Professional Documents
Culture Documents
1 2 3 4 5
DASAR UPAH
- Pekerja (pembantu tukang) upah minim
- Tukang
- Kepala Tukang
- Mandor
- Teknisi
- Supervisi
- Tenaga Ahli (Expert)
1 PEKERJA
Upah 1 hari 17,250 17,250
Transfort 1 hari 8,000 8,000
Uang Makan 1 hari 7,000 7,000
32,250 32,250
32250
2 TUKANG
Upah 1 hari 24,500 24,500
Transfort 1 hari 8,000 8,000
Uang Makan 1 hari 8,000 8,000
40,500 40,500
40500
3 TEKNISI
Upah 1 hari 38,250 38,250
Transfort 1 hari 8,000 8,000
Uang Makan 1 hari 10,000 10,000
56,250 56,250
56250
5 SUPERVISI
Upah 1 hari 139,750 139,750
Transfort 1 hari 15,000 15,000 168750
Uang Makan 1 hari 20,000 20,000
174,750 174,750
168750
56250
ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA
206,760.00
299,460.00
303,200.00
270,950.00
303,200.00
224,060.00
288,560.00
385,310.00
514,310.00
111,870.00
96,430.00
128,680.00
256,310.00
96,430.00
193,180.00
120,080.00
120,080.00
39,960.00
39,960.00
137,980.00
96,430.00
55,930.00
2,210.00
52,500.00
127,500.00
26,250.00
390,530.00
146,430.00
159,810.00
159,810.00
137,930.00
117,310.00
78,000.00
56,100.00
5,362,850.00
3,227,290.00
39,000,000.00
650,000.00
43,225,000.00
650,000.00
ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA
Catatan :
- Rp. 20.386,15 -HS.Sipil Hal.2-No.02
- Rp. 9.464, -HS.DKI Hal.2-TN.10
- Rp. 3.713,3 = 2xRp.1068-HS.DKI Hal.3 TN.24
Catatan :
- Rp. 1.600,2 --HS DKI Hal.38 BKR.59
Pekerjaan Bongkar di tambah 10 Cm kiri dan kanan dari lebar galian
Catatan :
Pekerjaan Bongkar di tambah 10 Cm kiri dan kanan dari lebar galian
Catatan :
- Rp. 212.815,30-- HS.DKI hAL.33 - bkr.03
Pekerjaan Bongkar di tambah 10 Cm kiri dan kanan dari lebar galian
Catatan :
- Rp. 295.701.25,- - HS.SIPIL Hal.36 - BKR.04
Pekerjaan Bongkar di tambah 10 Cm kiri dan kanan dari lebar galian
1.8. POMPONGAN
- Pekerja 0.3333 Pekerj 32,250.00 10,750.00
Catatan :
- Rp.11.766.92,- - HS.DKI Hal.36 - BRK.07
- Rp.40.751,- - HS Sipil Hal.2 No.07
4. PENGEBORAN / CROSSING
4.1. Pengeboran dgn menggunakan Bor Manual/Hari dapat 8 M
- Teknisi 1.0000 Orang 56,250.00 56,250.00
- Tukang Kayu 1.0000 T.kayu 40,500.00 40,500.00
- Pekerja 5.0000 Pekerj 32,250.00 161,250.00
- Papan penahan tanah (2x3x2) + (3x1,5x2)x2x0,03 =
(12 + 9) x 2 = 21 x 2 = 42 x 0,03 = 1.2600 M3 572,000.00 720,720.00
- Dolken 5/7 = 12.0000 Batang 3,250.00 39,000.00
- Paku = 1.0000 Kg 2,600.00 2,600.00
1,020,320.00
8.00
4.2. Pengeboran dengan menggunakan Mesin Khusus Sesuai 127,540.00
Kontrak
5 PERBAIKAN BEKAS GALIAN ( BERIKUT MATERIAL )
5.1. T.Biasa/T.Rumput (perbaikan/pemadatan sudah termasuk
dlm pek galian)
5.2. T.Keras/Koral (perbaikan/pemadatan sudah termasuk
dlm pek galian)
5.3. Conblok (Interblok) / M2 22,697.00
5.4. Ubin Badak 26,707.00
5.5. Floor Beton Biasa 14,053.00
5.6. Floor Beton Cor 26,083.00
5.7. Floor Beton Bertulang 75,200.00
5.8. Shat Sheet 10,920.00
5.9. Aspal Biasa / Penetrasi
Penetrasi tebal 5 Cm 13,314.00 13,314.00
Macadam tebal 20 Cm 17,186.00 17,186.00
Sirtu Tebal 30 Cm 16,190.00 16,190.00
46,690.00
5.10. Aspal Hotmix 3/5/20/32
Hotmix tebal 3 Cm 12,517.00 12,517.00
Tack Coating 3,188.00 3,188.00
Penetrasi tebal 5 Cm 13,314.00 13,314.00
Macadam 20 Cm 17,186.00 17,186.00
Sirtu 32 Cm 16,190.00 16,190.00
62,395.00
