SCHEDULE OF QUANTITIES

Item No Brief Item Description Unit Qty Rate(Rs) Amount(Rs)

CIVIL WORKS FOR THE APPROACH ROAD

PART-A-EXCAVATION AND BACK FILLING

Earthwork in excavation and back filing in all types of soil, moorum


(hard, compacted or soft), rock, boulders, quartz etc. And fill
materials or any other debris etc. at depths as specified below in
foundations of structures and equipment, pipe trenches, tunnels,
A-1( a)
sewer lines, drains, basement cellars, etc. to required levels and
grades and dressing complete in all respect as per the specifications
and directions of the Engineer in both dry and
Wet conditions including necessary pumping/bailing out of water,
slush removal etc. And transporting the excavated materials to
spoil dumps/fill areas within a lead of1 Km at all heights and
descents including dozing, levelling at the site of filling all as
directed by the Engineer all tools plant and labour complete in all
respect (authorised working space, benching and side slopes for
the excavation will be measured and paid under this item.

(Note for item A-1(a)


This item will be operated upon that category of strata which can
be excavated with reasonable application of hydraulic excavator.
Soil report is attached for reference purpose only.

i) up to 1.0m depth below EGL Cum 2200.00

Same as in item A-1(a) but for excavation done at all depths with
A-1( b) the help of excavator provided with hydraulically operated rock
breaker ranging aboveEX-300uptoEX-700 an equivalent or for
excavation done by any other mechanical means as approved by
the Engineer, all tools, plant and labour complete in all respect:

i) Quantity considered up to EX-300 Cum Rate only

ii) Quantity considered from EX-300 to EX-700 Cum Rate only


SameasitemA-1(a),but for excavation done manually as approved
A-1( c) By the Engineer, with all tools, plant and labour complete in all
respect:
i) upto 2m depth below EGL Cum Rate only
ii) exceeding 2m depthupto6m depth below EGL Cum Rate
only
CUM 4500
Backfilling in all positions and heights and descents in
foundation pits, pipe trenches, tunnels, sewer lines, around
foundations and structures, in plinth etc. with approved soil
obtained within a lead of 1km including reclaiming from
spoil heaps at all heights, or reclaiming from dump at all
A-2 depths, transporting, depositing and dressing complete in all
respect all as per drawings, specifications and directions of
the Engineer, all tools, plant and labour complete in all
respect:

Cum Rate only


a)mass back filling including dozing, levelling, dressing and
compaction as per specification complete in all respect as
directed by the Engineer/ Consultant

Rate
b)back filling in layers not exceeding 300mm thickness Cum only
including dozing, levelling, dressing and compacting
complete in all respects as directed by the Engineer

Cum Rate
c) plinth filling in layers of 150mm thickness where only
special compaction is required including water in
gland consolidating by mechanical means as per
specification and directions of the Engineer.

A-3 Dozing, dressing and levelling of earth/plant debris/slag Cum Rate


dumped on ground or in excavated pit/areas of fill as per only
directions of the Engineer, all tools, plant and labour
complete in all respect

Extra o v e r i t e m N o . A-1(a), A-1(b), A-1(c), A-1(d) for


disposal of excavated material

A. Within Works
Cum Rate
a) foraleadbeyond1kmbutnotexceeding4km only
A-4
Cum Rate
b) for a lead beyond 4km but not exceeding 8km only.0.0

B. Outside Works
Cum Rate only
a)For a lead up to 10km.

Cum Rate only


b)For a lead beyond 10km up to 15km

c)For a lead beyond 15km up to 20km Cum Rate only

d)For a lead beyond 20km up to 25km Cum Rate only

Cum Rate only


e)For a lead beyond 25km up to 30km
Note for item A-4
The lead shall be measure don actual route of haulage.
However, the route Shall be approved by the Engineer prior
to commencement of work.
PLAIN & REINFORCED CEMENT CONCRETE
B B 1.SuffixA,B,C andD tothegradeof concreteindicatetheuseof size of
- The graded coarse stone aggregates in concrete as
1 follows:
Note:A-75mm and downgraded stone aggregate
B-40mmanddown graded stone aggregate
C-20mmanddown graded stone aggregate
D-10mmanddown graded stone aggregate

2. In case of supply of concrete, civil contractor shall use batchingplants,


transit mixers and concrete pumps with boom placer equipment(if
required)etc. For all major concreting works and the rates shall include
the provision for the same.

