Professional Documents
Culture Documents
The IGREENGrid
Project Increasing Hosting Capacity
in Distribution Grids
including controlling DRES active and reactive power gen- DRES control and energy storage), proposed as temporary,
eration, managing flexible demand, and smart charging of can be settled a long-term solution.
electric vehicles. These alternatives can be rapidly imple- After classifying the solutions by the problem they solve
mented in a cost-effective way as temporary solutions to and determining which are the most promising for DRES inte-
solve local constraints until the tendencies of generation and gration, many elements should be taken into account: problem
consumption growth in the area become clearer. Regarding relevance, the applicability of each solution to the real grids,
continuous local increases, the reinforcement of the network cost, complexity, prerequisites (including skills and tools for
will take place considering the real necessities appeared, but planning and asset management), environmental impact, and
if the zone remains stable, smart grid alternatives (such as customer acceptance. A list of parameters and key performance
indicators to measure the main aspects involved in the with the set of resulting levels from simulations (Figure 2).
selection process was studied, but finally there is one indi- The returned HC is a series of values describing the realistic
cator standing out from all the others: increasing hosting potential of the network for DG integration, including the
capacity (HC). dependency between maximum generation and position of
DG units, the best and worst cases of HC, and eventual pres-
Measuring Hosting Capacity ence of network bottlenecks.
HC is defined as the maximum distributed generation (DG) The extraction of HC values is computationally demand-
penetration for which the power system operates satisfac- ing due to the necessity of simulating several DG scenarios
torily. According to this definition, numerous methods for (Monte Carlo simulation). The process can be faster when
estimating HC have been tested in the past. The most recur- combined with an OPF-based approach. Once a value of
rent solution for an effective HC evaluation is based on opti- nominal power is randomly assigned to each simulated DG
mal power flow (OPF), in which the objective function is unit, the optimization problem can be set up to maximize
designed to maximize the injection of active power within production by DRESs while respecting network constraints
the selected limits (typically voltage and loading). However, but maintaining the initial power proportion among genera-
OPF-based approaches have a strong limitation: the returned tors. At this point, when repeating the OPF for several DG
HC value is often referred to as fixed allocation of one or initial power distributions, the returned values of maximum
more generators on the network. Typically, one DRES unit generation can be summarized by the probabilistic func-
is simulated and the HC calculation is repeated for all the tions, as shown in Figure 3.
network buses, obtaining the results plotted in Figure 1. Having checked the equivalence of these results with
From the study of the obtained curves, relevant informa- the ones plotted in Figure 2, it can be concluded that the
tion about the amount of production that can be connected proposed probabilistic method is more realistic than the tra-
to the network can be deduced. This method is traditionally ditional one (Figure 1) where a single DG unit is normally
adopted in network planning due to its simplicity. However, considered. According to this, simulating realistic scenarios
a single generator is often an unrealistic representation of (in which the dispersed nature of DG is taken into account)
the DG expansion since it is more dispersed throughout the is a very good basis for studying the distribution network
distribution network, with no control from grid operators. potential in terms of HC increase in relation to SG technol-
In IGREENGrid, a simulation approach is preferred in ogy implementation.
which numerous allocations and dimensions of multiple gen-
eration units are considered for each selected network, and Solutions for Increasing
the HC is deduced by comparing the voltage/current limits Grid Hosting Capacity
In a first attempt to compare solutions that were installed
in different countries and operating conditions, it was clear
that centralized or even supervised (centrally monitored but
40 not real-time controlled) solutions are generally more effec-
Voltage HC
Current HC tive (in terms of HC increase, see Table 1) than decentralized
30 Overall HC solutions. The best performing solutions usually include a
Bus HC (MW)
1.1 Voltage HC
14
1.08 12
HC Probability (%)
10
1.06
Voltage Limit
8
1.04
6
1.02 4
2
1
0 10 20 30 40 50 0
Total Nominal Power of Installed DG (MW) 0 10 20 30 40 50
(a) Total Nominal Power of Installed DG (MW)
150
(a)
Network Loading (%)
Loading HC
100 14
Loading Limit
12
HC Probability (%)
10
50
8
6
0
0 10 20 30 40 50 4
Total Nominal Power of Installed DG (MW) 2
(b)
0
Single Generator Installed in the Most Remote Bus 0 10 20 30 40 50
DG Uniformly Distributed on the Network Total Nominal Power of Installed DG (MW)
Single Generator Installed in Proximity of the
Primary Substation (b)
Random Position of DG Units
In general, the performance of distributed solutions highly We analyzed two complete distribution grids of different
depends on the position of the DRES units. The performance distribution system operators (DSOs) and identified voltage
of centralized/supervised technologies, however, is almost violations as the most important problem when increasing the
the same in all of the scenarios considered. number of DG units. For the first DSO, 90% of the feeders
Another common factor among the best performing solu- were voltage constrained while only 10% were loading con-
tions is field measurements of a few parameters at well-selected strained (Figure 4). The second DSO presented 77% of the
points in the network. These studies show that approximately feeders as voltage constrained, with a homogeneous distribu-
80% of the medium-voltage (MV) feeders present only one tion of DG until current constraints occur.
