You are on page 1of 1

Project : Design and Construction of Putatan Water Treatment Plant 2 Consultant : Arup

Owner : Maynilad Water Services, Inc. Contractor : AJF Consortium


WATERTIGHTNESS TEST REPORT
Structure : Sludge Area-GL 1-5/A-D Test Period : April 20-22, 2018

Equivalent Change in Elev., Absolute


Date Time Reading, cm Remarks
Water Level, m m Value, mm
Apr. 20, 2018 Friday 8:00 AM 100.00 5.849 Initial reading
Apr. 21, 2018 Saturday 8:00 AM 99.80 5.85 - 0.002 2.000 Daily Reading
Apr. 22, 2018 Sunday 8:00 AM 99.50 5.844 - 0.003 3.000 Final reading
2.50 Average Daily drop in level

Final Water Level, m 5.844


Equivalent Water Level at Tank - 0.005 5.000 Difference of Water Level (A), mm
Initial Water Level, m 5.849

Water Level at Container Final Water Level, cm 24.100 - 0.900 9.000 Difference of Water Level (B), mm
Initial Water Level, cm 25.000

Correction due to Precipitation or Evaporation - 4.000 Evaporation

Satisfactory. The actual change of water


Corrected Change of Water Level (A ± B), mm
4.000 level is lower than the Allowable Drop in
Use plus sign when the correction is due to evaporation, minus if otherwise.
Water Level.
=5.849/500 x
Allowable Drop in Level (Ht/500), mm 11.698
1000
Remarks: The structure is considered water-tight.

Prepared by: Noted by: Verified by:

AJF QC representative AJF Construction Manager Arup Representative