5.11. Aspal Hotmix 5/5/20/28
Hotmix tebal 5 Cm 20,744.00 20,744.00
Tack Coating 3,188.00 3,188.00
Penetrasi tebal 5 Cm 13,314.00 13,314.00
Macadam 20 Cm 17,186.00 17,186.00
Sirtu 32 Cm = 32/30 16,190.00 16,190.00
70,622.00
5.12. Aspal Hotmix 7/5/20/28
Hotmix tebal 7 Cm 28,972.00 28,972.00
Tack Coating 3,188.00 3,188.00
Penetrasi tebal 5 Cm 13,314.00 13,314.00
Macadam 20 Cm 17,186.00 17,186.00
Sirtu 28 Cm = 28/30 16,190.00 16,190.00
78,850.00
5.13. Perbaikan Keramik
- Pasang Keramik 10 x 20 1.00 m 37,999.00
- Pasang Keramik 20 x 20 1.00 m 40,742.00
- Pasang Keramik 30 x 20 1.00 m 33,440.00
10,280.25
12,850.31
16,705.40
19,275.47
21,721.80
32,768.29
0.00
11,511.31
14,389.14
18,705.88
21,583.71
25,900.46
36,692.31
0.00
11,132.72
13,835.89
17,890.64
20,753.83
24,808.58
34,945.47
0.00
10,995.63
13,688.19
17,698.64
20,532.29
24,542.74
34,888.89
0.00
18,938.19
22,927.89
143,246.35
34,391.83
253,191.68
55,283.32
0.00
11,559.07
14,300.99
41,035.01
345,096.50
353,201.34
77,762.20
0.00
16,932.07
21,165.09
27,514.61
31,747.63
38,097.15
53,968.93
10,750.00
3,034.67
3,793.33
103,625.00
21093.75 42187.5
103,625.00
135,875.00
850.00
140.00
49,960.00
11,100.00
5,110.00
20,220.00
258,000.00
127,540.00
22,700.00
26,710.00
14,050.00
26,080.00
75,200.00
10,920.00
46,690.00
62,390.00
70,620.00
78,850.00
38,000.00
40,740.00
43,470.00
ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA
5 PEMASANGAN/PERBAIKAN KUTR
5.1 Pemasangan KUTR 4 Kawat BC 25/50 mm2
- Penarikan KUTR 1 Gawang 0.5 Mandor 56,250.00 28,125.00
2 Tukang 40,500.00 81,000.00
1.5 Pekerja 32,250.00 48,375.00
5.13 Pemasangan/Penanaman Pipa Arde (1,5 inc per 1,5 mtr) perbatang
0.25 Pemasangan 26,000.00 6,500.00
Pengadaan pipa Arde (1.5 inc per 1,5 m) 0.25 Pemasangan 50,718.00 12,680.00
5.14 Pemasangan Pipa Arde (1,5 inc) & (6) pengikat (3) dipipa (3) dikabel
0.25 Mandor 56,250.00 14,062.50
0.5 Tukang 40,500.00 20,250.00
5.15 Pemasangan Pipa Opstyg (2,5) & (6) pengikat (3) dipipa (3) dikabel
0.25 Mandor 56,250.00 14,062.50
0.5 Tukang 40,500.00 20,250.00
12.2 Menyetel KWH meter 3 phase pada tutup OK.III & memasang MCB
1 0.2 Mandor 56,250.00 11,250.00
0.4 Tukang 40,500.00 16,200.00
0.33333333
1.66666667
86,250.00
0.33333333
2
99,750.00
0.33333333
2
99,750.00
0.33333333
2.66666667
126,750.00
0.33333333
3.33333333
153,750.00
32,500.00 3 32,565.98
40,500.00
44,800.00
56,400.00
65,800.00
0.33333333
2.66666667
126,750.00
0.33333333
3.33333333
153,750.00
0.5
4
190,125.00
0.5
4.5
210,375.00
0.5
5
230,625.00
47,200.00
53,900.00
20,600.00
1,400.00
99,280.00
108,220.00
143,610.00
156,330.00
260,430.00
157,500.00
115,750.00
54,562.50
68,625.00
157,500.00
115,750.00
12,093.75
8,578.13
10,750.00
30,937.50
39,687.50
30,937.50
19,180.00
34,312.50
34,312.50
24,240.00
61,140.00
85,480.00
61,143.00
85,480.00
86,250.00
99,750.00
99,750.00
126,750.00
153,750.00
86,250.00
6,500.00
129,000.00
100,875.00
126,750.00
153,750.00
190,125.00
210,375.00
230,625.00
157,500.00
115,750.00
328,687.50
9,350.00
12,190.00
18,690.00
24,380.00
9,350.00
12,647.73
27,450.00
68,625.00
99,068.00
91,500.00
ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA
2004
HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN BIAYA
(Rp.) (Rp.)
