PROJECT COMPANY

PROJECT COMPANY ENGINEER

EPC CONTRACTOR

PROJECT

DEWA PHASE III 800 MW PV SOLAR POWER PROJECT


ORIGINATOR

DOCUMENT TITLE

METHOD STATEMENT: LOADING & UNLOADING OF OFFICE CONTAINERS,


INSTALLATION OF OFFICE CONTAINERS

PCO Document Code


Responsible
Project Phase Number Discipline System Document Type Serial Number LBS
Organization

EPC Company Code

Project Group Issuing discipline Document type Originator Company Serial Number

DWA 00 HS MS GNF 0001

Rev Date Reason of issue Drafted by Reviewed by Approved by

00A 31-10-17 Approval RP

The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS

DOCUMENT CHANGES LOG

Revision Remarks Section/Paragraph

00A Initial Issue All

The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.

Page 2 of 17
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS

1. Table of Contents

1. TABLE OF CONTENTS ................................................................................................................... 3

2.0 PURPOSE & SCOPE ........................................................................................................................ 4

3.0 REFERENCES .................................................................................................................................. 4

4.0 CONSTRUCTION METHODOLOGY ............................................................................................... 4

4.1 Summary .................................................................................................... 4


4.2 Methodology ............................................................................................... 4
4.3 Permit, Access, Approval and Site Preparation ................................................... 4
4.4 Loading & unloading of office containers, Installation of office containers. ............... 4
4.5 WORK EXECUTION METHOD. ......................................................................... 5
5.0 NATURE OF WORK ......................................................................................................................... 6

6.0 REQUIREMENT OF TEMPORARY WORKS ......................................................... 6


7.0 ACTIVITY SCHEDULE & MILESTONES ........................................................................................ 6
8.0 ROLES AND RESPONSIBILITY ..................................................................................................... 7

8.1 PERSONNEL ..................................................................................................................................... 7

8.2 PLANT & EQUIPMENT .................................................................................................................. 11

9.0 HAZARD IDENTIFICATION, RISK ASSESSMENT AND CONTROL ........................................ 12

10.0EMERGENCY PROCEDURES & RESPONSE PLAN ................................................................ 12

11.0 RISK ASSESSMENT (RA) ............................................................................. 14

The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.

Page 3 of 17
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS

2.0 PURPOSE & SCOPE


This Method statement is to define the methods, procedures and activities, which will be used
for loading & unloading of office containers, Installation of office containers for DEWA PHASE
III 800 MW PV SOLAR POWER PROJECT as per the approved designated place to ensure
that all works are executed in a safely manner and in accordance with the EPC Contractor
Contract Specification, approved Health and Safety Plan.
3.0 REFERENCES
UAE Rules & Regulations.
Code of Construction Safety Practice of Dubai Municipality.
Project HSE Plan & Procedures.
Project Contract Documents.
International Safety Codes and Standards.

4.0 CONSTRUCTION METHODOLOGY

4.1 Summary
This MS will be outlining the sequences and methods of works intended for loading &
unloading of office containers, Installation of the office containers.

4.2 Methodology

Step Description

1 Permit, Safety and Site Preparation

Method Statement for loading & unloading of office containers, Installation


2
of office containers.

4.3 Permit, Access, Approval and Site Preparation


a. Obtain necessary permit such as Permit To Work (PTW) from the contractor.
b. Check relevant items like PPE’s, access of working area, equipment to be used etc. to ensure
safety, workability and environmental requirements.

4.4 Loading & unloading of office containers, Installation of office


containers.
4.4.1 Preparatory Work

The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.

