Professional Documents
Culture Documents
特別号 (
) ) 43
Debris flows are very dangerous phenomena in mountainous areas. Sabo dams are
commonly used to mitigate debris flows and they are effective countermeasures against
debris flow disasters. However, human life and property remain at risk off debris flows.
In order to develop measures to increase the effectiveness of a Sabo dam, its control
function and design have been reported. Nevertheless, few studies have discussed the
control functions of a series of Sabo dams. This paper estimates debris flow discharges
at a Sabo dam site using overflow equations. A 1-D numerical simulation method of
debris flows is presented. Numerical simulations of debris flow were conducted
including overflow discharge at the dam point and laboratory experiments were
performed to validate the simulation results. Comparisons between the numerical
simulation results and laboratory experimental results show reasonable agreement.
Application of the numerical model used here is recommended to calculate overflow
discharge at Sabo dam sites and to evaluate the sediment capturing effects of Sabo dam
arrangements.
Key words: debris flow, Sabo dam, overflow equation, deposition, numerical simulation
*
Student Member of JSNDS, Doctoral Student, Department ***
Member of JSNDS, Dr. of Eng., Assoc. Prof., DPRI,
of Civil and Earth Resources Engineering, Kyoto Kyoto University (Yoko-oji, Fushimi, Kyoto 612-8235,
University (Katsura Campus, Nishikyo-ku, Kyoto JAPAN)
615-8540, JAPAN) ****
Member of JSNDS, Dr. of Eng., Assist. Prof., DPRI,
**
Member of JSNDS, Dr. of Eng., Prof., DPRI, Kyoto Kyoto University (Yoko-oji, Fushimi, Kyoto 612-8235,
University (Yoko-oji, Fushimi, Kyoto 612-8235, JAPAN) JAPAN)
43
44 A STUDY ON DEBRIS FLOW OUTFLOW DISCHARGE AT A SERIES OF SABO DAMS
Fig.1 Sediment-related disasters (Photo source : Fig.2 The number of debris flow occurrence in Japan
DPWH, Japan) (Data source : MLIT, Japan)
自然災害科学 特別号( ) 45
(7) (15)
If 0.03< tanθw ≤ 0.138, an immature type of debris where, n is the Manning resistance coefficient.
flow occurs, and
2.2 Conditions of Sabo Dam
(8) The closed-type Sabo dam is set at the grid line
where discharge is calculated (Fig. 3). The grid
If tanθw ≤ 0.03, a turbulent water flow with bed load size is 5 cm. The flow surface gradient, θw, and bed
transport occurs, and gradient, θb, are calculated at the center of the cell.
The flow surface gradient θw and bed gradient θb are
(9) calculated by the average of each value of θw, i+1,
θb, i+1 and θw, i-1, θb, i-1. However, if there is a Sabo dam,
(10) the calculation method is changed as follows:
(12) (16)
(13)
3. LABORATORY EXPERIMENTS
(19)
Figure 4 shows the experimental flume setup.
2.3 Overflow Equations The laboratory experiments were conducted using
Sabo dams involve obstructing the path of flow. a rectangular flume, which is 6.5m long, 13 cm
This is a vertical obstruction over which the debris high, 10 cm wide and has an incline of 18°. The
must flow such as a weir. At that time, outflow flume is divided into two parts by an 8cm high sand
discharge at the dam point can be calculated using stopper that is installed 1.5m from the upstream
cer tain equations. To calculate debris flow end of the flume. The upstream part is filled with a
discharge at the dam point, the overflow equation movable bed that consists of silica sand and gravel
and free overfall equation are applied.
Table 1 Flow conditions at Sabo dam
Overflow equation (Complete flow):
(20)
(21)
(22)
mixtures. The movable bed was set 20cm upstream wide and 1 cm thick were used for the
from the upstream end of the flume, length 150 cm, experiments. The lower Sabo dam was set 30 cm
8 cm high, and 10 cm wide. Sediment materials upstream from the downstream end of the flume
with mean diameter d m=2.86mm, maximum the upper Sabo dam was set 30 cm, 55 cm, 80 cm
diameter dmax=15mm and density σ=2.65g/cm , 3
upstream from the lower Sabo dam.
internal friction angle of a sediment tanϕ=0.7 were Two runs were conducted under the same
used. The particle size distribution of the movable experimental conditions in order to obtain reliable
bed is shown in Figure 5. data. Debris flow discharge and sediment
To generate the debris flow, the movable bed is concentration at each dam point were measured
saturated by seepage flow. After fully saturating the using sampler. Debris flow deposition upstream of
movable bed, the debris flow is generated through the Sabo dam was measured by video camera and
supplying clear water. The debris flow developed in the images were analyzed over time.
the experiments is fully stony type debris flow and
larger particles are accumulated at the forefront of 4. RESULTS AND DISCUSSION
the debris flow. This debris flow, overtopping the The numerical simulations were conducted to
sand stopper, reaches the downstream part of the calculate debris flow discharge at the dam point
flume. After overtopping the two Sabo dams, debris and experiments were also performed to validate
flows are captured by the sampler. the numerical model.