01 02 03 04
3 CONBLOCK/INTERBLOCK
a 1 dan 2 Jalur (1,00x0,40x1,20)
- Bongkar Conblock/Interblok = 0.6 m2 1,600.20 960.12
- Galian Tanah Keras = 0.456 m3 24,233.23 11,050.35
- Urugan Tanah Keras = 0.32 m3 9,464.00 3,028.48
- Pemadatan = 0.4 m2 3,713.30 1,485.32
16,524.27
b 3 Jalur (1,00x0,60x1,20)
- Bongkar Conblock/Interblok = 0.8 m2 1,600.20 1,280.16
- Galian Tanah Keras = 0.654 m3 24,233.23 15,848.53
- Urugan Tanah Keras = 0.48 m3 9,464.00 4,542.72
- Pemadatan = 0.6 m2 3,713.30 2,227.98
23,899.39
c 4 Jalur (1,00x0,80x1,20)
- Bongkar Conblock/Interblok = 1 m2 1,600.20 1,600.20
- Galian Tanah Keras = 0.912 m3 24,233.23 22,100.71
- Urugan Tanah Keras = 0.64 m3 9,464.00 6,056.96
- Pemadatan = 0.8 m2 3,713.30 2,970.64
32,728.51
d 5 dan 6 Jalur (1,00x0,60x1,40)
- Bongkar Conblock/Interblok = 0.8 m2 1,600.20 1,280.16
- Galian Tanah Keras = 0.804 m3 24,233.23 19,483.52
- Urugan Tanah Keras = 0.48 m3 9,464.00 4,542.72
- Pemadatan = 0.6 m2 3,713.30 2,227.98
27,534.38
e 7 dan 8 Jalur (1,00x0,80x1,40)
- Bongkar Conblock/Interblok = 1 m2 1,600.20 1,600.20
- Galian Tanah Keras = 1.072 m3 24,233.23 25,978.02
- Urugan Tanah Keras = 0.64 m3 9,464.00 6,056.96
- Pemadatan = 0.8 m2 3,713.30 2,970.64
36,605.82
f 9 dan 10 Jalur (1,00x1,00x1,40)
- Bongkar Conblock/Interblok = 1.2 m2 1,600.20 1,920.24
- Galian Tanah Keras = 1.34 m3 24,233.23 32,472.53
- Urugan Tanah Keras = 0.8 m3 9,464.00 7,571.20
- Pemadatan = 1 m2 3,713.30 3,713.30
45,677.27
g 11 dan 12 Jalur (1,00 x 1,20 x 1,40)
- Bongkar Conblock/Interblok = 1.4 m2 1,600.20 2,240.28
- Galian Tanah Keras = 1.608 m3 24,233.23 38,967.03
- Urugan Tanah Keras = 0.96 m3 9,464.00 9,085.44
- Pemadatan = 1.2 m2 3,713.30 4,455.96
54,748.71
h 13,14 dan 15 Jalur (1,00 x 1,00 x 1,60)
- Bongkar Conblock/Interblok = 1.2 m2 1,600.20 1,920.24
- Galian Tanah Keras = 1.54 m3 24,233.23 37,319.17
- Urugan Tanah Keras = 0.8 m3 9,464.00 7,571.20
- Pemadatan = 1 m2 3,713.30 3,713.30
50,523.91
i Penyuntikan Kabel (1,50 x 0,50 x 1,10)
- Bongkar Conblock/Interblok = 1.05 m2 1,600.20 1,680.21
- Galian Tanah Keras = 0.78 m3 24,233.23 18,901.92
- Urugan Tanah Keras = 0.63 m3 9,464.00 5,962.32
- Pemadatan = 0.75 m2 3,713.30 2,784.98
29,329.42
j Galian Lub.Sambungan 1 s/d 2 Jalur (2,00 x 1,30 x 1,20)
- Bongkar Conblock/Interblok = 3 m2 1,600.20 4,800.60
- Galian Tanah Keras = 2.964 m3 24,233.23 71,827.29
- Urugan Tanah Keras = 2.444 m3 9,464.00 23,130.02
- Pemadatan = 2.6 m2 3,713.30 9,654.58
109,412.49
k Galian Lub.Pengeboran Manual (2,00 x 1,50 x 3,00)
