Professional Documents
Culture Documents
CAST-IN-PLACE CONCRETE
PART 1 – GENERAL
A. This Section establishes general criteria for materials, mixes and placement of
concrete as required for this and other related sections of these specifications.
C. The work also includes constructing expansion joints, construction joints, water
stops and corrosion protection for cast-in-place concrete.
D. Unless otherwise noted, all reinforced concrete exterior surfaces below finish
grade shall be protected either per item 1 or per item 2, as described below: See
Figure 1.
2. For all other structures not covered in item 1 above, apply (Liquid)
Waterproofing per Section 07100 for all surfaces up to finish grade.
4. All concrete structures which depend for their stability mainly upon the
friction developed between their bottom surfaces and soil or blinding
concrete (such as thrust blocks) shall not be waterproofed (liquid or
membrane). The concrete encasement for electrical and telecom duct
banks shall also not be waterproofed.
E. Related Work:
A. Codes and Standards: Comply with the provisions of the following codes,
specifications and standards, except as otherwise shown or specified.
10. Where provisions of the above codes, specifications, and standards are in
conflict with RC Structural Code, the most stringent provisions shall
govern.
B. Concrete Testing: Materials and installed work may require testing and retesting,
as directed by the Royal Commission, at any time during the progress of the
work. Allow free access to material stockpiles and facilities at all times.
2. For portland cement, sample the cement and determine its properties by
the methods of test of ASTM C 150.
1.3 SUBMITTALS
B. Samples:
C. Mock-Ups:
b. Column section, approximately 1.5m high and not less than 300mm
diameter for round sections and not less than 300mm in least
dimension for rectangular sections, unless otherwise shown.
Chamfer exposed edges of rectangular sample columns as
required.
d. Pan-formed section using at least two pan form units. Sets units to
illustrate method of blending exposed pan joints.
1. Submit copies of laboratory test reports for concrete materials and mix
design tests or other certificates for concrete.
E. Material Certificates:
G. Delivery Tickets: Furnish copies of delivery tickets for each load of concrete
delivered to the site. Provide items of information as specified.
H. Provide batch tickets for each batch of job-site mixed concrete, as specified.
TABLE 2.1A
ADDITIONAL REQUIREMENTS
Alkalis (Na2O + 0.658K2O) (see Note 2 below) 0.6% Maximum 0.6% Maximum
Tricalcium Aluminate (3CaO.Al2O3) 5.0% Maximum 8% to 14%
Tricalcium Silicate (3CaO.SiO2) 40% to 60% 40% to 60%
Tetracalcium Aluminoferrite (4CaO.Al2O3.Fe2O3) 15% Maximum 15% Maximum
4. Use only one brand of cement for each required type throughout the
project, unless otherwise acceptable to the Royal Commission.
B. Cement may be accepted on the basis of a manufacturer’s mill certificate that the
cement furnished meets the physical and chemical requirements of ASTM C 150.
The Royal Commission reserves the right, to sample and conduct such tests on
cement as it deems necessary for compliance with the specifications.
C. Aggregates:
1. Fine Aggregate: Clean, sharp, natural sand free from loam, clay lumps, or
other deleterious substances and with rounded or sub-rounded particles.
Fine aggregate shall be selected to comply with the requirements of
ASTM C 33 and test requirements therein and with requirements specified
in Table 2.1B below (Natural sand may need to be washed with potable
water to achieve these requirements):
TABLE 2.1B
FINE AGGREGATE REQUIREMENTS
TABLE 2.1C
COARSE AGGREGATE REQUIREMENTS
50 100 --
25 40 – 80 100
16 30 – 55 55 – 90
9.5 25 – 50 40 – 65
4.75 20 – 40 30 – 50
0.60 15 – 33 10 – 25
0.30 6 – 17 5 – 15
0.15 0–6 0–8
75 Microns 0–1 0–2
2. Fly ash shall conform to ASTM C 618 requirements for Class F fly ash.
To ensure durability of produced concrete, the following tests shall be carried out.
A. Salt Limits: The total acid soluble chloride ion in hardened concrete as
determined by ASTM C 1152 at 28 days shall not exceed 0.13% by weight of the
cement. The total soluble sulfate salt expressed as S04, as determined by BS
1377, shall not exceed 4.0% by weight of the cement.
C. Ice Content: The amount of ice batched shall be sufficient to provide concrete
meeting maximum temperature requirement of 25°C at the point of discharge.
B. Non shrink cementitious grout shall be used for static loading and non-shrink
epoxy grout shall be used for machinery or vibrating equipment.
