You are on page 1of 4

QA Quality Assurance

Optimizing Array-to-Inverter Power Ratio


D evelopers and PV system designers
are challenged to stay competitive
in the constantly evolving solar market-
in large part because module prices
are an increasingly smaller percentage
of total project costs.
mismatch, array degradation, conduc-
tor resistance and so forth—without
exceeding the inverter capacity under
place. With the steep decline of solar Traditional approach. When module typical real-world conditions.
module prices, designers are exploring prices were high, the system designer’s Higher dc loading approach. As mod-
the economic benefits of increasing main goal was to define a dc load ratio ule prices have fallen, PV system design
the array-to-inverter power ratio. Here that ensured none or very little of the philosophy has shifted. Rather than
I discuss dc loading in general, then power produced by the expensive PV focusing on production efficiency and
focus on array-to-inverter sizing design array was wasted. Designers specifically maximizing the output of each indi-
approaches. I describe some scenarios wanted to avoid inverter power limit- vidual module, designers have begun
supporting the trend for higher dc ing, which occurs whenever the array is designing for maximum financial effi-
load ratios and present some relevant ciency at the

S
production modeling results. I also dis- system level.
cuss typical inverter operational limits In many cases,
related to dc loading. the incremen-
tal cost to
DC Loading As module prices have fallen, PV system design increase PV
The array-to-inverter power ratio is array capac-
defined as the relationship between philosophy has shifted. Rather than focusing ity is small
array capacity in dc watts and inverter compared to
capacity in ac watts. Array capacity is on production efficiency and maximizing the the value of
determined by the array nameplate the associated
power rating under standard test con- output of each individual module, designers energy produc-
ditions (STC), meaning at 1,000 W/m2, tion gains. This
25°C cell temperature and a reference have begun designing for maximum financial allows system
solar spectral irradiance of air mass designers to
1.5. The total inverter maximum output efficiency at the system level. capitalize on
power rating determines the inverter higher dc load
capacity. For example, if you connect ratios—up to
a solar array with an STC rating of 1.5 and in some
575 kWdc to one or several inverters capable of producing more power than cases even higher—despite the poten-
with a total maximum rated output the inverter can process. They would tial for PV power generation to exceed
power of 500 kWac, then the resulting typically determine a project’s optimal inverter capacity during peak hours.
array-to-inverter power ratio is 1.15, dc-to-ac sizing ratio by analyzing the
or 115% (575 kWdc ÷ 500 kWac). Other annual energy production per kilowatt Rationale for High-DC Loading
terms for array-to-inverter power ratio of PV energy at different loading ratios. Project developers and system designers
include dc load ratio, dc-to-ac ratio, This kWh/kW metric is known as spe- might opt to increase dc loading beyond
oversizing ratio and overloading ratio. cific yield and is a measure of produc- 1.2 for several reasons. Higher dc load
tion efficiency. ratios allow designers to get more value
Evolving Design Practices The traditional design approach from fixed development costs. They also
System design approaches to dc generally results in dc load ratios allow designers to capitalize on high-
loading have evolved over the past 5 within a 1.1–1.2 range, depending on value energy rates, or time-of-delivery
years and are closely tied to module the project location and design details. or time-of-day (TOD) rate structures
price trends. The traditional design These conservative overloading ratios that incentivize summer production.
approach to dc loading is conserva- allow the designer to offset a variety Increasing the dc load ratio is a com-
tive, as it was a direct response to of environmental and system-level pelling design approach when there is
high module prices. Newer design loss factors—such as cell temperature, a limit on ac system size but no cor-
approaches use higher loading ratios, irradiance, tilt angle, soiling, module responding limit on C O N T I N U E D O N P A G E 1 6

14 S O L A R PR O | October/November 2014
QA
Figure 1 The idealized 1 MWac
power curves in this figure High dc-to-ac ratio “Clipping” losses
represent system perfor- (energy not generated due
mance on a cool, sunny day to inverter power limiting)
in early summer in an area System power Additional energy generated
with a high TOD multiplier for by increasing dc-to-ac ratio
energy produced between
High value energy generated
noon and 6pm. While the Low dc-to-ac ratio during summer afternoons
system with the low dc-to- (subject to high TOD multiplier)
ac ratio will have the better
production efficiency (kWh/
kW), the system with the
high dc-to-ac load ratio will 6am Noon 6pm
generate more revenue and
Time of day
better financial returns.