- Bongkar Conblock/Interblok = 3.4 m2 1,600.20 5,440.68
- Galian Tanah Keras = 8.82 m3 36,349.84 320,605.59
- Urugan Tanah Keras = 8.22 m3 9,464.00 77,794.08
- Pemadatan = 3 m2 3,713.30 11,139.90
414,980.25
Catatan :
- Rp. 1.600,2 --HS DKI Hal.38 BKR.59
- Pekerjaan bongkar di tambah 10 cm kiri dan kanan dari lebar
galian.
7 ASPAL BIASA/HOTMIX
a 1 dan 2 Jalur (1,00 x 1,40 x 1,20)
- Bongkar Aspal/Hotmix = 0.4 m2 11,766.92 4,706.77
- Galian Tanah Berbatu = 0.26 m3 40,751.00 10,595.26
- Galian Tanah Keras = 0.2 m3 24,233.23 4,846.65
- Urugan Tanah Keras = 0.12 m3 9,464.00 1,135.68
- Pemadatan = 0.4 m2 1,856.65 742.66
22,027.01
b 3 Jalur (1,00 x 0,60 x 1,20)
- Bongkar Aspal/Hotmix = 0.6 m2 11,766.92 7,060.15
- Galian Tanah Berbatu = 0.39 m3 40,751.00 15,892.89
- Galian Tanah Keras = 0.3 m3 24,233.23 7,269.97
- Urugan Tanah Keras = 0.18 m3 9,464.00 1,703.52
- Pemadatan = 0.6 m2 1,856.65 1,113.99
33,040.52
c 4 Jalur (1,00 x 0,80 x 1,20)
- Bongkar Aspal/Hotmix = 0.8 m2 11,766.92 9,413.54
- Galian Tanah Berbatu = 0.52 m3 40,751.00 21,190.52
- Galian Tanah Keras = 0.4 m3 24,233.23 9,693.29
- Urugan Tanah Keras = 0.24 m3 9,464.00 2,271.36
- Pemadatan = 0.8 m2 1,856.65 1,485.32
44,054.03
d 5 dan 6 Jalur (1,00 x 0,60 x 1,40)
- Bongkar Aspal/Hotmix = 0.6 m2 11,766.92 7,060.15
- Galian Tanah Berbatu = 0.39 m3 40,751.00 15,892.89
- Galian Tanah Keras = 0.42 m3 24,233.23 10,177.96
- Urugan Tanah Keras = 0.18 m3 9,464.00 1,703.52
- Pemadatan = 0.6 m2 1,856.65 1,113.99
35,948.51
e 7 dan 8 Jalur (1,00 x 0,80 x 1,40)
- Bongkar Aspal/Hotmix = 0.8 m2 11,766.92 9,413.54
- Galian Tanah Berbatu = 0.52 m3 40,751.00 21,190.52
- Galian Tanah Keras = 0.56 m3 24,233.23 13,570.61
- Urugan Tanah Keras = 0.24 m3 9,464.00 2,271.36
- Pemadatan = 0.8 m2 1,856.65 1,485.32
47,931.34
f 9 dan 10 Jalur (1,00 x 1,00 x 1,40)
- Bongkar Aspal/Hotmix = 1 m2 11,766.92 11,766.92
- Galian Tanah Berbatu = 0.65 m3 40,751.00 26,488.15
- Galian Tanah Keras = 0.7 m3 24,233.23 16,963.26
- Urugan Tanah Keras = 0.3 m3 9,464.00 2,839.20
- Pemadatan = 1 m2 1,856.65 1,856.65
59,914.18
g 11 dan 12 Jalur (1,00 x 1,20 x 1,40)
- Bongkar Aspal/Hotmix = 1.2 m2 11,766.92 14,120.30
- Galian Tanah Berbatu = 0.78 m3 40,751.00 31,785.78
- Galian Tanah Keras = 0.84 m3 24,233.23 20,355.91
- Urugan Tanah Keras = 0.36 m3 9,464.00 3,407.04
- Pemadatan = 1.2 m2 1,856.65 2,227.98
71,897.02
h 13, 14 dan 15 Jalur (1,00 x 1,00 x 1,60)
- Bongkar Aspal/Hotmix = 1 m2 11,766.92 11,766.92
- Galian Tanah Berbatu = 0.65 m3 40,751.00 26,488.15