A. Provide moisture barrier cover over prepared base material. Use membrane
sheet moisture barrier consisting of multiple layers of asphalt-saturated felt, glass
fiber reinforcement, and inner plastic core materials, total 3mm thick and
weighing not less than 3 Kgs/m2. Use only materials which are resistant to decay
when tested in accordance with ASTM E 154.
B. Provide 200 micron thick polyethylene sheets under all concrete foundations and
slabs on grade, if directly placed on soil. If placed on blinding concrete, provide
Waterproofing or Membrane Waterproofing as described in this specification
and/or shown on the contract drawings.
2. Provide silicon carbide grits as abrasive aggregate for non-slip finish. Use
material that is factory-graded, packaged, rustproof, and unaffected by
freezing, moisture, and cleaning materials.
3. Provide any of the above for dry shake application for heavy-duty wear-
resistant finish at Contractor’s option.
B. Burlap cloth made from jute or kenaf, weighing approximately 290 grams/m2 and
complying with AASHTO M182, Class 3.
1. Composition:
3. Strength:
4. Water Content: Use the minimum net water content necessary to properly
place the concrete mixture. The net water content in the mix shall include
both the water added to the mix and the surface water in the aggregates,
but does not include the moisture absorbed by the aggregates. Water
content in concrete to be placed in water may be sufficient to produce a
concrete having a slump greater than prescribed in paragraph 2.9H
providing it does not exceed 160 mm.
9. Inspection: Any admixture and the cement proposed for use shall be
selected well in advance of concrete placing and the Contractor shall
provide facilities satisfactory to the Royal Commission for the ready
procurement of adequate test samples.
B. Provide the current mix design with the following data to the Royal Commission.
C. Submit written reports complete with 7 and 28 day strength tests to the Royal
Commission of each proposed mix for each type of concrete at least 15 days
prior to start of work. Do not begin concrete production until mixes have been
reviewed by the Royal Commission.
D. Laboratory Trial Batches: Laboratory trial batches in accordance with ACI 211.1
shall be used to select concrete proporations, prepare test specimens in
accordance with ASTM C 192 and conduct strength tests in accordance with
ASTM C 39, as specified in ACI 318.
E. Field Experience Method: When field experience methods are used to select
concrete proportions, establish proportions as specified in ACI 318.
1. After sufficient experience and test data become available from the job
use ACI 214 methods of evaluation in accordance with ASTM C 94.
H. Slump Limits:
Without Superplasticizer:
75 mm 100 mm 40 mm 140 mm
With Superplasticizer:
75 mm 125 mm 40 mm 165 mm
The main margin for error can only be used for a maximum of one
truckload out of ten consecutive truckloads of concrete. Immediately,
when concrete slump exceeds the working limit, the concrete supplier
shall be requested to make proper adjustment.
J. Unit Weight: Unit weight of fresh concrete shall not be less than 2400 kg/m3 as
determined by ASTM C 138.
K. Air Content: Air content of fresh concrete shall not exceed 2% as determined by
ASTM C 173.
A. General:
B. Job Site Mixing: When job site mixing of concrete is permitted, mix all materials
for concrete in an acceptable drum type batch machine mixer. For mixers of one
cubic meter, or smaller capacity, continue mixing at least 1½ minutes, but not
more than 5 minutes after all ingredients are in the mixer, before any part of the
batch is released. For mixers of capacity larger than one cubic meter, increase
the minimum 1½ minutes of mixing time by 15 seconds for each additional cubic
meter, or fraction thereof. Do not exceed the catalog rating or nameplate
capacity for the total volume of materials used per batch. Equip the mixer with
automatic controls, or semi-automatic controls if acceptable, for proportioning
materials and the proper measured quantities. Do not exceed 30 minutes total
elapsed time between intermingling of damp aggregates and cement to the
discharge of the completed mix.
1. Provide a batch ticket for each batch discharged and used in the work,
indicating the project identification name, number, date, mix type, mix
time, quantity, and amount of water introduced.
C. Ready-mix Concrete:
2. Tolerance in Slump: Provide slump of not more than the values as herein
specified, in lieu of ASTM C 94 Section 6.1. Comply with other criteria of
ASTM C 94 Section 6.
3. Mixing and Delivery: Delete the references for allowing additional water to
be added to the batch for material with insufficient slump. Addition of
water to the batch will not be permitted as specified in ASTM C 94 Section
10.7. In addition to the requirements of ASTM C 94 Section 10.7, when
the air temperature is between 29° and 35°C, reduce the mixing and
delivery time to 60 minutes. When a truck mixer is used for the complete
mixing of the concrete, begin the mixing operation within 30 minutes after
the cement has been intermingled with the aggregates.
