You are on page 1of 98

ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA

ANALISA HARGA SATUAN JASA


PEMASANGAN INSTALASI LISTRIK

NO JENIS PEKERJAAN HARGA BIAYA JUMLAH


SATUAN (Rp.) DIBULATKAN
(Rp.) (Rp.)

1 2 3 4 5

DASAR UPAH
- Pekerja (pembantu tukang) upah minim
- Tukang
- Kepala Tukang
- Mandor
- Teknisi
- Supervisi
- Tenaga Ahli (Expert)

1 PEKERJA
Upah 1 hari 17,250 17,250
Transfort 1 hari 8,000 8,000
Uang Makan 1 hari 7,000 7,000
32,250 32,250

32250

2 TUKANG
Upah 1 hari 24,500 24,500
Transfort 1 hari 8,000 8,000
Uang Makan 1 hari 8,000 8,000
40,500 40,500

40500

3 TEKNISI
Upah 1 hari 38,250 38,250
Transfort 1 hari 8,000 8,000
Uang Makan 1 hari 10,000 10,000
56,250 56,250

56250

4 TENAGA AHLI MUDA


Upah 1 hari 93,500 93,500
Transfort 1 hari 15,000 15,000
Uang Makan 1 hari 15,000 15,000
123,500 123,500
123500

5 SUPERVISI
Upah 1 hari 139,750 139,750
Transfort 1 hari 15,000 15,000 168750
Uang Makan 1 hari 20,000 20,000
174,750 174,750

168750
56250
ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA

ANALISA HARGA SATUAN


PEKERJAAN PEMASANGAN INSTALASI GARDU
Belum termasuk resiko,over head,keuntungan 10 % dan PPN 10 %
2004
HARGA BIAYA
NO JENIS PEKERJAAN SATUAN ( Rupiah )
( Rupiah )
1 2 3 4
1a PEKERJAAN PEMASANGAN INSTALASI GARDU
1.1 Pemasangan kubikel LBS/PT/B1
- Tenaga Ahli Muda 0.3750 Hari 123,500 46,312.50
2.0000 Tukang 40,500 81,000.00
2.0000 Pekerja 32,250 64,500.00
- Pengadaan/Pemasangan Angkur 4.0000 Buah 3,738 14,952.00
206,764.50
1.2 Pemasangan Kubikel PGDB/PGDT
- Tenaga Ahli Muda 0.5000 Hari 123,500 61,750.00
4.0000 Tukang 40,500 162,000.00
2.0000 Pekerja 32,250 64,500.00
- Pengadaan/Pemasangan Angkur 3.0000 Buah 3,738 11,214.00
299,464.00
1.3 Pemasangan SACO
- Tenaga Ahli Muda 0.5000 Hari 123,500 61,750.00
4.0000 Tukang 40,500 162,000.00
2.0000 Pekerja 32,250 64,500.00
- Pengadaan/Pemasangan Angkur 4.0000 Buah 3,738 14,952.00
303,202.00
1.4 Pemasangan RMU.3 dan 4 Terminal(Panel Kontrol UPD)
- Tenaga Ahli Muda 0.5000 Hari 123,500 61,750.00
4.0000 Tukang 40,500 162,000.00
1.0000 Pekerja 32,250 32,250.00
- Pengadaan/Pemasangan Angkur 4.0000 Buah 3,738 14,952.00
270,952.00
1.5 Pemasangan RMU ( LBS,LBS,PB) ( Beton,Kiosk,Portal)
- Tenaga Ahli Muda 0.5000 Hari 123,500 61,750.00
4.0000 Tukang 40,500 162,000.00
2.0000 Pekerja 32,250 64,500.00
- Pengadaan/Pemasangan Angkur 4.0000 Buah 3,738 14,952.00
303,202.00
1.6 Pemasangan ( Peletakan ke posisi sebenarnya ) Trafo 100 kVA s/d 315 KVA
- Tenaga Ahli Muda 0.3750 Hari 123,500 46,312.50
2.0000 Tukang 40,500 81,000.00
3.0000 Pekerja 32,250 96,750.00
224,062.50
1.7 Pemasangan ( Peletakan ke posisi sebenarnya )Trafo 400 kVA s/d 630 kVA
- Tenaga Ahli Muda 0.3750 Hari 123,500 46,312.50
2.0000 Tukang 40,500 81,000.00
5.0000 Pekerja 32,250 161,250.00
288,562.50
1.8 Pemasangan ( Peletakan ke posisi sebenarnya )Trafo 1.000 kVA s/d 1.250 KVA
- Tenaga Ahli Muda 0.3750 Hari 123,500 46,312.50
2.0000 Tukang 40,500 81,000.00
8.0000 Pekerja 32,250 258,000.00
385,312.50
1.9 Pemasangan ( Peletakan ke posisi sebenarnya )Trafo 1.600 kVA s/d 2.000 KVA
- Tenaga Ahli Muda 0.3750 Hari 123,500 46,312.50
2.0000 Tukang 40,500 81,000.00
12.0000 Pekerja 32,250 387,000.00
514,312.50
1.10 Bracket (Kabel Tray) dan Grounding
- Tenaga Ahli Muda 0.2500 Hari 123,500 30,875.00
2.0000 Tukang 40,500 81,000.00
32,250 111,875.00
1.11 Rak TR 4 Jurusan
- Tenaga Ahli Muda 0.1250 Hari 123,500 15,437.50
2.0000 Tukang 40,500 81,000.00
32,250 96,437.50
1.12 Rak TR 6 & 8 Jurusan
- Tenaga Ahli Muda 0.1250 Hari 123,500 15,437.50
2.0000 Tukang 40,500 81,000.00
1.0000 Pekerja 32,250 32,250.00
128,687.50
1.13 Pemasangan LBS untuk Gardu Beton Open Type
- Tenaga Ahli Muda 0.3750 Hari 123,500 46,312.50
2.0000 Tukang 40,500 81,000.00
- Pengadaan/Pemasangan angkur 4.0000 Pekerja 32,250 129,000.00
256,312.50
1.14 L.V.C.B Outdoor untuk gardu CANTOL
- Tenaga Ahli Muda 0.1250 Hari 123,500 15,437.50
2.0000 Tukang 40,500 81,000.00
96,437.50
1.15 L.V.S.B Outdoor untuk gardu Portal
- Tenaga Ahli Muda 0.1250 Hari 123,500 15,437.50
2.0000 Tukang 40,500 81,000.00
3.0000 Pekerja 32,250 96,750.00
193,187.50
1.16 Single Core TM 3 x ( 1x 25 mm2 ) di MV Cell
- Tenaga Ahli Muda 0.6667 Hari 123,500 82,333.33
0.6667 Tukang 40,500 27,000.00
0.3333 Pekerja 32,250 10,750.00
120,083.33
1.17 Single Core TM 3 x ( 1x 25 mm2 ) di Trafo
- Tenaga Ahli Muda 0.6667 Hari 123,500 82,333.33
0.6667 Tukang 40,500 27,000.00
0.3333 Pekerja 32,250 10,750.00
120,083.33
1.18 Single Core TR 7 x ( 1x 240 mm2 ) di Trafo
- Tenaga Ahli Muda 0.2500 Hari 123,500 30,875.00
0.1250 Tukang 40,500 5,062.50
0.1250 Pekerja 32,250 4,031.25
39,968.75
1.19 Single Core TR 7 x ( 1x 240 mm2 ) di TR
- Tenaga Ahli Muda 0.2500 Hari 123,500 30,875.00
0.1250 Tukang 40,500 5,062.50
0.1250 Pekerja 32,250 4,031.25
39,968.75
1.20 Pengadaan Penyangga Kabel TM 20 kV
- Tenaga Ahli Muda 0.1250 Hari 123,500 15,437.50
1.0000 Tukang 40,500 40,500.00
2.0000 Pekerja 32,250 64,500.00
- Pengad/Pemas Besi U 85x45x6 mm 1.0000 Meter 15,600 15,600.00
- Pengad/Pemas Klem Besi 1.0000 Buah 1,950 1,950.00
137,987.50
1.21 IndikatormGangguan Tanah/GFD
- Tenaga Ahli Muda 0.1250 Hari 123,500 15,437.50
2.0000 Tukang 40,500 81,000.00
96,437.50
1.22 Pemasangan Instalasi Heater Kubikel
- Tenaga Ahli Muda 0.1250 Hari 123,500 15,437.50
1.0000 Tukang 40,500 40,500.00
55,937.50
1.23 Pengadaan Kabel Heater Kubikel 1.0000 Meter 2,210 2,210.00
1.24 Pembersihan Ruangan Gardu 2.0000 Pekerja 26,250 52,500.00

1.25 Bantuan Tenaga untuk Pengujian 2.0000 Tukang 37,500 75,000.00


Pengopersian 2.0000 Pekerja 26,250 52,500.00
127,500.00
1.b PEKERJAAN PEMBONGKARAN INSTALASI GARDU
1 No: 1 s/d 19 sama dengan Pekerjaan Pemasangan
2 Pembongkaran Terminal Indoor 20 KV di Cubikel 1 Pekerja 26,250 26,250
II PEMASANGAN APP TYPE KHUSUS IB,IC DAN IIF
2.1 Dengan Pondasi
- Galian tanah biasa/rumput untk pondasi 0.1300 m3 20,386 2,650.18
- Pasang Batu Bata 0.2600 m3 201,578 52,410.28
- Pasang Angkur 4.0000 Buah 3,738 14,952.00
- Pasang Fisher 4.0000 Buah 1,430 5,720.00
- Plesteran 1 PC: 2 Ps ( tebal 15 mm) 2.2700 m2 10,777 24,463.79
- Acian Beton 2.2700 m2 4,420 10,033.40
- Jasa Pelaksanaan Sipil 0.5000 Hari 123,500 61,750.00
3.0000 Tukang 40,500 121,500.00
- Jasa Pelaksanan Listrik 0.1300 Hari 123,500 16,055.00
2.0000 Tukang 40,500 81,000.00
390,534.65
2.2 Dengan Strain Hook
- Pasang Strain Hook 4.0000 Buah 6,500 26,000.00
- Tenaga Ahli Muda 0.1250 Hari 123,500 15,437.50
1.0000 Tukang 40,500 40,500.00
2.0000 Pekerja 32,250 64,500.00
146,437.50
III PEKERJAAN PEMELIHARAAN INSTALASI GARDU
3.1 Kubikel TM
- Tenaga Ahli Muda 0.1250 Hari 123,500 15,437.50
- Tukang 2.0000 Tukang 40,500 81,000.00
- Majun 0.5000 Kg 8,000 4,000.00
- YC.8513 ( Minyak Pembersih ) 0.5000 Liter 75,000 37,500.00
- Pasline Putih Type G.658 SFG 0.2500 Kg 87,500 21,875.00
159,812.50
3.2 Kubikel pengukuran ( PGDB )
- Tenaga Ahli Muda 0.1250 Hari 123,500 15,437.50
- Tukang 2.0000 Tukang 40,500 81,000.00
- Majun 0.5000 Kg 8,000 4,000.00
- YC.8513 ( Minyak Pembersih ) 0.5000 Liter 75,000 37,500.00
- Pasline Putih Type G.658 SFG 0.2500 Kg 87,500 21,875.00
159,812.50
3.3 Trafo Distribusi
- Tenaga Ahli Muda 0.1250 Hari 123,500 15,437.50
- Tukang 2.0000 Tukang 40,500 81,000.00
- Majun 0.5000 Kg 8,000 4,000.00
- YC.8513 ( Minyak Pembersih ) 0.5000 Liter 75,000 37,500.00
137,937.50
3.4 Rak TR
- Tenaga Ahli Muda 0.1250 Hari 123,500 15,437.50
- Tukang 1.0000 Tukang 40,500 40,500.00
- Majun 0.2500 Kg 8,000 2,000.00
- YC.8513 ( Minyak Pembersih ) 0.5000 Liter 75,000 37,500.00
- Pasline Putih Type G.658 SFG 0.2500 Kg 87,500 21,875.00
117,312.50
3.5 Detektor gangguan tanah/GFD
- Tukang 1.0000 Tukang 40,500 40,500.00
- YC.8513 ( Minyak Pembersih ) 0.5000 Kg 75,000 37,500.00
78,000.00
3.6 Pembersihan Ruangan Gardu
- Alat Vacum Cleaner 1.0000 Buah 13,000 13,000.00
- Bahan Bakar/Olie 1.0000 Liter 2,600 2,600.00
- Instalator 1.0000 Tukang 40,500 40,500.00
56,100.00
IV PEKERJAAN LAIN - LAIN
4.1 Pemasangan Gardu Besi/Kios berikut Pondasi
a Pekerjaan Persiapan 1.0000 Lokasi 130,000 130,000.00
b Pasang Bouplank 17.0000 Meter 8,398 142,766.00
c Galian Tanah Biasa/Rumput 9.0000 m3 20,386 183,474.00
d Urugan Pasir Padat 0.5000 m3 49,842 24,921.00
e Pondasi Beton Tulang 1:2:3 4.6000 m3 689,193 3,170,287.80
f Pantek Pipa Arde Komplit 4.0000 Batang 130,000 520,000.00
g Plesteran 1:2 35.0000 m2 10,738 375,830.00
h Acian Beton 35.0000 m2 4,420 154,700.00
i Pasang Arde Keliling Pondasi 10.0000 Kg 2,925 29,250.00
j Beton Lantai Kerja 1:2:3 6.0000 m2 23,375 140,250.00
k Pekerjaan Stel Kios
- Pelaksana 1.0000 Ten.Ahl.Md 123,500 123,500.00
2.0000 Tukang 40,500 81,000.00
3.0000 Pekerja 32,250 96,750.00
l Pembuangan tanah keluar lokasi 9.0000 M3 21,125 190,125.00
Angkutan Truk dengan Kap.3.m3 5,362,853.80
2 Pemasangan Gardu Kios Compact berikut Pondasi
a Pekerjaan Persiapan 1.0000 Lokasi 130,000 130,000.00
b Pasang Bouplank 9.0000 Meter 8,398 75,582.00
c Galian Tanah Biasa/Rumput 4.5000 m3 7,878 35,451.00
d Urugan Pasir Padat 0.2500 m3 49,842 12,460.50
e Pondasi Beton Tulang 1:2:3 2.3000 m3 689,193 1,585,143.90
f Pantek Pipa Arde Komplit 4.0000 Batang 130,000 520,000.00
g Plesteran 1:2 18.0000 m2 10,738 193,284.00
h Acian Beton 18.0000 m2 4,420 79,560.00
i Pasang Arde Keliling Pondasi 10.0000 Kg 2,925 29,250.00
j Beton Lantai Kerja 1:2:3 3.0000 m2 23,375 70,125.00
k Pekerjaan Stel Kios
- Pelaksana 1.0000 Ten.Ahl.Md 123,500 123,500.00
2.0000 Tukang 40,500 81,000.00
6.0000 Pekerja 32,250 193,500.00
l Sewa Mobil Crane 0.8750 Hari 112,500 98,437.50
m Pembuangan tanah keluar lokasi 4.5000 Rit 0.00
Angkutan Truk dengan Kap.3 m3 3,227,293.90

3 Pengadaan Gardu Susun GRC 400 KVA Kososng (1,5x2,5x3,9)m


dan saluran kabel GRC 630 KVA Kosong (1,5x2,5x4,2)
4 Pengadaan Gardu Susun GRC 400 KVA Kososng (1,5x2,5x3,9)m
dan saluran kabel GRC 630 KVA Kosong (1,5x2,5x4,2)
JUMLAH
DIBULATKAN
( Rupiah )
5

206,760.00

299,460.00

303,200.00

270,950.00

303,200.00

224,060.00
288,560.00

385,310.00

514,310.00

111,870.00

96,430.00

128,680.00

256,310.00

96,430.00

193,180.00

120,080.00

120,080.00
39,960.00

39,960.00

137,980.00

96,430.00

55,930.00
2,210.00
52,500.00

127,500.00

26,250.00

390,530.00
146,430.00

159,810.00

159,810.00

137,930.00

117,310.00

78,000.00

56,100.00
5,362,850.00

3,227,290.00

39,000,000.00
650,000.00
43,225,000.00
650,000.00
ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA

ANALISA HARGA SATUAN


PEKERJAAN SALURAN KABEL TEGANGAN RENDAH
Belum termasuk resiko, over head, keuntungan 10 % dan PPN 10 %
2004
HARGA JUMLAH
NO. URAIAN PEKERJAAN SATUAN BIAYA
(RUPIAH) (RUPIAH)
1 2 3 4

1. PEKERJAAN GALIAN, URUGAN DAN PEMADATAN


1.1 GALIAN URUGAN DAN PEMADATAN
PADA TANAH BIASA / TANAH RUMPUT
a. 1 s/d 2 jalur ( 1,00 x 0,40 x 0,80 )
- GALIAN TANAH BIASA/TN.RUMPUT = 0.3200 m3 20,386.15 6,523.57
- URUGAN TANAH BIASA/TN.RUMPUT = 0.2400 m3 9,464.00 2,271.36
- PEMADATAN = 0.4000 m2 3,713.30 1,485.32

b. 3 Jalur (1,00 x 0,50 x 0,80 )


- GALIAN TANAH BIASA/TN.RUMPUT = 0.4000 m3 20,386.15 8,154.46
- URUGAN TANAH BIASA/TN.RUMPUT = 0.3000 m3 9,464.00 2,839.20
- PEMADATAN = 0.5000 m2 3,713.30 1,856.65

c. 4 Jalur (1,00 x 0,65 x 0,80 )


- GALIAN TANAH BIASA/TN.RUMPUT = 0.5200 m3 20,386.15 10,600.80
- URUGAN TANAH BIASA/TN.RUMPUT = 0.3900 m3 9,464.00 3,690.96
- PEMADATAN = 0.6500 m2 3,713.30 2,413.65

d. GALIAN PENYUNTIKAN KABEL PADA


TANAH BIASA/TN.RUMPUT (1,50 x 0,50 x 0,80 )
- GALIAN TANAH BIASA/TN.RUMPUT = 0.6000 m3 20,386.15 12,231.69
- URUGAN TANAH BIASA/TN.RUMPUT = 0.4500 m3 9,464.00 4,258.80
- PEMADATAN = 0.7500 m2 3,713.30 2,784.98

e. GALIAN LUBANG SAMBUNGAN PADA


TANAH BIASA/TN.RUMPUT
( 1 s/d 2 Jalur = 1,50 X 0,50 X 0,80 )
- GALIAN TANAH BIASA/TN.RUMPUT = 0.7200 m3 20,386.15 14,678.03
- URUGAN TANAH BIASA/TN.RUMPUT = 0.4500 m3 9,464.00 4,258.80
- PEMADATAN = 0.7500 m2 3,713.30 2,784.98

f. GALIAN LUBANG SAMBUNGAN PADA


TANAH BIASA/TANAH RUMPUT
( 3 s/d 4 Jalur = 1,50 X 0,85 X 0,80 )
- GALIAN TANAH BIASA/TN.RUMPUT = 1.0200 m3 20,386.15 20,793.87
- URUGAN TANAH BIASA/TN.RUMPUT = 0.7650 m3 9,464.00 7,239.96
- PEMADATAN = 1.2750 m2 3,713.30 4,734.46

g. GALIAN LUBANG PENGEBORAN MANUAL PADA


TANAH BIASA/TANAH RUMPUT
(2,00 X 1,50 X 3,00 )
- HS SAMA DENGAN HS SKTM

Catatan :
- Rp. 20.386,15 -HS.Sipil Hal.2-No.02
- Rp. 9.464, -HS.DKI Hal.2-TN.10
- Rp. 3.713,3 = 2xRp.1068-HS.DKI Hal.3 TN.24

1.2. GALIAN URUGAN DAN PEMADATAN


PADA TANAH KERAS / TANAH KORAL
a. 1 s/d 2 jalur ( 1,00 x 0,40 x 0,80 )
- GALIAN TANAH KERAS / KORAL = 0.3200 m3 24,233.23 7,754.63
- URUGAN TANAH KERAS / KORAL = 0.2400 m3 9,464.00 2,271.36
- PEMADATAN = 0.4000 m2 3,713.30 1,485.32

b. 3 jalur ( 1,00 x 0,50 x 0,80 )