- Galian Tanah Keras = 0.9 m3 24,233.23 21,809.91
- Urugan Tanah Keras = 0.3 m3 9,464.00 2,839.20
- Pemadatan = 1 m2 1,856.65 1,856.65
64,760.83
i Penyuntikan Kabel ( 1,50 x 0,50 x 1,10 )
- Bongkar Aspal/Hotmix = 0.75 m2 11,766.92 8,825.19
- Galian Tanah Berbatu = 0.4875 m3 40,751.00 19,866.11
- Galian Tanah Keras = 0.3 m3 24,233.23 7,269.97
- Urugan Tanah Keras = 0.225 m3 9,464.00 2,129.40
- Pemadatan = 0.75 m2 1,856.65 1,392.49
39,483.16
j Galian Lub. Sambungan 1 s/d Jalur ( 2,00 x 1,30 x 1,20 )
- Bongkar Aspal/Hotmix = 2.6 m2 11,766.92 30,593.99
- Galian Tanah Berbatu = 1.69 m3 40,751.00 68,869.19
- Galian Tanah Keras = 1.3 m3 24,233.23 31,503.20
- Urugan Tanah Keras = 0.78 m3 9,464.00 7,381.92
- Pemadatan = 2.6 m2 1,856.65 4,827.29
143,175.59
k Galian Lub. Pengeboran Manual ( 2,00 x 1,50 x 3,00 )
- Bongkar Aspal/Hotmix = 3 m2 11,766.92 35,300.76
- Galian Tanah Berbatu = 1.95 m3 40,751.00 79,464.45
- Galian Tanah Keras = 6.9 m3 24,233.23 167,209.29
- Urugan Tanah Keras = 6.3 m3 9,464.00 59,623.20
- Pemadatan = 3 m2 1,856.65 5,569.95
347,167.65
8 POMPONGAN
- Pekerja 0.3 pekerja 32,250.00 10,750.00
Catatan :
- Rp.11.766.92,- - HS.DKI Hal.36 - BRK.07
- Rp.40.751,- - HS Sipil Hal.2 No.07
- Rp. 1.856.65 - HS.DKI Hal.3 TN.24
Catatan :
- Beton 1:2:3 / m3 (100 kg) Rp.687.193,- HS.SIPIL No.34
- Angkutan Rp. 65.000,-/Rit HS.DKI Hal.122 - 15007
- Rp.137,- (Harga Batu Bata Rp.130 + ongkos Pasang Rp.7,-)
Catatan :
- Rp. 4.200,- Hs Sipil No.44
- Rp. 49.960,- Hs.Sipil No.7
- Rp. 11.100,- HS.Sipil No.50
- Rp. 33.220,- Hs.Sipil No.45
Catatan : (*)
- Lapisan Pasir tebal 20 cm/m2 Rp.12.960 - HS.SKI Hal.36-LBJ.03
- Lapisan Sirtu tebal 30 cm/m2 Rp.16.190-HS.DKI Hal.25-LBJ.13
- Rp. 216.240,- Hs. Sipil No.136
- Rp. 233.750,- Hs. Sipil No. 27
- Rp. 687.190 - Hs. Sipil No. 34
- Rp. 26.710 Hs. DKI Lt.03 +LBJ.04(16.960 + 9.750)
- Rp. 572.000,- Hs.DKI Hal.108 - 3007
- Rp. 3.250,- Hs.DKI Hal.108 - 3034
- Rp. 2.600,- Hs.DKI Hal.118 - 12001
- Rp. 31.980,- Hs.DKI Hal. 31 - TBJ.04
- Rp. 5.000,- Hs.DKI Hal.31 - TBJ.04
p Ubin Keramik
- Pasang Keramik 10 x 20 = 1.00 m2 37,999.00 37,999.00
- Pasang Keramik 20 x 20 = 1.00 m2 40,742.00 40,742.00
- Pasang Keramik 30 x 30 = 1.00 m2 43,472.00 43,472.00
q Rumput / Taman
- Perbaikan rumput/taman disesuaikan dengan HS.DKI/Pertamanan
( Dalam bestek biaya perbaikan rumput/taman tidak dicantumkan dan
akan dibayar sesuai realisasi berdasarkan bukti yang dapat di
pertanggung jawabkan )
Catatan (*)
- Rp. 13.320 Hs.DKI hal.30 LAJ.04 - Rp. 12.520,21 Hs.DKI Hal.49 - Rp. 38.000 - HS.Sipil No.84
