Professional Documents
Culture Documents
Point
2 Opertaive Period
3 Eligible units
4 Spinning
Interest Subsidy
capital subsidy
VAT Concession
Entry Tax
5 Weaving
Interest Subsidy
capital subsidy
VAT Concession
Entry Tax
Assistance for advanced training to
Power loom owner/ jobber and worker
6 Processing
Interest Subsidy
capital subsidy
VAT Concession
Entry Tax
7 Garmenting
Interest Subsidy
capital subsidy
VAT Concession
Entry Tax
Training Centers
Reimbursementof tuition fees to Trainees
Interest Subsidy
capital subsidy
Entry Tax
9 Silk Industry
Interest Subsidy
capital subsidy
VAT Concession
Entry Tax
10 Others
Interest Subsidy
capital subsidy
VAT Concession
Entry Tax
Interest Subsidy
capital subsidy
Interest Subsidy Period
Projects sanctioned on or after the date 1.4.2011 under theCentrally sponsored TUFS
Maximum interest subsidy will be at the rate of 12.5% interest ( for Vidarbha, Marathwada,
North Maharashtra, Konkan and D+ Industrial Areas) and 10.5% rate of interest in other
regions considering at 12.5% base rate (Including Interest Subsidy under RTUFS)
10% Capital subsidy to new textile units in Vidarbha, Marathwada and NorthMaharashtra
--------NA-------
--------NA-------
--------NA-------
--------NA-------
Maximum interest subsidy will be at the rate of 12.5% of interest in the entire State
considering at 12.5% base rate (Including Interest Subsidy under RTUFS)
10% Capital subsidy to new textile units in Vidarbha, Marathwada and North
Maharashtra
--------NA-------
--------NA-------
--------NA-------
--------NA-------
--------NA-------
--------NA-------
Maximum interest subsidy will be at the rate of 12.5% interest ( for Vidarbha, Marathwada,
North Maharashtra, Konkan and D+ Industrial Areas) and 10.5% rate of interest in other
regions considering at 12.5% base rate
10% Capital subsidy to new textile units in Vidarbha, Marathwada and NorthMaharashtra
--------NA-------
--------NA-------
Maximum interest subsidy will be at the rate of 12.5% of interest in the entire State
considering at 12.5% base rate (Including Interest Subsidy under RTUFS)
10% Capital subsidy to new textile units in Vidarbha, Marathwada and NorthMaharashtra
--------NA-------
--------NA-------
--------NA-------
--------NA-------
--------NA-------
--------NA-------
Maximum interest subsidy will be at the rate of 12.5% interest ( for Vidarbha, Marathwada,
North Maharashtra, Konkan and D+ Industrial Areas) and 10.5% rate of interest in other
regions considering at 12.5% base rate
10% Capital subsidy to new textile units in Vidarbha, Marathwada and NorthMaharashtra
--------NA-------
Maximum interest subsidy will be at the rate of 12.5% of interest in the entire State
considering at 12.5% base rate (Including Interest Subsidy under RTUFS)
10% Capital subsidy to new textile units in Vidarbha, Marathwada and NorthMaharashtra
--------NA-------
--------NA-------
Maximum interest subsidy will be at the rate of 12.5% interest ( for Vidarbha, Marathwada,
North Maharashtra, Konkan and D+ Industrial Areas) and 10.5% rate of interest in other
regions considering at 12.5% base rate
10% Capital subsidy to new textile units in Vidarbha, Marathwada and NorthMaharashtra
--------NA-------
--------NA-------
Maximum interest subsidy will be at the rate of 12.5% of interest in the entire State
considering at 12.5% base rate (Including Interest Subsidy under RTUFS)
10% Capital subsidy to new textile units in Vidarbha, Marathwada and NorthMaharashtra
7 years, which will include 2 years of moratorium OR for the period of repayment of loan
whichever is earlier
--------NA-------
--------NA-------
--------NA-------
Gujarat Textile Policy - 2012
Listed and identified under TUF scheme or compatible with TUF scheme will be considered
eligible.
Five Years (5/09/2012 to 4/09/2017)
All the textile units/ activities commissioned after the announcement of Gujarat Industrial
Policy - 2009 i.e February - 2009
--------NA-------
Power tarif subsidy @ RS.1per unit for Spinning & Weaving for the period of 5 years
Assured supply of lignite by way of supply agreement withGMDC for the period of 5 years for
capitive power
To the extent of 100% the eligible fixed capital investments Refund of VAT paid by the unit on
purchases of intermediate product/raw material except for certain goods and certain
transactions which are not eligible for tax credit under The Gujarat VAT Act, 2003. concession
will be available within 8 years from the date of the production.
--------NA-------
--------NA-------
Power tarif subsidy @ RS.1per unit for Spinning & Weaving for the period of 5 years
Assured supply of lignite by way of supply agreement withGMDC for the period of 5 years for
capitive power
To the extent of 100% the eligible fixed capital investments Refund of VAT paid by the unit on
purchases of intermediate product/raw material except for certain goods and certain
transactions which are not eligible for tax credit under The Gujarat VAT Act, 2003. concession
will be available within 8 years from the date of the production.
