the Pipe 2292 meters
Drilling holes into the rock from the bottom of cut off
trench by wagon drill to the specified depth at
2 intervals as directed for washing holes with air jet and
water in the drilled holes, founfation treatment
including refilling the holes whereever necessary
Length of dam 1143 meters
Interval of Grouting holes 3 meters
Total no of holes 382 meters
Depth of each Hole 12 meters
Total length of the Drilling holes into the rock from the
4584 meters
bottom of cut off trench

Conducting in situ permeability test at 2Mtr. Zones,


3
using double packer in the drilled holes

Length of dam 1143 meters


Interval of testing holes 50 meters
Total no of holes 23 meters
Depth of each Hole 12 meters
Total length of the Pipe 276 meters

Grouting the holes with cement slurry with specified


4 MT
ratio of water cement mix incliding cost of cement

Total length of the Drilling holes into the rock from the
4584 meters
bottom of cut off trench
Cement consumption 0.75 Bag for one RMT
Total Cement Consumption 3438 Bags
Total Cement Consumption 172 MT
Formation Mallamadugu Reservoir
BUND-2
Detailed Es mate for 'Parpet wall' on U/S
150

CC M15-40 MSA
600
T BL .+131.000

1000

CC M 15 40 MSA 200
600
Details of Parapet

S.No Description of Item Nos Length Width Depth Quantity


1 2 3 4 5 6 7
Earth work excavation for
1 1 1143.00 0.60 1.00 685.80 Cum
Deflector wall
Levelling course in CC
2 M15 with 40 MSA 1 1143.00 0.60 0.20 137.16 Cum
Deflector wall
CC M15 with 40 MSA for
3 1 1143.00 1.60 0.30 548.64 Cum
Parpet wall
(∏ X 0.15
4 Top Curve Portion 1 1143.00 0.0353 40.35 Cum
X 0.15) /2

Detailed Es mate for 'Guard Stone' @ 3M C/C on D/S


225

750
TBL-131.000

2
450
1

Guard Stone @ 3 m C/C

S.No Description of Item Nos Length Width Depth Quantity


1 2 3 4 5 6 7
Earth work excavation for
1 382 0.225 0.225 0.45 8.70 Cum
Deflector wall
CC M15 with 40 MSA for
2 382 0.225 0.225 1.20 23.21 Cum
Parpet wall
Details Estimate of Rock Toe of Bund-2
T.B.L = + 129.500 M Height of Rock-Toe = 20 % of Hydraluical Head= (FRL-Stipped Levels) X 20%
F.R.L = + 127.500 M Minimum Height of Rock -Toe = 1.5 Meters
M.W.L = + 127.500 M Maximum Height of Rock -Toe = 6 Meters
Bottom
Height of Rock- Top Level of Mean Area Quantity
Slno Chainage Stripped Level Width of Area (Sqm) Remarks
Toe (M) Rock -Toe (Sqm) (Cum)
Rock-Toe (M)

1 0.000 0.00 0.000 0.00 0.00


2 0.025 123.325 1.50 124.825 4.50 3.38 1.69 42.25
3 0.050 117.070 2.09 119.156 6.26 6.53 4.96 123.88
4 0.075 113.015 2.90 115.912 8.69 12.59 9.56 239.00
5 0.100 113.380 2.82 116.204 8.47 11.97 12.28 307.00
6 0.125 112.880 2.92 115.804 8.77 12.83 12.40 310.00
7 0.150 112.880 2.92 115.804 8.77 12.83 12.83 320.75
8 0.175 112.965 2.91 115.872 8.72 12.68 12.76 318.88
9 0.200 112.990 2.90 115.892 8.71 12.64 12.66 316.50
10 0.225 113.220 2.86 116.076 8.57 12.24 12.44 311.00
11 0.250 113.300 2.84 116.140 8.52 12.10 12.17 304.25
12 0.275 113.335 2.83 116.168 8.50 12.04 12.07 301.75
13 0.300 113.645 2.77 116.416 8.31 11.52 11.78 294.50
14 0.325 113.790 2.74 116.532 8.23 11.28 11.40 285.00
15 0.350 113.880 2.72 116.604 8.17 11.14 11.21 280.25
16 0.375 113.870 2.73 116.596 8.18 11.15 11.15 278.63
17 0.400 113.905 2.72 116.624 8.16 11.09 11.12 278.00
18 0.425 113.950 2.71 116.660 8.13 11.02 11.06 276.38
19 0.450 113.925 2.72 116.640 8.15 11.06 11.04 276.00
20 0.475 113.855 2.73 116.584 8.19 11.18 11.12 278.00
21 0.500 113.755 2.75 116.504 8.25 11.34 11.26 281.50
22 0.525 113.680 2.76 116.444 8.29 11.46 11.40 285.00
23 0.550 113.610 2.78 116.388 8.33 11.58 11.52 288.00
24 0.575 113.545 2.79 116.336 8.37 11.69 11.64 290.88
25 0.600 113.545 2.79 116.336 8.37 11.69 11.69 292.25
26 0.625 113.440 2.81 116.252 8.44 11.87 11.78 294.50
27 0.650 113.400 2.82 116.220 8.46 11.93 11.90 297.50
28 0.675 113.395 2.82 116.216 8.46 11.94 11.94 298.38
29 0.700 113.240 2.85 116.092 8.56 12.21 12.08 301.88
30 0.725 113.175 2.87 116.040 8.60 12.32 12.27 306.63
31 0.750 113.080 2.88 115.964 8.65 12.48 12.40 310.00
32 0.775 113.040 2.89 115.932 8.68 12.55 12.52 312.88
33 0.800 112.760 2.95 115.708 8.84 13.04 12.80 319.88
34 0.825 112.655 2.97 115.624 8.91 13.23 13.14 328.38
35 0.850 112.405 3.02 115.424 9.06 13.68 13.46 336.38
36 0.875 112.375 3.03 115.400 9.08 13.73 13.71 342.63
37 0.900 111.920 3.12 115.036 9.35 14.57 14.15 353.75
38 0.925 111.700 3.16 114.860 9.48 14.98 14.78 369.38
39 0.950 111.420 3.22 114.636 9.65 15.52 15.25 381.25
40 0.975 111.115 3.28 114.392 9.83 16.11 15.82 395.38
41 1.000 110.965 3.31 114.272 9.92 16.41 16.26 406.50
42 1.025 110.895 3.32 114.216 9.96 16.55 16.48 412.00
43 1.050 110.595 3.38 113.976 10.14 17.15 16.85 421.25
44 1.075 110.920 3.32 114.236 9.95 16.50 16.83 420.62
45 1.100 110.220 3.46 113.676 10.37 17.92 17.21 430.25
46 1.125 109.730 3.55 113.284 10.66 18.95 18.44 460.87
47 1.143 111.595 3.18 114.776 9.54 15.18 17.07 307.17
Total Quantity 14387.05 Cum
Grand Total 14387.05 Cum
Filters Below Rock-Toe
200 mm thick Sand Filters
Bottom Top Width Avg Width
Height of Rock- Top Level of Mean Area
Slno Chainage Stripped Level Width of of Sand of Sand Area (Sqm) Quantity (Cum) Remarks
Toe (M) Rock -Toe (Sqm)
Sand Filter Filter Filter
1 0.000 0.0 0.000 0.00 0.00 0.00 0.00
2 0.025 123.325 1.5 124.825 4.50 3.90 4.20 0.84 0.42 10.50
3 0.050 117.070 2.1 119.156 6.26 5.66 5.96 1.19 1.02 25.40
4 0.075 113.015 2.9 115.912 8.69 8.09 8.39 1.68 1.43 35.87
5 0.100 113.380 2.8 116.204 8.47 7.87 8.17 1.63 1.66 41.41
6 0.125 112.880 2.9 115.804 8.77 8.17 8.47 1.69 1.66 41.61
7 0.150 112.880 2.9 115.804 8.77 8.17 8.47 1.69 1.69 42.36
8 0.175 112.965 2.9 115.872 8.72 8.12 8.42 1.68 1.69 42.23
9 0.200 112.990 2.9 115.892 8.71 8.11 8.41 1.68 1.68 42.07
10 0.225 113.220 2.9 116.076 8.57 7.97 8.27 1.65 1.67 41.69
11 0.250 113.300 2.8 116.140 8.52 7.92 8.22 1.64 1.65 41.22
12 0.275 113.335 2.8 116.168 8.50 7.90 8.20 1.64 1.64 41.05
13 0.300 113.645 2.8 116.416 8.31 7.71 8.01 1.60 1.62 40.53
14 0.325 113.790 2.7 116.532 8.23 7.63 7.93 1.59 1.59 39.85
15 0.350 113.880 2.7 116.604 8.17 7.57 7.87 1.57 1.58 39.50
16 0.375 113.870 2.7 116.596 8.18 7.58 7.88 1.58 1.58 39.38
17 0.400 113.905 2.7 116.624 8.16 7.56 7.86 1.57 1.57 39.34
18 0.425 113.950 2.7 116.660 8.13 7.53 7.83 1.57 1.57 39.22
19 0.450 113.925 2.7 116.640 8.15 7.55 7.85 1.57 1.57 39.19
20 0.475 113.855 2.7 116.584 8.19 7.59 7.89 1.58 1.57 39.33
21 0.500 113.755 2.7 116.504 8.25 7.65 7.95 1.59 1.58 39.59
22 0.525 113.680 2.8 116.444 8.29 7.69 7.99 1.60 1.59 39.85
23 0.550 113.610 2.8 116.388 8.33 7.73 8.03 1.61 1.60 40.07
24 0.575 113.545 2.8 116.336 8.37 7.77 8.07 1.61 1.61 40.27
25 0.600 113.545 2.8 116.336 8.37 7.77 8.07 1.61 1.61 40.37
26 0.625 113.440 2.8 116.252 8.44 7.84 8.14 1.63 1.62 40.52
27 0.650 113.400 2.8 116.220 8.46 7.86 8.16 1.63 1.63 40.74
28 0.675 113.395 2.8 116.216 8.46 7.86 8.16 1.63 1.63 40.81
29 0.700 113.240 2.9 116.092 8.56 7.96 8.26 1.65 1.64 41.05
30 0.725 113.175 2.9 116.040 8.60 8.00 8.30 1.66 1.66 41.38
31 0.750 113.080 2.9 115.964 8.65 8.05 8.35 1.67 1.66 41.62
32 0.775 113.040 2.9 115.932 8.68 8.08 8.38 1.68 1.67 41.82
33 0.800 112.760 2.9 115.708 8.84 8.24 8.54 1.71 1.69 42.30
34 0.825 112.655 3.0 115.624 8.91 8.31 8.61 1.72 1.72 42.88
35 0.850 112.405 3.0 115.424 9.06 8.46 8.76 1.75 1.74 43.41
36 0.875 112.375 3.0 115.400 9.08 8.48 8.78 1.76 1.75 43.83
37 0.900 111.920 3.1 115.036 9.35 8.75 9.05 1.81 1.78 44.56
38 0.925 111.700 3.2 114.860 9.48 8.88 9.18 1.84 1.82 45.57
39 0.950 111.420 3.2 114.636 9.65 9.05 9.35 1.87 1.85 46.32
40 0.975 111.115 3.3 114.392 9.83 9.23 9.53 1.91 1.89 47.20
41 1.000 110.965 3.3 114.272 9.92 9.32 9.62 1.92 1.92 47.88
42 1.025 110.895 3.3 114.216 9.96 9.36 9.66 1.93 1.93 48.21
43 1.050 110.595 3.4 113.976 10.14 9.54 9.84 1.97 1.95 48.76
44 1.075 110.920 3.3 114.236 9.95 9.35 9.65 1.93 1.95 48.73
45 1.100 110.220 3.5 113.676 10.37 9.77 10.07 2.01 1.97 49.29
46 1.125 109.730 3.6 113.284 10.66 10.06 10.36 2.07 2.04 51.07
47 1.143 111.595 3.2 114.776 9.54 8.94 9.24 1.85 1.96 35.29
Total Quantity 1895.08 Cum
200 mm thick Metal Filters

Bottom Top Width Avg Width


Height of Rock- Top Level of Mean Area
Slno Chainage Stripped Level Width of of Metal of Metal Area (Sqm) Quantity (Cum) Remarks
Toe (M) Rock -Toe (Sqm)
Metal Filter Filter Filter
1 0.000 0.000 0.0 0.000 0.00 0.00 0.00 0.00
2 0.025 123.325 1.5 124.825 3.90 3.30 3.60 0.72 0.36 9.00
3 0.050 117.070 2.1 119.156 5.66 5.06 5.36 1.07 0.90 22.40
4 0.075 113.015 2.9 115.912 8.09 7.49 7.79 1.56 1.31 32.87
5 0.100 113.380 2.8 116.204 7.87 7.27 7.57 1.51 1.54 38.41
6 0.125 112.880 2.9 115.804 8.17 7.57 7.87 1.57 1.54 38.61
7 0.150 112.880 2.9 115.804 8.17 7.57 7.87 1.57 1.57 39.36
8 0.175 112.965 2.9 115.872 8.12 7.52 7.82 1.56 1.57 39.23
9 0.200 112.990 2.9 115.892 8.11 7.51 7.81 1.56 1.56 39.07
10 0.225 113.220 2.9 116.076 7.97 7.37 7.67 1.53 1.55 38.69
11 0.250 113.300 2.8 116.140 7.92 7.32 7.62 1.52 1.53 38.22
12 0.275 113.335 2.8 116.168 7.90 7.30 7.60 1.52 1.52 38.05
13 0.300 113.645 2.8 116.416 7.71 7.11 7.41 1.48 1.50 37.53
14 0.325 113.790 2.7 116.532 7.63 7.03 7.33 1.47 1.47 36.85
15 0.350 113.880 2.7 116.604 7.57 6.97 7.27 1.45 1.46 36.50
16 0.375 113.870 2.7 116.596 7.58 6.98 7.28 1.46 1.46 36.38
17 0.400 113.905 2.7 116.624 7.56 6.96 7.26 1.45 1.45 36.34
18 0.425 113.950 2.7 116.660 7.53 6.93 7.23 1.45 1.45 36.22
19 0.450 113.925 2.7 116.640 7.55 6.95 7.25 1.45 1.45 36.19
20 0.475 113.855 2.7 116.584 7.59 6.99 7.29 1.46 1.45 36.33
21 0.500 113.755 2.7 116.504 7.65 7.05 7.35 1.47 1.46 36.59
22 0.525 113.680 2.8 116.444 7.69 7.09 7.39 1.48 1.47 36.85
23 0.550 113.610 2.8 116.388 7.73 7.13 7.43 1.49 1.48 37.07
24 0.575 113.545 2.8 116.336 7.77 7.17 7.47 1.49 1.49 37.27
25 0.600 113.545 2.8 116.336 7.77 7.17 7.47 1.49 1.49 37.37
26 0.625 113.440 2.8 116.252 7.84 7.24 7.54 1.51 1.50 37.52
27 0.650 113.400 2.8 116.220 7.86 7.26 7.56 1.51 1.51 37.74
28 0.675 113.395 2.8 116.216 7.86 7.26 7.56 1.51 1.51 37.81
29 0.700 113.240 2.9 116.092 7.96 7.36 7.66 1.53 1.52 38.05
30 0.725 113.175 2.9 116.040 8.00 7.40 7.70 1.54 1.54 38.38
31 0.750 113.080 2.9 115.964 8.05 7.45 7.75 1.55 1.54 38.62
32 0.775 113.040 2.9 115.932 8.08 7.48 7.78 1.56 1.55 38.82
33 0.800 112.760 2.9 115.708 8.24 7.64 7.94 1.59 1.57 39.30
34 0.825 112.655 3.0 115.624 8.31 7.71 8.01 1.60 1.60 39.88
35 0.850 112.405 3.0 115.424 8.46 7.86 8.16 1.63 1.62 40.41
36 0.875 112.375 3.0 115.400 8.48 7.88 8.18 1.64 1.63 40.83
37 0.900 111.920 3.1 115.036 8.75 8.15 8.45 1.69 1.66 41.56
38 0.925 111.700 3.2 114.860 8.88 8.28 8.58 1.72 1.70 42.57
39 0.950 111.420 3.2 114.636 9.05 8.45 8.75 1.75 1.73 43.32
40 0.975 111.115 3.3 114.392 9.23 8.63 8.93 1.79 1.77 44.20
41 1.000 110.965 3.3 114.272 9.32 8.72 9.02 1.80 1.80 44.88
42 1.025 110.895 3.3 114.216 9.36 8.76 9.06 1.81 1.81 45.21
43 1.050 110.595 3.4 113.976 9.54 8.94 9.24 1.85 1.83 45.76
44 1.075 110.920 3.3 114.236 9.35 8.75 9.05 1.81 1.83 45.73
45 1.100 110.220 3.5 113.676 9.77 9.17 9.47 1.89 1.85 46.29
46 1.125 109.730 3.6 113.284 10.06 9.46 9.76 1.95 1.92 48.07
47 1.143 111.595 3.2 114.776 8.94 8.34 8.64 1.73 1.84 33.13
Total Quantity 1759.42 Cum
Details for Chute Drain on D/S of BUND-2
EARTH WORK EXCAVATION:

1). Cross sectional Area at Transition starting point 0.855 Sqm.


=
2). Cross sectional Area at Transition ending point 0.583 Sqm.
=
CC M15 GRADE CONCRE WITH 40 MSA:

3). Cross sectional Area at Transition starting point = 0.585 Sqm.

4). Cross sectional Area at Transition ending point = 0.403 Sqm.

5). Transition length = 0.500 Rmt.

0.45 1.50 0.45


0.23
1.329 TW of Bed
2:1 2:1 0.409 BW of Bed
0.07 0.200 Bed Area
0.30 0.072 Sides Area
0.23 0.313 Lugs Area
All Dimensions in m 0.409 0.585 Total Area

0.30 0.90 0.30


0.23 0.950 TW of Bed
0.490 BW of Bed
1:1 1:1 0.166 Bed Area
0.07 0.046 Sides Area
0.30 0.191 Lugs Area
0.23 0.403 Total Area
0.490
DETAILED ESTIMATE OF CHUTE DRAIN @ EVERY 45 m INTERVAL ON D/S OF BUND -2

Height of Slope length of Chute Drain Earth work Excavation CC M15 Quantity
Rock Bund
Stripped
S.No. Chainage Toe Top above Length Quantity Quantity in
Level Details Details Details
level rock toe in m in Cum Cum
in m
1 2 5 6 7 8

1 0.000

2 0.045 120.198 121.698 7.80 (7.8x2.236) 17.45 0.5X(0.855+0.583)/2+(17.45-0.5)X0.583 10.24 0.5X(0.585+0.403)/2+(17.45-0.5)X0.403 7.08

3 0.090 113.198 116.058 13.44 (13.44x2.236) 30.06 0.5X(0.855+0.583)/2+(30.06-0.5)X0.583 17.59 0.5X(0.585+0.403)/2+(30.06-0.5)X0.403 12.16

4 0.135 112.880 115.804 13.70 (13.7x2.236) 30.62 0.5X(0.855+0.583)/2+(30.62-0.5)X0.583 17.92 0.5X(0.585+0.403)/2+(30.62-0.5)X0.403 12.39

5 0.180 112.978 115.882 13.62 (13.62x2.236) 30.45 0.5X(0.855+0.583)/2+(30.45-0.5)X0.583 17.82 0.5X(0.585+0.403)/2+(30.45-0.5)X0.403 12.32

6 0.225 113.220 116.076 13.42 (13.42x2.236) 30.02 0.5X(0.855+0.583)/2+(30.02-0.5)X0.583 17.57 0.5X(0.585+0.403)/2+(30.02-0.5)X0.403 12.14

7 0.270 113.318 116.154 13.35 (13.35x2.236) 29.84 0.5X(0.855+0.583)/2+(29.84-0.5)X0.583 17.46 0.5X(0.585+0.403)/2+(29.84-0.5)X0.403 12.07

8 0.315 113.718 116.474 13.03 (13.03x2.236) 29.13 0.5X(0.855+0.583)/2+(29.13-0.5)X0.583 17.05 0.5X(0.585+0.403)/2+(29.13-0.5)X0.403 11.78

9 0.360 113.875 116.600 12.90 (12.9x2.236) 28.84 0.5X(0.855+0.583)/2+(28.84-0.5)X0.583 16.88 0.5X(0.585+0.403)/2+(28.84-0.5)X0.403 11.67

10 0.405 113.928 116.642 12.86 (12.86x2.236) 28.75 0.5X(0.855+0.583)/2+(28.75-0.5)X0.583 16.83 0.5X(0.585+0.403)/2+(28.75-0.5)X0.403 11.63

11 0.450 113.925 116.640 12.86 (12.86x2.236) 28.75 0.5X(0.855+0.583)/2+(28.75-0.5)X0.583 16.83 0.5X(0.585+0.403)/2+(28.75-0.5)X0.403 11.63

12 0.495 113.805 116.544 12.96 (12.96x2.236) 28.97 0.5X(0.855+0.583)/2+(28.97-0.5)X0.583 16.96 0.5X(0.585+0.403)/2+(28.97-0.5)X0.403 11.72

13 0.540 113.645 116.416 13.08 (13.08x2.236) 29.26 0.5X(0.855+0.583)/2+(29.26-0.5)X0.583 17.13 0.5X(0.585+0.403)/2+(29.26-0.5)X0.403 11.84

14 0.585 113.545 116.336 13.16 (13.16x2.236) 29.43 0.5X(0.855+0.583)/2+(29.43-0.5)X0.583 17.23 0.5X(0.585+0.403)/2+(29.43-0.5)X0.403 11.91

15 0.630 113.420 116.236 13.26 (13.26x2.236) 29.66 0.5X(0.855+0.583)/2+(29.66-0.5)X0.583 17.36 0.5X(0.585+0.403)/2+(29.66-0.5)X0.403 12.00

16 0.675 113.395 116.216 13.28 (13.28x2.236) 29.70 0.5X(0.855+0.583)/2+(29.7-0.5)X0.583 17.38 0.5X(0.585+0.403)/2+(29.7-0.5)X0.403 12.01

17 0.720 113.208 116.066 13.43 (13.43x2.236) 30.04 0.5X(0.855+0.583)/2+(30.04-0.5)X0.583 17.58 0.5X(0.585+0.403)/2+(30.04-0.5)X0.403 12.15

18 0.765 113.060 115.948 13.55 (13.55x2.236) 30.30 0.5X(0.855+0.583)/2+(30.3-0.5)X0.583 17.73 0.5X(0.585+0.403)/2+(30.3-0.5)X0.403 12.26

19 0.810 112.708 115.666 13.83 (13.83x2.236) 30.93 0.5X(0.855+0.583)/2+(30.93-0.5)X0.583 18.10 0.5X(0.585+0.403)/2+(30.93-0.5)X0.403 12.51
Height of Slope length of Chute Drain Earth work Excavation CC M15 Quantity
Rock Bund
Stripped
S.No. Chainage Toe Top above Length Quantity Quantity in
Level Details Details Details
level rock toe in m in Cum Cum
in m
20 0.855 112.390 115.412 14.09 (14.09x2.236) 31.50 0.5X(0.855+0.583)/2+(31.5-0.5)X0.583 18.43 0.5X(0.585+0.403)/2+(31.5-0.5)X0.403 12.74

21 0.900 111.920 115.036 14.46 (14.46x2.236) 32.34 0.5X(0.855+0.583)/2+(32.34-0.5)X0.583 18.92 0.5X(0.585+0.403)/2+(32.34-0.5)X0.403 13.08

22 0.945 111.560 114.748 14.75 (14.75x2.236) 32.99 0.5X(0.855+0.583)/2+(32.99-0.5)X0.583 19.30 0.5X(0.585+0.403)/2+(32.99-0.5)X0.403 13.34

23 0.990 111.040 114.332 15.17 (15.17x2.236) 33.92 0.5X(0.855+0.583)/2+(33.92-0.5)X0.583 19.84 0.5X(0.585+0.403)/2+(33.92-0.5)X0.403 13.72

24 1.035 110.745 114.096 15.40 (15.4x2.236) 34.44 0.5X(0.855+0.583)/2+(34.44-0.5)X0.583 20.15 0.5X(0.585+0.403)/2+(34.44-0.5)X0.403 13.92

25 1.080 110.570 113.956 15.54 (15.54x2.236) 34.76 0.5X(0.855+0.583)/2+(34.76-0.5)X0.583 20.33 0.5X(0.585+0.403)/2+(34.76-0.5)X0.403 14.05

26 1.125 109.730 113.284 16.22 (16.22x2.236) 36.26 0.5X(0.855+0.583)/2+(36.26-0.5)X0.583 21.21 0.5X(0.585+0.403)/2+(36.26-0.5)X0.403 14.66

27 1.143 111.508 114.706 14.79 (14.79x2.236) 33.08 0.5X(0.855+0.583)/2+(33.08-0.5)X0.583 19.35 0.5X(0.585+0.403)/2+(33.08-0.5)X0.403 13.38

Total Total Quantity 463.19 Total Quantity 320.16

Longitudinal Chute Drain

Length = 1.143 Km
Cross sectional Area at EWE= 0.583 Sqm

Cross sectional Area Concrete= 0.403 Sqm

EWE Quanity 742.159 Cum

Concrete Quanity- M15-40 MSA 513.019 Cum

Total EWE Quantity 742.159+463.19 1205.35 Cum

Total Concrete Quantity 513.019+320.16 833.18 Cum


Formation of Mallamadugu Reservoir
BUND-2
Details Estimate of D/S Turfing
Rock Top
Length Stripped Height of Slope length of Turfing Avg
Slno Chiange Level+1 meter Area (Sqm) Remarks
(M) Level Turfing Length
protection Details Length in m
1 0.000 (0x2.236) 0.00
2 0.025 25 123.325 125.825 3.675 (3.68x2.236) 8.22 4.11 102.75
3 0.050 25 117.070 120.156 9.344 (9.34x2.236)+5 25.89 17.06 426.38
4 0.075 25 113.015 116.912 12.588 (12.59x2.236)+5 33.15 29.52 738.00
5 0.100 25 113.380 117.204 12.296 (12.3x2.236)+5 32.49 32.82 820.50
6 0.125 25 112.880 116.804 12.696 (12.7x2.236)+5 33.39 32.94 823.50
7 0.150 25 112.880 116.804 12.696 (12.7x2.236)+5 33.39 33.39 834.75
8 0.175 25 112.965 116.872 12.628 (12.63x2.236)+5 33.24 33.32 832.88
9 0.200 25 112.990 116.892 12.608 (12.61x2.236)+5 33.19 33.22 830.38
10 0.225 25 113.220 117.076 12.424 (12.42x2.236)+5 32.78 32.99 824.63
11 0.250 25 113.300 117.140 12.360 (12.36x2.236)+5 32.64 32.71 817.75
12 0.275 25 113.335 117.168 12.332 (12.33x2.236)+5 32.57 32.61 815.13
13 0.300 25 113.645 117.416 12.084 (12.08x2.236)+5 32.02 32.30 807.38
14 0.325 25 113.790 117.532 11.968 (11.97x2.236)+5 31.76 31.89 797.25
15 0.350 25 113.880 117.604 11.896 (11.9x2.236)+5 31.60 31.68 792.00
16 0.375 25 113.870 117.596 11.904 (11.9x2.236)+5 31.62 31.61 790.25
17 0.400 25 113.905 117.624 11.876 (11.88x2.236)+5 31.55 31.59 789.63
18 0.425 25 113.950 117.660 11.840 (11.84x2.236)+5 31.47 31.51 787.75
19 0.450 25 113.925 117.640 11.860 (11.86x2.236)+5 31.52 31.50 787.38
20 0.475 25 113.855 117.584 11.916 (11.92x2.236)+5 31.64 31.58 789.50
21 0.500 25 113.755 117.504 11.996 (12x2.236)+5 31.82 31.73 793.25
22 0.525 25 113.680 117.444 12.056 (12.06x2.236)+5 31.96 31.89 797.25
23 0.550 25 113.610 117.388 12.112 (12.11x2.236)+5 32.08 32.02 800.50
24 0.575 25 113.545 117.336 12.164 (12.16x2.236)+5 32.20 32.14 803.50
25 0.600 25 113.545 117.336 12.164 (12.16x2.236)+5 32.20 32.20 805.00
26 0.625 25 113.440 117.252 12.248 (12.25x2.236)+5 32.39 32.30 807.38
27 0.650 25 113.400 117.220 12.280 (12.28x2.236)+5 32.46 32.43 810.63
28 0.675 25 113.395 117.216 12.284 (12.28x2.236)+5 32.47 32.47 811.63
29 0.700 25 113.240 117.092 12.408 (12.41x2.236)+5 32.74 32.61 815.13
30 0.725 25 113.175 117.040 12.460 (12.46x2.236)+5 32.86 32.80 820.00
31 0.750 25 113.080 116.964 12.536 (12.54x2.236)+5 33.03 32.95 823.63
32 0.775 25 113.040 116.932 12.568 (12.57x2.236)+5 33.10 33.07 826.63
33 0.800 25 112.760 116.708 12.792 (12.79x2.236)+5 33.60 33.35 833.75
34 0.825 25 112.655 116.624 12.876 (12.88x2.236)+5 33.79 33.70 842.38
35 0.850 25 112.405 116.424 13.076 (13.08x2.236)+5 34.24 34.02 850.38
36 0.875 25 112.375 116.400 13.100 (13.1x2.236)+5 34.29 34.27 856.63
37 0.900 25 111.920 116.036 13.464 (13.46x2.236)+5 35.11 34.70 867.50
38 0.925 25 111.700 115.860 13.640 (13.64x2.236)+5 35.50 35.31 882.63
39 0.950 25 111.420 115.636 13.864 (13.86x2.236)+5 36.00 35.75 893.75
40 0.975 25 111.115 115.392 14.108 (14.11x2.236)+5 36.55 36.28 906.88
41 1.000 25 110.965 115.272 14.228 (14.23x2.236)+5 36.81 36.68 917.00
42 1.025 25 110.895 115.216 14.284 (14.28x2.236)+5 36.94 36.88 921.87
43 1.050 25 110.595 114.976 14.524 (14.52x2.236)+5 37.48 37.21 930.25
44 1.075 25 110.920 115.236 14.264 (14.26x2.236)+5 36.89 37.19 929.62
45 1.100 25 110.220 114.676 14.824 (14.82x2.236)+5 38.15 37.52 938.00
46 1.125 25 109.730 114.284 15.216 (15.22x2.236)+5 39.02 38.59 964.62
47 1.143 18 111.595 115.776 13.724 (13.72x2.236)+5 35.69 37.36 672.39
Total Quantity 37129.97 Cum
Formation of Mallamadugu Reservoir
BUND-2
Detail Estimate U/S Toe Wall
Rip Rap
4.605
3.784
2.963
0.675
0.875
1.075