- Rp. 17.200 Hs.DKI hal.36 LBJ.07 - Rp. 20.745 Hs.DKI Hal.49 - Rp. 40740 - HS.Sipil No.80
- Rp. 10.920, - Hs.DKI hal.36 LBJ.17 - Rp. 28.970 Hs.DKI Hal.49 - Rp. 43.470 - HS.Sipil No.81
- Rp. 16.200 Hs.DKI hal.36 LBJ.13 - Rp. 22.025 Hs.DKI Hal.36 LBJ.14
- Rp. 3.200 - Hs.DKI hal.30 LBJ.07
IX PEKERJAAN LAIN-LAIN
a Pembuangan tanah bekas galian dengan truck kapasitas 21,125.00
3 s/d 4m3 jarak>20 Km (Volume yang di buang =Lebar galianx
(tinggi lapisan pasir urug + lapisan penutup galian)xpanjang
(trace galian)
b Penjagaan 32,250.00 32,250.00
- 1 Pekerja/Hari
c Penyediaan tenaga untuk bantu pengujian kabel TM PLN
- Pekerja 2 Pekerja 32,250.00 64,500.00
- Instalatir 2 Instalatir 13,000.00 26,000.00
90,500.00
d Pemasangan arrester 20 KV termasuk pentanahan
( Sama dengan HS.SUTM )
- Pmasangan arresterdan pengadaan dudukan arreter 118,872.00 118,872.00
- Pengadaan/Pemasangan pipa arde 0 1,5 inci - 6 mtr 76,713.00 76,713.00
195,585.00
X BIAYA PENGURUSAN IJIN
1 Pemda DKI
a SPS BKJS ( Pengawasan,Perencanaan) 60% RAB perbaikan
b Q. Control pada hotmix/km 1,000/ 100 x 1 Titik 58,570.00 585,700.00
c Q. Control pada hotmix/km 1,000/ 100 x 1 Titik 10,790.00 107,900.00
d Proctor ( b + c )/ Km 75,660.00 151,320.00
e SPS.DTK ( Trace dan Gambar ) 501,260.00 501,260.00
f Pengurusan
2 Diluar Pemda DKI dan Instalasi lain
a Biaya Restribusi 130.00 130.00
b Pengurusan 65.00 65.00
3 Perum Otorita Jatiluhur/ Pengairan
a Biaya sewa lahan (Dalam bestek sewa lahan tidak dicantumkan
dan akan dibayar sesuai realisasi berdasarkan bukti - bukti
yang dapat dipertanggungjawabkan)
b Pengurusan ke Jatiluhur Purwakarta 65.00 65.00
Catatan :
Rp- Rp 21.25,- HS.DKI hal.5-AG.11
XI PENGANGKUTAN KABEL
Catatan :
- HS. Angkutan kabel TM sesuai HS.Biaya Jasa Angkutan
- Rp. 193.400,- HS.Sipil No.143 - Rp.14.365,- HS.DKI Hal.118/11035
- 1/3 Direksi Keet dianggap 3 kali pakai Rp.11.830,- HS DKI Hal. 111/6001
- 1/2 Direksi Keet dianggap 2 kali pakai - Rp.2.600 HS.DKI Hal.118-12001
- Rp.8.215 = Rp.591.500/72 batang - HS.DKI Hal.108 - 3027
XIII DOKUMENTASI
a Foto dokumentasi 2 x 36 lembar berwarna
- Film = 1 rool 10,400.00 10,400.00
- Cuci film = 1 roll 2,600.00 2,600.00
- Cetak 2 x 36 = 72 lembar 520.00 37,440.00
50,440.00
b Foto dokumentasi perlembar berwarna
- Film = 1 rool 10,400.00 10,400.00
- Cuci film = 1 roll 2,600.00 2,600.00
- Cetak 1 x 36 = 72 lembar 520.00 18,720.00
31,720.00
c As.build drawing 1 : 200 (1 kalkir + 5 blue print + 1 film )
Sesuai panjang galian, kanal dan crossing.