- GALIAN TANAH KERAS / KORAL = 0.4000 m3 24,233.23 9,693.29
- URUGAN TANAH KERAS / KORAL = 0.3000 m3 9,464.00 2,839.20
- PEMADATAN = 0.5000 m2 3,713.30 1,856.65

c. 4 jalur ( 1,00 x 0,65 x 0,80 )


- GALIAN TANAH KERAS / KORAL = 0.5200 m3 24,233.23 12,601.28
- URUGAN TANAH KERAS / KORAL = 0.3900 m3 9,464.00 3,690.96
- PEMADATAN = 0.6500 m2 3,713.30 2,413.65

d. GALIAN PENYUNTIKAN KABEL PADA


TANAH KERAS / KORAL
- GALIAN TANAH KERAS / KORAL = 0.6000 m3 24,233.23 14,539.94
- URUGAN TANAH KERAS / KORAL = 0.4500 m3 9,464.00 4,258.80
- PEMADATAN = 0.7500 m2 3,713.30 2,784.98

e. GALIAN LUBANG SAMBUNGAN PADA


TANAH KERAS / KORAL
( 1 s/d 2 jalur = 1,50 x 0,60 x 0,80 )
- GALIAN TANAH KERAS / KORAL = 0.7200 m3 24,233.23 17,447.93
- URUGAN TANAH KERAS / KORAL = 0.5400 m3 9,464.00 5,110.56
- PEMADATAN = 0.9000 m2 3,713.30 3,341.97

f. GALIAN LUBANG SAMBUNGAN PADA


TANAH KERAS / KORAL
( 3 s/d 4 jalur = 1,50 x 0,85 x 0,80 )
- GALIAN TANAH KERAS / KORAL = 1.0200 m3 24,233.23 24,717.89
- URUGAN TANAH KERAS / KORAL = 0.7650 m3 9,464.00 7,239.96
- PEMADATAN = 1.2750 m2 3,713.30 4,734.46

g. GALIAN LUBANG PENGEBORAN MANUAL PADA


TANAH KERAS / KORAL
( 2,00 x 1,50 x 3,00 )
- HS SAMA DENGAN HS SKTM
Catatan :
- Rp. 24.233,23 HS.Sipil Hal.1 No.06

1.3. GALIAN URUGAN DAN PEMADATAN


PADA CONBLOK / INTERBLOK
a. 1 s/d 2 jalur ( 1,00 x 0,40 x 0,80 )
- BONGKAR CONBLOK / INTERBLOK = 0.6000 m2 1,600.20 960.12
- GALIAN TANAH KERAS = 0.2960 m3 24,233.23 7,173.04
- URUGAN TANAH KERAS = 0.1600 m3 9,464.00 1,514.24
- PEMADATAN = 0.4000 m2 3,713.30 1,485.32

b. 3 jalur ( 1,00 x 0,50 x 0,80 )


- BONGKAR CONBLOK / INTERBLOK = 0.7000 m2 1,600.20 1,120.14
- GALIAN TANAH KERAS = 0.3700 m3 24,233.23 8,966.30
- URUGAN TANAH KERAS = 0.2000 m3 9,464.00 1,892.80
- PEMADATAN = 0.5000 m2 3,713.30 1,856.65

c. 4 jalur ( 1,00 x 0,65 x 0,80 )


- BONGKAR CONBLOK / INTERBLOK = 0.8500 m2 1,600.20 1,360.17
- GALIAN TANAH KERAS = 0.4810 m3 24,233.23 11,656.18
- URUGAN TANAH KERAS = 0.2600 m3 9,464.00 2,460.64
- PEMADATAN = 0.6500 m2 3,713.30 2,413.65

d. GALIAN PENYUNTIKAN KABEL PADA


CONBLOK / INTERBLOK ( 1,50 X 0,50 X 0,80 )
- BONGKAR CONBLOK / INTERBLOK = 1.0500 m2 1,600.20 1,680.21
- GALIAN TANAH KERAS = 0.5550 m3 24,233.23 13,449.44
- URUGAN TANAH KERAS = 0.3000 m3 9,464.00 2,839.20
- PEMADATAN = 0.7500 m2 3,713.30 2,784.98

e. GALIAN LUBANG SAMBUNGAN PADA


CONBLOK / INTERBLOK ( 1,50 X 0,60 X 0,80 )
( 1 s/d 2 jalur = 1,50 x 0,60 x 0,80 )
- BONGKAR CONBLOK / INTERBLOK = 1.2000 m2 1,600.20 1,920.24
- GALIAN TANAH KERAS = 0.6660 m3 24,233.23 16,139.33
- URUGAN TANAH KERAS = 0.3600 m3 9,464.00 3,407.04
- PEMADATAN = 0.9000 m2 3,713.30 3,341.97

f. GALIAN LUBANG SAMBUNGAN PADA


CONBLOK / INTERBLOK ( 1,50 X 0,85 X 0,80 )
( 3 s/d 4 jalur = 1,50 x 0,85 x 0,80 )
- BONGKAR CONBLOK / INTERBLOK = 1.5750 m2 1,600.20 2,520.32
- GALIAN TANAH KERAS = 0.9435 m3 24,233.23 22,864.05
- URUGAN TANAH KERAS = 0.5100 m3 9,464.00 4,826.64
- PEMADATAN = 1.2750 m2 3,713.30 4,734.46

g. GALIAN LUBANG PENGEBORAN MANUAL PADA


CONBLOK / INTERBLOK ( 1,50 X 0,85 X 0,80 )
( 2,00 x 1,50 x 3,00 )
- HS SAMA DENGAN HS SKTM

Catatan :
- Rp. 1.600,2 --HS DKI Hal.38 BKR.59
Pekerjaan Bongkar di tambah 10 Cm kiri dan kanan dari lebar galian

1.4. GALIAN URUGAN DAN PEMADATAN


PADA UBIN BADAK / KERAMIK / FLOOR BETON BIASA
a. 1 s/d 2 jalur ( 1,00 x 0,40 x 0,80 )
- BONGKAR U.BADAK / F.BETON BIASA = 0.6000 m2 1,600.20 960.12
- GALIAN TANAH KERAS = 0.2880 m3 24,233.23 6,979.17
- URUGAN TANAH KERAS = 0.1660 m3 9,464.00 1,571.02
- PEMADATAN = 0.4000 m2 3,713.30 1,485.32

b. 3 jalur ( 1,00 x 0,50 x 0,80 )


- BONGKAR U.BADAK / F.BETON BIASA = 0.7000 m2 1,600.20 1,120.14
- GALIAN TANAH KERAS = 0.3600 m3 24,233.23 8,723.96
- URUGAN TANAH KERAS = 0.2100 m3 9,464.00 1,987.44
- PEMADATAN = 0.5000 m2 3,713.30 1,856.65

c. 4 jalur ( 1,00 x 0,65 x 0,80 )


- BONGKAR U.BADAK / F.BETON BIASA = 0.8500 m2 1,600.20 1,360.17
- GALIAN TANAH KERAS = 0.4680 m3 24,233.23 11,341.15
- URUGAN TANAH KERAS = 0.2730 m3 9,464.00 2,583.67
- PEMADATAN = 0.6500 m2 3,713.30 2,413.65

d. GALIAN PENYUNTIKAN KABEL PADA


UBIN BADAK / F.BETON BIASA ( 1,50 X 0,50 X 0,80 )
- BONGKAR U.BADAK / F.BETON BIASA = 1.0500 m2 1,600.20 1,680.21
- GALIAN TANAH KERAS = 0.5400 m3 24,233.23 13,085.94
- URUGAN TANAH KERAS = 0.3150 m3 9,464.00 2,981.16
- PEMADATAN = 0.7500 m2 3,713.30 2,784.98

e. GALIAN LUBANG SAMBUNGAN PADA


UBIN BADAK / F.BETON BIASA
( 1 s/d 2 jalur = 1,50 x 0,60 x 0,80 )
- BONGKAR U.BADAK / F.BETON BIASA = 1.2000 m2 1,600.20 1,920.24
- GALIAN TANAH KERAS = 0.6480 m3 24,233.23 15,703.13
- URUGAN TANAH KERAS = 0.3780 m3 9,464.00 3,577.39
- PEMADATAN = 0.9000 m2 3,713.30 3,341.97

f. GALIAN LUBANG SAMBUNGAN PADA


UBIN BADAK / F.BETON BIASA
( 3 s/d 4 jalur = 1,50 x 0,85 x 0,80 )
- BONGKAR U.BADAK / F.BETON BIASA = 1.7750 m2 1,600.20 2,840.36
- GALIAN TANAH KERAS = 0.9180 m3 24,233.23 22,246.11
- URUGAN TANAH KERAS = 0.5355 m3 9,464.00 5,067.97
- PEMADATAN = 1.2750 m2 3,713.30 4,734.46

g. GALIAN LUBANG PENGEBORAN MANUAL PADA


UBIN BADAK / F.BETON BIASA ( 2,00 x 1,50 x 3,00 )
HS SAMA DENGAN HARGA SKTM

Catatan :
Pekerjaan Bongkar di tambah 10 Cm kiri dan kanan dari lebar galian

1.5. GALIAN URUGAN DAN PEMADATAN


PADA FLOOR BETON COR
a. 1 s/d 2 jalur ( 1,00 x 0,40 x 0,80 )
- BONGKAR FLOOR BETON COR = 0.0420 m2 212,815.30 8,938.24
- GALIAN TANAH KERAS = 0.2920 m3 24,233.23 7,076.10
- URUGAN TANAH KERAS = 0.1520 m3 9,464.00 1,438.53
- PEMADATAN = 0.4000 m2 3,713.30 1,485.32

b. 3 jalur ( 1,00 x 0,50 x 0,80 )


- BONGKAR FLOOR BETON COR = 0.0490 m2 212,815.30 10,427.95
- GALIAN TANAH KERAS = 0.3650 m3 24,233.23 8,845.13
- URUGAN TANAH KERAS = 0.1900 m3 9,464.00 1,798.16
- PEMADATAN = 0.5000 m2 3,713.30 1,856.65

c. 4 jalur ( 1,00 x 0,65 x 0,80 )


- BONGKAR FLOOR BETON COR = 0.5950 m2 212,815.30 126,625.10
- GALIAN TANAH KERAS = 0.4745 m3 24,233.23 11,498.67
- URUGAN TANAH KERAS = 0.2470 m3 9,464.00 2,337.61
- PEMADATAN = 0.7500 m2 3,713.30 2,784.98

d. GALIAN PENYUNTIKAN KABEL PADA


FLOOR BETON COR ( 1,50 x 0,50 x 0,80 )
- BONGKAR FLOOR BETON COR = 0.0735 m2 212,815.30 15,641.92
- GALIAN TANAH KERAS = 0.5475 m3 24,233.23 13,267.69
- URUGAN TANAH KERAS = 0.2850 m3 9,464.00 2,697.24
- PEMADATAN = 0.7500 m2 3,713.30 2,784.98

e. GALIAN LUBANG SAMBUNGAN PADA


FLOOR BETON COR
( 1 s/d 2 jalur = 1,50 x 0,60 x 0,80 )
- BONGKAR FLOOR BETON COR = 1.0840 m2 212,815.30 230,691.79
- GALIAN TANAH KERAS = 0.6570 m3 24,233.23 15,921.23
- URUGAN TANAH KERAS = 0.3420 m3 9,464.00 3,236.69
- PEMADATAN = 0.9000 m2 3,713.30 3,341.97

f. GALIAN LUBANG SAMBUNGAN PADA


FLOOR BETON COR
( 3 s/d 4 jalur = 1,50 x 0,85 x 0,80 )
- BONGKAR FLOOR BETON COR = 0.1100 m2 212,815.30 23,409.68
- GALIAN TANAH KERAS = 0.9307 m3 24,233.23 22,553.87
- URUGAN TANAH KERAS = 0.4845 m3 9,464.00 4,585.31
- PEMADATAN = 1.2750 m2 3,713.30 4,734.46

g. GALIAN LUBANG PENGEBORAN MANUAL PADA


FLOOR BETON COR ( 2,00 x 1,50 x 3,00 )
HS SAMA DENGAN HARGA SKTM

Catatan :
- Rp. 212.815,30-- HS.DKI hAL.33 - bkr.03
Pekerjaan Bongkar di tambah 10 Cm kiri dan kanan dari lebar galian

1.6. GALIAN URUGAN DAN PEMADATAN


PADA FLOOR BETON BERTULANG
a. 1 s/d 2 jalur ( 1,00 x 0,40 x 0,80 )
- BONGKAR FLOOR BETON BERTULANG = 0.0060 m2 295,701.25 1,774.21
- GALIAN TANAH KERAS = 0.2800 m3 24,233.23 6,785.30
- URUGAN TANAH KERAS = 0.1600 m3 9,464.00 1,514.24
- PEMADATAN = 0.4000 m2 3,713.30 1,485.32

b. 3 jalur ( 1,00 x 0,50 x 0,80 )


- BONGKAR FLOOR BETON BERTULANG = 0.0070 m2 295,701.25 2,069.91
- GALIAN TANAH KERAS = 0.3500 m3 24,233.23 8,481.63
- URUGAN TANAH KERAS = 0.2000 m3 9,464.00 1,892.80
- PEMADATAN = 0.5000 m2 3,713.30 1,856.65

c. 4 jalur ( 1,00 x 0,65 x 0,80 )


- BONGKAR FLOOR BETON BERTULANG = 0.0850 m2 295,701.25 25,134.61
- GALIAN TANAH KERAS = 0.4550 m3 24,233.23 11,026.12
- URUGAN TANAH KERAS = 0.2600 m3 9,464.00 2,460.64
- PEMADATAN = 0.6500 m2 3,713.30 2,413.65

d. GALIAN PENYUNTIKAN KABEL PADA


FLOOR BETON BERTULANG ( 1,50 x 0,50 x 0,80 )
- BONGKAR FLOOR BETON BERTULANG = 1.1050 m2 295,701.25 326,749.88
- GALIAN TANAH KERAS = 0.5250 m3 24,233.23 12,722.45
- URUGAN TANAH KERAS = 0.3000 m3 9,464.00 2,839.20
- PEMADATAN = 0.7500 m2 3,713.30 2,784.98

e. GALIAN LUBANG SAMBUNGAN PADA


FLOOR BETON BERTULANG
( 1 s/d 2 jalur = 1,50 x 0,60 x 0,80 )
- BONGKAR FLOOR BETON BERTULANG = 1.1200 m2 295,701.25 331,185.40
- GALIAN TANAH KERAS = 0.6300 m3 24,233.23 15,266.93
- URUGAN TANAH KERAS = 0.3600 m3 9,464.00 3,407.04
- PEMADATAN = 0.9000 m2 3,713.30 3,341.97

f. GALIAN LUBANG SAMBUNGAN PADA


FLOOR BETON BERTULANG
( 3 s/d 4 jalur = 1,50 x 0,85 x 0,80 )
- BONGKAR FLOOR BETON BERTULANG = 0.1575 m2 295,701.25 46,572.95
- GALIAN TANAH KERAS = 0.8925 m3 24,233.23 21,628.16
- URUGAN TANAH KERAS = 0.5100 m3 9,464.00 4,826.64
- PEMADATAN = 1.2750 m2 3,713.30 4,734.46
g. GALIAN LUBANG PENGEBORAN MANUAL PADA
FLOOR BETON BERTULANG ( 2,00 x 1,50 x 3,00 )
HS SAMA DENGAN HARGA SKTM

Catatan :
- Rp. 295.701.25,- - HS.SIPIL Hal.36 - BKR.04
Pekerjaan Bongkar di tambah 10 Cm kiri dan kanan dari lebar galian

1.7. GALIAN URUGAN DAN PEMADATAN


PADA A S P A L / H O T M I X
a. 1 s/d 2 jalur ( 1,00 x 0,40 x 0,80 )
- BONGKAR ASPAL / HOTMIX = 0.4000 m2 11,766.92 4,706.77
- GALIAN TANAH BERBATU = 0.3000 m3 40,751.00 12,225.30

b. 3 jalur ( 1,00 x 0,50 x 0,80 )


- BONGKAR ASPAL / HOTMIX = 0.5000 m2 11,766.92 5,883.46
- GALIAN TANAH BERBATU = 0.3750 m3 40,751.00 15,281.63

c. 4 jalur ( 1,00 x 0,65 x 0,80 )


- BONGKAR ASPAL / HOTMIX = 0.6500 m2 11,766.92 7,648.50
- GALIAN TANAH BERBATU = 0.4875 m3 40,751.00 19,866.11

d. GALIAN PENYUNTIKAN KABEL PADA


ASPAL / HOTMIX ( 1,50 x 0,50 x 080 )
- BONGKAR ASPAL / HOTMIX = 0.7500 m2 11,766.92 8,825.19
- GALIAN TANAH BERBATU = 0.5625 m3 40,751.00 22,922.44

e. GALIAN LUBANG SAMBUNGAN PADA


AS PAL / H O T M I X
( 1 s/d 2 jalur = 1,50 x 0,60 x 0,80 )
- BONGKAR ASPAL / HOTMIX = 0.9000 m2 11,766.92 10,590.23
- GALIAN TANAH BERBATU = 0.6750 m3 40,751.00 27,506.93

f. GALIAN LUBANG SAMBUNGAN PADA


AS PAL / H O T M I X
( 3 s/d 4 jalur = 1,50 x 0,85 x 0,80 )
- BONGKAR ASPAL / HOTMIX = 1.2750 m2 11,766.92 15,002.82
- GALIAN TANAH BERBATU = 0.9562 m3 40,751.00 38,966.11

g. GALIAN LUBANG PENGEBORAN MANUAL PADA


AS PAL / H O T M I X
- HS SAMA DENGAN HS SKTM

1.8. POMPONGAN
- Pekerja 0.3333 Pekerj 32,250.00 10,750.00
Catatan :
- Rp.11.766.92,- - HS.DKI Hal.36 - BRK.07
- Rp.40.751,- - HS Sipil Hal.2 No.07

2 PENARIKAN , PENYAMBUNGAN DAN TERMINASI KABEL


2.1. Penarikan Kabel 4 x 16 S/D 50 mm2
Gelar Kabel / hari = 750 meter
- Teknisi 1.0000 orang 123,500.00 123,500.00
- Mandor 1.0000 Mandor 56,250.00 56,250.00
- Pekerja 65.0000 Pekerj 32,250.00 2,096,250.00
Rp.3.575,- --HS DKI Hal.33--BKR-09 2,276,000.00
750
2.2. Penarikan Kabel 4 x 70 s/d 150 mm2 3,034.67
Gelar Kabel / hari = 600 meter
- Tenaga Ahli Muda 1.0000 Orang 123,500.00 123,500.00
- Teknisi 1.0000 Orang 56,250.00 56,250.00
- Pekerja 65.0000 Pekerj 32,250.00 2,096,250.00
2,276,000.00
600.00
3,793.33
2.3. Penyambungan Kabel
- Tenaga Ahli Muda 0.2500 Orang 123,500.00 30,875.00
- Tukang / Instalator 1.0000 Tuk./ I 40,500.00 40,500.00
- Pekerja 1.0000 Pekerj 32,250.00 32,250.00

2.4. Terminasi Kabel Indoor


- Tenaga Ahli Muda 0.2500 Orang 123,500.00 30,875.00
- Tukang / Instalator 1.0000 Tuk./ I 40,500.00 40,500.00
- Pekerja 1.0000 Pekerj 32,250.00 32,250.00

2.5. Terminasi Kabel Outdoor


- Tenaga Ahli Muda 0.2500 Orang 123,500.00 30,875.00
- Tukang / Instalator 1.0000 Tuk./ I 40,500.00 40,500.00
- Pekerja 2.0000 Pekerj 32,250.00 64,500.00

