You are on page 1of 4

CorrosionManagement | May/June 2016

TECHNICALARTICLE TECHNICALARTICLE

Enhancing Pipeline Integrity Using External


Corrosion Direct Assessment: Case Study of
United Energy Pakistan
Fahad Muhammad and Sheikh Muhammad Abdullah: Engineering Services Department, United Energy Pakistan

Abstract
External corrosion is a well-known threat to
structural integrity of buried pipelines in the
oil and gas industry. Regulatory authorities
along with a current slump in oil and gas prices
are putting increasing pressure on pipeline
operators to safeguard pipeline integrity and
minimize maintenance cost. NACE standard
SP0502 completely defines the pipeline
external corrosion management, though, the
order in which pipeline defect locations are
interrogated is at the discretion of pipeline
operators. This paper presents a novel cost
effective approach to quantify the pipeline
defects severity and to prioritize the pipeline
excavations comprising minimal number of
digs to precisely locate the pipeline defects.
Buried carbon steel oil and gas pipeline
network spanning over 70 kilometres is
assessed to evaluate and obviate the threat
of external corrosion. Alignment of indirect
Figure 1: Anomalies Record (2012-2015).
inspection data obtained from multiple indirect
inspection surveys is also presented. Finally,
the proposed criterion is assessed and found
the safety, environmental performance and 2.1.1 Data Collection
economics of pipelines operations.
to be very effective showing 50% reduction in
Pipeline External Corrosion Direct Assessment
and Pipeline Risk
cost and improved pipeline integrity.
methodology is described in NACE SP0502.This Ranking
1. Introduction standard practice does not provide absolute For current work, a comprehensive pipeline
Structural integrity of buried onshore pipelines severity classification and excavation criteria, risk ranking assessment was carried out in
in the oil and gas industry is of particular allowing pipeline operator to classify defects which the data related to pipeline design,
importance as their failure can result in severity and develop excavation prioritization construction, soil, environment, corrosion
safety hazards, substantial economic losses on their judgement and in accordance with the control, cathodic protection and operational
and environmental damage. United Energy specific conditions of the pipeline. history is taken into account in combination
Pakistan (UEP) is a private firm operating in The objective of this paper is to present a with the data which has an impact on business,
Pakistan primarily focusing on exploration and workable newly developed approach that can environment and people. The pipelines risk
production of oil and gas in the Sind province be used as a basis to prioritize the excavations is calculated based on the probability and
of Pakistan having buried onshore pipeline resulting in an enhanced pipeline integrity consequence of a corrosion event. Out of 40
networks spanning over 1100 kilometres. spending minimal cost. pipelines, 10 high-risk pipeline regions were
Under the Integrity Management System, UEP shortlisted through a rigorous risk-ranking
uses Pipeline Integrity Management Scheme 2. The Four-Step process and categorized into different regions
(PIMS) to identify the potential threats to Methodology (discussed later). The regions consist of around
the pipelines due to external corrosion and 70 kilometres of buried onshore CS pipelines
As stated in SP0502, ECDA involves four steps
their continuous mitigation. As a part of PIMS, of different lengths. All pipelines shortlisted are
which are discussed in detail in the subsequent
External Corrosion Direct Assessment (ECDA) of API 5 L grade, coated with fusion bonded
sections.
is carried out on an annual basis in UEP to epoxy.
boost pipelines integrity in accordance with 2.1 Step 1: Pre Assessment 2.1.2 ECDA Feasibility
the NACE standard SP0502. This step requires sufficient amount of data
The historical distribution of major pipeline collection, integration and examination Assessment
defects recorded on the pipeline system of UEP related to pipeline construction, operations The data gathered in the data collection phase
operations is summarized in Figure 1. Given and environment to decide whether ECDA is was amalgamated and scrutinized to check
the share of external corrosion, it is apparent feasible for the pipeline to be evaluated along for any condition, which can make the use
that appropriate external corrosion control with the selection of indirect inspection tools. of indirect inspection tools impracticable or
methods would have a foremost influence on could impede the ECDA application, such as