Page 4 of 17
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS

a) The documents submitted/referred with this method statement shall be considered as


an integral part of this method statement and shall be read in conjunction with the
same.
b) All vehicles & equipment to be used in the work should be initially checked and
approved by the authorized personnel.
c) Survey and measurement should be taken and marked, for lifting, unloading and installing of
site office cabins.
d) Cable detection must be carried out to make sure no underground services.
e) Foreman & Crane operator will check & plan the travel routes prior to mobilization. Ensure
travel routes & access to the jobsite is in good condition and free from obstruction.
f) Check and confirm crane set-up positioning.
g) Soil compaction must be carried out to set adequate ground condition for container
and lifting work.
h) Container must be placed at least 300mm above from the ground level.
i) Working area shall be barricaded with proper devices & warning signs to display.
j) Unauthorized person are not allowed in the area barricaded off
k) Workers shall wear appropriate PPE for the task.
l) Safety Coordinator & Lifting supervisor shall be present at all time during lifting activity.

4.5 WORK EXECUTION METHOD.

a) All lifting tools, equipments and ropes used for lifting shall be inspected and certified by Third
party Agency approved by Dubai Muncipality.
b) Lifting plan shall be filled up and attached with load chart shall be submitted during permit
application if the load exceeds 10Tonnes.
c) Safety officer will conduct tool box and brief the safe lifting operation before work start.
d) Before starting the lifting work, the assigned people must wear proper PPE and adequate
safety procedure must be implemented.
e) All employee and worker involved in the work should first undergo training or safety induction.
f) Project Manager shall employ an experienced, competent and responsible Foreman to plan
and execute lifting operations and rigger with third party.
g) Barricade the marked location scheduled for unloading and lifting operation with safety
signage’s.
h) To Provide safe work during mobilization and demobilization of office containers, there are
consideration which take according to weight of the container.
i) The site supervisor should prepare the site area to be clean and clear from obstruction.
j) Positioned the Crane near the designated storage area and steel plate should be place over
the landed of the crane out-rigger.
k) Attached the four hooks lifting gear with tag line to the hook attached.

The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.

Page 5 of 17
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS

l) Attached the four hooks to the four lifting slot corners of steel plates, container and ensure
that the hooks were locked.
m) Lift one container at a time and unload at the nearby designated storage area.
n) The load shall be controlled by means of tag lines to prevent the load from turning or
swinging.
o) Repeat the process until all materials were unloaded.
p) Safety equipment must always present and ready for immediate use.
q) The weight of container is 5 Tonnes.

5.0 NATURE OF WORK

 Confined Space - Confined Space Permit shall obtain and copy must be available at
site when the activities is being done under confined space area like cable pit etc.
Section 6.2.2.7 Confined space work of the HSE Management Plan must be observed
(and mentioned) Confined Spaces. Excavation and Earthworks must observed and
mentioned.
 Work at Height – Work at Height Permit shall be obtained and copy must be available
at site. When the activities to be done above 1.8 meters, flat form or scaffold must be
erected.
 Working During Summer Time – Working direct exposed to sunlight during summer
season shall not be permitted as directed by the labor law. Ensure to provide proper
sun shades, drinking water at site.

6.0 REQUIREMENT OF TEMPORARY WORKS


 Necessary warning signs shall be provided around the working areas.
 Erect / install scaffold when working at height.

7.0 ACTIVITY SCHEDULE & MILESTONES

The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.

Page 6 of 17
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS

Activity Duration Remarks

Loading & unloading of Completion of activities


office containers, Installation of As per activity schedule depends site access and site
office containers condition

8.0 ROLES AND RESPONSIBILITY

8.1 PERSONNEL

 Dy. General Manager - Overall In-charge of the project and report to General Manager.

 Project Manager

 Responsible to implementation and proper completion of the project.