3. MATERIAL PELENGKAP BERIKUT PEMASANGAN


- Keramik Tanda Peringatan Kabel PLN 845.00
Ukuran (22,5 x 30 x 4) Cm - Sertifikat LMK
- Batu Merah 137.00
- Pasir Urug Darat 49,959.00
- Buis Beton O 20 Cm 11,102.00
- Papan Penahan Tanah 5,107.00
- PVC O 4" type AW 20,215.00
Catatan :
Rp. 5.107 = Rp.572.000,- (Harga Papan / M3)
4 x 28 lembar papan / M3

4. PENGEBORAN / CROSSING
4.1. Pengeboran dgn menggunakan Bor Manual/Hari dapat 8 M
- Teknisi 1.0000 Orang 56,250.00 56,250.00
- Tukang Kayu 1.0000 T.kayu 40,500.00 40,500.00
- Pekerja 5.0000 Pekerj 32,250.00 161,250.00
- Papan penahan tanah (2x3x2) + (3x1,5x2)x2x0,03 =
(12 + 9) x 2 = 21 x 2 = 42 x 0,03 = 1.2600 M3 572,000.00 720,720.00
- Dolken 5/7 = 12.0000 Batang 3,250.00 39,000.00
- Paku = 1.0000 Kg 2,600.00 2,600.00
1,020,320.00
8.00
4.2. Pengeboran dengan menggunakan Mesin Khusus Sesuai 127,540.00
Kontrak
5 PERBAIKAN BEKAS GALIAN ( BERIKUT MATERIAL )
5.1. T.Biasa/T.Rumput (perbaikan/pemadatan sudah termasuk
dlm pek galian)
5.2. T.Keras/Koral (perbaikan/pemadatan sudah termasuk
dlm pek galian)
5.3. Conblok (Interblok) / M2 22,697.00
5.4. Ubin Badak 26,707.00
5.5. Floor Beton Biasa 14,053.00
5.6. Floor Beton Cor 26,083.00
5.7. Floor Beton Bertulang 75,200.00
5.8. Shat Sheet 10,920.00
5.9. Aspal Biasa / Penetrasi
Penetrasi tebal 5 Cm 13,314.00 13,314.00
Macadam tebal 20 Cm 17,186.00 17,186.00
Sirtu Tebal 30 Cm 16,190.00 16,190.00
46,690.00
5.10. Aspal Hotmix 3/5/20/32
Hotmix tebal 3 Cm 12,517.00 12,517.00
Tack Coating 3,188.00 3,188.00
Penetrasi tebal 5 Cm 13,314.00 13,314.00
Macadam 20 Cm 17,186.00 17,186.00
Sirtu 32 Cm 16,190.00 16,190.00
62,395.00
5.11. Aspal Hotmix 5/5/20/28
Hotmix tebal 5 Cm 20,744.00 20,744.00
Tack Coating 3,188.00 3,188.00
Penetrasi tebal 5 Cm 13,314.00 13,314.00
Macadam 20 Cm 17,186.00 17,186.00
Sirtu 32 Cm = 32/30 16,190.00 16,190.00
70,622.00
5.12. Aspal Hotmix 7/5/20/28
Hotmix tebal 7 Cm 28,972.00 28,972.00
Tack Coating 3,188.00 3,188.00
Penetrasi tebal 5 Cm 13,314.00 13,314.00
Macadam 20 Cm 17,186.00 17,186.00
Sirtu 28 Cm = 28/30 16,190.00 16,190.00
78,850.00
5.13. Perbaikan Keramik
- Pasang Keramik 10 x 20 1.00 m 37,999.00
- Pasang Keramik 20 x 20 1.00 m 40,742.00
- Pasang Keramik 30 x 20 1.00 m 33,440.00

5.14. Perbaikan rumput disesuaikan dgn HS DKI/Pertanaman


( Dalam bestek biaya perbaikan rumput/taman tidak
dicantumkan dan akan dibayar sesuai realisasi berdasarkan
bukti yang dapat dipertanggung jawabkan ).
JUMLAH
DIBULATKAN
(RUPIAH)
5

10,280.25

12,850.31

16,705.40

19,275.47

21,721.80

32,768.29
0.00

7880 - Rp. 3.713,3 = 2xRp.1068-HS.DKI Hal.3 2136


3445 - Rp. 11.139,9 =6xRp.1068-HS.DKI HAl.3 4408.24
2140 - Rp. 20.386,15 -HS.Sipil Hal.2-No.02 7878
- Rp. 30.579,- (300/200)x7878 HS. Sipil H 11817
- Rp. 9.464, -HS.DKI Hal.2-TN.10 3445

11,511.31

14,389.14

18,705.88

21,583.71

25,900.46

36,692.31

0.00
11,132.72

13,835.89

17,890.64

20,753.83

24,808.58

34,945.47
0.00

10,995.63

13,688.19

17,698.64

20,532.29

24,542.74

34,888.89
0.00

18,938.19

22,927.89

143,246.35

34,391.83

253,191.68

55,283.32
0.00

11,559.07

14,300.99

41,035.01

345,096.50

353,201.34

77,762.20
0.00

16,932.07

21,165.09

27,514.61

31,747.63

38,097.15

53,968.93

10,750.00

- Rp.11.766.92,- - HS.DKI Hal.36 - BRK.07


- Rp.40.751,- - HS Sipil Hal.2 No.07
- Rp. 1.856.65 - HS.DKI Hal.3 TN.24
0

3,034.67

3,793.33

103,625.00

21093.75 42187.5
103,625.00

135,875.00

850.00

140.00
49,960.00
11,100.00
5,110.00
20,220.00

258,000.00
127,540.00

22,700.00
26,710.00
14,050.00
26,080.00
75,200.00
10,920.00

46,690.00

62,390.00

70,620.00

78,850.00

38,000.00
40,740.00
43,470.00
ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA

ANALISA HARGA SATUAN


PEKERJAAN : SUTR DAN SAMBUNGAN LISTRIK
Belum Termasuk resiko, over head, keuntungan 10 % dan PPN 10 %
2004
HARGA BIAYA
NO. JENIS PEKERJAAN SATUAN
(RUPIAH) (RUPIAH)
1 2 3 4

1 PENANAMAN TIANG BESI 9 METER


1.1 Tiang Besi 9 meter 200 daN
- Pengeboran Tanah/ 0.333333333 Mandor 56,250.00 18,750.00
Mendirikan Tiang 1.666666667 Tukang 40,500.00 67,500.00

1.2 Tiang Besi 9 meter 350 daN


- Pengeboran Tanah/ 0.333333333 Mandor 56,250.00 18,750.00
Mendirikan Tiang 2 Tukang 40,500.00 81,000.00

1.3 Tiang Besi 9 meter 500 daN


- Pengeboran Tanah/ 0.333333333 Mandor 56,250.00 18,750.00
Mendirikan Tiang 2 Tukang 40,500.00 81,000.00

1.4 Tiang Besi 9 meter 800 daN


- Pengeboran Tanah/ 0.333333333 Mandor 56,250.00 18,750.00
Mendirikan Tiang 2.666666667 Tukang 40,500.00 108,000.00

1.5 Tiang Besi 9 meter 1.200 daN


- Pengeboran Tanah/ 0.333333333 Mandor 56,250.00 18,750.00
Mendirikan Tiang 3.333333333 Tukang 40,500.00 135,000.00

2 PENGECATAN TIANG BESI 9 METER


2.1 Tiang Besi 9 meter 200 daN 3.175 m2 10,257.00 32,565.98
2.2 Tiang Besi 9 meter 350 daN 3.954 m2 10,257.00 40,556.18
2.3 Tiang Besi 9 meter 500 daN 4.376 m2 10,257.00 44,884.63
2.4 Tiang Besi 9 meter 800 daN 5.506 m2 10,257.00 56,475.04
2.5 Tiang Besi 9 meter 1.200 daN 6.423 m2 10,257.00 65,880.71

3 PENANAMAN TIANG BETON 9 METER


3.1 Tiang Beton 9 meter 200 daN
- Pengeboran Tanah/ 0.333333333 Mandor 56,250.00 18,750.00
Mendirikan Tiang 2.666666667 Tukang 40,500.00 108,000.00

3.2 Tiang beton 9 meter 350 daN


- Pengeboran Tanah/ 0.333333333 Mandor 56,250.00 18,750.00
Mendirikan Tiang 3.333333333 Tukang 40,500.00 135,000.00

3.3 Tiang beton 9 meter 500 daN


- Pengeboran Tanah/ 0.5 Mandor 56,250.00 28,125.00
Mendirikan Tiang 4 Tukang 40,500.00 162,000.00

3.4 Tiang beton 9 meter 800 daN


- Pengeboran Tanah/ 0.5 Mandor 56,250.00 28,125.00
Mendirikan Tiang 4.5 Tukang 40,500.00 182,250.00

3.5 Tiang beton 9 meter 1.200 daN


- Pengeboran Tanah/ 0.5 Mandor 56,250.00 28,125.00
Mendirikan Tiang 5 Tukang 40,500.00 202,500.00

4 PEMBUATAN PONDASI TIANG BESI/BETON 9 METER


4.1 Pondasi Tiang 9 meter Type A
- Galian Tanah biasa/rumput 6.00 m3 7,878.00 47,268.00
- Sirtu dipadatkan 0.60 m3 89,842.00 53,905.20
- Beton Block 1:2:3 0.03 m3 687,193.00 20,615.79
- Urugan Pasir 0.03 m3 49,842.00 1,495.26

4.2 Ponsdasi Tiang 9 meter Type B


- Galian Tanah biasa/rumput 0.50 m3 7,878.00 3,939.00
- Beton Tumbuk 1:2:3 0.38 m3 216,242.00 82,172.00
- Beton Block 1:2:3 0.03 m3 687,193.00 20,616.00
- Urugan Pasir 0.03 m3 49,842.00 1,495.00

4.3 Pondasi Tiang 9 meter Type C


- Galian Tanah biasa/rumput 0.60 m3 7,878.00 4,727.00
- Beton Tumbuk 1:2:3 0.54 m3 216,242.00 116,771.00
- Beton Block 1:2:3 0.03 m3 687,193.00 20,616.00
- Urugan Pasir 0.03 m3 49,842.00 1,495.00

4.4 Pondasi Tiang 9 meter Type D


- Galian Tanah biasa/rumput 0.50 m3 7,878.00 3,939.00
- Beton Tumbuk 1:2:3 0.38 m3 216,242.00 82,172.00
- Beton Block 1:2:3 0.10 m3 687,193.00 68,719.00
- Urugan Pasir 0.03 m3 49,842.00 1,495.00

4.5 Pondasi Tiang 9 meter Type E


- Galian Tanah biasa/rumput 0.60 m3 7,878.00 4,727.00
- Beton Tumbuk 1:2:3 0.54 m3 216,242.00 116,771.00
- Beton Block 1:2:3 0.20 m3 687,193.00 137,439.00
- Urugan Pasir 0.03 m3 49,842.00 1,495.00

5 PEMASANGAN/PERBAIKAN KUTR
5.1 Pemasangan KUTR 4 Kawat BC 25/50 mm2
- Penarikan KUTR 1 Gawang 0.5 Mandor 56,250.00 28,125.00
2 Tukang 40,500.00 81,000.00
1.5 Pekerja 32,250.00 48,375.00

5.2 Pemasangan Twisted Cable 3 x 35 s/d 70 mm2 + N


- Penarikan KUTR 1 Gawang 0.333333333 Mandor 56,250.00 18,750.00
1.333333333 Tukang 40,500.00 54,000.00
1.333333333 Pekerja 32,250.00 43,000.00

5.3 Pemasangan SL 1 Phase Twisted/Kawat Udara


- Sambungan Rumah (SR) 0.25 Mandor 56,250.00 14,062.50
1 Tukang 40,500.00 40,500.00

5.4 Pemasangan SL 3 Phase Twisted/Kawat Udara


- Sambungan Rumah (SR) 0.5 Mandor 56,250.00 28,125.00
1 Tukang 40,500.00 40,500.00

5.5 Perbaikan KUTR Kendor BC Sama dengan pasang 157,500.00 157,500.00


5.6 Perbaikan KUTR Kendor Twisted Sama dengan pasang 115,750.00 115,750.00
5.7 Pemasangan / Montage Joint Sleve Uk.35 s/d 70 mm2 Set (4 Bh)
0.125 Mandor 56,250.00 7,031.25
0.125 Tukang 40,500.00 5,062.50

5.8 Pemasangan / Montage Conector Uk.35 s/d 70 mm2 Set (4 Bh)


0.0625 Mandor 56,250.00 3,515.63
0.125 Tukang 40,500.00 5,062.50

5.9 Pemasangan / Perbaikan Jumper SUTR/Phase (Buah)


- Mandor Pengawas 0.083333333 Mandor 56,250.00 4,687.50
- Tukang 0.083333333 Tukang 40,500.00 3,375.00
- Pekerja 0.083333333 Pekerja 32,250.00 2,687.50

5.10 Pemasangan Suspension Assemby (Set)


- Mandor Pengawas 0.083333333 Mandor 56,250.00 4,687.50
- Tukang 0.25 Tukang 40,500.00 10,125.00
- Pekerja 0.5 Pekerja 32,250.00 16,125.00

5.11 Pemasangan Dead End Essembly (Set)


- Mandor Pengawas 0.083333333 Mandor 56,250.00 4,687.50
- Tukang 0.333333333 Tukang 40,500.00 13,500.00
- Pekerja 0.666666667 Pekerja 32,250.00 21,500.00

5.12 Pemasangan Pelindung Listrik & Mekanik (Bundle end Protection)


- Mandor Pengawas 0.083333333 Mandor 56,250.00 4,687.50
- Tukang 0.25 Tukang 40,500.00 10,125.00
- Pekerja 0.5 Pekerja 32,250.00 16,125.00

5.13 Pemasangan/Penanaman Pipa Arde (1,5 inc per 1,5 mtr) perbatang
0.25 Pemasangan 26,000.00 6,500.00
Pengadaan pipa Arde (1.5 inc per 1,5 m) 0.25 Pemasangan 50,718.00 12,680.00

5.14 Pemasangan Pipa Arde (1,5 inc) & (6) pengikat (3) dipipa (3) dikabel
0.25 Mandor 56,250.00 14,062.50
0.5 Tukang 40,500.00 20,250.00

5.15 Pemasangan Pipa Opstyg (2,5) & (6) pengikat (3) dipipa (3) dikabel
0.25 Mandor 56,250.00 14,062.50
0.5 Tukang 40,500.00 20,250.00

6 PERBAIKAN PONDASI DAN TIANG MIRING 9 METER


( BESI DAN BETON )
6.1 Pondasi Tiang 9 meter Type A
- Galian tanah biasa/rumput 0.42 m3 7,878.00 3,309.00
- Sirtu dipadatkan 0.42 m3 49,842.00 20,934.00

6.2 Pondasi Tiang 9 meter Type B


- Galian tanah biasa/rumput 0.35 m3 7,878.00 2,727.00
- Beton tumbuk 1:2:3 0.27 m3 216,242.00 58,385.00

6.3 Pondasi Tiang 9 meter Type C


- Galian tanah biasa/rumput 0.42 m3 7,878.00 3,309.00
- Beton tumbuk 1:2:3 0.38 m3 216,242.00 82,172.00

6.4 Pondasi Tiang 9 meter Type D


- Galian tanah biasa/rumput 0.35 m3 7,878.00 2,752.00
- Beton tumbuk 1:2:3 0.27 m3 216,242.00 58,385.00

6.5 Pondasi Tiang 9 meter Type E


- Galian tanah biasa/rumput 0.42 m3 7,878.00 3,309.00
- Beton tumbuk 1:2:3 0.38 m3 216,242.00 82,172.00

7 PEMBONGKARAN TIANG BESI


7.1 Pembongkaran Tiang Besi 9/200 daN Sama Dengan Pasang 86,250.00 86,250.00
7.2 Pembongkaran Tiang Besi 9/350 daN Sama Dengan Pasang 99,750.00 99,750.00
7.3 Pembongkaran Tiang Besi 9/500 daN Sama Dengan Pasang 99,750.00 99,750.00
7.4 Pembongkaran Tiang Besi 9/800 daN Sama Dengan Pasang 126,750.00 126,750.00
7.5 Pembongkaran Tiang Besi 9/1200 daN Sama Dengan Pasang 153,750.00 153,750.00
7.6 Pembongkaran Drak Skur sama dengan pasang Tiang Besi 9/200 86,250.00 86,250.00
7.7 Pembongkaran Drak Skur sama dengan pasang arde KUTR
1 / 4 Pemasang 26,000.00 6,500.00
7.8 Bongkar Pasang Box SKTR
Panel Utama 1 Mandor 56,250.00 56,250.00
1 Tukang 40,500.00 40,500.00
1 Pekerja 32,250.00 32,250.00

7.9 Panel Pembagi 0.5 Mandor 56,250.00 28,125.00


1 Tukang 40,500.00 40,500.00
1 Pekerja 32,250.00 32,250.00

8 PEMBONGKARAN TIANG BETON


8.1 Pembongkaran Tiang Beton 9/200 daN Sama Dengan Pasang 126,750.00 126,750.00
8.2 Pembongkaran Tiang Beton 9/350 daN Sama Dengan Pasang 153,750.00 153,750.00
8.3 Pembongkaran Tiang Beton 9/500 daN Sama Dengan Pasang 190,125.00 190,125.00
8.4 Pembongkaran Tiang Beton 9/800 daN Sama Dengan Pasang 210,375.00 210,375.00
8.5 Pembongkaran Tiang Beton 9/1200 daN Sama Dengan Pasang 230,625.00 230,625.00
9 PEMBONGKARAN KUTR
9.1 Kawat Udara 4 kawat BC 25/50 mm2 Sama Dengan Pasang 157,500.00 157,500.00
9.2 Twisted kabel 3 x 35 s/d 70 mm2 + N Sama Dengan Pasang 115,750.00 115,750.00
9.3 Pembongkaran Travers SUTR 0.083333333 Mandor 56,250.00 4,687.50
8 Tukang 40,500.00 324,000.00

10 PERBAIKAN LISTRIK (SL)


10.1 SL 1 Phase Twisted / Kawat Udara 0.50 Pasang 18,644.00 9,347.00
10.2 SL 3 Phase Twisted / Kawat Udara 0.50 Pasang 24,375.00 12,188.00

11 PEMBONGKARAN 7 REHABILITASI SAMBUNGAN LISTRIK SL


11.1 SL 1 Phase Twisted / Kawat Udara 1 Pasang 18,694.00 18,694.00
11.2 SL 3 Phase Twisted / Kawat Udara 1 Pasang 24,375.00 24,375.00
11.3 Rehabilitasi SL 1 Phase akibat penggeseran tiang
- Pelaksana 1 / 2 Pasang 18,694.00 9,347.00

12 PEKERJAAN LAIN - LAIN


12.1 Menyetel KWH meter 1 phase pada tutup OK.I & memasang MCB
- Mandor Pengawas 0.045454545 Mandor 53,250.00 2,420.45
- Tukang 0.272727273 Tukang 37,500.00 10,227.27

12.2 Menyetel KWH meter 3 phase pada tutup OK.III & memasang MCB
1 0.2 Mandor 56,250.00 11,250.00
0.4 Tukang 40,500.00 16,200.00

12.3 Pemasangan APP Type Khusus I A


- Pelaksana 0.5 Mandor 56,250.00 28,125.00
1 Tukang 40,500.00 40,500.00

12.4 Pemasangan Box TR


- Galian Pondasi tanah biasa / rumput 0.41 m3 7,878.00 3,230.00
- Pondasi Batu Merah 0.135 m3 201,578.00 27,213.00
- Pelaksana 0.5 Mandor 56,250.00 28,125.00
1 Tukang 40,500.00 40,500.00

12.5 Potong Cabang pohon dengan minimal dari hantaran


- Pekerjaan Penebangan 0.333333333 Mandor 56,250.00 18,750.00
1 Tukang 40,500.00 40,500.00
1 Pekerja 32,250.00 32,250.00
JUMLAH
DIBULATKAN
(RUPIAH)
5

