DR

Effectivity Date:
CIVIL WORKS PROCEDURE June 4, 2018
Project Name:
Document Code:
CIVIL WORKS - JGSPC OSBL FOR STAGE 1 EXPANSION
K006-MS-OPE-018
PROJECT (K006)
Document Title:

METHOD STATEMENT FOR Rev. No. Page No.


THE CONSTRUCTION OF TEMPORARY SHELTER 0 1 of 10
FOR G08 – NCP UTILITIES AREA

CIVIL WORKS PROCEDURE –


METHOD STATEMENT FOR
THE CONSTRUCTION OF TEMPORARY SHELTER
FOR G08 -NCP UTILITIES AREA

Prepared by: Reviewed by: Verified by: Approved by:

Ghienuel B. Rosas Rodel P. Duyo Josie Castro Angelito B. Ebora


Project Superintendent Project in Charge QA/QC Manager Project Manager

Execution Revision Revision Page


Description of Changes Originator
Date Number Type Affected
06-04-2018 0 New Initial Issuance - GBRosas
DR

Effectivity Date:
CIVIL WORKS PROCEDURE June 4, 2018
Project Name:
Document Code:
CIVIL WORKS - JGSPC OSBL FOR STAGE 1 EXPANSION
K006-MS-OPE-018
PROJECT (K006)
Document Title:

METHOD STATEMENT FOR Rev. No. Page No.


THE CONSTRUCTION OF TEMPORARY SHELTER 0 2 of 10
FOR G08 – NCP UTILITIES AREA

Table of Contents

1. PURPOSE ......................................................................................................................................3
2. SCOPE OF WORK .........................................................................................................................3
2.1 General Description .............................................................................................. 3
2.2 Tools and Equipment ........................................................................................... 5
2.3 Materials ................................................................................................................. 5
2.4 Site planning & preparation ................................................................................ 5
2.5 Work Methodology ................................................................................................ 6
2.6 Organization, Responsibilities & Supervision .................................................... 8
2.6.1 Personnel Organization .............................................................................. 8
2.6.2 Responsibility & Supervision ........................................................................ 8
2.7 Work Force............................................................................................................. 9
3 REFERENCES ................................................................................................................................9
4 ENVIRONMENTAL, SAFETY AND HEALTH ..................................................................................9
4.1 Job Hazard Analysis .............................................................................................. 9
4.2 Protective & Safety Equipment ........................................................................... 9
4.3 Information to Personnel ................................................................................... 10
4.4 Emergency Procedures ...................................................................................... 10
5 QUALITY ASSURANCE .............................................................................................................. 10
5.1 Quality Requirements Table .............................................................................. 10
6 APPENDICES ............................................................................................................................. 10
6.1 Journey Management Plan (JMP) ..................................................................... 10
DR

Effectivity Date:
CIVIL WORKS PROCEDURE June 4, 2018
Project Name:
Document Code:
CIVIL WORKS - JGSPC OSBL FOR STAGE 1 EXPANSION
K006-MS-OPE-018
PROJECT (K006)
Document Title:

METHOD STATEMENT FOR Rev. No. Page No.


THE CONSTRUCTION OF TEMPORARY SHELTER 0 3 of 10
FOR G08 – NCP UTILITIES AREA
1. PURPOSE

The method statement enumerated hereto represents an approach for the


construction/erection of temporary shelter not limited for G08 NCP Utilities Area and other
similar activity in accordance with the contract requirement for the welfare of manpower.

2. SCOPE OF WORK

2.1 General Description

The methodology discussed on this procedure will ensure that all activities and
execution of works from hauling ang transport, erection and construction of shelter for safe
usage shall be met based on standard degree of workmanship.
DR

Effectivity Date:
CIVIL WORKS PROCEDURE June 4, 2018
Project Name:
Document Code:
CIVIL WORKS - JGSPC OSBL FOR STAGE 1 EXPANSION
K006-MS-OPE-018
PROJECT (K006)
Document Title:

METHOD STATEMENT FOR Rev. No. Page No.


THE CONSTRUCTION OF TEMPORARY SHELTER 0 4 of 10
FOR G08 – NCP UTILITIES AREA

1500mm
2000mm

2000mm

2500mm
2000mm
Base
Jack

400mm
2000mm

3000mm
2000mm

Isometric View and Detail of Temporary Shelter

(All Pipes in Swivel Clamp Connections)


DR

Effectivity Date:
CIVIL WORKS PROCEDURE June 4, 2018
Project Name:
Document Code:
CIVIL WORKS - JGSPC OSBL FOR STAGE 1 EXPANSION
K006-MS-OPE-018
PROJECT (K006)
Document Title:

METHOD STATEMENT FOR Rev. No. Page No.


