You are on page 1of 1

BALDEV INFRA PROJECTS (P) LTD

Construction of 168 Units Type III T/S Quarters at NMDC Bacheli


TODAYS ATTENDANCE OF STAFF (Enter: A = Absent, L = Leave, E = Excused,
DAILY SITE REPORT FOR SITE NO. I & II Dated- 20-Jan-12 or P = Present)
20-Jan-12

WORK MEN DETAILS Sr No. Name of Staff & Designation Attendance

REJA COOLIE MASON CENTRING MISTRI CENTRING HELPER SUPERVISOR OTHERS TOTAL REMARKS 1 Sunil Kulkarni (Proj. Mgr) P
Co's side, de watering, cleaning of slurry, raft rcc, road cleaning,
25 12 0 0 1 As per attendance 0 38 boulder loading & breaking, sand boulder filling. 2 Kailash Wakode (Engr) P
0 0 0 bricks made (half size) 0 Dept. (Brick making team) 3 Pranav Patel (Engr) P
18 2 4 16 16 1 1 58 SSM Engineers (Murty/Madhav Rao) 4 Prahlad Sharma (Works Mgr) P
27 3 0 12 7 1 0 50 Shashikant Kanwar 5 P. L. Khande (Supervisor) L
0 0 0 7 9 0 0 16 Tulsi Dass (Shuttering/centering team) 6 N. Kumar (Supervisor) P
7 5 66 bricks made (full size) Electrical shutdown 12 Ramesh Agrawal (Brick making team) 7 Raju Chapadi (Supervisor) P
Mukesh Bhaskar (Supervisor)
MACHINERY DETAILS 8
(on leave since 24th Dec)
P

TYPE OF MACHINE START READING END READING TOTAL RUNNING HSD ISSUED READING AT TIME OF REMARK 9 Gautam Srivastav (Tract. Driv) P
ISSUE
EX-110 35.5 45.7 10.2 26.9 4 hrs Plinth filling at bl-14, loading of soil for shifting, metal loading & misc works 10 Bhola Nag (Dumper Driv) P
Tractor Hr Mtr not working local shifting of soil, cement, boulders etc 11 Moti Ram More (Office Boy) P
Mixure RM-800 1447.7 1447.7 0 idle 12 Damyanti Bai (Cook) P
Dumper 2207 75427 75433 6 metal & soil shifting local 13 Night Watchmen, Idea Sec (1st Site) P
5 HP Diesel pump 5 hrs at bl-07 14 Night Watchmen, Idea Sec (2nd Site) P
2 HP elect pump 5 hrs at bl-06 15 Sushant (RM800 Operator) P

INWARDS METAL, SAND & BOULDERS ONLY 16 J. P. Wahane (Engr.) P

Sleep No issued by Other details A P E L


ITEM SUPPLIER QTY (Cft) Time of Unloading VEHICLE DIMENSION VEHICLE NO.
us Pit pass No. No. of trips Remarks 0 15 0 1
TODAYS Expences with balance 20-Jan-12
8680 Metal 20 mm (G) Durga st. cru. 300 11.2 14.6x8x2.7 CG-18-H-1069 5672704 1 Sr. No Particulars DR CR
8681, 83 Sand P.D. Sing 2x308 12.30, 18 14.6x7.6x2.10 CG-18-H-1091 5671796, 2913 2 NMDC BACHELI SITE
8679, 82 Sand P.D. Sing 2x308 10.50, 17.15 14.6x7.6x2.10 5671791, 2911 2 B/f 29448
1 Photocopy & courior 50
LOCAL PURCHASE/machine/other materials received 2 mess expences 191
S.NO ITEM SUPPLIER QTY SIZE VEHICLE DIMENSION VEHICLE NO. REMARK 3 Data card recharge 98
1 Engine oil *petrolium 1ltr For co's mixure machine 4
2 5
3 6
4 7

WORK DETAILS 8
DETAILS NO'S QUANTITY TARGETED ACTUAL ACHIEVED NEXT DAY TARGET REMARKS 9
Backfilling 100 100 100 100 At bl- 14 Total 29448 339
Excavation 0 0 0 0 Balance (+ for Dr, - for Cr) 29109
Sand & boulder 15 20 15 20 for 6 rafts at bl-07
filling

RCC 1:2:4 13.94 15 13.94 15 5th fl at bl-01, 4 rafts at bl-06, 12 col at bl-09, 6 col & 11 caps at bl-11

PCC 5 5 5 5 for 6 rafts at bl-07


REQUIREMENT STOCK POSITION HSD DETAILS

ITEM QTY Details of material Required for the Upto date Qty OPENING RECEIVED TOTAL CONSUMPTION BALANCE Sr No. Particulars Opening balance Issued qty
project
CEMENT Bag 88288 16200 377 0 377 99 278 1 4
Curing pipe 1/2 inch 4 bundle STEEL (MT) 834.48 273.34 50.53 0.00 50.53 0.60 49.93 2 Purchased

Sprinkler with stand 3 nos METAL 40 MM (Cft) 48410 17850 1561 0.00 1561 159 1402 3 Ex-110

METAL 20 MM diesel pump+mixure


concrete breaker 1 Granite (Cft) 22110 6005 300.00 6305.30 6305.30 4 machine+vibrator 4
197951 0+3+0
METAL 20 MM 59318 9008 0.00 9008 443 8565 5 Tractor
Regular (Cft)

METAL 12 MM (Cft) 53640 24075 15015 0.00 15015 16 14999 Total 4 4

SAND (Cft) 157700 115018 36614 1232 37846 1137 36709 Balance 0
CC BRICKS NOS 340000 17432 17796 66 17862 0 17862
Boulders(cft) 70000 6650 1750 0 1750 378 1372.44
overall position of project Special Remarks and happenings during the day

Bl-01: SF slab shuttering in prog.


Bl-02: Yet to start.
Bl-03:plinth complete, backfilling in prog. Pl arrange for the steel shuttering of slab as discussed
Bl-04: Gf slab casting done on 8th Jan 12.
Bl-05: GF slab complete, ff columns complete.
Bl-06: pb compl for 2 unit, col started, sand/boulder filling/PCC/
rafts started for remaining 2 units.
Bl-07: Excavn done for 2 units, sand/boulder filling / PCC started.
Bl-08: Filling upto pl bot in prog.
Bl-09: Plinth Beam complete, columns started.
Field Er Mr. J.P. Wahane joined today

Bl-10: Ff slab casting done on 19th Jan.


Bl-11: Ff col in progress.
Bl-12: Shuttering for GF slab in progress.
Bl-13:col for gf complete.
Bl-14:Plinth beams complete, plinth filling in prog.

Out of 42 slabs, 7 slabs complete, 2 are sure in


Mr. Patel,Khande & P. Sharma SUNIL KULKARNI
this month, backlog will be of 1 slab as per
REPORT PREPARED BY CHECKED BY
planning.

You might also like