0.33333333
1.66666667
86,250.00

0.33333333
2
99,750.00

0.33333333
2
99,750.00

0.33333333
2.66666667
126,750.00

0.33333333
3.33333333
153,750.00

32,500.00 3 32,565.98
40,500.00
44,800.00
56,400.00
65,800.00

0.33333333
2.66666667
126,750.00

0.33333333
3.33333333
153,750.00

0.5
4
190,125.00

0.5
4.5
210,375.00

0.5
5
230,625.00

47,200.00
53,900.00
20,600.00
1,400.00
99,280.00

108,220.00

143,610.00

156,330.00

260,430.00

157,500.00
115,750.00

54,562.50

68,625.00

157,500.00
115,750.00

12,093.75

8,578.13

10,750.00

30,937.50

39,687.50

30,937.50

19,180.00

34,312.50
34,312.50

24,240.00

61,140.00

85,480.00

61,143.00

85,480.00

86,250.00
99,750.00
99,750.00
126,750.00
153,750.00
86,250.00

6,500.00

129,000.00

100,875.00

126,750.00
153,750.00
190,125.00
210,375.00
230,625.00
157,500.00
115,750.00

328,687.50

9,350.00
12,190.00

18,690.00
24,380.00

9,350.00

12,647.73

27,450.00

68,625.00

99,068.00

91,500.00
ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA

ANALISA HARGA SATUAN


PEKERJAAN SALURAN KABEL TEGANGAN MENENGAH
Biaya belum termasuk resiko,overhead,keuntungan 10% dan PPN 10%

2004
HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN BIAYA
(Rp.) (Rp.)
01 02 03 04

I PEKERJAAN GALIAN-URUGAN DAN PEMADATAN

1 TANAH BIASA/TANAH RUMPUT


a 1 dan 2 jalur (1,00 x0,50 x 1,30 )
- Galian Tanah biasa/Rumput = 0.65 m3 20,386.15 13,251.00
- Urugan Tanah Biasa/rumput = 0.4 m3 9,464.00 3,785.60
- Pemadatan = 0.4 m2 3,713.30 1,485.32
18,521.92
b 3 Jalur (1,00 x 0,60 x1,20)
- Galian Tanah biasa/Rumput = 0.72 m3 20,386.15 14,678.03
- Urugan Tanah Biasa/rumput = 0.6 m3 9,464.00 5,678.40
- Pemadatan = 0.6 m2 3,713.30 2,227.98
22,584.41
c 4 Jalur (1,00 x 0,80 x1,20)
- Galian Tanah biasa/Rumput = 0.96 m3 20,386.15 19,570.70
- Urugan Tanah Biasa/rumput = 0.8 m3 9,464.00 7,571.20
- Pemadatan = 0.8 m2 3,713.30 2,970.64
30,112.54
d 5 dan 6 Jalur (1,00 x 0,60 x1,40)
- Galian Tanah biasa/Rumput = 0.84 m3 20,386.15 17,124.37
- Urugan Tanah Biasa/rumput = 0.6 m3 9,464.00 5,678.40
- Pemadatan = 0.6 m2 3,713.30 2,227.98
25,030.75
e 7 dan 8 Jalur (1,00 x 0,80 x1,40)
- Galian Tanah biasa/Rumput = 1.12 m3 20,386.15 22,832.49
- Urugan Tanah Biasa/rumput = 0.8 m3 9,464.00 7,571.20
- Pemadatan = 0.8 m2 3,713.30 2,970.64
33,374.33
f 9 dan 10 Jalur (1,00 x 1,00 x1,40)
- Galian Tanah biasa/Rumput = 1.4 m3 20,386.15 28,540.61
- Urugan Tanah Biasa/rumput = 1 m3 9,464.00 9,464.00
- Pemadatan = 1 m2 3,713.30 3,713.30
41,717.91
g 11 dan 12 Jalur (1,00 x 1,00 x1,40)
- Galian Tanah biasa/Rumput = 1.66 m3 20,386.15 33,841.01
- Urugan Tanah Biasa/rumput = 0.2 m3 9,464.00 1,892.80
- Pemadatan = 0.2 m2 3,713.30 742.66
36,476.47
h 13,14 dan 15 Jalur (1,00 x 1,00 x 1,60)
- Galian Tanah biasa/Rumput = 1.6 m3 20,386.15 32,617.84
- Urugan Tanah Biasa/rumput = 1 m3 9,464.00 9,464.00
- Pemadatan = 1 m2 3,713.30 3,713.30
45,795.14
i Penyuntikan Kabel (1,50 x 0,50 x 1,10 )
- Galian Tanah biasa/Rumput = 0.825 m3 20,386.15 16,818.57
- Urugan Tanah Biasa/rumput = 0.75 m3 9,464.00 7,098.00
- Pemadatan = 0.75 m2 3,713.30 2,784.98
26,701.55
j Galian Lub.Sambungan 1 s/d 2 jalur(2,00x1,30x1,20)
- Galian Tanah biasa/Rumput = 3.12 m3 20,386.15 63,604.79
- Urugan Tanah Biasa/rumput = 2.6 m3 9,464.00 24,606.40
- Pemadatan = 2.6 m2 3,713.30 9,654.58
97,865.77
k Galian Lub.Pengeboran Manual (2,00 x 1,50 x 3,00)
- Galian Tanah biasa/Rumput = 9 m3 30,579.00 275,211.00
- Urugan Tanah Biasa/rumput = 8.4 m3 9,464.00 79,497.60
- Pemadatan = 3 m2 11,139.90 33,419.70
388,128.30
Catatan :
- Rp. 3.713,3 = 2xRp.1068-HS.DKI Hal.3 TN.24
- Rp. 11.139,9 =6xRp.1068-HS.DKI HAl.3 TN.24
- Rp. 20.386,15 -HS.Sipil Hal.2-No.02
- Rp. 30.579,- (300/200)x7878 HS. Sipil Hal.2 No.02
- Rp. 9.464, -HS.DKI Hal.2-TN.10

2 TANAH KERAS/TANAH KORAL


a 1 dan 2 Jalur (1,00x0,50x1,30)
- Galian Tanah Keras/Koral = 0.65 m3 24,233.23 15,751.60
- Urugan Tanah Keras/Koral = 0.4 m3 9,464.00 3,785.60
- Pemadatan = 0.4 m2 3,713.30 1,485.32
21,022.52
b 3 Jalur (1,00x0,60x1,20)
- Galian Tanah Keras/Koral = 0.72 m3 24,233.23 17,447.93
- Urugan Tanah Keras/Koral = 0.6 m3 9,464.00 5,678.40
- Pemadatan = 0.6 m2 3,713.30 2,227.98
25,354.31
c 4 Jalur (1,00x0,80x1,20)
- Galian Tanah Keras/Koral = 0.96 m3 24,233.23 23,263.90
- Urugan Tanah Keras/Koral = 0.8 m3 9,464.00 7,571.20
- Pemadatan = 0.8 m2 3,713.30 2,970.64
33,805.74
d 5 dan 6 Jalur (1,00x0,60x1,20)
- Galian Tanah Keras/Koral = 0.84 m3 24,233.23 20,355.91
- Urugan Tanah Keras/Koral = 0.6 m3 9,464.00 5,678.40
- Pemadatan = 0.6 m2 3,713.30 2,227.98
28,262.29
e 7 dan 8 Jalur (1,00x0,80x1,40)
- Galian Tanah Keras/Koral = 1.12 m3 24,233.23 27,141.22
- Urugan Tanah Keras/Koral = 0.6 m3 9,464.00 5,678.40
- Pemadatan = 0.8 m2 3,713.30 2,970.64
35,790.26
f 9 dan 10 Jalur (1,00x100x1,40)
- Galian Tanah Keras/Koral = 1.4 m3 24,233.23 33,926.52
- Urugan Tanah Keras/Koral = 1 m3 9,464.00 9,464.00
- Pemadatan = 1 m2 3,713.30 3,713.30
47,103.82
g 11 dan 12 Jalur (1,00x1,20x1,40)
- Galian Tanah Keras/Koral = 1.68 m3 24,233.23 40,711.83
- Urugan Tanah Keras/Koral = 1.2 m3 9,464.00 11,356.80
- Pemadatan = 1.2 m2 3,713.30 4,455.96
56,524.59
h 13,14 dan 15 Jalur (1,00x1,00x1,60)
- Galian Tanah Keras/Koral = 1.6 m3 24,233.23 38,773.17
- Urugan Tanah Keras/Koral = 1 m3 9,464.00 9,464.00
- Pemadatan = 1 m2 3,713.30 3,713.30
51,950.47
i Penyuntikan Kabel (1,50x0,50x1,10)
- Galian Tanah Keras/Koral = 0.825 m3 24,233.23 19,992.41
- Urugan Tanah Keras/Koral = 0.75 m3 9,464.00 7,098.00
- Pemadatan = 0.75 m2 3,713.30 2,784.98
29,875.39
j Galian Lub. Sambungan 1s/d2 Jalur ( 2,00x1,30x1,20 )
- Galian Tanah Keras/Koral = 3.12 m3 24,233.23 75,607.68
- Urugan Tanah Keras/Koral = 2.6 m3 9,464.00 24,606.40
- Pemadatan = 2.6 m2 3,713.30 9,654.58
109,868.66
k Galian Lub. Pengeboran Manual ( 2,00x1,50x3,00 )
- Galian Tanah Keras/Koral = 9 m3 24,233.23 218,099.07
- Urugan Tanah Keras/Koral = 2.6 m3 9,464.00 24,606.40
- Pemadatan = 2.6 m2 3,713.30 9,654.58
252,360.05
l Galian Lub. Sambungan 1s/d2 Jalur ( 2,00x1,30x1,20 )
- Galian Tanah Keras/Koral = 3.12 m3 24,233.23 75,607.68
- Urugan Tanah Keras/Koral = 2.6 m3 9,464.00 24,606.40
- Pemadatan = 2.6 m2 3,713.30 9,654.58
109,868.66
m Galian Lub. Pengeboran Manual ( 2,00x1,50x300 )
- Galian Tanah Keras/Koral = 9 m3 36,349.84 327,148.56
- Urugan Tanah Keras/Koral = 8.4 m3 9,464.00 79,497.60
- Pemadatan = 3 m2 3,713.30 11,139.90
417,786.06
Catatan:
- Rp. 24.233,23 HS.Sipil Hal.1 No.06
- Rp. 36.349,84. 300/200xRp.10.504 HS. Sipil Hal.1-No.06

3 CONBLOCK/INTERBLOCK
a 1 dan 2 Jalur (1,00x0,40x1,20)
- Bongkar Conblock/Interblok = 0.6 m2 1,600.20 960.12
- Galian Tanah Keras = 0.456 m3 24,233.23 11,050.35
- Urugan Tanah Keras = 0.32 m3 9,464.00 3,028.48
- Pemadatan = 0.4 m2 3,713.30 1,485.32
16,524.27
b 3 Jalur (1,00x0,60x1,20)
- Bongkar Conblock/Interblok = 0.8 m2 1,600.20 1,280.16
- Galian Tanah Keras = 0.654 m3 24,233.23 15,848.53
- Urugan Tanah Keras = 0.48 m3 9,464.00 4,542.72
- Pemadatan = 0.6 m2 3,713.30 2,227.98
23,899.39
c 4 Jalur (1,00x0,80x1,20)
- Bongkar Conblock/Interblok = 1 m2 1,600.20 1,600.20
- Galian Tanah Keras = 0.912 m3 24,233.23 22,100.71
- Urugan Tanah Keras = 0.64 m3 9,464.00 6,056.96
- Pemadatan = 0.8 m2 3,713.30 2,970.64
32,728.51
d 5 dan 6 Jalur (1,00x0,60x1,40)
- Bongkar Conblock/Interblok = 0.8 m2 1,600.20 1,280.16
- Galian Tanah Keras = 0.804 m3 24,233.23 19,483.52
- Urugan Tanah Keras = 0.48 m3 9,464.00 4,542.72
- Pemadatan = 0.6 m2 3,713.30 2,227.98
27,534.38
e 7 dan 8 Jalur (1,00x0,80x1,40)
- Bongkar Conblock/Interblok = 1 m2 1,600.20 1,600.20
- Galian Tanah Keras = 1.072 m3 24,233.23 25,978.02
- Urugan Tanah Keras = 0.64 m3 9,464.00 6,056.96
- Pemadatan = 0.8 m2 3,713.30 2,970.64
36,605.82
f 9 dan 10 Jalur (1,00x1,00x1,40)
- Bongkar Conblock/Interblok = 1.2 m2 1,600.20 1,920.24
- Galian Tanah Keras = 1.34 m3 24,233.23 32,472.53
- Urugan Tanah Keras = 0.8 m3 9,464.00 7,571.20
- Pemadatan = 1 m2 3,713.30 3,713.30
45,677.27
g 11 dan 12 Jalur (1,00 x 1,20 x 1,40)
- Bongkar Conblock/Interblok = 1.4 m2 1,600.20 2,240.28
- Galian Tanah Keras = 1.608 m3 24,233.23 38,967.03
- Urugan Tanah Keras = 0.96 m3 9,464.00 9,085.44
- Pemadatan = 1.2 m2 3,713.30 4,455.96
54,748.71
h 13,14 dan 15 Jalur (1,00 x 1,00 x 1,60)
- Bongkar Conblock/Interblok = 1.2 m2 1,600.20 1,920.24
- Galian Tanah Keras = 1.54 m3 24,233.23 37,319.17
- Urugan Tanah Keras = 0.8 m3 9,464.00 7,571.20
- Pemadatan = 1 m2 3,713.30 3,713.30
50,523.91
i Penyuntikan Kabel (1,50 x 0,50 x 1,10)
- Bongkar Conblock/Interblok = 1.05 m2 1,600.20 1,680.21
- Galian Tanah Keras = 0.78 m3 24,233.23 18,901.92
- Urugan Tanah Keras = 0.63 m3 9,464.00 5,962.32
- Pemadatan = 0.75 m2 3,713.30 2,784.98
29,329.42
j Galian Lub.Sambungan 1 s/d 2 Jalur (2,00 x 1,30 x 1,20)
- Bongkar Conblock/Interblok = 3 m2 1,600.20 4,800.60
- Galian Tanah Keras = 2.964 m3 24,233.23 71,827.29
- Urugan Tanah Keras = 2.444 m3 9,464.00 23,130.02
- Pemadatan = 2.6 m2 3,713.30 9,654.58
109,412.49
k Galian Lub.Pengeboran Manual (2,00 x 1,50 x 3,00)
- Bongkar Conblock/Interblok = 3.4 m2 1,600.20 5,440.68
- Galian Tanah Keras = 8.82 m3 36,349.84 320,605.59
- Urugan Tanah Keras = 8.22 m3 9,464.00 77,794.08
- Pemadatan = 3 m2 3,713.30 11,139.90
414,980.25
Catatan :
- Rp. 1.600,2 --HS DKI Hal.38 BKR.59
- Pekerjaan bongkar di tambah 10 cm kiri dan kanan dari lebar
galian.

4 UBIN BADAK/KERAMIK/FLOOR BETON BIASA


a 1 dan 2 Jalur (1,00 x 0,40 x 1,20 )
- Bongkar Ubin Badak/F.Beton Biasa = 0.6 m2 1,600.20 960.12
- Galian Tanah Keras = 0.446 m3 24,233.23 10,808.02
- Urugan Tanah Keras = 0.328 m3 9,464.00 3,104.19
- Pemadatan = 0.4 m2 3,713.30 1,485.32
16,357.65
b 3 Jalur (1,00 x 0,60 x 1,20 )
- Bongkar Ubin Badak/F.Beton Biasa = 0.8 m2 1,600.20 1,280.16
- Galian Tanah Keras = 0.672 m3 24,233.23 16,284.73
- Urugan Tanah Keras = 0.492 m3 9,464.00 4,656.29
- Pemadatan = 0.6 m2 3,713.30 2,227.98
24,449.16
c 4 Jalur (1,00 x 0,80 x 1,20 )
- Bongkar Ubin Badak/F.Beton Biasa = 1 m2 1,600.20 1,600.20
- Galian Tanah Keras = 0.896 m3 24,233.23 21,712.97
- Urugan Tanah Keras = 0.656 m3 9,464.00 6,208.38
- Pemadatan = 0.8 m2 3,713.30 2,970.64
32,492.20
d 5 dan 6 Jalur (1,00 x 0,60 x 1,40 )
- Bongkar Ubin Badak/F.Beton Biasa = 0.8 m2 1,600.20 1,280.16
- Galian Tanah Keras = 0.792 m3 24,233.23 19,192.72
- Urugan Tanah Keras = 0.492 m3 9,464.00 4,656.29
- Pemadatan = 0.6 m2 3,713.30 2,227.98
27,357.15
e 7 dan 8 Jalur (1,00 x 0,80 x 1,40 )
- Bongkar Ubin Badak/F.Beton Biasa = 1 m2 1,600.20 1,600.20
- Galian Tanah Keras = 1.056 m3 24,233.23 25,590.29
- Urugan Tanah Keras = 0.656 m3 9,464.00 6,208.38
- Pemadatan = 0.8 m2 3,713.30 2,970.64
36,369.51
f 9 dan 10 Jalur (1,00 x 1,00 x 1,40 )
- Bongkar Ubin Badak/F.Beton Biasa = 1.2 m2 1,600.20 1,920.24
- Galian Tanah Keras = 1.32 m3 24,233.23 31,987.86
- Urugan Tanah Keras = 0.82 m3 9,464.00 7,760.48
- Pemadatan = 1 m2 3,713.30 3,713.30
45,381.88
g 11 dan 12 Jalur (1,00 x 1,20 x 1,40 )
- Bongkar Ubin Badak/F.Beton Biasa = 1.4 m2 1,600.20 2,240.28
- Galian Tanah Keras = 1.584 m3 24,233.23 38,385.44
- Urugan Tanah Keras = 0.984 m3 9,464.00 9,312.58
- Pemadatan = 1.2 m2 3,713.30 4,455.96
54,394.25
h 13, 14 dan 15 Jalur (1,00 x 1,00 x 1,60)
- Bongkar Ubin Badak/F.Beton Biasa = 1.2 m2 1,600.20 1,920.24
- Galian Tanah Keras = 1.52 m3 24,233.23 36,834.51
- Urugan Tanah Keras = 0.82 m3 9,464.00 7,760.48
- Pemadatan = 1 m2 3,713.30 3,713.30
50,228.53
i Penyuntikan Kabel (1,50 x 0,50 x 1,10)
- Bongkar Ubin Badak/F.Beton Biasa = 1.05 m2 1,600.20 1,680.21
- Galian Tanah Keras = 0.765 m3 24,233.23 18,538.42
- Urugan Tanah Keras = 0.6525 m3 9,464.00 6,175.26
- Pemadatan = 0.75 m2 3,713.30 2,784.98
29,178.87
i Galian Lub. Sambungan 1 s/d 2 Jalur (2,00 x 1,30 x 1,20)
- Bongkar Ubin Badak/F.Beton Biasa = 3 m2 1,600.20 4,800.60
- Galian Tanah Keras = 2.912 m3 24,233.23 70,567.17
- Urugan Tanah Keras = 2.522 m3 9,464.00 23,868.21
- Pemadatan = 2.6 m2 3,713.30 9,654.58
108,890.55
k Galian Lub. Pengeboran (2,00 x 1,50 x 3,00)
- Bongkar Ubin Badak/F.Beton Biasa = 3.4 m2 1,600.20 5,440.68
- Galian Tanah Keras = 8.75 m3 36,349.84 318,061.10
- Urugan Tanah Keras = 8.31 m3 9,464.00 78,645.84
- Pemadatan = 3 m2 3,713.30 11,139.90
413,287.52
5 FLOOR BETON COR
a 1 dan 2 Jalur (1,00 x 0,40 x 1,20)
- Bongkar Floor Beton cor = 0.042 m3 212,815.30 8,938.24
- Galian Tanah Keras = 0.452 m3 24,233.23 10,953.42
- Urugan Tanah Keras = 0.312 m3 9,464.00 2,952.77
- Pemadatan = 0.42 m2 3,713.30 1,559.59
24,404.02
b 3 Jalur (1,00 x 0,60 x 1,20)
- Bongkar Floor Beton cor = 0.056 m3 212,815.30 11,917.66
- Galian Tanah Keras = 0.678 m3 24,233.23 16,430.13
- Urugan Tanah Keras = 0.468 m3 9,464.00 4,429.15
- Pemadatan = 0.6 m2 3,713.30 2,227.98
35,004.92
c 4 Jalur (1,00 x 0,80 x 1,20)
- Bongkar Floor Beton cor = 0.07 m3 212,815.30 14,897.07
- Galian Tanah Keras = 0.904 m3 24,233.23 21,906.84
- Urugan Tanah Keras = 0.624 m3 9,464.00 5,905.54
- Pemadatan = 0.8 m2 3,713.30 2,970.64
45,680.09
d 5 dan 6 Jalur (1,00 x 0,60 x 1,40)
- Bongkar Floor Beton cor = 0.056 m3 212,815.30 11,917.66
- Galian Tanah Keras = 0.798 m3 24,233.23 19,338.12
- Urugan Tanah Keras = 0.468 m3 9,464.00 4,429.15
- Pemadatan = 0.6 m2 3,713.30 2,227.98
37,912.91
e 7 dan 8 Jalur (1,00 x 0,80 x 1,40)
- Bongkar Floor Beton cor = 0.07 m3 212,815.30 14,897.07
- Galian Tanah Keras = 1.064 m3 24,233.23 25,784.16
- Urugan Tanah Keras = 0.624 m3 9,464.00 5,905.54
- Pemadatan = 0.8 m2 3,713.30 2,970.64
49,557.40
f 9 dan 10 Jalur (1,00 x 1,00 x 1,40)
- Bongkar Floor Beton cor = 0.084 m3 212,815.30 17,876.49
- Galian Tanah Keras = 1.33 m3 24,233.23 32,230.20
- Urugan Tanah Keras = 0.728 m3 9,464.00 6,889.79
- Pemadatan = 1 m2 3,713.30 3,713.30
60,709.77
g 11 dan 12 Jalur (1,00 x 1,20 x 1,40)
- Bongkar Floor Beton cor = 0.098 m3 212,815.30 20,855.90
- Galian Tanah Keras = 1.596 m3 24,233.23 38,676.24
- Urugan Tanah Keras = 0.936 m3 9,464.00 8,858.30
- Pemadatan = 1.2 m2 3,713.30 4,455.96
72,846.40
h 13,14 dan 15 Jalur (1,00 x 1,00 x 1,60)
- Bongkar Floor Beton cor = 0.084 m3 212,815.30 17,876.49
- Galian Tanah Keras = 1.53 m3 24,233.23 37,076.84
- Urugan Tanah Keras = 0.78 m3 9,464.00 7,381.92
- Pemadatan = 1 m2 3,713.30 3,713.30
66,048.55
i Penyuntikan Kabel (1,50 x 0,50 x 1,10)
- Bongkar Floor Beton cor = 0.0735 m3 212,815.30 15,641.92
- Galian Tanah Keras = 0.7725 m3 24,233.23 18,720.17
- Urugan Tanah Keras = 0.6225 m3 9,464.00 5,891.34
- Pemadatan = 0.75 m2 3,713.30 2,784.98
43,038.41
j Galian Lub. Sambungan 1 s/d 2 Jalur (2,00 x 1,30 x 1,20)
- Bongkar Floor Beton cor = 0.21 m3 212,815.30 44,691.21
- Galian Tanah Keras = 2.938 m3 24,233.23 71,197.23
- Urugan Tanah Keras = 2.418 m3 9,464.00 22,883.95
- Pemadatan = 0.6 m2 3,713.30 2,227.98
141,000.37
k Galian Lub. Pengeboran Manual (2,00 x 1,50 x 3,00)
- Bongkar Floor Beton cor = 0.238 m3 212,815.30 50,650.04
- Galian Tanah Keras = 8.79 m3 24,233.23 213,010.09
- Urugan Tanah Keras = 8.19 m3 9,464.00 77,510.16
- Pemadatan = 3 m2 3,713.30 11,139.90
352,310.19
Catatan :
- Rp. 212.815,30-- HS.DKI hAL.33 - bkr.03