The experimental conditions are shown in Table Figure 6 shows the simulated results and
2. Two closed-type Sabo dams 6 cm high, 10 cm experimental results of debris flow discharge and
sediment concentration. In this graph, time 0
means the start time to supply clear water. The
start time of blue line means the time the debris
flow reached the upper Sabo dam. Table 3 shows
the time the debris flows reached each position.
In Case A, the overflow time of debris flow at the
lower Sabo dam is earlier than in Case B and Case
C. The distance between two Sabo dams is not
sufficient capture debris flow. Sufficient distance
Fig. 5 Particle size distribution of sediment materials
Table 3 Debris flow time (unit : sec)
Table 2 Experimental conditions
自然災害科学 特別号( ) 49
between two Sabo dams means that the length deposition height is equal to 0.
between two Sabo dams is longer than the Table 4 shows the debris flow peak discharge.
deposition length upstream of one Sabo dam. This In the experimental results, debris flow discharge
deposition starting from the Sabo dam to the is calculated at the downstream end of the flume
under the no Sabo dam case. Simulated results of the shape of the deposition between the simulated
debris flow discharge are consistent with the results and experimental results. The height of
experimental results. Through the series of Sabo deposition in the experimental results is higher
dams, the total discharge of debris flow and peak than that in the simulation results. The simulation
discharge is decreased. results are underestimated. Therefore, a more
The total average peak discharge rate is 48.4% in feasible coef ficient of erosion velocity and
the experimental results and 48.1% in the coefficient of deposition velocity are required.
simulation results. However, the longer the Through adjusting the discharge coefficient and
distance between two Sabo dams, the higher the erosion, deposition coefficient, the debris flow
rate of total discharge decrease. The situation is deposition pattern could be further improved.
different in the lower Sabo dam. The longer the In this study the debris flow overflow discharge
distance between two Sabo dams, the easier it is to at a series of Sabo dams was evaluated. The
form a fully developed debris flow. suggested simulation method for calculating debris
The average decrease rate of the upper Sabo flow discharge results in good agreement with the
dam is 29.8% in the experimental results and 31.9% experimental results.
in the simulation results. However, the average
decrease rate of the lower Sabo dam is 18.6% in the 5. CONCLUSIONS
experimental results and 16.2% in the simulation The numerical model was developed to simulate
results. The efficiency of the decrease rate of the debris flow discharge at the dam point.
debris flow peak discharge at the lower Sabo dam Laboratory experiments were conducted and good
is less than the upper Sabo dam. The reason for results of debris flow discharge as well as sediment
this is the sediment concentration. In the Figure concentration were obtained. Debris flow
6(b), as debris flows pass the Sabo dam, sediment deposition will be further improved through
concentration decreased. First, the sediment adjustment of the coefficient.
concentration is consistent at around 35%. As the Through considering the combination of Sabo
debris flows passed the upper Sabo dam, sediment dams, elucidation of technical criteria on the
concentration decreased to around 30% and when distance between Sabo dam is expected.
passing the lower Sabo dam, sediment
concentration fur ther decreased. However, ACKNOWLEDGMENT
overflowed debris flow at the lower Sabo dam does This research was supported by the JSPS AA
not have a consistent sediment concentration. The Science Platform Program (Coordinator: H.
initial sediment concentration is lower than 5%. Nakagawa) and support of the Wakate fund
This means that debris flow that is not fully program by the Kyoto University Global COE
developed reaches the lower Sabo dam. As debris Program (GCOE-ARS).
flows overflow the Sabo dam, sediment is captured
by the Sabo dam. Therefore, the forefront of the REFERENCES
Armanini A., Dellagiacoma F., and Ferrai L., 1991.
debris flow has a low sediment concentration.
From the check dam to the development of
Figure 7 shows the debris flow deposition
functional check dams; Fluvial hydraulics of
upstream of the Sabo dam. In this graph, time 0 mountain regions. Lecture notes on Earth
means the start time of debris flow being captured Sciences, Vol. 37, Springer, Berlin, 331-344.
by the Sabo dam. Some discrepancies are found in Di Silvio, G., 1991. Soil erosion and conservation Part
自然災害科学 特別号( ) 51
(投稿受理:平成 26 年 4 月 18 日)