- Mengambar 1 km Trace
- Tenaga Ahli Muda (D - 2) = 2 jam/ 1 orang 11,089.00 22,178.00
- Petugas Survey (E - 5) = 8 jam/1 orang 9,620.00 76,960.00
- Pekerja = 2 Orang 9,750.00 19,500.00
- Tukang Gambar ( E - 5 ) = 32 Jam 9,620.00 307,840.00
- Kertas kalkir ukuran = 0.30 x 5 3,900.00 19,500.00
- Cetak Blue Print = 5 lembar 3,120.00 15,600.00
- Cetak film Ukuran = 0.30 x 5 19,500.00 97,500.00
559,078.00
Biaya Menggambar / Meter = 559.078/1.000 = 559.00
d As.Build Drawing 1:5000 (1 kalkir + 5 blue print) print gambar spindle
- Tenaga Ahli Muda ( D - 2 ) = 1 jam /1 Orang 11,089.00 11,089.00
- Tukang Gambar (E - 5 ) = 16 Jam/1 Orang 9,620.00 153,920.00
1 13,000.00 13,000.00
- Kertas Kalkir Ukuran = 1 Meter 3,900.00 3,900.00
- Cetak Blue Print 1,950.00 9,750.00
191,659.00
Catatan (*)
- Rp.10.400,- Hs.DKI Hal.122 - 15001
- Rp.2.600,- Hs.DKI Hal.122 - 15002
- Rp.520,- Hs.DKI Hal.122 - 15003
JUMLAH
DIBULATKAN
(Rp.)
05
0.65
18,522
0.72
22,584
30,113
25,031
33,374
5.835
41,718
36,476
45,795
0.825
26,702
3.12
97,866
388,128
2136 3713.3
4408.24 11139.9
7878
11817
3445
0.65
21,022.52
25,354.31
33,805.74
28,262.29
35,790.26
47,103.82
56,524.59
51,950.47
29,875.39
109,868.66
252,360.05
1.5
14196
5569.5
109,868.66
9
14197.5
417,786.06
10504
15756
16,524.27
23,899.39
32,728.51
27,534.38
36,605.82
45,677.27
54,748.71
50,523.91
29,329.42
109,412.49
414,980.25
16,357.65
24,449.16
32,492.20
27,357.15
36,369.51
45,381.88
54,394.25
50,228.53
29,178.87
108,890.55
413,287.52
33585.72
24,404.02 0.072
35,004.92
0.096
45,680.09
37,912.91
49,557.40
60,709.77
72,846.40
66,048.55
43,038.41
141,000.37
352,310.19
79970
0.06
0.44
0.32
0.39981273
32,547.17
46,420.73
59,922.97
49,328.72
63,800.28
78,271.85
92,743.41
83,118.50
61,400.23
189,817.75
399,165.83
22,027.01
33,040.52
44,054.03
35,948.51
47,931.34
59,914.18
71,897.02
64,760.83
39,483.16
143,175.59
347,167.65
10,750.00
3575
15769
1068
4,330.00
5,190.00
5,190.00
426,125.00
426,125.00
426,125.00
9,870.00
9,870.00
136.00
0.03
18,192.00
910.00
127,540.00
91,130.00
2,073,500.00
3,822,000.00
5,505,500.00
7,252,700.00
22,700.00
26,710.00
0.05 10812.1
0.25
14,052.35
0.05
0.75
21,408.40
0.1
0.5
75,199.80
10,930.00
46,700.00
70,630.00
76,460.00
92,980.00
84,680.00
101,201.00
62,390.00
38,000.00
40,740.00
43,470.00
21,130.00
32,250.00
90,500.00
195,585.00
585,700.00
107,900.00
151,320.00
501,260.00
130.00