dc system size. It also allows designers as much energy as possible through interconnected electric power produc-
to increase production in response to that fixed investment over the life of tion sources: “The sum of the ratings
suboptimal conditions such as cloudy the PPA [power purchase agreement], of all overcurrent devices connected
climates or long-term array degradation. even if that means sacrificing produc- to power production sources shall
Fixed development costs. When tion efficiency.” not exceed the rating of the service.”
system designers increase the dc-to-ac High-value rate structures. System Furthermore, Section 690.8 requires
load ratio beyond 1.2, the total system designers have more incentive to that the overcurrent device rating for
cost does not increase in direct propor- increase dc load ratios when the value an inverter output circuit be no less
tion to the increase in array capacity for the produced energy is high, as is than 125% of the inverter continuous
since many of the project costs remain the case with Ontario’s feed-in tariff output-current rating. Taken together,
the same. These fixed costs include program, or when energy generated these requirements effectively limit the
permitting, interconnection fees, legal on summer afternoons is subject to inverter capacity rating for a supply-
fees, and inverter and ac interconnec- preferential on-peak pricing, as is the side connection to no more than 80%
tion hardware costs. Therefore, the cost case with some utilities serving the of the service transformer kVA rating.
to add array capacity is limited to the desert Southwest. Increasing dc load For a site served by a 500 kVA trans-
material and labor costs associated ratios allows designers to deliver more former, the maximum interconnected
with adding more modules and dc bal- high-value electricity. inverter capacity is 400 kW.
ance of system components. By increas- Evarts and LeDucq explain how In this scenario and others pertain-
ing the dc loading ratio, designers may TOD multipliers for on-peak energy ing to load-side interconnections, the
be able to take full advantage of these can influence system design decisions: NEC places a hard limit on inverter
fixed development and structural costs. “To capitalize on energy values that are capacity. However, manufacturer
In their article “Designing for Value two to three times the baseline rate, product specifications and available
in Large-Scale PV Systems” (SolarPro designers oversize the dc-to-ac ratio so array area are the only hard limits to
magazine, June/July 2013), Graham that inverters run at full power when dc system capacity. Therefore, as long
Evarts and Matt LeDucq explain how energy is the most valuable. The general as system designers use the inverter
getting the most value for the develop- idea is that you are willing to give away according to the manufacturer’s instal-
ment costs applies within the context (via clipping) 2 MWh of energy at $100/ lation instructions, they can increase
of a ground-mounted PV power plant: MWh to get 1 MWh of energy at $250/ the PV array capacity until the available
“Developers have invested a lot of MWh, because this nets you $50.” Figure array area is fully utilized or there is
money in land, interconnection fees, 1 illustrates how designers can use a no economic justification for installing
lawyers and personnel to create the high dc-to-ac load ratio in response to additional modules.
project opportunity. They have also on-peak pricing to generate more high- There are also scenarios where a
built a substantial ac system infra- value energy. designer might choose to limit the
structure—one that includes invert- AC capacity limits. Since the NEC ac system capacity and use a high dc
ers, transformers, switchgear and a 2011 edition, Section 705.12(A) specifi- load ratio to avoid high capital costs
substation—and they want to push cally limits the capacity of supply-side associated with C O N T I N U E D O N PA G E 1 8

16 S O L A R PR O | October/November 2014
QA
purchasing specialized equipment or inevitable impacts of array degradation. the optimal design based on typical
upgrading a service. For example, the As PV arrays age, module performance meteorological year weather data and
utility may have special requirements— degrades. Ideally, this degradation is other project-specific variables. When
such as redundant relaying or direct linear and the annual power loss does choosing the PV system model, design-
transfer trip—above a certain capac- not exceed 0.5% annually. If designers ers must select a simulation program
ity threshold, or the existing electrical want to ensure that a PV array’s power that can model the effects of inverter
infrastructure or building service may output fully loads an inverter under power limiting and changes in inverter
limit the ac system size. A designer certain conditions in the summer of efficiency based on different voltage
might also opt to limit inverter capacity year 10 or year 20, then they must and power levels.
in response to break points in a feed-in specify a higher dc-to-ac ratio than is The basis of comparison when
tariff program. required to accomplish this same load- optimizing dc loading ratio is typi-
Suboptimal conditions. In the desert ing in year 1. cally a financial metric like cost per
Southwest, PV modules are routinely kilowatt-hour, levelized cost of energy,
exposed to irradiance values approach- Modeling Performance net present value or internal rate of
ing and even exceeding 1,000 W/m2. The best way for system designers to return. Several project-specific factors
These high-irradiance conditions are optimize the array-to-inverter power determine the optimal level of dc load-
less common in other parts of North ratio for a specific project is to use a ing, including location, system design
America. For example, in Ontario or PV system modeling program such as and inverter topology. The project’s cost
New England the plane-of-array irradi- HelioScope, PVsyst, PV*SOL or System structure and financial goals also drive
ance on a typical clear day might reach Advisor Model (SAM). By keeping the design decisions. On average, design-
800 W/m2. In locations like these, it inverter capacity constant and vary- ers and developers reach a point of
makes sense for designers to increase ing the array capacity, designers can diminishing economic returns at array-
the dc load ratio. model the financial and production to-inverter ratios of about 1.5. Beyond
PV system designers can also efficiencies resulting from different dc that, they eventually reach a tipping
use a high dc load ratio to offset the loading options. They can then select point above which C O N T I N U E D O N P A G E 2 0