0.6
1 in 1 0.722 2.5 in 1
0.843

200mm thk Sand Above 13.5 m Height 200 mm thk Metal

Rip Rap
4.085
3.355
2.625
0.675
0.875
1.075

0.6
1 in 1 0.730 2 in 1
0.860

200mm thk Sand Below 13.5 m Height 200 mm thk Metal

EWE of Toe Wall


Stripped Height of Bottom Avg Mean
Slno Chainge Top Width Depth Area Quantity
Level Bund Width Width Area
1 0.000 0.000 0.000 0.000 0 0 1.075 0
2 0.025 123.325 6.175 0.860 4.085 2.473 1.075 2.658 1.329 33.225
3 0.050 117.070 12.430 0.860 4.085 2.473 1.075 2.658 2.658 66.450
4 0.075 113.015 16.485 0.843 4.605 2.724 1.075 2.928 2.793 69.825
5 0.100 113.380 16.120 0.843 4.605 2.724 1.075 2.928 2.928 73.200
6 0.125 112.880 16.620 0.843 4.605 2.724 1.075 2.928 2.928 73.200
7 0.150 112.880 16.620 0.843 4.605 2.724 1.075 2.928 2.928 73.200
8 0.175 112.965 16.535 0.843 4.605 2.724 1.075 2.928 2.928 73.200
9 0.200 112.990 16.510 0.843 4.605 2.724 1.075 2.928 2.928 73.200
10 0.225 113.220 16.280 0.843 4.605 2.724 1.075 2.928 2.928 73.200
11 0.250 113.300 16.200 0.843 4.605 2.724 1.075 2.928 2.928 73.200
12 0.275 113.335 16.165 0.843 4.605 2.724 1.075 2.928 2.928 73.200
13 0.300 113.645 15.855 0.843 4.605 2.724 1.075 2.928 2.928 73.200
14 0.325 113.790 15.710 0.843 4.605 2.724 1.075 2.928 2.928 73.200
15 0.350 113.880 15.620 0.843 4.605 2.724 1.075 2.928 2.928 73.200
16 0.375 113.870 15.630 0.843 4.605 2.724 1.075 2.928 2.928 73.200
17 0.400 113.905 15.595 0.843 4.605 2.724 1.075 2.928 2.928 73.200
18 0.425 113.950 15.550 0.843 4.605 2.724 1.075 2.928 2.928 73.200
19 0.450 113.925 15.575 0.843 4.605 2.724 1.075 2.928 2.928 73.200
20 0.475 113.855 15.645 0.843 4.605 2.724 1.075 2.928 2.928 73.200
21 0.500 113.755 15.745 0.843 4.605 2.724 1.075 2.928 2.928 73.200
22 0.525 113.680 15.820 0.843 4.605 2.724 1.075 2.928 2.928 73.200
23 0.550 113.610 15.890 0.843 4.605 2.724 1.075 2.928 2.928 73.200
24 0.575 113.545 15.955 0.843 4.605 2.724 1.075 2.928 2.928 73.200
25 0.600 113.545 15.955 0.843 4.605 2.724 1.075 2.928 2.928 73.200
26 0.625 113.440 16.060 0.843 4.605 2.724 1.075 2.928 2.928 73.200
27 0.650 113.400 16.100 0.843 4.605 2.724 1.075 2.928 2.928 73.200
28 0.675 113.395 16.105 0.843 4.605 2.724 1.075 2.928 2.928 73.200
29 0.700 113.240 16.260 0.843 4.605 2.724 1.075 2.928 2.928 73.200
30 0.725 113.175 16.325 0.843 4.605 2.724 1.075 2.928 2.928 73.200
31 0.750 113.080 16.420 0.843 4.605 2.724 1.075 2.928 2.928 73.200
32 0.775 113.040 16.460 0.843 4.605 2.724 1.075 2.928 2.928 73.200
33 0.800 112.760 16.740 0.843 4.605 2.724 1.075 2.928 2.928 73.200
34 0.825 112.655 16.845 0.843 4.605 2.724 1.075 2.928 2.928 73.200
35 0.850 112.405 17.095 0.843 4.605 2.724 1.075 2.928 2.928 73.200
36 0.875 112.375 17.125 0.843 4.605 2.724 1.075 2.928 2.928 73.200
37 0.900 111.920 17.580 0.843 4.605 2.724 1.075 2.928 2.928 73.200
38 0.925 111.700 17.800 0.843 4.605 2.724 1.075 2.928 2.928 73.200
39 0.950 111.420 18.080 0.843 4.605 2.724 1.075 2.928 2.928 73.200
40 0.975 111.115 18.385 0.843 4.605 2.724 1.075 2.928 2.928 73.200
41 1.000 110.965 18.535 0.843 4.605 2.724 1.075 2.928 2.928 73.200
42 1.025 110.895 18.605 0.843 4.605 2.724 1.075 2.928 2.928 73.200
43 1.050 110.595 18.905 0.843 4.605 2.724 1.075 2.928 2.928 73.200
44 1.075 110.920 18.580 0.843 4.605 2.724 1.075 2.928 2.928 73.200
45 1.100 110.220 19.280 0.843 4.605 2.724 1.075 2.928 2.928 73.200
46 1.125 109.730 19.770 0.843 4.605 2.724 1.075 2.928 2.928 73.200
47 1.143 111.595 17.905 0.843 4.605 2.724 1.075 2.928 2.928 52.704
Total Quantity 3296.604
Rip rap
Stripped Height of Bottom Avg Mean
Slno Chainge Top Width Depth Area Quantity
Level Bund Width Width Area
1 0.000 0.000 0.000 0.000 0 0 0 0
2 0.025 123.325 6.175 0.600 2.625 1.613 0.675 1.089 0.545 13.625
3 0.050 117.070 12.430 0.600 2.625 1.613 0.675 1.089 1.089 27.225
4 0.075 113.015 16.485 0.600 2.963 1.782 0.675 1.203 1.146 28.650
5 0.100 113.380 16.120 0.600 2.963 1.782 0.675 1.203 1.203 30.075
6 0.125 112.880 16.620 0.600 2.963 1.782 0.675 1.203 1.203 30.075
7 0.150 112.880 16.620 0.600 2.963 1.782 0.675 1.203 1.203 30.075
8 0.175 112.965 16.535 0.600 2.963 1.782 0.675 1.203 1.203 30.075
9 0.200 112.990 16.510 0.600 2.963 1.782 0.675 1.203 1.203 30.075
10 0.225 113.220 16.280 0.600 2.963 1.782 0.675 1.203 1.203 30.075
11 0.250 113.300 16.200 0.600 2.963 1.782 0.675 1.203 1.203 30.075
12 0.275 113.335 16.165 0.600 2.963 1.782 0.675 1.203 1.203 30.075
13 0.300 113.645 15.855 0.600 2.963 1.782 0.675 1.203 1.203 30.075
14 0.325 113.790 15.710 0.600 2.963 1.782 0.675 1.203 1.203 30.075
15 0.350 113.880 15.620 0.600 2.963 1.782 0.675 1.203 1.203 30.075
16 0.375 113.870 15.630 0.600 2.963 1.782 0.675 1.203 1.203 30.075
17 0.400 113.905 15.595 0.600 2.963 1.782 0.675 1.203 1.203 30.075
18 0.425 113.950 15.550 0.600 2.963 1.782 0.675 1.203 1.203 30.075
19 0.450 113.925 15.575 0.600 2.963 1.782 0.675 1.203 1.203 30.075
20 0.475 113.855 15.645 0.600 2.963 1.782 0.675 1.203 1.203 30.075
21 0.500 113.755 15.745 0.600 2.963 1.782 0.675 1.203 1.203 30.075
22 0.525 113.680 15.820 0.600 2.963 1.782 0.675 1.203 1.203 30.075
23 0.550 113.610 15.890 0.600 2.963 1.782 0.675 1.203 1.203 30.075
24 0.575 113.545 15.955 0.600 2.963 1.782 0.675 1.203 1.203 30.075
25 0.600 113.545 15.955 0.600 2.963 1.782 0.675 1.203 1.203 30.075
26 0.625 113.440 16.060 0.600 2.963 1.782 0.675 1.203 1.203 30.075
27 0.650 113.400 16.100 0.600 2.963 1.782 0.675 1.203 1.203 30.075
28 0.675 113.395 16.105 0.600 2.963 1.782 0.675 1.203 1.203 30.075
29 0.700 113.240 16.260 0.600 2.963 1.782 0.675 1.203 1.203 30.075
30 0.725 113.175 16.325 0.600 2.963 1.782 0.675 1.203 1.203 30.075
31 0.750 113.080 16.420 0.600 2.963 1.782 0.675 1.203 1.203 30.075
32 0.775 113.040 16.460 0.600 2.963 1.782 0.675 1.203 1.203 30.075
33 0.800 112.760 16.740 0.600 2.963 1.782 0.675 1.203 1.203 30.075
34 0.825 112.655 16.845 0.600 2.963 1.782 0.675 1.203 1.203 30.075
35 0.850 112.405 17.095 0.600 2.963 1.782 0.675 1.203 1.203 30.075
36 0.875 112.375 17.125 0.600 2.963 1.782 0.675 1.203 1.203 30.075
37 0.900 111.920 17.580 0.600 2.963 1.782 0.675 1.203 1.203 30.075
38 0.925 111.700 17.800 0.600 2.963 1.782 0.675 1.203 1.203 30.075
39 0.950 111.420 18.080 0.600 2.963 1.782 0.675 1.203 1.203 30.075
40 0.975 111.115 18.385 0.600 2.963 1.782 0.675 1.203 1.203 30.075
41 1.000 110.965 18.535 0.600 2.963 1.782 0.675 1.203 1.203 30.075
42 1.025 110.895 18.605 0.600 2.963 1.782 0.675 1.203 1.203 30.075
43 1.050 110.595 18.905 0.600 2.963 1.782 0.675 1.203 1.203 30.075
44 1.075 110.920 18.580 0.600 2.963 1.782 0.675 1.203 1.203 30.075
45 1.100 110.220 19.280 0.600 2.963 1.782 0.675 1.203 1.203 30.075
46 1.125 109.730 19.770 0.600 2.963 1.782 0.675 1.203 1.203 30.075
47 1.143 111.595 17.905 0.600 2.963 1.782 0.675 1.203 1.203 21.654
Total Quantity 1354.304
Metal Filters
Metal Filters including Rip rap
Stripped Height of Bottom Avg Mean
Slno Chainge Top Width Depth Area Quantity
Level Bund Width Width Area
1 0.000 0.000 0.000 0.000 0 0 0.875 0
2 0.025 123.325 6.175 0.730 3.355 2.043 0.875 1.788 0.894 22.350
3 0.050 117.070 12.430 0.730 3.355 2.043 0.875 1.788 1.788 44.700
4 0.075 113.015 16.485 0.722 3.784 2.253 0.875 1.971 1.88 47.000
5 0.100 113.380 16.120 0.722 3.784 2.253 0.875 1.971 1.971 49.275
6 0.125 112.880 16.620 0.722 3.784 2.253 0.875 1.971 1.971 49.275
7 0.150 112.880 16.620 0.722 3.784 2.253 0.875 1.971 1.971 49.275
8 0.175 112.965 16.535 0.722 3.784 2.253 0.875 1.971 1.971 49.275
9 0.200 112.990 16.510 0.722 3.784 2.253 0.875 1.971 1.971 49.275
10 0.225 113.220 16.280 0.722 3.784 2.253 0.875 1.971 1.971 49.275
11 0.250 113.300 16.200 0.722 3.784 2.253 0.875 1.971 1.971 49.275
12 0.275 113.335 16.165 0.722 3.784 2.253 0.875 1.971 1.971 49.275
13 0.300 113.645 15.855 0.722 3.784 2.253 0.875 1.971 1.971 49.275
14 0.325 113.790 15.710 0.722 3.784 2.253 0.875 1.971 1.971 49.275
15 0.350 113.880 15.620 0.722 3.784 2.253 0.875 1.971 1.971 49.275
16 0.375 113.870 15.630 0.722 3.784 2.253 0.875 1.971 1.971 49.275
17 0.400 113.905 15.595 0.722 3.784 2.253 0.875 1.971 1.971 49.275
18 0.425 113.950 15.550 0.722 3.784 2.253 0.875 1.971 1.971 49.275
19 0.450 113.925 15.575 0.722 3.784 2.253 0.875 1.971 1.971 49.275
20 0.475 113.855 15.645 0.722 3.784 2.253 0.875 1.971 1.971 49.275
21 0.500 113.755 15.745 0.722 3.784 2.253 0.875 1.971 1.971 49.275
22 0.525 113.680 15.820 0.722 3.784 2.253 0.875 1.971 1.971 49.275
23 0.550 113.610 15.890 0.722 3.784 2.253 0.875 1.971 1.971 49.275
24 0.575 113.545 15.955 0.722 3.784 2.253 0.875 1.971 1.971 49.275
25 0.600 113.545 15.955 0.722 3.784 2.253 0.875 1.971 1.971 49.275
26 0.625 113.440 16.060 0.722 3.784 2.253 0.875 1.971 1.971 49.275
27 0.650 113.400 16.100 0.722 3.784 2.253 0.875 1.971 1.971 49.275
28 0.675 113.395 16.105 0.722 3.784 2.253 0.875 1.971 1.971 49.275
29 0.700 113.240 16.260 0.722 3.784 2.253 0.875 1.971 1.971 49.275
30 0.725 113.175 16.325 0.722 3.784 2.253 0.875 1.971 1.971 49.275
31 0.750 113.080 16.420 0.722 3.784 2.253 0.875 1.971 1.971 49.275
32 0.775 113.040 16.460 0.722 3.784 2.253 0.875 1.971 1.971 49.275
33 0.800 112.760 16.740 0.722 3.784 2.253 0.875 1.971 1.971 49.275
34 0.825 112.655 16.845 0.722 3.784 2.253 0.875 1.971 1.971 49.275
35 0.850 112.405 17.095 0.722 3.784 2.253 0.875 1.971 1.971 49.275
36 0.875 112.375 17.125 0.722 3.784 2.253 0.875 1.971 1.971 49.275
37 0.900 111.920 17.580 0.722 3.784 2.253 0.875 1.971 1.971 49.275
38 0.925 111.700 17.800 0.722 3.784 2.253 0.875 1.971 1.971 49.275
39 0.950 111.420 18.080 0.722 3.784 2.253 0.875 1.971 1.971 49.275
40 0.975 111.115 18.385 0.722 3.784 2.253 0.875 1.971 1.971 49.275
41 1.000 110.965 18.535 0.722 3.784 2.253 0.875 1.971 1.971 49.275
42 1.025 110.895 18.605 0.722 3.784 2.253 0.875 1.971 1.971 49.275
43 1.050 110.595 18.905 0.722 3.784 2.253 0.875 1.971 1.971 49.275
44 1.075 110.920 18.580 0.722 3.784 2.253 0.875 1.971 1.971 49.275
45 1.100 110.220 19.280 0.722 3.784 2.253 0.875 1.971 1.971 49.275
46 1.125 109.730 19.770 0.722 3.784 2.253 0.875 1.971 1.971 49.275
47 1.143 111.595 17.905 0.722 3.784 2.253 0.875 1.971 1.971 35.478
Total Quantity Metal Filters including Rip Rap 2219.078
Deduct Rip Rap Quantity 1354.304
Total Quantity of Metal Filters 864.774
Sand Filters
Sand Filters including Rip rap and Metal Filters
Stripped Height of Bottom Avg Mean
Slno Chainge Top Width Depth Area Quantity
Level Bund Width Width Area
1 0.000 0.000 0.000 0.000 0 0 1.075 0
2 0.025 123.325 6.175 0.860 4.085 2.473 1.075 2.658 1.329 33.225
3 0.050 117.070 12.430 0.860 4.085 2.473 1.075 2.658 2.658 66.450
4 0.075 113.015 16.485 0.843 4.605 2.724 1.075 2.928 2.793 69.825
5 0.100 113.380 16.120 0.843 4.605 2.724 1.075 2.928 2.928 73.200
6 0.125 112.880 16.620 0.843 4.605 2.724 1.075 2.928 2.928 73.200
7 0.150 112.880 16.620 0.843 4.605 2.724 1.075 2.928 2.928 73.200
8 0.175 112.965 16.535 0.843 4.605 2.724 1.075 2.928 2.928 73.200
9 0.200 112.990 16.510 0.843 4.605 2.724 1.075 2.928 2.928 73.200
10 0.225 113.220 16.280 0.843 4.605 2.724 1.075 2.928 2.928 73.200
11 0.250 113.300 16.200 0.843 4.605 2.724 1.075 2.928 2.928 73.200
12 0.275 113.335 16.165 0.843 4.605 2.724 1.075 2.928 2.928 73.200
13 0.300 113.645 15.855 0.843 4.605 2.724 1.075 2.928 2.928 73.200
14 0.325 113.790 15.710 0.843 4.605 2.724 1.075 2.928 2.928 73.200
15 0.350 113.880 15.620 0.843 4.605 2.724 1.075 2.928 2.928 73.200
16 0.375 113.870 15.630 0.843 4.605 2.724 1.075 2.928 2.928 73.200
17 0.400 113.905 15.595 0.843 4.605 2.724 1.075 2.928 2.928 73.200
18 0.425 113.950 15.550 0.843 4.605 2.724 1.075 2.928 2.928 73.200
19 0.450 113.925 15.575 0.843 4.605 2.724 1.075 2.928 2.928 73.200
20 0.475 113.855 15.645 0.843 4.605 2.724 1.075 2.928 2.928 73.200
21 0.500 113.755 15.745 0.843 4.605 2.724 1.075 2.928 2.928 73.200
22 0.525 113.680 15.820 0.843 4.605 2.724 1.075 2.928 2.928 73.200
23 0.550 113.610 15.890 0.843 4.605 2.724 1.075 2.928 2.928 73.200
24 0.575 113.545 15.955 0.843 4.605 2.724 1.075 2.928 2.928 73.200
25 0.600 113.545 15.955 0.843 4.605 2.724 1.075 2.928 2.928 73.200
26 0.625 113.440 16.060 0.843 4.605 2.724 1.075 2.928 2.928 73.200
27 0.650 113.400 16.100 0.843 4.605 2.724 1.075 2.928 2.928 73.200
28 0.675 113.395 16.105 0.843 4.605 2.724 1.075 2.928 2.928 73.200
29 0.700 113.240 16.260 0.843 4.605 2.724 1.075 2.928 2.928 73.200
30 0.725 113.175 16.325 0.843 4.605 2.724 1.075 2.928 2.928 73.200
31 0.750 113.080 16.420 0.843 4.605 2.724 1.075 2.928 2.928 73.200
32 0.775 113.040 16.460 0.843 4.605 2.724 1.075 2.928 2.928 73.200
33 0.800 112.760 16.740 0.843 4.605 2.724 1.075 2.928 2.928 73.200
34 0.825 112.655 16.845 0.843 4.605 2.724 1.075 2.928 2.928 73.200
35 0.850 112.405 17.095 0.843 4.605 2.724 1.075 2.928 2.928 73.200
36 0.875 112.375 17.125 0.843 4.605 2.724 1.075 2.928 2.928 73.200
37 0.900 111.920 17.580 0.843 4.605 2.724 1.075 2.928 2.928 73.200
38 0.925 111.700 17.800 0.843 4.605 2.724 1.075 2.928 2.928 73.200
39 0.950 111.420 18.080 0.843 4.605 2.724 1.075 2.928 2.928 73.200
40 0.975 111.115 18.385 0.843 4.605 2.724 1.075 2.928 2.928 73.200
41 1.000 110.965 18.535 0.843 4.605 2.724 1.075 2.928 2.928 73.200
42 1.025 110.895 18.605 0.843 4.605 2.724 1.075 2.928 2.928 73.200
43 1.050 110.595 18.905 0.843 4.605 2.724 1.075 2.928 2.928 73.200
44 1.075 110.920 18.580 0.843 4.605 2.724 1.075 2.928 2.928 73.200
45 1.100 110.220 19.280 0.843 4.605 2.724 1.075 2.928 2.928 73.200
46 1.125 109.730 19.770 0.843 4.605 2.724 1.075 2.928 2.928 73.200
47 1.143 111.595 17.905 0.843 4.605 2.724 1.075 2.928 2.928 52.704
Total Quantity Metal Filters including Rip Rap 3296.604
Deduct Rip Rap Quantity 1354.304
Deduct Metal Filters Quantity 864.774
Total Quantity of Sand Filters 1077.526
Remarks
Cum
Remarks
Cum

Remarks
Cum
Cum
Cum
Remarks
Cum
Cum
Cum
Cum
Formation of Mallamadugu Reservoir
BUND-2
Detail Estimate D/S Toe Drain

0.5 M GL
2 in 1 1 in 1 300 mm Thk Rip Rap.
0.5 M 200 mm thk Metal
0.5 M 200 mm thk Sand
0.695
2 in1 0.825 1in1
0.955

D/S Toe Wall


Earthwork Excavation
Top wodth of Toe Wall at Stripped Level = 3.47 M
Bottom Width of Toe Wall = 0.955 M
Height = 1.2 M
3.47+0.955
Area of EWE X 1.2 = 2.66 Sqm
2

Area of Rip rap


Bottom Width of Toe Drain = 0.5 M
Bed Level of The Toe drain = (GL-0.5)
Top Width of the Lug = 0.5 M

300 MM thk Rip Rap


BED
Bottom Width of Rip rap = 0.695 M
Top Width 0.695+0.3X3 = 1.595 M
1.595+0.695
Area of Bed X 0.3 = 0.34 Sqm
2
R/S Slope= (sqrt(1X1+1X1) X 0.3) X0.2 = 0.08 Sqm
L/S Slope (sqrt(2X1+2X1) X 0.3) X0.5 = 0.34 Sqm
Lug
Top Width = 0.5 M
Bottom Width 0.5+0.3X1 = 0.8 M
0.8+0.5
Area of Lug X 0.3 = 0.2 Sqm
2
0.34+0.08+0.34+0.2 = 0.96 Sqm
Total Area of Rip Rap

200 mm Thk Metal


BED
Bottom Width = 0.825 M
Top Width 0.825+0.2X3 = 1.425 M
1.425+0.825
Area of Bed X 0.2 = 0.23 Sqm
2
R/S Slope= (sqrt(1X1+1X1) X 0.2) X0.3 = 0.08 Sqm
L/S Slope (sqrt(2X1+2X1) X 0.2) X0.8 = 0.36 Sqm
Lug
Top Width = 0.38 M
Bottom Width 0.38+0.2X1 = 0.58 M
0.58+0.38
Area of Lug X 0.2 = 0.1 Sqm
2
Total Area of Metal 0.23+0.08+0.36+0.1 = 0.77 Sqm
Filter
200 mm Thk Sand
BED
Bottom Width = 0.955 M
Top Width 0.955+0.2X3 = 1.555 M
1.555+0.955
Area of Bed X 0.2 = 0.25 Sqm
2
R/S Slope= (sqrt(1X1+1X1) X 0.2) X0.3 = 0.08 Sqm
L/S Slope (sqrt(2X1+2X1) X 0.2) X1 = 0.45 Sqm
Lug
Top Width = 0.29 M
Bottom Width 0.29+0.2X1 = 0.49 M
0.49+0.29
Area of Lug X 0.2 = 0.08 Sqm
2
Total Area of Sand 0.25+0.08+0.45+0.08 = 0.86 Sqm
Filter

Length Area Quanitty


Slno Descrption of item Remarks
(M) (Sqm) (Cum)
1 Eath work Excavation 1143 2.66 3040.38
2 Rip Rap 1143 0.96 1097.28
3 Metal Filters 1143 0.77 880.11
5 Sand Filters 1143 0.86 982.98
Formation of Mallamadugu Reservoir
BUND-2
Detail Estimate D/S Rock- Toe Protection

300 mm Thick Rip Rap

1M

200 mm thick Metal Filter

200 mm thick Sand Filter

Height of Toe Protection = 1 M


Incliend Height of Toe protection Sqrt(2X2+1X1) x 1 m = 2.24 M
Thick ness of Rip Rap = 0.3 M
Thickness of Metal Filter = 0.2 M
Thickness of Sand Filter = 0.2 M
Area of Rip Rap = 2.24X0.3 = 0.67 Sqm
Area of Metal Filter = 2.24X0.2 = 0.45 Sqm
Area of Sand Filter = 2.24X0.2 = 0.45 Sqm

Length of Area in Quantity


Slno Descrption of item Remarks
Bund in M Sqm in Cum

1 Rip Rap 1143 0.67 765.81


2 Metal Fiters 1143 0.45 514.35
3 Sand Filters 1143 0.45 514.35
Formation Mallamadugu Reservoir
BUND-3-Area / Quantity Statement
Behind sand Behind Metal Inclined Sand horizontal Sand 450mm thk Rip
Stripping Rock-toe Hearting 200mm thk Metal 200mm thk sand Net Casing Area
Filters Filters Chimney Filter Rap
Chainge
Slno
in Km
Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity
Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum

1 0.000 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2 0.025 18.70 233.75 3.09 38.63 0.41 5.13 0.41 5.13 57.96 724.50 6.90 86.25 19.63 245.38 12.99 162.38 5.77 72.13 5.77 72.13 183.78 2297.25

3 0.050 29.51 602.63 14.48 219.63 0.88 16.13 0.88 16.13 186.35 3053.88 19.50 330.00 24.16 547.38 23.49 456.00 10.44 202.63 10.44 202.63 594.77 9731.88

4 0.075 33.25 784.50 20.09 432.13 1.04 24.00 1.04 24.00 244.15 5381.25 23.21 533.85 26.65 635.13 26.85 629.25 11.93 279.63 11.93 279.63 798.11 17411.03

5 0.100 32.99 828.00 19.69 497.25 1.02 25.75 1.02 25.75 240.08 6052.88 22.97 577.20 26.48 664.13 26.62 668.38 11.83 297.00 11.83 297.00 783.69 19772.55

6 0.125 32.65 820.50 19.15 485.50 1.01 25.38 1.01 25.38 234.43 5931.38 22.62 569.85 26.25 659.13 26.31 661.63 11.69 294.00 11.69 294.00 764.04 19346.65

7 0.150 32.29 811.75 18.58 471.63 1.00 25.13 1.00 25.13 228.72 5789.38 22.26 561.00 26.01 653.25 25.99 653.75 11.55 290.50 11.55 290.50 743.79 18847.88

8 0.175 32.04 804.13 18.19 459.63 0.98 24.75 0.98 24.75 224.69 5667.63 22.02 553.50 25.85 648.25 25.77 647.00 11.45 287.50 11.45 287.50 729.89 18421.00

9 0.200 31.79 797.88 17.81 450.00 0.97 24.38 0.97 24.38 220.80 5568.63 21.77 547.35 25.68 644.13 25.54 641.38 11.35 285.00 11.35 285.00 715.95 18073.03

10 0.225 31.52 791.38 17.38 439.88 0.96 24.13 0.96 24.13 216.42 5465.25 21.49 540.75 25.50 639.75 25.29 635.38 11.24 282.38 11.24 282.38 700.80 17709.38

11 0.250 31.50 787.75 17.35 434.13 0.96 24.00 0.96 24.00 216.15 5407.13 21.47 537.00 25.49 637.38 25.28 632.13 11.23 280.88 11.23 280.88 699.62 17505.25

12 0.270 30.69 621.90 16.16 335.10 0.93 18.90 0.93 18.90 203.78 4199.30 20.68 421.44 24.95 504.40 24.56 498.40 10.91 221.40 10.91 221.40 656.36 13559.86

