PROPOSAL
AMENDMENT III
FOR
Between
PT PLN (Persero)
and
-
AMENDMENT III
Of
NORTH WEST SUMATERA INTERCONNECTOR
TRANSMISSION LINE CONSTRUCTION PROJECT
With regard to the contract No. 038.PJ/041/DIR/2013 dated March 06, 2013 for Package 2 :
275 kV Transmission line (hereinafter referred to as the “CONTRACT” ), between :
PT. Perusahaan Lisrik Nasional (Persero), a corporation incorporated under the laws of
Indonesia and having its principal place of business at Jl. Trunojoyo Blok M I/135,
Kebayoran Baru, Jakarta Selatan 12160 – Indonesia.
(Hereinafter called “the Employer”)
Of the first party
and
CONSORTIUM OF
Hyundai Engineering & Construction Co., Ltd, A corporation organized and existing
under the laws of the Republic of Korea having its Business Office at Hyundai Building,
140-2 Kye-dong, Jongno-gu, Seoul, 110-920, Korea
(Hereinafter called “The Contractor”) as leader of Consortium
PT. Multi Fabrindo Gemilang, A corporation organized and doing business under the
Law of Republic of Indonesia with its registered business office at MEDCO Building II,
3rd Floor, Jl. Ampera Raya No. 20 Cilandak, Jakarta 12560 - INDONESIA
(Hereinafter called “The Contractor”) as member of Consortium
Of the second party
-
WHEREAS:
On 06th March, 2013, the Employer on the part and the Contractor entered into a contract to
design, manufacture, test, deliver, install complete site test and commissioning the certain
Facilities, North West Sumatera Interconnector Transmission Lines Construction Project,
Package 2 : 275 kV Transmission Line, Supply and installation for 275 kV Transmission Line
Padang Sidempuan – Payakumbuh.
On 14th November 2014, the Employer and the contractor signed an amendment I No.
038A.PJ/041/DIR/2014 for the purpose of changing in source of financing of the contract.
On 15th December 2015, the Employer and the contractor signed an amendment II No.
038B.PJ/041/DIR/2014 for the purpose of changing in Price Schedule No. 1 of the contract.
and based on
Therefore, The parties have mutually agreed to amend the Contract and any amendment
thereto as follows:
1. COMPLETION TIME
The completion time of the contract shall be extended 16 (sixteen) month or 480 (four
hundred eighty) days.
The completion time of the contract shall be revised 42 (fourty two) months or 1271 (one
thousand two hundred seventy one) days calendar from the effective date of contract.
Completion date shall be September 04, 2016
The revised overall schedule for this project as per attachment 2
-
2. The Site Project Supervisor
To amend clause 1.2 and clause 1.3 of the contract discussion agreement to be as follows
:
3. SCOPE OF WORKS
4. SOURCE OF FINANCE
PLN confirmed that the source of finance for the Amendment is as per Amendment I No.
038A.PJ/041/DIR/2014
-
5. REVISED CONTRACT PRICE
The Contract price is amended, excluding VAT 10% as follows :
Contract Price
Description
USD JPY EUR IDR
Contract Price Amendment II 44,387,503 742,430,160 2,585,507 348,151,260,000
consist of :
Sc 1. Plant and mandatory Spare 44,387,503 742,430,160 2,585,507
Parts supplied from abroad.
Sc 2. Plant and mandatory Spare
Parts supplied from within
the employer’s country
Sc 3 Local Transport 30,692,299,000
Sc 4 Installation Services 317,458,961,000
-
6. CONTRACT PRICE
The Agreed contract price for Amendment III No. 038C.PJ/041/DIR/2015 is follows :
a. The Contract Price including VAT 10% (Nilai Kontrak)
Says :
- In words United States Dollar Forty Nine Million Six Hundred Eleven Thousand
Eight Hundred Thirty,
- In words Japanese Yen Eight Hundred Sixteen Million Six Hundred Seventy Three
Thousand One Hundred Seventy Six
- In words Euro Two Million Eight Hundred Forty Four Thousand Fifty Eight, and
- In words Indonesian Rupiah Four Hundred Thirty Six Billion Six Hundred thirteen
Million One Hundred Eighty Six Thousand Four Hundred Sixty.
Consist Of :
IDR. 101,262,108,651.00
-
c. VAT/PPN 10 %
Consist Of :
c.1 VAT/PPN OF ADB Portion
(PPN Porsi PHLN/Pinjaman Hibah Luar Negeri tidak dipungut)
IDR. 10,126,210,865
The Breakdown of the contract price is attached to this Amendment (Attachment 5).
The Terms and Procedures of Payment shall remain unchanged as per Amendment I No
038A.PJ/041/DIR/2014
The terms and conditions of the Main Contract dated 06 March 2013 which are not
modified by this Amendment No. 038C.PJ/041/DIR/2015 shall remain unchanged, fully
valid and in force to the Parties herein.
This Amendment No. 038C.PJ/041/DIR/2015 shall form an integral part of the Contract, as
further assigned and amended.
In case of discrepancy between the Main Contract and this Amendment No.
038C.PJ/041/DIR/2015 , this Amendment No. 038C.PJ/041/DIR/2015 shall prevail.
-
IN WITNESS WHEREOF the Parties hereto have caused this Amendment No.
038C.PJ/041/DIR/2015 to be executed by their only duly authorized representative on this day
of …………. ……………………………………………. 2015.
Leader of Consortium
Consortium of Hyundai Engineering &
Construction Co, Ltd
Member of Consortium
PT. Multi Fabrindo Gemilang
GANDEN A HENDRATMO
OPERATIONAL DIRECTOR