12
TECHNICALARTICLE TECHNICALARTICLE

Cathodic
Construction Prior
S.No Pipeline Diameter (in) Length (m) Material & Coating Protection
Year Corrosion
Type

1 Region A 6 7,561 1996 API 5L-X46, FBE No ICCP


2 Region B 8 7,052 1994 API 5L-X46, FBE Yes ICCP
3 Region C 8 4,188 1999 API 5L-X46, FBE No ICCP
4 Region D 6 5,000 1997 API 5L-X46, FBE Yes ICCP
5 Region E 4 5,029 2007 API 5L-X52, FBE No ICCP
6 Region F 6 4,878 2003 API 5L-X46, FBE Yes ICCP
7 Region G 8 16,816 1997 API 5L-X46, FBE No ICCP
8 Region H 6 5,945 1997 API 5L-X46, FBE Yes ICCP
9 Region I 8 2,058 2002 API 5L-X46, FBE No ICCP
10 Region J 6 12,195 1997 API 5L-X46, FBE No ICCP
Table 1- ECDA Regions Details.

pavements, frozen grounds and inaccessible provide the pipe to soil potential profile of the builds a solid footing for direct examinations.
areas. However, majority of the pipeline pipeline, CIPS is performed to explore the ON After identification of the faults, they are
regions were found to be feasible for ECDA and Instant-OFF potentials over the entire classified in accordance with their severity. For
assessment, except a few locations such as pipeline regions. In addition, CIPS also gauges this study, a stringent severity classification
paved road crossings and water crossings the performance of the CP system. In short, criterion is devised and incorporated into
which may pose a challenge to apply ECDA the tools were selected such that the strength prioritization criterion shown in Table 2.
and requires an alternate integrity assessment of one tool compensates the limitations of The criterion provides specific quantifiable
method extending beyond the scope of another. and explicitly definable conditions and is
this study. An ECDA region is a region that has similar developed on the basis of previous corrosion
physical characteristics, corrosion histories, activities on pipelines, CP system performance
2.1.3 Selection of expected future corrosion conditions, and uses and pipelines physical and operational history,
Indirect Inspection the same indirect inspection tool. In this work, complying with one of the aims of this
the selected pipeline regions have different work. A similar criterion has been described
Tools & ECDA Regions physical conditions, cathodic protection, previously [1]; however, more realistic and
Determination corrosion history and construction year and stringent numbers are used here for accurate
Consistent with SP-0502, the regions where are all buried in dissimilar soil environment. classification according to specific pipeline
ECDA is to be applied, a minimum of two Therefore, 10 different non continuous regions conditions.
indirect inspections tools should be selected. are defined, details of which is presented in
However, based on their ability to accurately Table 1. 2.2.1 Defect
detect coating defects and corrosion activity,
2.2. Step 2: Indirect Prioritization
the following three techniques used for
indirect inspections are chosen from the ECDA Inspections Criterion
tools selection matrix given in SP 0502: Faulty regions identified during the indirect
The central focus of indirect inspection is
inspection step necessitate efficient
Pipeline Current Mapper (PCM) to identify and address coating faults and
excavations to expose the pipe surface so that
Direct Current Voltage Gradient (DCVG) corrosion activity along with the other
measurements and pipeline health assessments
associated defects without exposing the pipe
Close Internal Potential Surveys (CIPS) [7] can be made, which is the principal target of the
surface. This is a key stage as it produces a
These tools are selected based upon the direct examinations. Based on the likelihood
direct examination plan that will minimize
individual strengths associated with each tool. of current corrosion activity, the magnitude
the direct examination costs while achieving
PCM works on a current attenuation principle and severity of prior corrosion and approach
the required confidence level. In this work,
and helps to detect the exact pipeline location, of optimal digs and reduced cost, severity
the three tools mentioned above were used
burial depth, casing shorts, unauthorized classification and prioritization criterion is
one by one between short time intervals
pipeline connections and spots the area of presented in this study as shown in Table 2. The
over the entire buried length of the pipeline
reduced coating quality, though it does not severity and prioritization crieterions are both
to circumvent any changes in the survey
identifies the exact coating defect location incorporated into a single matrix, contrary to
conditions such as change in temperature and
unless a secondary holiday pinpoint survey is the previously proposed criterions which are
soil moisture content. The complete survey
used. On the other hand, DCVG overcomes the described separately [1],[2]. Referring to Table
on a 70 Km pipeline network took around
limitation associated with the PCM, and is used 2, the results obtained through DCVG and
25 days. Data collected from three surveys
to pin point the coating defects by providing PCM are plotted against CIPS to prioritize the
during indirect examinations were pooled
the approximate defect size, defect severity pipeline excavation. The pipeline prioritization
and evaluated in combination with each
estimation and corrosion state of a coating and excavation scheme (dig & no dig areas)
other. It is noteworthy that correlating and
holiday. Moreover, the DCVG survey is said is clearly defined in the criterion. Table 2 also
aligning the data gathered from three different
to locate the coating holidays more precisely contains the notes describing the excavation
surveys plays a pivotal part in determining
than any other survey [7]. Since DCVG doesn’t prioritization.
the effectiveness of indirect examinations and