 Responsible for proper planning of all resources required to complete the works in
accordance with the program, ensure all persons at site are adequately experienced and
trained to carry out their allocated tasks.
 Responsible for the day to day management of the project, both on and off the site,
together with proper delegation of duties in accordance with the organization chart and for
the effective implementation of the project management system.
 Take prompt corrective actions to remove any unsafe or unhealthy work conditions and to
 Maintain effectively such corrections made.
 Ensure good housekeeping is practiced on site.
 Ensure the delegated site personnel are conversant with and operate the prescribed QMS
and Safety Plans correctly.
 Able to properly communicate with and manage all persons on site.
 Ensure that all dangerous activities are carried out under Permit to Work Procedure.
 Ensure that all training requirements are put in place (scaffolding, machinery operator
certificate, first aider, fire watcher, etc.)
 To ensure the effective implementation of all Plans, Procedures and Forms included in the
HSE Management System. Ensure that all equipment and machinery have third party
certificate (when applicable).
 Lead all construction activities and enforce strict adherence to all project requirements.
Report to Dy. General Manager.

 Engineers

The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.

Page 7 of 17
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS

 Responsible for the site coordination and execution of the project construction.
 Prepare technical document, material, and shop drawings submittals.
 Raising RFI’s, IR’s to the client.
 Preparing weekly look ahead reports.
 Attending coordination meetings between client and consultant.
 Transmitting client instructions to the project manager and the construction team.
 Managing the QA/QC team, coordinating and assisting in all QA/QC documentation as per
project quality plan.
 Establish and maintain a programme for the identification and assessment of hazards.
 Assist in the investigation of every serious or fatal accident and dangerous occurrence
and
Recommend preventive measures.
 Ensure that method statements, hazard analysis and safe work procedures for hazardous
Operations must be submitted before commencement of work on site.
 Preparing Method Statements and lias with HSE officer for Risk Assessements.
 Ensure that al dangerous activites are carried out under Permit to Work Procedure.

 HSE Officer

 To ensure that the activities are performed as to the project HSE plan so that the work is
at minimum risk to the construction personnel at site.
 Coordinate and ensure with various levels of people at site to have a safe Working place.
 To ensure that the work is carried out with minimum impact to the
environment.
 To ensure and monitor the condition of machinery and plant and report any hazardous
defect to the plant department.
 To investigate site accidents and prepare accident reports to the EPC contractor.
 To provide safety induction program to workers, prior access to site.
 To contact client associated personnel in case of an accident or injury.
 Attend HSE teams meetings with the HSE manager and transmit instructions to site
personnel.
 Prepare Risk Assessment as per project HSE plan
 Ensure that all dangerous activities are carried out under Permit to Work Procedure.
 Ensure that all training requirements are put in place (scaffolding, machinery operator
certificate)
 To ensure the effective implementation of all Plans, Procedures and Forms included in the
HSE Management System.

The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.

Page 8 of 17
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS

 Ensure that all equipment and machinery have third party certificate (when applicable).
 . Report to Dy. Project Manager.
 To ensure that the activities are performed as to the project HSE plan so that the work is at
minimum risk to the construction personnel at site.
 Coordinate and ensure with various levels of people at site to have a safe Working place.
 To ensure that the work is carried out with minimum impact to the environment.
 Provide periodic tool box talks to labours on site.
 To ensure and monitor the condition of machinery and plant and report any hazardous
defect to the plant department.
 To investigate site accidents and prepare accident reports to the construction team.
 To contact client associated personnel & relevant authorities in case of an accident or
injury if necessary.
 Attend HSE teams meetings with the HSE manager in a weekly basis and transmit
instructions to site personnel.
 Prepare Risk Assessment as per project HSE plan
 Ensure that all dangerous activities are carried out under Permit to Work Procedure.

 Crane Operators

 Undergone Crane Operator's Training Course and possess valid certificate.


