You are on page 1of 1

Project Owner : Infineon Technologies (Malaysia) Sdn Bhd Prepare By : KOOLHABA ENERGY SDN BHD

Propose Project Schedule (Mechanical)


Project Title : Infineon B8 L1 UPGRADING WORKS Issue Date : 19 APRIL '18 Revision : 0

Project APRIL' 2018 MAY ' 2018 JUNE ' 2018


Item Job Scope Duration, Week
Start End 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
F Airconditioning Installation.
1 General Condition And Preliminary
1.1 Preliminary 14 Days 17-Apr 30-Apr

1.2 Long Lead Equipment Arrival 49 Days 10-Apr 29-Apr

2 Mechanical Works
QFC CLEAN ROOM
2.1 Dismantle of Existing ACSU (2 Nos) 2 Days 8-May 11-May

2.2 Relocation of ACSU to New LAN Room (2 Nos) 4 Days 9-May 13-May

2.3 Dismantle of Existing Ducting and FCU (3 Nos) 4 Days 26-Apr 29-Apr

2.4 Ducting Installation Works at Logistic 13 Days 23-Apr 6-May

2.5 FCU Relocation Work In QFC (2 Nos) 3 Days 30-Apr 2-May

2.6 Installs Chilled Water Pipe Works for FCU (2 Nos) 4 Days 3-May 6-May

2.7 AHU & MAU Installation Works 6 Days 30-May 4-Jun

2.8 Chilled Water Pipe Works 3 Days 4-Jun 6-Jun

2.9 Installation of Supply Air Grille 4 Days 1-Jun 4-Jun

NEW SURAU, MOTHER'S ROOM & TOILET


2.1O Dismantle of Existing CWCC (4 Nos) 4 Days 27-May 30-May

2.11 Relocation of Existing CWCC (4 Nos) 4 Days 31-May 3-Jun

LOCKER ROOM
2.12 Ducting & Piping Works in Locker Room 5 Days 24-May 28-May

2.13 Relocation of FCU in Locker Room (1 Nos) 4 Days 29-May 1-Jun

2.14 Exhaust Fan Installation Works 2 Days 2-Jun 3-Jun

3 Electical & Control Works


3.1 Dismantle of Existing ACSU Wiring Works 4 Days 8-May 13-May

3.2 ACSU Wiring Works 4 Days 8-May 13-May

3.3 Dismantle of Existing FCU Wiring Works 3 Days 30-Apr 2-Apr

3.4 Sensor & Transmitter Wiring Works 8 Days 29-May 6-Jun

3.5 FCU, ACSU & CWCC Wiring Works 8 Days 29-May 6-Jun
3.6 AHU, MAU & Heater Wring Works 3 Days 30-May 1-Jun
3.7 Control Panel Installation and Wiring Works 4 Days 2-Jun 5-Jun

3.8 Test and Commissioning 2 Days 6-Jun 7-Jun

4 Others
4.1 Air Balancing and Tuning Works 2 Days 6-Jun 7-Jun

4.2 Cleanroom Technical Cleaning works 2 Days 8-Jun 9-Jun

4.3 Cleanroom T&C 1 Day 10-Jun 10-Jun