Total 7884.15 4263.48 237.65 237.65 53241.18 5258.19 6478.28 6285.65 2793.03 2793.03 172675.74
Formation Mallamadugu Reservoir
BUND-3
Cross Section 0.025 Km
T.B.L = + 131.000 M Avg. G.L = + 120.625 M
Stripped.Level = + 120.325 M Stri.Lev = + 120.325 M
Height of Bund 10.675 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 131.000 - 120.325 )X 4+6+10+1.717+1.9= 62.32 M
Depth of Stripping ( 120.625 - 120.325 ) = 0.300 M
Area of Stripping ( 62.320 X 0.300 ) = 18.700 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-120.325 )X 20% 1.435 = 1.44 M
Bottom Width of Rock-Toe = 1.435 X 3 = 4.31 M
Area of Rock -Toe =1/2X4.31X1.435 = 3.09 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.435 = 2.03 M
Area = 2.03X0.2 = 0.41 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.435 = 2.03 M
Area = 2.03X0.2 = 0.41 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 120.325 )X 0.5*2+3 = 11.18 M
Top Width = 3M
Arae of Hearting Soils = 3+11.18
X 8.175 = 57.96 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 131-120.325)X2+3+5-0.57-4.31- 11.18/2 = 18.88 M
Top Width = 18.88+1.5 = 20.38 M
Arae of Hearting Soils = 20.38+18.88
X 1.000 = 19.63 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 121.325
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X 6.175 = 6.9 M
Area of Inclined Sand Chimney = 6.9 X 1 = 6.9 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 10.675 + 5 = 28.87 M
Arae of 450thk Rip Rap = 28.87X0.45 = 12.99 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 10.675 + 5 = 28.87 M
Arae of 200thk Sand = 28.87X0.2 = 5.77 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 10.675 + 5 = 28.87 M
Arae of 200thk Sand = 28.87X0.2 = 5.77 Sqm
9) Area of Bund
Bottom Width ( 131.000 - 120.325 )X 4+6+10 = 58.7 M
At 120.8 Incl Berm ( 131.000 - 120.800 )X 4+6+10 56.8 M
Top Width = 6M
Arae of Bund up to Berm = 56.8+58.7
X 0.475 = 27.43 Sqm
2
Arae of Bund Berm to TBL = 6+46.8
X 10.200 = 269.28 Sqm
2
Total 296.71 Sqm
12)Net casing Area = 296.71-3.09-0.41-0.41-57.96-19.63-6.9-12.99-5.77-5.77 = 183.78 Sqm
Slno Descrption Area
1 Stripping = 18.700 Sqm
8 Rock-toe = 3.09 Sqm
9 Behind sand Filters = 0.41 Sqm
10 Behind Metal Filters = 0.41 Sqm
11 Hearting = 57.96 Sqm
12 Inclined Sand Chimney = 6.9 Sqm
13 horizontal Sand Filter = 19.63 Sqm
14 450mm thk Rip Rap = 12.99 Sqm
15 200mm thk Metal = 5.77 Sqm
16 200mm thk sand = 5.77 Sqm
17 Net Casing Area = 183.78 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.050 Km
T.B.L = + 129.500 M Avg. G.L = + 112.265 M
Stripped.Level = + 111.965 M Stri.Lev = + 111.965 M
Height of Bund 17.535 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 111.965 )X 4.5+6+10+1.567+2.5= 98.37 M
Depth of Stripping ( 112.265 - 111.965 ) = 0.300 M
Area of Stripping ( 98.370 X 0.300 ) = 29.510 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-111.965 )X 20% 3.107 = 3.11 M
Bottom Width of Rock-Toe = 3.107 X 3 = 9.32 M
Area of Rock -Toe = 1/2X9.32X3.107 = 14.48 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.107 = 4.39 M
Area = 4.39X0.2 = 0.88 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.107 = 4.39 M
Area = 4.39X0.2 = 0.88 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 111.965 )X 0.5*2+3 = 19.54 M
Top Width = 3 M
Arae of Hearting Soils = 3+19.54
X 16.535 = 186.35 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-111.965)X2+3+5-0.57-9.32- 19.54/2 = 23.41 M
Top Width = 23.41+1.5 = 24.91 M
Arae of Hearting Soils = 24.91+23.41
X 1.000 = 24.16 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 112.965
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 14.535 = 16.25 M
Area of Inclined Sand Chimney = 16.25 X 1.2 = 19.5 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 17.535 + 5 = 52.21 M
Arae of 450thk Rip Rap = 52.21X0.45 = 23.49 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 17.535 + 5 = 52.21 M
Arae of 200thk Sand = 52.21X0.2 = 10.44 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 17.535 + 5 = 52.21 M
Arae of 200thk Sand = 52.21X0.2 = 10.44 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 111.965 )X 4.5+6+10 = 94.91 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+94.91
X 8.835 = 662.89 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 885.39 Sqm
12)Net casing Area = 885.39-14.48-0.88-0.88-186.35-24.16-19.5-23.49-10.44-10.44 = 594.77 Sqm
Slno Descrption Area
1 Stripping = 29.510 Sqm
8 Rock-toe = 14.48 Sqm
9 Behind sand Filters = 0.88 Sqm
10 Behind Metal Filters = 0.88 Sqm
11 Hearting = 186.35 Sqm
12 Inclined Sand Chimney = 19.5 Sqm
13 horizontal Sand Filter = 24.16 Sqm
14 450mm thk Rip Rap = 23.49 Sqm
15 200mm thk Metal = 10.44 Sqm
16 200mm thk sand = 10.44 Sqm
17 Net Casing Area = 594.77 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.075 Km
T.B.L = + 129.500 M Avg. G.L = + 109.500 M
Stripped.Level = + 109.200 M Stri.Lev = + 109.200 M
Height of Bund 20.300 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 109.200 )X 4.5+6+10+1.567+2.5= 110.8 M
Depth of Stripping ( 109.500 - 109.200 ) = 0.300 M
Area of Stripping ( 110.820 X 0.300 ) = 33.250 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-109.2 )X 20% 3.66 = 3.66 M
Bottom Width of Rock-Toe = 3.66 X 3 = 10.98 M
Area of Rock -Toe = 1/2X10.98X3.66 = 20.09 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.660 = 5.18 M
Area = 5.18X0.2 = 1.04 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.660 = 5.18 M
Area = 5.18X0.2 = 1.04 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 109.200 )X 0.5*2+3 = 22.3 M
Top Width = 3 M
Arae of Hearting Soils = 3+22.3
X 19.300 = 244.15 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-109.2)X2+3+5-0.57-10.98 - 22.3/2 = 25.90 M
Top Width = 25.9+1.5 = 27.40 M
Arae of Hearting Soils = 27.4+25.9
X 1.000 = 26.65 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 110.200
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 17.300 = 19.34 M
Area of Inclined Sand Chimney = 19.34 X 1.2 = 23.208 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 20.300 + 5 = 59.66 M
Arae of 450thk Rip Rap = 59.66X0.45 = 26.85 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 20.300 + 5 = 59.66 M
Arae of 200thk Sand = 59.66X0.2 = 11.93 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 20.300 + 5 = 59.66 M
Arae of 200thk Sand = 59.66X0.2 = 11.93 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 109.200 )X 4.5+6+10 = 107.35 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+107.35
X 11.600 = 942.50 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 1165.00 Sqm
12)Net casing Area = 1165-20.09-1.04-1.04-244.15-26.65-23.208-26.85-11.93-11.93 = 798.11 Sqm
Slno Descrption Area
1 Stripping = 33.250 Sqm
8 Rock-toe = 20.09 Sqm
9 Behind sand Filters = 1.04 Sqm
10 Behind Metal Filters = 1.04 Sqm
11 Hearting = 244.15 Sqm
12 Inclined Sand Chimney = 23.208 Sqm
13 horizontal Sand Filter = 26.65 Sqm
14 450mm thk Rip Rap = 26.85 Sqm
15 200mm thk Metal = 11.93 Sqm
16 200mm thk sand = 11.93 Sqm
17 Net Casing Area = 798.11 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.100 Km
T.B.L = + 129.500 M Avg. G.L = + 109.685 M
Stripped.Level = + 109.385 M Stri.Lev = + 109.385 M
Height of Bund 20.115 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 109.385 )X 4.5+6+10+1.567+2.5= 110 M
Depth of Stripping ( 109.685 - 109.385 ) = 0.300 M
Area of Stripping ( 109.980 X 0.300 ) = 32.990 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-109.385 )X 20% 3.623 = 3.62 M
Bottom Width of Rock-Toe = 3.623 X 3 = 10.87 M
Area of Rock -Toe = 1/2X10.87X3.623 = 19.69 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.623 = 5.12 M
Area = 5.12X0.2 = 1.02 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.623 = 5.12 M
Area = 5.12X0.2 = 1.02 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 109.385 )X 0.5*2+3 = 22.12 M
Top Width = 3 M
Arae of Hearting Soils = 3+22.12
X 19.115 = 240.08 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-109.385)X2+3+5-0.57-10.87 - 22.12/2 = 25.73 M
Top Width = 25.73+1.5 = 27.23 M
Arae of Hearting Soils = 27.23+25.73
X 1.000 = 26.48 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 110.385
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 17.115 = 19.14 M
Area of Inclined Sand Chimney = 19.14 X 1.2 = 22.968 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 20.115 + 5 = 59.16 M
Arae of 450thk Rip Rap = 59.16X0.45 = 26.62 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 20.115 + 5 = 59.16 M
Arae of 200thk Sand = 59.16X0.2 = 11.83 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 20.115 + 5 = 59.16 M
Arae of 200thk Sand = 59.16X0.2 = 11.83 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 109.385 )X 4.5+6+10 = 106.52 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+106.52
X 11.415 = 922.73 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 1145.23 Sqm
12)Net casing Area = 1145.23-19.69-1.02-1.02-240.08-26.48-22.968-26.62-11.83-11.83 = 783.69 Sqm
Slno Descrption Area
1 Stripping = 32.990 Sqm
8 Rock-toe = 19.69 Sqm
9 Behind sand Filters = 1.02 Sqm
10 Behind Metal Filters = 1.02 Sqm
11 Hearting = 240.08 Sqm
12 Inclined Sand Chimney = 22.968 Sqm
13 horizontal Sand Filter = 26.48 Sqm
14 450mm thk Rip Rap = 26.62 Sqm
15 200mm thk Metal = 11.83 Sqm
16 200mm thk sand = 11.83 Sqm
17 Net Casing Area = 783.69 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.125 Km
T.B.L = + 129.500 M Avg. G.L = + 109.940 M
Stripped.Level = + 109.640 M Stri.Lev = + 109.640 M
Height of Bund 19.860 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 109.640 )X 4.5+6+10+1.567+2.5= 108.8 M
Depth of Stripping ( 109.940 - 109.640 ) = 0.300 M
Area of Stripping ( 108.840 X 0.300 ) = 32.650 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-109.64 )X 20% 3.572 = 3.57 M
Bottom Width of Rock-Toe = 3.572 X 3 = 10.72 M
Area of Rock -Toe = 1/2X10.72X3.572 = 19.15 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.572 = 5.05 M
Area = 5.05X0.2 = 1.01 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.572 = 5.05 M
Area = 5.05X0.2 = 1.01 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 109.640 )X 0.5*2+3 = 21.86 M
Top Width = 3 M
Arae of Hearting Soils = 3+21.86
X 18.860 = 234.43 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-109.64)X2+3+5-0.57-10.72- 21.86/2 = 25.50 M
Top Width = 25.5+1.5 = 27.00 M
Arae of Hearting Soils = 27+25.5
X 1.000 = 26.25 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 110.640
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 16.860 = 18.85 M
Area of Inclined Sand Chimney = 18.85 X 1.2 = 22.62 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 19.860 + 5 = 58.47 M
Arae of 450thk Rip Rap = 58.47X0.45 = 26.31 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 19.860 + 5 = 58.47 M
Arae of 200thk Sand = 58.47X0.2 = 11.69 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 19.860 + 5 = 58.47 M
Arae of 200thk Sand = 58.47X0.2 = 11.69 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 109.640 )X 4.5+6+10 = 105.37 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+105.37
X 11.160 = 895.70 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 1118.20 Sqm
12)Net casing Area = 1118.2-19.15-1.01-1.01-234.43-26.25-22.62-26.31-11.69-11.69 = 764.04 Sqm
Slno Descrption Area
1 Stripping = 32.650 Sqm
8 Rock-toe = 19.15 Sqm
9 Behind sand Filters = 1.01 Sqm
10 Behind Metal Filters = 1.01 Sqm
11 Hearting = 234.43 Sqm
12 Inclined Sand Chimney = 22.62 Sqm
13 horizontal Sand Filter = 26.25 Sqm
14 450mm thk Rip Rap = 26.31 Sqm
15 200mm thk Metal = 11.69 Sqm
16 200mm thk sand = 11.69 Sqm
17 Net Casing Area = 764.04 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.150 Km
T.B.L = + 129.500 M Avg. G.L = + 110.205 M
Stripped.Level = + 109.905 M Stri.Lev = + 109.905 M
Height of Bund 19.595 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 109.905 )X 4.5+6+10+1.567+2.5= 107.6 M
Depth of Stripping ( 110.205 - 109.905 ) = 0.300 M
Area of Stripping ( 107.640 X 0.300 ) = 32.290 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-109.905 )X 20% 3.519 = 3.52 M
Bottom Width of Rock-Toe = 3.519 X 3 = 10.56 M
Area of Rock -Toe = 1/2X10.56X3.519 = 18.58 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.519 = 4.98 M
Area = 4.98X0.2 = 1 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.519 = 4.98 M
Area = 4.98X0.2 = 1 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 109.905 )X 0.5*2+3 = 21.6 M
Top Width = 3M
Arae of Hearting Soils = 3+21.6
X 18.595 = 228.72 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-109.905)X2+3+5-0.57-10.56 - 21.6/2 = 25.26 M
Top Width = 25.26+1.5 = 26.76 M
Arae of Hearting Soils = 26.76+25.26
X 1.000 = 26.01 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 110.905
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 16.595 = 18.55 M
Area of Inclined Sand Chimney = 18.55 X 1.2 = 22.26 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 19.595 + 5 = 57.76 M
Arae of 450thk Rip Rap = 57.76X0.45 = 25.99 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 19.595 + 5 = 57.76 M
Arae of 200thk Sand = 57.76X0.2 = 11.55 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 19.595 + 5 = 57.76 M
Arae of 200thk Sand = 57.76X0.2 = 11.55 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 109.905 )X 4.5+6+10 = 104.18 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6M
Arae of Bund up to Berm = 55.15+104.18
X 10.895 = 867.95 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 1090.45 Sqm
12)Net casing Area = 1090.45-18.58-1-1-228.72-26.01-22.26-25.99-11.55-11.55 = 743.79 Sqm
Slno Descrption Area
1 Stripping = 32.290 Sqm
8 Rock-toe = 18.58 Sqm
9 Behind sand Filters = 1 Sqm
10 Behind Metal Filters = 1 Sqm
11 Hearting = 228.72 Sqm
12 Inclined Sand Chimney = 22.26 Sqm
13 horizontal Sand Filter = 26.01 Sqm
14 450mm thk Rip Rap = 25.99 Sqm
15 200mm thk Metal = 11.55 Sqm
16 200mm thk sand = 11.55 Sqm
17 Net Casing Area = 743.79 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.175 Km
T.B.L = + 129.500 M Avg. G.L = + 110.390 M
Stripped.Level = + 110.090 M Stri.Lev = + 110.090 M
Height of Bund 19.410 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 110.090 )X 4.5+6+10+1.567+2.5= 106.8 M
Depth of Stripping ( 110.390 - 110.090 ) = 0.300 M
Area of Stripping ( 106.810 X 0.300 ) = 32.040 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-110.09 )X 20% 3.482 = 3.48 M
Bottom Width of Rock-Toe = 3.482 X 3 = 10.45 M
Area of Rock -Toe = 1/2X10.45X3.482 = 18.19 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.482 = 4.92 M
Area = 4.92X0.2 = 0.98 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.482 = 4.92 M
Area = 4.92X0.2 = 0.98 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 110.090 )X 0.5*2+3 = 21.41 M
Top Width = 3 M
Arae of Hearting Soils = 3+21.41
X 18.410 = 224.69 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-110.09)X2+3+5-0.57-10.45- 21.41/2 = 25.10 M
Top Width = 25.1+1.5 = 26.60 M
Arae of Hearting Soils = 26.6+25.1
X 1.000 = 25.85 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 111.090
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 16.410 = 18.35 M
Area of Inclined Sand Chimney = 18.35 X 1.2 = 22.02 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 19.410 + 5 = 57.26 M
Arae of 450thk Rip Rap = 57.26X0.45 = 25.77 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 19.410 + 5 = 57.26 M
Arae of 200thk Sand = 57.26X0.2 = 11.45 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 19.410 + 5 = 57.26 M
Arae of 200thk Sand = 57.26X0.2 = 11.45 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 110.090 )X 4.5+6+10 = 103.35 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+103.35
X 10.710 = 848.77 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 1071.27 Sqm
12)Net casing Area = 1071.27-18.19-0.98-0.98-224.69-25.85-22.02-25.77-11.45-11.45 = 729.89 Sqm
Slno Descrption Area
1 Stripping = 32.040 Sqm
8 Rock-toe = 18.19 Sqm
9 Behind sand Filters = 0.98 Sqm
10 Behind Metal Filters = 0.98 Sqm
11 Hearting = 224.69 Sqm
12 Inclined Sand Chimney = 22.02 Sqm
13 horizontal Sand Filter = 25.85 Sqm
14 450mm thk Rip Rap = 25.77 Sqm
15 200mm thk Metal = 11.45 Sqm
16 200mm thk sand = 11.45 Sqm
17 Net Casing Area = 729.89 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.200 Km
T.B.L = + 129.500 M Avg. G.L = + 110.575 M
Stripped.Level = + 110.275 M Stri.Lev = + 110.275 M
Height of Bund 19.225 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 110.275 )X 4.5+6+10+1.567+2.5= 106 M
Depth of Stripping ( 110.575 - 110.275 ) = 0.300 M
Area of Stripping ( 105.980 X 0.300 ) = 31.790 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-110.275 )X 20% 3.445 = 3.45 M
Bottom Width of Rock-Toe = 3.445 X 3 = 10.34 M
Area of Rock -Toe = 1/2X10.34X3.445 = 17.81 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.445 = 4.87 M
Area = 4.87X0.2 = 0.97 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.445 = 4.87 M
Area = 4.87X0.2 = 0.97 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 110.275 )X 0.5*2+3 = 21.23 M
Top Width = 3 M
Arae of Hearting Soils = 3+21.23
X 18.225 = 220.80 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-110.275)X2+3+5-0.57-10.34 - 21.23/2 = 24.93 M
Top Width = 24.93+1.5 = 26.43 M
Arae of Hearting Soils = 26.43+24.93
X 1.000 = 25.68 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 111.275
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 16.225 = 18.14 M
Area of Inclined Sand Chimney = 18.14 X 1.2 = 21.768 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 19.225 + 5 = 56.76 M
Arae of 450thk Rip Rap = 56.76X0.45 = 25.54 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 19.225 + 5 = 56.76 M
Arae of 200thk Sand = 56.76X0.2 = 11.35 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 19.225 + 5 = 56.76 M
Arae of 200thk Sand = 56.76X0.2 = 11.35 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 110.275 )X 4.5+6+10 = 102.51 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+102.51
X 10.525 = 829.69 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 1052.19 Sqm
12)Net casing Area = 1052.19-17.81-0.97-0.97-220.8-25.68-21.768-25.54-11.35-11.35 = 715.95 Sqm
Slno Descrption Area
1 Stripping = 31.790 Sqm
8 Rock-toe = 17.81 Sqm
9 Behind sand Filters = 0.97 Sqm
10 Behind Metal Filters = 0.97 Sqm
11 Hearting = 220.80 Sqm
12 Inclined Sand Chimney = 21.768 Sqm
13 horizontal Sand Filter = 25.68 Sqm
14 450mm thk Rip Rap = 25.54 Sqm
15 200mm thk Metal = 11.35 Sqm
16 200mm thk sand = 11.35 Sqm
17 Net Casing Area = 715.95 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.225 Km
T.B.L = + 129.500 M Avg. G.L = + 110.780 M
Stripped.Level = + 110.480 M Stri.Lev = + 110.480 M
Height of Bund 19.020 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 110.480 )X 4.5+6+10+1.567+2.5= 105.1 M
Depth of Stripping ( 110.780 - 110.480 ) = 0.300 M
Area of Stripping ( 105.060 X 0.300 ) = 31.520 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-110.48 )X 20% 3.404 = 3.40 M
Bottom Width of Rock-Toe = 3.404 X 3 = 10.21 M
Area of Rock -Toe = 1/2X10.21X3.404 = 17.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.404 = 4.81 M
Area = 4.81X0.2 = 0.96 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.404 = 4.81 M
Area = 4.81X0.2 = 0.96 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 110.480 )X 0.5*2+3 = 21.02 M
Top Width = 3 M
Arae of Hearting Soils = 3+21.02
X 18.020 = 216.42 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-110.48)X2+3+5-0.57-10.21- 21.02/2 = 24.75 M
Top Width = 24.75+1.5 = 26.25 M
Arae of Hearting Soils = 26.25+24.75
X 1.000 = 25.50 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 111.480
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 16.020 = 17.91 M
Area of Inclined Sand Chimney = 17.91 X 1.2 = 21.492 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 19.020 + 5 = 56.21 M
Arae of 450thk Rip Rap = 56.21X0.45 = 25.29 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 19.020 + 5 = 56.21 M
Arae of 200thk Sand = 56.21X0.2 = 11.24 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 19.020 + 5 = 56.21 M
Arae of 200thk Sand = 56.21X0.2 = 11.24 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 110.480 )X 4.5+6+10 = 101.59 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+101.59
X 10.320 = 808.78 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 1031.28 Sqm
12)Net casing Area = 1031.28-17.38-0.96-0.96-216.42-25.5-21.492-25.29-11.24-11.24 = 700.80 Sqm
Slno Descrption Area
1 Stripping = 31.520 Sqm
8 Rock-toe = 17.38 Sqm
9 Behind sand Filters = 0.96 Sqm
10 Behind Metal Filters = 0.96 Sqm
11 Hearting = 216.42 Sqm
12 Inclined Sand Chimney = 21.492 Sqm
13 horizontal Sand Filter = 25.50 Sqm
14 450mm thk Rip Rap = 25.29 Sqm
15 200mm thk Metal = 11.24 Sqm
16 200mm thk sand = 11.24 Sqm
17 Net Casing Area = 700.80 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.250 Km
T.B.L = + 129.500 M Avg. G.L = + 110.795 M
Stripped.Level = + 110.495 M Stri.Lev = + 110.495 M
Height of Bund 19.005 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 110.495 )X 4.5+6+10+1.567+2.5= 105 M
Depth of Stripping ( 110.795 - 110.495 ) = 0.300 M
Area of Stripping ( 104.990 X 0.300 ) = 31.500 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-110.495 )X 20% 3.401 = 3.40 M
Bottom Width of Rock-Toe = 3.401 X 3 = 10.20 M
Area of Rock -Toe = 1/2X10.2X3.401 = 17.35 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.401 = 4.81 M
Area = 4.81X0.2 = 0.96 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.401 = 4.81 M
Area = 4.81X0.2 = 0.96 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 110.495 )X 0.5*2+3 = 21.01 M
Top Width = 3 M
Arae of Hearting Soils = 3+21.01
X 18.005 = 216.15 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-110.495)X2+3+5-0.57-10.2- 21.01/2 = 24.74 M
Top Width = 24.74+1.5 = 26.24 M
Arae of Hearting Soils = 26.24+24.74
X 1.000 = 25.49 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 111.495
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 16.005 = 17.89 M
Area of Inclined Sand Chimney = 17.89 X 1.2 = 21.468 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 19.005 + 5 = 56.17 M
Arae of 450thk Rip Rap = 56.17X0.45 = 25.28 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 19.005 + 5 = 56.17 M
Arae of 200thk Sand = 56.17X0.2 = 11.23 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 19.005 + 5 = 56.17 M
Arae of 200thk Sand = 56.17X0.2 = 11.23 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 110.495 )X 4.5+6+10 = 101.52 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+101.52
X 10.305 = 807.24 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 1029.74 Sqm
12)Net casing Area = 1029.74-17.35-0.96-0.96-216.15-25.49-21.468-25.28-11.23-11.23 = 699.62 Sqm
Slno Descrption Area
1 Stripping = 31.500 Sqm
8 Rock-toe = 17.35 Sqm
9 Behind sand Filters = 0.96 Sqm
10 Behind Metal Filters = 0.96 Sqm
11 Hearting = 216.15 Sqm
12 Inclined Sand Chimney = 21.468 Sqm
13 horizontal Sand Filter = 25.49 Sqm
14 450mm thk Rip Rap = 25.28 Sqm
15 200mm thk Metal = 11.23 Sqm
16 200mm thk sand = 11.23 Sqm
17 Net Casing Area = 699.62 Sqm
Formation Mallamadugu Reservoir
BUND-1
Cross Section 0.275 Km
T.B.L = + 129.500 M Avg. G.L = + 111.390 M
Stripped.Level = + 111.090 M Stri.Lev = + 111.090 M
Height of Bund 18.410 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 111.090 )X 4.5+6+10+1.567+2.5= 102.3 M
Depth of Stripping ( 111.390 - 111.090 ) = 0.300 M
Area of Stripping ( 102.310 X 0.300 ) = 30.690 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-111.09 )X 20% 3.282 = 3.28 M
Bottom Width of Rock-Toe = 3.282 X 3 = 9.85 M
Area of Rock -Toe = 1/2X9.85X3.282 = 16.16 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.282 = 4.64 M
Area = 4.64X0.2 = 0.93 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 3.282 = 4.64 M
Area = 4.64X0.2 = 0.93 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 111.090 )X 0.5*2+3 = 20.41 M
Top Width = 3 M
Arae of Hearting Soils = 3+20.41
X 17.410 = 203.78 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-111.09)X2+3+5-0.57-9.85 - 20.41/2 = 24.20 M
Top Width = 24.2+1.5 = 25.70 M
Arae of Hearting Soils = 25.7+24.2
X 1.000 = 24.95 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 112.090
thick ness of sand = 1.2 M
Slan Length = sqrt (1*1+0.5*0.5) X 15.410 = 17.23 M
Area of Inclined Sand Chimney = 17.23 X 1.2 = 20.676 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2.5X2.5+1X1) X 18.410 + 5 = 54.57 M
Arae of 450thk Rip Rap = 54.57X0.45 = 24.56 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2.5X2.5+1X1) X 18.410 + 5 = 54.57 M
Arae of 200thk Sand = 54.57X0.2 = 10.91 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2.5X2.5+1X1) X 18.410 + 5 = 54.57 M
Arae of 200thk Sand = 54.57X0.2 = 10.91 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 111.090 )X 4.5+6+10 = 98.85 M
At 120.8 Incl Berm ( 129.500 - 120.800 )X 4.5+6+10 55.15 M
Top Width = 6 M
Arae of Bund up to Berm = 55.15+98.85
X 9.710 = 747.67 Sqm
2
Arae of Bund Berm to TBL = 6+45.15
X 8.700 = 222.50 Sqm
2
Total 970.17 Sqm
12)Net casing Area = 970.17-16.16-0.93-0.93-203.78-24.95-20.676-24.56-10.91-10.91 = 656.36 Sqm
Slno Descrption Area
1 Stripping = 30.690 Sqm
8 Rock-toe = 16.16 Sqm
9 Behind sand Filters = 0.93 Sqm
10 Behind Metal Filters = 0.93 Sqm
11 Hearting = 203.78 Sqm
12 Inclined Sand Chimney = 20.676 Sqm
13 horizontal Sand Filter = 24.95 Sqm
14 450mm thk Rip Rap = 24.56 Sqm
15 200mm thk Metal = 10.91 Sqm
16 200mm thk sand = 10.91 Sqm
17 Net Casing Area = 656.36 Sqm
Formation Mallamadugu Reservoir
BUND-3
Detail Estimate of Profile Wall
0.3

450 thk Rip Rap

Profile wall
200 thk Metal
200 thk Sand

0.3
Casing Soils
Area of Earthwork Excavation = 0.3 X 0.3 0.09 Sqm
Area of Concrete = (0.45 +0.2+0.2+0.3) X 0.3 0.35 Sqm

Concrete with grade of


U/S Face Slant Length EWE of Profile Wall
Stripped Top of the Height Mix CC M15-40 MSA
Slno Chainage Remarks
Level Profile Wall of Bund
Area Quantity Area Quantity
Details Length
(Sqm) (Cum) (Sqm) (Cum)
1 0.000 130.600 129.500 0.000 sqrt(2.0X2.0+1X1) X0 = 0.000 0.09 0.000 0.35 0.000
2 0.030 116.145 129.500 13.355 sqrt(2.5X2.5+1X1) +5 X13.355 = 40.959 0.09 3.690 0.35 14.340
3 0.060 110.583 129.500 18.917 sqrt(2.5X2.5+1X1) +5 X18.917 = 55.936 0.09 5.030 0.35 19.580
4 0.090 109.293 129.500 20.207 sqrt(2.5X2.5+1X1) +5 X20.207 = 59.409 0.09 5.350 0.35 20.790
5 0.120 109.513 129.500 19.987 sqrt(2.5X2.5+1X1) +5 X19.987 = 58.817 0.09 5.290 0.35 20.590
6 0.150 109.905 129.500 19.595 sqrt(2.5X2.5+1X1) +5 X19.595 = 57.761 0.09 5.200 0.35 20.220
7 0.180 110.183 129.500 19.317 sqrt(2.5X2.5+1X1) +5 X19.317 = 57.013 0.09 5.130 0.35 19.950
8 0.210 110.378 129.500 19.122 sqrt(2.5X2.5+1X1) +5 X19.122 = 56.488 0.09 5.080 0.35 19.770
9 0.240 110.488 129.500 19.012 sqrt(2.5X2.5+1X1) +5 X19.012 = 56.191 0.09 5.060 0.35 19.670
10 0.270 110.793 129.500 18.707 sqrt(2.5X2.5+1X1) +5 X18.707 = 55.370 0.09 4.980 0.35 19.380
Total Quantity 44.810 Cum 174.290 Cum
Formation Mallamadugu Reservoir
BUND-3
Detail Estimate of Drilling & Grouting
Drilling holes and driving casing pipe 63mm dia in the
consolidated cut off trench upto the bottom off cut of
1
along bund axis as directed in the soil with drilling
machine and casing bit including cost of casing pipe

Length of dam 270 meters


Interval of Grouting holes 3 meters
Total no of holes 91 meters
Depth of Casing Pipe 6 meters
Total length of the Pipe 546 meters
Drilling holes into the rock from the bottom of cut off
trench by wagon drill to the specified depth at
2 intervals as directed for washing holes with air jet and
water in the drilled holes, founfation treatment
including refilling the holes whereever necessary
Length of dam 270 meters
Interval of Grouting holes 3 meters
Total no of holes 91 meters
Depth of each Hole 12 meters
Total length of the Drilling holes into the rock from the
1092 meters
bottom of cut off trench

Conducting in situ permeability test at 2Mtr. Zones,


3
using double packer in the drilled holes

Length of dam 270 meters


Interval of testing holes 50 meters
Total no of holes 6 meters
Depth of each Hole 12 meters
Total length of the Pipe 72 meters

Grouting the holes with cement slurry with specified


4 100.18 MT
ratio of water cement mix incliding cost of cement

Total length of the Drilling holes into the rock from the
1092 meters
bottom of cut off trench
Cement consumption 0.75 Bag for one RMT
Total Cement Consumption 819 Bags
Total Cement Consumption 41 MT
Formation Mallamadugu Reservoir
BUND-3
Detailed Estimate for 'Parpet wall' on U/S

150

CC M15-40 MSA
600
T BL .+131.000

1000

CC M 15 40 MSA 200
600
Details of Parapet

S.No Description of Item Nos Length Width Depth Quantity


1 2 3 4 5 6 7
Earth work excavation for
1 1 270.00 0.60 1.00 162.00 Cum
Deflector wall
Levelling course in CC
2 M15 with 40 MSA 1 270.00 0.60 0.20 32.40 Cum
Deflector wall
CC M15 with 40 MSA for
3 1 270.00 1.60 0.30 129.60 Cum
Parpet wall
(∏ X 0.15 X
4 Top Curve Portion 1 270.00 0.0353 9.53 Cum
0.15) /2

Detailed Estimate for 'Guard Stone' @ 3M C/C on D/S


225

750
TBL-131.000

2
450
1

Guard Stone @ 3 m C/C

S.No Description of Item Nos Length Width Depth Quantity


1 2 3 4 5 6 7
Earth work excavation for
1 91 0.225 0.225 0.45 2.07 Cum
Deflector wall
CC M15 with 40 MSA for
2 91 0.225 0.225 1.20 5.53 Cum
Parpet wall
Details for Chute Drain on D/S of BUND-3
EARTH WORK EXCAVATION:

1). Cross sectional Area at Transition starting point 0.855 Sqm.


=
2). Cross sectional Area at Transition ending point 0.583 Sqm.
=
CC M15 GRADE CONCRE WITH 40 MSA:

3). Cross sectional Area at Transition starting point = 0.585 Sqm.

4). Cross sectional Area at Transition ending point = 0.403 Sqm.

5). Transition length = 0.500 Rmt.

0.45 1.50 0.45


0.23
1.329 TW of Bed
2:1 2:1 0.409 BW of Bed
0.07 0.200 Bed Area
0.30 0.072 Sides Area
0.23 0.313 Lugs Area
All Dimensions in m 0.409 0.585 Total Area

0.30 0.90 0.30


0.23 0.950 TW of Bed
0.490 BW of Bed
1:1 1:1 0.166 Bed Area
0.07 0.046 Sides Area
0.30 0.191 Lugs Area
0.23 0.403 Total Area
0.490
DETAILED ESTIMATE OF CHUTE DRAIN @ EVERY 45 m INTERVAL ON D/S OF BUND -3

Slope length of Chute Drain Earth work Excavation CC M15 Quantity


Stripped Rock Toe Height of
S.No. Chainage Length Quantity in Quantity in
Level Top level Bund in m Details Details Details
in m Cum Cum
1 2 5 6 7 8

1 0.000 130.600 131.000 0.00 (0x2.236) 0.00 0.00 0.00

2 0.045 116.145 118.416 11.08 (11.08x2.236) 24.78 0.5X(0.855+0.583)/2+(24.78-0.5)X0.583 14.51 0.5X(0.585+0.403)/2+(24.78-0.5)X0.403 10.03

3 0.090 109.293 112.934 16.57 (16.57x2.236) 37.04 0.5X(0.855+0.583)/2+(37.04-0.5)X0.583 21.66 0.5X(0.585+0.403)/2+(37.04-0.5)X0.403 14.97

4 0.135 109.773 113.318 16.18 (16.18x2.236) 36.18 0.5X(0.855+0.583)/2+(36.18-0.5)X0.583 21.16 0.5X(0.585+0.403)/2+(36.18-0.5)X0.403 14.63

5 0.180 110.183 113.646 15.85 (15.85x2.236) 35.45 0.5X(0.855+0.583)/2+(35.45-0.5)X0.583 20.74 0.5X(0.585+0.403)/2+(35.45-0.5)X0.403 14.33

6 0.225 110.480 113.884 15.62 (15.62x2.236) 34.92 0.5X(0.855+0.583)/2+(34.92-0.5)X0.583 20.43 0.5X(0.585+0.403)/2+(34.92-0.5)X0.403 14.12

7 0.270 110.793 114.134 15.37 (15.37x2.236) 34.36 0.5X(0.855+0.583)/2+(34.36-0.5)X0.583 20.10 0.5X(0.585+0.403)/2+(34.36-0.5)X0.403 13.89

Total Total Quantity 118.60 Total Quantity 81.97

Longitudinal Chute Drain

Length = 0.27 Km
Cross sectional Area at EWE= 0.583 Sqm

Cross sectional Area Concrete= 0.403 Sqm

EWE Quanity 216.293 Cum

Concrete Quanity- M15-40 MSA 149.513 Cum

Total EWE Quantity 216.293+118.6 334.89 Cum

Total Concrete Quantity 149.513+81.97 231.48 Cum


Details Estimate of Rock Toe of Bund-3
T.B.L = + 131.000 M Height of Rock-Toe = 20 % of Hydraluical Head= (FRL-Stipped Levels) X 20%
F.R.L = + 127.500 M Minimum Height of Rock -Toe = 1.5 Meters
M.W.L = + 127.500 M Maximum Height of Rock -Toe = 6 Meters
Bottom
Height of Rock- Top Level of Mean Area Quantity
Slno Chainage Stripped Level Width of Area (Sqm) Remarks
Toe (M) Rock -Toe (Sqm) (Cum)
Rock-Toe (M)

1 0.000 130.600 0.00 130.600 0.00 0.00


2 0.025 120.325 1.50 121.825 4.50 3.38 1.69 42.25
3 0.050 111.965 3.11 115.072 9.32 14.49 8.94 223.38
4 0.075 109.200 3.66 112.860 10.98 20.10 17.30 432.38
5 0.100 109.385 3.62 113.008 10.87 19.69 19.90 497.38
6 0.125 109.640 3.57 113.212 10.72 19.14 19.42 485.38
7 0.150 109.905 3.52 113.424 10.56 18.58 18.86 471.50
8 0.175 110.090 3.48 113.572 10.45 18.19 18.39 459.63
9 0.200 110.275 3.45 113.720 10.34 17.81 18.00 450.00
10 0.225 110.480 3.40 113.884 10.21 17.39 17.60 440.00
11 0.250 110.495 3.40 113.896 10.20 17.36 17.38 434.38
12 0.270 111.090 3.28 114.372 9.85 16.16 16.76 335.20
Total Quantity 4271.45 Cum
Grand Total 4271.45 Cum

Filters Below Rock-Toe


200 mm thick Sand Filters
Bottom Top Width
Height of Rock- Top Level of Avg Width of Mean Area
Slno Chainage Stripped Level Width of of Sand Area (Sqm) Quantity (Cum) Remarks
Toe (M) Rock -Toe Sand Filter (Sqm)
Sand Filter Filter
1 0.000 130.600 0.0 130.600 0.00 0.00 0.00 0.00
2 0.025 120.325 1.5 121.825 4.50 3.90 4.20 0.84 0.42 10.50
3 0.050 111.965 3.1 115.072 9.32 8.72 9.02 1.80 1.32 33.05
4 0.075 109.200 3.7 112.860 10.98 10.38 10.68 2.14 1.97 49.25
5 0.100 109.385 3.6 113.008 10.87 10.27 10.57 2.11 2.12 53.12
6 0.125 109.640 3.6 113.212 10.72 10.12 10.42 2.08 2.10 52.46
7 0.150 109.905 3.5 113.424 10.56 9.96 10.26 2.05 2.07 51.68
8 0.175 110.090 3.5 113.572 10.45 9.85 10.15 2.03 2.04 51.01
9 0.200 110.275 3.4 113.720 10.34 9.74 10.04 2.01 2.02 50.45
10 0.225 110.480 3.4 113.884 10.21 9.61 9.91 1.98 1.99 49.87
11 0.250 110.495 3.4 113.896 10.20 9.60 9.90 1.98 1.98 49.54
12 0.270 111.090 3.3 114.372 9.85 9.25 9.55 1.91 1.94 38.90
Total Quantity 489.84 Cum
200 mm thick Metal Filters

Bottom Top Width


Height of Rock- Top Level of Avg Width of Mean Area
Slno Chainage Stripped Level Width of of Metal Area (Sqm) Quantity (Cum) Remarks
Toe (M) Rock -Toe Metal Filter (Sqm)
Metal Filter Filter
1 0.000 130.600 0.0 130.600 0.00 0.00 0.00 0.00
2 0.025 120.325 1.5 121.825 3.90 3.30 3.60 0.72 0.36 9.00
3 0.050 111.965 3.1 115.072 8.72 8.12 8.42 1.68 1.20 30.05
4 0.075 109.200 3.7 112.860 10.38 9.78 10.08 2.02 1.85 46.25
5 0.100 109.385 3.6 113.008 10.27 9.67 9.97 1.99 2.00 50.12
6 0.125 109.640 3.6 113.212 10.12 9.52 9.82 1.96 1.98 49.46
7 0.150 109.905 3.5 113.424 9.96 9.36 9.66 1.93 1.95 48.68
8 0.175 110.090 3.5 113.572 9.85 9.25 9.55 1.91 1.92 48.01
9 0.200 110.275 3.4 113.720 9.74 9.14 9.44 1.89 1.90 47.45
10 0.225 110.480 3.4 113.884 9.61 9.01 9.31 1.86 1.87 46.87
11 0.250 110.495 3.4 113.896 9.60 9.00 9.30 1.86 1.86 46.54
12 0.270 111.090 3.3 114.372 9.25 8.65 8.95 1.79 1.82 36.50
Total Quantity 458.94 Cum
Formation of Mallamadugu Reservoir
BUND-3
Details Estimate of D/S Turfing
Length Stripped Rock Top Level+1 Height of Slope length of Turfing Avg Area
Slno Chiange Remarks
(M) Level meter protection Turfing Length (Sqm)
Details Length in m
1 0.000 130.600 131.000 0.000 (0x2.236) 0.00
2 0.025 25 120.325 122.825 6.675 (6.68x2.236) 14.93 7.47 186.63
3 0.050 25 111.965 116.072 13.428 (13.43x2.236)+5 35.03 24.98 624.50
4 0.075 25 109.200 113.860 15.640 (15.64x2.236)+5 39.97 37.50 937.50
5 0.100 25 109.385 114.008 15.492 (15.49x2.236)+5 39.64 39.81 995.13
6 0.125 25 109.640 114.212 15.288 (15.29x2.236)+5 39.18 39.41 985.25
7 0.150 25 109.905 114.424 15.076 (15.08x2.236)+5 38.71 38.95 973.63
8 0.175 25 110.090 114.572 14.928 (14.93x2.236)+5 38.38 38.55 963.63
9 0.200 25 110.275 114.720 14.780 (14.78x2.236)+5 38.05 38.22 955.38
10 0.225 25 110.480 114.884 14.616 (14.62x2.236)+5 37.68 37.87 946.63
11 0.250 25 110.495 114.896 14.604 (14.6x2.236)+5 37.65 37.67 941.63
12 0.270 20 111.090 115.372 14.128 (14.13x2.236)+5 36.59 37.12 742.40
Total Quantity 9252.31 Sqm
Formation of Mallamadugu Reservoir
BUND-3
Detail Estimate U/S Toe Wall
Rip Rap
4.605
3.784
2.963
0.675
0.875
1.075

0.6
1 in 1 0.722 2.5 in 1
0.843

200mm thk Sand Above 13.5 m Height 200 mm thk Metal

Rip Rap
4.085
3.355
2.625
0.675
0.875
1.075

0.6
1 in 1 0.730 2 in 1
0.860

200mm thk Sand Below 13.5 m Height 200 mm thk Metal

EWE of Toe Wall


Stripped Height of Bottom Avg Mean
Slno Chainge Top Width Depth Area Quantity
Level Bund Width Width Area
1 0.000 130.600 0.000 0.860 4.085 2.473 1.075 2.658
2 0.025 120.325 9.175 0.860 4.085 2.473 1.075 2.658 2.658 66.450
3 0.050 111.965 17.535 0.843 4.605 2.724 1.075 2.928 2.793 69.825
4 0.075 109.200 20.300 0.843 4.605 2.724 1.075 2.928 2.928 73.200
5 0.100 109.385 20.115 0.843 4.605 2.724 1.075 2.928 2.928 73.200
6 0.125 109.640 19.860 0.843 4.605 2.724 1.075 2.928 2.928 73.200
7 0.150 109.905 19.595 0.843 4.605 2.724 1.075 2.928 2.928 73.200
8 0.175 110.090 19.410 0.843 4.605 2.724 1.075 2.928 2.928 73.200
9 0.200 110.275 19.225 0.843 4.605 2.724 1.075 2.928 2.928 73.200
10 0.225 110.480 19.020 0.843 4.605 2.724 1.075 2.928 2.928 73.200
11 0.250 110.495 19.005 0.843 4.605 2.724 1.075 2.928 2.928 73.200
12 0.270 111.090 18.410 0.843 4.605 2.724 1.075 2.928 2.928 58.560
Total Quantity 780.435
Rip rap
Stripped Height of Bottom Avg Mean
Slno Chainge Top Width Depth Area Quantity
Level Bund Width Width Area
1 0.000 130.600 0.000 0.600 2.625 1.613 0.675 1.089
2 0.025 120.325 9.175 0.600 2.625 1.613 0.675 1.089 1.089 27.225
3 0.050 111.965 17.535 0.600 2.963 1.782 0.675 1.203 1.146 28.650
4 0.075 109.200 20.300 0.600 2.963 1.782 0.675 1.203 1.203 30.075
5 0.100 109.385 20.115 0.600 2.963 1.782 0.675 1.203 1.203 30.075
6 0.125 109.640 19.860 0.600 2.963 1.782 0.675 1.203 1.203 30.075
7 0.150 109.905 19.595 0.600 2.963 1.782 0.675 1.203 1.203 30.075
8 0.175 110.090 19.410 0.600 2.963 1.782 0.675 1.203 1.203 30.075
9 0.200 110.275 19.225 0.600 2.963 1.782 0.675 1.203 1.203 30.075
10 0.225 110.480 19.020 0.600 2.963 1.782 0.675 1.203 1.203 30.075
11 0.250 110.495 19.005 0.600 2.963 1.782 0.675 1.203 1.203 30.075
12 0.270 111.090 18.410 0.600 2.963 1.782 0.675 1.203 1.203 24.060
Total Quantity 320.535
Metal Filters
Metal Filters including Rip rap
Stripped Height of Bottom Avg Mean
Slno Chainge Top Width Depth Area Quantity
Level Bund Width Width Area
1 0.000 130.600 0.000 0.730 3.355 2.043 0.875 1.788
2 0.025 120.325 9.175 0.730 3.355 2.043 0.875 1.788 1.788 44.700
3 0.050 111.965 17.535 0.722 3.784 2.253 0.875 1.971 1.88 47.000
4 0.075 109.200 20.300 0.722 3.784 2.253 0.875 1.971 1.971 49.275
5 0.100 109.385 20.115 0.722 3.784 2.253 0.875 1.971 1.971 49.275
6 0.125 109.640 19.860 0.722 3.784 2.253 0.875 1.971 1.971 49.275
7 0.150 109.905 19.595 0.722 3.784 2.253 0.875 1.971 1.971 49.275
8 0.175 110.090 19.410 0.722 3.784 2.253 0.875 1.971 1.971 49.275
9 0.200 110.275 19.225 0.722 3.784 2.253 0.875 1.971 1.971 49.275
10 0.225 110.480 19.020 0.722 3.784 2.253 0.875 1.971 1.971 49.275
11 0.250 110.495 19.005 0.722 3.784 2.253 0.875 1.971 1.971 49.275
12 0.270 111.090 18.410 0.722 3.784 2.253 0.875 1.971 1.971 39.420
Total Quantity Metal Filters including Rip Rap 525.320
Deduct Rip Rap Quantity 320.535
Total Quantity of Metal Filters 204.785
Sand Filters
Sand Filters including Rip rap and Metal Filters
Stripped Height of Bottom Avg Mean
Slno Chainge Top Width Depth Area Quantity
Level Bund Width Width Area
1 0.000 130.600 0.000 0.860 4.085 2.473 1.075 2.658
2 0.025 120.325 9.175 0.860 4.085 2.473 1.075 2.658 2.658 66.450
3 0.050 111.965 17.535 0.843 4.605 2.724 1.075 2.928 2.793 69.825
4 0.075 109.200 20.300 0.843 4.605 2.724 1.075 2.928 2.928 73.200
5 0.100 109.385 20.115 0.843 4.605 2.724 1.075 2.928 2.928 73.200
6 0.125 109.640 19.860 0.843 4.605 2.724 1.075 2.928 2.928 73.200
7 0.150 109.905 19.595 0.843 4.605 2.724 1.075 2.928 2.928 73.200
8 0.175 110.090 19.410 0.843 4.605 2.724 1.075 2.928 2.928 73.200
9 0.200 110.275 19.225 0.843 4.605 2.724 1.075 2.928 2.928 73.200
10 0.225 110.480 19.020 0.843 4.605 2.724 1.075 2.928 2.928 73.200
11 0.250 110.495 19.005 0.843 4.605 2.724 1.075 2.928 2.928 73.200
12 0.270 111.090 18.410 0.843 4.605 2.724 1.075 2.928 2.928 58.560
Total Quantity Metal Filters including Rip Rap 780.435
Deduct Rip Rap Quantity 320.535
Deduct Metal Filters Quantity 204.785
Total Quantity of Sand Filters 255.115
Remarks

Cum
Remarks

Cum

Remarks

Cum
Cum
Cum
Remarks

Cum
Cum
Cum
Cum
Formation of Mallamadugu Reservoir
BUND-3
Detail Estimate D/S Toe Drain

0.5 M GL
2 in 1 1 in 1 300 mm Thk Rip Rap.
0.5 M 200 mm thk Metal
0.5 M 200 mm thk Sand
0.695
2 in1 0.825 1in1
0.955

D/S Toe Wall


Earthwork Excavation
Top wodth of Toe Wall at Stripped Level = 3.47 M
Bottom Width of Toe Wall = 0.955 M
Height = 1.2 M
3.47+0.955
Area of EWE X 1.2 = 2.66 Sqm
2

Area of Rip rap


Bottom Width of Toe Drain = 0.5 M
Bed Level of The Toe drain = (GL-0.5)
Top Width of the Lug = 0.5 M