 Before the start of every work shift, to carry out operational tests on all limiting and
indicating devices under no load conditions before any lifting operation is carried out and
shall enter the results of such tests in a log book or log-sheet.
 To ascertain whether the ground conditions, in particular the ground surface on which a
mobile crane is to be operated, are safe for travel or any lifting operation; and if he is of the
opinion that it is not safe for travel or any lifting operation, he shall report this to the Foreman
Supervisor.
 To ensure that any outrigger when it is required is fully extended and secured
 Not to carry out any lifting operation unless he has received by the Supervisor/Foreman.
 Not to hoist any object if he is unable to ascertain the weight of the load.
 Not to hoist any load unless he has received a clear signal from a signalman.
 Not to engage in any act which is not in accordance with safe and sound practice.
 Not to hoist any load if there is any obstruction in the path and if there is any
such obstruction, he shall report this immediately to the lifting supervisor.
 Not to hold any suspended load over any public road or public area unless that road or area
has been cordoned off
 Not to operate a mobile crane or a tower crane within 3 metres of any live overhead power
line.
 Not to use the crane for any operation for which it is not intended, including pulling or
dragging a load
 To ensure that any stationary truck mounted or wheel mounted crane is adequately and
securely blocked while it is on a slope.
The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.

Page 9 of 17
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS

 To report any failure or malfunction of the crane to the lifting supervisor and to make an
appropriate entry of the failure or malfunction in the log book or log-sheet of the crane.

 Riggers

 Appoint a rigger in a workplace unless the person has successfully completed rigger training
course acceptable to the Main contractor.
 Check the slings to be used for slinging the loads to ensure that the slings are of good
construction, sound and suitable material, and adequate strength and free from patent
defect.
 Ensure that an adequate number of legs of the sling are used and that the slinging angle is
correct so as to prevent the sling from being overloaded during the hoisting.
 Determine the weight of the load which is to be lifted and inform the crane operator of the
weight of the load;
 Ensure that only proper lifting gears are used in conjunction with the sling.
 Ensure that the load to be lifted is secure, stable and balanced.
 Ensure that any loose load (which includes any cable drums, Drum stands) is placed in a
receptacle to prevent the load or part thereof from falling during the lifting operation.
 Place adequate padding at the edges of the load which come in contact with the sling so as
to prevent the sling from being damaged; and Report any defect in the lifting gear to the
lifting supervisor.

 Signalmen

 Ensure or verify with the rigger that the load is properly rigged up before he gives a clear
signal to the crane operator to lift the load.
 Give correct and clear signals to guide the crane operator in the maneuver of the load safely
to its destination.

 Workers
 Accepting individual responsibility for their own safe behavior as well as
sharing responsibility with their fellow workers and line supervision to look out for their own
as well as their co-workers.
 Work in a safe manner at all times.
 Complying with HSE requirements which apply to an individual’s work activities.
 Keeping the work area in an orderly condition.
 Wear PPE provided to them and inspect it daily.
 Comply with work instructions and permits.
The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.

Page 10 of 17
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS

 Attend daily tool box/pre-task meetings


 Inspect all tools before use and on a daily basis.

 Supervisor / Technicians
 Ensure that all activities to be done in accordance with the approved MS/RA,
 Supervisor shall monitor site installation, conduct tool box meeting and discuss to crew
member the hazard of the activities to be done.
 Supervisor also ensure that site installation shall be as per project specification.
 Technician shall be attended and pass necessary trainings required for the job to ensure the
competency and to comply with the requirements of Contractor/Engineer.
 Site activities / installation shall be executed in compliance to quality, safety and standard
requirements. Report to Engineer.

8.2 PLANT & EQUIPMENT

8.2.1 Equipment’s

 50 Tonne Mobile Crane with Third Party Certificate.


 Electrical Generator with Drip tray.
 Trailer
 40Ft Container.
 9 mtr & 12 mtr Caravan

8.2.2 Tools

 Measuring and Levelling Tools


 Clamping Tools
 Hand held Tools- Spanner, screw driver, plumb etc.
 Lifting Tools- Belts, Sling, Chain Block, Hoist, Shackle, Ropes etc.
 Portable power Tools like Grinding machine, Drilling Machine etc.
 Stepladder & Extension ladder
 Nails for the metal roofing
 Heavy duty hammer & half a pound 2” sized roofing nails
 Hand Saw
 Scaffolding pipe
 GI wire.

