Professional Documents
Culture Documents
1
Versus
APL Yashomanagal Devclopers
(Greenficlds Phase-.I) Respondents
Final Order
9th N1arch 2018
Factual Matrix.
3
complainants? Nos.3,10,11,13,
^14
& 77.
REASONS
5. Mr.N{ahadeo Dattu Nalawade has filerl p.rurshis marked Exh. l Ior the
purpose of identilication to show that tht' above named comPlainants' .ase
4
may be treatcd as withdrawn. Hence, it is llecessary to dismiss the r:ase of the
aforesaid complainants as dismissed for wanL of prosccution. The practice of
involving the others as comPlainants without their consent, knowledge and
active participation, is hereb;' deprecaterl.
Misioinder of parties:
6. N{iss. Charu Kamboj u'ants rcfund of her amount bccause she wants to
withdra\a,from the project. The conterlts of the comPlaint do show that the
complainants want to continue in thc ProiBct and they claim intcrcst on their
investment for delayed possession. Nlaterial facts must bc Pleaded and dren
proved is the elementary rulc of law in civil matters. ln viert'of this, I find it
difficult to decide the case of Miss. Charu Kamboj with other comPlainants
.I
which is quite distinct ftom the casc of other coml.rlainants. c'chnically, it
amounts to misjoinder of parties ancl herlce, it is neccssdry to dismiss her case
by giving her liberty to file another case for getting refund of her amount.
2. Internal roads:
Thc respondents agree fo comPlete the construction of internal roads
with BT Surlace Layer within 30 clays. Thc resPondents are directed to
5
complete if, as agreed.
3. Amenities:
'I
he rcspondents agree to provide all the amenities like swimming pool,
club house, Childrcn plav area, tree plantation, street lights by August 2018. lf
they have not provided, the same be provided rvithin next 4 months.
the complainants complain that the solar water heater svstem is not
provided. The respondents agree that they agreed to provide solar h'ater
heater system approved by Covernment but Government has not approvcd
any system as such ancl therefore, water geysers have been installecl in the
units. The respondcnts to take steps for fitting of solar water heating system
approvecl by the Government within 2 months of according approval by Govt.
as agreed. Thereafter, they are entitled to remove the individual watcr
geysers.
6
8. Electrical meters:
The electric meters have not been provided in some flats and common
area. The respondents agree to take three phase meter for comrnon area and to
provide electric meters to all the units. The respondents are directed to take
immediate steps for taking three phase supply and install the meter for
common area. They shall provide electric meters to the units before handing
over their possession. Respondents shall provide mete.rs lo the units
possessed by complainants within 15 days from dris order, if not provided
earlier.
The respondents have applied for checking the plinth and drerea{ter
they shall apply for occupation certificate. The respondents are directed to do
the needful at the earliest.
7
-t2/2013
6 I'ratiksha A-101
Waman
8 Vijay F-302 72/201,3
Gheh,ari
9 Dhiraj A-105 12/201.3
Mane
.10
Akash F-103 12/ 2013 -No-
Mahali
.ll Ninral.r G-302 12/ 2O1i -No-
r
Bhatia
1t Vilas Rane E-305 Yes 06/2015 No
14 Datta E-301 No 09 / 2011 No
Ghare
15 Itahul Patil E-204 09 201.1 Ycs
17 Ralcndra D-202 Yos 72/ 2013 No
Sa!vant
23 Sanjav c-302 Yes 12/2013 Yes
Chavan
Delayed project:
.10. Thc above hformation discloses the lact that except complainant No.
14, Datta Ghare, all other complainants hav('received fit out possession of
their respcctive flats. It is fact t}Iat Section 3(2)(i) of the Maharashtra
8
Ownership Flabs Act, 1963 provides that the promoter shall not allow persons
to enter into possession until the completion certificate is given. Similarly, it
provides that no persons shall take possession of the flat until the completion
certificate is duly given by dre legal authority. In view of this provision the fit
out possession cannot be treated as the legal possession. However, the
distinction has to be made in respect of complainanL nos. ^1,2, 1, 5, -12,78,9,1,5
and 23 because after taking the fit out possession, they have actually been
occupying theh flats. Therefore, I find thaL these persons are not entitled to get
any relief under Section 18 of RERA. So far as the complainant nos. 3,70,11,
13, -14, & 17 are concerned, they have not actually occupied their flats. They
have filed Affidavit to this effect. Hence, to this extend, I hold that the
respondents have failed to deliver possession of their flals on lhe agreed dates
and therefore, I record my finding to this effect.
13. The complainant no. 3 Mr. Kamble filed the Affidavit and produced the
statement oI payment marked Exh. 2 for the purpose of identi{ication along
with it. The agreed date for delivery of possession of his flat is 31st January
2014. He paid Rs. 22,85,900/ - towards the consideration of the flat before the
said date. Hence he is entitled to get the interest on his investment Irom
01.02.2014.
14. Complainant no. 10 Akash Mohali was entitled to get the possession of
his flat by 31.12.2013. But he paid some amount even thereafter as it reflected
in the statement marked Exh.3. He paid Rs. 18,45,635/- before the agreed date
of possession. He is entitled to get the interest on it ftom lst January 2014 and
remaining amount shown in Exh.3 paid lowards the consideration shall carry
the interest ftom the respective dates of their payment.