300 MM thk Rip Rap


BED
Bottom Width of Rip rap = 0.695 M
Top Width 0.695+0.3X3 = 1.595 M
1.595+0.695
Area of Bed X 0.3 = 0.34 Sqm
2
R/S Slope= (sqrt(1X1+1X1) X 0.3) X0.2 = 0.08 Sqm
L/S Slope (sqrt(2X1+2X1) X 0.3) X0.5 = 0.34 Sqm
Lug
Top Width = 0.5 M
Bottom Width 0.5+0.3X1 = 0.8 M
0.8+0.5
Area of Lug X 0.3 = 0.2 Sqm
2
0.34+0.08+0.34+0.2 = 0.96 Sqm
Total Area of Rip Rap

200 mm Thk Metal


BED
Bottom Width = 0.825 M
Top Width 0.825+0.2X3 = 1.425 M
1.425+0.825
Area of Bed X 0.2 = 0.23 Sqm
2
R/S Slope= (sqrt(1X1+1X1) X 0.2) X0.3 = 0.08 Sqm
L/S Slope (sqrt(2X1+2X1) X 0.2) X0.8 = 0.36 Sqm
Lug
Top Width = 0.38 M
Bottom Width 0.38+0.2X1 = 0.58 M
0.58+0.38
Area of Lug X 0.2 = 0.1 Sqm
2
Total Area of Metal 0.23+0.08+0.36+0.1 = 0.77 Sqm
Filter
200 mm Thk Sand
BED
Bottom Width = 0.955 M
Top Width 0.955+0.2X3 = 1.555 M
1.555+0.955
Area of Bed X 0.2 = 0.25 Sqm
2
R/S Slope= (sqrt(1X1+1X1) X 0.2) X0.3 = 0.08 Sqm
L/S Slope (sqrt(2X1+2X1) X 0.2) X1 = 0.45 Sqm
Lug
Top Width = 0.29 M
Bottom Width 0.29+0.2X1 = 0.49 M
0.49+0.29
Area of Lug X 0.2 = 0.08 Sqm
2
Total Area of Sand 0.25+0.08+0.45+0.08 = 0.86 Sqm
Filter

Length Area Quanitty


Slno Descrption of item Remarks
(M) (Sqm) (Cum)
1 Eath work Excavation 270 2.66 718.2
2 Rip Rap 270 0.96 259.2
3 Metal Filters 270 0.77 207.9
5 Sand Filters 270 0.86 232.2
Formation of Mallamadugu Reservoir
BUND-3
Detail Estimate D/S Rock- Toe Protection

300 mm Thick Rip Rap

1M

200 mm thick Metal Filter

200 mm thick Sand Filter

Height of Toe Protection = 1 M


Incliend Height of Toe protection Sqrt(2X2+1X1) x 1 m = 2.24 M
Thick ness of Rip Rap = 0.3 M
Thickness of Metal Filter = 0.2 M
Thickness of Sand Filter = 0.2 M
Area of Rip Rap = 2.24X0.3 = 0.67 Sqm
Area of Metal Filter = 2.24X0.2 = 0.45 Sqm
Area of Sand Filter = 2.24X0.2 = 0.45 Sqm

Length of Area in Quantity


Slno Descrption of item Remarks
Bund in M Sqm in Cum

1 Rip Rap 270 0.67 180.90


2 Metal Fiters 270 0.45 121.50
3 Sand Filters 270 0.45 121.50
Formation Mallamadugu Reservoir
Saddle Bund-Area / Quantity Statement
Behind sand Behind Metal Inclined Sand horizontal Sand 450mm thk Rip
Stripping Rock-toe Hearting 200mm thk Metal 200mm thk sand Net Casing Area
Filters Filters Chimney Filter Rap
Chainge
Slno
in Km
Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity Area in Quantity
Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum Sqm in Cum

1 0.000

2 0.025 3.25 40.63 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0.3 3.75 0.13 1.63 0.13 1.63 1.42 17.75

3 0.050 6.19 118.00 3.38 42.25 0.42 5.25 0.42 5.25 6.81 85.13 0 0.00 1.81 22.63 2.77 38.38 1.23 17.00 1.23 17.00 13.64 188.25

4 0.075 6.19 154.75 3.38 84.50 0.42 10.50 0.42 10.50 6.81 170.25 0 0.00 1.81 45.25 2.77 69.25 1.23 30.75 1.23 30.75 13.64 341.00

5 0.100 6.19 154.75 3.38 84.50 0.42 10.50 0.42 10.50 6.81 170.25 0 0.00 1.81 45.25 2.77 69.25 1.23 30.75 1.23 30.75 13.64 341.00

6 0.125 6.19 154.75 3.38 84.50 0.42 10.50 0.42 10.50 6.81 170.25 0 0.00 1.81 45.25 2.77 69.25 1.23 30.75 1.23 30.75 13.64 341.00

7 0.150 6.19 154.75 3.38 84.50 0.42 10.50 0.42 10.50 6.81 170.25 0 0.00 1.81 45.25 2.77 69.25 1.23 30.75 1.23 30.75 13.64 341.00

8 0.175 6.19 154.75 3.38 84.50 0.42 10.50 0.42 10.50 6.81 170.25 0 0.00 1.81 45.25 2.77 69.25 1.23 30.75 1.23 30.75 13.64 341.00

9 0.200 6.19 154.75 3.38 84.50 0.42 10.50 0.42 10.50 6.81 170.25 0 0.00 1.81 45.25 2.77 69.25 1.23 30.75 1.23 30.75 13.64 341.00

10 0.225 6.19 154.75 3.38 84.50 0.42 10.50 0.42 10.50 6.81 170.25 0 0.00 1.81 45.25 2.77 69.25 1.23 30.75 1.23 30.75 13.64 341.00

11 0.250 0 77.38 42.25 5.25 5.25 85.13 0.00 22.63 34.63 15.38 15.38 170.50

Total 1319.25 676.00 84.00 84.00 1362.00 0.00 362.00 561.50 249.25 249.25 2763.50
Formation Mallamadugu Reservoir
Saddle Portion
Cross Section 0.025 Km
T.B.L = + 129.500 M Avg. G.L = + 129.500 M
Stripped.Level = + 129.200 M Stri.Lev = + 129.200 M
Height of Bund 0.300 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 129.200 )X 4+6+1.717+1.9= 10.82 M
Depth of Stripping ( 129.500 - 129.200 ) = 0.300 M
Area of Stripping ( 10.820 X 0.300 ) = 3.250 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-129.2 )X 20% -0.34 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 0 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 129.200 )X 0.5*2+3 = 2.3 M
Top Width = 3M
Arae of Hearting Soils = 3+2.3
X -0.700 = 0.00 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-129.2)X2+3-0.57-4.5 - 2.3/2 = -2.62 M
Top Width = -2.62+1.5 = -1.12 M
Arae of Hearting Soils = -1.12+-2.62
X 1.000 = 0.00 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 130.200
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X -2.700 = -3.02 M
Area of Inclined Sand Chimney = -3.02 X 1 = 0 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 0.300 = 0.67 M
Arae of 450thk Rip Rap = 0.67X0.45 = 0.3 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 0.300 = 0.67 M
Arae of 200thk Sand = 0.67X0.2 = 0.13 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 0.300 = 0.67 M
Arae of 200thk Sand = 0.67X0.2 = 0.13 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 129.200 )X 4+6 = 7.2 M
Top Width = 6M
Arae of Bund = 6+7.2
X 0.300 = 1.98 Sqm
2
12)Net casing Area = 1.98-0-0-0-0-0-0-0.3-0.13-0.13 = 1.42 Sqm

Slno Descrption Area


1 Stripping = 3.250 Sqm
8 Rock-toe = 0 Sqm
9 Behind sand Filters = 0 Sqm
10 Behind Metal Filters = 0 Sqm
11 Hearting = 0.00 Sqm
12 Inclined Sand Chimney = 0 Sqm
13 horizontal Sand Filter = 0.00 Sqm
14 450mm thk Rip Rap = 0.3 Sqm
15 200mm thk Metal = 0.13 Sqm
16 200mm thk sand = 0.13 Sqm
17 Net Casing Area = 1.42 Sqm
Formation Mallamadugu Reservoir
Saddle Portion
Cross Section 0.050 Km
T.B.L = + 129.500 M Avg. G.L = + 127.045 M
Stripped.Level = + 126.745 M Stri.Lev = + 126.745 M
Height of Bund 2.755 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 126.745 )X 4+6+1.717+1.9= 20.64 M
Depth of Stripping ( 127.045 - 126.745 ) = 0.300 M
Area of Stripping ( 20.640 X 0.300 ) = 6.190 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-126.745 )X 20% 0.151 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 126.745 )X 0.5*2+3 = 4.76 M
Top Width = 3 M
Arae of Hearting Soils = 3+4.76
X 1.755 = 6.81 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-126.745)X2+3-0.57-4.5 - 4.76/2 = 1.06 M
Top Width = 1.06+1.5 = 2.56 M
Arae of Hearting Soils = 2.56+1.06
X 1.000 = 1.81 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 127.745
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X -0.245 = 0 M
Area of Inclined Sand Chimney = 0X 1 = 0 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 450thk Rip Rap = 6.16X0.45 = 2.77 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 200thk Sand = 6.16X0.2 = 1.23 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 200thk Sand = 6.16X0.2 = 1.23 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 126.745 )X 4+6 = 17.02 M
Top Width = 6 M
Arae of Bund = 6+17.02
X 2.755 = 31.71 Sqm
2
12)Net casing Area = 31.71-3.38-0.42-0.42-6.81-1.81-0-2.77-1.23-1.23 = 13.64 Sqm

Slno Descrption Area


1 Stripping = 6.190 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 6.81 Sqm
12 Inclined Sand Chimney = 0 Sqm
13 horizontal Sand Filter = 1.81 Sqm
14 450mm thk Rip Rap = 2.77 Sqm
15 200mm thk Metal = 1.23 Sqm
16 200mm thk sand = 1.23 Sqm
17 Net Casing Area = 13.64 Sqm
Formation Mallamadugu Reservoir
Saddle Portion
Cross Section 0.075 Km
T.B.L = + 129.500 M Avg. G.L = + 127.045 M
Stripped.Level = + 126.745 M Stri.Lev = + 126.745 M
Height of Bund 2.755 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 126.745 )X 4+6+1.717+1.9= 20.64 M
Depth of Stripping ( 127.045 - 126.745 ) = 0.300 M
Area of Stripping ( 20.640 X 0.300 ) = 6.190 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-126.745 )X 20% 0.151 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 126.745 )X 0.5*2+3 = 4.76 M
Top Width = 3 M
Arae of Hearting Soils = 3+4.76
X 1.755 = 6.81 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-126.745)X2+3-0.57-4.5 - 4.76/2 = 1.06 M
Top Width = 1.06+1.5 = 2.56 M
Arae of Hearting Soils = 2.56+1.06
X 1.000 = 1.81 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 127.745
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X -0.245 = 0 M
Area of Inclined Sand Chimney = 0X 1 = 0 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 450thk Rip Rap = 6.16X0.45 = 2.77 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 200thk Sand = 6.16X0.2 = 1.23 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 200thk Sand = 6.16X0.2 = 1.23 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 126.745 )X 4+6 = 17.02 M
Top Width = 6 M
Arae of Bund = 6+17.02
X 2.755 = 31.71 Sqm
2
12)Net casing Area = 31.71-3.38-0.42-0.42-6.81-1.81-0-2.77-1.23-1.23 = 13.64 Sqm

Slno Descrption Area


1 Stripping = 6.190 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 6.81 Sqm
12 Inclined Sand Chimney = 0 Sqm
13 horizontal Sand Filter = 1.81 Sqm
14 450mm thk Rip Rap = 2.77 Sqm
15 200mm thk Metal = 1.23 Sqm
16 200mm thk sand = 1.23 Sqm
17 Net Casing Area = 13.64 Sqm
Formation Mallamadugu Reservoir
Saddle Portion
Cross Section 0.100 Km
T.B.L = + 129.500 M Avg. G.L = + 127.045 M
Stripped.Level = + 126.745 M Stri.Lev = + 126.745 M
Height of Bund 2.755 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 126.745 )X 4+6+1.717+1.9= 20.64 M
Depth of Stripping ( 127.045 - 126.745 ) = 0.300 M
Area of Stripping ( 20.640 X 0.300 ) = 6.190 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-126.745 )X 20% 0.151 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 126.745 )X 0.5*2+3 = 4.76 M
Top Width = 3 M
Arae of Hearting Soils = 3+4.76
X 1.755 = 6.81 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-126.745)X2+3-0.57-4.5 - 4.76/2 = 1.06 M
Top Width = 1.06+1.5 = 2.56 M
Arae of Hearting Soils = 2.56+1.06
X 1.000 = 1.81 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 127.745
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X -0.245 = 0 M
Area of Inclined Sand Chimney = 0X 1 = 0 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 450thk Rip Rap = 6.16X0.45 = 2.77 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 200thk Sand = 6.16X0.2 = 1.23 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 200thk Sand = 6.16X0.2 = 1.23 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 126.745 )X 4+6 = 17.02 M
Top Width = 6 M
Arae of Bund = 6+17.02
X 2.755 = 31.71 Sqm
2
12)Net casing Area = 31.71-3.38-0.42-0.42-6.81-1.81-0-2.77-1.23-1.23 = 13.64 Sqm

Slno Descrption Area


1 Stripping = 6.190 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 6.81 Sqm
12 Inclined Sand Chimney = 0 Sqm
13 horizontal Sand Filter = 1.81 Sqm
14 450mm thk Rip Rap = 2.77 Sqm
15 200mm thk Metal = 1.23 Sqm
16 200mm thk sand = 1.23 Sqm
17 Net Casing Area = 13.64 Sqm
Formation Mallamadugu Reservoir
Saddle Portion
Cross Section 0.125 Km
T.B.L = + 129.500 M Avg. G.L = + 127.045 M
Stripped.Level = + 126.745 M Stri.Lev = + 126.745 M
Height of Bund 2.755 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 126.745 )X 4+6+1.717+1.9= 20.64 M
Depth of Stripping ( 127.045 - 126.745 ) = 0.300 M
Area of Stripping ( 20.640 X 0.300 ) = 6.190 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-126.745 )X 20% 0.151 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 126.745 )X 0.5*2+3 = 4.76 M
Top Width = 3 M
Arae of Hearting Soils = 3+4.76
X 1.755 = 6.81 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-126.745)X2+3-0.57-4.5 - 4.76/2 = 1.06 M
Top Width = 1.06+1.5 = 2.56 M
Arae of Hearting Soils = 2.56+1.06
X 1.000 = 1.81 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 127.745
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X -0.245 = 0 M
Area of Inclined Sand Chimney = 0X 1 = 0 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 450thk Rip Rap = 6.16X0.45 = 2.77 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 200thk Sand = 6.16X0.2 = 1.23 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 200thk Sand = 6.16X0.2 = 1.23 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 126.745 )X 4+6 = 17.02 M
Top Width = 6 M
Arae of Bund = 6+17.02
X 2.755 = 31.71 Sqm
2
12)Net casing Area = 31.71-3.38-0.42-0.42-6.81-1.81-0-2.77-1.23-1.23 = 13.64 Sqm

Slno Descrption Area


1 Stripping = 6.190 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 6.81 Sqm
12 Inclined Sand Chimney = 0 Sqm
13 horizontal Sand Filter = 1.81 Sqm
14 450mm thk Rip Rap = 2.77 Sqm
15 200mm thk Metal = 1.23 Sqm
16 200mm thk sand = 1.23 Sqm
17 Net Casing Area = 13.64 Sqm
Formation Mallamadugu Reservoir
Saddle Portion
Cross Section 0.150 Km
T.B.L = + 129.500 M Avg. G.L = + 127.045 M
Stripped.Level = + 126.745 M Stri.Lev = + 126.745 M
Height of Bund 2.755 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 126.745 )X 4+6+1.717+1.9= 20.64 M
Depth of Stripping ( 127.045 - 126.745 ) = 0.300 M
Area of Stripping ( 20.640 X 0.300 ) = 6.190 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-126.745 )X 20% 0.151 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 126.745 )X 0.5*2+3 = 4.76 M
Top Width = 3M
Arae of Hearting Soils = 3+4.76
X 1.755 = 6.81 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-126.745)X2+3-0.57-4.5 - 4.76/2 = 1.06 M
Top Width = 1.06+1.5 = 2.56 M
Arae of Hearting Soils = 2.56+1.06
X 1.000 = 1.81 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 127.745
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X -0.245 = 0M
Area of Inclined Sand Chimney = 0X 1 = 0 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 450thk Rip Rap = 6.16X0.45 = 2.77 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 200thk Sand = 6.16X0.2 = 1.23 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 200thk Sand = 6.16X0.2 = 1.23 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 126.745 )X 4+6 = 17.02 M
Top Width = 6M
Arae of Bund = 6+17.02
X 2.755 = 31.71 Sqm
2
12)Net casing Area = 31.71-3.38-0.42-0.42-6.81-1.81-0-2.77-1.23-1.23 = 13.64 Sqm

Slno Descrption Area


1 Stripping = 6.190 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 6.81 Sqm
12 Inclined Sand Chimney = 0 Sqm
13 horizontal Sand Filter = 1.81 Sqm
14 450mm thk Rip Rap = 2.77 Sqm
15 200mm thk Metal = 1.23 Sqm
16 200mm thk sand = 1.23 Sqm
17 Net Casing Area = 13.64 Sqm
Formation Mallamadugu Reservoir
Saddle Portion
Cross Section 0.175 Km
T.B.L = + 129.500 M Avg. G.L = + 127.045 M
Stripped.Level = + 126.745 M Stri.Lev = + 126.745 M
Height of Bund 2.755 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 126.745 )X 4+6+1.717+1.9= 20.64 M
Depth of Stripping ( 127.045 - 126.745 ) = 0.300 M
Area of Stripping ( 20.640 X 0.300 ) = 6.190 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-126.745 )X 20% 0.151 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 126.745 )X 0.5*2+3 = 4.76 M
Top Width = 3M
Arae of Hearting Soils = 3+4.76
X 1.755 = 6.81 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-126.745)X2+3-0.57-4.5 - 4.76/2 = 1.06 M
Top Width = 1.06+1.5 = 2.56 M
Arae of Hearting Soils = 2.56+1.06
X 1.000 = 1.81 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 127.745
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X -0.245 = 0M
Area of Inclined Sand Chimney = 0X 1 = 0 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 450thk Rip Rap = 6.16X0.45 = 2.77 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 200thk Sand = 6.16X0.2 = 1.23 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 200thk Sand = 6.16X0.2 = 1.23 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 126.745 )X 4+6 = 17.02 M
Top Width = 6M
Arae of Bund = 6+17.02
X 2.755 = 31.71 Sqm
2
12)Net casing Area = 31.71-3.38-0.42-0.42-6.81-1.81-0-2.77-1.23-1.23 = 13.64 Sqm

Slno Descrption Area


1 Stripping = 6.190 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 6.81 Sqm
12 Inclined Sand Chimney = 0 Sqm
13 horizontal Sand Filter = 1.81 Sqm
14 450mm thk Rip Rap = 2.77 Sqm
15 200mm thk Metal = 1.23 Sqm
16 200mm thk sand = 1.23 Sqm
17 Net Casing Area = 13.64 Sqm
Formation Mallamadugu Reservoir
Saddle Portion
Cross Section 0.200 Km
T.B.L = + 129.500 M Avg. G.L = + 127.045 M
Stripped.Level = + 126.745 M Stri.Lev = + 126.745 M
Height of Bund 2.755 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 126.745 )X 4+6+1.717+1.9= 20.64 M
Depth of Stripping ( 127.045 - 126.745 ) = 0.300 M
Area of Stripping ( 20.640 X 0.300 ) = 6.190 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-126.745 )X 20% 0.151 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 126.745 )X 0.5*2+3 = 4.76 M
Top Width = 3M
Arae of Hearting Soils = 3+4.76
X 1.755 = 6.81 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-126.745)X2+3-0.57-4.5 - 4.76/2 = 1.06 M
Top Width = 1.06+1.5 = 2.56 M
Arae of Hearting Soils = 2.56+1.06
X 1.000 = 1.81 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 127.745
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X -0.245 = 0M
Area of Inclined Sand Chimney = 0X 1 = 0 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 450thk Rip Rap = 6.16X0.45 = 2.77 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 200thk Sand = 6.16X0.2 = 1.23 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 200thk Sand = 6.16X0.2 = 1.23 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 126.745 )X 4+6 = 17.02 M
Top Width = 6M
Arae of Bund = 6+17.02
X 2.755 = 31.71 Sqm
2
12)Net casing Area = 31.71-3.38-0.42-0.42-6.81-1.81-0-2.77-1.23-1.23 = 13.64 Sqm

Slno Descrption Area


1 Stripping = 6.190 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 6.81 Sqm
12 Inclined Sand Chimney = 0 Sqm
13 horizontal Sand Filter = 1.81 Sqm
14 450mm thk Rip Rap = 2.77 Sqm
15 200mm thk Metal = 1.23 Sqm
16 200mm thk sand = 1.23 Sqm
17 Net Casing Area = 13.64 Sqm
Formation Mallamadugu Reservoir
Saddle Portion
Cross Section 0.225 Km
T.B.L = + 129.500 M Avg. G.L = + 127.045 M
Stripped.Level = + 126.745 M Stri.Lev = + 126.745 M
Height of Bund 2.755 M Depth of Stripping 0.300 M
MWL=+ 127.500 M FRL 127.500 M
1)Stripping
Bottom Width of Bund ( 129.500 - 126.745 )X 4+6+1.717+1.9= 20.64 M
Depth of Stripping ( 127.045 - 126.745 ) = 0.300 M
Area of Stripping ( 20.640 X 0.300 ) = 6.190 Sqm
2)Rock-Toe
Height of Rock-Toe ( 127.5-126.745 )X 20% 0.151 = 1.50 M (Minimum Height of Rock-
Bottom Width of Rock-Toe = 1.5 X 3 = 4.50 M Toe)
Area of Rock -Toe = 1/2X4.5X1.5 = 3.38 Sqm
a)Metal Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
b)Sand Filter Behind Rock-Toe (200 mm Thk)
Incliend length = Sqrt(1X1+1X1) X 1.500 = 2.12 M
Area = 2.12X0.2 = 0.42 Sqm
3) Area of Herating Portion
Bottom Width ( 128.500 - 126.745 )X 0.5*2+3 = 4.76 M
Top Width = 3M
Arae of Hearting Soils = 3+4.76
X 1.755 = 6.81 Sqm
2
4) Area of horizontal Sand Filter (Sand Blanketn-1 M Thick)
Bottom Width of Sand ( 129.5-126.745)X2+3-0.57-4.5 - 4.76/2 = 1.06 M
Top Width = 1.06+1.5 = 2.56 M
Arae of Hearting Soils = 2.56+1.06
X 1.000 = 1.81 Sqm
2
5) Area of Inclined Sand Chimney
Top Level of Sand = 127.500
bottom level of sand = 127.745
thick ness of sand = 1M
Slan Length = sqrt (1*1+0.5*0.5) X -0.245 = 0M
Area of Inclined Sand Chimney = 0X 1 = 0 Sqm
6)Area of 450mm thk Rip Rap
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 450thk Rip Rap = 6.16X0.45 = 2.77 Sqm
7)Area of 200 mm thk Metal
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 200thk Sand = 6.16X0.2 = 1.23 Sqm
8) Area of Inclined Sand Chimney
Incliend length = Sqrt(2X2+1X1) X 2.755 = 6.16 M
Arae of 200thk Sand = 6.16X0.2 = 1.23 Sqm
9) Area of Bund
Bottom Width ( 129.500 - 126.745 )X 4+6 = 17.02 M
Top Width = 6M
Arae of Bund = 6+17.02
X 2.755 = 31.71 Sqm
2
12)Net casing Area = 31.71-3.38-0.42-0.42-6.81-1.81-0-2.77-1.23-1.23 = 13.64 Sqm

Slno Descrption Area


1 Stripping = 6.190 Sqm
8 Rock-toe = 3.38 Sqm
9 Behind sand Filters = 0.42 Sqm
10 Behind Metal Filters = 0.42 Sqm
11 Hearting = 6.81 Sqm
12 Inclined Sand Chimney = 0 Sqm
13 horizontal Sand Filter = 1.81 Sqm
14 450mm thk Rip Rap = 2.77 Sqm
15 200mm thk Metal = 1.23 Sqm
16 200mm thk sand = 1.23 Sqm
17 Net Casing Area = 13.64 Sqm
Formation Mallamadugu Reservoir
Saddle Portion
Detail Estimate of Profile Wall
0.3

450 thk Rip Rap

Profile wall
200 thk Metal
200 thk Sand

0.3
Casing Soils
Area of Earthwork Excavation = 0.3 X 0.3 0.09 Sqm
Area of Concrete = (0.45 +0.2+0.2+0.3) X 0.3 0.35 Sqm

Concrete with grade of


U/S Face Slant Length EWE of Profile Wall
Stripped Top of the Height Mix CC M15-40 MSA
Slno Chainage Remarks
Level Profile Wall of Bund
Area Quantity Area Quantity
Details Length
(Sqm) (Cum) (Sqm) (Cum)
1 0.000 129.500
2 0.030 126.745 129.500 2.755 sqrt(2.0X2.0+1X1) X2.755 = 7.418 0.09 0.670 0.35 2.600
3 0.060 126.745 129.500 2.755 sqrt(2.0X2.0+1X1) X2.755 = 7.418 0.09 0.670 0.35 2.600
4 0.090 126.745 129.500 2.755 sqrt(2.0X2.0+1X1) X2.755 = 7.418 0.09 0.670 0.35 2.600
5 0.120 126.745 129.500 2.755 sqrt(2.0X2.0+1X1) X2.755 = 7.418 0.09 0.670 0.35 2.600
6 0.150 126.745 129.500 2.755 sqrt(2.0X2.0+1X1) X2.755 = 7.418 0.09 0.670 0.35 2.600
7 0.180 126.745 129.500 2.755 sqrt(2.0X2.0+1X1) X2.755 = 7.418 0.09 0.670 0.35 2.600
8 0.210 126.745 129.500 2.755 sqrt(2.0X2.0+1X1) X2.755 = 7.418 0.09 0.670 0.35 2.600
9 0.240 126.745 129.500 2.755 sqrt(2.0X2.0+1X1) X2.755 = 7.418 0.09 0.670 0.35 2.600
10 0.250
Total Quantity 5.360 Cum 20.800 Cum
Formation Mallamadugu Reservoir
Saddle Portion
Detail Estimate of Drilling & Grouting
Drilling holes and driving casing pipe 63mm dia in the
consolidated cut off trench upto the bottom off cut of
1
along bund axis as directed in the soil with drilling
machine and casing bit including cost of casing pipe

Length of dam 250 meters


Interval of Grouting holes 3 meters
Total no of holes 84 meters
Depth of Casing Pipe 3 meters
Total length of the Pipe 252 meters
Drilling holes into the rock from the bottom of cut off
trench by wagon drill to the specified depth at
2 intervals as directed for washing holes with air jet and
water in the drilled holes, founfation treatment
including refilling the holes whereever necessary
Length of dam 250 meters
Interval of Grouting holes 3 meters
Total no of holes 84 meters
Depth of each Hole 12 meters
Total length of the Drilling holes into the rock from the
1008 meters
bottom of cut off trench

Conducting in situ permeability test at 2Mtr. Zones,


3
using double packer in the drilled holes

Length of dam 250 meters


Interval of testing holes 50 meters
Total no of holes 6 meters
Depth of each Hole 12 meters
Total length of the Pipe 72 meters

Grouting the holes with cement slurry with specified


4 MT
ratio of water cement mix incliding cost of cement

Total length of the Drilling holes into the rock from the
1008 meters
bottom of cut off trench
Cement consumption 0.75 Bag for one RMT
Total Cement Consumption 756 Bags
Total Cement Consumption 38 MT
Formation Mallamadugu Reservoir
Saddle Portion
Detailed Estimate for 'Parpet wall' on U/S

150

CC M15-40 MSA
600
T BL .+131.000

1000

CC M 15 40 MSA 200
600
Details of Parapet

S.No Description of Item Nos Length Width Depth Quantity


1 2 3 4 5 6 7
Earth work excavation for
1 1 250.00 0.60 1.00 150.00 Cum
Deflector wall
Levelling course in CC
2 M15 with 40 MSA 1 250.00 0.60 0.20 30.00 Cum
Deflector wall
CC M15 with 40 MSA for
3 1 250.00 1.60 0.30 120.00 Cum
Parpet wall
(∏ X 0.15 X
4 Top Curve Portion 1 250.00 0.0353 8.83 Cum
0.15) /2

Detailed Estimate for 'Guard Stone' @ 3M C/C on D/S


225

750
TBL-131.000

2
450
1

Guard Stone @ 3 m C/C

S.No Description of Item Nos Length Width Depth Quantity


1 2 3 4 5 6 7
Earth work excavation for
1 84 0.225 0.225 0.45 1.92 Cum
Deflector wall
CC M15 with 40 MSA for
2 84 0.225 0.225 1.20 5.12 Cum
Parpet wall
Details for Chute Drain on D/S of Saddle Portion
EARTH WORK EXCAVATION:

1). Cross sectional Area at Transition starting point 0.855 Sqm.


=
2). Cross sectional Area at Transition ending point 0.583 Sqm.
=
CC M15 GRADE CONCRE WITH 40 MSA:

3). Cross sectional Area at Transition starting point = 0.585 Sqm.

4). Cross sectional Area at Transition ending point = 0.403 Sqm.

5). Transition length = 0.500 Rmt.

0.45 1.50 0.45


0.23
1.329 TW of Bed
2:1 2:1 0.409 BW of Bed
0.07 0.200 Bed Area
0.30 0.072 Sides Area
0.23 0.313 Lugs Area
All Dimensions in m 0.409 0.585 Total Area

0.30 0.90 0.30


0.23 0.950 TW of Bed
0.490 BW of Bed
1:1 1:1 0.166 Bed Area
0.07 0.046 Sides Area
0.30 0.191 Lugs Area
0.23 0.403 Total Area
0.490
DETAILED ESTIMATE OF CHUTE DRAIN @ EVERY 45 m INTERVAL ON D/S OF Saddle Portion

Slope length of Chute Drain Earth work Excavation CC M15 Quantity


Stripped Rock Toe Height of
S.No. Chainage Length Quantity in Quantity in
Level Top level Bund in m Details Details Details
in m Cum Cum
1 2 5 6 7 8

1 0.000

2 0.045 126.745 128.245 1.26 (1.26x2.236) 2.81 0.5X(0.855+0.583)/2+(2.81-0.5)X0.583 1.71 0.5X(0.585+0.403)/2+(2.81-0.5)X0.403 1.18

3 0.090 126.745 128.245 1.26 (1.26x2.236) 2.81 0.5X(0.855+0.583)/2+(2.81-0.5)X0.583 1.71 0.5X(0.585+0.403)/2+(2.81-0.5)X0.403 1.18

4 0.135 126.745 128.245 1.26 (1.26x2.236) 2.81 0.5X(0.855+0.583)/2+(2.81-0.5)X0.583 1.71 0.5X(0.585+0.403)/2+(2.81-0.5)X0.403 1.18

5 0.180 126.745 128.245 1.26 (1.26x2.236) 2.81 0.5X(0.855+0.583)/2+(2.81-0.5)X0.583 1.71 0.5X(0.585+0.403)/2+(2.81-0.5)X0.403 1.18

6 0.225 126.745 128.245 1.26 (1.26x2.236) 2.81 0.5X(0.855+0.583)/2+(2.81-0.5)X0.583 1.71 0.5X(0.585+0.403)/2+(2.81-0.5)X0.403 1.18

7 0.250

Total Total Quantity 8.55 Total Quantity 5.90

Longitudinal Chute Drain

Length = 0.25 Km
Cross sectional Area at EWE= 0.583 Sqm

Cross sectional Area Concrete= 0.403 Sqm

EWE Quanity 55.968 Cum

Concrete Quanity- M15-40 MSA 38.688 Cum

Total EWE Quantity 55.968+8.55 64.52 Cum

Total Concrete Quantity 38.688+5.9 44.59 Cum


Formation of Mallamadugu Reservoir
Saddle Portion
Details Estimate of D/S Turfing
Rock Top
Length Stripped Height of Slope length of Turfing Avg
Slno Chiange Level+1 meter Area (Sqm) Remarks
(M) Level Turfing Length
protection Details Length in m

1 0.000

2 0.025 25 129.200 131.700

3 0.050 25 126.745 129.245 0.255 (0.25x2.236) 0.57 0.57 14.25

4 0.075 25 126.745 129.245 0.255 (0.25x2.236) 0.57 0.57 14.25

5 0.100 25 126.745 129.245 0.255 (0.25x2.236) 0.57 0.57 14.25

6 0.125 25 126.745 129.245 0.255 (0.25x2.236) 0.57 0.57 14.25

7 0.150 25 126.745 129.245 0.255 (0.25x2.236) 0.57 0.57 14.25

8 0.175 25 126.745 129.245 0.255 (0.25x2.236) 0.57 0.57 14.25

9 0.200 25 126.745 129.245 0.255 (0.25x2.236) 0.57 0.57 14.25

10 0.225 25 126.745 129.245 0.255 (0.25x2.236) 0.57 0.57 14.25

0.250
Total Quantity 114.00 Cum
Details Estimate of Rock Toe of Saddle Bund
T.B.L = + 131.000 M Height of Rock-Toe = 20 % of Hydraluical Head= (FRL-Stipped Levels) X 20%
F.R.L = + 127.500 M Minimum Height of Rock -Toe = 1.5 Meters
M.W.L = + 127.500 M Maximum Height of Rock -Toe = 6 Meters
Bottom
Height of Rock- Top Level of Mean Area Quantity
Slno Chainage Stripped Level Width of Area (Sqm) Remarks
Toe (M) Rock -Toe (Sqm) (Cum)
Rock-Toe (M)

1 0.000 0.00 0.00


2 0.025 129.200 1.50 130.700 4.50 3.38 1.69 42.25
3 0.050 126.745 1.50 128.245 4.50 3.38 3.38 84.50
4 0.075 126.745 1.50 128.245 4.50 3.38 3.38 84.50
5 0.100 126.745 1.50 128.245 4.50 3.38 3.38 84.50
6 0.125 126.745 1.50 128.245 4.50 3.38 3.38 84.50
7 0.150 126.745 1.50 128.245 4.50 3.38 3.38 84.50
8 0.175 126.745 1.50 128.245 4.50 3.38 3.38 84.50
9 0.200 126.745 1.50 128.245 4.50 3.38 3.38 84.50
10 0.225 126.745 1.50 128.245 4.50 3.38 3.38 84.50
11 0.250
Total Quantity 718.25 Cum
Grand Total 718.25 Cum

Filters Below Rock-Toe


200 mm thick Sand Filters
Bottom Top Width
Height of Rock- Top Level of Avg Width of Mean Area
Slno Chainage Stripped Level Width of of Sand Area (Sqm) Quantity (Cum) Remarks
Toe (M) Rock -Toe Sand Filter (Sqm)
Sand Filter Filter
1 0.000 0.0 0.000 0.00 0.00 0.00 0.00
2 0.025 129.200 1.5 130.700 4.50 3.90 4.20 0.84 0.42 10.50
3 0.050 126.745 1.5 128.245 4.50 3.90 4.20 0.84 0.84 21.00
4 0.075 126.745 1.5 128.245 4.50 3.90 4.20 0.84 0.84 21.00
5 0.100 126.745 1.5 128.245 4.50 3.90 4.20 0.84 0.84 21.00
6 0.125 126.745 1.5 128.245 4.50 3.90 4.20 0.84 0.84 21.00
7 0.150 126.745 1.5 128.245 4.50 3.90 4.20 0.84 0.84 21.00
8 0.175 126.745 1.5 128.245 4.50 3.90 4.20 0.84 0.84 21.00
9 0.200 126.745 1.5 128.245 4.50 3.90 4.20 0.84 0.84 21.00
10 0.225 126.745 1.5 128.245 4.50 3.90 4.20 0.84 0.84 21.00
11 0.250 0.000 0.0 0.000 0.00 -0.60 -0.30 -0.06 0.39 9.75
Total Quantity 188.25 Cum
200 mm thick Metal Filters

