MANO DE OBRA
0101010003 OPERARIO hh 85.3313 17.17 1,465.14
0101010004 OFICIAL hh 4.0000 14.56 58.24
0101010005 PEON hh 178.6687 13.11 2,342.35
3,865.73
MATERIALES
02070100010002 PIEDRA CHANCADA 1/2" m3 3.4700 55.00 190.85
02070200010002 ARENA GRUESA m3 6.3100 55.00 347.05
0213010001 CEMENTO PORTLAND TIPO I (42.5 kg) bol 78.4400 18.05 1,415.84
02190900010002 TAPA CON MARCO FIERRO FUNDIDO DE DESAGUE 12" X 24" pza 61.0000 83.05 5,066.05
02190900010003 TAPA CON MARCO FIERRO GALVANIZADO DE 12" X 12" pza 61.0000 55.08 3,359.88
0290130022 AGUA m3 1.3176 0.85 1.12
10,380.79
EQUIPOS
0301010006 HERRAMIENTAS MANUALES %mo 115.97
115.97
Total S/. 14,362.49