9
15. Complainant no. 11, Nirmala Bhatia was entitled to get the possession
of her flat by 31,.12.2013. FIer statement of payment Exh.4 shows that before
the agreed date of possession, she paid Rs. 16,53,96O/-. This amount shall
carry the interest from 1st lanuary 2014 and the remaining amount shown in
Exh,4 shall carry the interest lrom the date of their respective payments.
16. Complainant no.13, Vilas Rane was enritled to get possession of his flat
by 30th June 2015. The statement of payment submitted by him marked Exh.5
shows that he paid Rs. 21,05,835/- towards consideration of the Ilat before the
agreed date of possession. He is entitled to get interest of it from 0'1.07.2075
onwards.
1,7. The complainant no. 14, Datta Ghare was entitled to get possession of
his flat by 13th September 2014. He has submitted statement of payment
marked Exh.5 showing that he paid Rs. "17,62,203 / - before the said date.
Hence, he is entitled to get the interest on this amount from 01.07.2014. He
paid Rs. 01,70,536/- on '11.."12.2014, hence, he will get the interest on this
amount from the said date.
18. Complainant no. 17, Rajendra Sawant was entitled to get possession by
30th June 2015. His statement of payment marked Exh.7 shows that he paid
Rs.79,73,347 / - before the said date. Hence, he is entitled to get the interest on
this amount from 1.7.2015.
19. Complainant nos.3,10,11,13,14,17 are entided to get simple interest on
their investment at prescribed rate. Prescribed rate is 2% above the current
highest marginal cost of lending rate of SBI which 'is 8.05% Irom the above
mentioned dates till Ltre legal possession of their flats are handed over. Hence
the order.
Order
1. The respondents shall do as directed in para number 8 of this order.
10
4. Respondents shall pay the complainants Rs.20,000/ towards the cost of
the complaint.
5. Respondents shall remove the balconies of one BHK flats which are not
in sanctioned plan. If plan is revised, they be properly covered to have
privacy of the allottees.
6. The complaint of the complainant no. 12 Charu Kamboj is dismissed,
however, she is permitted to file another complaint on the same cause
of action under section 18 oI RERA.
(B,D
9\ r
s)
Mumbai. Member & Adjudicating Officer
Date:09.03.2018 MahaRERA, Mumbai.
11
iaD: A-lr Dw-v lthd
Fol-rr AIr clhtl*t n vdrs lti.t Ph-arfloa
H.r xE rct, F *rno - Co6o.n..dcn C.kulrlon Hh
Enlc. lAx VT OGGbrrBt tf,hihtu. 6tslp Drny in0drnbn
a 3t.ll!
UJ
o rosrs7 - uco
tt ,r543
t)
F N]
lJ,,
E
=l
't ,a6T
f o
o z ia{5q
o
o F rir. roazrz rcrr
I z o
1
F o i "Y:.
nafn
!
i
'A!.[ p.yDrtr.r trd. d pr trr drn.nd rnbr 6t[a tE rut.hr Do.d on.ba. Gmd.rhn rth.ut.r, rat t
-'"
(!-
.!.+
,- .v
o irq sd o
,.
d
G
t EXIBIT IB'
E S I
t{rE.: Nkm.l. tunrr shrtl. & (unarxrrhr.l.l rhali.
Prol.cl: All. GE.rrl.ldr rt V.d!ton Mrv.l, P!n._412106
t&r6FehtuhLroDdld
t.. a,
0.
''1,
a
F tr
lGm:D.tlr Mrftip.ti Gh-€
Prol€d alph. Grcelfi€ldr v.dt.oi - fl.i tlol
tnr09, lu!!
3 6l mr1 8n5vr llit3 r]16207 1316207 l2t6 518743.15E4
I r:r:s
7 1x/JnlaM 585275 1565 52D 5!70 1G3 l87t.4ri!7
8 LLlt2ln.t4 58527{ 1564 l7st6 rD5$ 1(E3 50n0.15(xa
sut Tot l t9!2,l9 s9n2 2211' tm rm) ,9a51.02L
c ln cese af
Iotri P.IHI! ,Ed€: E 2l6i[99
the respondent aSrees to return the principalamount along with the interest mentioned
above tilldate and wishes to cancelthe agreement I hereby declare that we willatreeto do 50.
ln case the respondent do€sn't aSree to aancel the aSreerE€nt and wishes to hMdover th€ complcte
ffat we wlsh to recelve comp€nsatlon of Rr. t,79,{5, as lnlerest amount tlll 3F Oct 2017 3nd
thereafter monthlv interest a mount o{ R3. 21,325 till such timc flat construction ls complet€ e nd
the Occupancy certifrcate is received and flat rs handed overto us le8ally.
o)
l-tL Plece: Hyderabad
\O, oate:16rh oct 2017
Datta Ghar€
E On 8€half of
oatta MahipatiGhare
a i7ts.! o
4 ,|,: F]
,t'At4OfrA.R PEDDY