critical node affected by maximum acceptable voltage con- The horizontal axis of Figure 4 represents the percent-
straints. This means that it is not necessary to deploy an enor- age loading for the feeders. Most of the feeders are voltage
mous number of sensors to obtain the best results for increasing constrained (blue bars) and present a loading that is well
HC, but it is important to select the right places to install them. below the 100% loading limit. The black curve (cumulative
Identifying a node for measuring normal conditions is much distribution function) shows that for half of the feeders, the
easier than examining different scenarios of emergency supply normal loading is below 37%. This means there is a large
for forced outages or alternative supply under system mainte- reserve (more than 63%) of thermal loading capability.
nance conditions. But even for normal conditions, the critical This loading reserve is obtained at a homogenous DG pen-
node might change when additional DG units are installed. In etration without applying any SG solution. In general, rural
the analyzed low-voltage (LV) grids, 60% of the feeders present feeders are voltage constrained, while urban feeders are load-
more than one critical node. Since the number of required sen- ing constrained. The global results, however, depend on the
sors is highly dependent on the connection point of the DRESs type of feeders. For the second DSO, for instance, the loading
along the feeders, this aspect must be studied case by case. reserve is about 40% for half of the feeders. From this analysis,
0.12
MV side] to correct these contrasting voltage levels. Then
0.4 0.08 the flexibility can be doubled at the MV level to absorb the
0.2 0.04 LV variations due to generators and loads. When LV lines of
0.0 a certain secondary substation present contrasting voltage
10 20 30 40 50 60 70 80 90 100
levels, introducing autotransformers [Figure 5(b), the LV
% Loading
side] in some LV lines also increases the flexibility of the
whole system. The problem with this and similar ideas is the
figure 4. The probability distribution function (pdf) of
cost of the new elements, but the potential to increase HC
distribution grids from one Austrian DSO in function of
the loading reserve. The voltage-constrained feeders are and the effectiveness of existing assets is enormous.
in blue, loading-constrained feeders are in red, and both Flexibility can be also obtained from third parties [Figure 5(c)]
voltage- and loading-constrained feeders are in magenta. such as generators and consumers. Active demand techniques
The cumulated density function (cdf) of these grids in or energy storage installed at customers are some of the pos-
function of the loading reserve is shown in black. sibilities to regulate the loads in the lines. In some countries,
MV Grid
+10% LV Grid
+10% Asym 253.0 V
3% 248.4 V 3% LV DG
243.8 V 2% MV DG
239.2 V 2% HV/MV
234.6 V 5% MV Voltage
U 230.0 V Drop at Lines
225.4 V 2% MV/LV Transformer
220.8 V
216.2 V 6% LV Voltage
–10% 6% 211.6 V Drop at Lines
Asy 207.0 V
m
–10%
–15% 5% of Intervals/Week
(a)
MV-Regulation LV-Regulation
HV/MV G Transformer G Transformer
HV MV/LV G G
∑ ∑
+10% +10%
Asym 253.0 V
3% ym 3% LV DG
6% As 12% 248.4 V
2% MV DG
3% 3% 243.8 V
9% 239.2 V 2% HV/MV
234.6 V 5% MV Voltage
U 4% 4% 230.0 V Drop at Lines
8% 225.4 V 2% MV/LV Transformer
220.8 V
9%
–10% As 6% As 15% 216.2 V 6% LV Voltage
ym ym 211.6 V Drop at Lines
–10% 207.0 V
–15% 5% of Intervals/Week
(b)
DG with Curtailment
and VVC
HV HV/MV G G MV/LV G G
Flexible Loads
+10%
+10% m
Asy
253.0 V
248.4 V 3% LV DG
243.8 V 2% MV DG
239.2 V 2% HV/MV
234.6 V 5% MV Voltage
U 230.0 V Drop at Lines
225.4 V 2% MV/LV Transformer
220.8 V
216.2 V 6% LV Voltage
–10% 211.6 V Drop at Lines
–10% 207.0 V
Asy
m
–15% 5% of Intervals/Week
(c)
figure 5. Voltage regulation bands with (a) only OLTC at the primary substation, (b) MV and LV inline autotransformers, and (c)
using flexibility from generators (red and blue) and consumers (clear green). Color bands: yellow and brown indicate raising margins
in LV and MV lines, respectively; dark green and blue indicate voltage drops in LV and MV lines, respectively; margins at the sub-
stations are indicated in white. The asymmetry of loads among phases (asym) requires the preservation of part of the voltage band.