6 FLOOR BETON BERTULANG


a 1 dan 2 (1,00 x 0,40 x 1,20)
- Bongkar Floor Beton Bertulang = 0.06 m3 295,701.25 17,742.08
- Galian Tanah Keras = 0.44 m3 24,233.23 10,662.62
- Urugan Tanah Keras = 0.32 m3 9,464.00 3,028.48
- Pemadatan = 0.3 m2 3,713.30 1,113.99
32,547.17
b 3 Jalur (1,00 x 0,60 x 1,20)
- Bongkar Floor Beton Bertulang = 0.08 m3 295,701.25 23,656.10
- Galian Tanah Keras = 0.66 m3 24,233.23 15,993.93
- Urugan Tanah Keras = 0.48 m3 9,464.00 4,542.72
- Pemadatan = 0.6 m2 3,713.30 2,227.98
46,420.73
c 4 Jalur (1,00 x 0,80 x 1,20)
- Bongkar Floor Beton Bertulang = 0.1 m3 295,701.25 29,570.13
- Galian Tanah Keras = 0.88 m3 24,233.23 21,325.24
- Urugan Tanah Keras = 0.64 m3 9,464.00 6,056.96
- Pemadatan = 0.8 m2 3,713.30 2,970.64
59,922.97
d 5 dan 6 Jalur (1,00 x 0,60 x 1,40)
- Bongkar Floor Beton Bertulang = 0.08 m3 295,701.25 23,656.10
- Galian Tanah Keras = 0.78 m3 24,233.23 18,901.92
- Urugan Tanah Keras = 0.48 m3 9,464.00 4,542.72
- Pemadatan = 0.6 m2 3,713.30 2,227.98
49,328.72
e 7 dan 8 Jalur (1,00 x 0,80 x 1,40)
- Bongkar Floor Beton Bertulang = 0.1 m3 295,701.25 29,570.13
- Galian Tanah Keras = 1.04 m3 24,233.23 25,202.56
- Urugan Tanah Keras = 0.64 m3 9,464.00 6,056.96
- Pemadatan = 0.8 m2 3,713.30 2,970.64
63,800.28
f 9 dan 10 Jalur (1,00 x 1,00 x 1,40)
- Bongkar Floor Beton Bertulang = 0.12 m3 295,701.25 35,484.15
- Galian Tanah Keras = 1.3 m3 24,233.23 31,503.20
- Urugan Tanah Keras = 0.8 m3 9,464.00 7,571.20
- Pemadatan = 1 m2 3,713.30 3,713.30
78,271.85
g 11 dan 12 Jalur (1,00 x 1,20 x 1,40)
- Bongkar Floor Beton Bertulang = 0.14 m3 295,701.25 41,398.18
- Galian Tanah Keras = 1.56 m3 24,233.23 37,803.84
- Urugan Tanah Keras = 0.96 m3 9,464.00 9,085.44
- Pemadatan = 1.2 m2 3,713.30 4,455.96
92,743.41
h 13,14 dan 15 Jalur (1,00 x 1,00 x 1,60)
- Bongkar Floor Beton Bertulang = 0.12 m3 295,701.25 35,484.15
- Galian Tanah Keras = 1.5 m3 24,233.23 36,349.85
- Urugan Tanah Keras = 0.8 m3 9,464.00 7,571.20
- Pemadatan = 1 m2 3,713.30 3,713.30
83,118.50
i Penuntikan Kabel (1,50 x 0,50 x 1,10)
- Bongkar Floor Beton Bertulang = 0.105 m3 295,701.25 31,048.63
- Galian Tanah Keras = 0.75 m3 24,233.23 18,174.92
- Urugan Tanah Keras = 0.6 m3 9,464.00 5,678.40
- Pemadatan = 1.75 m2 3,713.30 6,498.28
61,400.23
j Galian Lub. Sumbangan 1 s/d 2 Jalur (2,00 x 1,30 x 1,20)
- Bongkar Floor Beton Bertulang = 0.3 m3 295,701.25 88,710.38
- Galian Tanah Keras = 2.86 m3 24,233.23 69,307.04
- Urugan Tanah Keras = 2.34 m3 9,464.00 22,145.76
- Pemadatan = 2.6 m2 3,713.30 9,654.58
189,817.75
k Galian Lub. Pengeboran Manual (2,00 x 1,50 x 3,00)
- Bongkar Floor Beton Bertulang = 0.34 m3 295,701.25 100,538.43
- Galian Tanah Keras = 8.7 m3 24,233.23 210,829.10
- Urugan Tanah Keras = 8.1 m3 9,464.00 76,658.40
- Pemadatan = 3 m2 3,713.30 11,139.90
399,165.83
Catatan :
- Rp. 295.701.25,- - HS.SIPIL Hal.36 - BKR.04

7 ASPAL BIASA/HOTMIX
a 1 dan 2 Jalur (1,00 x 1,40 x 1,20)
- Bongkar Aspal/Hotmix = 0.4 m2 11,766.92 4,706.77
- Galian Tanah Berbatu = 0.26 m3 40,751.00 10,595.26
- Galian Tanah Keras = 0.2 m3 24,233.23 4,846.65
- Urugan Tanah Keras = 0.12 m3 9,464.00 1,135.68
- Pemadatan = 0.4 m2 1,856.65 742.66
22,027.01
b 3 Jalur (1,00 x 0,60 x 1,20)
- Bongkar Aspal/Hotmix = 0.6 m2 11,766.92 7,060.15
- Galian Tanah Berbatu = 0.39 m3 40,751.00 15,892.89
- Galian Tanah Keras = 0.3 m3 24,233.23 7,269.97
- Urugan Tanah Keras = 0.18 m3 9,464.00 1,703.52
- Pemadatan = 0.6 m2 1,856.65 1,113.99
33,040.52
c 4 Jalur (1,00 x 0,80 x 1,20)
- Bongkar Aspal/Hotmix = 0.8 m2 11,766.92 9,413.54
- Galian Tanah Berbatu = 0.52 m3 40,751.00 21,190.52
- Galian Tanah Keras = 0.4 m3 24,233.23 9,693.29
- Urugan Tanah Keras = 0.24 m3 9,464.00 2,271.36
- Pemadatan = 0.8 m2 1,856.65 1,485.32
44,054.03
d 5 dan 6 Jalur (1,00 x 0,60 x 1,40)
- Bongkar Aspal/Hotmix = 0.6 m2 11,766.92 7,060.15
- Galian Tanah Berbatu = 0.39 m3 40,751.00 15,892.89
- Galian Tanah Keras = 0.42 m3 24,233.23 10,177.96
- Urugan Tanah Keras = 0.18 m3 9,464.00 1,703.52
- Pemadatan = 0.6 m2 1,856.65 1,113.99
35,948.51
e 7 dan 8 Jalur (1,00 x 0,80 x 1,40)
- Bongkar Aspal/Hotmix = 0.8 m2 11,766.92 9,413.54
- Galian Tanah Berbatu = 0.52 m3 40,751.00 21,190.52
- Galian Tanah Keras = 0.56 m3 24,233.23 13,570.61
- Urugan Tanah Keras = 0.24 m3 9,464.00 2,271.36
- Pemadatan = 0.8 m2 1,856.65 1,485.32
47,931.34
f 9 dan 10 Jalur (1,00 x 1,00 x 1,40)
- Bongkar Aspal/Hotmix = 1 m2 11,766.92 11,766.92
- Galian Tanah Berbatu = 0.65 m3 40,751.00 26,488.15
- Galian Tanah Keras = 0.7 m3 24,233.23 16,963.26
- Urugan Tanah Keras = 0.3 m3 9,464.00 2,839.20
- Pemadatan = 1 m2 1,856.65 1,856.65
59,914.18
g 11 dan 12 Jalur (1,00 x 1,20 x 1,40)
- Bongkar Aspal/Hotmix = 1.2 m2 11,766.92 14,120.30
- Galian Tanah Berbatu = 0.78 m3 40,751.00 31,785.78
- Galian Tanah Keras = 0.84 m3 24,233.23 20,355.91
- Urugan Tanah Keras = 0.36 m3 9,464.00 3,407.04
- Pemadatan = 1.2 m2 1,856.65 2,227.98
71,897.02
h 13, 14 dan 15 Jalur (1,00 x 1,00 x 1,60)
- Bongkar Aspal/Hotmix = 1 m2 11,766.92 11,766.92
- Galian Tanah Berbatu = 0.65 m3 40,751.00 26,488.15
- Galian Tanah Keras = 0.9 m3 24,233.23 21,809.91
- Urugan Tanah Keras = 0.3 m3 9,464.00 2,839.20
- Pemadatan = 1 m2 1,856.65 1,856.65
64,760.83
i Penyuntikan Kabel ( 1,50 x 0,50 x 1,10 )
- Bongkar Aspal/Hotmix = 0.75 m2 11,766.92 8,825.19
- Galian Tanah Berbatu = 0.4875 m3 40,751.00 19,866.11
- Galian Tanah Keras = 0.3 m3 24,233.23 7,269.97
- Urugan Tanah Keras = 0.225 m3 9,464.00 2,129.40
- Pemadatan = 0.75 m2 1,856.65 1,392.49
39,483.16
j Galian Lub. Sambungan 1 s/d Jalur ( 2,00 x 1,30 x 1,20 )
- Bongkar Aspal/Hotmix = 2.6 m2 11,766.92 30,593.99
- Galian Tanah Berbatu = 1.69 m3 40,751.00 68,869.19
- Galian Tanah Keras = 1.3 m3 24,233.23 31,503.20
- Urugan Tanah Keras = 0.78 m3 9,464.00 7,381.92
- Pemadatan = 2.6 m2 1,856.65 4,827.29
143,175.59
k Galian Lub. Pengeboran Manual ( 2,00 x 1,50 x 3,00 )
- Bongkar Aspal/Hotmix = 3 m2 11,766.92 35,300.76
- Galian Tanah Berbatu = 1.95 m3 40,751.00 79,464.45
- Galian Tanah Keras = 6.9 m3 24,233.23 167,209.29
- Urugan Tanah Keras = 6.3 m3 9,464.00 59,623.20
- Pemadatan = 3 m2 1,856.65 5,569.95
347,167.65
8 POMPONGAN
- Pekerja 0.3 pekerja 32,250.00 10,750.00
Catatan :
- Rp.11.766.92,- - HS.DKI Hal.36 - BRK.07
- Rp.40.751,- - HS Sipil Hal.2 No.07
- Rp. 1.856.65 - HS.DKI Hal.3 TN.24

II PENARIKAN DAN PENYAMBUNGAN


1 a Penarikan/Penggelaran Kabel 3 x 150 mm2
1 Hari / 8 Jam = 600 Meter
- Tenaga Ahli Muda 1 Tenaga.Ah.Muda 123,500.00 123,500.00
- Teknisi 1 Teknisi 56,250.00 56,250.00
- Pekerja ### Pekerja 32,250.00 2,418,750.00
2,598,500.00
Biaya Penggelaran Kabel / Meter = 2.598.500 / 600 4,330.83
b Penarikan/Penggelaran Kabel 3 x 240 mm2
1 Hari / 8 Jam = 500 Meter
- Tenaga Ahli Muda 1 Tenaga.Ah.Muda 123,500.00 123,500.00
- Teknisi 1 Teknisi 56,250.00 56,250.00
- Pekerja ### Pekerja 32,250.00 2,418,750.00
2,598,500.00
Biaya Penggelaran Kabel / Meter = 2.598,500 / 500 5,197.00
c Penarikan/Penggelaran Kabel 3 x 300 mm2
1 Hari / 8 Jam = 500 Meter
- Tenaga Ahli Muda 1 Tenaga.Ah.Muda 123,500.00 123,500.00
- Teknisi 1 Teknisi 56,250.00 56,250.00
- Pekerja ### Pekerja 32,250.00 2,418,750.00
2,598,500.00
Biaya Penggelaran Kabel / Meter = 2.598.500 / 500 5,197.00

2 Penyambungan SKTM 20 KV 3 x 150 / 240 / 300 mm2


a Dengan Pola S / E
1 Hari / 6 Jam = 1 Set
- Tenaga Ahli Muda (Jointer) 1 Tenaga.Ah.Muda 123,500.00 61,750.00
- Tukang 3 Orang 1 Tukang 40,500.00 20,250.00
82,000.00
- Supervisi Pabrikan 174,750.00
Main Kontraktor 50% 169,375.00
426,125.00

3 Terminasi Kabel Indoor 20 KV 3 x 150,3 x 240,3 x 300 mm2


a Dengan Pola S / E
1 Hari / 4 Jam = 1 Set
- Tenaga Ahli Muda (Jointer) 1 Tenaga.Ah.Muda 123,500.00 61,750.00
- Tukang 3 Orang 1 Tukang 40,500.00 20,250.00
82,000.00
- Supervisi Pabrikan 174,750.00
Main Kontraktor 50% 169,375.00
426,125.00
b Terminasi Kabel Outdoor 20 KV 3 x 150,3 x 240,3 x 300 mm2
Dengan Pola S / E
1 Hari / 4 Jam = 1 Set
- Tenaga Ahli Muda (Jointer) 1 Tenaga.Ah.Muda 123,500.00 61,750.00
- Tukang 3 Orang 1 Tukang 40,500.00 20,250.00
82,000.00
- Supervisi Pabrikan 174,750.00
Main Kontraktor 50% 169,375.00
426,125.00

III MATERIAL PELENGKAP


a Pengadaan dan Pemas.Patok Tanda Kabel 20 KV PLN
- Beton Bertulang 1:2:3 = 0.012 m3 687,193.00 8,246.00
- Angkatan ( Rit ) 1/ 40 Buah 65,000.00 1,625.00
9,871.00
b Pengadaan dan Pemasangan Tanda Mof Kabel 20 KV PLN
- Beton Bertulang 1:2:3 = 0.012 m3 687,193.00 8,246.00
- Angkatan ( Rit ) 1/ 40 Buah 65,000.00 1,625.00
9,871.00
c Pengadaan & Pemasangan Batu Bata Merah ( 5x10x20 )
d Pengad. & Pemas.Timah Lebel Uk.(5cm x 25cm x 1,2mm)
- Harga Timah = Rp.5.200.000/Ton 867.00
- 1 Ton timah Dpt = 6.000 buah Timah lebel
- Bahan timah = Rp.5.200.000/6.000 buah

- Pekerja = 2/ 60 Buah 32,250.00 1,075.00


- Angkutan ( Rit ) = 1/ 4,000 Buah 65,000.00 16,250.00
18,192.00

Catatan :
- Beton 1:2:3 / m3 (100 kg) Rp.687.193,- HS.SIPIL No.34
- Angkutan Rp. 65.000,-/Rit HS.DKI Hal.122 - 15007
- Rp.137,- (Harga Batu Bata Rp.130 + ongkos Pasang Rp.7,-)

e Pengad. & Pemasangan Keramik Tanda Peringan Kabel PLN


- Bahan (0,225 x 0,30) + Produksi 449.00 449.00
- Biaya Penyusutan 104.00 104.00
- Angkutan dari pabrik ke lokasi pekerjaan 260.00 260.00
- Ongkos Pasang 98.00 96.00
(*) Catatan : 909.00
Sumber Analisa dan Pabrikan

f Pengadaan/pemasangan pasir urug darat sepanjang galian


dan lubang sambungan kabel 20 KV PLN. 49,959.00
g Pengad.&Pemas.pipa Buis Beton Konstruksi Khusus O 20cm/mtr 11,102.00
h Pengad.& Pemas.Pipa Pralon O 6 Insi type AW / meter 33,215.00
i Pengad.& Pemasangan Besi Kanal UNP 120.55.7 Double
- UNP .120.55.7 = 26.80 Kg/Mtr Double 112,533.00
j Pengad.& Pemasangan Besi Kanal UNP 140.60.7 Double
- UNP .140.60.7 = 32.00 Kg/Mtr Double 134,368.00

Catatan :
- Rp. 4.200,- Hs Sipil No.44
- Rp. 49.960,- Hs.Sipil No.7
- Rp. 11.100,- HS.Sipil No.50
- Rp. 33.220,- Hs.Sipil No.45

