Figure 3: Netwaork Diagram

Architectural decisions Kernel specifications Disk drivers


Start: 1/4/10 ID: 24 Start: 2/8/10 ID: 10 Start: 3/8/10 ID: 12
Finish: 2/5/10 Dur: 25 days Finish: 3/5/10 Dur: 20 days Finish: 7/27/10 Dur: 100 days
Res: Res: Res:

Memory management
Start: 3/8/10 ID: 14
Finish: 7/13/10 Dur: 90 days
Res:

Operating system documentation


Start: 3/8/10 ID: 15
Finish: 4/9/10 Dur: 25 days
Res:

Routine utilities
Start: 3/1/10 ID: 19
Finish: 5/21/10 Dur: 60 days
Res:

Complex utilities
Start: 3/1/10 ID: 20
Finish: 6/21/10 Dur: 80 days
Res:

Utilities documentation
Start: 3/1/10 ID: 21
Finish: 3/26/10 Dur: 20 days
Res:

Utilities specifications
Start: 2/8/10 ID: 18
Finish: 2/26/10 Dur: 15 days
Res:

Integration first phase Prototypes


Start: 9/9/10 ID: 25 Start: 11/18/10 ID: 6
Finish: 11/17/10 Dur: 50 days Finish: 3/15/11 Dur: 80 days
Res: Res:

Hardware specifications Hardware design Hardware documentation


Start: 2/8/10 ID: 3 Start: 4/19/10 ID: 4 Start: 7/28/10 ID: 5
Finish: 4/16/10 Dur: 50 days Finish: 7/27/10 Dur: 70 days Finish: 9/8/10 Dur: 30 days
Res: Res: Res: Serial I/0 drivers
Start: 11/18/10 ID: 13
Finish: 5/24/11 Dur: 130 days
Res:

Assemble preproduction models


System hard/software test Order circuit boards Start: 1/4/10 ID: 8
Start: 5/25/11 ID: 26 Start: 6/30/11 ID: 7 Finish: 2/12/10 Dur: 30 days
Finish: 6/29/11 Dur: 25 days Finish: 7/7/11 Dur: 5 days Res:
Res: Res:

Network interface
Start: 6/30/11 ID: 16
Finish: 11/4/11 Dur: 90 days
Res:

Shell
Start: 6/30/11 ID: 22
Finish: 9/23/11 Dur: 60 days
Integration acceptance testing
Res:
Start: 9/26/11 ID: 28
Project documentation Finish: 12/19/11 Dur: 60 days
Start: 6/30/11 ID: 27 Res:
Finish: 9/9/11 Dur: 50 days
Res: