JOB SAFETY ANALYSIS

Ref
Rev 000
INSTALLATION OF CHILLED WATER PIPES Date 04-06-2018

Consequence Who might be Current Risk Responsible Final Risk


Task (Steps) Potential Hazard Details Existing Control Co Additional Control
affected n
Prob Risk person Cons Prob Risk

Use of Electrical Electric Shock Pre use inspection of the 4 3 12 Supervisor/ 4 2 8


Powered tools tool and electric cables shall Safe Use of power tools Engineer/
Flying particles be carried out by the training shall be arranged Workers/ Safety
operative. for the operatives.
Eye injuries Double insulated tools shall
be used to prevent electric All power tools to be 110v.
Noise Lti shock.
Operatives Cable management shall be Power supply to be taken
Fire Equpment Damage property carried out to prevent slips, through ELCB only.
trips and falls. Main contactors
Un inspected tools Fire Power supply to be cut of instruction to be followed.
while repairs or changing PAT test will conduct
Lack of PPEs grinding blades. under the supervisoion of
Man And Material All combustibles materials to electrical engineer
HAVS be moved from the area or Powertools inspection
Man injuries should be covered with fire done and colour will
blankets. followed
Ear defenders shall be
provided to the operatives
for hearing protection.
Serviceable, inspected fire
extinguisher to be kept near
the working area.
All tools and equipment’s
shall be inspected and color
coded by a competent
person.
All mandatory PPE Wear
during work
eg:helmet,shoes,googles,fac
Page 1 of 6
JOB SAFETY ANALYSIS
Ref
Rev 000
INSTALLATION OF CHILLED WATER PIPES Date 04-06-2018

Consequence Who might be Current Risk Responsible Final Risk


Task (Steps) Potential Hazard Details Existing Control Co Additional Control
affected n
Prob Risk person Cons Prob Risk

e protection/ear puf,mask
Job rotatation giving to
operaters to prevent HAVS.
Main Contractors Permit to
work system shall be
followed.
Maximum 20 kg will load
manually during work
SWL system will follow
Equpment Damage Safe Manual handling
Back Injuries
methods shall be adopted by
Financial Loss keeping the back straight
Sprains
Operatives, and knees bended to
Safety Precautions with
Man And Material property prevent back injuries.
Strains the workforce to be
Lifting of heavy load should
discussed by the
Man injuries be avoided and shall be
Hernias supervisor.
Manual handling lifted by mechanical means
Supervision to monitor
during or by team lift. Supervisor/
Slips and Trips the task.
Installation of Area shall be kept clean and 5 3 15 Engineer/ 4 2 8
Manual Handling training
Chilled water tidy to prevent slips and falls. Workers
Work related upper to the operatives shall be
pipes Adequate personnel
limbs disorder delivered.
protective equipment’s to be
TBT conducted to workers
worn by the operatives to
Cuts injuries about SWL, ergonomics
prevent cuts injuries caused
hazards.
by sharp edges.
Lack of PPEs
Job rotation or sufficient
breaks shall be given to the
Ergonomics hazards
workers.
Tool box talks to be
conducted by the concerned
supervisor prior the task.

Page 2 of 6
JOB SAFETY ANALYSIS
Ref
Rev 000
INSTALLATION OF CHILLED WATER PIPES Date 04-06-2018

Consequence Who might be Current Risk Responsible Final Risk


Task (Steps) Potential Hazard Details Existing Control Co Additional Control
affected n
Prob Risk person Cons Prob Risk

Provision of cool drinking


water in the area to be
ensured.

Equipment should certified


by 3rd party
Area should be barricaded
Workers Work with the presence of
Supervisor Banks men
Nearby workers Operator should be certified
Engineer ensure the
Falling men Lti by 3rd party
supervisor is following
Falling objects and Give tool box talk before
PTW system
materials Equpment Damage starting the work
Proper traffic Supervisor/
Working above Equipment failure Keep fire extinguisher on the
5 5 25 management system Engineer/ 4 2 8
MEWP Un slope ground Man And Material platform of MEWP
Operator cross check the Workers
condition Use safety harness
equipment regularly
Weather condition Man injuries Follow main contractor PTW
Moniter the weather
Roofing condition System
condition
Follow the checklist
provided by main contractor
Close supervision of work
Activivty will stop when the
wind speed exceed more
than 20 knot.
Attend main contractor Full body harness Store/Engineers
Slip trip & fall 4 4 16 3 3 9
training awareness program inspection should be done /HSE Advisor
hazards
Prior toolbox talk before every month.
Working at Falling men
Equpment Damage Workers/ starting the work PTW system should be
height Falling materials
nearby workers Barricaded the work area is followed
Horse play
Man And Material relevant Ensure working under
Weather condition
Tie the power tools and tools close monitoring