--------NA-------
Allowances towards cost of transport & incidental expenses to weavers @ Rs.200/ - per day
for duration of two days and Jobbers @ Rs.300/ - per day for duration of six days. No
allowances will be given to Power loom owner
(ii) No fees will be charged by the Institution from Weaver, jobber or Owner for providing
training.
Trainees will be given stipend of Rs.2500/ - per month for the period of three months.
--------NA-------
To the extent of 100% the eligible fixed capital investments Refund of VAT paid by the unit on
purchases of intermediate product/raw material except for certain goods and certain
transactions which are not eligible for tax credit under The Gujarat VAT Act, 2003. concession
will be available within 8 years from the date of the production.
--------NA-------
--------NA-------
To the extent of 100% the eligible fixed capital investments Refund of VAT paid by the unit on
purchases of intermediate product/raw material except for certain goods and certain
transactions which are not eligible for tax credit under The Gujarat VAT Act, 2003. concession
will be available within 8 years from the date of the production.
--------NA-------
Assistance upto 85%, with ceiling of maximum of Rs 3 crore, of the project cost covering
fixed capital investment in building, equipments and machinery (including installation cost),
electrification, furniture and other miscellaneous investment required for setting up training
facilities, excluding land cost. Maximum 25% cost of Machineries and Training Equipments
will be eligible to consider for Infrastructure including Building
Training cost with maximum limit of Rs.7,000/- per trainer per week
--------NA-------
--------NA-------
--------NA-------
To the extent of 100% the eligible fixed capital investments Refund of VAT paid by the unit on
purchases of intermediate product/raw material except for certain goods and certain
transactions which are not eligible for tax credit under The Gujarat VAT Act, 2003. concession
will be available within 8 years from the date of the production.
--------NA-------
--------NA-------
To the extent of 100% the eligible fixed capital investments Refund of VAT paid by the unit on
purchases of intermediate product/raw material except for certain goods and certain
transactions which are not eligible for tax credit under The Gujarat VAT Act, 2003. concession
will be available within 8 years from the date of the production.
--------NA-------
--------NA-------
Five years OR for the period of repayment of loan whichever is earlier
1. Assistance up to 50%, Max Rs. 50,000 for Energy Audit/Water Audit Environmental
Compliance which will be applicable in each case separately.
2. Assistance up to 20% of cost of equipments, Max Rs. 20 lakhs which will be applicable in
each case separately.
3. The enterprises will be eligible for the above benefit once in 2 years of operating period of
the scheme.
The park will be provided financial assistance of up to 50%,with maximum limit of Rs. 10
crore (Rs.30 crores for Spinning park) of total project cost for establishing common
infrastructure facilities, excluding land cost.
exemption of stamp duty on purchase of land required for the new park as approved by SLAC
Madhya Pradesh Industrial Promotional Policy - 2010
As per RTUFS
Interest subsidy of @ 2% for a period of 5 years subjected to maximum limit of Rs. 5 Cr.
10% Capital subsidy to new textile units subjected to max. limit of Rs. 1 Cr.
Entry Tax excemption for a period of 7 years for Investment of more than Rs. 100 Cr.
Interest subsidy of @ 2% for a period of 5 years subjected to maximum limit of Rs. 5 Cr.
10% Capital subsidy to new textile units subjected to max. limit of Rs. 1 Cr.
Entry Tax excemption for a period of 7 years for Investment of more than Rs. 100 Cr.
Interest subsidy of @ 2% for a period of 5 years subjected to maximum limit of Rs. 5 Cr.
10% Capital subsidy to new textile units subjected to max. limit of Rs. 1 Cr.
Entry Tax excemption for a period of 7 years for Investment of more than Rs. 100 Cr.
Interest subsidy of @ 2% for a period of 5 years subjected to maximum limit of Rs. 5 Cr.
10% Capital subsidy to new textile units subjected to max. limit of Rs. 1 Cr.
Entry Tax excemption for a period of 7 years for Investment of more than Rs. 100 Cr.
Interest subsidy of @ 2% for a period of 5 years subjected to maximum limit of Rs. 5 Cr.
10% Capital subsidy to new textile units subjected to max. limit of Rs. 1 Cr.
Entry Tax excemption for a period of 7 years for Investment of more than Rs. 100 Cr.
Interest subsidy of @ 2% for a period of 5 years subjected to maximum limit of Rs. 5 Cr.
10% Capital subsidy to new textile units subjected to max. limit of Rs. 1 Cr.
Entry Tax excemption for a period of 7 years for Investment of more than Rs. 100 Cr.
Interest subsidy of @ 2% for a period of 5 years subjected to maximum limit of Rs. 5 Cr.
10% Capital subsidy to new textile units subjected to max. limit of Rs. 1 Cr.
Entry Tax excemption for a period of 7 years for Investment of more than Rs. 100 Cr.
25% subsidy will be given for establishment of Apparel Trainning Institute subjected to max.
limit of 25 Lakhs