You are on page 1of 5

10/21/2016 (5) How do I calculate steel quantity for slab, footing, column?

 (assume the size yourself) ­ Quora

Before you start calculating the steel quantities, you need to visualize the dimensions(Length,
Breadth, Depth) of the structural member. (Be it a beam,

slab, column or a footing)

Then you need to visualize the shapes of bars that needs to be used.

You get the diameter of the bar details in the working drawings. Make a note of it.

If you observe the drawings properly, they provide you with spacing details like 100 mm or 150 mm or
200 mm c/c.

Let us consider 150 mm c/c spacing.

Then you need to know how much cover to provide.

(Go through the link below to know why we provide cover for RCC structures

Kasee Sreenivas' answer to Why do we provide cover on RCC structures? )

This will be required while calculating the length of the bar.

Length of the bar will be (Total Length of the span – cover on both the sides).

For example:

Take some span shown in the figure below..

https://www.quora.com/How­do­I­calculate­steel­quantity­for­slab­footing­column­assume­the­size­yourself 1/5
10/21/2016 (5) How do I calculate steel quantity for slab, footing, column? (assume the size yourself) ­ Quora

I consider cover for very severe type exposure condition. So cover is 50 mm on one side (as per
IS 456: 2000). We need to consider cover deduction for both the sides as shown in the above figure.

https://www.quora.com/How­do­I­calculate­steel­quantity­for­slab­footing­column­assume­the­size­yourself 2/5
10/21/2016 (5) How do I calculate steel quantity for slab, footing, column? (assume the size yourself) ­ Quora

So, remember 100 mm should be deducted from the total length of the span.

Now calculate the number of bottom mat bars required for 5500mm

span:

= ((Length of the span – Cover deduction) / Spacing) + 1

= ((5500­100)/150)+1

=(5400/150)+1

= 36+1

= 37 bars are required.

Now calculate the cutting length.

Cutting length = Length of the member – Deduction for bends.

(Length of the member = a+b+c in the image below.

&

Deduction for bends is twice the the diameter for one 90 degree  bend)

So if there are two perpendicular bends like this,

https://www.quora.com/How­do­I­calculate­steel­quantity­for­slab­footing­column­assume­the­size­yourself 3/5
10/21/2016 (5) How do I calculate steel quantity for slab, footing, column? (assume the size yourself) ­ Quora

You need to deduct ( 2*2*dia) i.e 4 times diameter of the rod.

Once you get cutting length, you multiply it with number of bars. You’ll get TOTAL LENGTH.

Then calculate UNIT WEIGHT.

Formula is (Diameter ^ 2) / 162

Example:

If you consider 25mm dia bars, unit weight

will be: (25*25)/162

=625/162

= 3.858

Finally,

UNIT WEIGHT X TOTAL LENGTH gives you the WEIGHT OF STEEL.

This is how steel quantity is calculated.

 ­­­­­­­­­­­­
https://www.quora.com/How­do­I­calculate­steel­quantity­for­slab­footing­column­assume­the­size­yourself 4/5
10/21/2016 (5) How do I calculate steel quantity for slab, footing, column? (assume the size yourself) ­ Quora

If you wish to know some thumb rules,

(This is purely based on my experience.)

You need to calculate how much concrete is required to cast the member first.

Example: Consider slab area is 400 square meter, thickness of the slab is 150 mm.

Concrete quantity required to cast this slab is 400*0.15 = 60 Cubic meter.

After calculating concrete quantity, you can remember these thumb rules just for getting a basic idea of
how much quantity of steel is required in those structural members.

Steel quantity in a conventional slab (excluding its beams) will be around 60 to 65 Kg per Cubic
meter.

In beams it will be around 200 to 220 kg per cubic meter.

In columns it'll be around 200 to 250 kg per cubic meter.

For footings it'll be around 100 to 120 kg per cubic meter.

https://www.quora.com/How­do­I­calculate­steel­quantity­for­slab­footing­column­assume­the­size­yourself 5/5

You might also like