13
CorrosionManagement | May/June 2016
TECHNICALARTICLE TECHNICALARTICLE

Table 2- Decision Matrix: Severity Classification and Excavation Prioritization Criterion.

2.3. Step 3: Direct


Examinations
2.3.1 Pipeline
Excavations and Data
Analysis
In agreement with the decision matrix
presented in Table 2, digs were performed on
each pipeline region. For region F (refer Table
1 for description), all digs fits as an immediate
excavation prioritization. Alignment of the
data acquired from three different indirect
inspection surveys are plotted against the
pipeline distance measured from riser first
flange as shown in Figure 2. The exposed pipe
condition is also presented at the corresponding
inspection digs. The ON potentials were well
above -1000mVCSE throughout the entire
pipeline. However, the OFF potentials were
less than 850mV at some defect locations.
Moreover, the current loss curve obtained
through PCM shows a gradual loss with no
abrupt current dips indicating a satisfactory Figure 2- Combined Graph and Aligned Data Analysis.
overall pipeline coating. The pipeline was lead to 49% DCVG defect; furthermore, a itself was corroding, hence, indicating an
exposed from five different locations which few excavation cuts were also found at this anodic area. At the three remaining digs,
were selected in accordance with the proposed dig. Interestingly, at dig-2, a pilferage clamp coating damages and disbonded coating in the
criterion. At four out of five digs, coating defects was found. Indirect examination at this defect form of flakes were found, along with blister
were found. As shown in Figure 2, an anchor location has shown a DCVG defect of 38% formation near the decayed coating area with
block (pre-casted steel reinforced concrete) with minor current loss rate and OFF potential no metal loss, thereby signifying an acceptable
was also found at dig-1which could possibly value of around -790mV. The pilferage clamp CP performance. In addition, water was found