B. During the placing of concrete, the Quality Control Supervisor shall provide for
continuous inspection of delivered concrete and other concrete construction
activities in accordance with ACI SP-2 Manual of Inspection and CIRIA SP-31
Guide to Concrete Construction.
1. Perform sampling and testing for field quality control during the placement
of concrete, as follows.
3. Slump: ASTM C 143; one test for each concrete load at point of
discharge.
a. Cast and store one set of cylinders for laboratory cured test
specimens and one set of field- cured test specimens as specified
in ASTM C 31.
6. Compressive Strength Tests: ASTM C 39; one set for each 100 m3 or
fraction thereof, of each mix design placed in any one day or for each
400m2 of surface area placed; 2 specimens tested at 7 days, 3 specimens
tested at 28 days, and one specimen retained in reserve for later testing if
required.
a. When the frequency of testing will provide less than 5 strength tests
for a given mix design, conduct testing from at least 5 randomly
selected batches or from each batch if fewer than 5 are used.
8. Appendix 2 lists the description and frequency of the tests that the
Contractor is required to perform on this project.
D. Additional Tests:
1. The testing service will make additional tests of in-place concrete when
test results indicate the specified concrete strengths and other
characteristics have not been attained in the structure, as directed by the
Royal Commission. The testing service shall conduct tests to determine
the strength and other characteristics of the in-place concrete by
compression to tests on cored cylinders complying with ASTM C 42, or by
load testing specified in ACI 318, or other acceptable non-destructive
testing methods, as directed.
1. Do not use concrete delivered to the final point of placement which has
slump, temperature or total air content outside the specified values.
The Contractor Quality Control shall assure the following by providing a signed
item checklist to the Royal Commission.
2. The unconfined free fall distance of concrete shall not exceed one meter.
1. Handle concrete from the point of delivery and transfer to the concrete
conveying equipment and to the locations of final deposit as rapidly as
practicable by methods which will prevent segregation and loss of
concrete mix materials.
1. Concrete mix shall not be deposited into forms from chutes, hoppers and
buckets at a free fall height greater than one meter above horizontal
formwork and one meter above bottom at vertical formwork.
1. The fall of the concrete from the chute shall be kept to a minimum height
to the top tier of ducts to minimize floating effects.
2. Placing of the concrete should start at one end, where the ducts are
terminated in a manhole or where the riser is securely restrained at the
equipment pad.
3. The concrete shall be placed around the ducts as soon as possible after
they have been placed to protect them from mechanical damage.
6. If a trench jack and wedges were used to secure the ducts, the wedges
shall be removed before the concrete sets and the voids left by them filled
with concrete and spaded.
4. Bring slab surfaces to the correct level with a straight edge and strike off.
Use bull floats or derbies to smooth the surface, leaving it free of humps or
hollows. Do not sprinkle water on the plastic surface. Do not disturb the
slab surfaces prior to beginning finishing operations.
G. Bonding:
2. Prepare for bonding of fresh concrete to new concrete that has set but is
not fully cured, as follows:
1. When hot weather conditions exist that would seriously impair the quality
and strength of concrete, a procedure shall be submitted for proposed
methods for compliance with hot weather concreting including delivery,
placement, curing and protection guidelines of ACI 305R.
I. Underwater Placing:
3.5 JOINTS
B. Construction Joints:
C. Waterstops:
1. As-cast rough form finish is permitted for deformed concrete surfaces that
are to be concealed in the finish work or by other construction, unless
otherwise indicated.
2. Standard rough form finish shall be the concrete surface having the
texture imparted by the form facing material used, with tie holes and
defective areas repaired and patched and all fins and other projections
exceeding 6 mm in height rubbed down or chipped off.
1. Provide as-cast smooth form finish for formed concrete surfaces that are
to be exposed-to-view, or that are to be covered with a coating material
applied directly to the concrete, or a covering material bonded to the
concrete such as waterproofing, dampproofing, painting, or other similar
system.
2. Combine one part portland cement to 1½ parts fine sand by volume, and
mix with water to the consistency of thick paint. Blend standard portland
cement and white portland cement, amounts determined by trial patches,
so that the final color of dry grout will closely match adjacent concrete
surfaces.
F. Bridge Structures:
3. Floor Finishes (Generator and Control Houses): Strike off and vibrate the
surface of concrete, work to force coarse aggregate away from surface,
screed to a true even surface, float and steel trowel to a hard dense,
smooth surface free from tool marks, granular areas or other
imperfections. Do not dust with any material to absorb surface water.
Tool exposed edges, if any, a 6 mm radius.
