Oil well construction requires several casing string to reach a planned depth of a well therefore we will
discuss about the basic of each casing string used in the oil wells.
In this article, we will cover the following strings;

Conductor Casing
Surface Casing (Structural Casing)
Intermediate Casing
Casing Liner
Production Casing
Production Tubing

The illustrations below (Figure 1 and Figure 2) are schematics of oil well in general. We will go into
details of each casing/tubing based on these two images.

Figure 1 – Casing and Tubing Schematic without Liner


Figure 2 – Casing and Tubing Schematic with liner

Conductor Casing

The conductor casing is the first string run in the well and its depth range is 40 to 300 ft. In soft formation
areas or offshore environment, the conductor pipe is hammered down by a large pipe hammer. In hard
rock areas, driving the casing is not doable therefore a larger hole must be drilled to landing depth
before running and cement this casing.
Figure 3 – Conductor Casing

Functions of conductor casing are as follows;

Protect formation washout at the shallow depth


Minimize loss circulation in shallow zones
Provide a fluid conduit from the bit to the surface
Minimize hole-caving issues. Unconsolidated formations (gravel) will fall into the well resulted in
drilling issues.

Surface Casing (Structural Casing)

In some drilling areas, it may require an additional casing string between conductor casing and surface
casing. This casing is called “Surface Casing (Structural Casing)” and it is typically run from 500 ft to
1,000 ft. This casing cannot be driven into the well so it requires drilling a hole before running it.

Figure 4 – Surface Casing (Structural Casing)

Functions of surface casing are as follows;

Minimize lost circulation in a shallow depth


Provide a fluid conduit
Provide wellbore integrity to prevent hole-caving
Cover weak formations when there is a well control situation
Support blow out preventer (BOP) for well control
Cover shallow fresh water zones from contamination

Intermediate Casing

The intermediate casing is run after surface casing and there can be several intermediate casing in one
well. Drilling intermediate section most of the time requires higher mud weight than normal pressure
gradient therefore the primary function of this casing is related to control high mud weight and formation
pressure.
Figure 5 – Intermediate Casing

Functions of intermediate casing are listed below;

Protect weak zones at shallower depth while drilling with higher mud weight
Provide wellbore integrity for well control
Isolate some formations which can cause drilling issues as lost circulations, shale sloughing, etc.
Support weight of well control equipment
Provide a fluid conduit

Casing Liner

Casing liner is widely used in the industry because it is a cost-effective way to run a casing string across
open hole length without running all string to the surface. The casing liner can be utilized as
intermediate casing or production casing. The casing liner is run into the shallower casing string and the
overlap between two strings is typically around 300 – 500 ft.

Figure 6 – Casing Liner

Production Casing/Liner
This casing string/liner can be set at a depth above, midway or below the pay zone depending on
completion strategies. Primary cement job is very critical for this string because it affects production from
the well.

Figure 7 – Production Casing


Figure 8 – Production Liner

Functions of production casing are listed below;

Isolate production zone(s) from other formations


Protect completion equipment
Provide a conduit for reservoir fluids
Provide annular passage for gas lift injection
Contain formation pressure in case of tubing leak

Production Tubing

The production tubing is run into the well after the production casing is in-place and all the completion
equipment is run with this string downhole. The tubing must be strong enough to support production
load and it should be able to workover in the future.

Figure 9 – Production Tubing

Functions of production tubing are listed below;


Provide the conduit for oil, gas, water from formation(s)
Protect the production casing from corrosion, wear and deposition from the reservoir fluids

Ref Book -> Applied Drilling Engineering Book special offer

Submit Your Abstracts Casing Size Selection Casing drilling Casing Design
– How To Select Underreamer - Block- Overview – Overall
Casing Size to Match... Type Process of How To...
Ad ADIPEC, Abu Dhabi drillingformulas.com Ad drillstar-industries.com drillingformulas.com

Engineering Casing Seat Selection Minimum strength to What factors must be


consulting – How To Select support casing string considered when
Casing Setting Depth designing a...

Ad www.spizuoco.com drillingformulas.com drillingformulas.com drillingformulas.com

Related Post
Important Material Properties of Tubular and Compl...
It is imperative to understand mechanical properties of tubular because it involves the safety structure of the well. Failure in completion
can cause ...

Casing Size Selection – How To Select Casing...


We’ve learnt several topics in regard to casing design and this article will demonstrate you how to determine casing size in the well.
Casing size ...

Tubular Material Selection for HTHP Well with Exam...


This article demonstrates how to select material that will be suitable for high pressure, high pressure and corrosive environment. The
material chart ...

Piston Effect on Tapered String and Expansion Devi...


In many situations, a completion string may consist of several size of strings and components so total axial force must be carefully
considered by app...

Share the joy


837

0
Shares
Tagged casing design, Oil Well Casing, tubing. Bookmark the permalink.

About DrillingFormulas.Com

Working in the oil field and loving to share knowledge.

View all posts by DrillingFormulas.Com →

« Basic Pressure Control In Drilling Piper Alpha The Biggest Oilfield Catastrophe –
Oilfield Incidents in The Past »

One Response to Basic Understanding of Oil Well Casing and


Tubing

M.Nasir Qidwai. NOVEMBER 5, 2016 AT 6:45 PM

Very helpfull side for students … Casing program is explained excellently …

Reply

Leave a reply

Default Comments Facebook Comments (0)


(1)
Your email address will not be published. Required fields are marked *

Comment
Name *

Email *

Website

Post Comment

Categories

Select Category 

Get Drilling Formulas Sheet For Free

Subscribe to Get Free Calculation Sheet

email address

Click Here

Search on Drillingformulas.com

Search
Custom Search
Well Control One Page
Drillingformulas.com on Facebook

‫اإلعجاب بالصفحة‬

.‫كن أول المعجبين بهذا من بين أصدقائك‬

OilfieldPix.com
Oilfield Acronyms

Recent Comments

Arabindra Dutta on Offshore Crane Failure Case Study

Kelvin on Cutting Carrying Index – Simple Tool To Determine Hole Cleaning

Chaouadi on Basic Understanding of Underbalanced Drilling

Mrinmoy on Basic Understanding About Positive Displacement Mud Pumps in Drilling

Industry

jilani on Pressure and Force Relationship and Its Application


Drilling Formulas and Drilling Calculations | Powered by Mantra & WordPress.

You might also like