3. All reinforced concrete shall be done using super-plasticiser as per


manufacturer’s instruction, Approved Design Mix and as directed by
Engineer.

4. All concreting work except fly ash concrete shall be done with Portland
slag cement conforming to IS: 455. For fly ash concrete 43/53 grade
OPC shall be used.

5) Mix design of all concrete to be submitted for approval b y


Engineer before commencement of concrete work.

6)Contractor shall use batching plant, transit mixers and concrete


pumps with boom placer equipment (if required)etc.The location of
batching plant will be outside of factory premises.

7)Cement and aggregates shall be supplied free of cost to the party for all
items

Supplying, laying and compacting plain cement concrete of


following grades as defined byIS:456,in all foundations, bed blocks,
manholes, chambers, tunnels, trenches, floors, roofs, pavements,
screenings, encasing etc. At and at all heights and depths above and
B-2
below finished ground level to required levels, slopes etc. Including curing
but excluding the cost of shuttering, all as per drawings, specifications
and directions of the Engineer/Consultant, all materials, tools, plant and
labour complete in all respect

a) form M10 grade concrete Cum 605

B-3 Supplying, laying and compacting reinforced cement concrete of


following grades as defined by IS:456,in RCC beam coping, crash barriers
etc including curing and super-plasticiser as per manufacturer's instruction
but excluding cost of shuttering and steel reinforcement, all as per
drawings specifications and directions of the Engineer, all materials, tools,
plant and labour complete in all respect
a) form M30 grade concrete 510
Cum
C STEELREINFORCEMENT
Note:

1. Reinforcement bars in item C-1will be measured in lengths


imposition to be laid as specified in drawings and will include
bends, hooks, crank sand authorised laps, chairs, separators
and dowels as per IS Weights shall be calculated in tonne
based on standard weights as per Indian Standards and/or as

2.The cutting and bending of steel reinforcement shall be


done by reinforcement cutting & bending machine and the
rate shall include the provision of same.

3. Reinforcement Steel(CRMFe500)shall be issued free of


cost to the Contractor.

Taking delivery from Employer's stores/stockyard or directly


from trucks at site, loading, transporting, unloading,
straightening, decoiling, cutting, bending, cranking, bending,
tack welding as necessary, placing and fixing in position steel
reinforcement including angles/pins provided for the
approved welded joints, at all levels above and below
finished ground level for reinforced cement concrete and
C-1 precast reinforced cement concrete work including supplying
approved 20SWGANNEALED BLACK binding wire, cover
blocks etc all as per drawings, specifications and directions of
the Engineer all materials, tools, plant and labour complete in
all respect:

a) with high strength deformed bars of grade CRM M


Fe415/500/TMT/THERMAX of all diameters. 12.20
t

D INSERTS, EMBEDMENTS AND OTHER STEEL WORKS


Taking delivery from Employer's stores/stockyard or directly
from trucks at site, structural steel materials, loading,
transporting, unloading, fabricating, erecting and fixing in
position at and at all heights and depths above and below
finished ground level, M.S. plates for anchor box, permanent
steel shuttering(with or without anchoring) for anchor bolt
pockets(straight or tapered) for embedding permanently in
D-1 concrete or masonry work, true to line, level and plumb Mt 1.0
including all connected works and adjustments in shuttering
and reinforcement, all as per drawings, specifications and
directions of the Engineer, all materials, tools, plant and
labour complete in all respect.
E GABION RETAINING WALL WORKS

GABION FILLING MATERIAL


1. Grading of fill:

Rock must be clean, sufficiently durable, hard, non friable and not show
any signs of weathering .Gabion fill is normally a graded fill of between
100 to 200mm in diameter with a nominal 6% smaller or larger. The
grading can be tightened to 80 to 150mm providing the control of the
grading is tight. Stones smaller than the mesh will not be contained by it.
The grading is important to ensure that voids within the unit are
minimized otherwise settlements can occur.