65.00
65.00
86,125.00
105,625.00
105,625.00
160,225.00
160,255.00
290,225.00
396,725.00
595,088.00
1,190,176.00
22,100.00
15,798.00
156.00
9,100.00
7,313.00
975.00
55,442.00
50,440.00
881.00
559.00
191,659.00
ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA
4.a Tiang Besi 11 Meter 200 daN 5.09 M2 10,257 52,208.00 52,210.00
4.b Tiang Besi 11 Meter 350 daN 5.48 M2 10,257 56,208.00 56,210.00
4.c Tiang Besi 11 Meter 500 daN 5.84 M2 10,257 59,901.00 59,900.00
4.d Tiang Besi 11 Meter 800 daN 6.99 M2 10,257 71,696.00 71,700.00
4.e Tiang Besi 11 Meter 1200 daN 8.31 M2 10,257 85,236.00 85,240.00
4.f Tiang Besi 11 Meter 200 daN Double 10.18 M2 10,257 104,416.00 104,420.00
4.g Tiang Besi 11 Meter 200 daN Double 10.96 M2 10,257 112,417.00 112,420.00
4.h Tiang Besi 11 Meter 200 daN Double 11.68 M2 10,257 119,802.00 119,800.00
4.i Tiang Besi 13 Meter 200 daN 6.17 M2 10,257 63,286.00 63,290.00
4.j Tiang Besi 13 Meter 350 daN 6.88 M2 10,257 70,568.00 70,570.00
4.k Tiang Besi 13 Meter 500 daN 8.68 M2 10,257 68,517.00 68,520.00
4.l Tiang Besi 13 Meter 800 daN 8.50 M2 10,257 87,185.00 87,190.00
4.m Tiang Besi 13 Meter 1200 daN 10.12 M2 10,257 103,801.00 103,800.00
4.n Tiang Besi 13 Meter 200 daN Double 12.34 M2 10,257 126,571.00 126,570.00
4.o Tiang Besi 13 Meter 350 daN Double 13.76 M2 10,257 141,136.00 141,140.00
4.p Tiang Besi 13 Meter 500 daN Double 17.36 M2 10,257 178,062.00 178,060.00
9 PEMASANGAN PIPA ARDE (1,5 Inc per 6 mtr) per batang 26,000 26,000.00
PENGADAAN PIPA ARDE (1,5 Inc per 6 mtr) per batang 50,718 50,718.00
76,718.00 76,720.00
10 PENARIKAN KAWAT HANTARAN/Gawang (Jarak Mx.40 m)
3 PEMBONGKARAN LBS TIANG SUTM ( sama dengan biaya pasang ) sama dgn by pemasangan
6 PERBAIKAN TRAVES UNP 12 - 1800 mm sama dengan pasang 10,023 10,023.00 10,020.00
7 PERBAIKAN TRAVES UNP 12 - 2200 mm sama dengan pasang 22,204 22,204.00 22,200.00
8 PERBAIKAN TRAVES UNP 12 - 2400 mm sama dengan pasang 22,204 22,204.00 22,200.00
9 PERBAIKAN ISOLATOR TUMPU MIRING sama dengan pasang 3,575 3,575.00 3,580.00
IV LAIN - LAIN
1 PEMBERSIH BENAMG LAYANGAN SUTM/GAWANG
- Pembersihan 1/5 Teknisi 56,250 11,250.00
2/5 Tukang 40,500 16,200.00
27,450.00 27,450.00
2 PEMANGKASAN CABANG POHON SUTM/GAWANG
- Pemangkasan 1/5 Teknisi 56,250 11,250.00
4/5 Tukang 40,500 32,400.00
1 1/3 Pekerja 32,250 43,000.00
3 FOTO DOKUMENTASI : 36 LEMBAR 86,650.00 86,650.00