Oil well construction requires several casing string to reach a planned depth of a well therefore we will
discuss about the basic of each casing string used in the oil wells.
In this article, we will cover the following strings;
Conductor Casing
Surface Casing (Structural Casing)
Intermediate Casing
Casing Liner
Production Casing
Production Tubing
The illustrations below (Figure 1 and Figure 2) are schematics of oil well in general. We will go into
details of each casing/tubing based on these two images.
Conductor Casing
The conductor casing is the first string run in the well and its depth range is 40 to 300 ft. In soft formation
areas or offshore environment, the conductor pipe is hammered down by a large pipe hammer. In hard
rock areas, driving the casing is not doable therefore a larger hole must be drilled to landing depth
before running and cement this casing.
Figure 3 – Conductor Casing
In some drilling areas, it may require an additional casing string between conductor casing and surface
casing. This casing is called “Surface Casing (Structural Casing)” and it is typically run from 500 ft to
1,000 ft. This casing cannot be driven into the well so it requires drilling a hole before running it.
Intermediate Casing
The intermediate casing is run after surface casing and there can be several intermediate casing in one
well. Drilling intermediate section most of the time requires higher mud weight than normal pressure
gradient therefore the primary function of this casing is related to control high mud weight and formation
pressure.
Figure 5 – Intermediate Casing
Protect weak zones at shallower depth while drilling with higher mud weight
Provide wellbore integrity for well control
Isolate some formations which can cause drilling issues as lost circulations, shale sloughing, etc.
Support weight of well control equipment
Provide a fluid conduit
Casing Liner
Casing liner is widely used in the industry because it is a cost-effective way to run a casing string across
open hole length without running all string to the surface. The casing liner can be utilized as
intermediate casing or production casing. The casing liner is run into the shallower casing string and the
overlap between two strings is typically around 300 – 500 ft.
Production Casing/Liner
This casing string/liner can be set at a depth above, midway or below the pay zone depending on
completion strategies. Primary cement job is very critical for this string because it affects production from
the well.
Production Tubing
The production tubing is run into the well after the production casing is in-place and all the completion
equipment is run with this string downhole. The tubing must be strong enough to support production
load and it should be able to workover in the future.
Submit Your Abstracts Casing Size Selection Casing drilling Casing Design
– How To Select Underreamer - Block- Overview – Overall
Casing Size to Match... Type Process of How To...
Ad ADIPEC, Abu Dhabi drillingformulas.com Ad drillstar-industries.com drillingformulas.com
Related Post
Important Material Properties of Tubular and Compl...
It is imperative to understand mechanical properties of tubular because it involves the safety structure of the well. Failure in completion
can cause ...
0
Shares
Tagged casing design, Oil Well Casing, tubing. Bookmark the permalink.
About DrillingFormulas.Com
« Basic Pressure Control In Drilling Piper Alpha The Biggest Oilfield Catastrophe –
Oilfield Incidents in The Past »
Reply
Leave a reply
Comment
Name *
Email *
Website
Post Comment
Categories
Select Category
email address
Click Here
Search on Drillingformulas.com
Search
Custom Search
Well Control One Page
Drillingformulas.com on Facebook
اإلعجاب بالصفحة
OilfieldPix.com
Oilfield Acronyms
Recent Comments
Industry