Bottom Top Width


Height of Rock- Top Level of Avg Width of Mean Area
Slno Chainage Stripped Level Width of of Metal Area (Sqm) Quantity (Cum) Remarks
Toe (M) Rock -Toe Metal Filter (Sqm)
Metal Filter Filter
1 0.000 0.000 0.0 0.000 0.00 0.00 0.00 0.00
2 0.025 129.200 1.5 130.700 3.90 3.30 3.60 0.72 0.36 9.00
3 0.050 126.745 1.5 128.245 3.90 3.30 3.60 0.72 0.72 18.00
4 0.075 126.745 1.5 128.245 3.90 3.30 3.60 0.72 0.72 18.00
5 0.100 126.745 1.5 128.245 3.90 3.30 3.60 0.72 0.72 18.00
6 0.125 126.745 1.5 128.245 3.90 3.30 3.60 0.72 0.72 18.00
7 0.150 126.745 1.5 128.245 3.90 3.30 3.60 0.72 0.72 18.00
8 0.175 126.745 1.5 128.245 3.90 3.30 3.60 0.72 0.72 18.00
9 0.200 126.745 1.5 128.245 3.90 3.30 3.60 0.72 0.72 18.00
10 0.225 126.745 1.5 128.245 3.90 3.30 3.60 0.72 0.72 18.00
11 0.250
Total Quantity 153.00 Cum
Formation of Mallamadugu Reservoir
Saddle Portion
Detail Estimate U/S Toe Wall
Rip Rap
4.605
3.784
2.963

0.675
0.875
1.075

0.6
1 in 1 0.722 2.5 in 1
0.843

200mm thk Sand Above 13.5 m Height 200 mm thk Metal

Rip Rap
4.085
3.355
2.625
0.675
0.875
1.075

0.6
1 in 1 0.730 2 in 1
0.860

200mm thk Sand Below 13.5 m Height 200 mm thk Metal

EWE of Toe Wall


Stripped Height of Bottom Avg Mean
Slno Chainge Top Width Depth Area Quantity Remarks
Level Bund Width Width Area
1 0.000 0.000 0.000 0 0 1.075 0
2 0.025 129.200 0.300 0.860 4.085 2.473 1.075 2.658 1.329 33.225
3 0.050 126.745 2.755 0.860 4.085 2.473 1.075 2.658 2.658 66.450
4 0.075 126.745 2.755 0.860 4.085 2.473 1.075 2.658 2.658 66.450
5 0.100 126.745 2.755 0.860 4.085 2.473 1.075 2.658 2.658 66.450
6 0.125 126.745 2.755 0.860 4.085 2.473 1.075 2.658 2.658 66.450
7 0.150 126.745 2.755 0.860 4.085 2.473 1.075 2.658 2.658 66.450
8 0.175 126.745 2.755 0.860 4.085 2.473 1.075 2.658 2.658 66.450
9 0.200 126.745 2.755 0.860 4.085 2.473 1.075 2.658 2.658 66.450
10 0.225 126.745 2.755 0.860 4.085 2.473 1.075 2.658 2.658 66.450
11 0.250

Total Quantity 564.825 Cum


Rip rap
Stripped Height of Bottom Avg Mean
Slno Chainge Top Width Depth Area Quantity Remarks
Level Bund Width Width Area
1 0.000 0.000 0.000 0.000 0 0 0.675 0
2 0.025 129.200 1.800 0.600 2.625 1.613 0.675 1.089 0.545 13.625
3 0.050 126.745 4.255 0.600 2.625 1.613 0.675 1.089 1.089 27.225
4 0.075 126.745 4.255 0.600 2.625 1.613 0.675 1.089 1.089 27.225
5 0.100 126.745 4.255 0.600 2.625 1.613 0.675 1.089 1.089 27.225
0.125 126.745 4.255 0.600 2.625 1.613 0.675 1.089 1.089 27.225
0.150 126.745 4.255 0.600 2.625 1.613 0.675 1.089 1.089 27.225
0.175 126.745 4.255 0.600 2.625 1.613 0.675 1.089 1.089 27.225
0.200 126.745 4.255 0.600 2.625 1.613 0.675 1.089 1.089 27.225
0.225 126.745 4.255 0.600 2.625 1.613 0.675 1.089 1.089 27.225
0.250
Total Quantity 231.425 Cum
Metal Filters
Metal Filters including Rip rap
Stripped Height of Bottom Avg Mean
Slno Chainge Top Width Depth Area Quantity Remarks
Level Bund Width Width Area
1 0.000 0.000 0.000 0.000 0 0 0.875 0
2 0.025 129.200 1.800 0.730 3.355 2.043 0.875 1.788 0.894 22.350
3 0.050 126.745 4.255 0.730 3.355 2.043 0.875 1.788 1.788 44.700
4 0.075 126.745 4.255 0.730 3.355 2.043 0.875 1.788 1.788 44.700
5 0.100 126.745 4.255 0.730 3.355 2.043 0.875 1.788 1.788 44.700
6 0.125 126.745 4.255 0.730 3.355 2.043 0.875 1.788 1.788 44.700
7 0.150 126.745 4.255 0.730 3.355 2.043 0.875 1.788 1.788 44.700
8 0.175 126.745 4.255 0.730 3.355 2.043 0.875 1.788 1.788 44.700
9 0.200 126.745 4.255 0.730 3.355 2.043 0.875 1.788 1.788 44.700
10 0.225 126.745 4.255 0.730 3.355 2.043 0.875 1.788 1.788 44.700
11 0.250
Total Quantity Metal Filters including Rip Rap 379.950 Cum
Deduct Rip Rap Quantity 231.425 Cum
Total Quantity of Metal Filters 148.525 Cum
Sand Filters
Sand Filters including Rip rap and Metal Filters
Stripped Height of Bottom Avg Mean
Slno Chainge Top Width Depth Area Quantity Remarks
Level Bund Width Width Area
1 0.000 0.000 0
2 0.025 129.200 1.800 0.860 4.085 2.473 1.075 2.658 1.329 33.225
3 0.050 126.745 4.255 0.860 4.085 2.473 1.075 2.658 2.658 66.450
4 0.075 126.745 4.255 0.860 4.085 2.473 1.075 2.658 2.658 66.450
5 0.100 126.745 4.255 0.860 4.085 2.473 1.075 2.658 2.658 66.450
6 0.125 126.745 4.255 0.860 4.085 2.473 1.075 2.658 2.658 66.450
7 0.150 126.745 4.255 0.860 4.085 2.473 1.075 2.658 2.658 66.450
8 0.175 126.745 4.255 0.860 4.085 2.473 1.075 2.658 2.658 66.450
9 0.200 126.745 4.255 0.860 4.085 2.473 1.075 2.658 2.658 66.450
10 0.225 126.745 4.255 0.860 4.085 2.473 1.075 2.658 2.658 66.450
11 0.250 0.000
Total Quantity Metal Filters including Rip Rap 564.825 Cum
Deduct Rip Rap Quantity 231.425 Cum
Deduct Metal Filters Quantity 148.525 Cum
Total Quantity of Sand Filters 184.875 Cum
Formation of Mallamadugu Reservoir
Saddle Portiion
Detail Estimate D/S Toe Drain

0.5 M GL
2 in 1 1 in 1 300 mm Thk Rip Rap.
0.5 M 200 mm thk Metal
0.5 M 200 mm thk Sand
0.695
2 in1 0.825 1in1
0.955

D/S Toe Wall


Earthwork Excavation
Top wodth of Toe Wall at Stripped Level = 3.47 M
Bottom Width of Toe Wall = 0.955 M
Height = 1.2 M
3.47+0.955
Area of EWE X 1.2 = 2.66 Sqm
2

Area of Rip rap


Bottom Width of Toe Drain = 0.5 M
Bed Level of The Toe drain = (GL-0.5)
Top Width of the Lug = 0.5 M

300 MM thk Rip Rap


BED
Bottom Width of Rip rap = 0.695 M
Top Width 0.695+0.3X3 = 1.595 M
1.595+0.695
Area of Bed X 0.3 = 0.34 Sqm
2
R/S Slope= (sqrt(1X1+1X1) X 0.3) X0.2 = 0.08 Sqm
L/S Slope (sqrt(2X1+2X1) X 0.3) X0.5 = 0.34 Sqm
Lug
Top Width = 0.5 M
Bottom Width 0.5+0.3X1 = 0.8 M
0.8+0.5
Area of Lug X 0.3 = 0.2 Sqm
2
0.34+0.08+0.34+0.2 = 0.96 Sqm
Total Area of Rip Rap

200 mm Thk Metal


BED
Bottom Width = 0.825 M
Top Width 0.825+0.2X3 = 1.425 M
1.425+0.825
Area of Bed X 0.2 = 0.23 Sqm
2
R/S Slope= (sqrt(1X1+1X1) X 0.2) X0.3 = 0.08 Sqm
L/S Slope (sqrt(2X1+2X1) X 0.2) X0.8 = 0.36 Sqm
Lug
Top Width = 0.38 M
Bottom Width 0.38+0.2X1 = 0.58 M
0.58+0.38
Area of Lug X 0.2 = 0.1 Sqm
2
Total Area of Metal 0.23+0.08+0.36+0.1 = 0.77 Sqm
Filter
200 mm Thk Sand
BED
Bottom Width = 0.955 M
Top Width 0.955+0.2X3 = 1.555 M
1.555+0.955
Area of Bed X 0.2 = 0.25 Sqm
2
R/S Slope= (sqrt(1X1+1X1) X 0.2) X0.3 = 0.08 Sqm
L/S Slope (sqrt(2X1+2X1) X 0.2) X1 = 0.45 Sqm
Lug
Top Width = 0.29 M
Bottom Width 0.29+0.2X1 = 0.49 M
0.49+0.29
Area of Lug X 0.2 = 0.08 Sqm
2
Total Area of Sand 0.25+0.08+0.45+0.08 = 0.86 Sqm
Filter

Length Area Quanitty


Slno Descrption of item Remarks
(M) (Sqm) (Cum)
1 Eath work Excavation 250 2.66 665
2 Rip Rap 250 0.96 240
3 Metal Filters 250 0.77 192.5
5 Sand Filters 250 0.86 215
Formation of Mallamadugu Reservoir
Saddle Portion
Detail Estimate D/S Rock- Toe Protection

300 mm Thick Rip Rap

1M

200 mm thick Metal Filter

200 mm thick Sand Filter

Height of Toe Protection = 1 M


Incliend Height of Toe protection Sqrt(2X2+1X1) x 1 m = 2.24 M
Thick ness of Rip Rap = 0.3 M
Thickness of Metal Filter = 0.2 M
Thickness of Sand Filter = 0.2 M
Area of Rip Rap = 2.24X0.3 = 0.67 Sqm
Area of Metal Filter = 2.24X0.2 = 0.45 Sqm
Area of Sand Filter = 2.24X0.2 = 0.45 Sqm

Length of Area in Quantity


Slno Descrption of item Remarks
Bund in M Sqm in Cum

1 Rip Rap 250 0.67 167.50


2 Metal Fiters 250 0.45 112.50
3 Sand Filters 250 0.45 112.50
Formation of Mallemadugu Reservoir
Bund-1 OT Sluices Detail Estimate
Elevation Length in M Width in M Depth in Quanity in
Slno Descrption of item Nos Remarks
From To Details Length Details Width M Cum
A EWE of Sluices
EWE of HR
1 U/S Wing Wall Minimum& Returns 1 X 2 111.500 108.150 7.69 1.9 3.350 97.89
2 U/S Wing Wall Maximum 1 X 2 111.500 108.150 2.86 (1.9+2.5)/2 2.2 3.350 42.16
3 U/S Apron 1 X 1 111.500 108.150 5.00 (9+6.1)/2 7.55 3.350 126.46
4 U/S Cut Off Trench 1 X 1 108.150 107.150 (0.55+0.3)/2 0.43 19.7 1.000 8.37
5 U/S Well portion 1 X 1 111.500 107.350 12.00 9.1 4.150 453.18
6 U/S Barral-Transaction Portion 1 X 1 111.500 107.550 8.00 (9.1+8)/2 8.55 3.950 270.18
7 Remaing Barral Portion-D/S Side 1 X 1 111.500 107.550 75.80 8 3.950 2395.28
8 D/S Apron 1 X 1 111.500 107.650 11.00 (9+5.4)/2 7.2 3.850 304.92
9 D/S Wing Wall Maximum 1 X 2 111.500 107.650 6.52 (3.8+2.3)/2 3.05 3.850 153.12
10 d/S Wing Wall Minimum& Returns 1 X 2 111.500 107.650 10.40 2.3 3.850 184.18
11 d/S Cut Off Trench 1 X 1 107.650 106.650 (0.55+0.3)/2 0.43 19.7 1.000 8.37
12 Cut off Collers 1 X 11 111.500 107.350 0.30 0.4 4.150 5.48
Total EWE of HR Quantity 4049.59 Cum
B Concrete
CC M15-40 MSA
1 U/S Wing Wall Minimum& Returns 1 X 2 108.150 108.650 7.69 1.90 0.500 14.61 Foundation
1 X 2 108.650 111.500 7.39 (1.6+0.5)/2 1.05 2.850 44.23
2 U/S Wing Wall Maximum 1 X 2 108.150 108.650 2.86 (2.5+1.9)/2 2.20 0.500 6.29 Foundation
(1.6+2.3+0.5+0 Height varies to
1 X 2 108.650 112.600 2.86 1.225 3.400 23.82
.5)/4 112.600 to 111.500
3 U/S Apron 1 X 1 108.150 108.650 5.00 (9+6.1)/2 7.55 0.500 18.88 Foundation
4 U/S Cut Off Trench 1 X 1 107.150 108.150 (0.55+0.3)/2 0.43 19.7 1.000 8.37 Foundation
5 U/S Well portion 1 X 1 107.350 107.850 12 9.1 0.500 54.60 Foundation
6 U/S Barral-Transaction Portion 1 X 1 107.550 107.850 8.00 (9.1+8)/2 8.55 0.30 20.52 Foundation
7 Remaing Barral Portion-D/S Side 1 X 1 107.550 107.850 75.80 8 0.30 181.92 Foundation
8 D/S Apron 1 X 1 107.650 108.150 11.00 (9+5.4)/2 7.2 0.50 39.60 Foundation
9 D/S Wing Wall Maximum 1 X 2 107.650 108.150 6.52 (3.8+2.3)/2 3.05 0.50 19.89 Foundation
(3.5+2+0.5+ Height varies to
1 X 2 108.150 114.600 6.52 1.625 6.45 136.68
0.5)/4 114.600 to 111.500
10 D/S Wing Wall Minimum& Returns 1 X 2 107.650 108.150 10.40 2.3 0.50 23.92 Foundation
1 X 2 108.150 111.500 10.40 (2+0.5)/2 1.25 3.35 87.10
11 D/S Cut Off Trench 1 X 1 107.650 106.650 (0.55+0.3)/2 0.43 19.7 1.000 8.37 Foundation
12 U/S head Wall 1 X 1 111.600 112.600 8.10 (0.5+0.8)/2 0.65 1.000 5.27
13 D/S head Wall 1 X 1 111.600 114.600 7.00 (0.5+2.5)/2 1.5 3.000 31.50
Total Concrete Quantity 725.57 Cum
Elevation Length in M Width in M Depth in Quanity in
Slno Descrption of item Nos Remarks
From To Details Length Details Width M Cum
RCC M20-20 MSA
1 U/S Well portion
Up to Slab Level
Bottom Raft 1 X 1 107.850 108.650 12.00 8.1 0.80 77.76
Side Walls 1 X 2 108.650 111.600 12.00 1 2.95 70.80
Middle Wall 1 X 1 108.650 111.600 12.00 1.5 2.95 53.10
Slab 1 X 2 110.800 111.600 12.00 2.3 0.80 44.16
From Slab top to FRL
U/S Wall and D/S Wall 1 X 2 111.600 128.000 (9.01+7.65)/2 8.33 0.5 16.40 136.61
Middle Wall 1 X 1 111.600 128.000 7.1 1.5 16.40 174.66
End Walls 1 X 2 111.600 128.000 3.41 1 16.40 111.85
Above FRL
U/S Wall and D/S Wall 1 X 2 128.000 131.000 (9.01+7.65)/2 8.33 0.5 3.00 24.99
Middle Wall 1 X 1 128.000 131.000 7.1 0.8 3.00 17.04
End Walls 1 X 2 128.000 131.000 3.41 0.65 3.00 13.30
2 U/S Barral-Transaction Portion
Bottom Raft 1 X 1 107.850 108.650 8.00 (8.1+7)/2 7.55 0.80 48.32
Side Walls 1 X 2 108.650 110.800 8.00 (1+0.8)/2 0.9 2.15 30.96
Middle Wall 1 X 1 108.650 110.800 8.00 (1.5+0.8)/2 1.15 2.15 19.78
Slab 1 X 1 110.800 111.600 8.00 (8.1+7)/2 7.55 0.80 48.32
3 Remaing Barral Portion-D/S Side
Bottom Raft 1 X 1 107.850 108.650 75.80 7 0.80 424.48
Side Walls 1 X 2 108.650 110.800 75.80 0.8 2.15 260.75
Middle Wall 1 X 1 108.650 110.800 75.80 0.8 2.15 130.38
Slab 1 X 1 110.800 111.600 75.80 7 0.80 424.48
4 Cut off Collers-Vertical 1 X 22 107.850 111.600 0.6 0.3 3.75 14.85
5 Cut off Collers-Horizontal above Slab 1 X 11 111.600 112.200 8.2 0.3 0.60 16.24
6 Twin Colunms for Foot Bridge 1 X 3 111.600 131.000 0.45 0.3 19.40 7.86
Tie Beams 1 X 15 3.1 0.3 0.30 4.19
Total Concrete Quantity 2154.88 Cum
CC M25-20 MSA
Wearing Coat
U/S Apron 1 X 1 108.650 108.800 5 (6.1+9)/2 7.55 0.15 5.66
Well and barral Portion 1 X 2 108.650 108.800 95.8 2.3 0.15 66.10
D/S Apron 1 X 1 108.150 108.300 5 (5.4+9)/2 7.2 0.15 5.40
Total Concrete Quantity 77.16 Cum
Grand Total 2957.61 Cum
Length of PVC Water Stooper for one Construction Joint 18.3 RMT
For 6 Construction joints 109.8 RMT
Formation of Mallemadugu Reservoir
Bund-1 OT Sluices Detail Estimate-Reinforcement Details
Unit Total
Dia spaceing Length of
S.no Descrption of item No's No of Bars Weight Weight Remarks
(MM) (MM) Bar (M)
(Kg's) (Kg's)
1 Barral Portion
Zone-1-48 M length
Main Bars-A A1A2A3 1 X 1 25 120 401 21.5 3.858 33261.75
Main Bars- BB1 1 X 2 25 180 268 7 3.858 14475.22
Vertical Bars-CC1 1 X 4 12 175 275 3.9 0.889 3813.81
Hunch Bars-HH1 1 X 8 12 175 275 2.19 0.889 4283.2
Extra Bars-H2H3 1 X 2 25 120 401 2.3 3.858 7116.47
Distribution Bars in all
Faces 1 X 1 12 175 293 48 0.889 12502.9
Zone-2-35.8 M length
Main Bars-A A1A2A3 1 X 1 25 180 200 21.5 3.858 16589.4
Main Bars- BB1 1 X 2 20 200 180 7 2.469 6221.88
Vertical Bars-CC1 1 X 4 12 150 240 3.9 0.889 3328.42
Hunch Bars-HH1 1 X 8 12 175 206 2.19 0.889 3208.51
Distribution Bars in all
Faces 1 X 1 12 175 293 35.8 0.889 9325.08
2 Well Portion-12 Meters
Main Bars-A A1A2A3 1 X 1 25 180 68 23.7 3.858 6217.55
Main Bars- BB1 1 X 2 25 200 61 8.1 3.858 3812.48
Vertical Bars-CC1 1 X 4 12 150 81 3.75 0.889 1080.14
Hunch Bars-HH1 1 X 8 12 175 70 2.19 0.889 1090.27
Distribution Bars in all
Faces 1 X 1 12 175 315 12 0.889 3360.42
Slab level to 128.000
Middle Wall Vertcals 1 X 1 12 300 48 16.4 0.889 699.82
Middle Wall Horizntal 1 X 2 12 300 56 7.1 0.889 706.93
End Wall Verticals 1 X 2 12 300 12 16.4 0.889 349.91
End Wall Horizntal 1 X 4 12 300 56 3.41 0.889 679.05
U/S & D/S Wall Verticals 1 X 2 12 300 31 16.4 0.889 903.94
U/S & D/S Wall Horizntal 1 X 4 12 300 56 9.01 0.889 1794.22
128.000 to 131.000 Level
Middle Wall Vertcals 1 X 1 12 300 48 3 0.889 128.02
Middle Wall Horizntal 1 X 2 12 300 11 7.1 0.889 138.86
End Wall Verticals 1 X 2 12 300 12 3 0.889 64.01
End Wall Horizntal 1 X 4 12 300 11 3.41 0.889 133.39
U/S & D/S Wall Verticals 1 X 2 12 300 31 3 0.889 165.35
U/S & D/S Wall Horizntal 1 X 4 12 300 11 9.01 0.889 352.44
3 Cut -off Collers
Vertical- Main Bars 1 X 22 12 6 4.35 0.889 510.46
Vertical- Dist Bars 1 X 22 8 300 15 1.80 0.395 234.63
Horizontal-Main Bars 1 X 11 12 6 7.00 0.889 410.72
Horizontal-Dist Bars 1 X 11 8 300 23 1.80 0.395 179.88
4 Foot Bridge Coloumns
Main Reinforcement 1 X 3 12 6 20.5 0.889 328.04
Distribution 1 X 3 10 250 82 1.5 0.617 227.67
Tie Beams
Main Reinforcement 1 X 15 12 6 3.1 0.889 248.03
Distribution 1 X 15 10 250 12 1.5 0.617 166.59
Total Quantity in MT 138.109 MT
ABSTRACT OF ESTIMATE
CONSTRUCTION OF SLUICES @ 0.475 KM AT BUND-1 OF MALLEMADUGU RESERVOIR
As per IBM As per deviations
Slno Descrption of item Unit Remarks
Quantity Rate Amount Quantity Rate Amount

1 EWE for Foundations

a)all Soils with lead of 250 meters Cum 480 36.50 17,520

b) HDR with lead of 500 meters Cum 840 90.70 76,188

c) Earth work excavation and depositing as New item ( due to


directed with machinery in hard rock and change in soil
boulders upto 3 Cum in size requiring Control clasification-open rock
blasting excluding stacking for cut off foundation) Required
excavation and excavation of leading channel Control Balsting
and conveyance with a lead of 500m Cum 4,049.59 402.75 1,630,972
2 CC M.15 for Foundations Cum 315 2,204.00 694,260 396.97 2,204.00 874,922

CC M-15 for Wings returns apron,head walls


3 Cum 645 3,315.00 2,138,175 328.60 3,315.00 1,089,309
4 CC M-20 for Barral slab walls and Rft Cum 92 5,190.00 477,480 2,154.88 5,190.00 11,183,827
5 CC M15-for Wearing coat Cum 18 2,584.00 46,512
CC M25-for Wearing Coat Cum 77.16 3,523.72 271,890
6 S & F HYSD Steel Reinforcement MT 25 33,378.00 834,450 138.11 33,378.00 4,609,818
7 PVC Water Stopper Rmt 24 710.00 17,040 109.80 710.00 77,958
Provision for door,window,hand railing inner &
outer sides gauge etc arrangments in head
8 L.S 150,000 150,000.00
room
provision for gate, hoist platform, screw
9 rod,gear box etc , arrangments L.S 548,375 548,375.00
Total 5,000,000 20,437,071

Slno Descrption of item As per IBM As per deviations Excess Remarks


1 Bund-1 5,000,000 20,437,071 15,437,071
2 Bund-2 4,000,000 11,543,127 7,543,127
3 Bund-3 - - -
Total 9,000,000 31,980,198 22,980,198
Formation of Mallemadugu Reservoir
Bund-1 OT Sluices Detail Estimate
Elevation Length in M Width in M Depth in Quanity in
Slno Descrption of item Nos Remarks
From To Details Length Details Width M Cum
A EWE of Sluices
EWE of Soils
1 U/S Wing Wall 1 X 2 113.100 109.150 8.82 2.20 3.950 153.29
2 U/S Apron 1 X 1 113.100 109.150 5.00 (6+2.3)/2 4.15 3.950 81.96
3 Well Portion 1 X 1 113.100 108.350 10.95 6.20 4.750 322.48
4 Barral Portion 1 X 1 113.100 108.550 86.60 4.70 4.550 1851.94
5 D/S Apron 1 X 1 113.100 108.850 8.00 (6+2.3)/2 4.15 4.250 141.10
6 D/S Wing Wall Maximum 1 X 2 113.100 108.850 3.10 (2.4+1.4)/2 1.90 4.250 50.07
7 d/S Wing Wall Minimum& Returns 1 X 2 113.100 108.850 8.63 1.40 4.250 102.70
8 Cut off Collers 1 X 13 113.100 108.550 0.3 0.6 4.550 10.65
9 U/S Cut-off Trench 1 X 1 113.100 108.000 13.10 (0.66+0.59)/2 0.625 5.100 41.76
10 D/S Cut-off Trench 1 X 1 113.100 108.000 13.10 (0.75+0.51)/2 0.63 5.100 42.09
Total 2798.04 Cum
EWE of HDR
9 U/S Cut-off Trench 1 X 1 108.000 107.650 13.10 (0.3+0.59)/2 0.445 0.350 2.04
10 D/S Cut-off Trench 1 X 1 108.000 107.350 13.10 (0.3+0.51)/2 0.405 0.650 3.45
Total 5.49 Cum
A Concrete
CC M15-40 MSA
1 U/S Wing Wall 1 X 2 109.150 109.650 8.82 2.20 0.500 19.40 Foundation
1 X 2 109.650 113.100 8.82 (1.9+0.5)/2 1.20 3.450 73.03
2 U/S Apron 1 X 1 109.150 109.650 5.00 (6+2.5)/2 4.25 0.500 10.63 Foundation
3 U/S Cut-off Trench 1 X 1 107.650 109.150 13.1 (0.66+0.3)/2 0.48 1.500 9.43 Foundation
4 U/S Well Portion 1 X 1 108.550 108.850 3.75 5.8 0.300 6.52 Foundation
1 X 1 108.350 108.650 7.2 6.2 0.300 13.39 Foundation
5 Barral Portion 1 X 1 108.550 108.850 86.6 4.7 0.300 122.11 Foundation
6 D/S Apron 1 X 1 108.850 109.350 8.00 (6+2.5)/2 4.25 0.500 17.00 Foundation
7 D/S Wing Wall Maximum 1 X 2 108.850 109.350 3.1 (2.4+1.4)/2 1.9 0.500 5.89 Foundation
1 X 2 109.350 113.100 3.1 (1.56+4.88)/2 3.22 19.96
8 D/S Wing Wall Minimum& Returns 1 X 2 108.850 109.350 8.63 1.4 0.500 12.08 Foundation
1 X 2 109.350 111.300 8.63 (0.5+1.1)/2 0.8 1.950 26.93
9 D/S Cut-off Trench 1 X 1 107.350 108.850 13.1 (0.75+0.3)/2 0.525 1.500 10.32 Foundation
10 U/S Head Wall 1 X 1 112.100 113.100 5.2 (0.5+0.8)/2 0.65 1.000 3.38
11 D/S Head Wall 1 X 1 112.100 113.100 4.1 (0.5+0.8)/2 0.65 1 2.67
Total 352.74 Cum
Elevation Length in M Width in M Depth in Quanity in
Slno Descrption of item Nos Remarks
From To Details Length Details Width M Cum
RCC M20-20 MSA
1 U/S Well portion-Slab Level
Raft 1 X 1 108.850 109.650 10.75 5.2 0.8 44.72
Side Walls 1 X 2 109.650 112.100 10.75 (0.5+0.8)/2 1.35 2.450 71.11
Slab 1 X 1 108.850 109.650 10.75 2.5 0.8 21.50
From Slab to FRL
U/S Wall and D/S Wall 1 X 2 112.100 128.000 2.66 0.5 15.90 42.29
End Walls 1 X 2 112.100 128.000 4.18 1.33 15.90 176.79
Above FRL
U/S Wall and D/S Wall 1 X 2 128.000 131.000 3.83 0.5 3.00 11.49
End Walls 1 X 2 128.000 131.000 4.18 0.85 3.00 21.32
2 Barral-Transaction Portion
Bottom Raft 1 X 1 108.850 109.650 86.60 4.1 0.80 284.05
Side Walls 1 X 2 109.650 111.300 86.60 0.8 1.65 228.62
Slab 1 X 1 111.300 112.100 86.60 4.1 0.80 284.05
4 Cut off Collers-Vertical 1 X 26 108.850 112.100 0.6 0.3 3.25 15.21
5 Cut off Collers-Horizontal above Slab 1 X 13 112.100 112.700 4.1 0.3 0.60 9.59
6 Twin Colunms for Foot Bridge 1 X 3 112.100 131.000 0.45 0.3 18.90 7.65
Tie Beams 1 X 15 3.3 0.3 0.30 4.46
Total 1222.85 Cum
CC M25-20 MSA
Wearing Coat
U/S Apron 1 X 1 109.650 109.800 5 (6+2.5)/2 4.25 0.15 3.19
Well and barral Portion 1 X 1 109.650 109.800 86.6 2.5 0.15 32.48
D/S Apron 1 X 1 109.350 109.500 8 (6+2.5)/2 4.25 0.15 5.10
Total 40.77 Cum
Grand Total 1616.36 Cum
Length of PVC Water Stooper for one Construction Joint 11.50 RMT
For 6 Construction joints 69.0 RMT
Formation of Mallemadugu Reservoir
Bund-1 OT Sluices Detail Estimate-Reinforcement Details
Unit Total
Dia spaceing No of Length of
S.no Descrption of item No's Weight Weight Remarks
(MM) (MM) Bars Bar (M)
(Kg's) (Kg's)
1 Barral Portion
Zone-1-56 M length
Main Bars-A A1A2A3 1 X 1 25 120 468 14.7 3.858 26541.5
Main Bars- BB1 1 X 2 25 110 510 4.1 3.858 16134.16
Vertical Bars-CC1 1 X 2 25 200 281 3.25 3.858 7046.64
Hunch Bars-HH1 1 X 4 12 200 281 2.39 0.889 2388.17

Distribution Bars in all Faces 1 X 1 12 170 174 56 0.889 8662.42


Zone-2-30.6 M length
Main Bars-A A1A2A3 1 X 1 20 145 212 14.7 2.469 7694.39
Main Bars- BB1 1 X 2 20 100 307 4.1 2.469 6215.46
Vertical Bars-CC1 1 X 2 20 250 123 3.25 2.469 1973.97
Hunch Bars-HH1 1 X 4 12 200 154 2.39 0.889 1308.82

Distribution Bars in all Faces 1 X 1 12 170 174 30.6 0.889 4733.39


2 Well Portion-10.750 Meters
Main Bars-A A1A2A3 1 X 1 25 145 75 16.82 3.858 4866.87
Main Bars- BB1 1 X 2 25 100 109 5.16 3.858 4339.79
Vertical Bars-CC1 1 X 4 12 250 44 3.25 0.889 508.51
Hunch Bars-HH1 1 X 8 12 200 55 2.39 0.889 934.87

Distribution Bars in all Faces 1 X 1 12 170 199 10.75 0.889 1901.79


Slab level to 128.000
End Wall Verticals 1 X 2 12 300 15 15.82 0.889 421.92
End Wall Horizntal 1 X 4 12 300 54 4.18 0.889 802.66
U/S & D/S Wall Verticals 1 X 2 12 300 10 15.82 0.889 281.28
U/S & D/S Wall Horizntal 1 X 4 12 300 54 2.66 0.889 510.78
128.000 to 131.000 Level
End Wall Verticals 1 X 2 12 300 15 3 0.889 80.01
End Wall Horizntal 1 X 4 12 300 11 4.18 0.889 163.5
U/S & D/S Wall Verticals 1 X 2 12 300 14 3 0.889 74.68
U/S & D/S Wall Horizntal 1 X 4 12 300 11 3.83 0.889 149.81
3 Cut -off Collers
Vertical- Main Bars 1 X 26 12 6 3.85 0.889 533.93
Vertical- Dist Bars 1 X 26 8 300 13 1.80 0.395 240.32
Horizontal-Main Bars 1 X 13 12 6 4.10 0.889 284.3
Horizontal-Dist Bars 1 X 13 8 300 14 1.80 0.395 129.4
4 Foot Bridge Coloumns
Main Reinforcement 1 X 3 12 6 18.9 0.889 302.44
Distribution 1 X 3 10 250 76 1.5 0.617 211.01
Tie Beams
Main Reinforcement 1 X 15 12 6 3.3 0.889 264.03
Distribution 1 X 15 10 250 13 1.2 0.617 144.38
Total Quantity in MT 99.85000 MT
ABSTRACT OF ESTIMATE
CONSTRUCTION OF SLUICES @ 1.200 KM AT BUND-2 OF MALLEMADUGU RESERVOIR
As per IBM As per deviations
Slno Descrption of item Unit Remarks
Quantity Rate Amount Quantity Rate Amount

