Professional Documents
Culture Documents
• It is the exploration of earth crust material not very far below the ground
level to know the type and characteristics of the bedding material on which
engineering structures are built.
• It includes boring, sampling and testing the materials encountered and
reporting for all activities performed.
• The investigation work is performed for both on the onshore and marine
structures.
• The GI is necessary because we need the structure safe against any loading
or adverse conditions in its life. The ground is explored for necessary
improvement if required.
• Safe
Page 1 of 13
Geotechnical Investigation
• A very hard and fast rule is not available for SPACING of boreholes. It is
dictated by available fund and field conditions.
• DEPTH of boring is dependent on size and type of structures and
characteristics of the deposits. Borehole depth is recommended in some
engineering codes and design manuals. It is essential that a boring must pass
through unsuitable strata.
• A restriction may be made on total number of blows. Usually not more than
50 blows are applied to penetrate 150mm of the spoon. In such cases record
the penetration in mm for 50 blows.
• The termination depth is defined in the specification or literatures for design
of pile foundation. Normally it must lie in a hard bed for an end bearing pile or
in a cohesive material when the frictional stress exceeds the FoS.
• All personels in the investigation work must be well trained and capable of
doing their work with confidence. A lack of knowledge may lead to
unbearable situations.
• A supervising engineer should be capable enough to foresee a possible
outcome of the investigation work being carried out. At the site the engineer
oversees boring work, soil encountered, performance of the equipment,
safety of the workers, progress of boring, temporary storage of soil,etc.
• The contractor must provide adequate boring tools at the site. Lack of
enough tools may lead to unnecessary delay, collapse of the borehole,
misuse of manpower etc. A boring equipment essentially consists of a steel
tripod long enough to accommodate drill rods, pulley, steel rope, pumping
device for circulation of mud water, driving hammer assembly, cutting shoe
or drill bit ….
• The foreman and the labourers must use PPE during work. Visitors will use the
PPE to approach to the working location. The working area must be clean
Page 2 of 13
Geotechnical Investigation
from any foreign substance spreaded over the area. Additional safety should
be provided with the boring conducted at offshore areas.
Page 3 of 13
Geotechnical Investigation
c) Desired precision of sampling and testing
d) Provision of more field tests such as vane shear, seismicity, electrical
resistivity, pressuremeter tests, etc.
e) Ground condition
f) Field condition, accessibility etc.
1.11 SPT
It is the most versatile and most preferred test recommended by engineers. The
reason of its versatility is that it is correlated with other engineering parameters
required for design. Moreover, a huge number of publications are now a days
available for estimating potential earthquake induced parameters with correlated
SPT N-values.
A stainless steel split spoon sampler having dimensions of OD= mm, ID= mm, L=
mm, of sharp is employed for the test. It is driven vertically at known depth with a
steel hammer of 140 lb (63.5±0.5kg) in weight with a free falling height of 30 in
(760±10 mm) by repeated drops. The number of hammer drops for each 6in
(150mm) is recorded and the number of blows required for the last 12in(300mm)
i.e. the number of blows per feet is called the SPT- N value or the standard
penetration resistance.
The SPT N-values are corrected for:
a) Energy delivered to the drive rods
b) Energy losses due to length of rods
c) Effect of overburden pressure in sands
to obtain corrected N values. Normalised N values are used for correlation purpose
by research workers.
Page 4 of 13
Geotechnical Investigation
1.12 Sample disturbance and its remedy
Causes of sample disturbance:
a) Impact load on the sampler during sampling
b) Hard or dense stratum cannot be easily penetrated by the sampler
c) Inappropriate sampler
d) Change in moisture content at the time of test
e) Disturbance caused during shifting of sample to the laboratory
f) Extrusion of sample by compressing at the laboratory
It is not possible to avoid all the reasons mentioned above. However, it can be
minimised by taking proper care and by choosing correct sampler. Often it would
cost extraordinarily to offset the allocated budget.
Page 5 of 13
Geotechnical Investigation
The upper part of the soil in the spoon is disregarded. Only the lower part is
considered to be representative and examined and tested.