IV PENGEBORAN CROSSING JALAN

a Crossing / Boring Manual


Boring Manual = 1 Hari = 8 meter
- Mandor 1 Mandor 56,250.00 56,250.00
- Tukang Kayu 1 Tk.Kayu 40,500.00 40,500.00
- Pekerja 5 Pekerja 32,250.00 161,250.00
- Papan Penahan Tanah ###m3 572,000.00 720,720.00
- Dolken 5/7 ###batang 3,250.00 39,000.00
- Paku 1 kg 2,600.00 2,600.00
1,020,320.00
Harga Pengeboran Meter = ### 127,540.00
b Boring Mesin(Lihat HS.Boring Mesin/sesuai Kontrak)
c Ijin Boring Jalan Tol Jasa Marga (4 Jalur)
d Ijin Boring Rel Kereta Api/PJKA (Dalam Bestek sewa lahan
tidak dicantumkan dan akan di bayar sesuai realisasi
berdasarkan bukti yang dapat diPertanggungJawabkan
- Biaya Penguatan 1 Spoor
- Biaya Penguatan 2 Spoor
- Biaya Penguatan 3 Spoor
- Biaya Penguatan 4 Spoor

V PERBAIKAN BEKAS GALIAN KABEL ( BERIKUT MATERIAL )


a Tanah Biasa/Tanah Rumput ( Pekerjaan Perbaikan/pemadatan
sudah termasuk dalan pekerjaan galian )
b Tanah Keras/Koral ( Pekerjaan perbaikan / pemadatan sudah
pekrjaan galian
c Conblock/Interblock
- Pengadaan Conblock/Interblock
Abu-abu segi 16 tebal 6 cm = 15 buah 640.00 9,594.00
- Ongkos Kerja = 1 m2 5,005.00 5,005.00
- Lapisan Pasir Tebal 5 cm = 1 m2 12,961.00 3,240.00
- Lapisan Sirtu Tebal 9 cm = 1 m2 16,189.00 4,857.00
(*) Rp. 640 = Rp. 31.980/50 buah 22,696.00
d Ubin Badak
- Ubin badak 30x30 cm adukan 1:3 = 1 m2 26,707.00 26,707.00
Alas Pasir Tebal 5 cm 26,707.00

e Floor Beton Biasa


- Lap.F.Beton Biasa 1:3 Tebal 5 cm = 1.00 m2/(5/100) 216,242.00 10,812.10
- Lapisan Pasir Tebal 5 cm = 1.00 m2/(5/20) 12,961.00 3,240.25
14,052.35

Catatan : (*)
- Lapisan Pasir tebal 20 cm/m2 Rp.12.960 - HS.SKI Hal.36-LBJ.03
- Lapisan Sirtu tebal 30 cm/m2 Rp.16.190-HS.DKI Hal.25-LBJ.13
- Rp. 216.240,- Hs. Sipil No.136
- Rp. 233.750,- Hs. Sipil No. 27
- Rp. 687.190 - Hs. Sipil No. 34
- Rp. 26.710 Hs. DKI Lt.03 +LBJ.04(16.960 + 9.750)
- Rp. 572.000,- Hs.DKI Hal.108 - 3007
- Rp. 3.250,- Hs.DKI Hal.108 - 3034
- Rp. 2.600,- Hs.DKI Hal.118 - 12001
- Rp. 31.980,- Hs.DKI Hal. 31 - TBJ.04
- Rp. 5.000,- Hs.DKI Hal.31 - TBJ.04

f Floor Beton Cor


- Lap.Floor Beton cor 1:3:5 Tebal 7 c = 1.00 m2/(7/100) 233,753.00 11,687.65
- Lapisan Pasir Tebal 15 cm = 1.00 m2/(15/20) 12,961.00 9,720.75
21,408.40
g Beton Bertulang
- Lap.Floor Cor 1:3 tebal 10 cm = 1.00 m2/(10/100) 687,193.00 68,719.30
- Lapisan Pasir Tebal 10 cm = 1.00 m2/(10/20) 12,961.00 6,480.50
75,199.80
h Shand sheet = 1.00 m2 10,920.00 10,926.00
i Aspal Biasa/Penetrasi : 5/20/30
- Lapisan Penetrasi Tebal 5 cm = 1.00 m2 13,313.00 13,313.00
- Lapisan Macadam Tebal 20 cm = 1.00 m2 17,186.00 17,186.00
- Lapisan Sirtu Tebal 30 cm = 1.00 m2 16,190.00 16,190.00
46,689.00
j Aspal Hotmix : 5/5/20/30 ( Jalan kelas III )
- Lapisan Hotmix tebal 5 cm = 1.00 m2 20,744.00 20,744.00
- Lapisan tebal Coating BC.II = 1.00 m2 3,188.00 3,188.00
- Lapisan Penetrasi Tebal 5 cm = 1.00 m2 13,314.00 13,314.00
- Lapisan Macadam Tebal 20 cm = 1.00 m2 17,186.00 17,186.00
- Lapisan Sirtu Tebal 30 cm = 1.00 m2 16,190.00 16,190.00
70,622.00

k Aspal Hotmix : 5/5/20/40 ( Jalan kelas II )


- Lapisan Hotmix tebal 5 cm = 1.00 m2 20,744.00 20,744.00
- Lapisan tebal Coating BC.II = 1.00 m2 3,188.00 3,188.00
- Lapisan Penetrasi Tebal 5 cm = 1.00 m2 13,314.00 13,314.00
- Lapisan Macadam Tebal 20 cm = 1.00 m2 17,186.00 17,186.00
- Lapisan Sirtu Tebal 40 cm = 1.00 m2 22,024.00 22,024.00
76,456.00

l Aspal Hotmix : 5/5/20/70 ( Crossing Open Cut Jalan kelas II )


- Lapisan Hotmix tebal 5 cm = 1.00 m2 20,744.00 20,744.00
- Lapisan tebal Coating BC.II = 1.00 m2 3,188.00 3,188.00
- Lapisan Penetrasi Tebal 5 cm = 1.00 m2 13,314.00 13,314.00
- Lapisan Macadam Tebal 20 cm = 1.00 m2 17,186.00 17,186.00
- Lapisan Sirtu Tebal 70 cm = 1.00 m2 (70/40) 22,024.00 38,541.00
92,973.00
m Aspal Hotmix : 7/5/20/40 ( Jalan kelas I )
- Lapisan Hotmix tebal 7 cm = 1.00 m2 28,972.00 28,972.00
- Lapisan tebal Coating BC.II = 1.00 m2 3,188.00 3,188.00
- Lapisan Penetrasi Tebal 5 cm = 1.00 m2 13,314.00 13,314.00
- Lapisan Macadam Tebal 20 cm = 1.00 m2 17,186.00 17,186.00
- Lapisan Sirtu Tebal 40 cm = 1.00 m2 22,024.00 22,024.00
84,684.00
n Aspal Hotmix : 7/5/20/70 ( Crossing Open Cut Jalan kelas I )
- Lapisan Hotmix tebal 7 cm = 1.00 m2 28,972.00 28,972.00
- Lapisan tebal Coating BC.II = 1.00 m2 3,188.00 3,188.00
- Lapisan Penetrasi Tebal 5 cm = 1.00 m2 13,314.00 13,314.00
- Lapisan Macadam Tebal 20 cm = 1.00 m2 17,186.00 17,186.00
- Lapisan Sirtu Tebal 70 cm = 1.00 m2 (70/40) 22,024.00 38,541.00
101,201.00
o Aspal Hotmix : 7/5/20/30 ( Jalan kelas IV )
- Lapisan Hotmix tebal 3 cm = 1.00 m2 12,517.00 12,517.00
- Lapisan tebal Coating BC.II = 1.00 m2 3,188.00 3,188.00
- Lapisan Penetrasi Tebal 5 cm = 1.00 m2 13,314.00 13,314.00
- Lapisan Macadam Tebal 20 cm = 1.00 m2 17,186.00 17,186.00
- Lapisan Sirtu Tebal 70 cm = 1.00 m2 16,190.00 16,190.00
62,395.00

p Ubin Keramik
- Pasang Keramik 10 x 20 = 1.00 m2 37,999.00 37,999.00
- Pasang Keramik 20 x 20 = 1.00 m2 40,742.00 40,742.00
- Pasang Keramik 30 x 30 = 1.00 m2 43,472.00 43,472.00

q Rumput / Taman
- Perbaikan rumput/taman disesuaikan dengan HS.DKI/Pertamanan
( Dalam bestek biaya perbaikan rumput/taman tidak dicantumkan dan
akan dibayar sesuai realisasi berdasarkan bukti yang dapat di
pertanggung jawabkan )

Catatan (*)
- Rp. 13.320 Hs.DKI hal.30 LAJ.04 - Rp. 12.520,21 Hs.DKI Hal.49 - Rp. 38.000 - HS.Sipil No.84
- Rp. 17.200 Hs.DKI hal.36 LBJ.07 - Rp. 20.745 Hs.DKI Hal.49 - Rp. 40740 - HS.Sipil No.80
- Rp. 10.920, - Hs.DKI hal.36 LBJ.17 - Rp. 28.970 Hs.DKI Hal.49 - Rp. 43.470 - HS.Sipil No.81
- Rp. 16.200 Hs.DKI hal.36 LBJ.13 - Rp. 22.025 Hs.DKI Hal.36 LBJ.14
- Rp. 3.200 - Hs.DKI hal.30 LBJ.07

VI PERBAIKAN BEKAS GALIAN PADA LUB.SAMBUNGAN


- HS. sama dengan HS. Perbaikan Bekas Galian Kabel

VII PERBAIKAN BEKAS GALIAN PADA LUB.PENGEBORAN


- HS. sama dengan HS. Perbaikan Bekas Galian Kabel

VIII PERBAIKAN BEKAS GALIAN PADA LUB.PENYUNTIKAN


- HS. sama dengan HS. Perbaikan Bekas Galian Kabel

IX PEKERJAAN LAIN-LAIN
a Pembuangan tanah bekas galian dengan truck kapasitas 21,125.00
3 s/d 4m3 jarak>20 Km (Volume yang di buang =Lebar galianx
(tinggi lapisan pasir urug + lapisan penutup galian)xpanjang
(trace galian)
b Penjagaan 32,250.00 32,250.00
- 1 Pekerja/Hari
c Penyediaan tenaga untuk bantu pengujian kabel TM PLN
- Pekerja 2 Pekerja 32,250.00 64,500.00
- Instalatir 2 Instalatir 13,000.00 26,000.00
90,500.00
d Pemasangan arrester 20 KV termasuk pentanahan
( Sama dengan HS.SUTM )
- Pmasangan arresterdan pengadaan dudukan arreter 118,872.00 118,872.00
- Pengadaan/Pemasangan pipa arde 0 1,5 inci - 6 mtr 76,713.00 76,713.00
195,585.00
X BIAYA PENGURUSAN IJIN
1 Pemda DKI
a SPS BKJS ( Pengawasan,Perencanaan) 60% RAB perbaikan
b Q. Control pada hotmix/km 1,000/ 100 x 1 Titik 58,570.00 585,700.00
c Q. Control pada hotmix/km 1,000/ 100 x 1 Titik 10,790.00 107,900.00
d Proctor ( b + c )/ Km 75,660.00 151,320.00
e SPS.DTK ( Trace dan Gambar ) 501,260.00 501,260.00
f Pengurusan
2 Diluar Pemda DKI dan Instalasi lain
a Biaya Restribusi 130.00 130.00
b Pengurusan 65.00 65.00
3 Perum Otorita Jatiluhur/ Pengairan
a Biaya sewa lahan (Dalam bestek sewa lahan tidak dicantumkan
dan akan dibayar sesuai realisasi berdasarkan bukti - bukti
yang dapat dipertanggungjawabkan)
b Pengurusan ke Jatiluhur Purwakarta 65.00 65.00

Catatan :
Rp- Rp 21.25,- HS.DKI hal.5-AG.11

XI PENGANGKUTAN KABEL

1 Angkutan kabel TM./Meter


a Angkutan SKTM 10 - 50 meter 86,125.00
b Angkutan SKTM 50 - 100 meter 105,625.00
c Angkutan SKTM 100 - 200 meter 105,625.00

2 Angkutan kabel TM./ haspel 160,225.00


a Angkutan SKTM 1 Haspel 160,255.00
b Angkutan SKTM 2 Haspel 290,225.00
c Angkutan SKTM 3 Haspel
XII DIREKSI KEET
a Pengdaan dan Pemasangan Diteksi Kett 2 x 4 meter = 8 m2
untuk pekerjaan dengan masa kerja :
- 1 s/d 30 HKL = 1/3 x 8 m2 148,772.00 396,725.00
- 31 s/d 180 HKL = 1/2 x 8 m2 148,772.00 595,088.00
- 181 s/d 360 HKL = 1/1 x m2 148,772.00 1,190,176.00

b Pengadaan dan Pemasangan Pagar dari seng


Gelombang ( 1,80 mtr/2 )
- Seng gelombang ( 180 x 90 x 0,2 ) = 2.00 lembar 11,050.00
- Kaso 5/7 = 2.50 batang 6,319.00
- Paku = 0.06 KG. 2,600.00
- Cat = 1.00 KG. 9,100.00
- Pekerja = 0.75 9,750.00
- Tukang Kayu = 0.075 13,000.00

Harga pagar pengaman per meter = Rp. 72.45/1,80 = Rp.40.25,-


karena dianggap 3 kali pakai rusak maka harga pagar pengaman /meter
menjadi Rp.40.040/3

Catatan :
- HS. Angkutan kabel TM sesuai HS.Biaya Jasa Angkutan
- Rp. 193.400,- HS.Sipil No.143 - Rp.14.365,- HS.DKI Hal.118/11035
- 1/3 Direksi Keet dianggap 3 kali pakai Rp.11.830,- HS DKI Hal. 111/6001
- 1/2 Direksi Keet dianggap 2 kali pakai - Rp.2.600 HS.DKI Hal.118-12001
- Rp.8.215 = Rp.591.500/72 batang - HS.DKI Hal.108 - 3027

XIII DOKUMENTASI
a Foto dokumentasi 2 x 36 lembar berwarna
- Film = 1 rool 10,400.00 10,400.00
- Cuci film = 1 roll 2,600.00 2,600.00
- Cetak 2 x 36 = 72 lembar 520.00 37,440.00
50,440.00
b Foto dokumentasi perlembar berwarna
- Film = 1 rool 10,400.00 10,400.00
- Cuci film = 1 roll 2,600.00 2,600.00
- Cetak 1 x 36 = 72 lembar 520.00 18,720.00
31,720.00
c As.build drawing 1 : 200 (1 kalkir + 5 blue print + 1 film )
Sesuai panjang galian, kanal dan crossing.
- Mengambar 1 km Trace
- Tenaga Ahli Muda (D - 2) = 2 jam/ 1 orang 11,089.00 22,178.00
- Petugas Survey (E - 5) = 8 jam/1 orang 9,620.00 76,960.00
- Pekerja = 2 Orang 9,750.00 19,500.00
- Tukang Gambar ( E - 5 ) = 32 Jam 9,620.00 307,840.00
- Kertas kalkir ukuran = 0.30 x 5 3,900.00 19,500.00
- Cetak Blue Print = 5 lembar 3,120.00 15,600.00
- Cetak film Ukuran = 0.30 x 5 19,500.00 97,500.00
559,078.00
Biaya Menggambar / Meter = 559.078/1.000 = 559.00
d As.Build Drawing 1:5000 (1 kalkir + 5 blue print) print gambar spindle
- Tenaga Ahli Muda ( D - 2 ) = 1 jam /1 Orang 11,089.00 11,089.00
- Tukang Gambar (E - 5 ) = 16 Jam/1 Orang 9,620.00 153,920.00
1 13,000.00 13,000.00
- Kertas Kalkir Ukuran = 1 Meter 3,900.00 3,900.00
- Cetak Blue Print 1,950.00 9,750.00
191,659.00
Catatan (*)
- Rp.10.400,- Hs.DKI Hal.122 - 15001
- Rp.2.600,- Hs.DKI Hal.122 - 15002
- Rp.520,- Hs.DKI Hal.122 - 15003
JUMLAH
DIBULATKAN
(Rp.)
05

0.65

18,522

0.72

22,584

30,113

25,031

33,374

5.835
41,718

36,476
45,795

0.825

26,702

3.12

97,866

388,128

2136 3713.3
4408.24 11139.9
7878
11817
3445

0.65

21,022.52

25,354.31

33,805.74

28,262.29
35,790.26

47,103.82

56,524.59

51,950.47

29,875.39

109,868.66

252,360.05

1.5
14196
5569.5
109,868.66

9
14197.5

417,786.06

10504
15756
16,524.27

23,899.39

32,728.51

27,534.38

36,605.82

45,677.27

54,748.71

50,523.91
29,329.42

109,412.49

414,980.25

16,357.65

24,449.16

32,492.20

27,357.15

36,369.51
45,381.88

54,394.25

50,228.53

29,178.87

108,890.55

413,287.52

33585.72

24,404.02 0.072

35,004.92
0.096

45,680.09

37,912.91

49,557.40

60,709.77

72,846.40

66,048.55

43,038.41

141,000.37
352,310.19

79970

0.06
0.44
0.32
0.39981273
32,547.17

46,420.73

59,922.97

49,328.72

63,800.28

78,271.85

92,743.41
83,118.50

61,400.23

189,817.75

399,165.83

22,027.01

33,040.52

44,054.03
35,948.51

47,931.34

59,914.18

71,897.02

64,760.83

39,483.16

143,175.59
347,167.65

10,750.00

3575
15769
1068

4,330.00

5,190.00

5,190.00

426,125.00
426,125.00

426,125.00

9,870.00

9,870.00
136.00

0.03

18,192.00

910.00
127,540.00

91,130.00

2,073,500.00
3,822,000.00
5,505,500.00
7,252,700.00

22,700.00

26,710.00

0.05 10812.1
0.25
14,052.35

0.05
0.75
21,408.40

0.1
0.5
75,199.80
10,930.00

46,700.00

70,630.00

76,460.00
92,980.00

84,680.00

101,201.00

62,390.00

38,000.00
40,740.00
43,470.00
21,130.00

32,250.00

90,500.00

195,585.00

585,700.00
107,900.00
151,320.00
501,260.00

130.00
65.00

65.00

86,125.00
105,625.00
105,625.00

160,225.00
160,255.00
290,225.00
396,725.00
595,088.00
1,190,176.00

22,100.00
15,798.00
156.00
9,100.00
7,313.00
975.00
55,442.00

50,440.00

881.00

559.00
191,659.00
ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA

ANALISA HARGA SATUAN


PEKERJAAN : SALURAN UDARA TEGANGAN MENENGAH
Belum termasuk resiko,over head,keuntungan 10% dan PPN 10%
2004
HARGA BIAYA JUMLAH
NO URAIAN PEKERJAAN SATUAN DIBULATKAN
(Rp.) (Rp.) (Rp.)
1 2 3 4 5
I PEKERJAAN PEMASANGAN
1 TIANG TUNGGAL
1.a Tiang besi 11 meter 200 daN
-Mendirikan Tiang 1/3 Teknisi 56,250 18,750.00
2 Tukang 32,250 64,500.00
1.b Tiang besi 11 meter 350 daN 83,250.00 83,250.00
-Mendirikan Tiang 1/3 Teknisi 56,250 18,750.00
2 1/3 Tukang 32,250 75,250.00
94,000.00 94,000.00
1.c Tiang besi 11 meter 500 daN
-Mendirikan Tiang 1/2 Teknisi 56,250 28,125.00
3 1/2 Tukang 32,250 112,875.00
141,000.00 141,000.00
1.d Tiang besi 13 meter 350 daN
-Mendirikan Tiang 1/2 Teknisi 56,250 28,125.00
3 1/2 Tukang 32,250 112,875.00
141,000.00 141,000.00
1.e Tiang besi 13 meter 500 daN
-Mendirikan Tiang 1/2 Teknisi 56,250 28,125.00
4 Tukang 32,250 129,000.00
157,125.00 157,120.00
1.f Tiang beton 11 meter 200 daN
-Mendirikan Tiang 1/2 Teknisi 56,250 28,125.00
4 1/2 Tukang 32,250 145,125.00
173,250.00 173,250.00
1.g Tiang beton 11 meter 350 daN
-Mendirikan Tiang 1/2 Teknisi 56,250 28,125.00
5 1/2 Tukang 32,250 177,375.00
205,500.00 205,500.00
1.h Tiang beton 11 meter 500 daN
Tiang beton 11 meter 350 daN
-Mendirikan Tiang 1/2 Teknisi 56,250 28,125.00
6 Tukang 32,250 193,500.00
1.i Tiang beton 11 meter 800 daN 221,625.00 221,620.00
-Mendirikan Tiang 1/2 Teknisi 56,250 28,125.00
6 Tukang 32,250 193,500.00
221,625.00 221,620.00
1.j Tiang beton 13 meter 350 daN
-Mendirikan Tiang 1/2 Teknisi 56,250 28,125.00
7 Tukang 32,250 225,750.00
253,875.00 253,870.00
1.k Tiang beton 13 meter 500 daN
-Mendirikan Tiang 1/2 Teknisi 56,250 28,125.00
7 Tukang 32,250 225,750.00
253,875.00 253,870.00
2 PEMASANGAN TIANG BESI & BETON DOUBLE
( 2 X Biaya Pemasangan Tiang Tunggal )
3 PEMBUATAN PONDASI TIANG BESI & BETON