1 EWE forr Foundations

a)all Soils with lead of 250 meters Cum 250 36.50 9,125 2798.04 36.50 102,128

b) HDR with lead of 500 meters Cum 580 90.70 52,606 5.49 90.70 498

2 CC M.15 for Foundations Cum 224 2,204.00 493,696 226.77 2,204.00 499,801

3 CC M-15 for wIngs returns apron,head walls Cum 484 3,315.00 1,604,460 125.97 3,315.00 417,604

4 CC M-20 for Barral slab walls and Rft Cum 65 5,190.00 337,350 1222.85 5,190.00 6,346,592

5 CC M-15 for Wearing Coat Cum 13 2,584.00 33,592 -

CC M-25 for Wearing Coat 40.77 3,523.72 143,662

6 S & F HYSD Steel Reinforcement MT 18 33,378.00 801,072 99.85 33,378.00 3,332,793

7 PVC Water Stopper RMT 24 710.00 17,040 69 710.00 48,990

8 Provision for door,window,hand railing inner &


outer sides gauge etc arrangments in head room LS 150,000 150,000

9 provision for gate, hoist platform, screw


rod,gear box etc , arrangments LS 501,059 501,059
Total 4,000,000 11,543,127
Formation of Mallemadugu Reservoir
Bund-3 OT Sluices Detail Estimate
Elevation Length in M Width in M Depth in Quanity in
Slno Descrption of item Nos Remarks
From To Details Length Details Width M Cum
A EWE of Sluices
EWE of Soils
1 U/S Wing Wall Minimum& Minimum 1 X 2 112.300 109.100 11.55 2.3 3.200 170.02
2 U/S Apron 1 X 1 112.300 109.100 5.00 4.7 3.200 75.20
3 U/S Well portion 1 X 1 112.300 109.100 12.75 8 3.200 326.40
4 U/S Barral-Transaction Portion 1 X 1 112.300 109.100 8.00 (8+5.6)/2 6.80 3.200 174.08
5 Remaing Barral Portion-D/S Side 1 X 1 112.300 109.100 76.00 5.60 3.200 1361.92
6 D/S Apron 1 X 1 112.300 109.100 10.00 (3.8+7)/2 5.40 3.200 172.80
7 D/S Wing Wall Maximum 1 X 2 112.300 109.100 3.77 (3.6+2.5)/2 3.05 3.200 73.59
8 d/S Wing Wall Minimum& Returns 1 X 2 112.300 109.100 12.59 2.50 3.200 201.44
9 Cut off Collers 1 X 11 112.300 109.100 0.30 0.6 3.200 6.34
Total 2561.79 Cum
EWE of HDR
1 U/S Wing Wall Minimum& Minimum 1 X 2 109.100 108.350 11.55 2.3 0.750 39.85
2 U/S Apron 1 X 1 109.100 108.350 5.00 4.7 0.750 17.63
3 U/S Well portion 1 X 1 109.100 107.750 12.75 8 1.350 137.70
4 U/S Barral-Transaction Portion 1 X 1 109.100 107.950 8.00 (8+5.6)/2 6.80 1.150 62.56
5 Remaing Barral Portion-D/S Side 1 X 1 109.100 107.950 76.00 5.60 1.150 489.44
6 D/S Apron 1 X 1 109.100 107.850 10.00 (3.8+7)/2 5.40 1.250 67.50
7 D/S Wing Wall Maximum 1 X 1 109.100 107.850 3.77 (3.6+2.5)/2 3.05 1.250 14.37
8 d/S Wing Wall Minimum& Returns 1 X 1 109.100 107.850 12.59 2.50 1.250 39.34
9 Cut off Collers 1 X 11 109.100 107.950 0.30 0.6 1.150 2.28
10 U/S Cut Off Trench 1 X 1 108.350 107.350 17.20 (0.3+0.55)/2 0.425 1.000 7.31
11 D/S Cut Off Trench 1 X 1 107.850 107.000 19.50 (0.55+0.47)/2 0.51 0.850 8.45
Total 886.43 Cum
EWE of F&F
1 D/S Cut Off Trench 1 X 1 107.000 106.850 19.50 (0.3+0.47)/2 0.385 0.150 1.13
Total 1.13 Cum
B Concrete
CC M15-40 MSA
1 U/S Wing Wall Minimum& Minimum 1 X 2 108.350 108.850 11.55 2.3 0.500 26.57 Foundation
1 X 2 108.850 112.300 11.55 (0.5+2)/2 1.25 3.450 99.62
U/S Apron 1 X 1 108.350 108.850 5.00 4.7 0.500 11.75 Foundation
U/S Cut-off Trench 1 X 1 107.350 108.350 17.20 (0.3+0.55)/2 0.425 1.000 7.31 Foundation
U/S well Portion 1 X 1 107.950 108.250 3.75 8 0.300 9.00 Foundation
1 X 1 107.750 108.250 9.00 8 0.500 36.00 Foundation
U/S Barral-Transaction Portion 1 X 1 107.750 108.250 8.00 (8+5.6)/2 6.80 0.500 27.20 Foundation
Remaing Barral Portion-D/S Side 1 X 1 107.750 108.250 76.00 5.6 0.500 212.80 Foundation
Elevation Length in M Width in M Depth in Quanity in
Slno Descrption of item Nos Remarks
From To Details Length Details Width M Cum
D/S Apron 1 X 1 107.850 108.350 10.00 (7+3.8)/2 5.4 0.500 27.00 Foundation
D/S Wing Wall Maximum 1 X 2 107.850 108.350 3.77 3.6 0.500 13.57 Foundation
((3.3+0.5)/2+(
1 X 2 108.350 114.100 3.77 3.15 4.850 115.19
2.2+0.3)/2)/2
D/S Wing Wall Minimum& Returns 1 X 2 107.850 108.350 12.59 2.5 0.500 31.48 Foundation
1 X 2 108.350 112.300 12.59 (2.2+0.5)/2 1.35 3.950 134.27
D/S Cut Off Trench 1 X 1 106.850 107.850 19.50 (0.3+0.55)/2 0.425 1.000 16.58 Foundation
U/S head Wall 1 X 1 111.100 112.300 7.00 (0.5+0.9)/2 0.7 1.200 5.88
D/S head Wall 1 X 1 111.100 114.100 5.00 (0.5+2.5)/2 1.5 3.000 22.50
Total 796.72 Cum
RCC M20-20 MSA
1 U/S Well portion
Up to Slab Level
Bottom Raft 1 X 1 108.250 108.850 12.75 7.00 0.60 53.55
Side Walls 1 X 2 108.850 111.100 12.75 1.15 2.25 65.98
Middle Wall 1 X 1 108.850 111.100 12.75 1.50 2.25 43.03
Slab 1 X 2 110.500 111.100 12.75 1.60 0.60 24.48
From Slab top to FRL
U/S Wall and D/S Wall 1 X 2 111.100 128.000 5.40 0.50 16.90 91.26
Middle Wall 1 X 1 111.100 128.000 6.00 1.50 16.90 152.10
End Walls 1 X 2 111.100 128.000 3.40 1.10 16.90 126.41
Above FRL
U/S Wall and D/S Wall 1 X 2 128.000 131.000 5.40 0.5 3.00 16.20
Middle Wall 1 X 1 128.000 131.000 6 0.8 3.00 14.40
End Walls 1 X 2 128.000 131.000 3.40 0.8 3.00 16.32
2 U/S Barral-Transaction Portion
Bottom Raft 1 X 1 108.250 108.850 8.00 (6.9+5)/2 5.95 0.60 28.56
Side Walls 1 X 2 108.850 110.500 8.00 (1.1+0.6)/2 0.85 1.65 22.44
Middle Wall 1 X 1 108.850 110.500 8.00 (1.5+0.6)/2 1.05 1.65 13.86
Slab 1 X 1 110.500 111.100 8.00 (6.9+5)/2 5.95 0.60 28.56
3 Remaing Barral Portion-D/S Side
Bottom Raft 1 X 1 108.250 108.850 76.00 5 0.60 228.00
Side Walls 1 X 2 108.850 110.500 76.00 0.6 1.65 150.48
Middle Wall 1 X 1 108.850 110.500 76.00 1.5 1.65 188.10
Slab 1 X 1 110.500 111.100 76.00 5 0.60 228.00
4 Cut off Collers-Vertical 1 X 22 108.250 111.700 0.6 0.3 3.45 13.66
5 Cut off Collers-Horizontal above Slab 1 X 11 111.100 111.700 5 0.3 0.60 9.90
6 Twin Colunms for Foot Bridge 1 X 3 111.100 131.000 0.45 0.3 19.90 8.06
Tie Beams 1 X 15 2.2 0.3 0.30 2.97
Total 1526.32 Cum
Elevation Length in M Width in M Depth in Quanity in
Slno Descrption of item Nos Remarks
From To Details Length Details Width M Cum
CC M25-20 MSA
Wearing Coat
U/S Apron 1 X 1 108.850 109.000 5 (4.7+4.7)/2 4.7 0.15 3.53
Well and barral Portion 1 X 2 108.850 109.000 96.75 2.3 0.15 66.76
D/S Apron 1 X 1 108.350 108.500 10 (7+3.8)/2 5.4 0.15 8.10
Total 78.39 Cum
Grand Total 2401.43 Cum
Length of PVC Water Stooper for one Construction Joint 13.3 RMT
For 6 Construction joints 79.8 RMT
Formation of Mallemadugu Reservoir
Bund-3 OT Sluices Detail Estimate-Reinforcement Details
Unit Total
Dia spaceing Length of
S.no Descrption of item No's No of Bars Weight Weight Remarks
(MM) (MM) Bar (M)
(Kg's) (Kg's)
1 Barral Portion
Zone-1-48 M length
Main Bars-A A1A2A3 1 X 1 20 140 344 15.7 2.469 13334.58
Main Bars- BB1 1 X 2 20 110 437 5.0 2.469 10789.53
Vertical Bars-CC1 1 X 4 12 150 321 2.85 0.889 3253.21
Hunch Bars-HH1 1 X 8 10 150 321 1.84 0.617 2915.4
Extra Bars-H2H3 1 X 2 20 140 344 2 2.469 3397.34

Distribution Bars in all Faces 1 X 1 10 150 248 48 0.617 7344.77


Zone-2-36.8 M length
Main Bars-A A1A2A3 1 X 1 20 150 246 15.7 2.469 9535.77
Main Bars- BB1 1 X 2 20 180 205 5 2.469 5061.45
Vertical Bars-CC1 1 X 4 12 150 246 2.85 0.889 2493.11
Hunch Bars-HH1 1 X 8 10 150 246 1.84 0.617 2234.23

Distribution Bars in all Faces 1 X 1 10 150 248 36.8 0.617 5630.99


2 Well Portion-12.75 Meters
Main Bars-A A1A2A3 1 X 1 20 150 86 19.7 2.469 4182.98
Main Bars- BB1 1 X 2 20 180 72 7 2.469 2488.75
Vertical Bars-CC1 1 X 4 12 150 86 2.85 0.889 871.58
Hunch Bars-HH1 1 X 8 10 150 86 2.55 0.617 1082.46

Distribution Bars in all Faces 1 X 1 10 150 302 12 0.617 2236.01


Slab level to 128.000
Middle Wall Vertcals 1 X 1 12 300 41 16.9 0.889 615.99
Middle Wall Horizntal 1 X 2 12 300 57 6 0.889 608.08
End Wall Verticals 1 X 2 12 300 12 16.4 0.889 349.91
End Wall Horizntal 1 X 4 12 300 57 3.4 0.889 689.15
U/S & D/S Wall Verticals 1 X 2 12 300 19 16.9 0.889 570.92
U/S & D/S Wall Horizntal 1 X 4 12 300 57 9.01 0.889 1826.25
3 128.000 to 131.000 Level
Middle Wall Vertcals 1 X 1 12 300 41 3 0.889 109.35
Middle Wall Horizntal 1 X 2 12 300 11 7.1 0.889 138.86
End Wall Verticals 1 X 2 12 300 12 3 0.889 64.01
End Wall Horizntal 1 X 4 12 300 11 3.41 0.889 133.39
U/S & D/S Wall Verticals 1 X 2 12 300 19 3 0.889 101.35
U/S & D/S Wall Horizntal 1 X 4 12 300 11 9.01 0.889 352.44
3 Cut -off Collers
Vertical- Main Bars 1 X 22 12 6 3.45 0.889 404.85
Vertical- Dist Bars 1 X 22 8 300 12 1.80 0.395 187.7
Horizontal-Main Bars 1 X 11 12 6 5.00 0.889 293.37
Horizontal-Dist Bars 1 X 11 8 300 17 1.80 0.395 132.96
4 Foot Bridge Coloumns
Main Reinforcement 1 X 3 12 6 19.9 0.889 318.44
Distribution 1 X 3 10 250 80 1.5 0.617 222.12
Tie Beams
Main Reinforcement 1 X 15 12 6 2.2 0.889 176.02
Distribution 1 X 15 10 250 9 1.5 0.617 124.94
Total Quantity in MT 84.272 MT
ABSTRACT OF ESTIMATE
CONSTRUCTION OF SLUICES AT BUND-3 OF MALLEMADUGU RESERVOIR
As per IBM As per deviations
Slno Descrption of item Unit Remarks
Quantity Rate Amount Quantity Rate Amount

1 EWE forr Foundations

a)all Soils with lead of 250 meters Cum 250 36.50 9,125 2561.79 36.50 93,505

b) HDR with lead of 500 meters Cum 580 90.70 52,606 886.43 90.70 80,399

b)F&F with lead of 500 meters 1.13

2 CC M.15 for Foundations Cum 224 2,204.00 493,696 419.26 2,204.00 924,049

3 CC M-15 for wIngs returns apron,head walls Cum 484 3,315.00 1,604,460 377.46 3,315.00 1,251,280

4 CC M-20 for Barral slab walls and Rft Cum 65 5,190.00 337,350 1526.32 5,190.00 7,921,601

5 CC M-15 for Wearing Coat Cum 13 2,584.00 33,592 -

CC M-25 for Wearing Coat 78.39 3,523.72 276,224

6 S & F HYSD Steel Reinforcement MT 18 33,378.00 801,072 84.27 33,378.00 2,812,839

7 PVC Water Stopper RMT 24 710.00 17,040 79.8 710.00 56,658


Provision for door,window,hand railing inner &
8 outer sides gauge etc arrangments in head
room LS 150,000 150,000
provision for gate, hoist platform, screw
9
rod,gear box etc , arrangments LS 501,059 501,059
Total 4,000,000 14,067,615
Formation Of Mallamadugu Reservoir
Details of Surplus Channel-0.000 KM of D/S of Spillway( From Apron End)
EWE Areas Calcuation Sheet
Bottom Area of
Distance in Bottom Level Bottom Level Bottom Depth of Depth of Area of F&F Depth of Area of HR
Slno Ground Level Level of Soils Remarks
Meters of Channel of Soils Level of HR Soils (M) F&F (M) (Sqm) HR (M) (Sqm)
F&F (Sqm)
1 36 111.105 102.783 111.105 105.870 102.783 0.000 5.235 3.087
2 31 111.340 102.783 111.340 105.870 102.783 0.000 0.00 5.470 26.76 3.087 15.44
3 26 111.640 102.783 111.640 105.870 102.783 0.000 0.00 5.770 28.10 3.087 15.44
4 21 110.590 102.783 110.590 105.870 102.783 0.000 0.00 4.720 26.23 3.087 15.44 L/S Portion
5 16 110.570 102.783 110.570 105.870 102.783 0.000 0.00 4.700 23.55 3.087 15.44
6 11 110.810 102.783 110.810 105.870 102.783 0.000 0.00 4.940 24.10 3.087 15.44
7 6 109.800 102.783 109.800 105.870 102.783 0.000 0.00 3.930 22.18 3.087 15.44
8 0 109.880 102.783 109.880 105.870 102.783 0.000 0.00 4.010 23.82 3.087 18.52 C/L of Channal
9 6 110.160 102.783 110.160 105.870 102.783 0.000 0.00 4.290 24.90 3.087 18.52
10 11 109.920 102.783 109.920 105.870 102.783 0.000 0.00 4.050 20.85 3.087 15.44
11 16 109.750 102.783 109.750 105.870 102.783 0.000 0.00 3.880 19.83 3.087 15.44
12 21 110.160 102.783 110.160 105.870 102.783 0.000 0.00 4.290 20.43 3.087 15.44 R/S Portion
13 26 110.120 102.783 110.120 105.870 102.783 0.000 0.00 4.250 21.35 3.087 15.44
14 31 110.260 102.783 110.260 105.870 102.783 0.000 0.00 4.390 21.60 3.087 15.44
15 36 109.920 102.783 109.920 105.870 102.783 0.000 0.00 4.050 21.10 3.087 15.44
Total 0.00 324.78 222.26
Formation Of Mallamadugu Reservoir
Details of Surplus Channel-0.025 KM of D/S of Spillway
EWE Areas Calcuation Sheet
Soils F&F HR
Bottom Bottom Bottom Bottom
Distance Ground Area of Area of
Slno Level of Level of Level of Level of Depth of Depth of Depth of Area of Remarks
in Meters Level Soils F&F
Channel Soils F&F HR Soils (M) F&F (M) HR (M) HR (Sqm)
(Sqm) (Sqm)
1 109.70 112.250 112.250 111.400 105.000 0.000 0.000 0.000
2 100 112.465 102.765 110.975 105.000 102.765 1.490 7.23 5.975 28.98 2.235 10.84
3 95 112.460 102.765 109.500 105.000 102.765 2.960 11.13 4.500 26.19 2.235 11.18
4 90 112.460 102.765 109.500 105.000 102.765 2.960 14.80 4.500 22.50 2.235 11.18
5 85 112.360 102.765 109.000 105.000 102.765 3.360 15.80 4.000 21.25 2.235 11.18
6 80 112.515 102.765 108.500 105.000 102.765 4.015 18.44 3.500 18.75 2.235 11.18
7 75 112.500 102.765 107.600 105.000 102.765 4.900 22.29 2.600 15.25 2.235 11.18
8 70 109.505 102.765 107.505 105.000 102.765 2.000 17.25 2.505 12.76 2.235 11.18
9 65 110.220 102.765 107.500 105.000 102.765 2.720 11.80 2.500 12.51 2.235 11.18
10 60 110.930 102.765 107.705 105.000 102.765 3.225 14.86 2.705 13.01 2.235 11.18
11 55 110.785 102.765 107.730 105.000 102.765 3.055 15.70 2.730 13.59 2.235 11.18
12 50 110.930 102.765 107.780 105.000 102.765 3.150 15.51 2.780 13.78 2.235 11.18
13 45 111.005 102.765 107.805 105.000 102.765 3.200 15.88 2.805 13.96 2.235 11.18
14 40 110.930 102.765 107.820 105.000 102.765 3.110 15.78 2.820 14.06 2.235 11.18
15 36 112.060 102.765 107.835 105.000 102.765 4.225 14.67 2.835 11.31 2.235 8.94
16 31 111.350 102.765 108.300 105.000 102.765 3.050 18.19 3.300 15.34 2.235 11.18
17 26 111.390 102.765 108.500 105.000 102.765 2.890 14.85 3.500 17.00 2.235 11.18
18 21 111.040 102.765 108.600 105.000 102.765 2.440 13.33 3.600 17.75 2.235 11.18
19 16 109.580 102.765 108.580 105.000 102.765 1.000 8.60 3.580 17.95 2.235 11.18
20 11 108.640 102.765 107.640 105.000 102.765 1.000 5.00 2.640 15.55 2.235 11.18
21 6 106.200 102.765 106.200 105.000 102.765 0.000 2.50 1.200 9.60 2.235 11.18
22 0 107.510 102.765 107.510 105.000 102.765 0.000 0.00 2.510 11.13 2.235 13.41
23 6 108.480 102.765 108.480 105.000 102.765 0.000 0.00 3.480 17.97 2.235 13.41
24 11 109.230 102.765 109.230 105.000 102.765 0.000 0.00 4.230 19.28 2.235 11.18
25 16 109.550 102.765 109.550 105.000 102.765 0.000 0.00 4.550 21.95 2.235 11.18
26 21 108.940 102.765 108.940 105.000 102.765 0.000 0.00 3.940 21.23 2.235 11.18
27 26 109.720 102.765 109.720 105.000 102.765 0.000 0.00 4.720 21.65 2.235 11.18
28 31 109.630 102.765 109.630 105.000 102.765 0.000 0.00 4.630 23.38 2.235 11.18
29 36 107.700 102.765 107.700 105.000 102.765 0.000 0.00 2.700 18.33 2.235 11.18
30 40 108.115 102.765 108.115 105.000 102.765 0.000 0.00 3.115 11.63 2.235 8.94
31 45 111.125 102.765 108.325 105.000 102.765 2.800 7.00 3.325 16.10 2.235 11.18
32 50 111.505 102.765 108.675 105.000 102.765 2.830 14.08 3.675 17.50 2.235 11.18
33 55 110.685 102.765 108.685 105.000 102.765 2.000 12.08 3.685 18.40 2.235 11.18
34 60 107.750 102.765 107.750 105.000 102.765 0.000 5.00 2.750 16.09 2.235 11.18
35 65 107.235 102.765 107.235 105.000 102.765 0.000 0.00 2.235 12.46 2.235 11.18
36 70 107.120 102.765 107.120 105.000 102.765 0.000 0.00 2.120 10.89 2.235 11.18
37 75 107.365 102.765 107.365 105.000 102.765 0.000 0.00 2.365 11.21 2.235 11.18
38 80 107.775 102.765 107.775 105.000 102.765 0.000 0.00 2.775 12.85 2.235 11.18
39 85 107.645 102.765 107.645 105.000 102.765 0.000 0.00 2.645 13.55 2.235 11.18
40 90 107.650 102.765 107.650 105.000 102.765 0.000 0.00 2.650 13.24 2.235 11.18
41 95 107.815 102.765 107.815 105.000 102.765 0.000 0.00 2.815 13.66 2.235 11.18
42 100 107.340 102.765 107.340 105.000 102.765 0.000 0.00 2.340 12.89 2.235 11.18
43 104.58 107.400 107.400 107.400 105.500 107.400 0.000 0.00 0.000 5.36 0.000 5.12
Total 311.73 Sqm 671.81 Sqm 462.96 Sqm
Formation Of Mallamadugu Reservoir
Details of Surplus Channel-0.050 KM of D/S of Spillway
EWE Areas Calcuation Sheet
Soils F&F HR
Bottom Bottom Bottom Bottom
Distance Ground Area of Area of
Slno Level of Level of Level of Level of Depth of Depth of Depth of Area of Remarks
in Meters Level Soils F&F
Channel Soils F&F HR Soils (M) F&F (M) HR (M) HR (Sqm)
(Sqm) (Sqm)
1 109.21 111.845 111.845 111.000 104.945 0.000 0.000 0.000
2 100 111.960 102.748 109.960 104.945 102.748 2.000 9.21 5.015 23.09 2.197 10.12
3 95 112.100 102.748 109.100 104.945 102.748 3.000 12.50 4.155 22.93 2.197 10.98
4 90 111.985 102.748 108.985 104.945 102.748 3.000 15.00 4.040 20.49 2.197 10.98
5 85 111.990 102.748 108.990 104.945 102.748 3.000 15.00 4.045 20.21 2.197 10.98
6 80 111.380 102.748 108.380 104.945 102.748 3.000 15.00 3.435 18.70 2.197 10.98
7 75 111.200 102.748 108.200 104.945 102.748 3.000 15.00 3.255 16.73 2.197 10.98
8 70 109.445 102.748 106.445 104.945 102.748 3.000 15.00 1.500 11.89 2.197 10.98
9 65 109.035 102.748 106.100 104.945 102.748 2.935 14.84 1.155 6.64 2.197 10.98
10 60 109.325 102.748 106.100 104.945 102.748 3.225 15.40 1.155 5.78 2.197 10.98
11 55 109.900 102.748 106.115 104.945 102.748 3.785 17.53 1.170 5.81 2.197 10.98
12 50 111.715 102.748 106.100 104.945 102.748 5.615 23.50 1.155 5.81 2.197 10.98
13 45 111.815 102.748 106.100 104.945 102.748 5.715 28.33 1.155 5.78 2.197 10.98
14 40 111.735 102.748 106.115 104.945 102.748 5.620 28.34 1.170 5.81 2.197 10.98
15 36 112.500 102.748 106.100 104.945 102.748 6.400 24.04 1.155 4.65 2.197 8.79
16 31 112.210 102.748 106.105 104.945 102.748 6.105 31.26 1.160 5.79 2.197 10.98
17 26 111.980 102.748 106.500 104.945 102.748 5.480 28.96 1.555 6.79 2.197 10.98
18 21 111.880 102.748 106.500 104.945 102.748 5.380 27.15 1.555 7.78 2.197 10.98
19 16 107.150 102.748 107.150 104.945 102.748 0.000 13.45 2.205 9.40 2.197 10.98
20 11 106.200 102.748 106.200 104.945 102.748 0.000 0.00 1.255 8.65 2.197 10.98
21 6 104.550 102.748 104.550 104.945 102.748 0.000 0.000 0.00 2.197 10.98
22 0 105.790 102.748 105.790 104.945 102.748 0.000 0.845 5.07 2.197 13.18
23 6 108.400 102.748 108.400 104.945 102.748 0.000 0.00 3.455 12.90 2.197 13.18
24 11 107.660 102.748 107.660 104.945 102.748 0.000 0.00 2.715 15.43 2.197 10.98
25 16 107.530 102.748 107.530 104.945 102.748 0.000 0.00 2.585 13.25 2.197 10.98
26 21 107.600 102.748 107.600 104.945 102.748 0.000 0.00 2.655 13.10 2.197 10.98
27 26 106.020 102.748 106.020 104.945 102.748 0.000 0.00 1.075 9.33 2.197 10.98
28 31 105.650 102.748 105.650 104.945 102.748 0.000 0.00 0.705 4.45 2.197 10.98
29 36 105.500 102.748 105.500 104.945 102.748 0.000 0.00 0.555 3.15 2.197 10.98
30 40 110.950 102.748 108.500 104.945 102.748 2.450 4.90 3.555 8.22 2.197 8.79
31 45 110.650 102.748 108.650 104.945 102.748 2.000 11.13 3.705 18.15 2.197 10.98
32 50 111.870 102.748 108.900 104.945 102.748 2.970 12.43 3.955 19.15 2.197 10.98
33 55 111.675 102.748 109.000 104.945 102.748 2.675 14.11 4.055 20.03 2.197 10.98
34 60 111.725 102.748 109.500 104.945 102.748 2.225 12.25 4.555 21.53 2.197 10.98
35 65 107.735 102.748 107.735 104.945 102.748 0.000 5.56 2.790 18.36 2.197 10.98
36 70 107.600 102.748 107.600 104.945 102.748 0.000 0.00 2.655 13.61 2.197 10.98
37 75 107.235 102.748 107.235 104.945 102.748 0.000 0.00 2.290 12.36 2.197 10.98
38 80 107.635 102.748 107.635 104.945 102.748 0.000 0.00 2.690 12.45 2.197 10.98
39 85 107.635 102.748 107.635 104.945 102.748 0.000 0.00 2.690 13.45 2.197 10.98
40 90 106.900 102.748 106.900 104.945 102.748 0.000 0.00 1.955 11.61 2.197 10.98
41 95 106.920 102.748 106.920 104.945 102.748 0.000 0.00 1.975 9.83 2.197 10.98
42 100 106.925 102.748 106.925 104.945 102.748 0.000 0.00 1.980 9.89 2.197 10.98
43 104.18 107.400 107.400 107.400 104.945 107.400 0.000 0.00 0.000 4.14 0.000 4.59
Total 409.88 Sqm 482.15 Sqm 454.11 Sqm
Formation Of Mallamadugu Reservoir
Details of Surplus Channel-0.075 KM of D/S of Spillway
EWE Areas Calcuation Sheet
Soils F&F HR
Bottom Bottom Bottom Bottom
Distance Ground Area of Area of
Slno Level of Level of Level of Level of Depth of Depth of Depth of Area of Remarks
in Meters Level Soils F&F
Channel Soils F&F HR Soils (M) F&F (M) HR (M) HR (Sqm)
(Sqm) (Sqm)
1 108.94 111.650 111.650 109.500 105.165 0.000 0.000 0.000
2 100 111.670 102.731 107.500 105.165 102.731 4.170 18.64 2.335 10.44 2.434 10.88
3 95 111.750 102.731 106.500 105.165 102.731 5.250 23.55 1.335 9.17 2.434 12.17
4 90 111.655 102.731 106.900 105.165 102.731 4.755 25.01 1.735 7.67 2.434 12.17
5 85 111.840 102.731 106.500 105.165 102.731 5.340 25.24 1.335 7.67 2.434 12.17
6 80 107.890 102.731 107.000 105.165 102.731 0.890 15.58 1.835 7.92 2.434 12.17
7 75 110.900 102.731 106.485 105.165 102.731 4.415 13.26 1.320 7.89 2.434 12.17
8 70 109.635 102.731 107.000 105.165 102.731 2.635 17.63 1.835 7.89 2.434 12.17
9 65 109.670 102.731 106.940 105.165 102.731 2.730 13.41 1.775 9.02 2.434 12.17
10 60 109.895 102.731 106.940 105.165 102.731 2.955 14.21 1.775 8.87 2.434 12.17
11 55 109.400 102.731 106.450 105.165 102.731 2.950 14.76 1.285 7.65 2.434 12.17
12 50 111.615 102.731 106.940 105.165 102.731 4.675 19.06 1.775 7.65 2.434 12.17
13 45 111.655 102.731 106.960 105.165 102.731 4.695 23.43 1.795 8.92 2.434 12.17
14 40 111.350 102.731 106.975 105.165 102.731 4.375 22.68 1.810 9.01 2.434 12.17
15 36 112.200 102.731 106.990 105.165 102.731 5.210 19.17 1.825 7.27 2.434 9.74
16 31 112.200 102.731 106.900 105.165 102.731 5.300 26.28 1.735 8.90 2.434 12.17
17 26 112.400 102.731 107.000 105.165 102.731 5.400 26.75 1.835 8.92 2.434 12.17
18 21 111.785 102.731 106.800 105.165 102.731 4.985 25.96 1.635 8.67 2.434 12.17
19 16 107.635 102.731 107.635 105.165 102.731 0.000 12.46 2.470 10.26 2.434 12.17
20 11 107.640 102.731 107.460 105.165 102.731 0.180 0.90 2.295 11.91 2.434 12.17
21 6 104.680 102.731 104.680 105.165 102.731 0.000 0.00 -0.485 5.73 1.949 10.96
22 0 104.975 102.731 104.975 105.165 102.731 0.000 0.00 -0.190 0.00 2.244 12.58
23 6 107.300 102.731 107.300 105.165 102.731 0.000 0.00 2.135 0.00 2.434 14.03
24 11 107.600 102.731 107.600 105.165 102.731 0.000 0.00 2.435 11.42 2.434 12.17
25 16 107.550 102.731 107.550 105.165 102.731 0.000 0.00 2.385 12.05 2.434 12.17
26 21 107.650 102.731 107.650 105.165 102.731 0.000 0.00 2.485 12.18 2.434 12.17
27 26 105.935 102.731 105.935 105.165 102.731 0.000 0.00 0.770 8.14 2.434 12.17
28 31 105.520 102.731 105.520 105.165 102.731 0.000 0.00 0.355 2.81 2.434 12.17
29 36 105.450 102.731 105.450 105.165 102.731 0.000 0.00 0.285 1.60 2.434 12.17
30 40 110.980 102.731 106.500 105.165 102.731 4.480 8.96 1.335 3.24 2.434 9.74
31 45 110.750 102.731 106.700 105.165 102.731 4.050 21.33 1.535 7.17 2.434 12.17
32 50 111.400 102.731 106.800 105.165 102.731 4.600 21.63 1.635 7.92 2.434 12.17
33 55 111.365 102.731 106.000 105.165 102.731 5.365 24.91 0.835 6.17 2.434 12.17
34 60 111.300 102.731 106.200 105.165 102.731 5.100 26.16 1.035 4.67 2.434 12.17
35 65 110.200 102.731 106.500 105.165 102.731 3.700 22.00 1.335 5.92 2.434 12.17
36 70 107.800 102.731 107.800 105.165 102.731 0.000 9.25 2.635 9.92 2.434 12.17
37 75 107.550 102.731 107.550 105.165 102.731 0.000 0.00 2.385 12.55 2.434 12.17
38 80 107.250 102.731 107.250 105.165 102.731 0.000 0.00 2.085 11.18 2.434 12.17
39 85 106.400 102.731 106.400 105.165 102.731 0.000 0.00 1.235 8.30 2.434 12.17
40 90 106.600 102.731 106.600 105.165 102.731 0.000 0.00 1.435 6.67 2.434 12.17
41 95 106.000 102.731 106.000 105.165 102.731 0.000 0.00 0.835 5.67 2.434 12.17
42 100 106.450 102.731 106.450 105.165 102.731 0.000 0.00 1.285 5.30 2.434 12.17
43 103.72 107.400 107.400 107.400 104.945 107.400 0.000 0.00 0.000 2.39 0.000 4.53
Total 492.21 Sqm 316.78 Sqm 498.40 Sqm
Formation Of Mallamadugu Reservoir
Details of Surplus Channel-0.100 KM of D/S of Spillway
EWE Areas Calcuation Sheet
Soils F&F HR
Bottom Bottom Bottom Bottom
Distance Ground Area of Area of
Slno Level of Level of Level of Level of Depth of Depth of Depth of Area of Remarks
in Meters Level Soils F&F
Channel Soils F&F HR Soils (M) F&F (M) HR (M) HR (Sqm)
(Sqm) (Sqm)
1 109.54 111.325 111.325 109.000 104.400 0.000 0.000 0.000
2 100 112.250 102.714 107.600 104.400 102.714 4.650 22.18 3.200 15.26 1.686 8.04
3 95 111.400 102.714 107.600 104.400 102.714 3.800 21.13 3.200 16.00 1.686 8.43
4 90 111.680 102.714 107.500 104.400 102.714 4.180 19.95 3.100 15.75 1.686 8.43
5 85 111.415 102.714 107.000 104.400 102.714 4.415 21.49 2.600 14.25 1.686 8.43
6 80 111.565 102.714 106.800 104.400 102.714 4.765 22.95 2.400 12.50 1.686 8.43
7 75 107.240 102.714 106.500 104.400 102.714 0.740 13.76 2.100 11.25 1.686 8.43
8 70 109.465 102.714 107.000 104.400 102.714 2.465 8.01 2.600 11.75 1.686 8.43
9 65 108.835 102.714 107.500 104.400 102.714 1.335 9.50 3.100 14.25 1.686 8.43
10 60 108.815 102.714 107.510 104.400 102.714 1.305 6.60 3.110 15.53 1.686 8.43
11 55 111.290 102.714 107.515 104.400 102.714 3.775 12.70 3.115 15.56 1.686 8.43
12 50 111.800 102.714 107.550 104.400 102.714 4.250 20.06 3.150 15.66 1.686 8.43
13 45 111.360 102.714 107.560 104.400 102.714 3.800 20.13 3.160 15.78 1.686 8.43
14 40 111.695 102.714 107.575 104.400 102.714 4.120 19.80 3.175 15.84 1.686 8.43
15 36 112.350 102.714 107.600 104.400 102.714 4.750 17.74 3.200 12.75 1.686 6.74
16 31 112.400 102.714 107.550 104.400 102.714 4.850 24.00 3.150 15.88 1.686 8.43
17 26 111.200 102.714 107.650 104.400 102.714 3.550 21.00 3.250 16.00 1.686 8.43
18 21 110.800 102.714 107.675 104.400 102.714 3.125 16.69 3.275 16.31 1.686 8.43
19 16 108.245 102.714 107.375 104.400 102.714 0.870 9.99 2.975 15.63 1.686 8.43
20 11 107.550 102.714 107.550 104.400 102.714 0.000 2.18 3.150 15.31 1.686 8.43
21 6 104.750 102.714 104.750 104.400 102.714 0.000 0.00 0.350 8.75 1.686 8.43
22 0 104.990 102.714 104.990 104.400 102.714 0.000 0.00 0.590 2.82 1.686 10.12
23 6 107.270 102.714 107.270 104.400 102.714 0.000 0.00 2.870 10.38 1.686 10.12
24 11 107.550 102.714 107.550 104.400 102.714 0.000 0.00 3.150 15.05 1.686 8.43
25 16 107.450 102.714 107.450 104.400 102.714 0.000 0.00 3.050 15.50 1.686 8.43
26 21 107.535 102.714 107.535 104.400 102.714 0.000 0.00 3.135 15.46 1.686 8.43
27 26 105.920 102.714 105.920 104.400 102.714 0.000 0.00 1.520 11.64 1.686 8.43
28 31 105.450 102.714 105.450 104.400 102.714 0.000 0.00 1.050 6.42 1.686 8.43
29 36 111.340 102.714 106.500 104.400 102.714 4.840 12.10 2.100 7.87 1.686 8.43
30 40 111.250 102.714 106.375 104.400 102.714 4.875 19.43 1.975 8.15 1.686 6.74
31 45 111.275 102.714 106.450 104.400 102.714 4.825 24.25 2.050 10.06 1.686 8.43
32 50 111.465 102.714 106.700 104.400 102.714 4.765 23.98 2.300 10.88 1.686 8.43
33 55 111.450 102.714 107.200 104.400 102.714 4.250 22.54 2.800 12.75 1.686 8.43
34 60 111.350 102.714 107.350 104.400 102.714 4.000 20.63 2.950 14.38 1.686 8.43
35 65 111.130 102.714 107.200 104.400 102.714 3.930 19.83 2.800 14.38 1.686 8.43
36 70 107.735 102.714 107.100 104.400 102.714 0.635 11.41 2.700 13.75 1.686 8.43
37 75 107.180 102.714 107.000 104.400 102.714 0.180 2.04 2.600 13.25 1.686 8.43
38 80 106.150 102.714 106.150 104.400 102.714 0.000 0.45 1.750 10.88 1.686 8.43
39 85 106.150 102.714 106.150 104.400 102.714 0.000 0.00 1.750 8.75 1.686 8.43
40 90 106.100 102.714 106.100 104.400 102.714 0.000 0.00 1.700 8.62 1.686 8.43
41 95 106.100 102.714 106.100 104.400 102.714 0.000 0.00 1.700 8.50 1.686 8.43
42 100 106.150 102.714 106.150 104.400 102.714 0.000 0.00 1.750 8.62 1.686 8.43
43 103.44 107.400 107.400 107.400 104.945 107.400 0.000 0.00 0.000 3.01 0.000 2.90
Total 466.49 Sqm 521.12 Sqm 348.14 Sqm
Formation Of Mallamadugu Reservoir
Details of Surplus Channel-0.125 KM of D/S of Spillway
EWE Areas Calcuation Sheet
Soils F&F HR
Bottom Bottom Bottom Bottom
Distance Ground Area of Area of
Slno Level of Level of Level of Level of Depth of Depth of Depth of Area of Remarks
in Meters Level Soils F&F
Channel Soils F&F HR Soils (M) F&F (M) HR (M) HR (Sqm)
(Sqm) (Sqm)
1 108.54 111.020 111.020 104.500 103.400 0.000 0.000 0.000
2 100 111.240 102.696 105.000 103.400 102.696 6.240 26.64 1.600 6.83 0.704 3.01
3 95 111.450 102.696 105.500 103.400 102.696 5.950 30.48 2.100 9.25 0.704 3.52
4 90 111.265 102.696 106.000 103.400 102.696 5.265 28.04 2.600 11.75 0.704 3.52
5 85 111.750 102.696 106.000 103.400 102.696 5.750 27.54 2.600 13.00 0.704 3.52
6 80 109.450 102.696 106.450 103.400 102.696 3.000 21.88 3.050 14.13 0.704 3.52
7 75 109.150 102.696 106.150 103.400 102.696 3.000 15.00 2.750 14.50 0.704 3.52
8 70 109.450 102.696 106.450 103.400 102.696 3.000 15.00 3.050 14.50 0.704 3.52
9 65 108.800 102.696 106.350 103.400 102.696 2.450 13.63 2.950 15.00 0.704 3.52
10 60 108.810 102.696 106.350 103.400 102.696 2.460 12.28 2.950 14.75 0.704 3.52
11 55 111.800 102.696 106.340 103.400 102.696 5.460 19.80 2.940 14.73 0.704 3.52
12 50 112.150 102.696 106.350 103.400 102.696 5.800 28.15 2.950 14.73 0.704 3.52
13 45 112.200 102.696 106.340 103.400 102.696 5.860 29.15 2.940 14.73 0.704 3.52
14 40 111.950 102.696 106.720 103.400 102.696 5.230 27.73 3.320 15.65 0.704 3.52
15 36 112.400 102.696 107.020 103.400 102.696 5.380 21.22 3.620 13.88 0.704 2.82
16 31 112.350 102.696 108.100 103.400 102.696 4.250 24.08 4.700 20.80 0.704 3.52
17 26 108.700 102.696 108.700 103.400 102.696 0.000 0.00 5.300 25.00 0.704 3.52
18 21 108.800 102.696 108.800 103.400 102.696 0.000 0.00 5.400 26.75 0.704 3.52
19 16 108.750 102.696 108.750 103.400 102.696 0.000 0.00 5.350 26.88 0.704 3.52
20 11 108.650 102.696 108.650 103.400 102.696 0.000 0.00 5.250 26.50 0.704 3.52
21 6 106.250 102.696 106.250 103.400 102.696 0.000 0.00 2.850 20.25 0.704 3.52
22 0 105.500 102.696 105.500 103.400 102.696 0.000 0.00 2.100 14.85 0.704 4.22
23 6 107.570 102.696 107.570 103.400 102.696 0.000 0.00 4.170 18.81 0.704 4.22
24 11 107.675 102.696 107.675 103.400 102.696 0.000 0.00 4.275 21.11 0.704 3.52
25 16 107.550 102.696 107.550 103.400 102.696 0.000 0.00 4.150 21.06 0.704 3.52
26 21 107.450 102.696 107.450 103.400 102.696 0.000 0.00 4.050 20.50 0.704 3.52
27 26 105.800 102.696 105.800 103.400 102.696 0.000 0.00 2.400 16.13 0.704 3.52
28 31 111.500 102.696 106.790 103.400 102.696 4.710 11.78 3.390 14.48 0.704 3.52
29 36 111.300 102.696 107.790 103.400 102.696 3.510 20.55 4.390 19.45 0.704 3.52
30 40 111.750 102.696 108.790 103.400 102.696 2.960 12.94 5.390 19.56 0.704 2.82
31 45 111.870 102.696 108.790 103.400 102.696 3.080 15.10 5.390 26.95 0.704 3.52
32 50 111.485 102.696 108.705 103.400 102.696 2.780 14.65 5.305 26.74 0.704 3.52
33 55 111.520 102.696 108.710 103.400 102.696 2.810 13.98 5.310 26.54 0.704 3.52
34 60 111.380 102.696 108.610 103.400 102.696 2.770 13.95 5.210 26.30 0.704 3.52
35 65 110.905 102.696 108.610 103.400 102.696 2.295 12.66 5.210 26.05 0.704 3.52
36 70 105.750 102.696 105.750 103.400 102.696 0.000 0.00 2.350 18.90 0.704 3.52
37 75 105.730 102.696 105.730 103.400 102.696 0.000 0.00 2.330 11.70 0.704 3.52
38 80 105.150 102.696 105.150 103.400 102.696 0.000 0.00 1.750 10.20 0.704 3.52
39 85 105.100 102.696 105.100 103.400 102.696 0.000 0.00 1.700 8.62 0.704 3.52
40 90 105.100 102.696 105.100 103.400 102.696 0.000 0.00 1.700 8.50 0.704 3.52
41 95 105.200 102.696 105.200 103.400 102.696 0.000 0.00 1.800 8.75 0.704 3.52
42 100 106.150 102.696 106.150 103.400 102.696 0.000 0.00 2.750 11.38 0.704 3.52
43 103.45 107.400 107.400 107.400 104.945 107.400 0.000 0.00 0.000 4.74 0.000 1.21
Total 456.19 Sqm 714.90 Sqm 145.02 Sqm
EWE Areas Calcuation Sheet
At Chinage 0.150 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 112.545 112.545 105.400 112.545 0.000 0.000
2 100 110.935 102.679 105.400 102.679 5.535 44.28 2.721 21.77
3 75 110.985 102.679 105.400 102.679 5.585 139.00 2.721 68.03
4 50 110.955 102.679 105.400 102.679 5.555 139.25 2.721 68.03
5 25 102.390 102.679 105.400 102.679 0.000 69.44 0.000 34.01
6 0 102.990 102.679 105.400 102.679 0.000 0.311 3.89
7 25 110.485 102.679 105.400 102.679 5.085 63.56 2.721 37.90
8 50 110.280 102.679 105.400 102.679 4.880 124.56 2.721 68.03
9 75 105.795 102.679 105.400 102.679 0.395 65.94 2.721 68.03
10 100 105.880 102.679 105.400 102.679 0.480 10.94 2.721 68.03
11 116 106.885 106.885 105.400 106.885 0.000 3.84 0.000 21.77
Total 660.81 459.49 Sqm