8.2.3 List of personal protective equipment

a. Mandatory PPE Requirements

 Safety helmets.
 Safety footwear.
 High visibility vests.
 Safety Glasses.

b. Work Specific PPE


The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.

Page 11 of 17
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS

 Hand gloves.
 Ear defenders.
 Welder face shield.
 Filter mask.
 Full body safety harness.

8.2.4. Survey and Set Out


 As per requirement

9.0 HAZARD IDENTIFICATION, RISK ASSESSMENT AND CONTROL


The Sub-Contractor will be responsible for all necessary safety measures at all time. All
works related will be executed in accordance with the Client and Contractor Project Health and
Safety Plan.
The work will only proceed when all necessary permits has been obtained or when
required. The permit will be kept on site for consultation during any site works.
Special attention will be given to:
 Cordoning off specified working area and provision of applicable safety warning sign boards.
 All the Important Task Activities and Potential Hazards including existing controls have been
properly mentioned on the Risk Assessment made.

9.1.1. Lifting Plan

 Lifting of office containers, cable drums and heavy construction equipments

9.1.2. Permits Required

Permit Required Issued By

PTW Contractor

WORK AT HEIGHT Contractor

CONFINED SPACE Contractor

10.0 EMERGENCY PROCEDURES & RESPONSE PLAN

 PHASE III 800 MW PV SOLAR POWER PROJECT EMERGENCY CONTACT


NOS.

The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.

Page 12 of 17
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS

Contact Person Designation Company Contact Numbers

CLINIC/AMBULANCE Clinic Nurse EPC +97155 506 7404

MIGUELANGEL HSE Manager EPC +97155 684 6144


MOYA

FRANCISCO GARCIA Site Project Manager EPC +97156 522 0617


BUENO

JOSE MIGUEL PLAZA Construction Manager EPC +97156 522 0618

ANANDAN PILLAI Sr. HSE Officer EPC +97150 106 8046

SYED OWAIS AHMED Accident Prevention EPC +97156 415 6639


Officer

JINISH HSE Officer EPC +97152 518 9809

ESPIRITUFIESTA Environmental Engr. EPC +97156 422 5737


ABUAN

MANIARASN.N Site Manager PAG +97155 523 9106

KURMA NARESH FOREMAN PAG +97155 600 3576

SECURITY -- EPC +97152 894 1684

The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.

Page 13 of 17
11.0 RISK ASSESSMENT (RA)
A INJURY SEVERITY B FREQUENCY of OCCURENCE RATING
0 No injury 0 Has not occurred in last two years RISK CLASSIFICATION RISK VALUE
Minor laceration, wound (first aid
2 2 Occurs very seldom LOW 0---6
case)
More severe injury medical
4 4 Occurs occasionally MEDIUM 6---16
attention
Serious injuries, broken bones,
8 8 Occurs often HIGH 16---32
amputation etc
10 Loss of life / fatality 10 Could / has happened CRITICAL 32---40
C POTENTIAL DAMAGE / LOSS D ENVIRONMENT ACTION REQUIRED
Supervision, training, certification, method/risk
No damage, minimal costs (UAE Good
0 0 No effect LOW assessments, safe work procedures training,
Dirhams) instruction.
toolbox talks.
Competent supervision, training certification, Change
Minor damage, small costs (UAE
2 2 Minor effect MEDIUM method/risk assessments, safe work method,
Dirhams)
procedures training, toolbox talks. mitigate
Spillage,noise,wat
Competent supervision, training certification, Change
Med damage, stoppage (On site Serious effect er, dust/ vapours/
4 4 HIGH method/risk assessments, safe work method,
repair) medium cost (UAE Dirhams) (Short term) faun and flora
procedures training, toolbox talks. mitigate.
Very serious
Close competent supervision, training Intolerable,
8 More serious damage 8 effect (Long
certification, method/risk assessments, safe change
Term) CRITICAL
work procedures, PJO’s, work permits, training, method,
Severe damage, long term Catastrophic
10 10 and toolbox talks. transfer risk.
stoppage, high costs effect

The printed version of this document is a non-controlled version. The current version is available in the software tool for documentation management.
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS

Whom / Additional
Hazards Identified A B C D R Controls Responsibility R
What Affected Controls
Access to Accident with *Workers 4 1 2 0 8 Proper Supervision Site Engineer 2
working spot moving vehicle *Staff  Provide the safe access to the site. /Foreman
area. worker and *Assistant  Before starting the work tool box should be
staff. conducted.
 Proper ppe should be worn at the site.