18 S O L A R PR O | October/November 2014
QA

Project IRR vs. DC loading ratio

Figure 2 This figure compares the modeled IRR at three

IRR
load ratios (1.2, 1.5 and 1.7) for a PV system in Ontario. In
each case, the cost of the inverters, ac switchgear and per-

Courtesy AE Solar Energy


mits are essentially constant, and adjustments were made
to reflect changes in the number of modules and dc wiring
runs. While the increase in IRR is significant when the dc
load ratio is increased from 1.2 to 1.5, the economic returns 1.1 1.3 1.5 1.7 1.9
begin to flatten out between 1.5 and 1.7. DC:AC ratio

the incremental cost to increase array operational limits that the inverter for Use with Distributed Energy
capacity outweighs financial gains manufacturer imposes. Resources,” inverters are subjected to
from the additional energy produc- Common-sense limits. When the a series of abnormal-condition tests.
tion. This tipping point is unique available dc power from a PV array During the output-overload test, a
for every project. To ensure that a exceeds the inverter maximum power technician applies twice the rated
project meets energy production and rating, the control logic in the inverter input current to the inverter, which
financial performance goals, it is responds by moving the PV array off its must maintain its rated output power.
important for designers to optimize maximum power point. Limiting power While this test proves that a listed
dc-to-ac power ratios on a project-by- in this manner ensures that excess inverter can limit power under normal
project basis. power is not dissipated as waste heat in operating conditions, it is only one
For example, Figure 2 shows the the inverter. In effect, the inverter com- of several factors that determine the
modeled internal rate of return (IRR) ponents are not exposed to this excess maximum equipment rating.
at three different load ratios for a power under normal operating condi- Another critical factor is the
project in Ontario, where the available tions. However, an inverter with a high amount of short-circuit current that
solar resource is modest but the value dc load ratio is still exposed to higher internal components such as busbars
of PV-generated energy is relatively internal operating temperatures com- and disconnect switches can with-
high. The model inputs assume that pared to an inverter with a low dc load stand during a fault on the dc side of
installed system costs are relatively ratio, simply because an overloaded the inverter. In the unlikely event that
low, as might be the case with aggres- inverter operates at its maximum rated the inverter’s firmware fails to limit
sive module pricing, and that the sys- power more often and for longer peri- the input current from the PV array,
tem is deployed using high-efficiency ods of time. Further, the inverter may the inverter components must be able
transformerless string inverters. The operate less efficiently when limiting to withstand the full short-circuit
results confirm that higher dc load array power, with an increase in inter- current of the dc source for the dura-
ratios can increase a project’s IRR, nal waste heat. tion of the fault without breaking or
even though initial installation costs Designers can account for this compromising safety. For this rea-
are greater. Of course, the optimal dc effect by designing the system to son, designers should follow inverter
load ratio is very different in Ontario promote optimal inverter cooling. manufacturers’ recommendations for
than in New Mexico. Similarly, the dc Additionally, system owners and O&M maximum allowable array-to-inverter
load ratio sweet spot might be dif- providers should ensure that inverter ratios. Most importantly, design-
ferent for a project that uses central cooling system components—like fans ers must ensure that the available
inverters rather than distributed and filters—are maintained properly. PV array short-circuit current never
string inverters. Hard design limits. Designers exceeds the manufacturer’s published
must use inverters in accordance maximum dc input short-circuit cur-
Inverter Operational Limits with the manufacturer’s installa- rent value.
To deploy PV systems with high dc tion instructions. As part of UL 1741, —Verena Sheldon /
load ratios, designers and develop- the product safety standard for AE Solar Energy / Sacramento, CA /
ers need to account for the effects “Inverters, Converters, Controllers and solarenergy.advanced-energy.com
of array oversizing and observe any Interconnection System Equipment

20 S O L A R PR O | October/November 2014

You might also like