Feeder
the solar generators to regulate the active or reactive power
injection. This coordinated control is made possible by power
figure 6. Feeder screening: the classification of feeders as line communications for getting voltage measurements from
voltage constrained (blue) or loading constrained (red) with smart meters and remotely parameterizing the solar inverter
the indication of HC and an HC increase for each one of controls. This change would affect large amounts of small
the feeders of a primary substation. devices and may require exploring alternative approaches to
facilitate implementation (e.g., generator design and use of generator pay extension costs. For generators lower than
public telecommunication infrastructure). 10 kW, there is no payment for access or the connection
The tradeoff between grid expansion costs and curtailed study (RD 900/2015).
energy costs should be analyzed. To incorporate new DRESs, The Italian Electrotechnical Committee (CEI) has released
it is often more efficient to reduce generation in critical the CEI 0-16 and CEI 0-21 standards, which define the tech-
moments than to reinforce the grid. A fix curtailment for nical rules for the connection of active and passive consum-
PV installations, limiting the maximum injection to 70% of ers to the HV, MV, and LV electrical public networks. Some
nominal power, can lead to an energy curtailment of between HV rules were extended to wind and PV plants in distribution
3 and 7%, which is acceptable, taking into account that it networks to avoid disconnection in case of system perturba-
produces around a 40% HC increase. When applied to wind tions (Annex A.70 of the Italian network code). These stan-
farms, a fix curtailment of 70% of nominal power can lead to dards also specify that the reactive power capabilities to be
higher amounts of energy curtailed (above 10%) and, conse- provided by each technology (such as static and synchronous)
quently, a higher economic impact on generators, for similar and the disconnection of DRES plants greater than or equal to
results in terms of HC. 100 kW for system security after a TSO request (reduction of
In France, a new nonfirm connection contract will allow distributed generation scheme, known as RIGEDI).
the curtailment of production during a few days a year, with In Spain, the obligation of maintaining connection dur-
the benefit of a lower connection cost for generators due to ing voltage dips only applies to PV and wind plants larger
avoided reinforcements. than 2 MW. In Greece, the obligation applies only beyond
3 MW. Concerning active voltage control, in Spain, plants
Regulation for Dres Connections larger than 5 MW are must follow the TSO commands, and
Should Be Homogenized the DSO can only propose actions to the TSO. In Greece, nei-
An overview of DRES connection procedures reveals rele- ther the TSO nor the DSO engages in active voltage control.
vant differences from country to country. Variations include
connection request processes, maximum acceptable limit Dso Services Should be Fairly Compensated
definitions, incentives, and cost attribution. Homogeneous rules with an Adequate Remuneration
could contribute to the development of widely applicable SG Investment recovery schemes should be adapted to promote
solutions that could pass more easily from research to busi- the use of SG solutions. An SG has the potential to provide
ness as usual. a more sustainable, efficient, and secure electricity supply to
In Spain, Royal Decree (RD) 413/2014 establishes that customers. However, the purchase, operation, and mainte-
generators with a nominal power of 5 MW or higher must nance of the new components are difficult to justify in cur-
be connected to a control center [transmission system opera- rent regulatory frameworks. The economic analysis shows
tor (TSO) or DSO]. The DSO must have access to real-time that, frequently, the SG solutions proposed to connect addi-
measurements for RESs equal to or higher than 1 MW, with tional renewable generation are less expensive than the tradi-
measurement costs borne by the generator. In Greece, all tional reinforcement of the grid, but DSOs are not stimulated
MV power plants and around 70% of LV ones can provide to take advantage of these solutions. The costs of grid rein-
remote measurements, but there is not a general requirement forcement costs recouped, but, in general, innovative solu-
for the DSO to have real-time measurements. Only measure- tions are not covered by existing regulatory frameworks. In
ments from large wind farms are linked to the TSO. certain countries, and in particular for SG solutions, capital
In Italy, DSOs have the obligation to connect DG units expenditures are covered, but operational expenditures are
with the fit-and-forget approach; this implies that, in some not, yet. Many SG solutions reduce capital expenditures but
cases, generators can be connected only after network re increase operational expenditures.
inforcements. Active users pay a standard connection fee, Incentives for information and communication technology
depending on the power and on the straight distance from the (ICT) deployment are required, and operation and maintenance
closest line. Generally, generators up to 100 kW are connected costs should be considered in DSO service remuneration.
to the LV level and larger plants (usually up to 10 MW) to Telecommunication solutions for some SG implementations
the MV level. In Spain there are no standard connection could be very expensive in sparsely populated areas. Regula-
costs. Each case should be studied and proposed that the tors should consider incentives to support the development and
3 PG(t ) Constraints
Constraint
Time
(voltage closer to the limits). Other
Demand
4 PG(t ) Violated
Losses
Time/Distance
SG solutions such as AVRs in
Voltage Profile
Increase the HC
the simulations.
