To Copy to,
Managing Director
BSRM Steels Limited Managing Director, PGCB
Mahbub Castle (1st, 2nd & 3rd Floor)
35/a Purana Platan, VIP Road, Dhaka-1000
√ Executive Director (P & D), PGCB
√ Master File
Dear Sir,
We are pleased to enclose the following documents for the purpose indicated below:
Issued by:
(1)
In case of any modification other than those desired are carried out, the same shall be
highlighted clearly in the Drawing/Document with full justification thereof and resubmitted SUKANTO LAL NAG
for approval.
Superintending Engr.
(2)
(Civil Design & Q/C),
Approval/Comments/Information conveyed herein neither relieves the contractor of his
contractual obligation and his responsibilities for correctness of dimensions, material of
constructions, weight, quantities, design details, assemble fits, performance particulars Our Ref: 04-PGCB/SE(Civil)/Design &
and conformity of the supplies with the Statutory Laws of Bangladesh as may be QC/2014/14
applicable, nor does it limit the Employer’s right under the contract.” Date: 01/09/2014
For information
(FI)
Received by Date
Note:
(1)
The above paragraph shall be added if the status of the document is C/RR/FI.
(2)
The above paragraph shall be added if the status of the document is A or C.
Annexure-1