2. Angularity of fill: CUM 10450


E-1
The more angular the fill, the better interlock and the less deformation
of the face occurs. Rounded stone has little interlock and results in
greater deformation of the face. Quarried stone which is normally
angular is the preferable fill as the interlock is very good. Ideally, all
gabions should be fair faced (hand packed on the exposed faces).

3. Density of considerable rock types: (Locally available material


conforming to density specified in detail drawing):
GABION MESH BOX MATERIAL

1. Mechanical Properties:

a. Tensile Strength : The tensile strength of wire used for


mechanically woven, double twisted hexagonal shaped mesh,
lacing wire and stiffener, when tested shall be in accordance
with the requirements of specification IS 280:2006 (350 -
500MPa) at a minimum elongation of 10%.

b. Tensile Strength of Mesh Panel: The minimum tensile strength of


the mesh panel must be 50.0kN/m in the parallel to twist direction
and 25.5kN/m in the perpendicular to twist direction in accordance
with the requirements of IS 16014: 2012.

2. Physical Properties:

a. Zinc Coating: The coating weight shall be heavily coated and soft
type conforming to the requirements of specification IS 4826:1972.

Adhesion of Zinc Coating: The zinc coating shall remain adherent to


the steel wire and conform to IS 4826 such that zinc coating does not SQM -
E-2 flake off, nor crack to such an extent that there is possibility of
removing any zinc by rubbing with bare fingers, the use of finger nails
being not allowed.

b. PVC Coating: The initial properties of PVC coating material shall


conform to the following requirements:

a) Specific gravity — In the range from 1.30 to 1.35 when tested in


accordance with IS 13360 (Part 3/Sec 1).

b) Tensile strength — Not less than 20.6MPa when tested in


accordance with IS 13360 (Part 5/Sec 1).

c) Hardness — Shore ‘D’ between 50 and 60, when tested in


accordance with IS 13360 (Part 5/Sec 11).

d) Resistance of PVC coating to sodium chloride solution — When PVC


coated wire is tested in accordance with 12.4 there shall be no loss of
mass.

e) Salt spray exposure — The PVC shall show no effect after 3 000 h of
salt spray exposure in accordance with IS 13360 (Part 8/Sec 14).

SQM 5100
E-3 GABION GEOTEXTILE FILTER

HDPE Geo membrane with 1mm thick or equivalent conforming clause


DRAINAGE PIPE

660
UNPLASTICIZED POLYVINYL CHLORIDE (UPVC) SINGLE WALL CORRUGATEDRMT
PIPES FOR DRAINAGE or equivalent conforming IS 9271:2004.

E-4

F CARRIAGE WAY WORKS


GANULAR SUB BASE

300mm thick Granular sub-base conforming clause 401.2 MORTH


specifications for Roads and Bridge Works.
F-1 CUM 750

PRIME COAT
75mm thick in two layers shall be laid over granular sub-base conforming
F-2 CUM 375
clause 502.2 MORTH specifications for Roads and Bridge Works.

Bituminous Macadam
65mm thick with coarse and fine aggregate bound with bitumen
F-3 conforming clause 504.2 MORTH specifications for Roads and Bridge CUM 160
Works.

PAVER BLOCKS FOR RAMP

Cast in situ CC of grade M20 as per section 1700 of MORTH specifications 505
SQM
for Roads and Bridge Works. The minimum size of the panels shall be
specified as per drawings
F-4