A. Steel trowel the final finished surfaces outside bearing areas after wood floating
to plan elevation. Where bridge shoes and bearing plates or slabs are to be
placed directly upon finished concrete bearing areas, the concrete shall be
placed 3 mm higher than the finish elevation shown on the plans. The bearing
pads shall be 75 mm larger than the bridge seat to be installed. After the
concrete has taken final set, grind the bearing areas to a uniform level surface at
the finish elevation. The bearing surface shall not vary more than 2 mm (+ 0.5
mm from a true plane).
A. Scratch Finish:
B. Float Finish:
1. Apply float finish to monolithic slab surfaces that are to receive trowel
finish and other finishes as hereinafter specified, and slab surfaces which
are to be covered with membrane or elastic roofing, or sand bed terrazzo,
and as otherwise shown on contract drawings or in schedules.
2. After placing concrete slabs, do not work the surface further until ready for
floating. Begin floating when the surface water has disappeared or when
the concrete has stiffened sufficiently to permit the operation of a power-
driven float, or both. Consolidate the surface with power-driven floats or
by hand-floating if area is small or inaccessible to power units. Check and
level the surface plane to a tolerance not exceeding 6 mm in 3 m when
tested with a 3 m straightedge placed on the surface at not less than 2
different angles. Cut down high spots and fill all low spots. Uniformly
slope surfaces to drains. Immediately after leveling, refloat the surface to
a uniform, smooth, granular texture.
C. Trowel Finish:
2. After floating, begin the first trowel finish operation using a power-driven
trowel. Begin final troweling when the surface produces a ringing sound
as the trowel is removed over the surface.
E. Chemical-Hardener Finish:
3. After curing, lightly work the surface with a steel wire brush, or an abrasive
stone, and water to expose the non-slip aggregate.
2. Apply dry shake materials for colored wear-resistant finish at the rate of
not less than 30 kilograms per 10 square meters, unless greater amount is
recommended by the material manufacturer.
THE BELOW FINISH FOR SLABS IS “SPECIAL” AND THE TYPE AND
GRADATION OF AGGREGATES MUST BE SPECIFIED UNDER THE
“FLOOR FINISH MATERIALS” ARTICLE.
1. Apply exposed aggregate finish to slabs, stairs, and other areas as shown
on the contract drawings or in schedules.
3. After the concrete has taken its initial set, expose the surface aggregates
using a water fog-spray and fiber-bristle brooms to remove the surface
matrix. Expose the coarse aggregate approximately 3 mm or more to
match the Royal Commission's sample, but not so deep as to displace the
bond of the aggregate to the matrix.
4. After the concrete has taken its final set, apply a weak acid wash to clean
the exposed aggregate surfaces. Thoroughly neutralize and flush the acid
wash from the finish surfaces. Protect all other adjacent construction and
finishes from damage due to the acid wash; repair to replace damaged or
defaced work as directed by Royal Commission.
A. General:
1. Protect freshly placed concrete from premature drying and excessive cold
or hot temperature, and maintain without drying at a relatively constant
temperature for the period of time necessary for hydration of the cement
and proper hardening of the concrete.
2. Start initial curing as soon as free moisture has disappeared from the
concrete surface after placing and finishing. Keep continuously moist for
not less than 72 hours.
B. Curing Methods:
a. For curing, use only water that is free of impurities which could etch
or discolor exposed, natural concrete surfaces.
1. Initially cure unformed surfaces, such as slabs, floor topping, and other flat
surfaces by moist curing.
1. Provide concrete fill for steel pan stair treads and landings and associated
items. Cast-in safety inserts and accessories as shown on contract
drawings. Screed, tamp, and finish concrete surfaces as scheduled.
B. Reinforced Masonry:
1. Provide concrete grout for reinforced masonry lintels and bond beams
where indicated on contract drawings and as scheduled. Maintain
accurate location of reinforcing steel during concrete placement.
C. Filling-In:
1. Fill-in holes and openings left in concrete structures for the passage of
work by other trades, unless otherwise shown or directed, after the work of
other trades is in place. Mix, place and cure concrete as herein specified,
to blend with in-place construction. Provide all other miscellaneous
concrete filling shown or required to complete the work.
1. Repair and patch defective areas with cement mortar immediately after
removal of forms, but only when directed by the Royal Commission.
2. Cut out honeycomb, rock pockets, voids over 12 mm diameter, and holes
left by tie rods and bolts, down to solid concrete but, in no case, to a depth
of less than 25 mm. Make edges of cuts perpendicular to the concrete
surface. Before placing the cement mortar, thoroughly clean, dampen
with water and brush-coat the area to be patched with neat cement grout.
3.12 DEFICIENCIES
C. Defective Work:
1. Water reducing admixtures shall be used as required to meet the limits specified
in this table and the required slump.