5 PG((tt )
2 PG(t )
1 PG(t )
Sometimes the complexity of a
Generation
ttii n
Efficiency
Generatio
solution is derived from the type
Supply
or number of agents involved. An
Fraud
OLTC or an OPF can be imple- BN 50160
mented by a DSO on its own, with
Operation Data
automatic reactive regulation of
Harmonized
Development of
Harmonized
oritizing simple but efficient solu-
Curtailment of
tions will accelerate the evolution DRES
toward the new SG and will help
EV-Charging Optimization
Strategy
Voltage Control
Replacement Compared to
Assess the Suitability of a
Monitoring (MV and LV)
Network
Asset
Side
connection of the generator as requested, leading to a violation progress to enable the widespread connection of DRESs
of its planning rules but keeping the right to curtail the injec- using SG solutions. When they become routine solutions,
tion of the generator for a given number of hours per year to the costs must be allocated among all the agents (DRES
prevent constraints on the distribution network. This allows the generators, DSOs, and TSOs) in a fair way.
DRESs to connect to the distribution network while minimizing Many SG solutions will become business as usual as
its connection costs and time. Consumers, prosumers, or genera- soon as the regulatory framework allows it. A balance
tors connected to the grid could obtain an advantage from this between new approaches and traditional reinforcement
contractual flexibility. will be found depending on technical aspects, the residual
Other technologies involving consumers or prosumers lifespan of assets, persistence and urgency of the problem,
are under development. DG units could contribute to volt- complexity of available solutions, and especially costs and
age control by modifying their reactive power following the recoupment. The digitalization and cost-effective decar-
DSO’s instructions. Smart-charging flexibility for electric bonization of the modern world makes the transition to
vehicles can be used to balance supply and demand, reduc- SGs critical.
ing the need for investment in grid reinforcements. Electric
vehicle charging connection can be incentivized or penal- For Further Reading
ized by the market through price signals. Energy storage M. Sebastián-Viana, et al. (2013). IGREENGrid Project [On-
solutions can be used to provide power when conditions are line]. Available: http://www.igreengrid-fp7.eu/
not favorable and to store power when there is a generation Commission regulation (EU) 2016/631. (2016, Apr.). Es-
excess. Until now, economic factors and regulatory issues tablishing a network code on requirements for grid con-
have hindered the application of these technologies. nection of generators [Online]. Available: http://eur-lex
A standard, completely interoperable interface between .europa.eu/legal-content/EN/TXT/?uri=OJ:JOL_2016_112
DSOs and customers will facilitate active demand manage- _R_0001
ment and DRES participation in grid operation and reli- A. Keane, L. F. Ochoa, C. L. T. Borges, G. W. Ault, A.
ability, promoting its own integration into the system. The D. Alarcon-Rodriguez, R. A. F. Currie, F. Pilo, C. Dent, and
development of this standard and the interoperability should G. P. Harrison, “State-of-the-art techniques and challenges
be promoted as a basis for the transition to SGs. ahead for distributed generation planning and optimization,”
Harmonized connection rules are urgently needed to IEEE Trans. Power Syst., vol. 28, no. 2, pp. 1493–1502,
facilitate a massive integration of DRESs. A uniform and May 2013.
clear regulatory framework for distribution grid connection, G. P. Harrison and A. R. Wallace, “Optimal power flow
independent of country or utility, will facilitate the process. evaluation of distribution network capacity for the connec-
DSOs can contribute to this framework by implementing tion of distributed generation,” IET Proc. Generat. Transm.
solutions for voltage control based on the reactive power Distrib., vol. 152, no. 1, pp. 115–122, Jan. 2005.
control of DRESs and providing the right balance at TSO/
DSO connection nodes. Biographies
The observability and control of distribution networks Jesús Varela is with Iberdrola Distribución Eléctrica S.A.U.,
need to be improved for the future. Variable generation Spain.
must be predicted and managed by improving the progno- Nikos Hatziargyriou is with the Hellenic Distribution
sis of consumption and DRES production as well as using Network Operator, Greece.
sophisticated algorithms to better estimate and control the Lisandro J. Puglisi is with Iberdrola Ingeniería S.A.U.,
status of the grid (state estimators and OPF-based products). Spain.
Distribution network operators require more advanced Marco Rossi is with Ricerca Sul Sistema Energetico, Italy.
planning and asset management tools to deal with chal- Andreas Abart is with Netz Oberösterreich GmbH,
lenges in the near future (probabilistic methods, OPF-based Austria.
techniques, ICT infrastructure, and flexibility services and Benoît Bletterie is with the Austrian Institute of Technol-
products). Additionally, the cost recovery framework for ogy, Austria.
DSOs should be modified to foster innovation. Pioneer-
p&e
ing initiatives should receive some revenue during their