Moving vehicle Adequate Fatality 2 2 4 0 16  Provide the safety barricades as per site Supervising & Site Engineer/ 4
equipment Access Egress. serious\Minor requirement. monitoring Supervisor
injuries  Apply appropriate signage and pedestrian
control.
 Keep Area clean & clear of obstacles.
 Maintain good housekeeping (remove
debris, trip hazards, site tidiness.
 Flag man should be available.

Accessing the Accident Workers 2 1 4 0 8  Provide safe and egress to work area Supervision & Site Engineer/ 4
trailer vehicle to With moving  Trailer container loaded vehicle should be in frequent monitoring Supervisor
site location vehicle worker good condition.
and staff  Flag man should be available.
Environment  Vehicle driver valid license should be
applicable.
 Vehicle third prty certificate.
 Authorised person should be operate the
trailer.
 Mobile phone using while driving is
prohibited.
 Comply with speed limit of 15km per hour

The printed version of this document is a non-controlled version. The current version is available in the software tool for documentation management.

Page 15 of 17
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS

Working in Physical injury workers 1 2 4 0 8  Before starting the work tool box should be More awareness Surveyor 5
site. of the person conducted. should be given in Site Engineer/
 Dont park the vehicle in front of the form of trainings and Supervisor
excavation. tool box talks
 Maintain distance from the excavation area.
 Ensure competent supervisión
 Trained and competent operatives allowed
to work

Usage of Minor injury of Workers / Staff 1 2 2 0 4  Use proper ppe safety helmet, & reflective Supervision Engineer/ 4
proper ppe and the person. jacket. supervisor
signage  Do not enter unauthorised person signage
boards. board.
 Advance warning sign should be provided.

Usage of Obstruction to Workers / 4 2 2 0 16  Clear access shall be marked and sign Adequate training Project 8
mobile crane. the walk way / property boards shall be kept prior. should be given Manger/
major injury by Damage  Check the mobile crane condition. Engineer/
the person.  Vehicle third party certificate. supervisor
 Depends upon the container use the sling.
 Vehicle condition should be checked infront
of the hook latch should be there. Then only
belt should be locked.
 This condition should be checked at the
mobile crane.
 Check the third party inspection for web
sling.
 Tag line should be provided at the both end
of the container.
 Ensure 3rd party training certificate for
crane operator and riggers.
 Proper barricading and signs.

The printed version of this document is a non-controlled version. The current version is available in the software tool for documentation management.

Page 16 of 17
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS

Unloading the Manjor injury to Employees / 2 4 4 0 32  Before unloading the container underground More awareness Site Engineer/ 16
container the person, Property cable should not be there. should be given in Supervisor
/Installation of Damage  Area should be cleared before unloading form of trainings and
Office the container. tool box talks
Containers.  The maneuver will be leaded by the certified
Rigger.
 Flag man should be available.
 Tag line should be provided.
 Area should be barricaded.
 Unauthorised person no entry.
 While loading the container keep the
support hallow block or wooden pieces to
load act on it.
 The weight of container is maximum 5
Tonnes.

 This RA has complied with 6.2.10.8. Critical


lifting operations, 6.2.9 Lifting Equipment
and Lifting Operations and 6.2.10. Selecting
the Right equipmeny in HSE Management
Plan (DWA-00-HS-PL-0001

The printed version of this document is a non-controlled version. The current version is available in the software tool for documentation management.

Page 17 of 17