At Chinage 0.175 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 111.200 111.200 105.500 111.200 0.000 0.000
2 100 111.055 102.662 105.500 102.662 5.555 44.44 2.838 22.70
3 75 110.885 102.662 105.500 102.662 5.385 136.75 2.838 70.95
4 50 110.995 102.662 105.500 102.662 5.495 136 2.838 70.95
5 25 102.815 102.662 105.500 102.662 0.000 68.69 0.153 37.39
6 0 107.900 102.662 105.500 102.662 2.400 30 2.838 37.39
7 25 109.685 102.662 105.500 102.662 4.185 82.31 2.838 70.95
8 50 109.745 102.662 105.500 102.662 4.245 105.38 2.838 70.95
9 75 105.720 102.662 105.500 102.662 0.220 55.81 2.838 70.95
10 100 105.870 102.662 105.500 102.662 0.370 7.37 2.838 70.95
11 116 107.910 107.910 105.500 107.910 2.410 22.24 0.000 22.70
Total 688.99 545.88 Sqm

At Chinage 0.200 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 111.015 111.015 105.000 111.015 0.000 0.000
2 100 110.955 102.645 105.000 102.645 5.955 47.64 2.355 18.84
3 75 110.895 102.645 105.000 102.645 5.895 148.13 2.355 58.88
4 50 102.850 102.645 105.000 102.645 0.000 73.69 0.205 32.00
5 25 102.985 102.645 105.000 102.645 0.000 0.340 6.81
6 0 109.655 102.645 105.000 102.645 4.655 58.19 2.355 33.69
7 25 109.995 102.645 105.000 102.645 4.995 120.63 2.355 58.88
8 50 105.660 102.645 105.000 102.645 0.660 70.69 2.355 58.88
9 75 105.620 102.645 105.000 102.645 0.620 16 2.355 58.88
10 100 105.580 102.645 105.000 102.645 0.580 15 2.355 58.88
11 116 108.125 108.125 105.000 108.125 3.125 29.64 0.000 18.84
Total 579.61 404.58 Sqm

At Chinage 0.225 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 111.230 111.230 105.000 111.230 6.230 0.000
2 100 111.055 102.627 105.000 102.627 6.055 98.28 2.373 18.98
3 75 111.120 102.627 105.000 102.627 6.120 152.19 2.373 59.33
4 50 102.655 102.627 105.000 102.627 0.000 76.5 0.028 30.01
5 25 102.755 102.627 105.000 102.627 0.000 0.128 1.95
6 0 109.930 102.627 105.000 102.627 4.930 61.62 2.373 31.26
7 25 109.885 102.627 105.000 102.627 4.885 122.69 2.373 59.33
8 50 105.295 102.627 105.000 102.627 0.295 64.75 2.373 59.33
9 75 105.390 102.627 105.000 102.627 0.390 8.56 2.373 59.33
10 100 105.320 102.627 105.000 102.627 0.320 8.87 2.373 59.33
11 116 108.420 108.420 105.000 108.420 3.420 29.92 0.000 18.98
Total 623.38 397.83 Sqm
At Chinage 0.250 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 110.425 110.425 105.000 110.425 0.000 0.000
2 100 110.585 102.610 105.000 102.610 5.585 44.68 2.390 19.12
3 75 102.540 102.610 105.000 102.610 0.000 69.81 0.000 29.88
4 50 102.380 102.610 105.000 102.610 0.000 0.000 0.00
5 25 102.450 102.610 105.000 102.610 0.000 0.000 0.00
6 0 108.790 102.610 105.000 102.610 3.790 47.37 2.390 29.88
7 25 108.715 102.610 105.000 102.610 3.715 93.81 2.390 59.75
8 50 108.570 102.610 105.000 102.610 3.570 91.06 2.390 59.75
9 75 108.655 102.610 105.000 102.610 3.655 90.31 2.390 59.75
10 100 109.820 102.610 105.000 102.610 4.820 105.94 2.390 59.75
11 116 110.220 110.220 105.000 110.220 0.000 38.56 0.000 19.12
Total 581.54 337.00 Sqm

At Chinage 0.275 Km
Bottom Bottom Soils HDR
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 110.625 110.625 104.700 110.625 0.000 0.000
2 100 110.745 102.593 104.700 102.593 6.045 48.36 2.107 16.86
3 75 102.065 102.593 104.700 102.593 0.000 75.56 0.000 26.34
4 50 102.215 102.593 104.700 102.593 0.000 0.000 0.00
5 25 102.310 102.593 104.700 102.593 0.000 0.000 0.00
6 0 106.970 102.593 104.700 102.593 2.270 28.37 2.107 26.34
7 25 107.060 102.593 104.700 102.593 2.360 57.87 2.107 52.68
8 50 106.690 102.593 104.700 102.593 1.990 54.37 2.107 52.68
9 75 107.020 102.593 104.700 102.593 2.320 53.87 2.107 52.68
10 100 109.530 102.593 104.700 102.593 4.830 89.37 2.107 52.68
11 116 110.435 110.435 104.700 110.435 0.000 38.64 0.000 16.86
Total 446.41 297.12 Sqm

At Chinage 0.300 Km
Bottom Bottom Soils HDR
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 110.300 110.300 105.000 110.300 0.000 0.000
2 100 110.325 102.576 105.000 102.576 5.325 42.6 2.424 19.39
3 75 104.670 102.576 105.000 102.576 0.000 66.56 2.094 56.48
4 50 103.515 102.576 105.000 102.576 0.000 0.939 37.91
5 25 107.575 102.576 105.000 102.576 2.575 32.19 2.424 42.04
6 0 105.855 102.576 105.000 102.576 0.855 42.87 2.424 60.60
7 25 107.185 102.576 105.000 102.576 2.185 38 2.424 60.60
8 50 106.565 102.576 105.000 102.576 1.565 46.88 2.424 60.60
9 75 106.155 102.576 105.000 102.576 1.155 34 2.424 60.60
10 100 109.175 102.576 105.000 102.576 4.175 66.63 2.424 60.60
11 116 110.385 110.385 105.000 110.385 0.000 33.4 0.000 19.39
Total 403.13 478.21 Sqm

At Chinage 0.325 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 109.810 109.810 109.810 109.810 0.000 0.000
2 100 109.765 102.558 104.700 102.558 5.065 40.52 2.142 17.14
3 75 104.680 102.558 104.700 102.558 0.000 63.31 2.122 53.30
4 50 102.950 102.558 104.700 102.558 0.000 0 0.392 31.42
5 25 106.445 102.558 104.700 102.558 1.745 21.81 2.142 31.67
6 0 106.295 102.558 104.700 102.558 1.595 41.75 2.142 53.55
7 25 106.890 102.558 104.700 102.558 2.190 47.31 2.142 53.55
8 50 106.715 102.558 104.700 102.558 2.015 52.56 2.142 53.55
9 75 106.120 102.558 104.700 102.558 1.420 42.94 2.142 53.55
10 100 107.795 102.558 104.700 102.558 3.095 56.44 2.142 53.55
11 116 108.460 108.460 108.460 108.460 0.000 24.76 0.000 17.14
Total 391.40 418.42 Sqm
At Chinage 0.350 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 106.050 106.050 106.050 106.050 0.000 0.000
2 100 105.475 102.541 104.200 102.541 1.275 10.2 1.659 13.27
3 75 103.365 102.541 104.200 102.541 0.000 15.94 0.824 31.04
4 50 102.865 102.541 104.200 102.541 0.000 0 0.324 14.35
5 25 106.430 102.541 104.200 102.541 2.230 27.87 1.659 24.79
6 0 105.775 102.541 104.200 102.541 1.575 47.56 1.659 41.48
7 25 106.890 102.541 104.200 102.541 2.690 53.31 1.659 41.48
8 50 106.335 102.541 104.200 102.541 2.135 60.31 1.659 41.48
9 75 105.835 102.541 104.200 102.541 1.635 47.12 1.659 41.48
10 100 107.780 102.541 104.200 102.541 3.580 65.19 1.659 41.48
11 116 108.375 108.375 108.375 108.375 0.000 28.64 0.000 13.27
Total 356.14 304.12 Sqm

At Chinage 0.375 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 106.100 106.100 106.100 106.100 0.000 0.000
2 100 105.225 102.524 104.300 102.524 0.925 7.4 1.776 14.21
3 75 103.775 102.524 104.300 102.524 0.000 11.56 1.251 37.84
4 50 103.595 102.524 104.300 102.524 0.000 0 1.071 29.02
5 25 106.295 102.524 104.300 102.524 1.995 24.94 1.776 35.59
6 0 105.745 102.524 104.300 102.524 1.445 43 1.776 44.40
7 25 106.470 102.524 104.300 102.524 2.170 45.19 1.776 44.40
8 50 105.975 102.524 104.300 102.524 1.675 48.06 1.776 44.40
9 75 105.385 102.524 104.300 102.524 1.085 34.5 1.776 44.40
10 100 107.700 102.524 104.300 102.524 3.400 56.06 1.776 44.40
11 116 108.555 108.555 108.555 108.555 0.000 27.2 0.000 14.21
Total 297.91 352.87 Sqm

At Chinage 0.400 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 106.225 106.225 106.225 106.225 0.000 0.000
2 100 104.710 102.507 104.100 102.507 0.610 4.88 1.593 12.74
3 75 103.750 102.507 104.100 102.507 0.000 7.62 1.243 35.45
4 50 104.005 102.507 104.100 102.507 0.000 0 1.498 34.26
5 25 105.690 102.507 104.100 102.507 1.590 19.88 1.593 38.64
6 0 106.055 102.507 104.100 102.507 1.955 44.31 1.593 39.82
7 25 105.730 102.507 104.100 102.507 1.630 44.81 1.593 39.82
8 50 105.465 102.507 104.100 102.507 1.365 37.44 1.593 39.82
9 75 105.835 102.507 104.100 102.507 1.735 38.75 1.593 39.82
10 100 107.765 102.507 104.100 102.507 3.665 67.5 1.593 39.82
11 116 108.420 108.420 108.420 108.420 0.000 29.32 0.000 12.74
Total 294.51 332.93 Sqm

At Chinage 0.425 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 106.100 106.100 106.100 106.100 0.000 0.000
2 100 104.115 102.489 104.000 102.489 0.115 0.92 1.511 12.09
3 75 103.050 102.489 104.000 102.489 0.000 1.44 0.561 25.90
4 50 103.845 102.489 104.000 102.489 0.000 0 1.356 23.96
5 25 104.175 102.489 104.000 102.489 0.175 2.19 1.511 35.84
6 0 105.985 102.489 104.000 102.489 1.985 27 1.511 37.77
7 25 105.095 102.489 104.000 102.489 1.095 38.5 1.511 37.77
8 50 106.300 102.489 104.000 102.489 2.300 42.44 1.511 37.77
9 75 106.905 102.489 104.000 102.489 2.905 65.06 1.511 37.77
10 100 107.695 102.489 104.000 102.489 3.695 82.5 1.511 37.77
11 116 108.310 108.310 108.310 108.310 0.000 29.56 0.000 12.09
Total 289.61 298.73 Sqm
At Chinage 0.450 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 105.880 105.880 105.880 105.880 0.000 0.000
2 100 103.685 102.472 103.900 102.472 0.000 0 1.213 9.70
3 75 103.475 102.472 103.900 102.472 0.000 0 1.003 27.70
4 50 103.225 102.472 103.900 102.472 0.000 0 0.753 21.95
5 25 103.185 102.472 103.900 102.472 0.000 0 0.713 18.32
6 0 105.855 102.472 103.900 102.472 1.955 24.44 1.428 26.76
7 25 104.925 102.472 103.900 102.472 1.025 37.25 1.428 35.70
8 50 105.055 102.472 103.900 102.472 1.155 27.25 1.428 35.70
9 75 107.160 102.472 103.900 102.472 3.260 55.19 1.428 35.70
10 100 107.780 102.472 103.900 102.472 3.880 89.25 1.428 35.70
11 116 108.375 108.375 108.375 108.375 0.000 31.04 0.000 11.42
Total 264.42 258.65 Sqm

At Chinage 0.475 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 105.650 105.650 105.650 105.650 0.000 0.000
2 100 103.975 102.455 103.800 102.455 0.175 1.4 1.345 10.76
3 75 103.965 102.455 103.800 102.455 0.165 4.25 1.345 33.63
4 50 103.815 102.455 103.800 102.455 0.015 2.25 1.345 33.63
5 25 103.585 102.455 103.800 102.455 0.000 0.19 1.130 30.94
6 0 102.845 102.455 103.800 102.455 0.000 0 0.390 19.00
7 25 104.825 102.455 103.800 102.455 1.025 12.81 1.345 21.69
8 50 106.880 102.455 103.800 102.455 3.080 51.31 1.345 33.63
9 75 106.895 102.455 103.800 102.455 3.095 77.19 1.345 33.63
10 100 106.955 102.455 103.800 102.455 3.155 78.12 1.345 33.63
11 116 107.895 107.895 107.895 107.895 0.000 25.24 0.000 10.76
Total 252.76 261.30 Sqm

At Chinage 0.500 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 107.420 107.420 107.420 107.420 0.000 0.000
2 100 107.565 102.438 104.800 102.438 2.765 22.12 2.362 18.90
3 75 108.170 102.438 104.800 102.438 3.370 76.69 2.362 59.05
4 50 108.385 102.438 104.800 102.438 3.585 86.94 2.362 59.05
5 25 103.565 102.438 104.800 102.438 0.000 44.81 1.127 43.61
6 0 102.365 102.438 104.800 102.438 0.000 0 0.000 14.09
7 25 104.775 102.438 104.800 102.438 0.000 0 2.337 29.21
8 50 108.980 102.438 104.800 102.438 4.180 52.25 2.362 58.74
9 75 109.110 102.438 104.800 102.438 4.310 106.13 2.362 59.05
10 100 109.385 102.438 104.800 102.438 4.585 111.19 2.362 59.05
11 116 109.410 109.410 109.410 109.410 0.000 36.68 0.000 18.90
Total 536.81 419.65 Sqm

At Chinage 0.525 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 107.410 107.410 107.410 107.410 0.000 0.000
2 100 107.480 102.420 104.800 102.420 2.680 21.44 2.380 19.04
3 75 108.265 102.420 104.800 102.420 3.465 76.81 2.380 59.50
4 50 108.395 102.420 104.800 102.420 3.595 88.25 2.380 59.50
5 25 105.175 102.420 104.800 102.420 0.375 49.62 2.380 59.50
6 0 104.325 102.420 104.800 102.420 0.000 4.69 1.905 53.56
7 25 102.165 102.420 104.800 102.420 0.000 0 0.000 23.81
8 50 109.005 102.420 104.800 102.420 4.205 52.56 2.380 29.75
9 75 109.130 102.420 104.800 102.420 4.330 106.69 2.380 59.50
10 100 109.280 102.420 104.800 102.420 4.480 110.13 2.380 59.50
11 116 109.300 109.300 109.300 109.300 0.000 35.84 0.000 19.04
Total 546.03 442.70 Sqm
At Chinage 0.550 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 107.385 107.385 107.385 107.385 0.000 0.000
2 100 107.425 102.403 104.500 102.403 2.925 23.4 2.097 16.78
3 75 107.465 102.403 104.500 102.403 2.965 73.62 2.097 52.42
4 50 107.545 102.403 104.500 102.403 3.045 75.12 2.097 52.42
5 25 105.240 102.403 104.500 102.403 0.740 47.31 2.097 52.42
6 0 103.760 102.403 104.500 102.403 0.000 9.25 1.357 43.17
7 25 102.685 102.403 104.500 102.403 0.000 0 0.282 20.49
8 50 105.065 102.403 104.500 102.403 0.565 7.06 2.097 29.74
9 75 108.675 102.403 104.500 102.403 4.175 59.25 2.097 52.42
10 100 108.915 102.403 104.500 102.403 4.415 107.38 2.097 52.42
11 116 109.005 109.005 109.005 109.005 0.000 35.32 0.000 16.78
Total 437.71 389.06 Sqm

At Chinage 0.575 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 107.005 107.005 107.005 107.005 0.000 0.000
2 100 107.260 102.386 104.600 102.386 2.660 21.28 2.214 17.71
3 75 107.325 102.386 104.600 102.386 2.725 67.31 2.214 55.35
4 50 107.465 102.386 104.600 102.386 2.865 69.87 2.214 55.35
5 25 105.040 102.386 104.600 102.386 0.440 41.31 2.214 55.35
6 0 104.375 102.386 104.600 102.386 0.000 5.5 1.989 52.54
7 25 102.745 102.386 104.600 102.386 0.000 0 0.359 29.35
8 50 108.625 102.386 104.600 102.386 4.025 50.31 2.214 32.16
9 75 108.655 102.386 104.600 102.386 4.055 101 2.214 55.35
10 100 108.825 102.386 104.600 102.386 4.225 103.5 2.214 55.35
11 116 108.875 108.875 108.875 108.875 0.000 33.8 0.000 17.71
Total 493.88 426.22 Sqm

At Chinage 0.600 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 108.140 108.140 108.140 108.140 0.000 0.000
2 100 108.255 102.369 104.700 102.369 3.555 28.44 2.331 18.65
3 75 108.185 102.369 104.700 102.369 3.485 88 2.331 58.28
4 50 106.255 102.369 104.700 102.369 1.555 63 2.331 58.28
5 25 104.915 102.369 104.700 102.369 0.215 22.12 2.331 58.28
6 0 104.485 102.369 104.700 102.369 0.000 2.69 2.116 55.59
7 25 102.675 102.369 104.700 102.369 0.000 0 0.306 30.27
8 50 108.675 102.369 104.700 102.369 3.975 49.69 2.331 32.96
9 75 108.755 102.369 104.700 102.369 4.055 100.38 2.331 58.28
10 100 108.865 102.369 104.700 102.369 4.165 102.75 2.331 58.28
11 116 109.010 109.010 109.010 109.010 0.000 33.32 0.000 18.65
Total 490.39 447.52 Sqm

At Chinage 0.625 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 108.395 108.395 108.395 108.395 0.000 0.000
2 100 108.415 102.351 104.700 102.351 3.715 29.72 2.349 18.79
3 75 108.130 102.351 104.700 102.351 3.430 89.31 2.349 58.73
4 50 106.385 102.351 104.700 102.351 1.685 63.94 2.349 58.73
5 25 104.590 102.351 104.700 102.351 0.000 21.06 2.239 57.35
6 0 104.375 102.351 104.700 102.351 0.000 0 2.024 53.29
7 25 102.605 102.351 104.700 102.351 0.000 0 0.254 28.47
8 50 108.710 102.351 104.700 102.351 4.010 50.12 2.349 32.54
9 75 108.840 102.351 104.700 102.351 4.140 101.88 2.349 58.73
10 100 108.855 102.351 104.700 102.351 4.155 103.69 2.349 58.73
11 116 108.980 108.980 108.980 108.980 0.000 33.24 0.000 18.79
Total 492.96 444.15 Sqm
At Chinage 0.650 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 107.740 107.740 107.740 107.740 0.000 0.000
2 100 107.700 102.334 104.600 102.334 3.100 24.8 2.266 18.13
3 75 107.785 102.334 104.600 102.334 3.185 78.56 2.266 56.65
4 50 106.070 102.334 104.600 102.334 1.470 58.19 2.266 56.65
5 25 106.095 102.334 104.600 102.334 1.495 37.06 2.266 56.65
6 0 104.235 102.334 104.600 102.334 0.000 18.69 1.901 52.09
7 25 102.580 102.334 104.600 102.334 0.000 0 0.246 26.84
8 50 108.025 102.334 104.600 102.334 3.425 42.81 2.266 31.40
9 75 108.645 102.334 104.600 102.334 4.045 93.38 2.266 56.65
10 100 108.780 102.334 104.600 102.334 4.180 102.81 2.266 56.65
11 116 108.830 108.830 108.830 108.830 0.000 33.44 0.000 18.13
Total 489.74 429.84 Sqm

At Chinage 0.675 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 107.700 107.700 107.700 107.700 0.000 0.000
2 100 107.765 102.317 104.300 102.317 3.465 27.72 1.983 15.86
3 75 107.725 102.317 104.300 102.317 3.425 86.12 1.983 49.58
4 50 106.050 102.317 104.300 102.317 1.750 64.69 1.983 49.58
5 25 106.035 102.317 104.300 102.317 1.735 43.56 1.983 49.58
6 0 103.960 102.317 104.300 102.317 0.000 21.69 1.643 45.33
7 25 102.930 102.317 104.300 102.317 0.000 0 0.613 28.20
8 50 103.485 102.317 104.300 102.317 0.000 0 1.168 22.26
9 75 108.045 102.317 104.300 102.317 3.745 46.81 1.983 39.39
10 100 108.620 102.317 104.300 102.317 4.320 100.81 1.983 49.58
11 116 108.655 108.655 108.655 108.655 0.000 34.56 0.000 15.86
Total 425.96 365.22 Sqm

At Chinage 0.700 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 108.010 108.010 108.010 108.010 0.000 0.000
2 100 107.955 102.300 104.300 102.300 3.655 29.24 2.000 16.00
3 75 107.915 102.300 104.300 102.300 3.615 90.87 2.000 50.00
4 50 105.320 102.300 104.300 102.300 1.020 57.94 2.000 50.00
5 25 105.680 102.300 104.300 102.300 1.380 30 2.000 50.00
6 0 103.710 102.300 104.300 102.300 0.000 17.25 1.410 42.63
7 25 102.980 102.300 104.300 102.300 0.000 0 0.680 26.12
8 50 103.640 102.300 104.300 102.300 0.000 0 1.340 25.25
9 75 107.605 102.300 104.300 102.300 3.305 41.31 2.000 41.75
10 100 108.460 102.300 104.300 102.300 4.160 93.31 2.000 50.00
11 116 108.510 108.510 108.510 108.510 0.000 33.28 0.000 16.00
Total 393.20 367.75 Sqm

At Chinage 0.725 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 105.320 105.320 105.320 105.320 0.000 0.000
2 100 105.115 102.283 103.500 102.283 1.615 12.92 1.217 9.74
3 75 104.940 102.283 103.500 102.283 1.440 38.19 1.217 30.43
4 50 105.070 102.283 103.500 102.283 1.570 37.62 1.217 30.43
5 25 105.240 102.283 103.500 102.283 1.740 41.37 1.217 30.43
6 0 103.755 102.283 103.500 102.283 0.255 24.94 1.217 30.43
7 25 102.810 102.283 103.500 102.283 0.000 3.19 0.527 21.80
8 50 103.920 102.283 103.500 102.283 0.420 5.25 1.217 21.80
9 75 107.655 102.283 103.500 102.283 4.155 57.19 1.217 30.43
10 100 108.480 102.283 103.500 102.283 4.980 114.19 1.217 30.43
11 116 108.570 108.570 108.570 108.570 0.000 39.84 0.000 9.74
Total 374.70 245.66 Sqm
At Chinage 0.750 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 105.225 105.225 105.225 105.225 0.000 0.000
2 100 105.155 102.265 103.500 102.265 1.655 13.24 1.235 9.88
3 75 105.010 102.265 103.500 102.265 1.510 39.56 1.235 30.88
4 50 103.865 102.265 103.500 102.265 0.365 23.44 1.235 30.88
5 25 103.595 102.265 103.500 102.265 0.095 5.75 1.235 30.88
6 0 103.610 102.265 103.500 102.265 0.110 2.56 1.235 30.88
7 25 102.480 102.265 103.500 102.265 0.000 1.37 0.215 18.12
8 50 103.980 102.265 103.500 102.265 0.480 6 1.235 18.12
9 75 103.920 102.265 103.500 102.265 0.420 11.25 1.235 30.88
10 100 108.455 102.265 103.500 102.265 4.955 67.19 1.235 30.88
11 116 108.555 108.555 108.555 108.555 0.000 39.64 0.000 9.88
Total 210.00 241.28 Sqm

At Chinage 0.775 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 105.100 105.100 105.100 105.100 0.000 0.000
2 100 104.805 102.248 103.400 102.248 1.405 11.24 1.152 9.22
3 75 104.635 102.248 103.400 102.248 1.235 33 1.152 28.80
4 50 104.505 102.248 103.400 102.248 1.105 29.25 1.152 28.80
5 25 103.300 102.248 103.400 102.248 0.000 13.81 1.052 27.55
6 0 102.720 102.248 103.400 102.248 0.000 0 0.472 19.05
7 25 102.175 102.248 103.400 102.248 0.000 0 0.000 5.90
8 50 104.210 102.248 103.400 102.248 0.810 10.12 1.152 14.40
9 75 104.675 102.248 103.400 102.248 1.275 26.06 1.152 28.80
10 100 107.960 102.248 103.400 102.248 4.560 72.94 1.152 28.80
11 116 108.110 108.110 108.110 108.110 0.000 36.48 0.000 9.22
Total 232.90 200.54 Sqm

At Chinage 0.800 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 105.215 105.215 105.215 105.215 0.000 0.000
2 100 104.905 102.231 103.700 102.231 1.205 9.64 1.469 11.75
3 75 104.685 102.231 103.700 102.231 0.985 27.38 1.469 36.73
4 50 104.675 102.231 103.700 102.231 0.975 24.5 1.469 36.73
5 25 103.130 102.231 103.700 102.231 0.000 12.19 0.899 29.60
6 0 102.650 102.231 103.700 102.231 0.000 0 0.419 16.47
7 25 102.530 102.231 103.700 102.231 0.000 0 0.299 8.97
8 50 107.590 102.231 103.700 102.231 3.890 48.63 1.469 22.10
9 75 107.600 102.231 103.700 102.231 3.900 97.37 1.469 36.73
10 100 107.605 102.231 103.700 102.231 3.905 97.56 1.469 36.73
11 116 107.710 107.710 107.710 107.710 0.000 31.24 0.000 11.75
Total 348.51 247.56 Sqm

At Chinage 0.825 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 105.005 105.005 105.005 105.005 0.000 0.000
2 100 104.575 102.214 103.600 102.214 0.975 7.8 1.386 11.09
3 75 104.125 102.214 103.600 102.214 0.525 18.75 1.386 34.65
4 50 104.235 102.214 103.600 102.214 0.635 14.5 1.386 34.65
5 25 103.030 102.214 103.600 102.214 0.000 7.94 0.816 27.52
6 0 101.990 102.214 103.600 102.214 0.000 0 0.000 10.20
7 25 103.570 102.214 103.600 102.214 0.000 0 1.356 16.95
8 50 107.325 102.214 103.600 102.214 3.725 46.56 1.386 34.27
9 75 107.275 102.214 103.600 102.214 3.675 92.5 1.386 34.65
10 100 107.245 102.214 103.600 102.214 3.645 91.5 1.386 34.65
11 116 107.330 107.330 107.330 107.330 0.000 29.16 0.000 11.09
Total 308.71 249.72 Sqm
At Chinage 0.850 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 104.985 104.985 104.985 104.985 0.000 0.000
2 100 104.465 102.196 103.700 102.196 0.765 6.12 1.504 12.03
3 75 104.385 102.196 103.700 102.196 0.685 18.13 1.504 37.60
4 50 104.285 102.196 103.700 102.196 0.585 15.88 1.504 37.60
5 25 102.800 102.196 103.700 102.196 0.000 7.31 0.604 26.35
6 0 101.650 102.196 103.700 102.196 0.000 0 0.000 7.55
7 25 107.355 102.196 103.700 102.196 3.655 45.69 1.504 18.80
8 50 107.345 102.196 103.700 102.196 3.645 91.25 1.504 37.60
9 75 107.235 102.196 103.700 102.196 3.535 89.75 1.504 37.60
10 100 107.175 102.196 103.700 102.196 3.475 87.63 1.504 37.60
11 116 107.235 107.235 107.235 107.235 0.000 27.8 0.000 12.03
Total 389.56 264.76 Sqm

At Chinage 0.875 Km
Soils HDR
Bottom Bottom
Distance Ground Bottom
Slno Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level Level of Soils
Channel HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 104.600 104.600 104.600 104.600 0.000 0.000
2 100 104.555 102.179 103.700 102.179 0.855 6.84 1.521 12.17
3 75 104.325 102.179 103.700 102.179 0.625 18.5 1.521 38.03
4 50 104.535 102.179 103.700 102.179 0.835 18.25 1.521 38.03
5 25 102.810 102.179 103.700 102.179 0.000 10.44 0.631 26.90
6 0 101.930 102.179 103.700 102.179 0.000 0 0.000 7.89
7 25 107.450 102.179 103.700 102.179 3.750 46.88 1.521 19.01
8 50 107.235 102.179 103.700 102.179 3.535 91.06 1.521 38.03
9 75 107.270 102.179 103.700 102.179 3.570 88.81 1.521 38.03
10 100 107.125 102.179 103.700 102.179 3.425 87.44 1.521 38.03
11 116 107.410 107.410 107.410 107.410 0.000 27.4 0.000 12.17
Total 395.62 268.29 Sqm
At Chinage 0.900 Km
Soils HDR F&F
Bottom Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Depth of Area of F&F Remarks
in Meters Level
Channel Soils HDR F&F Soils (M) (Sqm) HDR (M) HDR (Sqm) F&F (M) (Sqm)
1 116 106.620 106.620 106.620 106.620 0.000 0.000 0.00
2 100 106.755 102.162 103.800 103.500 102.162 2.955 23.64 0.300 2.40 1.338 10.7
3 75 106.775 102.162 103.800 103.500 102.162 2.975 74.12 0.300 7.50 1.338 33.45
4 50 106.735 102.162 103.800 103.500 102.162 2.935 73.88 0.300 7.50 1.338 33.45
5 25 101.790 102.162 103.800 103.500 102.162 0.000 36.69 0.000 3.75 0.000 16.72
6 0 102.080 102.162 103.800 102.162 0.000 0 0.000 0.00
7 25 106.085 102.162 103.800 102.162 2.285 28.56 1.638 20.47
8 50 106.175 102.162 103.800 102.162 2.375 58.25 1.638 40.95
9 75 106.185 102.162 103.800 102.162 2.385 59.5 1.638 40.95
10 100 106.145 102.162 103.800 102.162 2.345 59.13 1.638 40.95
11 116 106.210 106.210 106.210 106.210 0.000 18.76 0.000 13.10
Total 432.53 177.57 Sqm 94.32 Sqm