A) Recognize the colour of the soil.
B) Observe the structure of the soil; it can be mottled or homogeneous.
C) Recognize the principal constituent. If it is sand, check for grittiness and
recognize the size of sand whether it is fine, medium or coarse.
D) If the principal constituent is fines then proceed to ascertain whether it is clay
or silt. Clay is identified by stickiness at plum of hand when it is wet. Silt is
characterized by non-stickiness at plum when wet and exudes between
fingers.
E) Secondary constituents should be identified and described as a qualifying
term.
F) Follow the project specification for describing the soils e.g. USCS, BS, ISO, etc.
If nothing is specified then follow the suitable one preferred by the
geotechnical engineer.
Page 6 of 13
Geotechnical Investigation
1.17 Shallow boring
Sometimes it is necessary to know the type of soil lying within few metres below the
ground surface. In this case shallow boring is recommended. Assigned laboratory
tests are due to use of the material.
Page 7 of 13
Geotechnical Investigation
f) Direct Shear
In some cases mica analysis and chemical tests are performed on soil and
groundwater at borehole locations.
Page 8 of 13
Geotechnical Investigation
Types of CPT vary according to dimensions and use. Sizes of cones and sleeves vary
according to Manufaturers.
Some modification is done to the device to widen test facilities e.g.
Cone pressuremeter test (CPMT), seizmic cone penetration test (SCPT), etc.
Page 9 of 13
Geotechnical Investigation
1) Less time is required
2) No expense and risk to transfer field samples to laboratory
3) CPT uses data-logger that ensures that root data is saved and printed in
specified format.
4) Engineers can gather data much faster and can take spot decision for testing
intermediate locations.
5) Pore pressure is measured and hence it tends to produce more accurate
presentation of actual conditions underground.
6) Not laboratory testing is required.
Disadvatages:
1) There is no way to view the solids existing in the strata.
2) There is no way but to redo when there is conflict in data.
3) Atterberg Limits
It is reliable irrespective of the sample disturbance. Its value is slightly
changed when tested on an air dried sample.
4) Unconfined Compression
It is reliable when the sample is fine and saturated undisturbed soil. Because
of its simplicity, it is preferred by many organisations.
5) Triaxial Compression
The test is performed for granular and undisturbed fine soils and at different
loading and drainage conditions. It is costlier than unconfined compression
test. It is preferred test by geotechnical engineers.
Page 10 of 13
Geotechnical Investigation
7) Consolidation
The test is performed on soft fine soil to determine consolidation parameters.
It is a lengthy test to perform but valuable parameters are obtained. The test
is time consuming.
8) Chemical tests
Tests for sulphates and chlorides on soil (or groundwater) are performed
when deemed necessary. These are uncommon tests.
9) Mica Analysis
Sometimes analysis of mica is necessary to carry out. It is performed either
by physical separation or by flotation method. This is a rare test.
Page 11 of 13
Geotechnical Investigation
2.3 Lab CBR test and its use
It is a strength test performed on disturbed soil. Soil at optimum water content is
prepared in the laboratory and compacted in CBR moulds, normally 3 Nos, at three
energy levels. The compacted soils in the moulds are soaked under water for 4
days. After soaking those soaked soils are tested for penetration at a specified
penetration rate for about 10mm. A load penetration curve is obtained. The load at
2.5mm and 5.0mm penetrations are noted for each compacted specimen. CBR
value is the percentage of the load corresponding to the standard loads. Suppose P 1
and P2 are the loads obtained at 2.5 and 5mm penetrations for a particular
specimen. Then the CBR values are:
i) P1*100/13.24
ii) P2*100/19.96
when the loads are expressed in kN. The higher value of CBR is chosen as accepted
CBR.
In AASHTO design “resilient modulus” test is recommended. Its value is correlated
with CBR. As soon as CBR value is known, resilient modulus value is estimated and
used in the design of pavement.
Page 12 of 13
Geotechnical Investigation
Page 13 of 13