Page 3 of 6
JOB SAFETY ANALYSIS
Ref
Rev 000
INSTALLATION OF CHILLED WATER PIPES Date 04-06-2018

Consequence Who might be Current Risk Responsible Final Risk


Task (Steps) Potential Hazard Details Existing Control Co Additional Control
affected n
Prob Risk person Cons Prob Risk

Man injuries Proper monitoring


Use only double lane full Ensure the
body harness communication is proper
Awareness of weather  Ensure the full body
condition harness is inspected by
During work at height not main contractor
allowed to use shock Monitor the weather
absorber prior to bypass or condition
less than 6 meter.
Must follow scaf tag system
Scafolder must have 3rd Supervisor/engi 3 2 6
Use of scaffold, Slip/ Fall and trip party training certificate 4 5 20 neers/hse
and ladder hazard Workers/nearby Scafolding log should Monitor the work officer
Property damage Equpment Damage workers maintained Communicate with
Falling person Use only full body harness workers
with double line yard Avoid lone working
Man injuries Follow main contractor PTW Do not use un inspected
system full body harness
Give toolbox talk before Inspect the ladder when
starting work its coming to site store
During using of ladder one Do not use single line full
person should hold the body harness
ladder Stop the activity when the
Full body harness double scafold is not in good
lane should be 100% tie of condition
Double lane should hook to
the hook point while moving
also
Hydro pressure Do not exceed mentioned While testing
test of chilled Serious Injury to pressure in method 5 4 20 unauthorized personnel Supervisor/ 3 2 6
water piping. workers due to Lti statement. not to allow in working Engineer/
Page 4 of 6
JOB SAFETY ANALYSIS
Ref
Rev 000
INSTALLATION OF CHILLED WATER PIPES Date 04-06-2018

Consequence Who might be Current Risk Responsible Final Risk


Task (Steps) Potential Hazard Details Existing Control Co Additional Control
affected n
Prob Risk person Cons Prob Risk

Barricading & sign board to


Equpment Damage Worker/ co- be provided.
workers Do not repair any pipe, when
Man And Material Supervisor
it is in pressure. area.
Man injuries Only calibrated pressure Emergency numbers to be
gauge should be used to posted.
carry out pressure testing. Supervision to be]
(max pressure- pipe blasting, over Workers
Only authorized person to do provided.
15 bar) pressure.
the work. Follow main contractor
No other activity is allowed PTW System
in pressure test area. Mock drill conducted
Sign board should be in before activity.
entrance & pressurized area.
LOTO system to be
implemented.
Risk Matrix
Descriptor Likely Frequency Probability

Frequent Occurs frequently 5


Likelihood (From Consequence (From Table 1)

Table 2) Often Insignificant (1) OccursMinor


several
(2) times per year Moderate (3) Major (4) 4Catastrophic (5)
Rare (1) 1 2 3 4 5
Likely Has occurred more than once 3
Possible (2) 2 4 6 8 10
Likely Possible
(3) 3 Has
6 occurred 9 12 2 15
Often (4) 4 8 12 16 20
Rare Never occurred 1
Frequent/ Almost Certain (5)
5 10 15 20 25

15 - 25 Extreme Risk Activity or industry should not proceed in current form.


Page 5 of 6
Activity or industry should be modified to include remedial planning and action and be subject to detailed OSH
8 - 12 High Risk
assessment.

4-6 Moderate Risk Activity or industry can operate subject to management and /or modification.

1-3 Low Risk No immediate action required, unless escalation of risk is possible.
JOB SAFETY ANALYSIS
Ref
Rev 000
INSTALLATION OF CHILLED WATER PIPES Date 04-06-2018

RISK ASSESSMENT ORIENTATION ATTENDEES


Name Date Designation Comments Signature
1
2
RISK ASSESSORS
Name Date Designation Comments Signature
1
2

Page 6 of 6