3.a Pondasi Tiang 11 meter Type A


- Galian tanah biasa/rumput 0.9 M3 20,386 18,347.54
- Sirtu dipadatkan 0.67 M3 49,959 33,472.53
- Beton block 1:2:3 0.03 M3 687,193 20,615.79
- Urugan pasir 0.03 M3 49,959 1,498.77
73,934.63 73,930.00
3.b Pondasi Tiang 11 meter Type B
- Galian tanah biasa/rumput 0.6 M3 20,386 12,231.69
- Beton Tumbuk 1:2:3 0.47 M3 216,242 101,633.74
- Beton block 1:2:3 0.03 M3 687,193 20,615.79
- Urugan pasir 0.03 M3 49,959 1,498.77
135,979.99 135,970.00

3.c Pondasi Tiang 11 meter Type C


- Galian tanah biasa/rumput 0.08 M3 20,386 1,630.89
- Beton Tumbuk 1:2:3 0.67 M3 216,242 144,882.14
- Beton block 1:2:3 0.03 M3 687,193 20,615.79
- Urugan pasir 0.03 M3 49,959 1,498.77
168,627.59 173,300.00
3.d Pondasi Tiang 11 meter Type D
- Galian tanah biasa/rumput 0.8 M3 20,386 16,308.92
- Beton Tumbuk 1:2:3 0.47 M3 216,242 101,633.74
- Beton block 1:2:3 0.1 M3 687,193 68,719.30
- Urugan pasir 0.03 M3 49,959 1,498.77
188,160.73 188,160.00
3.e Pondasi Tiang 11 meter Type E
- Galian tanah biasa/rumput 0.8 M3 20,386 16,308.92
- Beton Tumbuk 1:2:3 0.67 M3 216,242 144,882.14
- Beton block 1:2:3 0.2 M3 687,193 137,438.60
- Urugan pasir 0.03 M3 49,959 1,498.77
300,128.43 290,120.00

3.f Pondasi Tiang 13 meter Type A


- Galian tanah biasa/rumput 0.9 M3 20,386 18,347.54
- Beton Tumbuk 1:2:3 0.78 M3 216,242 168,668.76
- Beton block 1:2:3 0.03 M3 687,193 20,615.79
- Urugan pasir 0.03 M3 49,959 1,498.77
209,130.86 68,170.00
3.g Pondasi Tiang 13 meter Type B
- Galian tanah biasa/rumput 0.9 M3 20,386 18,347.54
- Beton Tumbuk 1:2:3 0.54 M3 216,242 116,770.68
- Beton block 1:2:3 0.03 M3 687,193 20,615.79
- Urugan pasir 0.03 M3 49,959 1,498.77
157,232.78 145,980.00
3.h Pondasi Tiang 13 meter Type C
- Galian tanah biasa/rumput 0.9 M3 20,386 18,347.54
- Beton Tumbuk 1:2:3 0.78 M3 216,242 168,668.76
- Beton block 1:2:3 0.03 M3 687,193 20,615.79
- Urugan pasir 0.03 M3 49,959 1,498.77
209,130.86 197,880.00
3.i Pondasi Tiang 13 meter Type D
- Galian tanah biasa/rumput 0.9 M3 20,386 18,347.54
- Beton Tumbuk 1:2:3 0.54 M3 216,242 116,770.68
- Beton block 1:2:3 0.1 M3 687,193 68,719.30
- Urugan pasir 0.03 M3 49,959 1,498.77
205,336.29 194,080.00
3.j Pondasi Tiang 13 meter Type E
- Galian tanah biasa/rumput 0.9 M3 20,386 18,347.54
- Beton Tumbuk 1:2:3 0.78 M3 216,242 168,668.76
- Beton block 1:2:3 0.2 M3 687,193 137,438.60
- Urugan pasir 0.03 M3 49,959 1,498.77
325,953.67 314,700.00
3.k PEMASANGAN TIANG BESI & BETON DOUBLE
( 2 X Biaya pemasangan Tiang Tunggal )
4 PEKERJAAN PENGECATAN TIANG BESI ( Pek. Pemeliharaan )

4.a Tiang Besi 11 Meter 200 daN 5.09 M2 10,257 52,208.00 52,210.00
4.b Tiang Besi 11 Meter 350 daN 5.48 M2 10,257 56,208.00 56,210.00
4.c Tiang Besi 11 Meter 500 daN 5.84 M2 10,257 59,901.00 59,900.00
4.d Tiang Besi 11 Meter 800 daN 6.99 M2 10,257 71,696.00 71,700.00
4.e Tiang Besi 11 Meter 1200 daN 8.31 M2 10,257 85,236.00 85,240.00
4.f Tiang Besi 11 Meter 200 daN Double 10.18 M2 10,257 104,416.00 104,420.00
4.g Tiang Besi 11 Meter 200 daN Double 10.96 M2 10,257 112,417.00 112,420.00
4.h Tiang Besi 11 Meter 200 daN Double 11.68 M2 10,257 119,802.00 119,800.00
4.i Tiang Besi 13 Meter 200 daN 6.17 M2 10,257 63,286.00 63,290.00
4.j Tiang Besi 13 Meter 350 daN 6.88 M2 10,257 70,568.00 70,570.00
4.k Tiang Besi 13 Meter 500 daN 8.68 M2 10,257 68,517.00 68,520.00
4.l Tiang Besi 13 Meter 800 daN 8.50 M2 10,257 87,185.00 87,190.00
4.m Tiang Besi 13 Meter 1200 daN 10.12 M2 10,257 103,801.00 103,800.00
4.n Tiang Besi 13 Meter 200 daN Double 12.34 M2 10,257 126,571.00 126,570.00
4.o Tiang Besi 13 Meter 350 daN Double 13.76 M2 10,257 141,136.00 141,140.00
4.p Tiang Besi 13 Meter 500 daN Double 17.36 M2 10,257 178,062.00 178,060.00

5 PEMASANGAN / PENGADAAN TRAVERS


5.a Travers tunggal: UNP 12-1800 mm
- Pemasangan 1/12 Teknisi 56,250 4,687.50
2/ 3 Tukang 40,500 27,000.00
- Pengadaan 1 Buah 39,000 39,000.00
70,687.50 70,680.00
5.b Travers tunggal: UNP 12-2200 mm
- Pemasangan 1/ 6 Teknisi 56,250 9,375.00
1 1/ 2 Tukang 40,500 60,750.00
- Pengadaan 1 Buah 49,634 49,634.00
119,759.00 119,750.00
5.c Travers tunggal: UNP 12-2400 mm
- Pemasangan 1/ 6 Teknisi 56,250 9,375.00
1 1/ 2 Tukang 40,500 60,750.00
- Pengadaan 1 Buah 54,600 54,600.00
124,725.00 124,720.00
5.d Pemasangan Suspensi Assembly
1/12 Teknisi 56,250 4,687.50
1/ 4 Tukang 40,500 10,125.00
1/ 2 Pekerja 32,250 16,125.00
30,937.50 30,930.00
5.e Pemasangan Small Angle Assembly
1/12 Teknisi 56,250 4,687.50
1/ 3 Tukang 40,500 13,500.00
2/ 3 Pekerja 32,250 21,500.00
39,687.50 39,680.00
5.f Pemasangan Large Angle Assembly
1/12 Teknisi 56,250 4,687.50
1/ 3 Tukang 40,500 13,500.00
1/ 2 Pekerja 32,250 16,125.00
34,312.50 34,310.00
5.g Pemasangan Daed End Assembly
1/12 Teknisi 56,250 4,687.50
1/ 3 Tukang 40,500 13,500.00
1/ 2 Pekerja 32,250 16,125.00
34,312.50 34,310.00
6 PEMASANGAN PIN ISOLATOR
- Pemasangan 1/10 Teknisi 56,250 5,625.00
1/10 Tukang 40,500 4,050.00
9,675.00 9,670.00
7 PEMASANGAN HANG ISOLATOR
- Pemasangan 1/ 8 Teknisi 56,250 7,031.25
1/ 8 Tukang 40,500 5,062.50
12,093.75 12,090.00
8 PEMASANGAN POLE TOP SWITCH
- Pemasangan 1 Teknisi 56,250 56,250.00
6 Tukang 40,500 243,000.00
2 Pekerja 32,250 64,500.00
363,750.00 363,750.00

9 PEMASANGAN PIPA ARDE (1,5 Inc per 6 mtr) per batang 26,000 26,000.00
PENGADAAN PIPA ARDE (1,5 Inc per 6 mtr) per batang 50,718 50,718.00
76,718.00 76,720.00
10 PENARIKAN KAWAT HANTARAN/Gawang (Jarak Mx.40 m)

10.a Kawat A3C 3 x 35 s/d 150 mm2


- Penarikan 1/ 3 Teknisi 56,250 18,750.00
2 Tukang 40,500 81,000.00
1 1/ 3 Pekerja 32,250 43,000.00
142,750.00 142,750.00
10.b Kawat A3C 3 x 35 s/d 150 mm2
- Penarikan 1/ 2 Teknisi 56,250 28,125.00
3 Tukang 40,500 121,500.00
2 Pekerja 32,250 64,500.00
214,125.00 214,120.00
10.c SUTM Twisted Kabel 20 kV
- Penarikan 1/ 2 Teknisi 56,250 28,125.00
4 Tukang 40,500 162,000.00
5 Pekerja 32,250 161,250.00
351,375.00 351,370.00
10.d Pemasangan Terminal Outdoor 150 S/D 300 mm2/Set(=HS.SKTM) 187,343.00

10.e Pemasangan Kawat Pengikat Hantaran Isolator


1/10 Tukang 40,500 4,050.00 4,050.00

11 PEMASANGAN JUMPE /PHASE


- Mandor Pengawas 1/12 Teknisi 56,250 4,687.50
- Tukang 1/12 Tukang 40,500 3,375.00
- Pekerja 1/12 Pekerja 32,250 2,687.50
10,750.00 10,750.00
12 PEMASANGAN LBS TIANG SUTM
- Tenaga Ahli Muda 1/ 2 Hari 112,500 56,250.00
4 Tukang 40,500 162,000.00
2 Pekerja 32,250 64,500.00
- Sewa Crane 6 Jam 39,000 234,000.00
516,750.00 516,750.00
13 PENGADAAN DAN PEMASANGAN TANDA KILAT 20MKV
( 20 cm X 30 cm ), Tebal Plat 4mm
- Pengadaan 11,050 11,050.00
- Ongkos pasang 1,950 1,950.00
13,000.00 13,000.00
14 PENGADAAN DAN PEMASANGAN PENGHALANG PANJAT
- Pengadaan 29,445 29,445.00
- Ongkos pasang 1,950 1,950.00
- Pengelasan + Bahan 31,395.00 31,400.00

15 PEMASANGAN ARRESTER DAN PENGADAAN DUDUKAN


- Tenaga Ahli Muda 1/ 8 Hari 112,500 14,062.50
- Tukang 1 Tukang 40,500 40,500.00
- Pekerja 1/ 2 Pekerja 32,250 16,125.00
- Dudukan Arrester 1 set 56,628 56,628.00
- Angkutan 1/ 2 Rit 65,000 32,500.00
159,815.50 159,810.00
16 PEMASANGAN CUT OUT DAN PENGADAAN DUDUKAN
- Tenaga Ahli Muda 1/ 8 Hari 112,500 14,062.50
- Tukang 1 Tukang 40,500 40,500.00
- Pekerja 1/ 2 Pekerja 32,250 16,125.00
- Dudukan Arrester 1 set 56,628 56,628.00
- Angkutan 1/ 2 Rit 65,000 32,500.00
159,815.50 159,810.00
16A PEMASANGAN TREE GUARD 1 GAWANG
- Teknisi 1/ 3 Teknisi 56,250 18,750.00
- Instalator 1 1/ 3 Tukang 40,500 54,000.00
- Pekerja 1 1/ 3 Pekerja 32,250 43,000.00
115,750.00 115,750.00
17 PEMELIHARAAN JARINGAN
- Majun 1/ 4 Kg 8,000 2,000.00
- YC 8513 type G658SF6 1/ 2 Ltr 75,000 37,500.00
- Pasline 1/ 4 Kg 87,500 21,875.00
- Mandor Pengawas 1/ 2 Teknisi 56,250 28,125.00
- Angkutan 1/ 2 Rit 65,000 32,500.00
122,000.00 122,000.00
18 PEMELIHARAAN CUT OUT
- Majun 1/25 Kg 8,000 320.00
- YC 8513 type G658SF6 3/10 Ltr 75,000 22,500.00
- Pasline 1/ 4 Kg 87,500 21,875.00
- Mandor Pengawas 1/ 3 Teknisi 56,250 18,750.00
- Angkutan 1/ 3 Rit 65,000 21,666.67
85,111.67 85,110.00
19 PEMELIHARAAN GARDY/BOX SEKERING
- Majun 1/ 4 Kg 8,000 2,000.00
- YC 8513 type G658SF6 1/ 2 Ltr 75,000 37,500.00
- Pasline 1/ 4 Kg 87,500 21,875.00
- Mandor Pengawas 1/ 2 Teknisi 56,250 28,125.00
- Angkutan 1/ 2 Rit 65,000 32,500.00
122,000.00 122,000.00

20 PEMELIHARAAN RAK TR PADA GARDU PORTAL


- Majun 1/ 4 Kg 8,000 2,000.00
-Spirtus 1/ 2 Ltr 7,150 3,575.00
- Pasline 1/ 4 Kg 87,500 21,875.00
- Mandor Pengawas 1/ 2 Teknisi 56,250 28,125.00
- Tukang 2 Tukang 40,500 81,000.00
- Pekerja 2 Pekerja 32,250 64,500.00
201,075.00 201,070.00
21 PEMELIHARAAN LBS di SUTM
- Majun 1/ 4 Kg 8,000 2,000.00
- YC 8513 type G658SF6 1/ 2 Ltr 75,000 37,500.00
- Pasline 1/ 4 Kg 87,500 21,875.00
- Mandor Pengawas 1/ 2 Teknisi 56,250 28,125.00
- Tukang 1/ 2 Tukang 40,500 20,250.00
- Pekerja 1/ 2 Pekerja 32,250 16,125.00
125,875.00 125,870.00
22 PENGADAAN DAN PEMASANGAN NOMOR GARDU
- Pengadaan 26,936 26,936.00
- Ongkos Pasang 1,950 1,950.00
28,886.00 28,890.00
II PEKERJAAN PEMBONGKARAN
1 PEMBONGKARAN TIANG BESI DAN BETON
( sama dengan biaya pemasangan )

2 PEMBONGKARAN TIANG BESI DAN BETON sama dengan pemas tiang


DOUBLE ( sama dengan biaya pemasangan ) double yang sesuai ukuran

3 PEMBONGKARAN LBS TIANG SUTM ( sama dengan biaya pasang ) sama dgn by pemasangan

4 PEMBONGKARAN ARRESTER 20,580.00


- Mandor Pengawas 1/ 6 Teknisi 56,250 9,375.00
- Tukang 1/ 3 Tukang 40,500 13,500.00
- Pekerja 1/ 6 Pekerja 32,250 5,375.00
- Angkutan 1/ 6 Rit 65,000 10,833.33
39,083.33 39,080.00
5 PEMBONGKARAN CUT OUT
- Mandor Pengawas 1/ 6 Teknisi 56,250 9,375.00
- Tukang 1/ 3 Tukang 40,500 13,500.00
- Pekerja 1/ 6 Pekerja 32,250 5,375.00
- Angkutan 1/ 6 Rit 65,000 10,833.33
39,083.33 39,080.00
6 PEMBONGKARAN RAK TR PADA GARDU PORTAL
- Mandor Pengawas 1/ 2 Teknisi 56,250 28,125.00
- Tukang 2 Tukang 40,500 81,000.00
- Pekerja 1 Pekerja 32,250 32,250.00
141,375.00 141,370.00

7 PENGISIAN MINYAK TRAFO 1/ 2 Teknisi 56,250 28,125.00


1/ 2 Tukang 40,500 20,250.00
1/ 4 Pekerja 32,250 8,062.50
56,437.50 56,430.00

8 PEMBONGKARAN TERMINATING OUTDOOR 1/ 2 Teknisi 56,250 28,125.00


1/ 2 Tukang 40,500 20,250.00
1/ 4 Pekerja 32,250 8,062.50
56,437.50 56,430.00

9 Bongkar PIN ISOLATOR = biaya pasang x 1.2 3,575 4,290.00 4,290.00


10 Bonkar HANG ISOLATOR = Biaya pasang x 1.2 4,472 5,366.00 5,370.00
11 Bongkar Arde =Biaya pasang x 12 76,713 92,056.00 92,060.00
12 Bongkar Pole Top Switch = Biaya pasang x 1.2 132,860 159,432.00 159,430.00
13 Bongkar SUTM A3C = Biaya Pasang x 1.2 46,579 55,895.00 55,900.00
14 Bongkar SUTM A3CS = Biaya Pasang x 1.2 71,500 85,800.00 85,800.00
15 Bongkar SUTM Twisted = Biaya Pasang x 1.2 122,125 134,550.00 134,550.00

III. PEKERJAAN PERBAIKAN


1 PERBAIKAN TIANG BESI/BETON MIRING
BERIKUT PONDASI
1 . a Pondasi Tiang 11 meter Type A
- Galian tanah biasa/rumput 0.63 m3 20,386 12,843.27
- Sirtu dipadatkan 0.55 m3 49,959 27,477.45
40,320.72 40,320.00
1 . b Pondasi Tiang 11 meter Type B
- Galian tanah biasa/rumput 0.55 m3 20,386 11,212.38
- Beton Tumbuk 1:2:3 0.33 m3 216,242 71,359.86
82,572.24 82,570.00
1 . c Pondasi Tiang 11 meter Type C
- Galian tanah biasa/rumput 0.65 m3 20,386 13,251.00
- Beton Tumbuk 1:2:3 0.47 m3 216,242 101,633.74
114,884.74 114,880.00
1 . d Pondasi Tiang 11 meter Type D
- Galian tanah biasa/rumput 0.56 m3 20,386 11,416.24
- Beton Tumbuk 1:2:3 0.33 m3 216,242 71,359.86
82,776.10 82,770.00
1 . e Pondasi Tiang 11 meter Type E
- Galian tanah biasa/rumput 0.56 m3 20,386 11,416.24
- Beton Tumbuk 1:2:3 0.47 m3 216,242 101,633.74
113,049.98 113,040.00
1.f Pondasi Tiang 13 meter Type A
- Galian tanah biasa/rumput 0.63 m3 20,386 12,843.27
- Sirtu dipadatkan 0.55 m3 49,959 27,477.45
40,320.72 40,320.00
1 . g Pondasi Tiang 13 meter Type B
- Galian tanah biasa/rumput 0.42 m3 20,386 8,562.18
- Beton Tumbuk 1:2:3 0.38 m3 216,242 82,171.96
90,734.14 90,730.00
1 . h Pondasi Tiang 13 meter Type C
- Galian tanah biasa/rumput 0.63 m3 20,386 12,843.27
- Beton Tumbuk 1:2:3 0.55 m3 216,242 118,933.10
131,776.37 131,770.00
1.i Pondasi Tiang 13 meter Type D
- Galian tanah biasa/rumput 0.63 m3 20,386 12,843.27
- Beton Tumbuk 1:2:3 0.38 m3 216,242 82,171.96
95,015.23 95,010.00
1.j Pondasi Tiang 13 meter Type E
- Galian tanah biasa/rumput 0.56 m3 20,386 11,416.24
- Beton Tumbuk 1:2:3 0.47 m3 216,242 101,633.74
113,049.98 113,040.00

