AMITY SCHOOL OF ENGINEERING & TECHNOLOGY

Weekly Progress Report (WPR)


For the week commencing: 8 June 2015

WPR- 3 Enrollment number:


A2315813033333
Student Name: ss
Program: B.Tech (Civil Engineering)
Company Name: Central Public Work Department (CPWD)

Industry Guide’s Name: Mr. Sanjay Kumar(AEE)


Faculty guide’s name:
Project Title: Construction of Supreme Court building
Targets for this week:
1. Performing on Site tests in Lab (eg- moisture content, sieve analysis, Cube testing
etc).
2. Understanding its procedure and necessity of these Tests.
Achievements for this week:
• Successfully performed all tests listed and noted their Results.
• Was able to understand its procedure and their necessity.
Future work plans:
1. Studying, designing and checking BBS of certain beams of basement B1 & B2 of
Block-B

WPR of Week 1st (08/06/2015-14/06/2015)

Enrollment Number: Programme: B.Tech-Civil

Summer Internship Subject Area: Construction of Supreme Court building


Week’s Summary

Days/Time

Monday Brief introduction to the Tests, studying its apparatus and theory.

Tuesday Performing the test sieve analysis of Aggregate.

Wednesday Performing the tests (ie, Moisture content, sieve analysis) of Sand.

Thursday Performing the Cube Test of concrete and test to determine Slit content of
sand.

Friday Creating Lab Reports of Results of these tests and understanding its
procedure and necessity.