THE CONSTRUCTION OF TEMPORARY SHELTER 0 5 of 10
FOR G08 – NCP UTILITIES AREA

2.2 Tools and Equipment

The following items are the minimum equipment/ tools required for this specific scope
of work considering project scheduling requirements:

No. Tools/Equipment Qty Unit Remarks


1. Canter Truck and 1 ea.
accessories(delivery)
2. Back wrench 2 ea.
3. Wire cutter/Pliers 2 ea.
4. Electric Screw Driver 2 Ea. Used offsite

Note: The number and quantities of above equipment and plant will be determined to suit the
contract program or as per actual site requirement, but not limited to what is stated above.

2.3 Materials

1. Scaffolding pipes conforming to 50mm diameter Schedule 40 G.I. Pipes.


2. Scaffolding swivel clamp conforming safety/scaffolding standards.
3. Corrugated G.I. Sheet
4. Others: #16 G.I. Tie wire, 2 inch Tek screws, Vulca Seal.

2.4 Site planning & preparation

A pre-construction survey jointly with the Owner’s representative and Company shall be
undertaken to determine the extent and limits and location pre-approved by them.
DR

Effectivity Date:
CIVIL WORKS PROCEDURE June 4, 2018
Project Name:
Document Code:
CIVIL WORKS - JGSPC OSBL FOR STAGE 1 EXPANSION
K006-MS-OPE-018
PROJECT (K006)
Document Title:

METHOD STATEMENT FOR Rev. No. Page No.


THE CONSTRUCTION OF TEMPORARY SHELTER 0 6 of 10
FOR G08 – NCP UTILITIES AREA
2.5 Work Methodology

• To provide a detailed sequence for construction of temporary shelter near the


condensate polishing drain based from approved method statement.
OBJECTIVE
• To ensure that construction methods strictly conform to the specifications for the
on-time delivery and completion of specific scope of work of the project.
This procedure covers activities from site survey layout, delivery of material and
SCOPE assembly (construction) of the temporary shelter of workers for condensate
polishing drain construction.

Tools/
Responsibility Activities Notes Interfaces
Equipment
Field Engineer/
Assembly of main frame
Supervisor Note 1 Electric Screwdriver MS
and roof
(DMCI)

Field
PTW Request
Supervisor/
Secure Permit to Work JHA
Safety Note 2
and Delivery JMP
Inspector/PTW
ITP
Receiver

Field Engineer /
Supervisor/ EIC Material Delivery Note 3 Canter Truck PTW
(DMCI) Handling

Field Engineer /
Erection of Temporary Back wrench and wire
Supervisor Note 4 PTW
Shelter cutters/pliers
(DMCI)

Field Engineer / Back wrench, wire


Demolition and
Supervisor/EIC Note 5 cutters/pliers PTW
Transfer/Haul Out
(DMCI) Canter Truck

NOTE 1:
1. All Materials will be prepared at DMCI staging area (cutting and main frame with
roof assembly).
DR

Effectivity Date:
CIVIL WORKS PROCEDURE June 4, 2018
Project Name:
Document Code:
CIVIL WORKS - JGSPC OSBL FOR STAGE 1 EXPANSION
K006-MS-OPE-018
PROJECT (K006)
Document Title:

METHOD STATEMENT FOR Rev. No. Page No.


THE CONSTRUCTION OF TEMPORARY SHELTER 0 7 of 10
FOR G08 – NCP UTILITIES AREA

NOTE 2:
1. Accomplish a Permit to Work (PTW) document including all other necessary
attachment related to scope of work to be undertaken. Attach all other permit
including hot work permit, survey permit, excavation permit, lifting permit, and
confined space entry/exit permit among others. Include also the Journey
Management Plan (JMP) and the Job Hazard Analysis (JHA).
NOTE 3:
1. All materials will be securely carried on the canter truck, by the EIC(DMCI) or
authorized Personnel, that upon arrival on site no other equipment on site is
needed to unload the materials.
2. In construction site, the allotted manpower will unload the materials and should
not work on heights.
NOTE 4:
1. The pre-assembled roof with post shall be erected in sequence. The lower roof
with shorter post shall be lifted by 4 persons and secure the post temporarily.
2. The higher roof with longer post will be lifted by 4-6 persons slowly. When the
extents reached the post will be secured temporarily.
3. Stiffeners will be firstly secured by the scaffolders using the pipes and swivel
clamps as delivered.
4. The seat will be next in pipes as part of the assembly to be installed by the
scaffolders.
5. The base jack shall be placed next, lifting the side of the shelter and the rest also.
6. For additional shelter to be erected, please repeat Note 4: 1 to 5.
DR

Effectivity Date:
CIVIL WORKS PROCEDURE June 4, 2018
Project Name:
Document Code:
CIVIL WORKS - JGSPC OSBL FOR STAGE 1 EXPANSION
K006-MS-OPE-018
PROJECT (K006)
Document Title:

METHOD STATEMENT FOR Rev. No. Page No.