At Chinage 0.925 Km
Soils HDR F&F
Bottom Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Depth of Area of F&F Remarks
in Meters Level
Channel Soils HDR F&F Soils (M) (Sqm) HDR (M) HDR (Sqm) F&F (M) (Sqm)
1 116 106.620 106.620 106.620 106.620 0.000 0.000 0
2 100 106.645 102.145 103.295 103.295 102.145 3.350 26.8 0.000 0.00 1.150 9.2
3 75 106.715 102.145 103.295 103.295 102.145 3.420 84.62 0.000 0.00 1.150 28.75
4 50 106.775 102.145 103.295 103.295 102.145 3.480 86.25 0.000 0.00 1.150 28.75
5 25 101.850 102.145 103.295 102.145 102.145 0.000 43.5 0.000 0.00 0.000 14.38
6 0 102.820 102.145 103.295 102.145 0.000 0 0.675 8.44
7 25 106.095 102.145 103.295 102.145 2.800 35 1.150 22.81
8 50 106.015 102.145 103.295 102.145 2.720 69 1.150 28.75
9 75 106.345 102.145 103.295 102.145 3.050 72.12 1.150 28.75
10 100 106.155 102.145 103.295 102.145 2.860 73.88 1.150 28.75
11 116 106.240 106.240 106.240 106.240 0.000 22.88 0.000 9.20
Total 514.05 126.70 Sqm 81.08 Sqm

At Chinage 0.950 Km
Soils HDR F&F
Bottom Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Depth of Area of F&F Remarks
in Meters Level
Channel Soils HDR F&F Soils (M) (Sqm) HDR (M) HDR (Sqm) F&F (M) (Sqm)
1 116 106.690 106.690 106.690 106.690 0.000 0.000
2 100 106.620 102.127 103.800 102.127 2.820 22.56 1.673 13.38
3 75 106.720 102.127 103.800 102.127 2.920 71.75 1.673 41.83
4 50 106.770 102.127 103.800 102.127 2.970 73.62 1.673 41.83
5 25 101.830 102.127 103.800 102.127 0.000 37.13 0.000 20.91
6 0 103.140 102.127 103.800 102.127 0.000 0 1.013 12.66
7 25 105.690 102.127 103.800 102.127 1.890 23.62 1.673 33.57
8 50 106.095 102.127 103.800 102.127 2.295 52.31 1.673 41.83
9 75 106.100 102.127 103.800 102.127 2.300 57.44 1.673 41.83
10 100 106.180 102.127 103.800 102.127 2.380 58.5 1.673 41.83
11 116 106.310 106.310 106.310 106.310 0.000 19.04 0.000 13.38
Total 415.97 303.05 Sqm

At Chinage 0.975 Km
Soils HDR F&F
Bottom Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Depth of Area of F&F Remarks
in Meters Level
Channel Soils HDR F&F Soils (M) (Sqm) HDR (M) HDR (Sqm) F&F (M) (Sqm)
1 116 106.590 106.590 106.590 106.590 0.000 0.000
2 100 106.670 102.110 103.800 102.110 2.870 22.96 1.690 13.52
3 75 106.660 102.110 103.800 102.110 2.860 71.62 1.690 42.25
4 50 106.835 102.110 103.800 102.110 3.035 73.69 1.690 42.25
5 25 102.110 102.110 103.800 102.110 0.000 37.94 0.000 21.12
6 0 102.940 102.110 103.800 102.110 0.000 0 0.830 10.37
7 25 105.645 102.110 103.800 102.110 1.845 23.06 1.690 31.50
8 50 106.100 102.110 103.800 102.110 2.300 51.81 1.690 42.25
9 75 106.175 102.110 103.800 102.110 2.375 58.44 1.690 42.25
10 100 106.160 102.110 103.800 102.110 2.360 59.19 1.690 42.25
11 116 106.285 106.285 106.285 106.285 0.000 18.88 0.000 13.52
Total 417.59 301.28 Sqm

At Chinage 1.000 Km
Soils HDR HR
Bottom Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Depth of Area of HR Remarks
in Meters Level
Channel Soils HDR F&F Soils (M) (Sqm) HDR (M) HDR (Sqm) HR (M) (Sqm)
1 116 106.310 106.310 106.310 106.310 0.000 0.000
2 100 106.235 102.093 103.500 102.093 2.735 21.88 1.407 11.26
3 75 106.200 102.093 103.500 102.093 2.700 67.94 1.407 35.17
4 50 106.175 102.093 103.500 102.093 2.675 67.19 1.407 35.17
5 25 99.650 102.093 103.500 102.093 0.000 33.44 0.000 17.59
6 0 100.760 102.093 103.500 102.093 102.093 0.000 0 0.000 0.00 0.000
7 25 104.880 102.093 103.500 102.670 102.093 1.380 17.25 0.830 10.38 0.577 7.21
8 50 106.065 102.093 103.500 102.670 102.093 2.565 49.31 0.830 20.75 0.577 14.43
9 75 106.035 102.093 103.500 102.670 102.093 2.535 63.75 0.830 20.75 0.577 14.43
10 100 106.205 102.093 103.500 102.670 102.093 2.705 65.5 0.830 20.75 0.577 14.43
11 116 106.320 106.320 106.320 106.320 106.320 0.000 21.64 0.000 6.64 0.000 4.62
Total 407.90 178.46 Sqm 55.12 Sqm

At Chinage 1.025 Km
Soils HDR F&F
Bottom Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Depth of Area of F&F Remarks
in Meters Level
Channel Soils HDR F&F Soils (M) (Sqm) HDR (M) HDR (Sqm) F&F (M) (Sqm)
1 116 106.635 106.635 106.635 106.635 106.635 0.000 0.000 0.000
2 100 105.720 102.076 103.700 103.120 102.076 2.020 16.16 0.580 4.64 1.044 8.35
3 75 105.660 102.076 103.700 103.120 102.076 1.960 49.75 0.580 14.50 1.044 26.1
4 50 105.685 102.076 103.700 103.120 102.076 1.985 49.31 0.580 14.50 1.044 26.1
5 25 105.735 102.076 103.700 103.120 102.076 2.035 50.25 0.580 14.50 1.044 26.1
6 0 100.250 102.076 103.700 102.076 102.076 0.000 25.44 0.000 7.25 0.000 13.05
7 25 105.380 102.076 103.700 102.076 1.680 21 1.624 20.30
8 50 105.330 102.076 103.700 102.076 1.630 41.38 1.624 40.60
9 75 106.505 102.076 103.700 102.076 2.805 55.44 1.624 40.60
10 100 106.560 102.076 103.700 102.076 2.860 70.81 1.624 40.60
11 116 106.675 106.675 106.675 106.675 0.000 22.88 0.000 12.99
Total 402.42 210.48 Sqm 99.70 Sqm
EWE Areas Calcuation Sheet
At Chinage 1.050 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 105.770 105.770 105.770 105.770 0.000 0.000
2 100 105.690 102.058 103.700 102.058 1.990 15.92 1.642 13.14
3 75 105.595 102.058 103.700 102.058 1.895 48.56 1.642 41.05
4 50 105.855 102.058 103.700 102.058 2.155 50.63 1.642 41.05
5 25 105.710 102.058 103.700 102.058 2.010 52.06 1.642 41.05
6 0 100.050 102.058 103.700 102.058 0.000 25.13 0.000 20.52
7 25 105.420 102.058 103.700 102.058 1.720 21.5 1.642 20.52
8 50 105.405 102.058 103.700 102.058 1.705 42.81 1.642 41.05
9 75 106.530 102.058 103.700 102.058 2.830 56.69 1.642 41.05
10 100 106.550 102.058 103.700 102.058 2.850 71 1.642 41.05
11 116 106.710 106.710 106.710 106.710 0.000 22.8 0.000 13.14
Total 407.10 313.62 Sqm

At Chinage 1.075 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 106.320 106.320 106.320 106.320 0.000 0.000
2 100 106.020 102.041 103.600 102.041 2.420 19.36 1.559 12.47
3 75 105.830 102.041 103.600 102.041 2.230 58.13 1.559 38.97
4 50 105.910 102.041 103.600 102.041 2.310 56.75 1.559 38.97
5 25 105.860 102.041 103.600 102.041 2.260 57.13 1.559 38.97
6 0 100.745 102.041 103.600 102.041 0.000 28.25 0.000 19.49
7 25 101.215 102.041 103.600 102.041 0.000 0 0.000 0.00
8 50 106.245 102.041 103.600 102.041 2.645 33.06 1.559 19.49
9 75 106.380 102.041 103.600 102.041 2.780 67.81 1.559 38.97
10 100 106.415 102.041 103.600 102.041 2.815 69.94 1.559 38.97
11 116 106.510 106.510 106.510 106.510 0.000 22.52 0.000 12.47
Total 412.95 258.77 Sqm

At Chinage 1.100 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 105.785 105.785 105.785 105.785 0.000 0.000
2 100 105.530 102.024 103.500 102.024 2.030 16.24 1.476 11.81
3 75 105.660 102.024 103.500 102.024 2.160 52.38 1.476 36.90
4 50 105.880 102.024 103.500 102.024 2.380 56.75 1.476 36.90
5 25 105.745 102.024 103.500 102.024 2.245 57.81 1.476 36.90
6 0 100.500 102.024 103.500 102.024 0.000 28.06 0.000 18.45
7 25 101.610 102.024 103.500 102.024 0.000 0 0.000 0.00
8 50 106.190 102.024 103.500 102.024 2.690 33.63 1.476 18.45
9 75 106.325 102.024 103.500 102.024 2.825 68.94 1.476 36.90
10 100 106.395 102.024 103.500 102.024 2.895 71.5 1.476 36.90
11 116 106.485 106.485 106.485 106.485 0.000 23.16 0.000 11.81
Total 408.47 245.02 Sqm

At Chinage 1.125 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 105.660 105.660 105.660 105.660 0.000 0.000
2 100 105.565 102.007 103.200 102.007 2.365 18.92 1.193 9.54
3 75 105.540 102.007 103.200 102.007 2.340 58.81 1.193 29.82
4 50 105.605 102.007 103.200 102.007 2.405 59.31 1.193 29.82
5 25 104.375 102.007 103.200 102.007 1.175 44.75 1.193 29.82
6 0 100.905 102.007 103.200 102.007 0.000 14.69 0.000 14.91
7 25 100.205 102.007 103.200 102.007 0.000 0 0.000 0.00
8 50 105.510 102.007 103.200 102.007 2.310 28.88 1.193 14.91
9 75 105.540 102.007 103.200 102.007 2.340 58.13 1.193 29.82
10 100 105.555 102.007 103.200 102.007 2.355 58.69 1.193 29.82
11 116 105.615 105.615 105.615 105.615 0.000 18.84 0.000 9.54
Total 361.02 198.00 Sqm
At Chinage 1.150 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 105.715 105.715 105.715 105.715 0.000 0.000
2 100 105.585 101.989 103.000 101.989 2.585 20.68 1.011 8.09
3 75 105.515 101.989 103.000 101.989 2.515 63.75 1.011 25.27
4 50 104.235 101.989 103.000 101.989 1.235 46.88 1.011 25.27
5 25 101.765 101.989 103.000 101.989 0.000 15.44 0.000 12.64
6 0 100.215 101.989 103.000 101.989 0.000 0 0.000 0.00
7 25 100.310 101.989 103.000 101.989 0.000 0 0.000 0.00
8 50 105.440 101.989 103.000 101.989 2.440 30.5 1.011 12.64
9 75 105.485 101.989 103.000 101.989 2.485 61.56 1.011 25.27
10 100 105.515 101.989 103.000 101.989 2.515 62.5 1.011 25.27
11 116 105.625 105.625 105.625 105.625 0.000 20.12 0.000 8.09
Total 321.43 142.54 Sqm

At Chinage 1.175 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 106.110 106.110 106.110 106.110 0.000 0.000
2 100 105.905 101.972 103.000 101.972 2.905 23.24 1.028 8.22
3 75 104.840 101.972 103.000 101.972 1.840 59.31 1.028 25.70
4 50 104.890 101.972 103.000 101.972 1.890 46.63 1.028 25.70
5 25 100.765 101.972 103.000 101.972 0.000 23.63 0.000 12.85
6 0 100.140 101.972 103.000 101.972 0.000 0 0.000 0.00
7 25 99.925 101.972 103.000 101.972 0.000 0 0.000 0.00
8 50 105.250 101.972 103.000 101.972 2.250 28.13 1.028 12.85
9 75 105.555 101.972 103.000 101.972 2.555 60.06 1.028 25.70
10 100 105.695 101.972 103.000 101.972 2.695 65.63 1.028 25.70
11 116 105.805 105.805 105.805 105.805 0.000 21.56 0.000 8.22
Total 328.19 144.94 Sqm

At Chinage 1.200 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 106.050 106.050 106.050 106.050 0.000 0.000
2 100 105.880 101.955 103.000 101.955 2.880 23.04 1.045 8.36
3 75 104.795 101.955 103.000 101.955 1.795 58.44 1.045 26.13
4 50 104.865 101.955 103.000 101.955 1.865 45.75 1.045 26.13
5 25 100.165 101.955 103.000 101.955 0.000 23.31 0.000 13.06
6 0 100.530 101.955 103.000 101.955 0.000 0 0.000 0.00
7 25 101.110 101.955 103.000 101.955 0.000 0 0.000 0.00
8 50 105.230 101.955 103.000 101.955 2.230 27.88 1.045 13.06
9 75 105.540 101.955 103.000 101.955 2.540 59.63 1.045 26.13
10 100 105.665 101.955 103.000 101.955 2.665 65.06 1.045 26.13
11 116 105.745 105.745 105.745 105.745 0.000 21.32 0.000 8.36
Total 324.43 147.36 Sqm

At Chinage 1.225 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 106.145 106.145 106.145 106.145 0.000 0.000
2 100 105.995 101.938 103.000 101.938 2.995 23.96 1.062 8.50
3 75 105.055 101.938 103.000 101.938 2.055 63.13 1.062 26.55
4 50 105.185 101.938 103.000 101.938 2.185 53 1.062 26.55
5 25 99.995 101.938 103.000 101.938 0.000 27.31 0.000 13.28
6 0 100.735 101.938 103.000 101.938 0.000 0 0.000 0.00
7 25 101.085 101.938 103.000 101.938 0.000 0 0.000 0.00
8 50 105.240 101.938 103.000 101.938 2.240 28 1.062 13.28
9 75 105.530 101.938 103.000 101.938 2.530 59.63 1.062 26.55
10 100 105.635 101.938 103.000 101.938 2.635 64.56 1.062 26.55
11 116 105.660 105.660 105.660 105.660 0.000 21.08 0.000 8.50
Total 340.67 149.76 Sqm
At Chinage 1.250 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 102.115 102.115 102.115 102.115 0.000 0.000
2 100 101.930 101.920 102.300 101.920 0.000 0 0.010 0.08
3 75 100.210 101.920 102.300 101.920 0.000 0 0.000 0.13
4 50 104.020 101.920 102.300 101.920 1.720 21.5 0.380 4.75
5 25 99.800 101.920 102.300 101.920 0.000 21.5 0.000 4.75
6 0 100.630 101.920 102.300 101.920 0.000 0 0.000 0.00
7 25 100.925 101.920 102.300 101.920 0.000 0 0.000 0.00
8 50 104.895 101.920 102.300 101.920 2.595 32.44 0.380 4.75
9 75 104.970 101.920 102.300 101.920 2.670 65.81 0.380 9.50
10 100 105.020 101.920 102.300 101.920 2.720 67.38 0.380 9.50
11 116 105.115 105.115 105.115 105.115 0.000 21.76 0.000 3.04
Total 230.39 36.50 Sqm

At Chinage 1.275 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 102.140 102.140 102.140 102.140 0.000 0.000
2 100 101.960 101.903 102.200 101.903 0.000 0 0.057 0.46
3 75 102.035 101.903 102.200 101.903 0.000 0 0.000 0.71
4 50 99.395 101.903 102.200 101.903 0.000 0 0.000 0.00
5 25 100.395 101.903 102.200 101.903 0.000 0 0.000 0.00
6 0 101.110 101.903 102.200 101.903 0.000 0 0.000 0.00
7 25 101.415 101.903 102.200 101.903 0.000 0 0.000 0.00
8 50 104.180 101.903 102.200 101.903 1.980 24.75 0.297 3.71
9 75 104.955 101.903 102.200 101.903 2.755 59.19 0.297 7.42
10 100 105.005 101.903 102.200 101.903 2.805 69.5 0.297 7.42
11 116 105.190 105.190 105.190 105.190 0.000 22.44 0.000 2.38
Total 175.88 22.10 Sqm

At Chinage 1.300 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 102.580 102.580 102.580 102.580 0.000 0.000
2 100 102.515 101.886 102.200 101.886 0.315 2.52 0.314 2.51
3 75 102.365 101.886 102.200 101.886 0.165 6 0.314 7.85
4 50 103.110 101.886 102.200 101.886 0.910 13.44 0.314 7.85
5 25 100.955 101.886 102.200 101.886 0.000 11.38 0.000 3.93
6 0 100.465 101.886 102.200 101.886 0.000 0 0.000 0.00
7 25 102.100 101.886 102.200 101.886 0.000 0 0.214 2.67
8 50 104.185 101.886 102.200 101.886 1.985 24.81 0.314 6.60
9 75 104.095 101.886 102.200 101.886 1.895 48.5 0.314 7.85
10 100 103.295 101.886 102.200 101.886 1.095 37.38 0.314 7.85
11 116 103.330 103.330 103.330 103.330 0.000 8.76 0.000 2.51
Total 152.79 49.62 Sqm

At Chinage 1.325 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 103.585 103.585 103.585 103.585 0.000 0.000
2 100 103.505 101.869 102.300 101.869 1.205 9.64 0.431 3.45
3 75 103.410 101.869 102.300 101.869 1.110 28.94 0.431 10.77
4 50 102.685 101.869 102.300 101.869 0.385 18.69 0.431 10.77
5 25 101.525 101.869 102.300 101.869 0.000 4.81 0.000 5.39
6 0 100.845 101.869 102.300 101.869 0.000 0 0.000 0.00
7 25 102.235 101.869 102.300 101.869 0.000 0 0.366 4.58
8 50 103.135 101.869 102.300 101.869 0.835 10.44 0.431 9.96
9 75 103.025 101.869 102.300 101.869 0.725 19.5 0.431 10.77
10 100 103.045 101.869 102.300 101.869 0.745 18.38 0.431 10.77
11 116 103.285 103.285 103.285 103.285 0.000 5.96 0.000 3.45
Total 116.36 69.91 Sqm
At Chinage 1.350 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 103.345 103.345 103.345 103.345 0.000 0.000
2 100 103.640 101.851 102.400 101.851 1.240 9.92 0.549 4.39
3 75 103.635 101.851 102.400 101.851 1.235 30.94 0.549 13.73
4 50 102.635 101.851 102.400 101.851 0.235 18.38 0.549 13.73
5 25 101.685 101.851 102.400 101.851 0.000 2.94 0.000 6.86
6 0 100.855 101.851 102.400 101.851 0.000 0 0.000 0.00
7 25 102.335 101.851 102.400 101.851 0.000 0 0.484 6.05
8 50 103.675 101.851 102.400 101.851 1.275 15.94 0.549 12.91
9 75 103.735 101.851 102.400 101.851 1.335 32.62 0.549 13.73
10 100 103.765 101.851 102.400 101.851 1.365 33.75 0.549 13.73
11 116 103.880 103.880 103.880 103.880 0.000 10.92 0.000 4.39
Total 155.41 89.52 Sqm

At Chinage 1.375 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 103.190 103.190 103.190 103.190 0.000 0.000
2 100 102.915 101.834 102.300 101.834 0.615 4.92 0.466 3.73
3 75 103.260 101.834 102.300 101.834 0.960 19.69 0.466 11.65
4 50 102.540 101.834 102.300 101.834 0.240 15 0.466 11.65
5 25 101.810 101.834 102.300 101.834 0.000 3 0.000 5.82
6 0 101.145 101.834 102.300 101.834 0.000 0 0.000 0.00
7 25 102.195 101.834 102.300 101.834 0.000 0 0.361 4.51
8 50 102.135 101.834 102.300 101.834 0.000 0 0.301 8.28
9 75 103.740 101.834 102.300 101.834 1.440 18 0.466 9.59
10 100 103.785 101.834 102.300 101.834 1.485 36.56 0.466 11.65
11 116 104.100 104.100 104.100 104.100 0.000 11.88 0.000 3.73
Total 109.05 70.61 Sqm

At Chinage 1.400 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 103.005 103.005 103.005 103.005 0.000 0.000
2 100 102.895 101.817 102.200 101.817 0.695 5.56 0.383 3.06
3 75 103.005 101.817 102.200 101.817 0.805 18.75 0.383 9.58
4 50 102.955 101.817 102.200 101.817 0.755 19.5 0.383 9.58
5 25 102.820 101.817 102.200 101.817 0.620 17.19 0.000 4.79
6 0 101.325 101.817 102.200 101.817 0.000 7.75 0.000 0.00
7 25 102.055 101.817 102.200 101.817 0.000 0 0.238 2.98
8 50 102.145 101.817 102.200 101.817 0.000 0 0.328 7.08
9 75 101.565 101.817 102.200 101.817 0.000 0 0.000 4.10
10 100 103.745 101.817 102.200 101.817 1.545 19.31 0.383 4.79
11 116 104.080 104.080 104.080 104.080 0.000 12.36 0.000 3.06
Total 100.42 49.02 Sqm

At Chinage 1.425 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 102.980 102.980 102.980 102.980 0.000 0.000
2 100 102.740 101.800 102.000 101.800 0.740 5.92 0.200 1.60
3 75 103.800 101.800 102.000 101.800 1.800 31.75 0.200 5.00
4 50 102.790 101.800 102.000 101.800 0.790 32.38 0.200 5.00
5 25 101.945 101.800 102.000 101.800 0.000 9.88 0.000 2.50
6 0 101.455 101.800 102.000 101.800 0.000 0 0.000 0.00
7 25 102.055 101.800 102.000 101.800 0.055 0.69 0.200 2.50
8 50 102.305 101.800 102.000 101.800 0.305 4.5 0.200 5.00
9 75 102.205 101.800 102.000 101.800 0.205 6.38 0.000 2.50
10 100 101.265 101.800 102.000 101.800 0.000 2.56 0.000 0.00
11 116 101.350 101.350 101.350 101.350 0.000 0 0.000 0.00
Total 94.06 24.10 Sqm
At Chinage 1.450 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 103.450 103.450 103.450 103.450 0.000 0.000
2 100 103.365 101.783 102.200 101.783 1.165 9.32 0.417 3.34
3 75 103.295 101.783 102.200 101.783 1.095 28.25 0.417 10.43
4 50 102.780 101.783 102.200 101.783 0.580 20.94 0.417 10.43
5 25 101.950 101.783 102.200 101.783 0.000 7.25 0.167 7.30
6 0 101.485 101.783 102.200 101.783 0.000 0 0.000 2.09
7 25 102.075 101.783 102.200 101.783 0.000 0 0.292 3.65
8 50 102.585 101.783 102.200 101.783 0.385 4.81 0.417 8.86
9 75 102.385 101.783 102.200 101.783 0.185 7.12 0.417 10.43
10 100 102.915 101.783 102.200 101.783 0.715 11.25 0.417 10.43
11 116 103.070 103.070 103.070 103.070 0.000 5.72 0.000 3.34
Total 94.66 70.30 Sqm

At Chinage 1.475 Km
Soils HDR
Bottom Bottom Bottom
Distance Ground
Slno Level of Level of Level of Depth of Area of Soils Depth of Area of Soils Remarks
in Meters Level
Channel Soils HDR Soils (M) (Sqm) HDR (M) HDR (Sqm)
1 116 103.220 103.220 103.220 103.220 0.000 0.000
2 100 103.035 101.765 102.000 101.765 1.035 8.28 0.235 1.88
3 75 102.895 101.765 102.000 101.765 0.895 24.12 0.235 5.87
4 50 103.005 101.765 102.000 101.765 1.005 23.75 0.235 5.87
5 25 102.075 101.765 102.000 101.765 0.075 13.5 0.235 5.87
6 0 101.505 101.765 102.000 101.765 0.000 0.94 0.000 2.94
7 25 101.890 101.765 102.000 101.765 0.000 0 0.125 1.56
8 50 102.630 101.765 102.000 101.765 0.630 7.87 0.235 4.50
9 75 102.675 101.765 102.000 101.765 0.675 16.31 0.235 5.87
10 100 101.515 101.765 102.000 101.765 0.000 8.44 0.000 2.94
11 116 101.880 101.880 101.880 101.880 0.000 0 0.000 0.00
Total 103.21 37.30 Sqm
Name of work: GNSS Phase-II – Package No.10/06 - “Investigation, Design & Formation of Mallemadugu Reservoir and Excavation of Kailasagiri Canal from Km
0.000 to Km 65.500 including Construction of CM & CD works and distributory system including field channels to be feed an ayacut of 55000 acres in Chittoor and
Nellore Districts.
Quantity Statement
Excavation of Surplus course -D/S of Spillway (From Apron End)
Soils HDR F&F HR With Control Blasting
Slno Chainage (Km) Distance (M) Area of Soils Area of Soils Area of F & F Area of HR
Quantity (Cum) Quantity (Cum) Quantity (Cum) Quantity (Cum)
(Sqm) (Sqm) (Sqm) (Sqm)
1 0.000 - 324.78 222.26
2 0.025 25 311.73 3,896.68 671.81 12,457.47 462.96 8,565.27
3 0.050 25 409.88 9,020.11 482.15 14,424.53 454.11 11,463.34
4 0.075 25 492.21 11,276.03 316.78 9,986.59 498.40 11,906.36
5 0.100 25 466.49 11,983.69 521.12 10,473.80 348.14 10,581.77
6 0.125 25 456.19 11,533.50 714.90 15,450.31 145.02 6,164.53
7 0.150 25 660.81 13,962.53 459.49
8 0.175 25 688.99 16,872.50 545.88 12,567.13
9 0.200 25 579.61 15,857.50 404.58 11,880.75
10 0.225 25 623.38 15,037.38 397.83 10,030.13
11 0.250 25 581.54 15,061.50 337.00 9,185.38
12 0.275 25 446.41 12,849.38 297.12 7,926.50
13 0.300 25 403.13 10,619.25 478.21 9,691.63
14 0.325 25 391.40 9,931.63 418.42 11,207.88
15 0.350 25 356.14 9,344.25 304.12 9,031.75
16 0.375 25 297.91 8,175.63 352.87 8,212.38
17 0.400 25 294.51 7,405.25 332.93 8,572.50
18 0.425 25 289.61 7,301.50 298.73 7,895.75
19 0.450 25 264.42 6,925.38 258.65 6,967.25
20 0.475 25 252.76 6,464.75 261.30 6,499.38
21 0.500 25 536.81 9,869.62 419.65 8,511.87
22 0.525 25 546.03 13,535.50 442.70 10,779.38
23 0.550 25 437.71 12,296.75 389.06 10,397.00
24 0.575 25 493.88 11,644.88 426.22 10,191.00
25 0.600 25 490.39 12,303.38 447.52 10,921.75
26 0.625 25 492.96 12,291.88 444.15 11,145.88
27 0.650 25 489.74 12,283.75 429.84 10,924.88
28 0.675 25 425.96 11,446.25 365.22 9,938.25
29 0.700 25 393.20 10,239.50 367.75 9,162.13
30 0.725 25 374.70 9,598.75 245.66 7,667.63
31 0.750 25 210.00 7,308.75 241.28 6,086.75
32 0.775 25 232.90 5,536.25 200.54 5,522.75
33 0.800 25 348.51 7,267.63 247.56 5,601.25
34 0.825 25 308.71 8,215.25 249.72 6,216.00
35 0.850 25 389.56 8,728.38 264.76 6,431.00
36 0.875 25 395.62 9,814.75 268.29 6,663.13
37 0.900 25 432.53 10,351.88 177.57 5,573.25 94.32 2,358.00
38 0.925 25 514.05 11,832.25 126.70 3,803.38 81.08 2,192.50
39 0.950 25 415.97 11,625.25 303.05 5,371.88 - 1,013.50
40 0.975 25 417.59 10,419.50 301.28 7,554.13 - - -
41 1.000 25 407.90 10,318.63 178.46 5,996.75 - 55.12 689.00
42 1.025 25 402.42 10,129.00 210.48 4,861.75 99.70 1,246.25 - 689.00
43 1.050 25 407.10 10,119.00 313.62 6,551.25 - 1,246.25
44 1.075 25 412.95 10,250.63 258.77 7,154.87
45 1.100 25 408.47 10,267.75 245.02 6,297.37
46 1.125 25 361.02 9,618.62 198.00 5,537.75
47 1.150 25 321.43 8,530.62 142.54 4,256.75
48 1.175 25 328.19 8,120.25 144.94 3,593.50
49 1.200 25 324.43 8,157.75 147.36 3,653.75
50 1.225 25 340.67 8,313.75 149.76 3,714.00
51 1.250 25 230.39 7,138.25 36.50 2,328.25
52 1.275 25 175.88 5,078.37 22.10 732.50
53 1.300 25 152.79 4,108.37 49.62 896.50
54 1.325 25 116.36 3,364.37 69.91 1,494.12
55 1.350 25 155.41 3,397.12 89.52 1,992.87
56 1.375 25 109.05 3,305.75 70.61 2,001.62
57 1.400 25 100.42 2,618.37 49.02 1,495.37
58 1.425 25 94.06 2,431.00 24.10 914.00
59 1.450 25 94.66 2,359.00 70.30 1,180.00
60 1.475 25 103.21 2,473.37 37.30 1,345.00
Total 540,228.56 344,129.67 70,849.20 50,059.27
ANNEXURE-III
Name of work: GNSS Phase-II – Package No.10/06 - “Investigation, Design & Formation of Mallemadugu Reservoir and Excavation
of Kailasagiri Canal from Km 0.000 to Km 65.500 including Construction of CM & CD works and distributory system including field
channels to be feed an ayacut of 55000 acres in Chittoor and Nellore Districts"

2(C) -Estimate of Surplus course -(D/S of Spillway 0 (Apron Ending) to 1.475 Km)
Rate as per SSR-
Slno Descrption of item Unit Quantity Amount (Rs/-) Remarks
2006-07

Excavation in all soils up to SDR & Stone


1 matrix with machinery including conveyance Cum 100,000 36.50 3,650,000
with a lead of0 to 250 Meters

Excavation in all soils up to SDR & Stone


2 matrix with machinery including conveyance Cum 440,229 56.68 24,952,155
with a lead of 500 Meters

Earth work excavation and depositing on


banks with machinery in Hard disintegrated
3 Cum 344,130 90.69 31,209,120
rock or soft rock of conglomerate including
conveyance with a lead of 500 Meters

Excavation of Fissured and fractured rock


and boulders upto 3 cum in size requiring
4 Cum 70,849 196.98 13,955,875
blasting including conveyance with a lead of
500 Meters
Earth work excavation and depositing as
directed with machinery in hard rock and
5 boulders upto 3 Cum in size requiring Cum 1,400 160.90 225,260
blasting including conveyance with a lead of
500 Meters
Earth work excavation and depositing as
directed with machinery in hard rock and
6 boulders upto 3 Cum in size requiring Cum 48,659 402.75 19,597,521
Control blasting including conveyance with a
lead of 500 Meters

Total 93,589,931
Name of work: GNSS Phase-II – Package No.10/06 - “Investigation, Design & Formation of Mallemadugu Reservoir and
Excavation of Kailasagiri Canal from Km 0.000 to Km 65.500 including Construction of CM & CD works and distributory system
including field channels to be feed an ayacut of 55000 acres in Chittoor and Nellore Districts.
Data as per SSR 2006-07
Rate Analysis for Surplus Course items

Slno Descrption of item Unit Rate Remarks


Excavation in all soils up to SDR & Stone matrix with machinery
1
including conveyance with a lead of 0 to 250 Meters

Excavation in all soils up to SDR & Stone matrix with machinery within a Pg No 10 of
A cum 13.00
radius of 5 m i.e. cut and dump – Basic rate for SS 20B Item No11
CONVEYANCE OF EARTH,SAND&GRAVEL INCLUDING
B
LOADING, UNLOADING &STACKING ON METALLED ROAD
500 meters. cum 40.70 Pg No 198
Deduct loading ,unloading & stacking charges cum
Loading cum 7.90
Un Loading cum 6.50
Stacking charges cum 4.20
C Total Amount for loading ,unloading & stacking charges cum 18.60
D Rate per Cum (A+B-C) cum 35.10
E Add VAT 4% cum 1.40
F Rate per Cum (D+E) cum 36.50
Excavation in all soils up to SDR & Stone matrix with machinery
2
including conveyance with a lead of 500 Meters

Excavation in all soils up to SDR & Stone matrix with machinery within a Pg No 10 of
A cum 13.00
radius of 5 m i.e. cut and dump – Basic rate for SS 20B Item No11
CONVEYANCE OF EARTH,SAND&GRAVEL INCLUDING
B
LOADING, UNLOADING &STACKING ON METALLED ROAD
500 meters. cum 60.10 Pg No 198
Deduct loading ,unloading & stacking charges cum
Loading cum 7.90
Un Loading cum 6.50
Stacking charges cum 4.20
C Total Amount for loading ,unloading & stacking charges cum 18.60
D Rate per Cum (A+B-C) cum 54.50
E Add VAT 4% cum 2.18
F Rate per Cum (D+E) cum 56.68

Earth work excavation and depositing on banks with machinery in Hard


3 disintegrated rock or soft rock of conglomerate
Pg No 10 of
Excavation in H.D.R-I & II Rs: 19.50/Cum Cum 19.50 Item No11
CONVEYANCE
500 meters. cum 91.60
Deduct loading ,unloading & stacking charges 23.90
Rate per Cum cum 87.20
Add 4% VAT 3.49
Total 90.69
Excavation of Fissured and fractured rock and boulders upto 3 cum in
4
size requiring blasting including conveyance with a lead of 500 Meters
Sl no 251 18.a.I Fissured and fractured rock and boulders upto 3 cum in
A cum 121.70
size requiring blasting including stacking
B Add Conveyance 500 Meters lead cum 91.60
C Deduct loading ,unloading & stacking charges 23.90
D Rate per Cum (G+H-I) cum 189.40
Add 4% VAT 7.58
Total 196.98

Earth work excavation and depositing as directed with machinery in


5 hard rock and boulders upto 3 Cum in size requiring Control blasting
including conveyance with a lead of 500 Meters
Rate as per ENC lr No.ENC (1)/DCE(GD5)/OT1/AEE1/EPC works,Dt
08.0102016 for (IRR-DAW-15(b)) with lead up to 1 km and all lifts cum 391.06
Deduct 1/2 km Conveyance rate as per SSR 2006-07(i.e 95.40-91.60) cum 3.8
Rate Per Cum cum 387.26
Add 4% VAT 15.49
Total 402.75