2 PERBAIKAN KAWAT KENDOR A3C 3x35 s/d 150 mm2


( 3 Hantaran )
-Perbaikan 1 s/d 5 Gawang 1.2 Pasan 46,579 55,895.00 55,900.00
-Perbaikan 6 s/d 10 Gawang 1.1 Pasan 46,579 55,895.00 55,900.00

3 PERBAIKAN KAWAT KENDOR A3C3 3x35 s/d 150 mm2


( 3 hantaran )
- Perbaikan 1 s/d 5Gawang 1.2 Pasan 89,375 107,250.00 107,250.00
- Perbaikan 6 s/d 10 Gawang 1.1 Pasan 89,375 98,313.00 98,310.00

4 PERBAIKAN SUTM TWISTED 3x70 s/d 90 MM2 ( Gawang )


- Perbaikan 1 s/d 5Gawang 1.2 Pasan 112,125 134,550.00 134,550.00
- Perbaikan 6 s/d 10 Gawang 1.1 Pasan 112,125 134,550.00 134,550.00

5 PERBAIKAN JEMPER SUTM/ Phase


- Tenaga Ahli Muda 3/8 Hari 112,500 42,187.50
0.66 Tukang 40,500 26,730.00
68,917.50 68,910.00

6 PERBAIKAN TRAVES UNP 12 - 1800 mm sama dengan pasang 10,023 10,023.00 10,020.00
7 PERBAIKAN TRAVES UNP 12 - 2200 mm sama dengan pasang 22,204 22,204.00 22,200.00
8 PERBAIKAN TRAVES UNP 12 - 2400 mm sama dengan pasang 22,204 22,204.00 22,200.00
9 PERBAIKAN ISOLATOR TUMPU MIRING sama dengan pasang 3,575 3,575.00 3,580.00

IV LAIN - LAIN
1 PEMBERSIH BENAMG LAYANGAN SUTM/GAWANG
- Pembersihan 1/5 Teknisi 56,250 11,250.00
2/5 Tukang 40,500 16,200.00
27,450.00 27,450.00
2 PEMANGKASAN CABANG POHON SUTM/GAWANG
- Pemangkasan 1/5 Teknisi 56,250 11,250.00
4/5 Tukang 40,500 32,400.00
1 1/3 Pekerja 32,250 43,000.00
3 FOTO DOKUMENTASI : 36 LEMBAR 86,650.00 86,650.00

1/ 1 Rol Film 10,400 10,400.00


1/ 1 Cuci Fil 2,600 2,600.00
36/ 1 Cetak 2 520 18,720.00
31,720.00 31,720.00
- Galian Tanah= 0.65 m3
- Urugan Tanah
= 0.4 m3
- Pemadatan = 0.4 m2
ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA

ANALISA HARGA SATUAN


JASA PEKERJAAN ANGKUTAN
Biaya Belum termasuk resiko,overhead, keuntungan 10% dan PPN 10%
2004
HARGA BIAYA JUMLAH
NO URAIAN PEKERJAAN SATUAN DIBULATKAN
(RUPIAH) (RUPIAH) (RUPIAH)
1 2 3 4 5
1 BIAYA ANGKUTAN
1.1 Pick Up Per Rit 65,000.00 65,000.00
1.2 Truck Kecil /2 - 4 Ton Per Rit 84,500.00 84,500.00
1.3 Truck Kecil /5 - 7 Ton Per Rit 130,000.00 130,000.00
1.4 Truck Tronton /> 7 Ton Per Rit 214,500.00 214,500.00
1.5 Sepeda Motor Per Rit 7,150.00 7,150.00
1.6 Forklift 5 Ton Per Rit 14,300.00 14,300.00
1.7 Forklift 10 Ton Per Jam 21,450.00 21,450.00
1.8 Crane Per Jam 42,900.00 42,900.00

2 ANGKUTAN KUBIKEL ( 1 S/D 3 Bh ) 1 Rit 84,500.00 84,500.00


- Truck Kecil /2 - 4 ton 3 Jam 14,300.00 42,900.00
- Forklift 5 Ton 3 Mandor 56,250.00 168,750.00
- Pelaksana : 0.33 Pekerja 32,250.00 10,750.00
306,900.00 306,900.00
3 ANGKUTAN TRAFO 100 S/D 315 KVA
-Truck Kecil / 2-4 Ton 1 Rit 84,500.00 84,500.00
-Forklift 10 Ton 3 Jam 21,450.00 64,350.00
- Pelaksana 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
209,225.00 209,225.00
4 ANGKUTAN TRAFO 400 s/d 630 KVA
-Truck Kecil / 2-4 Ton 1 Rit 84,500.00 84,500.00
-Forklift 10 Ton 3 Jam 21,450.00 64,350.00
- Pelaksana 1 Mandor 56,250.00 56,250.00
2 Pekerja 32,250.00 64,500.00
269,600.00 269,600.00
5 ANGKUTAN TRAFO 400 s/d 1.250 KVA
-Truck Kecil / 2-4 Ton 1 Rit 84,500.00 84,500.00
-Forklift 10 Ton 3 Jam 21,450.00 64,350.00
=- Pelaksana 1 Mandor 56,250.00 56,250.00
2 Pekerja 32,250.00 64,500.00
269,600.00 269,600.00
6 ANGKUTAN TRAFO 1.000 s/d 1.250 KVA
Truck Tronton /> 7 Ton 1 Rit 214,500.00 214,500.00
-Forklift 10 Ton 3 Jam 21,450.00 64,350.00
-Pelaksana 1 Mandor 56,250.00 56,250.00
2 Pekerja 32,250.00 64,500.00
399,600.00 321,100.00
7 ANGKUTAN RAK TR DAN PERLENGKAPANNYA
Pick Up 1 Rit 65,000.00 65,000.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
125,375.00 125,375.00
8 ANGKUTAN SKTM 10 - 50 METER
Pick Up 1 Rit 65,000.00 65,000.00
- Pelaksana : 1 Mandor 56,250.00 28,125.00
0.67 Pekerja 32,250.00 21,500.00
114,625.00 114,625.00
9 ANGKUTAN SKTM 50 - 100 METER
Truck kecil / 2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 1/ 2 Mandor 56,250.00 112,500.00
2/ 2 Pekerja 32,250.00 64,500.00
261,500.00 261,500.00
10 ANGKUTAN SKTM 100 - 200 METER
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 1 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
144,875.00 144,875.00
11 ANGKUTAN SKTM 1 HASPEL
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Forklift 10 Ton 3 Mandor 56,250.00 168,750.00
- Pelaksana : 2 Pekerja 32,250.00 64,500.00
317,750.00 317,750.00
12 ANGKUTAN SKTM 2 HASPEL
- Truck Besar /5 - 7 Ton 1 Rit 130,000.00 130,000.00
- Forklift 10 Ton 3 Mandor 56,250.00 168,750.00
- Pelaksana 0.50 Pekerja 32,250.00 16,125.00
314,875.00 314,875.00
13 ANGKUTAN SKTM 3 HASPEL
- Truck Besar / > 7 Ton 1 Rit 214,500.00 214,500.00
- Forklift 10 Ton 3 Mandor 56,250.00 168,750.00
- Pelaksana 0.50 Pekerja 32,250.00 16,125.00
399,375.00 399,375.00
14 ANGKUTAN POLE TOP SWITCH 1 s/d 2 BUAH
-Pick Up 1 Rit 65,000.00 65,000.00
- Pelaksana : 1 Mandor 56,250.00 28,125.00
1.50 Pekerja 32,250.00 48,375.00
141,500.00 141,500.00
15 ANGKUTAN ISOLATOR 1 s/d 10 PETI
-Pick Up 1 Rit 65,000.00 65,000.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
125,375.00 125,375.00
16 ANGKUTAN FITTING 1 s/d 30 SET
-Pick Up 1 Rit 65,000.00 65,000.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
125,375.00 125,375.00
17 ANGKUTAN KAWAT A3C 150 mm2 50 - 150 METER
- Pick Up 1 Rit 65,000.00 65,000.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
18 ANGKUTAN KAWAT A3C 150 mm2 150 - 250 METER 125,375.00 125,375.00
-Truck kecil / 2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
144,875.00 144,875.00
19 ANGKUTAN TIANG BESI 9/200 DAN (1 S/D 4 BT)
- Pick Up 1 Rit 65,000.00 65,000.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
125,375.00 125,375.00
20 ANGKUTAN TIANG BESI 9/200 DAN (5 S/D 9 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
144,875.00 144,875.00
21 ANGKUTAN TIANG BESI 9/200 DAN (10 S/D 20 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
144,875.00 144,875.00
22 ANGKUTAN TIANG BESI 9/350 DAN (3 S/D 6 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1.50 Pekerja 32,250.00 48,375.00
161,000.00 161,000.00
23 ANGKUTAN TIANG BESI 9/350 DAN (7 S/D 15 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1.50 Pekerja 32,250.00 48,375.00
161,000.00 161,000.00
24 ANGKUTAN TIANG BESI 9/500 DAN (2 S/D 6 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2 Pekerja 32,250.00 64,500.00
177,125.00 177,125.00
25 ANGKUTAN TIANG BESI 9/500 DAN (7 S/D 10 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2 Pekerja 32,250.00 64,500.00
177,125.00 177,125.00
26 ANGKUTAN TIANG BESI 9/800 DAN (2 S/D 4 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2.50 Pekerja 32,250.00 80,625.00
193,250.00 193,250.00
27 ANGKUTAN TIANG BESI 9/800 DAN (5 S/D 8 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2.50 Pekerja 32,250.00 80,625.00
193,250.00 193,250.00
28 ANGKUTAN TIANG BETON 9/200 DAN (1 S/D 6 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1.50 Pekerja 32,250.00 48,375.00
161,000.00 161,000.00
29 ANGKUTAN TIANG BETON 9/350 DAN (1 S/D 5 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2 Pekerja 32,250.00 64,500.00
177,125.00 177,125.00
30 ANGKUTAN TIANG BETON 9/500 DAN (1 S/D 4 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2.50 Pekerja 32,250.00 80,625.00
193,250.00 193,250.00
31 ANGKUTAN TIANG BESI 11/200 DAN (1 S/D 3 BT)
- Pick Up 1 Rit 65,000.00 65,000.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
125,375.00 125,375.00
32 ANGKUTAN TIANG BESI 11/200 DAN (4 S/D 8 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
144,875.00 144,875.00
33 ANGKUTAN TIANG BESI 11/200 DAN (9 S/D 20 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
144,875.00 144,875.00
34 ANGKUTAN TIANG BESI 11/350 DAN (2 S/D 6 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1.50 Pekerja 32,250.00 48,375.00
161,000.00 161,000.00
35 ANGKUTAN TIANG BESI 11/350 DAN (7 S/D 15 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1.50 Pekerja 32,250.00 48,375.00
161,000.00 161,000.00
36 ANGKUTAN TIANG BESI 11/500 DAN (2 S/D 4 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2 Pekerja 32,250.00 64,500.00
177,125.00 177,125.00
37 ANGKUTAN TIANG BESI 11/500 DAN (5 S/D 10 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2 Pekerja 32,250.00 64,500.00
177,125.00 177,125.00
38 ANGKUTAN TIANG BESI 11/800 DAN (2 S/D 3 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2.50 Pekerja 32,250.00 80,625.00
193,250.00 193,250.00
39 ANGKUTAN TIANG BESI 11/800 DAN (4 S/D 8 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2.50 Pekerja 32,250.00 80,625.00
193,250.00 120,250.00
40 ANGKUTAN TIANG BESI 11/200 DAN (2 S/D 3 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2.50 Pekerja 32,250.00 80,625.00
193,250.00 193,250.00
41 ANGKUTAN TIANG BESI 11/1200 DAN (4 S/D 7 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2.50 Pekerja 32,250.00 80,625.00
193,250.00 193,250.00
42 ANGKUTAN TIANG BESI 13/1200 DAN (1 S/D 10 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1.50 Pekerja 32,250.00 48,375.00
161,000.00 161,000.00
43 ANGKUTAN TIANG BESI 13/350 DAN (1 S/D 8 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2 Pekerja 32,250.00 64,500.00
177,125.00 177,125.00
44 ANGKUTAN TIANG BESI 13/500 DAN (1 S/D 8 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2.50 Pekerja 32,250.00 80,625.00
193,250.00 193,250.00
45 ANGKUTAN TIANG BESI 13/500 DAN (1 S/D 6 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
3 Pekerja 32,250.00 96,750.00
209,375.00 209,375.00
46 ANGKUTAN TIANG BESI 13/1200 DAN (1 S/D 6 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
3.50 Pekerja 32,250.00 112,875.00
225,500.00 225,500.00
47 ANGKUTAN TIANG BETON 11/200 DAN (1 S/D 4 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1.50 Pekerja 32,250.00 48,375.00
161,000.00 161,000.00
48 ANGKUTAN TIANG BETON 11/350 DAN (1 S/D 3 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2 Pekerja 32,250.00 64,500.00
177,125.00 177,125.00
49 ANGKUTAN TIANG BETON 11/500 DAN (1 S/D 3 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2.50 Pekerja 32,250.00 80,625.00
193,250.00 193,250.00
50 ANGKUTAN TIANG BETON 13/200 DAN (1 S/D 3 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2 Pekerja 32,250.00 64,500.00
177,125.00 115,380.00
51 ANGKUTAN TIANG BETON 13/350 DAN (1 S/D 2 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2.50 Pekerja 32,250.00 80,625.00
193,250.00 193,250.00
52 ANGKUTAN TIANG BETON 13/500 DAN (1 S/D 2 BT)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
3 Pekerja 32,250.00 96,750.00
209,375.00 209,375.00
53 ANGKUTAN KABEL TWISTED 3x70+50 mm2 (10 S/D 250 MTR)
- Pick Up 1 Rit 65,000.00 65,000.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
125,375.00 125,375.00
54 ANGKUTAN KABEL TWISTED 3x70+50 mm2 (250 S/D 500 MTR)
- Truck Kecil /2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
144,875.00 144,875.00
55 ANGKUTAN KABEL TWISTED 3x70+50 mm2 1 HASPEL
- Pick Up 1 Rit 65,000.00 65,000.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
- Pekerja 1 Pekerja 32,250.00 32,250.00
- Sewa Forklift 5 Ton 2 Jam 14,300.00 28,600.00
153,975.00 153,975.00
56 ANGKUTAN KABEL TWISTED 3x70+50 mm2 2 HASPEL
- Truck Kecil / 2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
- Pekerja 1 Pekerja 32,250.00 32,250.00
- Sewa Forklift 5 Ton 2 Jam 14,300.00 28,600.00
173,475.00 173,475.00
57 ANGKUTAN KABEL TWISTED 3x70+50 mm2 3 - 4 HASPEL
- Truck Kecil / 2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
- Pekerja 1 Pekerja 32,250.00 32,250.00
- Sewa Forklift 5 Ton 3 Jam 14,300.00 42,900.00
187,775.00 187,775.00
58 ANGKUTAN BC 25 - 50 mm2 S/D 500 Kg
- Pick Up 1 Rit 65,000.00 65,000.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
125,375.00 125,375.00
59 ANGKUTAN BC 25 - 50 mm2 S/D 500 Kg - 1 Ton
- Truck Kecil / 2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
144,875.00 144,875.00
60 ANGKUTAN BC 25 - 50 mm2 2 - 4 HASPEL
- Truck Kecil / 2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
- Forklift 5 Ton 2 Jam 14,300.00 28,600.00
173,475.00 173,475.00
61 ANGKUTAN BC 25 - 50 mm2 5 - 8 HASPEL
- Truck Kecil / 2 - 4 Ton 1 Rit 65,000.00 65,000.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
- Forklift 5 Ton 4 Jam 14,300.00 57,200.00
182,575.00 162,830.00
62 ANGKUTAN KABEL NYFGBY 4x95 mm2, 4x120 mm2,
4x150 mm S/D 50 METER
- Pick Up 1 Rit 65,000.00 65,000.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
125,375.00 125,375.00
63 ANGKUTAN KABEL NYFGBY 4x95 mm2, 4x120 mm2,
4x150 mm S/D 200 METER
- Truck Kecil / 2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
144,875.00 144,875.00
64 ANGKUTAN KABEL NYFGBY 4x95 mm2, 4x120 mm2,
4x150 mm2, 200- 300 METER
- Truck Kecil / 2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
144,875.00 144,875.00
65 ANGKUTAN KABEL NYFGBY 4x95 mm2, 4x120 mm2,
4x150 mm2, 1 - 2 HASPEL
- Truck Kecil / 2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
- Forklift 5 Ton 2 Jam 14,300.00 28,600.00
173,475.00 173,475.00
66 ANGKUTAN KABEL NYFGBY 4x95 mm2, 4x120 mm2,
4x150 mm2, 3 - 4 HASPEL
- Truck Kecil / 2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
- Forklift 5 Ton 3 Jam 14,300.00 42,900.00
187,775.00 187,775.00
67 ANGKUTAN APP TYPE KHUSUS IB,IC,IFF: (1 - 4 Buah)
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
- Sepeda Motor 1 Rit 7,150.00 7,150.00
67,525.00 67,525.00
68 ANGKUTAN APP 1.A (1 - 6 Buah)
- Pick Up 1 Rit 65,000.00 65,000.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
125,375.00 125,375.00

69 ANGKUTAN APP TYPE KHUSUS IB,IC,IIF : ( 1 - 4 Buah)


- Pick Up 1 Rit 65,000.00 65,000.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1 Pekerja 32,250.00 32,250.00
125,375.00 86,130.00
70 ANGKUTAN UPS 40 KVA, 1 BUAH
- Pick Up 1 Rit 65,000.00 65,000.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2.50 Pekerja 32,250.00 80,625.00
173,750.00 173,750.00
71 ANGKUTAN UPS 100 KVA, 1 BUAH
- Tuck Kecol / 2 - 4 Ton 1 Rit 84,500.00 84,500.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
2.50 Pekerja 32,250.00 80,625.00
193,250.00 193,250.00
72 ANGKUTAN GENSET 10 S/D 50 KVA, 1 BUAH
- Pick Up 1 Rit 65,000.00 65,000.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
1.50 Pekerja 32,250.00 48,375.00
141,500.00 141,500.00

73 ANGKUTAN PERALATAN KONTROL

a. Pengangkutan Lemari Spindel


a). Pick Up 1 Rit 65,000.00 65,000.00
b). Sewa Forklift 5 Ton 3 Jam 14,300.00 42,900.00
- Pelaksana : 0.50 Mandor 56,250.00 28,125.00
3 Pekerja 32,250.00 96,750.00
232,775.00 232,775.00

b. Pengangkutan Lemari RTU = Angkutan Lemari Spind 148,525.00 148,525.00


c. Pengangkutan Lemari MDF = Angkutan Lemari Spind 148,525.00 148,525.00
d. Pengangkutan Lemari Rectifier Battery 48 V/110 Volt = Angkutan Lemari Spind 148,525.00 148,525.00
e. Pengangkutan Lemari Box Radio Key Point = Angkutan Lemari Spind 148,525.00 148,525.00
f. Pengangkutan Lemari Box Absorber = Angkutan Lemari Spind 148,525.00 148,525.00
g. Pengangkutan Lemari Box DS = Angkutan Lemari Spind 148,525.00 148,525.00

You might also like