THE CONSTRUCTION OF TEMPORARY SHELTER 0 8 of 10
FOR G08 – NCP UTILITIES AREA
NOTE 5:
1. After the main activity has finished, commence the demolition and transfer to the
next area for construction or haul out the materials if not needed anymore.

2.6 Organization, Responsibilities & Supervision

2.6.1 Personnel Organization

During the execution of work under this document the following personnel will be
deployed as minimum:

a. Project Supervisor/Field Engineer


b. Equipment In-charge
c. Safety Officer
d. PTW Receiver

2.6.2 Responsibility & Supervision

It is the responsibility of the Contractor’s staff and personnel to comply with the
procedures set out in this document. The responsibilities of the key personnel are
outlined for clarity and easy reference below.

a. Project Supervisor/Field Engineer:


1. Ensure that Construction Method Statement is strictly followed.
2. Monitor the implementation of work plan and on schedule.

b. Equipment In-charge:
1. Ensure that required equipment are available and in working condition.
2. Ensure that daily inspection checklist for each equipment are complied.
3. Ensure that equipment dispatch follows the approved schedule.

c. Safety Officer:
1. Ensure that all personnel have undergone safety induction/toolbox.
2. Ensure that all field personnel comply with the Owner HSSE plan
requirements.
3. Reports and investigate all accidents and incidents.

d. Permit Receiver/Coordinator
1. To coordinate with supervisor and area in-charge for all necessary permit
method statement and attachment.
2. Ensure that permit is complete, reviewed and submitted based on relevant
activity to undertaken.
3. Ensure that permit is submitted a day before work activity schedule duly
approved by the Company and the Owner.
DR

Effectivity Date:
CIVIL WORKS PROCEDURE June 4, 2018
Project Name:
Document Code:
CIVIL WORKS - JGSPC OSBL FOR STAGE 1 EXPANSION
K006-MS-OPE-018
PROJECT (K006)
Document Title:

METHOD STATEMENT FOR Rev. No. Page No.


THE CONSTRUCTION OF TEMPORARY SHELTER 0 9 of 10
FOR G08 – NCP UTILITIES AREA
4. Ensure that permit is readily available and visible at designated permit box on
each specific area.
5. Ensure a day to day close out of permit and re-application for continuous
activity for each area.
6. Permit receiver should be present at all times during execution of work

2.7 Work Force

No. Trade Qty Unit


1. Canter truck driver 1 ea.
2. Canter truck coordinator 1 ea.
3. Scaffolder 2 ea.
3. Skilled Worker 1 ea.
4. Helper 5 ea.
5. Flagman 2 ea.
6. Spotter 2 ea.
Note: The number of persons shall be selected in accordance with work conditions
and as per actual site requirements.
3 REFERENCES
a. Contract Documents
b. Contract Specification
c. Health, Safety, Security and Environmental Plan

4 ENVIRONMENTAL, SAFETY AND HEALTH

4.1 Job Hazard Analysis

a. Refer to Job Hazard Analysis in Section 6.1

4.2 Protective & Safety Equipment

Personal safety equipment is a must to be worn at all site activities.


1. Flame Resistant Clothing (FRC)
2. Hard hat
3. Cotton gloves
4. Safety shoes
5. Safety goggles with side protection
6. Hearing Protection
7. Dust Mask
8. Respirator
DR

Effectivity Date:
CIVIL WORKS PROCEDURE June 4, 2018
Project Name:
Document Code:
CIVIL WORKS - JGSPC OSBL FOR STAGE 1 EXPANSION
K006-MS-OPE-018
PROJECT (K006)
Document Title:

METHOD STATEMENT FOR Rev. No. Page No.


THE CONSTRUCTION OF TEMPORARY SHELTER 0 10 of 10
FOR G08 – NCP UTILITIES AREA
4.3 Information to Personnel

1. Tool box meeting or Safety Task Assign Meeting will be conducted by


Safety Officer or Supervisor to discuss work methodology and discuss
potential hazard and mitigation plan.
2. All safety related matters must be emphasized to the whole team.

4.4 Emergency Procedures

In case of Emergency situation, the Contractor should follow the Emergency


Response Procedure and, Emergency and Evacuation Response Plan submitted and
approved by the Company.

5 QUALITY ASSURANCE

5.1 Quality Requirements Table

Type Compliance Remarks


1. Specifications Yes
2. Material Submittal No
3. For Construction Drawing No
4. Quality Tests No

6 APPENDICES

6.1 Job Hazard Analysis (JHA)

6.2 Journey Management Plan (JMP)