14
TECHNICALARTICLE TECHNICALARTICLE

inside the blisters having a basic pH which determining the overall effectiveness of the approach of ECDA survey technique has been
might have caused the coating disbondment. ECDA process. Here, except at two locations demonstrated as well, which when used with
All the coating damage was repaired through no external corrosion damage was found. As the proposed decision matrix has resulted in a
liquid epoxy coat. After the coating repair, stated in SP0502, the reassessment intervals at dig efficiency of 97%.
cathodic protection current demand of the the corrosion areas were taken as one-half of This study is intended to provide the onshore
pipeline was decreased by 20%. Similar data the calculated remaining life. To estimate the pipeline operators with a value adding tool to
analysis and repair methodology was adopted remaining life due to corrosion damage, Fitness evaluate the condition of their buried pipelines
for the 9 remaining pipeline regions. Overall for Service evaluation was also performed for in an effective and consistent way. The use
cost of performing ECDA is around $1000 corrosion areas using API 579. of this technique will help pipeline operators
per Km which includes indirect surveys, dig In order to validate the ECDA effectiveness, to perform a correct interpretation of ECDA
excavations and inspection and coating repair one dig was additionally performed on all survey results and to make the right selection
cost. At the locations where corrosion activity ECDA regions categorized as “monitor” and “no for inspection dig locations, resulting not only
was found, calculations were performed to indication” in Table 2. The excavated locations in cost saving but will also improve the overall
estimate their remaining operational life along were found to be defect free, thus legitimizing integrity of the pipeline.
with Root Cause Analysis of the events to the success of the complete process.
mitigate any corrosion in future. 4. Acknowledgements
2.4.1 Continuous We would like to express our sincere gratitude
2.3.2 Assessment of
Improvement in Pipeline to the management of United Energy
Proposed Severity Pakistan for their support. Also, the work of
Integrity the contractors involved in this process is
Classification ECDA is a continuous improvement process gratefully acknowledged.
and Prioritization and its effectiveness is established on a
long-term basis. Compare to previous ECDA References
Criterion surveys, the survey under discussion is far [1] Corrpro, 2010. Improvement to the External Corrosion
The defect severity and prioritization criterion is more effective and efficient as presented in Direct Assessmemnt Process, Houston, Texas: Corrpro
evaluated to check if it is a true representation the Figure below. Companies, Inc..
of the magnitude of corrosion and coating
As shown in Figure 4, significant cost reduction [2] Corrpro, 2010. Improvement to the External Corrosion
damage found after pipeline excavations.
of 50% has been attained along with a dig Direct Assessmemnt Process (Severity Ranking of ECDA
After performing the schedule and immediate
efficiency of 97% as coating and corrosion Indirect Inspection Indications), Houston, Texas: US
excavations, the findings of the entire activity
damage is found at almost all digs. The dig Department of Transportation.
with reference to the actual corrosion and
efficiency achieved in this work is exceptional [3] Corrpro, 2010. Improvements to the External
coating damage found is summarized in Figure
3 below. Corrosion Direct Assessment Process (Cased Pipes),
Houston, Texas: US Department of Transportation.
As shown above, the proposed criterion is
found to be very effective. Though, there is [4] Kowarski, A. R., 2011. Direct Assessment Techniques
one location where criterion disagrees with for Underground Petroleum Pipelines. Paris, International
the practical damage found, which could Gas Union Gas Research Conference.
[5] Melo, C. A., 2010. ECDA Implementatiion on EDEN
YUTURI 18” Gathering Pipelines. Quito, Ecuador, s.n.
[6] Os, M. V., 2008. External Corrosion Direct Assessmengt
at Gasunie. Paris, International Gas Union Research
Conference.
[7] SP0502, N., 2012. Pipeline External Corrosion Direct
Assessment Methodology, Houston, Texas: NACE.

Figure 4 - Continuous Improvement in Pipeline Integrity.

when compare to ECDA 2014 (88%) and

For all the latest


ECDA 2013 (84%).
Figure 3- Assessment of Severity Classification & Excavation
Criterion. Finally, during ECDA 2015 comparatively
be possibly due to spatial errors during the
excavations. Additionally, ECDA is a continuous
less numbers of total corrosion and coating
damages were found which were addressed news, events
improvement process, therefore the defect
severity and prioritization criterion may be
timely signposting an improved net
management of corrosion and enhanced and debates
join us on
pipeline integrity.
adjusted in the future for more accurate
results. 3. Summary and
2.4 Step 4: Post Conclusions
Assessment A decision matrix for the classification of
defect severity and dig excavation priority is
The post assessment activity comprises of
presented to support the ECDA exercise on
defining the re-assessment intervals and
buried onshore pipeline systems. An innovative

15

You might also like